CESC Budge Budge VT Report

Embed Size (px)

Citation preview

  • Calcutta Electricity State Cooperation Limited

    (CESC Ltd)

    Budge Budge Generating Station

    Name SARTHAK MODAK

    Address 88, LENIN SARANI, KANCHRAPARA, NORTH

    24 PARGANAS

    Pin code - 743145

    College SAROJ MOHAN INSTITUTE OF TECHNOLOGY,

    U GUPTIPARA, HOOGLY

    Pin code - 712512

    Duration of Training From 24thdec 2012

    To 5th

    jan 2013

  • ACKNOWLEDGEMENT

    This Acknowledgement is not a formality but a way to show my deep sense of gratitude to

    all the people of BBGS for their inspiration & guidance during the training period whose co-

    operation and suggestions helped me a lot to complete this project.

    Firstly I would like to thank the following people for giving the opportunity to do the

    training:

    Mr. A. Saha (GENERAL MANAGER, BBGS)

    Mr. S. Dutta (DY. GENERAL MANAGER, BBGS)

    Mr. D. Maitra (DY. GENERAL MANAGER, HR)

    Mr. S. Roy (DY.GENERAL MANAGER,BBGS)

    I am also highly indebted to the following people under whose guidance I

    successfully completed my training in various departments of BBGS:

    Mr. Arijit Ghosh (SR. MANAGER, PLG)

    Mr. Subrata Mondal (DY. MANAGER, F&A)

    Mr. Santashri Ghosh (MANAGER, E&I)

    Mr. Kaushik Chaudhuri (MANAGER, OPS)

    Mr. Samir Bandyopadhyay (MANAGER, MMD)

    I am also extremely thankful to the following people whose constant support,

    encouragement & guidance helped me to do the training and understand the

    essence of a power-generation plant:

    Mr. S.P. Bhattacharya (CONSULTANT HR)

    Mr. S. Roy (ASST. ENGINEER, HRD)

    Last but not the least, I would like to sho my gratitude to all the labours, workers & various other employees of BBGS who have cordially helped me to understand

    the various technical aspects of the power-plant at different instants throughout

    the training period

  • SIGNATURES OF OFFICERS OF VARIOUS

    DEPARTMENTS

    DEPT: OPERATION

    NAME:- SIGNATURE:-

    _______________

    DEPT: F&A

    NAME:- SIGNATURE:- ________________

    DEPT: MMD

    NAME:- SIGNATURE:-

    ________________

    DEPT:- E&I

    NAME:- SIGNATURE:-

    ________________

    DEPT:-PLC

    NAME:- SIGNATURE:- _________________

    MARKS OBTAINED IN WRITTEN TEST:-

    ____

    ATTENDANCE:- _____

    DEPT:-PTC

    NAME:- SIGNATURE:- ______________

  • The Calcutta Electric Supply Corporation or CESC is an Indian electricity generating

    company serving the area administered by the Kolkata municipal corporation, in

    addition to the city of Kolkata, it also serves parts of the Howrah, Hooghly, 24 Parganas

    (North) and 24 Parganas (South) districts of West Bengal.

    On 7 January 1897 Kilburn & Co. secured the Calcutta (Now Kolkata) electric lighting

    license as agents of The Indian Electric Company Limited. The company soon changed

    its name to the Calcutta Electric Supply Corporation Limited. The first power

    generating station was begun on April 17, 1899 near the Princep Ghat. The Calcutta

    Tramways Company switched to electricity from horse drawn carriages in 1902. Three

    new power generating stations were started by 1906. The company was shifted to

    the Victoria House in Dharmatala in 1933, and still operates from this address.

    Load-shedding (interruption of power supply due to shortage of electricity) was

    common in Kolkata during 1970s and 1980s. In 1978 the company was christened as

    The Calcutta Electric Supply Corporation (India) Limited. The RPG Group was associated

    with The Calcutta Electric Supply Corporation (India) Limited from 1989, and the name

    was changed from The Calcutta Electric Supply Corporation (India) Limited to CESC

    Limited.

    Recently the Calcutta power grid has seen progressively better performance and fewer

    outages. In the power sector, CESC, currently having a generating capacity of 1225 MW,

    has major plans to expand generating capacity to 7000 MW over the next five or six

    years. The new power generating projects thermal, hydal and solarwill involve investments of more than ` 30,000 crore. Presently CESC Ltd is the flagship company

    of RP-SANJIV GOENKA GROUP.

    Generation and Distribution of Electricity since 1897

    First Thermal Power Generation Company in India

    Initial Licensed Area 14.44 sq. km

    Brought Electricity to Kolkata 10 years after it came to London

    Tunnel under Ganga for power transmission

    In 1989, CESC became a part of RPG Group

    In 2011, CESC became a part of RP-Sanjiv Goenka Group

    Salient features:

    No. of Consumers: 2.5 million

    No. of Employees: 10000

    Generation Capacity: 1225 MW

  • Substation Capacity: 7483 MVA

    Transmission and Distribution Network: 18449 ckt. KM

    Power Generation in the year 2010-11: 8756 MU

    Power export in the year 2010-11: 146 MU

    Power Import in the year 2010-11: 1523 MU

    Total Revenue in the year 2010-11: 4092 crores

    Profit after tax in the year 2010-11: 488 crores

    Generating station features:

    New Cossipore(NCGS):

    Commissioned: 1949

    Capacity: 100 MW (derated)

    Feature of boiler: Stoker fired

    Titagarh(TGS):

    Commissioned: 1983

    Capacity: 240 MW

    Feature of boiler: P.F.

    Southern(SGS):

    Commissioned: 1991

    Capacity: 135 MW

    Feature of boiler: P.F.

    Budge Budge(BBGS):

    Commissioned: 1997

    Capacity: 750 MW

    Feature of boiler: P.F.

