Upload
mas4ever
View
224
Download
0
Embed Size (px)
Citation preview
8/13/2019 Chapter 5 Labour Management[1].pdf
1/33
1
LABOUR RESOURCEMANAGEMENTLABOUR RESOURCE
MANAGEMENT
8/13/2019 Chapter 5 Labour Management[1].pdf
2/33
2
ContentsContentsContents
IntroductionIntroduction
Problems Related toProblems Related to Labour Labour Planning ofPlanning of Labour Labour ResourceResource
Resource SmoothingResource SmoothingResourceResource LevellingLevelling
Monitoring & ControlMonitoring & ControlSummarySummary
8/13/2019 Chapter 5 Labour Management[1].pdf
3/33
3
IntroductionIntroductionLabour resource management is an importantaspect that require serious consideration during
project development .
It is made up of between 20-30% of totalconstruction cost.
To ensure the success of a project, one has to properly manage labour. Managing labour involved planning, organising, monitoring andcontrol.
8/13/2019 Chapter 5 Labour Management[1].pdf
4/33
4
IntroductionIntroduction
Improper labour resource management cancause problems during the construction stage.
These problems is highlighted in Figure 1:
8/13/2019 Chapter 5 Labour Management[1].pdf
5/33
5
Problems Related to LabourProblems Related to Labour
These are various problems related to labour that can hinder the progress of works at
construction site. The problems highlighted arenot limited to the Figure 1 only.
8/13/2019 Chapter 5 Labour Management[1].pdf
6/33
6
Problems Related to LabourProblems Related to Labour
Poor
Planning
SHORTAGESSLOW MOBILISATION
UNSKILLED LOBOUR INAPPROPRIATE
MONITORING & CONTROL
UNRELIABLE
SUB-CONTRACTOR
Poor W orkmanship
LowProductivity
Lack of Experience
Abse nte eism
Poor Access
Inappropriate
MonitoringSystem
StrikeLo w
Morale/Motivation
PROBLEMS RELATEDTO LOBOUR
Lack of Experience& Training
Lack of Supervisors
PoorTransportation
System
Lack of Experience
POOR SUPERVISION
NoCertification
Figure 1
8/13/2019 Chapter 5 Labour Management[1].pdf
7/33
7
Problems Related to LabourProblems Related to Labour
If there is problem, for example shortages oflabour, can results in work interruption hence itis critical to resolve the problem at an early
stage.Poor planning may be identified as acontributing factor that cause shortages.The other main factors can be improved andrectified but this can be very expensive.
8/13/2019 Chapter 5 Labour Management[1].pdf
8/33
8
Planning of Labour ResourcePlanning of Labour ResourceThe first step of avoiding and reducing the problemrelated to labour, as mentioned earlier, is a to planthe labour resource requirements.If the project planning was prepared based ontime driven, which is a common practice in theMalaysian Construction Industry, then the planner
have to estimate the labour requirement. But if it isa resource driven then the resources required has been planned to estimate the duration of a particular work.
8/13/2019 Chapter 5 Labour Management[1].pdf
9/33
9
Planning of Labour ResourcePlanning of Labour Resource
The are two types of labour resources planning,depending on the situation and requirement of project. These two type are as follow:
1) Resource Smoothing (Time - limited
resources)
2) Resource Levelling (Resource - limited)
8/13/2019 Chapter 5 Labour Management[1].pdf
10/33
10
Planning of Labour ResourcePlanning of Labour Resource
The resource smoothing applies to situationswhere contract time is fixed (limited) and no problems in the availability of resources.
While, resource levelling is a situation wherethere is a labour shortage and the client permitsdelay in completion date.The examples of both types of planning isexplained in the next section.
8/13/2019 Chapter 5 Labour Management[1].pdf
11/33
11
Labour Resources SmoothingLabour Resources Smoothing
This type of planning applies to conditionwhere there is no shortage of labour but theirallocation must be smooth to avoid sudden
reduction or addition in the number of labour.Ideally the resources aggregation shouldgradually in crease in numbers until it reachthe peak then gradually reduce the numbers.An example of the ideal planning is as shown
in Figure 2a.
8/13/2019 Chapter 5 Labour Management[1].pdf
12/33
12
Figure 2a Graph of Resources Organisation
Time
No. of Labour
Preferred Avoid
Figure 2b Graph of Resources Aggregation
Peak Trough
Time
No. of Labour
8/13/2019 Chapter 5 Labour Management[1].pdf
13/33
13
In planning the labour allocation, the preferredresources allocation as shown in Graph 2a.One must avoid planning the resources
allocation as indicated in Graph 2b. Wherethere trough and peak aggregation of labour indicated that it can Influence the morale ormotivation of construction workers.
This is due to the discontinuity or employment
of workers.
8/13/2019 Chapter 5 Labour Management[1].pdf
14/33
14
Which also led to high labour turnover.Besides morale and motivation, productivitywill also be effected.
In the planning for labour resource smoothingtechnique the following condition applies:
Project duration is fixed In available to meet the completion dateResources in less important in comparison totime.
