Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
REPORT
Millport Coastal Flood Protection
Scheme: Environmental Statement
Chapter 7 Marine Water and Sediment Quality
Client: North Ayrshire Council
Reference: PB4749-RHD-ZZ-XX-RP-Z-0007
Status: Final/P01.01
Date: 31 January 2020
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
i
HASKONINGDHV UK LTD.
74/2 Commercial Quay
Commercial Street
Leith
Edinburgh
EH6 6LX
Industry & Buildings
VAT registration number: 792428892
+44 131 5550506
royalhaskoningdhv.com
T
E
W
Document title: Millport Coastal Flood Protection Scheme: Environmental Statement
Document short title:
Reference: PB4749-RHD-ZZ-XX-RP-Z-0007
Status: P01.01/Final
Date: 31 January 2020
Project name: Millport Coastal Flood Protection Scheme
Project number: PB4749
Author(s): Sarah Marjoram
Drafted by: Sarah Marjoram
Checked by: Christa Page
Date / initials: 14/11/2019
Approved by: Frank Fortune
Date / initials: 09/01/2020
Classification
Project related
Disclaimer
No part of these specifications/printed matter may be reproduced and/or published by print, photocopy, microfilm or by
any other means, without the prior written permission of HaskoningDHV UK Ltd.; nor may they be used, without such
permission, for any purposes other than that for which they were produced. HaskoningDHV UK Ltd. accepts no
responsibility or liability for these specifications/printed matter to any party other than the persons by whom it was
commissioned and as concluded under that Appointment. The integrated QHSE management system of
HaskoningDHV UK Ltd. has been certified in accordance with ISO 9001:2015, ISO 14001:2015 and ISO 45001:2018.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
Table of Contents
7 Marine Water and Sediment Quality 1
7.1 Introduction 1
7.2 Policy, Legislation and Guidance 1
7.3 Consultation 7
7.4 Methodology 8
7.5 Existing Environment 13
7.6 Embedded Mitigation 16
7.7 Potential Impacts during Construction 17
7.8 Potential Impacts during Operation 19
7.9 Potential Impacts during Decommissioning 20
7.10 Cumulative Impact Assessment 21
7.11 Inter-relationships 21
7.12 Interactions 22
7.13 Summary 23
7.14 References 24
Table of Tables
Table 7-1 Summary of key international legislation and policy relevant to this proposed scheme 2
Table 7-2 Summary of key national legislation and policy relevant to this proposed scheme 2
Table 7-3 Relevant local planning policies 7
Table 7-4 Consultation responses 8
Table 7-5 Definitions of Sensitivity Levels for a Receptor 10
Table 7-6 Definitions of magnitude levels 11
Table 7-7 Impact significance matrix 12
Table 7-8 Impact significance definitions 12
Table 7-9 2017 Classification status of Largs Channel (Fairlie Roads) coastal water body 14
Table 7-10 Potential construction impacts 17
Table 7-11 Potential operational impacts 20
Table 7-12 Inter-topic relationships 22
Table 7-13 Potential interaction between impacts 22
Table 7-14 Potential Impacts Identified for marine water and sediment quality 23
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
i
Table of Figures
Figure 7-1 Location of WFD water bodies and Bathing Waters
Figure 7-2 Location of vibrocore samples
Appendices
Appendix 7.1 Pre-Disposal Sampling Results Form
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
ii
Acronyms
Acronym Acronym description
CCME Canadian Council of Ministers of the Environment
CEMP Construction Environment Management Plan
CIA Cumulative Impact Assessment
DAERA Department of Agriculture, the Environment and Rural Affairs
EA Environment Agency
EIA Environmental Impact Assessment
EQS Environmental Quality Standards
ES Environmental Statement
FSA Food Standards Agency
GPP Guidance for Pollution Prevention
HMWB Heavily Modified Water Body
ISQG Interim Sediment Quality Guidelines
MS Marine Scotland
NIEA Northern Ireland Environment Agency
NRW Natural Resources Wales
PAH Polyaromatic Hydrocarbons
PEL Predicted Effects Level
PPG Pollution Prevention Guidelines
PSA Particle Size Analysis
RBMP River Basin Management Plan
SEPA Scottish Environmental Protection Agency
TEL Threshold Effects Level
WFD Water Framework Directive
WID Water Injection Dredging
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
iii
Glossary
Glossary Term Glossary Text
Environmental
Impact Assessment
(EIA)
A statutory process by which certain planned projects must be assessed before a
formal decision to proceed can be made. It involves the collection and
consideration of environmental information, which fulfils the assessment
requirements of the EIA Directive and EIA Regulations, including the publication
of an Environmental Statement.
Environmental
Statement (ES)
A document reporting the findings of the EIA and produced in accordance with the
EIA Directive as transposed into UK law by the EIA Regulations.
Millport Coastal
Flood Protection
Scheme
The scheme consists of offshore rock armour structures which will be built in the
vicinity of the rock islets within Millport Bay. Onshore works will include flood
walls, improvement works to existing coast protection structures, and works to
raise the level of existing grass areas. Works on the foreshore include shore-
connected rock armour breakwaters and rock armour revetments.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
1
7 Marine Water and Sediment Quality
7.1 Introduction
1. This chapter of the Environmental Statement (ES) considers the potential impacts of the proposed
Millport Coastal Flood Protection Scheme (the proposed scheme) on marine water and sediment
quality.
2. This chapter provides a summary description of key aspects relating to existing marine water and
sediment quality followed by an assessment of the magnitude and significance of the effects upon
the baseline conditions resulting from the construction, operation and decommissioning of the
proposed scheme as well as those effects resulting from cumulative interactions with other existing
or planned projects. The potential effects on marine water and sediment quality are assessed
conservatively using realistic worst-case scenarios for the proposed scheme.
3. All figures referred to in this chapter are provided in Volume II of this ES.
4. The assessment of potential effects has been made with specific reference to Scotland’s National
Planning Framework and Planning Policy . These are discussed further in Chapter 2 Policy and
Legislation and outlined below in Section 7.2. These are the principal decision-making documents
for flood protection schemes.
5. This chapter has been prepared by Royal HaskoningDHV in accordance with the relevant legislation
and policies, adhering to the methodology for Environmental Impact Assessment (EIA) and
Cumulative Impact Assessment (CIA) as discussed in Section 7.4.
6. As the movement of water and sediment within the marine environment is intrinsically linked with
physical processes, this chapter should be read in conjunction with Chapter 6 Marine Geology,
Oceanography and Physical Processes.
7. Information on the chemical analysis undertaken on sediments to support the assessment of impacts
on marine water and sediment quality is provided separately in Appendix 7.1 Pre-Disposal
Sampling Results Form (Volume III).
7.2 Policy, Legislation and Guidance
8. There are a number of pieces of legislation applicable to marine water and sediment quality which
are relevant to this chapter. Further details are provided in Chapter 2 Policy and Legislation.
9. The policies and plans outlined throughout this section have also been reviewed for their relevance
to marine water and sediment quality when undertaking the EIA for the proposed scheme.
7.2.1 International Legislation and Policy
10. Table 7-1 below provides a brief summary of the key international legislation and policy relevant to
the scheme.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
2
Table 7-1 Summary of key international legislation and policy relevant to this proposed scheme
Legislation Relevance
Water Framework Directive
(WFD) (2000/60/EC)
Council Directive 2000/60/EC establishing a framework for community action in the
field of water policy. requires that all European Union (EU) Member States must
prevent deterioration and protect and enhance the status of aquatic ecosystems.
This means that EU Member States must ensure that new schemes do not
adversely impact upon the status of aquatic ecosystems, and that historical
modifications that are already impacting it need to be addressed.
Bathing Water Directive
(2006/7/EC)
This Directive requires Member States to monitor and assess bathing waters and
inform the public about bathing water quality and beach management through
bathing water profiles. Bathing Waters are Protected Areas under the WFD.
Marine Strategy Framework
Directive (MSFD) (2008/56/EC)
The MSFD establishes a framework for community action in the field of marine
environmental policy and aims to achieve Good Environmental Status (GES) of the
EU's marine waters by 2020 and to protect the resource base upon which marine-
related economic and social activities depend. In order to achieve GES by 2020,
each Member State is required to develop a strategy for its marine waters (or
Marine Strategy).
The International Convention for
the Prevention of Marine
Pollution by Ships 73/78
(MARPOL)
The International Convention for the Prevention of Pollution from Ships (MARPOL),
to which the UK is a signatory, seeks to prevent and minimise marine pollution from
ships arising from operational and accidental events.
7.2.2 National Legislation and Policy
7.2.2.1 National Legislation
11. Table 7-2 below provides a brief summary of the key national legislation and policy relevant to the
scheme.
Table 7-2 Summary of key national legislation and policy relevant to this proposed scheme
Legislation Relevance
Marine and Coastal Access Act
2009
The Act provides executive devolution to Scottish Ministers of the new marine
planning and conservation powers in the offshore region (12-200 nautical miles),
coinciding with the existing executive devolution of marine licensing. The Marine
(Scotland) Act 2010 provides the legislation for marine planning, licensing and
conservation activities in the inshore region.
Marine (Scotland) Act 2010
The act defines the requirement for marine licences in Scottish waters which
includes the “construction of any works in or over the sea, and on or under the
seabed” and the carrying “out of any form of dredging within the Scottish marine
area (whether or not involving the removal of any material from the sea or sea
bed)”. The application for a licence must have regard to the need to protect the
environment, protect human health, prevent interference with legitimate uses of the
sea and other matters considered relevant by Scottish Ministers.
Marine Policy Statement (2011)
The Marine Policy Statement (MPS) is the framework for preparing Marine Plans
and taking decisions affecting the marine environment. It will contribute to the
achievement of sustainable development in the United Kingdom marine area,
ensuring that marine resources are used in a sustainable way in line with the high
level marine objectives.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
3
Legislation Relevance
Water Environment and Water
Services (Scotland) Act 2003
(WEWS Act)
This arose from the Water Framework Directive 2000/60/EC becoming law in
Scotland. It commits Scotland to achieve good qualitative and quantitative status of
all water bodies by 2015 with the final deadline for meeting objectives being 2027.
River basins comprise all transitional waters (estuaries) and coastal waters
extending to 3 nautical miles (nm) seaward from the territorial baseline. Any
proposed development within 3nm must have regard to the requirements of the
WFD to ensure that all transitional and coastal water bodies achieve ‘Good
Ecological Status’ and that there is no deterioration in status.
Water Environment (Controlled
Activities) (Scotland) Regulations
2011 (as amended)
The Controlled Activities Regulations 2011 (CARs) (and it’s amendments in 2013
and 2017) apply regulatory controls over activities which may affect Scotland’s
water environment. The regulations cover rivers, lochs, transitional waters
(estuaries), coastal waters, groundwater and groundwater dependent wetlands.