  • PROJECT PROFILE

    Capacity 750 MW (3 x 250 MW)

    Location PUJALI, BUDGE BUDGE, 24 PGS(S), WEST

    BENGAL

    COMMERCIAL GENERATION

    Unit # 1 07.10.97

    Unit # 2 01.07.99

    Unit # 2 28.01.10

    Fuel source ECL, BCCL, ICML & Imported Coals

    Fuel requirement 2.45 million tons of coal per annum

    Mode of transportation Rail

    Water source River Hooghly

    Land area 225 acres

    Ash dumping area 91 acres

    UNIQUE FEATURES

    Largest coal fired thermal power station of CESC Ltd

    Use of clarified water for condenser and other auxiliaries

    Vertical Down-Shot fired boilers having Non Turbulent, Low NOx

    Burners

    Use of gas re-circulation in boiler

    Use of Hydrogen Cooling and Stator Water Cooling for Generator (first in

    CESC)

    Use of Cooling Towers for Closed Circulating Water System (first in CESC)

    Use of Zero Discharge System for Bottom Ash Disposal

    Incorporation of Zero Effluent System

    Installation and Operation of a High Concentration Slurry System (HCSS)

  • BUDGE BUDGE GENERATING STATION

    No of units

    3

    Capacity

    250 MW

    Unit # 1

    Trial Synchronization

    16.9.97

    Commercial generation

    07.10.97

    Full Load Generation

    26.02.98

    Unit # 2

    Trial Synchronization

    06.03.99

    Commercial generation

    01.07.99

    Full Load Generation

    09.08.99

    Unit # 3

    Trial Synchronization

    12.07.09

    Commercial generation

    28.01.10

    Full Load Generation

    29.09.09

  • POWER GENERATION CYCLE

    Heat for the power cycle of CESC, Budge Budge Generating Station Unit No. 1 & 2 is

    derived from burning pulverized coal in a Natural Circulation, Balanced Draft, Two

    Pass, Down-Shot Fired, Single Reheat Drum Type Boiler and Unit 3 is Natural

    Circulation, Balanced Draft, Two Pass, Corner Fired, Single Reheat Drum Type Boiler.

    However, during Light-up LDO is used for support & stabilization. For unit 1 & 2 each

    unit has a 250 MW Rolls-Parsons turbo-generator, an Acc-Babcock make P.F boiler and

    unit 3 has 250 MW BHEL make turbo-generator & P.F boiler with a maximum continuous

    rating of 805T/hr of steam, and all auxiliary systems and equipment to make a

    complete generating unit.

    Each boiler has been provided with two forced draft fans (F.D), three induced draft fans

    (I.D) for unit 1&2 & two induced draft fans (I.D) for unit 3, two primary air fans (P.A),

    one primary tubular air heater, two secondary tubular air heaters for unit 1 & 2 and

    two rotary air heater for unit 3, six Ball & Race type pulverizes, six Volumetric coal

    feeders for unit 1 & 2 and five Bowl type pulverizes, five Gravimetric coal feeders for

    unit 3, etc. Soot blowing is done by steam. Main and reheat steam temperature is

    maintained from full load to 60% load. The boiler is capable of sustained stable

    operation down to 2 Mills at 30% capacity without oil support for flame stabilization.

    25% BMCR requirement can be achieved by burning LDO alone.

    The main turbine is a Tandem Compounded, Three Cylinder, Single Reheat, Double

    Flow LP cylinder, Condensing Type with uncontrolled Extraction.

    In the power plant there are nine cycles which makes the whole power plant work.

    They are:-

    1) Coal Cycle

    2) Steam Cycle

    3) Reheat, Regenerative Cycle/ Turbine cycle

    4) Electricity Cycle

    5) Light diesel oil (LDO) Cycle

    6) Ash cycle

    7) Feed water Cycle

    8) Air Cycle

    9) Condenser Cooling Water Cycle

    There are many departments in the Budge Budge Generating Station. They are:-

    1) Fuel & Ash department

    2) Planning & Environment department

    3) Mechanical Maintenance department

    4) Operations department

    5) Electrical & instrumental department

    6) Plant training center

  • FUEL AND ASH DEPARTMENT

    The primary fuel for these units is bituminous coal supplied from coal mines. The coal

    handling plant has been designed for 960 MTH coal of (-) 300 mm size which is

    generally received at the site from the mines. Coal is unloaded in the yard either by

    Roadside wagon tipplers or in the track hopper through bottom discharge wagons. The

    coal is crushed in two stages before it is fed into the boiler bunkers. In the first stage it

    is crushed to (-) 100 mm size by primary crushers and finally to (-) 20 mm by

    secondary crushers. 2 x 100% parallel chains of conveyors are provided to convey coal

    from the coal yard to boiler bunkers.

    The FUEL AND ASH DEPARTMENT can be broadly divided into two plants:-

    1) Coal handling plant

    2) Ash handling plant

    COAL HANDLING PLANT

    Capacity:-

    Design 960 T/Hr

    Rated 800 T/Hr

    No Of Wagon Tippler 2

    No Of Track Hopper 1

    Capacity 1500 MT

    Primary Crusher

    Quantity 2 Nos.

    Type Rotary Breaker

    Secondary Crusher

    Quantity 2 Nos.

    Type Ring Granulator

  • Each day he amount of coal required is about 10500T/day when the power plant is

    working a 100% load for 24 hours. The coal comes from ECL, BCCL, ICML, & Imported

    coal from Indonesia. Coal having ash contain less than 30% is used in power plant. The

    coal coming from Indonesia has a ash contain less than 5%.

    The coal comes via railway in BOBR & BOX(N) wagons. The BOBR wagons go into the

    track hopper and the coal fall into 1A and 1B conveyer belt through a 300 sq mm net

    while BOX(N) wagons unload into the wagon tripper which falls into the 1C & 1D

    conveyer belt. Then they pass through two electromagnetic separators and fall into the

    reversible belt feeder (RBF4A & RBF4B) and fall into the conveyer belt 2A & 2B. it leads

    to the primary crusher house which granulates the coal to size lesser than 100 sq mm

    it also separates the stone and coal. The stones go into the reject bin and the

    granulated coal goes into a reversible belt feeder (RBF1A & RBF1B) which leads the coal

    either to the coal stack yard or to the secondary crusher house.