8/13/2019 Chapter 5 Labour Management[1].pdf
15/33
15
Steps taken in using smoothing techniqueswere as follows:List all activities according to Earliest Start -Total Float (ES-TF) and Latest Start - TotalFloat (LS-TF)Draw resource aggregation graph (chart)
according to ES-TF and LS-TF Compare both graphs and try to develop a
preferred graph ie without trough
8/13/2019 Chapter 5 Labour Management[1].pdf
16/33
16
ExampleExample
Figure 3 shows the network of a small projectand Table 1 shows the labour requirementsTable 1 - Labour Requirements
Activity No. of Labour Activity No. of Labour 1 - 2 3 3 - 7 52 - 3 4 4 - 7 42 - 4 4 5 - 6 42 - 5 3 6 - 7 6
7 - 8 3
8/13/2019 Chapter 5 Labour Management[1].pdf
17/33
17
1
5 53
3
2
5 6
3
6 2
5 3
14
0 17 20
0 58
11
14
13 16
4 7 8
17 2011
13 16
0 Earliest Start (ES)
0 Latest Start (LS)
Critical Activity
Figure 3
1
8/13/2019 Chapter 5 Labour Management[1].pdf
18/33
18
Act ivi ty TF ES LS TOTAL LABOUR
1, 2 0 0 0 3
2, 3 3 5 8 4
2, 4 4 5 9 4
2, 5 0 5 5 3
3, 7 4 11 15 5
4, 7 3 11 14 4
5, 6 0 13 13 4
6, 7 0 16 16 6
7, 8 0 17 17 3
8/13/2019 Chapter 5 Labour Management[1].pdf
19/33
19
List according to priority ES - TF
Act ivi ty ES TF
1, 2 0 0
2, 5 5 0
2, 3 5 3
2, 4 5 4
4, 7 11 3
3, 7 11 4
5, 6 13 0
6, 7 16 0
7, 8 17 0
8/13/2019 Chapter 5 Labour Management[1].pdf
20/33
20
Plot the resource graph according to priority (ES TF)
Total Labour
14
12
10
8
6
4
2
2 4 6 8 10 12 14 16 18 20 22
Time(Days)1 2 2 5
2 4
2 3
3 7
4 7
5 6
6 -7
7 8
4 -
7
8/13/2019 Chapter 5 Labour Management[1].pdf
21/33
21
List according to priority LS - TF
Act ivi ty LS TF
1, 2 0 0
2, 5 5 0
2, 3 8 3
2, 4 9 4
5,6 13 0
4, 7 14 3
3,7 15 4
6, 7 16 0
7, 8 17 0
8/13/2019 Chapter 5 Labour Management[1].pdf
22/33
22
Plot the resource graph according to priority (LS TF)
Total Labour
14
12
10
8
6
4
2
2 4 6 8 10 12 14 16 18 20 22
Time(Days)1 2 2 5
2 4
2 3
5 6
6 -7
7 8
2
3 4 7
4 7
3 7
3 7
10
15
2 4
8/13/2019 Chapter 5 Labour Management[1].pdf
23/33
23
Compare both graphs and prepare a new preferred graph (smooth)
Total Labour
14
12
10
8
6
4
2
2 4 6 8 10 12 14 16 18 20 22
Time(Days)1 2 2 5
2 4
2 3
5 6
6 -7
7 8
3
7
4 7
8/13/2019 Chapter 5 Labour Management[1].pdf
24/33
24
Resources LevellingResources Levelling
There are several conditions that force a plannerto adopt this technique among the conditionincludes:Shortage of labour thus the labour is limited
Activities are planned according to theavailability of labour The completion date can be delayed if activitiescannot be arranged within the float timeDuration of project is less important as
compared to resources requirements
8/13/2019 Chapter 5 Labour Management[1].pdf
25/33
25
Resources LevellingResources Levelling
The steps taken in using levelling techniquewere as follows:
i) List all activities according to priority EarlyStart - Total Float (ES-TF) . If there is 2 ormore activities of the same TF Then durationof activity to be considered
ii) Draw the resource aggregation according to
the list of priority (ES-TF) and limit the labour requirementiii)Completion date of project will depend on the
availability of the resources.
8/13/2019 Chapter 5 Labour Management[1].pdf
26/33
26
ExampleExample
Figure 4 shows the network of a small project and Table 2 shows the labour requirements for each activity. Gang A islimited to 8 workers and Gang B is limited to6 workers.
Prepare resource allocation graph based on
ES-TF . List the date of all activities based onresource graph.
8/13/2019 Chapter 5 Labour Management[1].pdf
27/33
27
ExampleExample
Table 2 Activity Duration
(Days)Gang A
(Number)Gang B
(Number) A 7 6 -B 8 8 5
C 9 4 5D 10 6 -E 7 - 5F 12 4 -
G 9 - 6H 6 - 6I 6 6 -J 5 5 -
K 4 - 5
8/13/2019 Chapter 5 Labour Management[1].pdf
28/33
28
7
7
B
8
15
15
7
8
E
7
14
15
0
0
A
7
7
7
15
15
F
12
27
27
15
15
C
9
24
26
27
15
G
9
36
36
24
26
D
12
27
27
15
15
F
12
27
27
15
15
F
12
27
27
15
15
F
12
27
27
15
15
F
12
27
27
Figure 4 :
8/13/2019 Chapter 5 Labour Management[1].pdf
29/33
29
Activity MT1 JA
A 0 0B 7 0C 7 1D 15 0E 15 2F 24 2G 27 0H 36 0I 42 0J 42 1K 48 0
List According to Priority
8/13/2019 Chapter 5 Labour Management[1].pdf
30/33
30
Days
No. of Labour
2
4
6
8
10 20 30 40 50 60
1-2 A
2-6B
10-11I
10-12J
4-6C
5-7
F
6-8D
8/13/2019 Chapter 5 Labour Management[1].pdf
31/33
31
Days
2
4
6
8
10 20 30 40 50 60
4-6C
7-9G
12-13K
X
3-5E
9-10H
No. of Labour
2-4B
8/13/2019 Chapter 5 Labour Management[1].pdf
32/33
32
Activity MT1 JA
A 0 0B 7 0C 15 2D 24 2E 7 1F 5 0G 27 0H 36 0I 2 0J 42 1K 48 0
Solution
8/13/2019 Chapter 5 Labour Management[1].pdf
33/33
33