The Marine Strategy Regulations
2010
The MSFD 2008 (Directive 2008/56/EC) was transposed into UK law in 2010
through the Marine Strategy Regulations 2010. This establishes a framework for
community action in the field of marine environmental policy and aims to achieve
Good Environmental Status (GES) in UK marine waters by 2020.
Water Environment (Shellfish
Water Protected Areas:
Environmental Objectives etc.)
(Scotland) Regulations 2013
The Shellfish Waters Directive was repealed in 2013 and was replaced by this
legislation in 2013. The objectives of this regulation are to prevent the deterioration
of water quality within a shellfish water protected area and protect and improve
each protected area to achieve good water quality by 2015. In order to help
achieve this these regulations also put in place a monitoring and measures
programmes for each shellfish water.
Bathing Waters (Scotland)
Amendment Regulations 2012
Previously designated under the Bathing Water Directive (76/160/EEC), these
waters are now covered by the revised Bathing Water Directive (2006/7/EC) which
are transposed into Scottish law through the Bathing Waters (Scotland) Amendment
Regulations 2012
MARPOL Convention
The MARPOL Convention is the main international convention covering prevention
of pollution of the marine environment by ships from operational or accidental
causes. It is a combination of two treaties adopted in 1973 and 1978 respectively
and updated by amendments through the years. The Convention covers all the
technical aspects of pollution from ships, except the disposal of waste into the sea
by dumping, and applies to ships of all types, although it does not apply to pollution
arising out of the exploration and exploitation of sea-bed mineral resources.
Marine Scotland Action Levels for
the disposal of dredged material
Marine Scotland guideline Action Levels for the disposal of dredged material are not
statutory contaminant concentrations for dredged material but are used as part of a
weight of evidence approach to decision-making on the disposal of dredged
material to sea. These values are used in conjunction with a range of other
assessment methods as well as historical data and knowledge regarding the
dredging site, the material's physical characteristics, the disposal site characteristics
and other relevant data, to make management decisions regarding the fate of
dredged material.
The Action Levels are therefore not ‘pass/fail’ criteria but triggers for further
assessment. In general, contaminant levels in dredged material below Action Level
1 are of no concern and are unlikely to influence the licensing decision. However,
dredged material with contaminant levels above Action Level 2 is generally
considered unsuitable for sea disposal. Dredged material with contaminant levels
between Action Levels 1 and 2 requires further consideration and testing before a
decision can be made.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
4
7.2.2.2 National Planning Policy
National Planning Framework
12. Scotland’s Third National Planning Framework (NPF) (Scottish Government, 2014a) includes the
following ambitions relevant to the marine environment at Millport, and these have been considered
when undertaking the EIA for the proposed scheme:
13. Para 4.10: “The 2020 Challenge for Scotland’s Biodiversity aims to promote and enhance
Scotland’s nature, and to better connect people with the natural world. Maintaining our natural
capacity to provide services makes economic sense – to help achieve this, biodiversity in Scotland
needs to be viewed at a landscape scale;”
14. And:
15. Para 4.29: “The environment of our coastal areas, on land and at sea, is an outstanding,
internationally important resource. These natural assets support quality of life and underpin important
economic sectors like tourism, outdoor recreation and food and drink.”
16. Para 4.30: “The marine environment, and its natural resources, are central to this. National
and Regional Marine Plans will provide policies to achieve sustainable development, protection and,
where appropriate, enhancement of the marine area. Onshore, land management practices, including
crofting in the north and west and on the islands, help to sustain unique cultural and natural
environments.”
17. Para 4.31: “As climate change impacts on Scotland’s coastline, there will be a need to address
the long-term resilience of some island and coastal communities.”
Scottish Planning Policy
18. Scotland’s Planning Policy (SPP) (Scottish Government, 2014b) contains the following Policy
Principles with regards to Valuing the Natural Environment and these have been taken into
consideration when undertaking the EIA for the proposed scheme:
19. “The planning system should:
• Facilitate positive change while maintaining and enhancing distinctive landscape character;
• Conserve and enhance protected sites and species, taking account of the need to maintain
healthy ecosystems and work with the natural processes which provide important services to
communities;
• Promote protection and improvement of the water environment, including rivers, lochs,
estuaries, wetlands, coastal waters and groundwater, in a sustainable and co-ordinated way;
• Seek benefits for biodiversity from new development where possible, including the restoration
of degraded habitats and the avoidance of further fragmentation or isolation of habitats; and
• Support opportunities for enjoying and learning about the natural environment.
• The planning system should support an integrated approach to coastal planning to ensure that
development plans and regional marine plans are complementary.
Planning Advice Notes (PANS)
20. Planning Advice Note (PAN) 1/2013: Environmental Impact Assessment explains the role of individual
planning authorities and that of the Consultation Bodies in EIA, as well as providing guidance on the
ways in which EIA can be integrated into the overall development management process.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
5
21. PAN 60: Planning for Natural Heritage provides advice on how development and the planning system
can contribute to the conservation, enhancement, enjoyment and understanding of Scotland's natural
environment and encourages developers and planning authorities to be positive and creative in
addressing natural heritage issues. It complements the National Planning Policy Guideline on Natural
Heritage (NPPG 14), with examples of good planning practice in relation to natural heritage drawn
from across Scotland highlighted in a number of case studies.
National Planning Policy Guidelines (NPPG)
22. National Planning Policy Guideline (NPPG) 14: Natural Heritage gives guidance on how the
Government's policies for the conservation and enhancement of Scotland's natural heritage should
be reflected in land use planning. In this context, Scotland's natural heritage includes its plants and
animals, its landforms and geology, and its natural beauty and amenity. Natural heritage embraces
the combination and interrelationship of landform, habitat, wildlife and landscape and their capacity
to provide enjoyment and inspiration. It therefore encompasses both physical attributes and aesthetic
values and, given the long interaction between human communities and the land in Scotland, has
important cultural and economic dimensions.
Scotland’s National Marine Plan: A Single Framework for Managing Our Seas
23. This Plan covers both Scottish inshore waters (out to 12 nautical miles) and offshore waters (12 to
200 nautical miles). It also applies to the exercise of both reserved and devolved functions. Under
devolution, the Scottish Parliament can legislate in relation to activities affecting the marine
environment in Scotland’s inshore waters, except for reserved matters. The UK Parliament legislates
for Scotland’s offshore waters, but certain matters in this area have been executively devolved.
Marine planning matters in Scotland’s inshore waters are governed by the Marine (Scotland) Act
2010, an Act of the Scottish Parliament, and in its offshore waters by the Marine and Coastal Access
Act 2009, an Act of the UK Parliament.
24. The two Acts (referred to as the Marine Acts) established a new legislative and management
framework for the marine environment allowing the competing demands on the sea to be managed
in a sustainable way across all of Scotland’s seas. Under the Marine (Scotland) Act 2010 Scottish
Ministers must prepare and adopt a National Marine Plan covering Scottish inshore waters. In
addition, the Marine and Coastal Access Act 2009 required Scottish Ministers to ensure that a marine
plan was in place in the offshore region for when the Marine Policy Statement came into effect (in
2011).
7.2.3 Regional Legislation and Policy
7.2.3.1 Clyde Regional Marine Plan
25. The Marine (Scotland) Act allowed for the creation of 11 Scottish Marine Regions by the Scottish
Marine Regions Order 2015. The boundaries of these extend from MHWS out to 12 nm and up to
the Normal Tidal Limit of rivers within the region. The Act also allows for the development of regional
marine planning partnerships, of which Clyde and Shetland Isles are the first to be developed.
26. The Clyde Regional Marine Plan is being produced by the Clyde Marine Planning Partnership who
were given the powers to do so by Ministerial Direction in 2017. Pre-consultation on the draft Clyde
Regional Marine Plan took place between 18th March and 27th May 2019. This pre-consultation draft
is based on the Clyde Marine Region Assessment (2017) which provided a comprehensive review of
environmental, social and economic trends and issues in the Clyde Marine Region. The draft Plan
will be reviewed and updated following comments received and submitted for statutory consultation.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
6
The final version of the Clyde Regional Marine Plan is planned to be published in Q2/Q3 of 2020
following Scottish Ministerial approval.
27. The Plan will create a framework for integrated, sustainable and co-ordinated planning and
management of the Clyde Marine Region’s environmental, economic and community resource.
7.2.4 Local Planning Policy
28. The proposed scheme falls within the North Ayrshire Council local authority boundary.
7.2.4.1 North Ayrshire Local Development Plan
29. North Ayrshire Council have adopted a new Local Development Plan (LDP) for North Ayrshire on
28th November 2019 (North Ayrshire Council, 2019), the LDP covers a 20 year period. For the
purpose of the Local Plan, Millport and the footprint of the proposed scheme is categorised to be
within ‘Developed Coast’.
30. Within this LDP, the Millport Conservation Area Regeneration Scheme (CARS) and the Flood
Defence Scheme is listed as Strategic Development Area 3 for Millport, Cumbrae.
7.2.4.2 Ayrshire Joint Structure Plan
31. The Ayrshire Joint Structure Plan ‘Growing A Sustainable Ayrshire’ (North Ayrshire Council, East
Ayrshire Council and South Ayrshire Council, 2007) establishes a framework that brings together the
aspirations of communities with those of business and industry, and the area’s many supporting
agencies and organisations, to provide a strategic land use context to the year 2025.
7.2.4.3 Ayrshire Shoreline Management Plan 2018
32. The Ayrshire Shoreline Management Plan was development by the North and South Ayrshire
Councils and adopted in 2018. Millport is contained within Sub-Cell: Great Cumbrae. The Action
Plan for this sub cell contains actions for the maintenance of existing defences, the Millport Flood
Defence Scheme, Coastal flooding feasibility study and an action on coastal flood protection for
roads.
33. Table 7-2Table 7-3 provides details of the local planning policy documents and the relevant policies
in respect to marine water and sediment quality. These policy document have been considered when
undertaking the EIA for the proposed scheme.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
7
Table 7-3 Relevant local planning policies
Document Policy /
Guidance Policy / Guidance purpose ES Reference
Adopted Local
Development Plan
(North Ayrshire
Council, 2019)
Policy 22
Water Environment Quality:
Developments will be supported that help achieve
the objectives of the WFD and the River Basin
Management Plan for Scotland. The development
will be required to ensure no unacceptable adverse
impact on the water environment by:
Protecting and enhancing the ecological status …,
natural heritage, landscape values and physical
characteristics of water bodies (including biodiversity
and geodiversity);
… protecting opportunities for public access to and
recreation and enjoyment on and around … the
coastal marine area; and
Having regard to any designated Bathing Waters.
Section 7.5
Policy 24
Alignment with Marine Planning
1: Within the developed coast:
All marine proposals should identify environmental
impacts and mitigate against these to ensure there
are not any unacceptable adverse impacts.
Developments on coastal areas with significant
constraints will be supported, in principle, only where
they would also contribute to the economic
regeneration or well-being of communities whose
livelihood is dependent on marine or coastal
activities.
