Upload
vankien
View
223
Download
1
Embed Size (px)
Citation preview
DOC ID© Chevron 2010
Chevron U.S.A. Inc.Gulf of Mexico Business Unit
Subsea Engineering Team
Design, Construction and Performance of Subsea Production Flowlines in the
Blind Faith FieldGary Giordano
9 August 2010
DOC ID© Chevron 2010 2
Agenda
Overview of Chevron Assets in GoM
Blind Faith Subsea Development
Field Layout Selection
High Pressure High Temperature Flowlines Design
Flowlines and Accessories Fabrication
Installation of Flowlines System
Flowlines Pre-commissioning
Flowlines Performance
DOC ID© Chevron 2010 3
Blind Faith Overview
Chevron became operator of Blind Faith 1Q 2004
Chevron 75% & Anadarko 25%
Field located 160 miles SE of New Orleans, LA
Located in MC 695 & 696 in 7,000’ of water
Subsea Field Located 5 miles from Blind Faith Production Facility
Total length of flowlines loop is approx 10 miles
Blind Faith first oil was in November 2008
DOC ID© Chevron 2010 4
Suction PileChain
Sled (PLET)
Flowlines
Flowline Risers
Subsea Distribution Unit -
SDU
Umbilical
Manifold
Jumper
Flying Leads
Tree
Export Risers
7000 ft WD
Production Facility5 mile offset from well center
Buoyancies
DOC ID© Chevron 2010 5
Field Layout Selection
Field layout and length of flowlines were based on
Geohazard and geotechnical constraints
Flow assurance requirements
Required straight line length and curve radius past the riser touchdown point
Optimum length based on minimizing the impact of axial creeping and lateral buckling of the High Temperature flowlines
Environmental conditions for the selection of the orientation and location of the host
DOC ID© Chevron 2010 6
High Pressure High Temperature Flowlines Design
DESIGN BASIS
Design SITP 12.5 K, 300 F at mud line
Surface piping, flanges, Titanium Stress Joint (TSJ): 10 K, 250 F
Control upheaval and lateral buckling induced by product high temperature
Wet insulation applied for thermal management to maximize “No Touch” time to prevent hydrate plugging
DOC ID© Chevron 2010 7
High Pressure High Temperature (HPHT)
HPHT flowlines are more sensitive to the soil
Extensive HPHT flowlines analyses were undertaken
Independent verification was performed
The outcome of the analysis was used to define the Weld Defect Acceptance Criteria and the boundary conditions to the termination structures (PLETs)
The HPHT loads on the termination structures made the PLETs design and transition pieces challenging since several iterations with the designers and installation contractor were required
DOC ID© Chevron 2010
Special Flowline Design/Installation Considerations
Optimizing Pipe Weight – Design Pressure, On-Bottom Stability, Spanning, Buckling
Flow Assurance
Hydrate Remediation
Riser Hang Off System – Titanium Stress Joints versus Flex Joints
QA/QC for Girth Welds – Maximizing Design Strength and Operational and Installation Fatigue Life – ECA, AUT, Risers must be perfect
Installation Vessel Tension/Departure Angle required to retain Pipeline Catenary Shape
8
DOC ID© Chevron 2010 9
High Pressure High Temperature Flowlines Design
DESIGN OUTCOME
90 ft long, 16 ft diameter suction piles were required to anchor each flowline
Buoyancies were used to control the lateral buckling induced by high product temperature
High density layered PP was required for the bottom sections of the risers
Total outside diameter of the 7-in flowlines was approximately 14 inches
Pre-layed configurations was designed to accommodate post installation of the risers
DOC ID© Chevron 2010 10
Installation Sequence Constraints
2. Gas Export Riser
1. Oil Export Riser
4. West Flowline Riser
3. East Flowline
Riser
5. Umbilical
Installation Sequence: 1, 2, 3, 4 , 5
Host
DOC ID© Chevron 2010 11
Flowlines and Accessories Fabrication
Pipe Fabrication and Coating
Buoyancies, Strakes, Titanium Stress Joints
PLETs
Suction Piles
Intervention Spools
DOC ID© Chevron 2010 12
Insulation Qualifications
Extensive qualification were performed for flowlines insulation and heavy insulation (weight coating) required near the riser sag bend
DOC ID© Chevron 2010 13
Pipe Fabrication and Coating
Pipe Fabrication at Spool Base(Scotland)
Mill Pipe Production(Italy)
Coated Pipe Transportation(Norway)
DOC ID© Chevron 2010 14
Flowline Accessories
Strakes(Netherland)
Flowlines Buoyancies(USA)
Titanium Stress Joint(USA)
DOC ID© Chevron 2010 15
PLETs Fabrication
PLETs Fabrication(Houston - USA)
DOC ID© Chevron 2010 16