    The coal goes to the coal stack yard via the conveyer belt 8A & 8B then 10A & 10B then

    to the Stacker-Cum-Reclaimer which stacks the coal in the coal yard. When it is needed

    to reclaim the coal then the bucket wheel reclaimer reclaims the coal and sends it

    through the conveyer belts 11A & 11B then to 12A & 12B then through flap gates to

    conveyer belts 3A & 3B which goes into the secondary crusher house.

    Stacker-Cum-Reclaimer

    Type Slewing And Boom Stacker With Bucket Wheel

    Reclaimer, Rail Mounted, Suitable For

    Reversible Yard Conveyor.

    Nos. 2

    Total Travel (M) 308 M

    Lump Size (-)100 Mm

    Height Of Pile (M) 10.5

    Type of Material

    Handled-

    Material Semi Crushed Coal

    Lump size (-)100 mm

  • The secondary crusher house is a ring granular that granulates the coal to a size less

    than 20 mm sq. From there the coal in conveyed through 4A & 4B to the bunkers. Unit 1

    & unit 2 consists 6 bunkers each while unit 3 consists 5 bunkers. From there it goes

    into the coal mill. There are six Ball & Race type pulverizes, six Volumetric coal feeders

    for unit 1 & 2 and five Bowl type pulverizes, five Gravimetric coal feeders for unit 3.

    The other part of this department is the ash handling plant.

    ASH HANDLING SYSTEM

    Fly Ash Handling System

    Fly Ash Evacuation Rate 80 Mt/Hr

    Capacities of Tank / Vessel

    Air Heater 57 Litres

    ESP 1 & 2 485 Litres

    ESP 3 145 Litres

    ESP 4 To 7 85 Litres

    Bottom Ash System

    Bottom Ash Cleaning Rate 60 MT/Hr

    Effective Storage Capacity

    Bottom Ash Hopper 150 MT (Approx)

    De Watering Bin 432 MT (Approx)

    Settling Tank 1240 CUM (Approx)

    Surge Tank 1670 CUM (Approx)

    Overflow Transfer Tank 21 CUM (Approx)

    Decant Water Transfer Tank 35 CUM (Approx)

  • The complete ash handling system is divided as Bottom Ash Removal system and Fly

    Ash Removal system. The Fly Ash Removal system is continuous, whereas Bottom Ash

    Removal system is intermittent and carried out once per shift

    Bottom Ash Removal system is a wet system. The bottom ash of each unit is crushed by

    a convergent nozzle which is used to achieve high speed and hydraulically conveyed in

    the form of slurry by divergent nozzle which is used to increase the pressure of the

    water from bottom ash hopper to Dewatering bins/Ash tanks. Decanted water

    separated from the bins is further re-circulated by sending the water and ash mixture

    into the settling tank, where the ash settles down and clear water is taken out of it and

    moved into the surge the surge tank and then again the water is taken to clear the

    slurry. Collected bottom ash at the bins is removed by trucks. This method is called

    Zero discharge system.

    Fly ash collected in ESP & Air heater hoppers is removed in dry form by dense phase

    pneumatic conveying system in two stages. In the first stage, the flue gas enters the

    ESP which consists of both negative & positive plates which are charged with 75Kv DC

    supply. The dust from the flue gases get negatively charged and attaches with the

    positively charged plates which are then removed by hammer, and collected in the

    hopper. Fly ash collected in above hoppers is pneumatically conveyed with

    compressed conveying air called Makeover system to Intermediate Surge Hoppers. In

    the second stage, the dry fly ash is further conveyed from Intermediate Surge Hoppers

    to Fly Ash Silos or river side Burge to export as to Bangladesh cement industry by P.D

    pumps. Ash collected in Fly Ash Silos is removed by trucks through rotary unloader. A

    High concentration slurry system (HCSS) has been incorporated at BBGS with

    technology from Netherlands to handle the fly ash in the form of thick slurry which

    has a viscosity thinner than toothpaste and thicker than glue is produced using special

    pumps and transport the same to a distant location. This ash settles in the form of

    mounds over which suitably identified plantation will take place to convert the entire

    place into a environment friendly greenery zone. Provision has been made to unload

    the ash from Intermediate Surge Hoppers to trucks through unloading system in case

    of emergency.

    A majority of the fly ash is at present exported to Bangladesh though barges for use in

    their cement plants.

  • PLANNING & ENVIRONMENT DEPARTMENT

    The planning department of BBGS CESC Ltd. Is the department which controls every

    aspect of the progress of the company and supervises on the work of every department

    .This kind of management is maintained by the data which is provided by the

    respective departments .It not only monitors the progress of the company but also to

    the details of every person of the company including employees and workers. Routine

    maintenance , breakdown maintenance, and predictive maintenance are also being

    supervised by this department.

    Economics of this company is taken care by this dept. environment, emergency plan ,

    health and safety as well as computer defect, training ,infrastructure request, ac

    defect ,and phone numbers of officers are being supervised by this department.

    A generating station is combination of huge mechanical devices. The criteria of

    whether the machine is damaged or not is being set by this dept. for example to test

    the bearing of a turbine the frequency of it must be within 8db if its freq. is more than

    8 db then the bearing is in degrading condition .If it is above 12 db then the bearing

    must be changed.

    The whole of this management system is done by an oracle based software. The page

    by which the whole system is managed is shown below.