Sections 7.7
and 7.8
Ayrshire Joint
Structure Plan
(2014)
ENV 9 Water
Framework
Directive
The three Ayrshire councils shall work with other
agencies to introduce the Water Framework Directive
into Planning Policy.
Section 7.5.2
ENV 10
Integrated
Coastal Zone
Management
North and South Ayrshire Councils shall bring
forward proposals for a coastal zone management
plan for the Ayrshire coastline.
Chapter 18
Water
Resources and
Flood Risk
7.3 Consultation
34. To inform the ES, North Ayrshire Council has undertaken a thorough pre-application consultation
process, which has included the following key stages:
• Scoping Reports submitted to Marine Scotland and North Ayrshire Council (Royal HaskoningDHV
2017); and
• Scoping Opinion received from Marine Scotland and North Ayrshire Council (2017).
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
8
35. Full details of the proposed scheme consultation process to date is presented within Chapter 3 EIA
Methodology and Consultation.
36. A summary of the consultation carried out at key stages throughout the proposed scheme, of
particular relevance to marine water and sediment quality, is presented in Table 7-4.
Table 7-4 Consultation responses
Consultee Date/
Document Comment
Response / Where
addressed in the ES
SEPA
19/05/2017 /
Scoping
Report
Engineering works proposed are unlikely to require
CAR consent based on current design. Noted
Comply with PPG [Pollution Prevention Guidelines]
Notes during construction Section 7.4.1 and 7.7.1.
Do not agree that disturbed sediments are unlikely
to be an issue as there could be a risk if foreshore
works and/or dredging are done during the bathing
season (summer months). If works are to be
undertaken during the bathing waters season the
ES should address this.
Dredging works are
programmed to take place in
February 2022, outside the
Bathing Water season
(Section 7.6 and 7.7.1)
Welcome the consideration of impacts of existing
infrastructure on the environment and expect that
the ES will include information to confirm that there
will be no disruption to the sewerage system during
the bathing water season.
Addressed in Chapter 18
Water Resources and Flood
Risk
7.4 Methodology
37. This section describes the methodology used to obtain baseline data, characterise the marine water
and sediment quality of the area and undertake the EIA.
7.4.1 Best Practice and Guidance
38. The impact assessment has been based upon the following guidance and standards:
• Institute for Environmental Management and Assessment (IEMA) EIA Guidance
• SEPA (2016) Standing Advice for Marine Scotland on Small Scale Marine Licence Consultations.
39. SEPA has produced a number of guidance documents and Guidance for Pollution Prevention (GPP)
documents (in collaboration with Natural Resources Wales (NRW) and the Northern Ireland
Environment Agency (NIEA)) in the field of water quality which are relevant to the project:
• Supporting Guidance WAT-SG-53 on Environmental Quality Standards and Standards for
Discharges to Surface Waters (SEPA, 2019);
• GPP5: Works and maintenance in or near water (NIEA, Department for Agriculture the Environment
and Rural Affairs (DAERA), SEPA and NRW, 2018);
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
9
• Pollution Prevention Guidance (PPG) 6: Working at construction or demolition sites (Environment
Agency (EA), NIEA and SEPA, 2012);
• GPP21: Pollution incident response planning (NIEA, SEPA and NRW, 2017); and,
• GPP22: Dealing with spills (NIEA, DAERA, SEPA and NRW, 2018a).
40. PPG6 has not yet been superseded by an updated GPP document and in the absence of other
regulatory guidance this is still considered relevant to managing environmental responsibilities and
protection of the environment.
41. There is no specific legislation concerning marine sediment quality. There are however, non-statutory
guidelines and assessment criteria applicable to marine sediments and the following have been used
in this assessment:
• The revised Marine Scotland (MS) Action Levels for the disposal of dredged sediment; and,
• The Canadian Interim Sediment Quality Guidelines (ISQG)1.
7.4.2 Baseline Data and Study Area
7.4.2.1 Data Sources – Desk Study
42. This section describes the data sources used to inform the assessment of effects of the development
on water and sediment quality. Data were collated through desk-based studies and site-specific
survey work and analysis commissioned to inform this ES. Desk-based sources consulted include:
• SEPA’s website and tools including the Water Environment Hub - https://www.sepa.org.uk/data-
visualisation/water-environment-hub/
• Scotland’s Environment Web – Map - https://map.environment.gov.scot/sewebmap/
• Scotland Government website - https://www.gov.scot/policies/water/protected-waters/
7.4.2.1 Data Sources – Site Specific Surveys and Reports
43. A site-specific survey was undertaken between the 28th and 30th September 2019 during which
sediment samples were taken for chemical and physical analysis and sent to SOCOTEC. The
samples were tested for the standard suite of chemicals as specified by MS. The samples also
underwent Particle Size Analysis (PSA) to determine the physical composition of the sediment.
7.4.2.2 Summary of Study Areas
44. The primary study area comprises the footprint of the project, including the landside works, intertidal
works and subtidal works. Adjacent areas within 2km of Millport containing designated water bodies,
shellfish waters and/or bathing waters that may be indirectly impacted (as evaluated in the
hydrodynamic modelling studies) have also been included in this assessment.
1CCME Summary Table: http://st-ts.ccme.ca/en/index.html
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
10
7.4.3 Impact Assessment Methodology
45. General methods for EIA are discussed in Chapter 3 EIA Methodology and Consultation. The
following sections describe the methodology used to assess the potential impacts of the proposed
scheme on marine water and sediment quality in more detail.
46. The approach to determining the significance of an impact follows a systematic process for all
impacts. This involves identifying, qualifying and, where possible, quantifying the sensitivity, value
and magnitude of all ecological receptors which have been scoped into this assessment. Using this
information, a significance of each potential impact has been determined. Each of these steps is set
out in the remainder of this section.
47. For the impacts on marine water and sediment quality a number of discrete receptors can be
identified. These include certain designated areas with ascribed inherent values, such as:
• Bathing Waters,
• Shellfish Waters and,
• Nature conservation sites.
7.4.3.1 Sensitivity
48. The sensitivity of a receptor (Table 7-5) is dependent upon its:
• Tolerance: the extent to which the receptor is adversely affected by an effect;
• Adaptability: the ability of the receptor to avoid adverse impacts that would otherwise arise from an
effect; and
• Recoverability: a measure of a receptor’s ability to return to a state at, or close to, that which existed
before the effect caused a change.
49. The sensitivity is assessed using expert judgement and described with a standard semantic scale.
Definitions for each term are provided in Table 7-5. Expert judgements regarding receptor sensitivity
is closely guided by the conceptual understanding of baseline conditions.
Table 7-5 Definitions of Sensitivity Levels for a Receptor
Sensitivity Definition
High
The water quality of the receptor supports or contributes towards the designation of an
internationally or nationally important feature and/or has a very low capacity to accommodate any
change to current water quality status, compared to baseline conditions.
Medium The water quality of the receptor supports high biodiversity and/or has low capacity to
accommodate change to water quality status.
Low
The water quality of the receptor has a high capacity to accommodate change to water quality
status due, for example, to large relative size of the receiving water and capacity for dilution and
flushing. Background concentrations of certain parameters already exist.
Negligible Specific water quality conditions of the receptor are likely to be able to tolerate proposed change
with very little or no impact upon the baseline conditions detectable.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
11
50. The sensitivity criterion for water quality is a composite one; combining value (a measure of the
receptors importance, rarity and worth) with sensitivity. In some instances, the inherent value of a
receptor is recognised by means of designation (such as a bathing or shellfish water) and the ‘value’
element of the composite criterion recognises and gives weight in the assessment to that designation.
However, irrespective of the recognised value, all receptors will exhibit a greater or lesser degree of
sensitivity to the potential changes brought about by the proposed scheme.
7.4.3.2 Magnitude
51. The magnitude of the impact is assessed according to:
• The extent of the area subject to a predicted impact;
• The duration the impact is expected to last prior to recovery or replacement of the resource or
feature;
• Whether the impact is reversible, with recovery through natural or spontaneous regeneration, or
through the implementation of mitigation measures or irreversible, when no recovery is possible
within a reasonable timescale or there is no intention to reverse the impact; and
• The timing and frequency of the impact, i.e. conflicting with critical seasons or increasing impact
through repetition.
52. Where effects are anticipated to occur, their magnitude has been determined as per the criteria stated
in Table 7-6.
Table 7-6 Definitions of magnitude levels
Magnitude Definition
High Major change to one or more parameters of the baseline water and sediment physicochemical
characteristics.
Medium Noticeable change to one or more parameters of the baseline water and sediment physicochemical
characteristics.
Low Small or short-term change from the baseline water and sediment physico-chemical characteristics.
Negligible No detectable change to water and sediment physico-chemical characteristics or change is within
natural variation.
Duration
53. The definitions of duration used within this ES are dependent on the receptor, and how sensitive it is
to effects over different timescales. However, in general terms the following definitions have been
used:
• Short term: effects which typically occur over a matter of days or weeks, or less than one spring
tide cycle;
• Medium term: effects which occur over a full season such as one Bathing Water season (one
summer); and
• Long term: effects which occur over more than one year.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
12
54. Where deviations from the definitions used within Section 7.4.3 occur, this is explained within the text.
7.4.3.3 Impact Significance
55. Following the identification of receptor importance and magnitude of the effect, it is possible to
determine the significance of the impact.
56. Impacts are unlikely to be significant where features of low importance are subject to small scale or
short-term effects. If an impact is found not to be significant at the level at which the resource or
feature has been valued, it may be significant at a more local level.
57. Following the identification of receptor importance and magnitude of effect, the significance of the
impact has been considered using the matrix presented in Table 7-7 below and knowledge of the
ecological features affected.
58. The assessment of potential impacts has been undertaken assuming implementation of embedded
mitigation and commitments for the proposed scheme. Residual impacts include any additional
mitigation measures required. An assessment of residual impacts is then made, after assuming
implementation of additional mitigation measures where required, i.e. the significance of the effects
that are predicted to remain after the implementation of all committed mitigation measures.
Table 7-7 Impact significance matrix
Negative Magnitude Beneficial Magnitude
High Medium Low Negligible Negligible Low Medium High
Sensitiv
ity
High Major Major Moderate Minor Minor Moderate Major Major
Medium Major Moderate Minor Minor Minor Minor Moderate Major
Low Moderate Minor Minor Negligible Negligible Minor Minor Moderate
Negligible Minor Minor Negligible Negligible Negligible Negligible Minor Minor
59. The impact significance categories are defined as shown in Table 7-8.
Table 7-8 Impact significance definitions
Impact
Significance Definition
Major
A significant downgrading of a designated water body status or sediment quality classification as a
result of a long-term inability to meet Environmental Quality Standards or changes to other
classification parameters.
Moderate
A downgrading of a designated water body status or sediment quality classification as a result of a
temporary inability to meet Environmental Quality Standards or short-term changes to other
classification parameters.
Minor One or more classification parameters change but this does not result in the modification of the
status of a designated water body or sediment quality classification.
