Chapter 5 Labour Management[1].pdf

Embed Size (px)

Citation preview

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    1/33

    1

    LABOUR RESOURCEMANAGEMENTLABOUR RESOURCE

    MANAGEMENT

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    2/33

    2

    ContentsContentsContents

    IntroductionIntroduction

    Problems Related toProblems Related to Labour Labour Planning ofPlanning of Labour Labour ResourceResource

    Resource SmoothingResource SmoothingResourceResource LevellingLevelling

    Monitoring & ControlMonitoring & ControlSummarySummary

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    3/33

    3

    IntroductionIntroductionLabour resource management is an importantaspect that require serious consideration during

    project development .

    It is made up of between 20-30% of totalconstruction cost.

    To ensure the success of a project, one has to properly manage labour. Managing labour involved planning, organising, monitoring andcontrol.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    4/33

    4

    IntroductionIntroduction

    Improper labour resource management cancause problems during the construction stage.

    These problems is highlighted in Figure 1:

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    5/33

    5

    Problems Related to LabourProblems Related to Labour

    These are various problems related to labour that can hinder the progress of works at

    construction site. The problems highlighted arenot limited to the Figure 1 only.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    6/33

    6

    Problems Related to LabourProblems Related to Labour

    Poor

    Planning

    SHORTAGESSLOW MOBILISATION

    UNSKILLED LOBOUR INAPPROPRIATE

    MONITORING & CONTROL

    UNRELIABLE

    SUB-CONTRACTOR

    Poor W orkmanship

    LowProductivity

    Lack of Experience

    Abse nte eism

    Poor Access

    Inappropriate

    MonitoringSystem

    StrikeLo w

    Morale/Motivation

    PROBLEMS RELATEDTO LOBOUR

    Lack of Experience& Training

    Lack of Supervisors

    PoorTransportation

    System

    Lack of Experience

    POOR SUPERVISION

    NoCertification

    Figure 1

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    7/33

    7

    Problems Related to LabourProblems Related to Labour

    If there is problem, for example shortages oflabour, can results in work interruption hence itis critical to resolve the problem at an early

    stage.Poor planning may be identified as acontributing factor that cause shortages.The other main factors can be improved andrectified but this can be very expensive.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    8/33

    8

    Planning of Labour ResourcePlanning of Labour ResourceThe first step of avoiding and reducing the problemrelated to labour, as mentioned earlier, is a to planthe labour resource requirements.If the project planning was prepared based ontime driven, which is a common practice in theMalaysian Construction Industry, then the planner

    have to estimate the labour requirement. But if it isa resource driven then the resources required has been planned to estimate the duration of a particular work.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    9/33

    9

    Planning of Labour ResourcePlanning of Labour Resource

    The are two types of labour resources planning,depending on the situation and requirement of project. These two type are as follow:

    1) Resource Smoothing (Time - limited

    resources)

    2) Resource Levelling (Resource - limited)

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    10/33

    10

    Planning of Labour ResourcePlanning of Labour Resource

    The resource smoothing applies to situationswhere contract time is fixed (limited) and no problems in the availability of resources.

    While, resource levelling is a situation wherethere is a labour shortage and the client permitsdelay in completion date.The examples of both types of planning isexplained in the next section.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    11/33

    11

    Labour Resources SmoothingLabour Resources Smoothing

    This type of planning applies to conditionwhere there is no shortage of labour but theirallocation must be smooth to avoid sudden

    reduction or addition in the number of labour.Ideally the resources aggregation shouldgradually in crease in numbers until it reachthe peak then gradually reduce the numbers.An example of the ideal planning is as shown

    in Figure 2a.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    12/33

    12

    Figure 2a Graph of Resources Organisation

    Time

    No. of Labour

    Preferred Avoid

    Figure 2b Graph of Resources Aggregation

    Peak Trough

    Time

    No. of Labour

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    13/33

    13

    In planning the labour allocation, the preferredresources allocation as shown in Graph 2a.One must avoid planning the resources

    allocation as indicated in Graph 2b. Wherethere trough and peak aggregation of labour indicated that it can Influence the morale ormotivation of construction workers.

    This is due to the discontinuity or employment

    of workers.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    14/33

    14

    Which also led to high labour turnover.Besides morale and motivation, productivitywill also be effected.

    In the planning for labour resource smoothingtechnique the following condition applies:

    Project duration is fixed In available to meet the completion dateResources in less important in comparison totime.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    15/33

    15

    Steps taken in using smoothing techniqueswere as follows:List all activities according to Earliest Start -Total Float (ES-TF) and Latest Start - TotalFloat (LS-TF)Draw resource aggregation graph (chart)

    according to ES-TF and LS-TF Compare both graphs and try to develop a

    preferred graph ie without trough

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    16/33

    16

    ExampleExample

    Figure 3 shows the network of a small projectand Table 1 shows the labour requirementsTable 1 - Labour Requirements

    Activity No. of Labour Activity No. of Labour 1 - 2 3 3 - 7 52 - 3 4 4 - 7 42 - 4 4 5 - 6 42 - 5 3 6 - 7 6