    FOR ALL EXECUTIVES UPTO SR.DEPUTY MANAGER

    Logs

    &reports

    Performance Administratio

    n

    Financ

    e

    EHS For you Miscellaneou

    s

    Station

    reports

    Performance

    monitoring

    Supervisor

    Dbl/Due off

    Orders

    &bills

    OH&S menu About

    you

    Messages

    Coal reports Maintenance

    planning

    Workman OT OLMM

    reports

    Emergency

    plan

    Leave

    reports

    Infrastructur

    e Request

    Ash reports MTBF entry Workmen

    gatepass entry

    SERC

    reports

    NCR

    register

    Transpor

    t

    &medical

    Training

    Department

    al logs

    Survey defect

    management

    Attendance

    report

    Budget

    reports

    Environme

    nt

    Puja

    advance

    Chummery

    management

    Weighbridge

    data

    Mill

    performance

    Hol-call Entry ERP

    reports

    Standard

    formats

    Officers

    phone no.

    Drawing&

    Documentatio

    n

    Shift rota Petty

    cash

    Notice

    board

    Blood group

    Energy

    monitoring

    Computer

    defect

    AC m/c

    defect

  • The planning department of BBGS not only manages other departments and economy .it also

    manages the details of the executives of its own dept. which includes officers transport,

    strength, record, birthday, leave repots, leave summery ,BBGS gatepasses , Hol call allowance,

    along with the computers in the wholw unit of BBGS. such details are being recorded by the

    following table.

    FOR EXECUTIVES OF PLANNING ( UPTO SR. DEPUTY MANAGER ) ONLY

    Each and every department starting from coal unloading to generation of electricity has its own

    monthly and yearly targets. This target is set by the planning department in BBGS and the end

    of the respective month or year its is seen that the target is being achieved or not and the

    required regulation is taken according to it. This determination is very valuable because it is

    important to determine the position of the power plant among the others in India .

    Apart from this planning department also makes a record of unit trips , leaks of tube , heat rate

    , total generation loss , and environment related failures

    Examples of such spreadsheets are respectively given:-

    Parameters Daily

    actual

    MTD YTD Yearl

    y

    target

    MTD

    actual

    YTD

    actual Target Actual Target actual

    Generation

    (MU)

    STN 11.20 434.9

    5

    419.4

    3

    4664.9

    5

    4612.5

    6

    5995 439.33 4553.

    07

    PLF % STN 62.23 86.30 83.22 95.28 94.21 91.25 87.17 93.00

    Auxiliary% STN 9.24 8.15 8.53 8.19 8.27 8.20 8.14 8.26

    PAF % STN 100.0

    0

    99.87 97.97 99.07 99.20 96.00 95.95 97.11

    Oil

    figure(ml/kwh

    )

    STN 0.107 0.128 0.331 0.207 0.116 0.300 0.175 0.377

    Rate of

    unloading

    BOX

    N

    0 10 10.14 10 10.7 10 11.3 11.5

    BOBR 0.00 3 2.82 3 3.15 3 3.78 3.8

  • One of the employees of any department can raise a issue regarding any machinery in the plant

    planning department takes the issue into account and checks whether the issue is being solved

    or not and take steps according to the progress of the work in desired time. Such a minutes of

    the meeting is published below.

    Parameters Yearly target Actual

    Unit

    trips(number)

    STN 8 4

    Tube leaks (no.) STN 3 1

    Reportable

    accidents

    STN 6 8

    SPM(mg/Nm3)

    Unit1&2 40 23

    Unit3 30 23

    Heat

    rate(Kcal/kwh)

    STN 2215 2230

    Total gen

    loss(mu)

    STN 39 3.06

    Total R/M exp. STN 7195 3789

    Env. Related

    failures

    STN 2 3

  • OPERATIONS DEPARTMENT

    RANKINE CYCLE:

    The Rankine cycle is a thermodynamic cycle which converts heat into work.The heat is

    supplied externally to a closed loop, which usually uses water as the working fluid.This

    cycle generates about 80% of all electric power used in America and throughout the

    world including virtually all solar thermal, biomass, coal and nuclear power plants.It is

    named after William John Macquorn Rankine, a Scottish polymath.

    A Rankine cycle describes a model of the operation of steam heat engines most

    commonly found in power generation plants. Common heat sources for power plants

    using the Rankine cycle are coal, natural gas, oil, and nuclear.

    The efficiency of a Rankine cycle is usually limited by the working fluid. Without the

    pressure going super critical the temperature range the cycle can operate over is quite

    small,turbine entry temperatures are typically 565C (the creep limit of stainless steel)

    and condenser temperatures are around 30C. This gives a theoretical Carnot efficiency

    of around63% compared with an actual efficiency of 42% for a modern coal-fired power

    station. This low turbine entry temperature (compared with a gas turbine) is why the

    Rankine cycle is often used as a bottoming cycle in combined cycle gas turbine power

    stations

    One of the principal advantages it holds over other cycles is that during the

    compression stage relatively little work is required to drive the pump, due to the

    working fluid being in its liquid phase at this point. By condensing the fluid to liquid,

    the work required by the pump will only consume approximately 1% to 3% of the

    turbine power and so give a much higher efficiency for a real cycle. The benefit of this

    is lost somewhat due to the lower heat addition temperature. Gas turbines, for

    instance, have turbine entry temperatures approaching 1500C.Nonetheless, the

    efficiencies of steam cycles and gas turbines are fairly well matched.

    There are four processes in the Rankine cycle. These states are identified by numbers

    (in brown) in the above Ts diagram.

    Process 1-2: The working fluid is pumped from low to high pressure. As the fluid is a

    liquid at this stage the pump requires little input energy.

    Process 2-3: The high pressure liquid enters a boiler where it is heated at constant

    pressure by an external heat source to become a dry saturated vapor. The input energy

  • required can be easily calculated using mollier diagram or h-s chart or enthalpy-

    entropy chart also known as steam tables.

    Process 3-4: The dry saturated vapor expands through a turbine, generating power.