Negligible Impact does not result in changes to any of the classification parameters that decide the status of
a designated water body or sediment quality classification.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
13
60. Note that for the purposes of this ES, major and moderate impacts are deemed to be significant. In
addition, whilst minor impacts are not significant in their own right, it is important to distinguish these
from other non-significant impacts as they may contribute to significant impacts cumulatively or
through interactions.
61. Embedded mitigation has been referred to and included in the initial assessment of impact. If the
impact does not require mitigation (or none is possible) the residual impact remains the same.
However, if mitigation is required, an assessment of the post-mitigation residual impact is provided.
62. For the purposes of this ES, ‘major’ and ‘moderate’ impacts are deemed to be significant (in EIA
terms). In addition, whilst ‘minor’ impacts may not be significant, it is important to distinguish these
from other non-significant (negligible) impacts as they may contribute to significant impacts
cumulatively. Following initial assessment, if the impact does not require additional mitigation (or
none is possible) the residual impact will remain the same. If, however, additional mitigation is
proposed there will be an assessment of the post-mitigation residual impact.
7.4.3.4 Cumulative Impact Assessment
63. For an introduction to the methodology used for the Cumulative Impact Assessment (CIA), please
refer to Chapter 3 EIA Methodology and Consultation. This chapter includes those cumulative
impacts that are specific to marine water and sediment quality.
64. The CIA involves consideration of whether impacts on a receptor can occur on a cumulative basis
between the Project and other activities, projects and plans for which sufficient information regarding
location and scale exist.
65. The potential for cumulative effects has been considered for the construction, operation and
decommissioning of the proposed scheme cumulatively with other projects.
66. It is assumed that any consented development would be subject to mitigation and management
measures which would reduce impacts to non-significant unless there were exceptional
circumstances, it is accepted that such projects or schemes may contribute to a wider cumulative
impact.
67. Finally, in cases where this proposed scheme has negligible or no impact on a receptor (through for
example avoidance of impact through routeing or construction methodology) it is considered that
there is no pathway for a cumulative impact.
7.5 Existing Environment
7.5.1 Overview
68. The island of Great Cumbrae is located in the Firth of Clyde about 1.5km from the mainland. The
majority of the coast of the island is characterised by an emergent rock platform, with isolated pocket
bays containing beaches. The rock foreshore is currently stable with low rates of change. Millport Bay
is the part of the island coast that contains larger lengths of mobile beach sediment. The bay can be
divided into three parts:
• Kames Bay located in the northeast corner of Millport which contains a 150m-wide sandy beach;
• a sandy beach (about 50m wide) on rock platform at Newtown Bay; and,
• the rest of the Millport shore, which has a sand and gravel veneer overlying rock platform.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
14
69. Millport Bay faces south, with Kames Bay (at the eastern end) aligned to the south-southwest. Within
the bay, there are large rock outcrops, known as the Eileans, the Leug and the Spoig, which provide
shelter to the central section of Millport Bay against waves from the south. The shelter provided by
these outcrops has led to the deposition of sand in their lee along the Newtown Bay shoreline (i.e.
forming a small salient).
70. Although the seawater in Millport Bay is fully marine, Smith (1955) observed that there was a
significant interstitial input of freshwater creating permanently brackish conditions locally on the
beach. Smith (1955) suggested that this was the result of rainwater which collects on a clay layer
above the underlying rocks in the dip of the Great Cumbrae Fault, and subsequently seeping through
the sand (creating local brackish conditions).
7.5.2 WFD Waterbody Classification
71. The proposed scheme is located within the Largs Channel (Fairlie Roads) coastal WFD waterbody
(ID: 200026) (Figure 7.1, Volume II). The waterbody has an overall Status of ‘Good’, with an overall
Ecology Status of ‘Good’, a Hydromorphology Status of ‘Good’ and Chemical Status of ‘Pass’. The
water body is expected to maintain this status in 2021 and 2027. Full classification details of this
waterbody are provided in Table 7-9.
Table 7-9 2017 Classification status of Largs Channel (Fairlie Roads) coastal water body
Parameter Status Confidence of Class
Overall Status Good High
Macro-invertebrates Good Medium
Alien species Good High
Morphology Good Medium
Specific pollutants Pass High
Macroalgae Good High
Dissolved Inorganic Nitrogen High Medium
Dissolved Oxygen High High
7.5.3 Millport Bay Bathing Water
72. Millport Bay bathing water is located between Marine Parade in the east and Knox’s Pier in the west
(Figure 7.1, Volume II). The bathing season runs between the 1st June and the 15th September during
which SEPA undertake water monitoring. Overall, the bathing water quality within Millport Bay during
2018 has been reported by SEPA as ‘Excellent’2. SEPA reports that the potential pollutant sources
at, or near the Millport Bay bathing water include four sewage pumping stations, and a surface water
discharge. However, SEPA reports that there are no significant pollution inputs to the Millport bathing
water under dry weather conditions.
2 https://apps.sepa.org.uk/bathingwaters/Classifications.aspx
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
15
7.5.4 Shellfish Waters
73. The Fairlie Shellfish Designated Water for mussels and oyster is located approximately 3.4km to the
west of the proposed scheme at Fairlie. The area is also designated as a Shellfish Harvesting Area
by the Food Standards Agency (FSA) for Class A and Class B oysters.
74. The most recently available monitoring results show that the Fairlie shellfish water had an overall
result of Pass for the water quality and biota standard, however it failed to meet the standard for
faecal coliforms. SEPA consider that livestock farming is the most likely cause of Fairlies past failures
to meet shellfish water standards3.
75. Under the WFD, the target objectives expect this shellfish water to Pass by 2021 (first River Basin
Management Plan (RBMP) Cycle) for Imperative Shellfish Growing Water Standards with high
confidence but the Guideline Shellfish Growing Water Standards is also predicted to pass by 2021
but with low confidence. No improvement actions are scheduled for this shellfish water.
76. Due to the distance of this shellfish water from the proposed scheme, it is considered that there is no
pathway for potential water quality impacts arising from the proposed scheme to affect the shellfish
water. As such this receptor is not considered further in this assessment.
7.5.5 Sediment Quality
77. A drop-down video survey was undertaken in January 2018 in the subtidal nearshore zone throughout
Millport Bay (Aquatic Survey and Monitoring Ltd (ASML), 2018) and described the biotopes present
within the bay. For the purposes of this report, the analysis is simplified to describe generalised
particle size only from the original descriptions (Chapter 6, Table 6-9). The results show that the
eastern part of Millport Bay (east of the Eileans) is dominated by a fine sand substrate closer to shore
and a muddy substrate further offshore. Across the western part of the bay and within the vicinity of
the Eileans the sea bed is either mixed sediment or rock outcrop. Further south, in the western part
of the bay, the sea bed is muddy (Figure 6-7, Volume II). This pattern of substrate correlates with the
bathymetry recorded across this area (Figure 6-4, Volume II).
78. To provide information on any chemical contamination present within the sediments, a geotechnical
site investigation survey was undertaken in September 2019. Using vibrocores, sediment cores
within, and adjacent to the footprint of the offshore breakwater (Figure 7-2, Volume II) were collected.
These were pushed through the sediment layer until core hit the bed rock. Sediment samples were
then taken from the surface, mid and bottom of the cores and sent to a certified laboratory
(SOCOTEC) for chemical and physical analysis.
79. The results of the analysis are presented in Appendix 7.1 (Volume III). A summary of the results is
provided below for ease of reference.
7.5.5.1 Particle Size Analysis
80. PSA results show that the sediment present within the offshore proposed scheme is comprised of
mixed sediments with the majority comprising sand and silt, and the surface samples being mainly
comprised of coarser sediment. The samples taken at mid- and bottom depth were made up of finer
material.
3 http://apps.sepa.org.uk/shellfish/pdf/47.pdf
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
16
7.5.5.2 Heavy Metals and Organotins
81. Concentration levels of heavy metals were found to be very low across samples. The mid-core
sample taken from VC06 contained slightly elevated levels of cadmium, chromium, mercury and lead.
In addition, slightly elevated levels of copper were found in the mid- and bottom-core samples of
VC04 and VC05. However, none of the heavy metals found were present at levels of concern and
only marginally exceeded MS Action Level 1. When averaged, the concentration of all the heavy
metals present in the samples is below MS Action Level 1.
82. Levels of organotins (tributyltin and dibutyltin) were found to be less than the Limit of Detection and
are therefore not of concern.
7.5.5.3 Polyaromatic Hydrocarbons
83. Levels of all polyaromatic hydrocarbons (PAH) were found to be below MS Action Level 1. As such
these contaminants are not present within the sediment at levels of concern.
7.5.5.4 Organohalogens
84. Levels of all organohalogens were found to be below MS Action Level 1. As such these contaminants
are not present within the sediment at levels of concern.
7.5.6 Anticipated Trends in Baseline Conditions
85. It is important to recognise that the baseline physical environment is not static, but instead will exhibit
considerable variability due to cycles or trends of natural change. These can include (for example)
the short-term effects of storms and surges, the well-observed patterns in the movement of tides
during spring and neap cycles and the longer-term effects of sea-level rise associated with global
climate change. Climate change will also likely alter rainfall patterns and bring more heavy
downpours. Coupled with the increased risk of storm level surges the frequency of flooding events
within coastal areas is expected to increase in the future. However, it is not anticipated that this would
result in a significant change in the current water and sediment quality environment within Millport
Bay and the wider Largs Channel area.
7.6 Embedded Mitigation
7.6.1.1 Scheme Design
86. Embedding mitigation into the proposed scheme design is a type of primary mitigation and is an
inherent aspect of the EIA process. A full account of embedded mitigation measures is contained in
Chapter 5 Project Description.
87. The current construction schedule for dredging and offshore construction works will avoid the Bathing
Water season which would be a mitigation measure recommended by SEPA. Further mitigation
measures relevant for marine water and sediment quality would include the adherence to the standard
best practice and policy requirements as set out in Section 7.4.1.
88. As the guidance notes set out in Section 7.4.1 will be followed throughout the construction and
operation of the proposed scheme the risk of an accidental spill occurring is considered to be
adequately mitigated and will not be considered further, as set out in the Scoping Report.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
17
7.7 Potential Impacts during Construction
89. This section discusses the potential impacts which may occur to marine water and sediment quality
receptors during activities associated with the construction of the proposed scheme. Impacts to
marine geology, oceanography and physical processes are considered in Chapter 6 Marine
Geology, Oceanography and Physical Processes. Impacts to intertidal and marine habitats and
species are considered in Chapter 8 Benthic and Intertidal Ecology.