Suction Pile Fabrication
Suction Piles Fabrication(Corpus Christi - USA)
DOC ID© Chevron 2010 17
Closing Spools Fabrication
Photos of flowline closing spools
DOC ID© Chevron 2010 18
Suction Piles
Pile penetration
DOC ID© Chevron 2010 19
Suction Piles Lessons Learned
Suction pile stopped penetrating and questions were raised on whether the soils were different at that location
It was found out that pressure gauge was not providing correct readings due to its location
Lesson Learned: Ensure the pile design includes a suction gauge close to the suction pile to provide accurate readings
DOC ID© Chevron 2010 20
PLETs Lessons Learned
Interface
Equipment Constraints
DOC ID© Chevron 2010 21
PLETs Lessons Learned
The PLET/flowline interface required many iterations between the fabrication and installation contractors to ensure the PLET fits the handling frame on the installation vessel
Lesson Learned: Evaluate critical interfaces very early in the project and work the issues as early as possible
DOC ID© Chevron 2010 22
Flowlines Installation
New build vessel was used to reel coated flowlines (14-inch total outside diameter)
Coated pipe was load-tested on tensioner before the offshore installation
Titanium Stress Joint mock up was used to ensure it fits within the vessel access constraints
PLET mock up was fabricated to help ensure it can be properly handled with the vessel equipment
Extensive installation analyses were performed to cover a wide range of weather conditions offshore
DOC ID© Chevron 2010 23
Titanium Stress Joints
Took longer than expected to fabricate
Required extensive interface with the installation contractor
DOC ID© Chevron 2010 24
Flowlines Jumpers Installation
DOC ID© Chevron 2010 25
Intervention Spools
Fitting
DOC ID© Chevron 2010 26
Risers Installation
Risers were installed with a newly build anchor-handling type vessel (WD approx 7000 ft)
600-mt risers pull in equipments were used to hang the risers in their respective baskets
Risers Pull-in Equipment on Platform
DOC ID© Chevron 2010 27
Subsea Offshore Campaign Vessels
Boa Sub CSeven OceansToisa VigilantChloe CandiesHarvey DiscoveryM/V Andrea Cenac/OC-260Maersk AchieverNormand CutterHOS DominatorVeolia -King FisherVeolia-Sword FishM/V John G. / Barge M960 AdriaticWarren Thomas M/V Miss Lis Karen Kobe /JMC 252 M/V Admiral Lee/JMC 184
Note: The list does not include geophysical, geotechnical, diving, and pre-commissioning vessels used to support the subsea scope of work.Note: The list does not include geophysical, geotechnical, diving, and pre-commissioning vessels used to support the subsea scope of work.
2008 Storms
Arthur
Bertha
Cristobal
Dolly
Edouard
Fay
Gustav
Hanna
Ike
Josephine
DOC ID© Chevron 2010
HPHT Flowline Performance
28
Original Simulation showed single mode buckle
Lateral Nodal Displacements With Two Engineered Buckle Sections @ Sta 130+00 and Sta 170+00 For 5 Startup Cycles
-40
-30
-20
-10
0
10
20
30
40
50
1000 1100 1200 1300 1400 1500 1600 1700 1800
Stations from Riser to PLET (10*ft)
Dis
plac
emen
t (ft)
As_Laid Hydrotest Startup_1 Startup_2 Startup_3 Startup_4 Startup_5
ST1
ST2
ST3 ST4
ST5
ST1
DOC ID© Chevron 2010
HPHT Flowlines Performance
29
Side Sonar Scan method was used to determine lateral buckling of flowlines after first oil
DOC ID© Chevron 2010
HPHT Flowline Performance
30
Side sonar scan survey post start-up showed a different mode response (2nd mode buckling shape)
Flowline deflections and stresses were determined to be within design requirements
DOC ID© Chevron 2010 31
Blind Faith Achievements
Blind Faith is Chevron first development in 7000 ft
Chevron first subsea development with SITP of 12.5 ksi, and product temperature over 280 F (300 F downstream of choke)
The flowlines were the industry first application of wet thermal insulation rated for 300 F that was installed using a reel lay vessel
Blind Faith is Chevron first application of Titanium Stress Joints for SCR's supported from a floating production facility
An anchor type vessel was used to install the risers at 7000 ft. This was first in the industry
DOC ID© Chevron 2010
Blind Faith Future Plans
Seafloor Gas Lift Major Capital Project Team established – Start up planned for 2013
Considering Downhole Gas Lift and Subsea Boosting
Additional Subsea Wells and Third Party Tie-backs are potential future options
Recompletion and Sidetracks of existing wells highly likely in later life
32