    This decreases the temperature and pressure of the vapor, and some condensation may

    occur. The output in this process can be easily calculated using the Enthalpy-entropy

    chart or the steam tables.

    Process 4-1: The wet vapor then enters a condenser where it is condensed at a constant

    temperature to become a saturated liquid.

    In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and

    turbine would generate no entropy and hence maximize the net work output. Processes

    1-2 and 3-4 would be represented by vertical lines on the T-S diagram and more closely

    resemble that of the Carnot cycle. The Rankine cycle shown here prevents the vapor

    ending up in the superheat region after the expansion in the turbine, [1]

    which reduces

    the energy removed by the condensers

  • REGENERATIVE RANKINE CYCLE:

    The regenerative Rankine cycle is so named because

    after emerging from the condenser(possibly as a sub-cooled liquid) the working fluid is

    heated by steam tapped from the hot portion of the cycle. On the diagram shown, the

    fluid at 2 is mixed with the fluid at 4 (both at the same pressure) to end up with the

    saturated liquid at 7. The Regenerative Rankine cycle(with minor variants) is commonly

    used in real power stations.

    Another variation is where 'bleed steam' from between turbine stages is sent to

    feedwater heaters to preheat the water on its way from the condenser to the boiler .

  • BOILER

    Boiler is a steam raising unit of single radiant furnace type with auxiliaries,

    designated to generate steam 272 kg/hr. at 91.4 kg/cm

    2 V pressure. The unit burns pulverized low grade bituminous coal and is equipped

    with oil burners. This plant is designed to operate at a 475m.above sea level the

    ambient temperature is 40degree C with a humidity of 70%.Furnace consists of walls,

    tangent bare water tubes. Rear water tubes from a cavity for the pendant super-

    heater.There are many advantages of using water tube boiler: Water tube boilers are

    small in size,the volume of the boiler is comparatively small in comparison to the same

    size fire tubeboiler, better circulation of water in the boiler is possible.

    MANUFACTURER :

    Unit 1 & Unit 2: M/S ABB ABL Limited,Durgapur

    Unit 3: M/S BHEL

    TYPE:

    Horizontal single drum,natural circulation,water wall tube

    Each boiler has been provided with two forced draft fans (F.D), three induced draft fans

    (I.D) for unit 1&2 & two induced draft fans (I.D) for unit 3, two primary air fans (P.A),

    one primary tubular air heater, two secondary tubular air heaters for unit 1 & 2 and

    two rotary air heater for unit 3, six Ball & Race type pulverizers, six Volumetric coal

    feeders for unit 1 & 2 and five Bowl type pulverizers, five Gravimetric coal feeders for

    unit 3, etc. Soot blowing is done by steam. Main and reheat steam temperature is

    maintained from full load to 60% load. The boiler is capable of sustained stable

    operation down to 2 Mills at 30% capacity without oil support for flame stabilisation.

    25% BMCR requirement can be achieved by burning LDO alone .

  • BOILER

  • BOILER DRUM

    The steam drum is made up of high carbon as its thermal stress is very high. There is a

    safety valve in the drum, which may explode if the temperature and the pressure of the

    steam are beyond a set value. A safety is a valve mechanism for the automatic release

    of a gas from a boiler, pressure vessel or other system when the pressure or

    temperature exceeds preset limits.

    It is a part of a bigger set named Pressure Safety Valve (PSV) or Pressure Relief Valve

    (PRV). The other parts of the set are named relief valves.

    The boiler drum has the following purpose:

    1.It stores and supplies water to the furnace wall headers and the generating tubes.

    2.It acts as the collecting space for the steam produced.

    3.The separation of water and steam tube place here

    4.Any necessary blow down for reduction of boiler water concentration is done from

    the drum.

    RISER AND DOWN COMERS

    Boiler is a closed vessel in which water is converted into the steam by the application

    of the thermal energy. Several tubes coming out from the boiler drum surrounding the

    furnace.Outside the water wall there is a thermal insulation such that the heat is not

    lost in the surroundings. Some of the tubes of the water wall known as the down

  • comer, which carries the cold water to the furnace and some of other known as the

    riser comer, which take the steam in the upward direction. At the different load riser

    and the down comers may change their property. There is a natural circulation of water

    in the riser and the down comers due to different densities of the water and the steam

    water mixture. As the heat is supplied, the steam is generated in the risers. Lower

    density of the steam water mixture in the riser than water in the down comer causes

    natural circulation of water. Down comer connected to the mud drum, which

    accumulates the mud and the water.

    SUPER HEATER

    The super heater rises the temperature of the steam above its saturation point and

    there are two reasons for doing this: FIRST- There is a thermodynamic gain in the

    efficiency. SECOND- The super-heated steam has fewer tendencies to condense in the

    last stages of the turbine.

    It is composed of four sections, a platen section, pendant section, rear horizontal

    section and steam cooled wall and roof radiant section. The platen section is located

    directly above the furnace in front of the furnace arch. It is composed of 29 assemblies

    spaced at 457.2mmcenters from across the width of the furnace. The pendant section

    is located in the back of the screen wall tubes.

    It is composed of 119 assemblies at 1114mm centers across the furnace width. The

    horizontal section of the superheater is located in the rear vertical gas pass above the

    economizer. It is composed of 134 assemblies spaced at 102 mm centers across

    furnace width. The steam cooled wall section from the side front and rear walls and the

    roof of the vertical gas pass.no reheater is used.