90. Three potential impacts to marine water and sediment quality resulting from the construction stage
have been identified. These are described in Table 7-10:
Table 7-10 Potential construction impacts
Activity Receptor Impact
Capital
dredge
Disturbance of sediments and release of
sediment-bound substances into the
water column
Changes to classification status of designated RBMP
water bodies or Bathing Waters as a result of
noncompliance with standards
Deposition of mobilised sediments on
sea bed
Changes to sediment quality classification in the areas
affected by sediment deposition
7.7.1 Construction Impact 1: Deterioration in water quality resulting from the
disturbance of sediments and release of sediment-bound contaminants
into the water column
91. Construction works to be undertaken which could affect the water quality of the Millport Bay Bathing
Water and the Largs Channel (Fairlie Roads) coastal water body include:
• Removal of sediments covering the bedrock within the footprint of the offshore breakwaters using
water injection dredging (WID); and
• The excavation of intertidal beach sediment to allow for the construction of the onshore breakwater,
including the grouting of dowel bars into the bedrock to tie in the toe beam of the onshore breakwater
and revetment.
92. Some excavation of sediment within the intertidal zone may be required for construction of the
onshore rock armour breakwater, the Clyde Street rock armour revetment and the refurbishment of
the existing jetties. In total this will remove approximately 210m3 of sediment from the intertidal beach
at Millport. The sediment present on the beach is coarse sand and as such will not contain significant
concentrations of contaminants as they do not sorb easily to coarser sediments compared to fine
sediments (National Research Council (NRC), 1997). The sediment will be scraped to the side and
retained elsewhere on the beach above the mean high-water mark to ensure that none is lost with
the tide.
93. There will also be a small amount of bedrock excavation for construction of the toe to the stepped
concrete revetments, of approximately 150m3 in total. The excavated rock will likely be used a fill
beneath the new revetments. The excavation of the bedrock will also take place at low tide and as
such is not considered to have an adverse impact on marine water quality. Should any of the arisings
be washed out by the tide this is also not considered to have an adverse impact as the volume is
predicted to be very small and would not contain any contaminants.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
18
94. The installation of steel dowel bars will require the use of grout to secure them in place. The risk of
impacts from the release of grout into the marine environment will be minimised using best-practice
control measures which will be detailed in a Construction Environment Management Plan (CEMP).
These would include ensuring the grout is not spilled by not overfilling the holes and any spillages
should be cleaned up immediately.
95. If required, the removal of sediments from within the footprint of the proposed offshore breakwaters
is proposed to be undertaken by WID. There is approximately 1m to 2m of sediment present over
the bedrock. It is currently expected to be possible to construct the offshore breakwaters directly onto
this sediment, without the need to dredge to bedrock. However, if areas of greater sediment depth
or particularly loose sediment are encountered at the time of construction then a limited volume of
dredging may be required. It is estimated that a maximum of 25,000m3 of sediment would need to
be removed from the footprint of the breakwaters, with the total sediment excavation volume more
likely to be less than 10,000m3. The indicative construction programme estimates that any dredging
would be undertaken during February 2022 and will take up to three weeks to complete.
96. Chemical analysis undertaken on the sediment within the footprint of the offshore breakwaters
showed that there were five individual samples which contained marginal exceedances of Action
Level 1 for the heavy metals copper, cadmium, chromium, mercury and lead. However, when
averaged the concentrations of these heavy metals did not exceed Action Level 1. All other
contaminants were found at levels below Action Level 1 and are therefore not of concern.
97. An increase in suspended sediment concentration during the construction of the proposed scheme
could also lead to a potential reduction in water clarity and therefore quality. Changes in suspended
sediment concentrations were assessed to be negligible within Chapter 6 Section 6.8.1. The
process of WID will fluidise the sediment at the sea bed and would not cause a significant increase
in suspended sediment throughout the water column. PSA shows the dredged sediment is comprised
of coarse but fine mixed material, rather than containing lots of fine silty sediment, which will reduce
the risk of sediment plumes. The low silt levels are also unlikely to affect other water quality
parameters such as dissolved oxygen and in addition to this the dredge will be carried out in the
winter, further minimising any risk to dissolved oxygen. The coastal water body would also therefore
not be restricted in terms of dilution. Additionally, the works are short term (up to three weeks) and
would not be undertaken continuously.
98. Water quality within Millport Bay and the Largs Channel (Fairlie Roads) coastal water body is
considered to be of medium value as the area supports designations such as Millport Bay bathing
water, which is classed as ‘Excellent’ but the receiving water body is large compared to the size of
the proposed scheme and has a large capacity for dilution and flushing.
99. Adherence to the proposed methodologies and standard best practice measures described above
(Section 7.4.1), supported by a CEMP, the intertidal works are considered to have an effect of
negligible magnitude on the Bathing Water and coastal waterbody. The low levels of contamination
within the sediment, the duration and the timing of the offshore dredge are also considered to have
an effect of negligible magnitude on the Bathing Water and coastal water body. This therefore
results in an impact of minor adverse significance (which is considered to be not significant).
Mitigation
100. No mitigation is required to reduce the impact significance.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
19
Residual Impact
101. The residual impact is minor adverse, which is Not Significant.
7.7.2 Construction Impact 2: Deposition of mobilised sediments on the sea bed
causing a deterioration in sediment quality
102. WID is a hydrodynamic dredging technique where the sediment is remobilised using the action of
natural currents. Water is pumped into the sediment at low pressure, fluidising the sediment and
turning it into a density current which remains close to the sea bed. This fluidised sediment is then
picked up by natural currents and flow horizontally away from the dredged area. The method ensures
that the sediment remains within the sediment budget of the area and minimises dramatic increases
in the suspended sediment concentrations within the water column.
103. The chemical analysis carried out on the sediment within the footprint of the offshore breakwaters
shows that the sediment contains very marginal exceedances of heavy metals within five samples.
These concentrations, when averaged, do not exceed Action Level 1. All other contaminants were
present at levels below Action Level 1 and are not of concern to water or sediment quality (Appendix
7.1, Volume III).
104. As such these sediment contaminant concentrations do not present a risk to sea bed sediments,
infauna or epifauna where the sediment may be deposited. Consequently, the potential magnitude
of this effect is considered to be negligible. The sensitivity of the Largs Channel (Fairlie Roads)
coastal water body and the Millport Bay Bathing Water to this impact are the same as that defined in
Impact 1 – medium. This therefore results in an impact of minor adverse significance (which is
considered to be not significant).
Mitigation
105. No mitigation is required to reduce the impact significance.
Residual Impact
106. The residual impact is minor adverse which is Not Significant.
7.8 Potential Impacts during Operation
107. This section discusses the potential impacts which may occur to marine water and sediment quality
receptors during activities associated with the operation of the proposed scheme. Impacts to marine
geology, oceanography and physical processes are considered in Chapter 6 Marine Geology,
Oceanography and Physical Processes. Impacts to intertidal and marine habitats and species are
considered in Chapter 8 Benthic and Intertidal Ecology.
108. Potential impacts to marine water and sediment quality during the operation of the proposed scheme
are defined in Table 7-11.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
20
Table 7-11 Potential operational impacts
Activity Receptor Impact
Reduced flushing of water within
Millport Bay due to enclosure of
water within breakwater
Entrainment of
contaminants
Changes to classification status of designated RBMP
water bodies or Bathing Waters as a result of
noncompliance with standards.
7.8.1 Operation Impact 1: Entrainment of contaminants due to decreased
flushing of water within Millport Bay
109. The presence of an offshore breakwater has the potential to result in reduced flushing of water within
Millport Bay, potentially leading to a reduction in water quality through the entrainment of
contaminants entering the Bay from river/stream discharges during flood events. Chapter 6 Marine
Geology, Oceanography and Physical Processes assessed the potential changes to the tidal
current regime due to the presence of the proposed scheme (Chapter 6, Section 6.9.2) which is
summarised here for ease of reference.
110. Millport Bay is a sheltered area where baseline tidal currents are low. Flows are complicated by their
interaction with the offshore islands and are likely to accelerate slightly through the gaps between
The Leug, The Spoig and the southern Eilean islet rock outcrop. The presence of the offshore
breakwater would close the gaps between the islands and provide a permanent barrier to the
movement of water between the islands. However, the passage of water into the Bay would still be
effective around the east and west sides of the breakwaters, as water will be forced in these directions
by the obstruction.
111. The predicted changes to circulation and the local increases and decreases in current velocity are
not significant because the existing currents are already very low velocity. The barrier across the
central passage of water would not significantly affect the flushing ability of the Bay as the passages
to the east and west would continue to allow entry and exit of water. The impact assessment in
Chapter 6, Section 6.9.2 concluded that the presence of the proposed scheme would have an impact
of negligible significance on tidal currents, and consequently the flushing ability, within Millport Bay.
112. As such the magnitude of this potential impact is considered to be negligible on water quality. The
Largs Channel (Fairlie Roads) coastal water body and the Millport Bay Bathing Water are considered
to have a sensitivity of medium as the entrainment of contaminants is considered to be unlikely and
recoverable in the short term (less than one year). As such the potential impact is of minor adverse
significance (which is considered to be not significant).
Mitigation
113. No mitigation is required to reduce the impact significance.
Residual Impact
114. The residual impact is minor adverse which is Not Significant.
7.9 Potential Impacts during Decommissioning
115. The structures forming the coastal flood prevention scheme would be designed to have a life of at
least 50 years. As the purpose of the proposed scheme is for flood protection, it is unlikely that it
would be decommissioned entirely; it is more likely that the scheme would be repaired, or sections
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
21
replaced or improved if needed in the future. No decision has been made regarding the final
decommissioning policy for the offshore infrastructure of the proposed scheme as it is recognised
that industry best practice, rules and legislation change over time.
116. The detail and scope of the decommissioning works will be determined by the relevant legislation and
guidance at the time of decommissioning and agreed with the regulator. As discussed in Chapter 5
Project Description, a decommissioning plan will be submitted for approval by the regulatory
authorities prior to construction. As such, impacts no greater than those identified for the construction
phase are expected for the decommissioning phase.
7.10 Cumulative Impact Assessment
117. This section describes the CIA for marine water and sediment quality and will consider the Hunterston
Marine Construction Yard Proposals. Currently there are no other marine construction projects
planned which could result in cumulative effects with the proposed scheme.
118. Peel Ports own Hunterston Marine Construction Yard and are planning to construct, decommission
or reverse engineer large marine related structures. This will require improvements to the
hammerhead quay (and associated dredging) and creation of dock gates to the existing dry dock.
119. The proposals will take place within the Largs Channel (Fairlie Roads) coastal water body and is
approximately 3km from the Millport Bay Bathing Water and therefore could result in cumulative
impacts with the proposed scheme in relation to overlap of sediment plumes which could lead to
changes in physico-chemical parameters and contaminants. However, information for the proposed
dredge at Hunterston is not available and as such a cumulative impact on the marine water and
sediment quality of the coastal water body and the Bathing Water is not yet possible. It is therefore
assumed that any consented development would be subject to mitigation and management measures
which would reduce impacts to non-significant unless there were exceptional circumstances, it is
accepted that such projects or schemes may contribute to a wider cumulative impact.
120. The potential cumulative impact between the proposed scheme and the Hunterston proposals will
therefore be assessed within the submission for the Hunterston proposals.