    7 - 8 3

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    17/33

    17

    1

    5 53

    3

    2

    5 6

    3

    6 2

    5 3

    14

    0 17 20

    0 58

    11

    14

    13 16

    4 7 8

    17 2011

    13 16

    0 Earliest Start (ES)

    0 Latest Start (LS)

    Critical Activity

    Figure 3

    1

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    18/33

    18

    Act ivi ty TF ES LS TOTAL LABOUR

    1, 2 0 0 0 3

    2, 3 3 5 8 4

    2, 4 4 5 9 4

    2, 5 0 5 5 3

    3, 7 4 11 15 5

    4, 7 3 11 14 4

    5, 6 0 13 13 4

    6, 7 0 16 16 6

    7, 8 0 17 17 3

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    19/33

    19

    List according to priority ES - TF

    Act ivi ty ES TF

    1, 2 0 0

    2, 5 5 0

    2, 3 5 3

    2, 4 5 4

    4, 7 11 3

    3, 7 11 4

    5, 6 13 0

    6, 7 16 0

    7, 8 17 0

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    20/33

    20

    Plot the resource graph according to priority (ES TF)

    Total Labour

    14

    12

    10

    8

    6

    4

    2

    2 4 6 8 10 12 14 16 18 20 22

    Time(Days)1 2 2 5

    2 4

    2 3

    3 7

    4 7

    5 6

    6 -7

    7 8

    4 -

    7

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    21/33

    21

    List according to priority LS - TF

    Act ivi ty LS TF

    1, 2 0 0

    2, 5 5 0

    2, 3 8 3

    2, 4 9 4

    5,6 13 0

    4, 7 14 3

    3,7 15 4

    6, 7 16 0

    7, 8 17 0

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    22/33

    22

    Plot the resource graph according to priority (LS TF)

    Total Labour

    14

    12

    10

    8

    6

    4

    2

    2 4 6 8 10 12 14 16 18 20 22

    Time(Days)1 2 2 5

    2 4

    2 3

    5 6

    6 -7

    7 8

    2

    3 4 7

    4 7

    3 7

    3 7

    10

    15

    2 4

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    23/33

    23

    Compare both graphs and prepare a new preferred graph (smooth)

    Total Labour

    14

    12

    10

    8

    6

    4

    2

    2 4 6 8 10 12 14 16 18 20 22

    Time(Days)1 2 2 5

    2 4

    2 3

    5 6

    6 -7

    7 8

    3

    7

    4 7

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    24/33

    24

    Resources LevellingResources Levelling

    There are several conditions that force a plannerto adopt this technique among the conditionincludes:Shortage of labour thus the labour is limited

    Activities are planned according to theavailability of labour The completion date can be delayed if activitiescannot be arranged within the float timeDuration of project is less important as

    compared to resources requirements

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    25/33

    25

    Resources LevellingResources Levelling

    The steps taken in using levelling techniquewere as follows:

    i) List all activities according to priority EarlyStart - Total Float (ES-TF) . If there is 2 ormore activities of the same TF Then durationof activity to be considered

    ii) Draw the resource aggregation according to

    the list of priority (ES-TF) and limit the labour requirementiii)Completion date of project will depend on the

    availability of the resources.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    26/33

    26

    ExampleExample

    Figure 4 shows the network of a small project and Table 2 shows the labour requirements for each activity. Gang A islimited to 8 workers and Gang B is limited to6 workers.

    Prepare resource allocation graph based on

    ES-TF . List the date of all activities based onresource graph.

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    27/33

    27

    ExampleExample

    Table 2 Activity Duration

    (Days)Gang A

    (Number)Gang B

    (Number) A 7 6 -B 8 8 5

    C 9 4 5D 10 6 -E 7 - 5F 12 4 -

    G 9 - 6H 6 - 6I 6 6 -J 5 5 -

    K 4 - 5

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    28/33

    28

    7

    7

    B

    8

    15

    15

    7

    8

    E

    7

    14

    15

    0

    0

    A

    7

    7

    7

    15

    15

    F

    12

    27

    27

    15

    15

    C

    9

    24

    26

    27

    15

    G

    9

    36

    36

    24

    26

    D

    12

    27

    27

    15

    15

    F

    12

    27

    27

    15

    15

    F

    12

    27

    27

    15

    15

    F

    12

    27

    27

    15

    15

    F

    12

    27

    27

    Figure 4 :

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    29/33

    29

    Activity MT1 JA

    A 0 0B 7 0C 7 1D 15 0E 15 2F 24 2G 27 0H 36 0I 42 0J 42 1K 48 0

    List According to Priority

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    30/33

    30

    Days

    No. of Labour

    2

    4

    6

    8

    10 20 30 40 50 60

    1-2 A

    2-6B

    10-11I

    10-12J

    4-6C

    5-7

    F

    6-8D

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    31/33

    31

    Days

    2

    4

    6

    8

    10 20 30 40 50 60

    4-6C

    7-9G

    12-13K

    X

    3-5E

    9-10H

    No. of Labour

    2-4B

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    32/33

    32

    Activity MT1 JA

    A 0 0B 7 0C 15 2D 24 2E 7 1F 5 0G 27 0H 36 0I 2 0J 42 1K 48 0

    Solution

  • 8/13/2019 Chapter 5 Labour Management[1].pdf

    33/33

    33