    SPRAY ATTEMPERATOR

    In order to deliver a constant steam temperature over a range of load, a steam

    generating unit(Boiler) may incorporate a spray attemperator. It reduces the steam

    temperature by spraying controlled amount of water into the super-heated steam. The

    steam is cooled by evaporating and super heating the spray water. The spray nozzle is

    situated at the entrance to a restricted venture sections and introduces water into the

    steam. A thermal sleeve linear protects the steam line from sudden temperature shock

    due to impingement of the spray droplets on the pipe walls. The spray attemperator is

    located in between the primary super heater outlet and the secondary super heater

    inlet. Except on recommendation of the boiler manufacturer the spray water flow rate

    must never exceed the flow specified for maximum designed boiler rating. Excessive

    attemperation may cause over heating of the super heater tubes preceding the

  • attemperator, since the steam generated by evaporation of spray water and it does not

    pass through the tubes. Care must also be taken not to introduce so much that the

    unevaporated water enters the secondary stage of the super heaters.

    AIR PRE-HEATER

    The air heater is placed after the economizer in the path of the boiler flue gases and

    preheats the air for combustion and further economy. There are 3 types of air pre

    heaters: Tubular type, rotary type and plate type. Tubular type of air heater is used in

    TGS. Hot air makes the combustion process more efficient making it more stable and

    reducing the energy loss due to incomplete combustion and unburnt carbon. The air is

    sent by FD fan heated by the flue gas leaving the economizer. The preheated air is sent

    to coal mill as primary air where coal is pulverized. The air sucked is heated to a

    temperature of 240-280oC. The primary air transports the pulverized coal through

    three burners at TGS after drying in the mill.

    ECONOMIZER

    The heat of the flue gas is utilized to heat the boiler feed water. During the start up

    when no feed water goes inside the boiler water could stagnate and over heat in the

    economizer. To avoid this, economizer re circulation is provided from the boiler drum

    to the economizer inlet. The feed water coming out from deaerator passes through to

    special shape of pipes inside the economizer. The special shapes of tubes provide

    increase the contact surface area between the flue gas and the feed water, so that

    maximum heat exchanging can take place.

  • ELECTROSTATIC PRECIPITATOR

    It is a device that separates fly ash from outgoing flue gas before it discharged to the

    stack.There are four steps in precipitation:-

    1.Ionization of gases and charging of dust particles.

    2.Migration of particle to the collector.

    3.Deposition of charged particles on collecting surface.

    4.Dislodging of particles from the collecting surface.By the electrostatic discharge the

    ash particles are charged due to high voltage (56KV)between two electrodes.

    Generally maximum amount of ash particles are collected in the form of dry ash,

    stored inside the SILO.

    Rest amount of ash (minimum) are collected in the form of bottom ash and stored

    under the water inside HYDROBIN.

  • SAFETY VALVE

    A safety valve is a valve mechanism which automatically releases a substance from a

    boiler, pressure vessel, or other system, when the pressure or temperature exceeds

    preset limits. It is one of a set of pressure safety valves (PSV) or pressure relief valves

    (PRV), which also includes relief valves, safety relief valves, pilot-operated relief

    valves, low pressure safety valves, and vacuum pressure safety valves.

    Vacuum safety valves (or combined pressure/vacuum safety valves) are used to

    prevent a tank from collapsing while it is being emptied, or when cold rinse water is

    used after hot CIP (clean-in-place) or SIP (sterilization-in-place) procedures. When

    sizing a vacuum safety valve, the calculation method is not defined in any norm,

    particularly in the hot CIP / cold water scenario, but some manufacturers have

    developed sizing simulations

    No of Safety valves Unit#1&2 Unit#3

    At Drum 2 3

    At Superheater 2 2

    At CRH 4 1

    At HRH 2 4

    No of Air heater 3 2

    No of F.D Fan 2 2

    No of I.D Fan 3 2

    No of P.A Fan 2 2

    No of Coal Mills

    6

    5

    TURBINE

    Turbine is a rotating device which converts heat energy of steam into mechanical

    energy. It is a two cylinder machine of impulse reaction type comprising a single flow

    high pressure turbine and a double flow low pressure turbine.The H.P. turbine shaft

    and the generator are all rigidly coupled together, the assembly being located axially

    by a thrust bearing at the inlet end of H.P. turbine. The turbine receives high pressure

    steam from the boiler via two steam chests. The H.P.turbine cylinder has its steam

    inlets at the end adjacent to the no. one bearing block, the steam flow towards the

    generator. Exhaust steam passes through twin over-head pipes to the L.P.turbine inlet

  • belt where the steam flows in both directions through the L.P. turbine where it

    exhausts into under slung condenser.Steam is extracted from both the H.P. & L.P.

    turbine at various expansion stages & fed into four feedwater heaters. Here spherically

    seated Journal Bearing is used.

    The main turbine is a Tandem Compounded, Three Cylinder, Single Reheat, Double

    Flow LP cylinder, Condensing Type with uncontrolled Extraction .

    No. of cylinders HP-1 Single Flow

    IP-1 Single Flow

    LP-1 Double Flow

    SV Pressure & Temp 146 kg/cm^2 Abs & 537deg C

    Reheat Pressure & Temp

    35.7 kg/cm^2 Abs & 535deg C

    Speed

    3000 Rev/Min

    No. of blading stages

    Unit 1

    Unit 2 & Unit 3

    HP 1-Impulse

    25-Reaction

    18-50% Reaction

    IP 16-50% Reaction

    17-Reaction

    LP 4-50% Reaction per

    flow,3-variable reaction

    8-Reaction per flow

  • The steam turbine drives a 250 MW, 3 Alternator with Hydrogen cooled Rotor and

    Stator Core and DM water cooled Stator Windings(Unit 1&2) at a speed of 3,000 rpm.

    The turbine shafts & generator rotor are rigidly coupled together. The generator field is

    excited from a static excitation system. Power is generated at 16.5 kV and is stepped

    up to a voltage of 132 kV (unit 1&2) and 220 kV (unit 3) in a generator transformer for

    onward transmission to the system and there is an inter connection between 132 kV

    switchyard and 220 kV switchyard thru ICT(Inter connecting transformer). The turbine

    utilizes an electro-hydraulic governing system. The start-up, shut-down and loading of

    the turbine can be achieved automatically. The turbine throttle pressure is 146 Kg/Cm2

    (abs.), the main steam temperature is 537C and the reheat steam temperature is 535C.