7.11 Inter-relationships
Table 7-12 lists out the inter relationships between other chapters within the ES.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
22
Table 7-12 Inter-topic relationships
Topic Related Chapter Where addressed
in this chapter Rationale
Effects on water quality
arising from dredging
activities
Chapter 9 Fish and
Shellfish Resource
Sections 7.7 and
7.8
Changes in water quality may adversely impact fish
within spawning or nursery grounds
Chapter 12
Commercial
Fisheries
Changes in water quality may affect the quality,
movement or location of commercial fish or shellfish
species or fishing grounds
Chapter 23 Tourism
and Recreation
Changes in water quality may prevent tourism and
recreation activities within Millport Bay
Changes in sediment
quality arising from
dredging activities
Chapter 8 Benthic
and Intertidal
Ecology
Changes in sediment quality through the deposition
of contaminated sediment may affect benthic
communities
7.12 Interactions
121. The impacts identified and assessed in this chapter have the potential to interact with each other,
which could give rise to synergistic impacts as a result of that interaction. The worst-case impacts
assessed within this chapter take these interactions into account and for the impact assessments are
considered conservative and robust. For clarity, the areas of interaction between impacts are
presented in Table 7-13 along with an indication as to whether the interaction may give rise to
synergistic impacts.
Table 7-13 Potential interaction between impacts
Potential interaction between impacts
Construction
1: Deterioration in water quality resulting from
the disturbance of sediments and release of
sediment-bound contaminants into the water
column
2:
Deposition
of mobilised
sediments
on the sea
bed causing
a
deterioration
in sediment
quality
1: Deterioration in water quality resulting from
the disturbance of sediments and release of
sediment-bound contaminants into the water
column
Yes
2: Deposition of mobilised sediments on the
sea bed causing a deterioration in sediment
quality
Yes
Operation 1: Entrainment of contaminants due to
decreased flushing of water within Millport Bay
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
23
Potential interaction between impacts
1: Entrainment of contaminants due to
decreased flushing of water within Millport Bay Yes
7.13 Summary
122. The main potential impacts of the proposed scheme on marine water and sediment quality receptors
have been identified. Three potential impacts during construction and two potential impacts during
operation have been identified. A summary of the potential impacts and proposed mitigation is
presented in Table 7-14.
Table 7-14 Potential Impacts Identified for marine water and sediment quality
Potential Impact Receptor Value Magnitude Significance Mitigation
Measures
Residual
Impact
Construction
Impact 1:
Deterioration in
water quality
resulting from the
disturbance of
sediments and
release of
sediment-bound
contaminants into
the water column
Millport Bay
Bathing Water
and Largs
Channel (Fairlie
Roads) coastal
water body
Medium Negligible Negligible n/a Minor
Adverse
Impact 2:
Deposition of
mobilised
sediments on the
sea bed causing a
deterioration in
sediment quality
Millport Bay
Bathing Water
and Largs
Channel (Fairlie
Roads) coastal
water body
Medium Negligible Negligible n/a Minor
Adverse
Operation
Impact 1:
Entrainment of
contaminants due
to decreased
flushing of water
within Millport Bay
Millport Bay
Bathing Water
and Largs
Channel (Fairlie
Roads) coastal
water body
Medium Negligible Negligible n/a Minor
Adverse
Decommissioning
As a flood prevention scheme, the proposed scheme is anticipated to be maintained rather than removed, and
therefore decommissioning activities are currently unknown. This will be assessed at the time of any
decommissioning activities required.
P r o j e c t r e l a t e d
31 January 2020 PB4749-RHD-ZZ-XX-RP-Z-0007
24
7.14 References
ASML (2018) Millport Flood Protection Scheme – Drop Down Video Survey Report. Report to Royal
HaskoningDHV, February 2018.
EA, NIEA and SEPA (2012) Working at construction and demolition sites: PPG6. 2nd Edition 2012
NIEA, SEPA and NRW (2017) GPP 21: Pollution Incident Response Plans. July 2017
NIEA, DAERA, SEPA and NRW (2018) Guidance for Pollution Prevention: Works and maintenance in or
near water: GPP5. Version 1.2. February 2018
NIEA, DAERA, SEPA and NRW (2018a) Guidance for Pollution Prevention. Dealing with spills: GPP 22.
Version 1. October 2018
North Ayrshire Council, East Ayrshire Council and South Ayrshire Council (2007) Ayrshire Joint Structure
Plan. Available at: https://www.south-
ayrshire.gov.uk/documents/ayrshire%20joint%20structure%20plan%202007.pdf. Accessed: 20.11.19.
North Ayrshire Council (2019) Local Development Plan. Available at: https://www.north-
ayrshire.gov.uk/planning-and-building-standards/ldp/local-development-plan.aspx Accessed 30.01.20.
NRC (1997) Contaminated Sediments in Ports and Waterways: Cleanup Strategies and Technologies.
Washington, D.C.: The National Academic Press
Scottish Government (2014a) National Planning Framework (NPF) Available at:
https://www.gov.scot/publications/national-planning-framework-3/ Accessed: 20.11.19.
Scottish Government (2014b) Scotland’s Planning Policy (SPP). Available at:
https://www.gov.scot/publications/scottish-planning-policy/ Accessed: 20.11.19.
Scottish Government (2019) Planning Advice Notes. Available at
https://www.gov.scot/collections/planning-advice-notes-pans/ Accessed: 20.11.19.
SEPA (2019) Supporting Guidance (WAT-SG-53) Environmental Quality Standards and Standards for
Discharges to Surface Waters. Version 7. September 2019
Title:
Project:Millport Flood
Protection Scheme- EIA Report
Client:
Contains OS data © Crown Copyrightand database right 2019
North Ayrshire Council
±
Drawn: Scale:Checked:Date:Revision:
Drawing No:
Size:
British National Grid
Figure:
Co-ordinate system:
!(
Contains OS data © Crown Copyright and database right 2019
216000
216000
222000
222000
6540
00
6540
00
6600
00
6600
00
ROYAL HASKONINGDHV
±
Marlborough HouseMarlborough Crescent
Newcastle-upon-Tyne, NE1 4EE+44 (0)191 211 1300
www.royalhaskoningdhv.com
7.1
0 3 Kilometres
Legend
1:50,0000 TC A3SM14/11/2019
Location of WFD water bodiesand Bathing Waters
Redline BoundaryLargs Channel (Fairlie Roads) coastal WFD water body
© HaskoningDHV UK Ltd.© Crown copyright and database rights 2019 Ordnance Survey 100023393.Use of this data is subject to terms and conditions.
Bathing Water Quality: Millport Bay - Excellent!(
Title:
Project:Millport Flood
Protection Scheme- EIA Report
Client:
Contains OS data © Crown Copyrightand database right 2019
North Ayrshire Council
±
Drawn: Scale:Checked:Date:Revision:
Drawing No:
Size:
British National Grid
Figure:
Co-ordinate system:
!(!(
!(!(
!(!(
!(
VC06
VC05VC04
VC03
VC02
VC01
VC03a
216000
216000
217000
217000
6540
00
6540
00
6550
00
6550
00
ROYAL HASKONINGDHV
±
Marlborough HouseMarlborough Crescent
Newcastle-upon-Tyne, NE1 4EE+44 (0)191 211 1300
www.royalhaskoningdhv.com
7.2
0 200 400 Metres
Legend
0 TC A3SM14/11/2019
Location of vibrocore samples
Redline BoundaryPotential Site CompoundPotential Materials StorageFlood WallsRock BreakwaterRock RevetmentModifications to existing coast protection structuresModifications to existing promenade and grass areasOffshore Breakwater
!( Vibrocore Sample Locations
© HaskoningDHV UK Ltd.© Crown copyright and database rights 2019 Ordnance Survey 100023393.Use of this data is subject to terms and conditions.
1:6,0001:6,5001 TC A3AS04/02/2020
REPORT
Millport Coastal Flood Protection
Scheme: Environmental Statement
Appendix 7.1 Pre-Disposal Sampling Results Form
Client: North Ayrshire Council
Reference: PB4749-RHD-ZZ-XX-RP-Z-0007.1
Status: Final/F01
Date: 31 January 2020
a b
Pre-disposal Sampling Results Form Version 2 - June 2017
This form should be used to submit the results from your pre-disposal sampling plan.
Full information must be provided in all relevant sheets of this workbook. The blue cells in each worksheet indicate where information can be entered.
Where information cannot be provided, or where there are more than 30 samples required, please contact the Marine Scotland - Licensing Operations Team (MS-LOT)
using the contact details below.
Once you have completed this form, send it (including any reference number for the dredging and sea disposal marine licence application in the subject header of your email) to the following email address:
If you have any questions in relation to this form contact MS-LOT:
Marine Scotland - Licensing Operations Team
Marine Laboratory
375 Victoria Road
Aberdeen, AB11 9DB
01224 295579
Applicant Information
Sample Details & Physical Properties
Sample information:
MAR00392.00 VC01 ES1 ° . ˈN ° . ˈW 0 84 14.3 35.1 50.7
MAR00392.00 VC01 ES3 ° . ˈN ° . ˈW 1.1 87.7 42 31.4 26.6
MAR00392.00 VC01 ES2 ° . ˈN ° . ˈW 5.7 89.2 18.6 40.4 41
MAR00392.00 VC02 ES1 ° . ˈN ° . ˈW 0 87.3 58 28.3 13.7
MAR00392.00 VC02 ES2 ° . ˈN ° . ˈW 1.3 84.8 2.1 41.8 56.2
MAR00392.00 VC02 ES3 ° . ˈN ° . ˈW 2 85.1 0 36.6 63.4
MAR00392.00 VC03 ES1 ° . ˈN ° . ˈW 0 82.3 63 29.4 7.6
MAR00392.00 VC03 ES2 ° . ˈN ° . ˈW 0.3 86.1 22.2 58 19.7
MAR00392.00 VC03A ES1 ° . ˈN ° . ˈW 0 82.2 76.7 15.4 7.8
MAR00392.01 VC04 ES1 ° . ˈN ° . ˈW 0 84.8 22.5 64.4 13.1
MAR00392.01 VC04 ES2 ° . ˈN ° . ˈW 0.7 88.1 29.2 39.1 31.7
MAR00392.01 VC04 ES3 ° . ˈN ° . ˈW 1.7 88.9 12.5 38.8 48.7
MAR00392.01 VC05 ES1 ° . ˈN ° . ˈW 0 85.9 59.4 26.3 14.3
MAR00392.01 VC05 ES2 ° . ˈN ° . ˈW 1.4 87 12.6 34.2 53.2
MAR00392.01 VC05 ES3 ° . ˈN ° . ˈW 2.8 83.3 17.4 27 55.5
MAR00392.01 VC06 ES1 ° . ˈN ° . ˈW 0 83.3
MAR00392.01 VC06 ES2 ° . ˈN ° . ˈW 1.45 92.3 22.3 34.2 43.5
MAR00392.01 VC06 ES3 ° . ˈN ° . ˈW 1 89.7 24 33.6 42.4
° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW° . ˈN ° . ˈW
Silt
(%)
Total amount to be dredged (wet tonnes)
Explanatory Notes:
An example of a 'Dredge area' is: 'Dock A, Harbour X'
Provide description of the dredge area and the latitude and longitude co-oridnates (WGS84) for each sample location. Co-ordinates taken from GPS equipment should be set to WGS84.