    The turbine cycle includes two stages of feed-water pumping (boiler feed pumps and

    condensate extraction pumps), consisting seven stages of regenerative feed-water

    heating by turbine bled steam, viz, two high pressure regenerative closed feed-water

    heaters at the boiler feed pump discharge, four low pressure closed feed-wafer heaters

    at the condensate extraction pump discharge and one direct contact heater (deaerator)

    for unit 1&2 and two high pressure regenerative closed feed-water heaters at the boiler

    feed pump discharge, three low pressure closed feed-wafer heaters at the condensate

    extraction pump discharge and one direct contact heater (deaerator) for unit 3. All the

    feed-water heaters are of horizontal type. The two (2) lowest pressure heaters LPH-1 &

    2 (unit 1&2) and LPH-1 (unit 3) are located inside the neck of the condenser and LPH-1

    is provided with an external drain cooler.

  • Turbine Generator

  • CONDENSER

    Condenser is a device used for converting a gas or vapour to liquid. Condensers are

    employed in power plants to condense exhaust steam from turbines. In doing so, the

    latent heat is given up by the substance and it will be transferred to the condenser

    coolant.

    A surface condenser is a shell and tube heat exchanger installed at the outlet of every

    steam turbine in thermal power stations.

    The cooling water flows through the tube side and the steam enters the shell side

    where the condensation occurs on the outside of the heat transfer tubes. The

    condensate drips down and collects at the bottom, in a pan called hot well. Initial air

    extraction from the condenser and steady vacuum inside the condenser is achieved by

    two nos. motor driven, water sealed, air extraction pumps commonly called NASH

    pump. During normal operation of the plant, vacuum is maintained by the circulating

    water flowing inside the condenser and the non-condensable gases are extracted by

    one of the NASH pumps. 2 nos. separate condensate storage tanks, interconnected to

  • each other, are provided for the three units. Condensate storage tanks receive

    demineralised water from DM Plant.

    FEEDWATER HEATER

    Feedwater heaters are used in powerplants to preheat water delivered hot steam to the

    generating boiler. Preheating the feedwater reduces the irreversibilities insteam

    generation and hence improves the efficiency of the system. This method is

    economical and reduces thermal shock when the feed water is introduced back in the

    cycle. In steam power plants, there are two kinds of low pressure & high pressure

    heater. These heaters help to bring the feedwater to satuiration temperature very

    gradually. Feed water is taken from the De-aerator, a feed water storage tank, by motor

    driven feed water pumps, and discharged through two stages of high pressure

    regenerative feed water heaters and flue gas heated economizer into the boiler drum.

    Provision is kept for condensate bypassing of LP Heaters in two groups in the event of

    heater flooding so that the turbine is protected from water ingress viz. LP Heaters-2 &

    1 and drain cooler as one group, and LP Heaters-3 & 4 as the other of unit 1&2 and LP

    Heaters-1 and drain cooler as one group, and LP Heaters-2 & 3 as the individual of unit

    3. LP Heater-2 drain is cascaded to LP Heater-l via a flash box, while LP Heater-l drain is

    cascaded to the condenser-drains flash box via the drain cooler. LP Heater-4 drain is

  • similarly cascaded to LP Heater-3, while LP Heater-3 normal drain is pumped forward

    by a 1 x 100% drain pump via control valves to LP Heater-3 main condensate outlet of

    unit 1&2. LP Heater-2 drain is cascaded to LP Heater-l and alternate drain to LP Heater

    flash box, while LP Heater-l drain is cascaded to the condenser-drains flash box via the

    drain cooler. LP Heater-3 drain is similarly cascaded to LP Heater-2 and alternate drain

    to LP Heater flash box.

    DEAREATOR

    Deaerator is a device widely used for the removal of oxygen and other dissolved gasses

    from thefeedwater. It mostly uses low pressure steam obtained from an extraction

    point in their steam turbine system. They use steam to heat the water to the full

    saturation temperature corresponding to the steam pressure in the deaerator and to

    scrub out and carry away dissolved gases. Steam flow may be parallel, cross, or

    counter to the water flow. The deaerator consists ofa deaeration section, a storage

    tank, and a vent. In the deaeration section, steam bubbles through the water, both

    heating and agitating it. Steam is cooled by incoming water and condensed at the vent

    condenser. Noncondensable gases and some steam are released through the vent.

    Steam provided to the deaerator provides physical stripping action and heats the

    mixture of returned condensate and boiler feedwater makeup to saturation

    temperature. Most of the steam will condense, but a small fraction must be vented to

    accommodate the stripping requirements. Normal design practice is to calculate the

    steam required for heating and then make sure that the flow is sufficient for stripping

    as well.

  • COOLING TOWER

    Cooling towers are heat removal devices used to transfer process waste heat to the

    atmosphere. Cooling towers may either use the evaporation of water to remove process

    heat and cool the working fluid or, in the case of closed circuit dry cooling towers, rely

    solely on air to cool the working fluid. The primary use of large, industrial cooling

    towers is to remove the heat absorbed in the circulating cooling water systems used in

    power plants. The circulation rate of cooling water in a typical 700 MW coal-fired

    power plant with a cooling tower amounts to about 71,600 cubic metres an hourand

    the circulating water requires a supply water make up rate of perhaps 5 percent.

    Facilities such as power plants,steel processing plants use field erected type cooling

    towers due to their greater capacity to reject heat.

    With respect to the heat transfer mechanism employed, the main types are:

    Dry cooling towers operate by heat transfer through a surface that separates the

    working fluid from ambient air, such as in a tube to air heat exchanger, utilizing

    convective heat transfer. They do not use evaporation.

    Wet cooling towers or open circuit cooling towers operate on the principle of

    evaporative cooling. The working fluid and the evaporated fluid (usually water)

    are one and the same.