Note for sample depth that the seabed is 0 metres.
Gravel is defined as >2mm, Sand is defined as >63um<2mm, Silt is deinfed as <63um).
Sample ID Dredge area Latitude Longitude
TOC
(%) Specific gravity Asbestos
Type of
sample
Sample depth
(m)
Total solids
(%)
Gravel
(%)
Sand
(%)
Applicant:
Description of dredging:
Trace Metals & Organotins
Sample information:
Arsenic (As) Cadmium (Cd) Chromium (Cr) Copper (Cu) Mercury (Hg) Nickel (Ni) Lead (Pb) Zinc (Zn) Dibutyltin (DBT) Tributyltin (TBT)
MAR00392.00 VC01 ES1 0 0 7.6 0.18 16.3 15.9 <0.01 16.7 8.3 50.3 <0.001 <0.001
MAR00392.00 VC01 ES3 0 1.1 4.4 0.21 20.4 21.5 <0.01 19.4 6.1 40 <0.001 <0.001
MAR00392.00 VC01 ES2 0 5.7 2.9 0.16 16.3 18.1 <0.01 16.4 5.2 39.2 <0.001 <0.001
MAR00392.00 VC02 ES1 0 0 6.8 0.19 17.2 13.6 0.02 14.4 7.4 43.4 <0.001 <0.001
MAR00392.00 VC02 ES2 0 1.3 4 0.15 17.2 18.9 <0.01 17.2 5.8 33.6 <0.001 <0.001
MAR00392.00 VC02 ES3 0 2 3.7 0.17 16.5 21.4 <0.01 16.2 5.5 42.1 <0.001 <0.001
MAR00392.00 VC03 ES1 0 0 5.6 0.11 15.9 14.6 0.02 14.5 6.6 52.4 <0.001 <0.001
MAR00392.00 VC03 ES2 0 0.3 3.5 0.12 13.5 13.2 <0.01 11.1 5.2 38.4 <0.001 <0.001
MAR00392.00 VC03A ES1 0 0 7.1 0.16 13.8 12.7 0.014 10.4 9.7 44.3 <0.001 <0.001
MAR00392.01 VC04 ES1 0 0 6.6 0.14 14.9 12.5 <0.01 13 11.6 47.9 <0.001 <0.001
MAR00392.01 VC04 ES2 0 0.7 3.3 0.16 21.8 30.2 <0.01 22 7.6 53.5 <0.001 <0.001
MAR00392.01 VC04 ES3 0 1.7 3.7 0.2 24.3 56.6 <0.01 25.2 7.8 57.6 <0.001 <0.001
MAR00392.01 VC05 ES1 0 0 7.7 0.16 20.2 20.7 0.036 24.2 8.4 67.1 <0.001 <0.001
MAR00392.01 VC05 ES2 0 1.4 4.6 0.15 22.5 61.9 0.011 25.4 7.6 67.3 <0.001 <0.001
MAR00392.01 VC05 ES3 0 2.8 5.2 0.15 23.1 31.7 <0.01 25.5 8.9 71.2 <0.001 <0.001
MAR00392.01 VC06 ES1 0 0 7.8 0.14 15.6 14.5 <0.01 17.1 11.2 57.4 <0.001 <0.001
MAR00392.01 VC06 ES2 0 1.45 4.1 1.42 52.4 26.2 0.56 29 68 55 <0.001 <0.001
MAR00392.01 VC06 ES3 0 1 4.1 0.15 22.1 27.1 0.02 22.8 7.7 70.5 <0.001 <0.001
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
Explanatory Notes:
Results above Action Level 1 will be highlighted in blue and above Action Level 2 in red.
Sample ID Dredge area
Type of
sample
Sample depth
(m) mg/kg dry weight
Polyaromatic Hydrocarbons (PAH)
Definitions:
ACENAPTH Acenaphthene
ACENAPHY Acenaphthylene
ANTHRACN Anthracene
BAA Benz(a)anthracene
BAP Benzo(a)pyrene
BBF Benzo(b)fluoranthene
BEP Benzo(e)pyrene
BENZGHIP Benzo(ghi)perylene
BKF Benzo(K)fluoranthene
C1N C1-naphthalenes
C1PHEN C1-phenanthrene
C2N C2-naphthalenes
C3N C3-naphthalenes
CHRYSENE Chrysene
DBENZAH Diben(ah)anthracene
FLUORANT Fluoranthene
FLUORENE Fluorene
INDPYR Indeno(1,2,3-cd)pyrene
NAPTH Naphthalene
PERYLENE Perylene
PHENANT Phenanthrene
PYRENE Pyrene
THC Total Hydrocarbon Content
Sample information:
ACENAPTH ACENAPHY ANTHRACN BAA BAP BBF BEP BENZGHIP BKF C1N C1PHEN C2N C3N CHRYSENE DBENZAH FLUORANT FLUORENE INDPYR NAPTH PERYLENE PHENANT PYRENE THC
MAR00392.001 VC01 ES1 0 0 <1 <1 <1 1.49 2.53 3.26 2.62 3.47 1.66 1.71 2.01 1.77 1.9 1.94 <1 2.49 <1 2.73 <1 1.13 1.9 2.98 5100
MAR00392.002 VC01 ES3 0 1.1 <1 <1 <1 <1 <1 1.7 1.34 1.45 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 1.31 <1 1720
MAR00392.003 VC01 ES2 0 5.7 <1 <1 <1 <1 <1 1.88 1.59 1.75 <1 <1 <1 <1 <1 <1 <1 1.45 <1 <1 <1 <1 2.07 1.18 1550
MAR00392.004 VC02 ES1 0 0 <1 <1 2.28 5.85 10.5 11.5 9 9.91 4.68 2.74 5.21 3.16 3.17 7.25 1.7 10.4 <1 9.78 1.46 2.72 5.18 15.1 11500
MAR00392.005 VC02 ES2 0 1.3 <1 <1 <1 <1 <1 2.11 1.65 1.68 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 1.69 <1 1360
MAR00392.006 VC02 ES3 0 2 <1 <1 <1 <1 <1 1.84 1.57 1.4 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 1.45 <1 2030
MAR00392.007 VC03 ES1 0 0 <1 <1 2.14 7.49 11 11.2 9.62 10.9 6.62 4.64 7.66 4.66 5.97 8.64 1.62 13.6 <1 10.6 2.15 3.25 6.58 15.1 13900
MAR00392.008 VC03 ES2 0 0.3 <1 <1 2.68 3.37 4.62 4.54 3.74 4.61 1.95 1.78 2.82 2.14 1.94 4.46 <1 6.75 <1 3.87 1.99 1.57 2.65 6.78 4730
MAR00392.009 VC03A ES1 0 0 <1 1.22 3.31 10.6 14.8 15.9 12.6 15.5 7.3 7.3 10.6 7.65 8.69 11.6 2.38 17.8 1.61 14.5 3.26 3.93 9.43 18.9 20400
MAR00392.010 VC04 ES1 0 0 <1 <1 <1 <1 1.47 1.61 1.54 2.06 <1 1.28 1.37 <1 <1 1.39 <1 1.7 <1 1.65 <1 <1 1.35 1.91 11100
MAR00392.011 VC04 ES2 0 0.7 <1 <1 <1 <1 <1 1.15 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 1.2 <1 2520
MAR00392.012 VC04 ES3 0 1.7 <1 <1 <1 <1 <1 1.44 1.17 1.36 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 1.41 <1 2280
MAR00392.013 VC05 ES1 0 0 <1 <1 1.86 3.7 3.83 5.41 4.21 5.46 1.88 6.09 16.1 13.5 25.1 4.64 <1 5.6 1.6 3.46 1.55 1.58 7.66 6.42 8480
MAR00392.014 VC05 ES2 0 1.4 <1 <1 <1 <1 <1 2.14 1.98 1.86 <1 <1 <1 <1 <1 1.31 <1 1.59 <1 <1 <1 <1 2.52 1.35 1840
MAR00392.015 VC05 ES3 0 2.8 <1 <1 <1 <1 <1 2 1.71 1.95 <1 1.81 1.77 1.33 1.47 1.2 <1 1.31 <1 <1 <1 1.86 2.12 1.33 5130
MAR00392.016 VC06 ES1 0 0 <1 <1 1.85 4.97 7.47 8.72 7.04 8.44 4.19 13.5 10.2 14.6 12.3 5.81 1.28 8.62 <1 7.89 2.93 2.29 9.08 10 15200
MAR00392.017 VC06 ES2 0 1.45 <1 <1 <1 <1 <1 2.32 1.75 1.77 <1 <1 <1 <1 <1 1.2 <1 1.29 <1 <1 <1 1.86 1.95 <1 6360
MAR00392.018 VC06 ES3 0 1 <1 <1 <1 <1 <1 2.58 1.85 1.88 <1 <1 <1 <1 <1 1.28 <1 1.41 <1 <1 <1 1.92 1.97 <1 9890
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
Explanatory Notes:
Results above Action Level 1 will be highlighted in blue and above Action Level 2 in red.
Sample ID Dredge area
Type of
sample
Sample depth
(m)
µg/kg
Organohalogens
Definitions:
AHCH alpha-Hexachlorcyclohexane
BHCH beta-Hexachlorcyclohexane
GHCH gamma-Hexachlorcyclohexane
DIELDRIN Dieldrin
HCB Hexachlorobenzene
PPDDE p,p'-Dichorodiphenyldicloroethylene
PPDDT p,p'-Dichorodiphenyltrichloroethane
PPTDE p,p'-Dichorodiphenyldicloroethane
Sample information:
PCB28 PCB52 PCB101 PCB118 PCB138 PCB153 PCB18 PCB105 PCB110 PCB128 PCB141 PCB149 PCB151 PCB156 PCB158 PCB170 PCB180 PCB183 PCB187 PCB194 PCB31 PCB44 PCB47 PCB49 PCB66 ICES7 AHCH BHCH GHCH DIELDRIN HCB DDE DDT TDE BDE100 BDE138 BDE153 BDE154 BDE17 BDE183 BDE209 BDE28 BDE47 BDE66 BDE85 BDE99
MAR00392.00 VC01 ES1 0 0 0.301 0.162 <0.08 <0.08 <0.08 <0.08 0.466 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.326 0.136 <0.08 0.12 <0.08 0.863 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC01 ES3 0 1.1 0.285 0.149 <0.08 <0.08 <0.08 <0.08 0.381 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.283 0.104 <0.08 0.117 <0.08 0.834 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC01 ES2 0 5.7 0.305 0.164 <0.08 <0.08 <0.08 <0.08 0.449 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.307 0.106 <0.08 0.139 <0.08 0.869 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC02 ES1 0 0 0.276 0.161 <0.08 <0.08 <0.08 <0.08 0.415 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.293 0.104 <0.08 0.111 0.083 0.837 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC02 ES2 0 1.3 0.192 0.105 <0.08 <0.08 <0.08 <0.08 0.257 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.254 <0.08 <0.08 0.081 <0.08 0.697 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC02 ES3 0 2 0.136 <0.08 <0.08 <0.08 <0.08 <0.08 0.205 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.138 <0.08 <0.08 <0.08 <0.08 0.616 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC03 ES1 0 0 0.318 0.131 <0.08 <0.08 <0.08 <0.08 0.411 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.308 0.1 <0.08 0.105 0.097 0.849 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC03 ES2 0 0.3 0.18 0.088 <0.08 <0.08 <0.08 <0.08 0.222 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.2 <0.08 <0.08 <0.08 <0.08 0.668 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.158 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.00 VC03A ES1 0 0 0.194 0.122 <0.08 <0.08 0.122 <0.08 0.282 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.206 <0.08 <0.08 <0.08 0.097 0.758 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC04 ES1 0 0 0.178 0.095 <0.08 <0.08 <0.08 <0.08 0.288 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.208 <0.08 <0.08 <0.08 <0.08 0.673 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC04 ES2 0 0.7 0.263 0.101 <0.08 <0.08 <0.08 <0.08 0.346 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.246 0.081 <0.08 <0.08 <0.08 0.764 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC04 ES3 0 1.7 0.186 0.092 <0.08 <0.08 <0.08 <0.08 0.234 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.185 <0.08 <0.08 <0.08 <0.08 0.678 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC05 ES1 0 0 0.561 0.289 <0.08 <0.08 <0.08 <0.08 0.699 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.575 0.204 0.083 0.216 0.13 1.25 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.251 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC05 ES2 0 1.4 0.397 0.201 <0.08 <0.08 <0.08 <0.08 0.658 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.407 0.154 <0.08 0.15 0.093 0.998 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.15 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC05 ES3 0 2.8 0.122 <0.08 <0.08 <0.08 <0.08 <0.08 0.188 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.144 <0.08 <0.08 <0.08 <0.08 0.602 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC06 ES1 0 0 0.243 0.122 <0.08 <0.08 <0.08 <0.08 0.353 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.252 <0.08 0.081 0.084 <0.08 0.765 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC06 ES2 0 1.45 0.354 0.17 <0.08 <0.08 <0.08 <0.08 0.528 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.351 0.105 <0.08 0.12 <0.08 0.924 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
MAR00392.01 VC06 ES3 0 1 0.216 0.17 <0.08 <0.08 <0.08 <0.08 0.353 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 0.266 0.122 <0.08 0.11 <0.08 0.786 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
µg/kg
Explanatory Notes:
Results above Action Level 1 will be highlighted in blue and above Action Level 2 in red.
ICES7 is the sum of PCB 28,52,101,138,153,180 and 118.
Sample ID Dredge area
Type of
sample
Sample depth
(m)
PR Details
Average for the total dredge area:
Total Solids % 86.2
Gravel % 29.2
Sand % 36.1
Silt % 34.7
Arsenic (As) 4.5
Cadmium (Cd) 0.2
Chromium (Cr) 18
Copper (Cu) 21.3
Mercury (Hg) 0.04
Nickel (Ni) 16.8
Lead (Pb) 9.9
Zinc (Zn) 45.8
Dibutyltin (DBT) <0.001
Tributyltin (TBT) <0.001
Acenapth <1
Acenapthylene 1
Anthracn 1.33
BAA 2.36
BAP 3.18
BBF 3.83
BEP 3.12
Benzghip 3.61
BKF 1.93
C1N 2.4
C1PHEN 3.21
C2N 2.84
C3N 3.39
Chrysene 2.71
Debenzah 1.1
Flurant 3.75
Fluorene 1.04
Indypr 3.1
napth 1.29
perylene 1.49
phenant 2.91
Explanatory Notes:
The values entered for each determinand should be an average wet weight concentration from all the samples representing the material to be disposed to sea. They should be entered in the units
stated in the Unit of measurement column in the table below.
Results above Action Level 1 will be highlighted in blue and above Action Level 2 in red.
Total amount to be dredged (wet tonnes)
mg/kg
Sample ID
Unit of
measurement
pyrene 4.18
THC 5922
PCB28 0.23
PCB52 0.12
PCB101 <0.08
PCB118 <0.08
PCB138 <0.08
PCB153 <0.08
PCB18 0.33
PCB105 <0.08
PCB110 <0.08
PCB128 <0.08
PCB141 <0.08
PCB149 <0.08
PCB151 <0.08
PCB156 <0.08
PCB158 <0.08
PCB170 <0.08
PCB180 <0.08
PCB183 <0.08
PCB187 <0.08
PCB194 <0.08
PCB31 0.24
PCB44 0.09
PCB47 <0.08
PCB49 0.09
PCB66 0.08
ICES7 0.71
AHCH <0.1
BHCH <0.1
GHCH <0.1
DIELDRIN <0.1
HCB <0.1
DDE <0.1
DDT <0.1
TDE 0.1
BDE100 <0.1
BDE138 <0.1
BDE153 <0.1
BDE154 <0.1
BDE17 <0.1
BDE183 <0.1
BDE209 <0.1
BDE28 <0.1
BDE47 <0.1
BDE66 <0.1
BDE85 <0.1
BDE99 <0.1
µg/kg
Comments:
Laboratory Details
Laboratory 1 Details:
LabRefMat Q1
Yes
CompAnal Q2Yes
QAQC Q3
Yes
InterlabCaleb Q4
Yes
InternatCaleb Q5Yes
SpikedSamples Q6Yes
BlindSamples Q7Yes
Ranking Q8
Yes
FracAnal Q9 <63um(metals)
GranMeth Q10
OCMeth Q11
MetExtrType Q12
MethOfDetMetals Q13
PAHExtrType Q14
MethOfDetPAH Q15
OHExtrType Q16
MethOfDetOH Q17
Method of extraction used for poly aromatic hydrocarbon analysis
Method of detection used for poly aromatic hydrocarbons analysis
Method of extraction used for organohalogens inc PCBs, pesticides, flame retardants etc
analysis
Method of detection used for organohalogens inc PCBs, pesticides, flame retardants etc
analysis
Does the laboratory carrying out the analyses undertake periodic comparative analysis of
laboratory reference materials and certified reference materials?
PSA method
Organic Carbon method
Method of extraction used for metal analysis
Method of detection used for metal analysis
Does the laboratory carrying out the analyses undertake periodic participation in national and,
where possible, international laboratory proficiency schemes?
If the answer to questions 4 or 5 is 'Yes' then does the laboratory analyse samples of
substances which are provided by the organisers of the scheme?
If the answer to questions 4 or 5 is 'Yes' then does the laboratory confirm that the composition
of those samples is not disclosed in advance?
If the answer to questions 4 or 5 is 'Yes' then does the laboratory confirm that the results of the
scheme for each participating laboratory are made available to all participating laboratories?
Enter the size fraction that is analysed i.e. Whole or less than 63µm etc.
Explanatory Notes:
Please complete a separate worksheet for each laboratory (e.g. complete 'Laboartory_1' worksheet for 1 laboratory and complete
'Laboartory_2' worksheet for a second laboratory). If there are more than 3 laboratories then please contact MS-LOT.
SOCOTEC
2019
carbonate removal and sulfurous acid/combustion at 800°C/NDIR,
Aquaregia
NMBAQC
Laboratory name:
Year:
ICP-MS
Methanol/DCM solvent extraction with silica clean up and copper clean up stages
GCMS
Does the laboratory carrying out the analyses undertake the analysis of blank samples and
laboratory reference materials with each batch of samples of waste and other material dumped
in the maritime area that is analysed by that laboratory?
Does the laboratory carrying out the analyses undertake the compilation of quality control
charts based upon the data resulting from the analyses of the laboratory reference materials
and certified reference materials, and the use of those quality control charts to monitor
analytical performance in relation to all samples of dumped wastes or other materials?
Does the laboratory carrying out the analyses undertake periodic participation in
interlaboratory comparison exercises, including, where possible, international comparison
exercises?
Ultrasonic acetone/hexane solvent extraction
GCMSMS
OTExtrType Q18
MethOfDetOT Q19
LOD/LOQ Precision (%) Recovery (%)
Hg 0.01 4.2 93
As 0.5 2.7 99
Cd 0.04 3.6 103
Cu 0.5 2.9 105
Pb 0.5 3 98
Zn 2 2.6 102
Cr 0.5 3.1 95
Ni 0.5 3.6 98
TBT 0.001 12.62 96
DBT 0.001 12.62 113
PCB28 0.08 12.56 62
PCB31 0.08 5.3 101
PCB44 0.08 5.7 87
PCB47 0.08 5.7 96
PCB49 0.08 5.2 97
PCB52 0.08 6.999 90
PCB66 0.08 10.7 89
PCB101 0.08 8.43 93
PCB105 0.08 8.6 80
PCB110 0.08 5.2 101
PCB118 0.08 14.61 96
PCB128 0.08 7.6 76
PCB138+163 0.08 12.93 118
PCB141 0.08 7.6 101
PCB149 0.08 6.7 81
PCB151 0.08 7.6 103
PCB153 0.08 7.41 82
PCB156 0.08 8.4 91
PCB158 0.08 7.6 98
PCB170 0.08 6 82
PCB180 0.08 9.85 89
PCB183 0.08 6.2 75
PCB187 0.08 6.6 80
PCB194 0.08 6.5 70
DDE 0.1 8.2 81
DDT 0.1 10.6 100
DDD 0.1 11 113
Dieldrin 0.1 10.8 98
Lindane 0.1 8.5 97
HCB 0.1 2.8 128
BDE17BDE28BDE47BDE66BDE85BDE99
BDE100BDE138BDE153BDE154
Method of extraction used for organotin analysis
mg/kg
µg/kg
derivatisation and solvent extraction
GCMSMethod of detection used for organotin analysis
BDE183BDE209
ACENAPTH 1 6.68 67
ACENAPHY 1 7.74 102
ANTHRACN 1 4.95 70
BAA 1 9.8 71
BAP 1 9.07 61
BBF 1 8.44 87
BENZGHIP 1 13.46 71
BEP 1 7.9 88
BKF 1 8.9 88
C1N 1 8.27 78
C1PHEN 1 N/A 81
C2N 1 N/A 109
C3N 1 N/A 136
CHRYSENE 1 7.87 92
DBENZAH 1 19.23 101
FLUORENE 1 5.25 55
FLUORANT 1 4.36 81
INDPYR 1 17.1 75
NAPTH 1 3.02 62
PERYLENE 1 N/A 62
PHENANT 1 5.41 80
PYRENE 1 4.29 75
THC 100 N/A 107