    Fluid coolers or closed circuit cooling towers are hybrids that pass the working fluid

    through a tube bundle, upon which clean water is sprayed and a fan-induced draft

    applied. The resulting heat transfer performance is much closer to that of a wet cooling

    tower, with the advantage provided by a dry cooler of protecting the working fluid

    from environmental exposure and contamination

    CONDENSATE EXTRACTION PUMP (CEP)

  • The pumps are vertical multi-stage bowl diffuser type, arranged inside a suction

    barrel. The condensate pump is normally located adjacent to the main condenser

    hotwell often directly below it. The condensate water is drawn from the condenser by

    the extraction pumps and sent to the low pressure feed heaters.

    BOILER FEED PUMP (BFP)

    A boiler feedwater pump is a specific type of pump used to pump feedwater into a

    steam boiler. The water may be freshly supplied or returning condensate produced as

    a result of the condensation of the steam produced by the boiler. It consists of two

    parts, first the booster pump then the main pump. The water enters the booster pump

    at 7kg/ and it increases the pressure to about 20 kg/ . Then it enters the main

    pump and by fluid coupling mechanism it increases the pressure to 150 kg/ . It is

    achieved by increasing the speed to about 5700 r.p.m. If the amount of oil is

    decreased in between the fluid coupling then the speed will decrease. Thus a gear box

    is not required, instead a device called scoop is required that removes the oil and

    control the speed of rotation. It consumes the highest amount of power about 8.8 MW.

    DEMINERLISING PLANT

    Raw water is passed via two small polystyrene bead filled (ion exchange resins)

    beds. While The cations get exchanged with hydrogen ions in first bed,the anions are

    exchanged with hydroxyl ions, in the second one. Demineralized water also known as

    deionized water, water that has had its mineral ions removed. Deionization is a

    physical process which uses specially manufactured ion exchange resins which

    provides ion exchange site for the replacement of the mineral salts inwater with water

    forming H+ and OH- ions. Because the majority of water impurities are dissolved

    salts,deionization produces a high purity water that is generally similar to distilled

    water, and this process is quick and without scale buildup. De-mineralization

    technology is the proven process for treatment of water. A DM Water System produces

    mineral free water by operating on the principles of ion exchange, degasification, and

    polishing. Demineralised Water System finds wide application in the field of steam,

    power, process, and cooling.

  • AIR & FLUE PATH

    Drives & Equipments :

    FD fans - 2 nos.

    PA fans 2 nos.

    Scanner air fans 2 nos. (Fan A-AC ; Fan B-DC).

    Regenerative air preheater 2 nos.

    Seal air fans 2 nos.

    ID Fans - 2 nos.

    Air & Flue path dampers & gates.

    Fans in air & flue path:

  • FD fans : Air suction from atmosphere.

    Motor rated continuous output : 750 KW

    Full load /No load amps : 81 / 24

    Rated rpm : 1486

    PA fans : Air suction from atmosphere.

    Scanner air fans : Suction from FD fan discharge cross over duct.

    Seal air fans : Suction from cold PA header.

    ID fans: Motor rated continuous output : 1800 KW

    Full load /No load amps : 199 / 74

    Rated rpm : 746.

    MECHANICAL MAINTENANCE DEPARTMENT

    Maintenance is a set of organised activities that are carried out in order to keep

    equipment in its best operational condition with minimum cost acquired. It includes

    performing routine actions which keep the device in working order or prevent trouble

    from arising.

    MAINTENANCE TYPES

    Broadly speaking, there are three types of maintenance in use:

    Preventive Maintenance: Preventive maintenance is the maintenance performed

    in an attempt to avoid failures, unnecessary production loss and safety

    violations. It includes scheduled maintenance (daily and routine) of the

    equipment and includes activities like regularly monitoring the temperature and

    pressure of the bearing, grease, windings, oil, air and gases, the flow of air,

    water and oil, the rotation of bearing lubricating rings, moisture content in the

    gases, etc. It is the maintenance before the breakdown occurs.

  • Corrective Maintenance: It is the maintenance where equipment is maintained

    after break down. This maintenance is often most expensive because worn

    equipment can damage other parts and cause multiple damage. The corrective

    maintenance is carried out to bring it back the equipment in the working order.

    Predictive Maintenance: This kind of maintenance includes activities to foresee

    events in the future that could lead to damage of the equipment or cause a

    failure in the system. It implies vibration monitoring, Ultrasound tests, Breaker

    timing test, Thermograph etc.

    The major divisions in this department include:

    Maintenance of Boiler & its auxiliaries: Boiler

    ID Fan

    FD Fan

    PA Fan

    Coal Mill

    Various Pumps, etc.

    Maintenance of Turbine & its auxiliaries:

    Turbine

    CEP

    BFP

    NASH Pump

    HP_LP Bypass System

    Condensate Transfer Pump

    Circulating Cooling Water (CW) Pumps

    Service Cooling Water Pumps, etc.

    Maintenance of Fuel and Ash: Conveyor System

    Rotary Breakers

    Crusher

    Wagon Tipplers

    Track Hoppers

    Bottom & Fly Ash

    While performing maintenance activities, it is important we maintain a schedule for the

    same, take in to safety considerations, keep all necessary tools and equipment in the

    vicinity of the equipment, ensuring only skilled man power to handle the machine.

    Also the various maintenance activities should be practiced in a sequential manner and

    proper note be taken. Given below are checklists for HP-LP Bypass Maintenance and for

    Cooling Tower Fan Maintenance.

    LUBRICATION SYSTEM

  • Lubrication is an essential activity for the healthy working of equipment. It is the

    process or technique employed to reduce wear off one or both surfaces in close

    proximity and moving relative to each other, by interposing a lubricant by interposing

    a lubricant between the surfaces to carry or to help carry the load between the

    opposing surfaces. Lubrication purposes to:

    Lubricate: Reduces Friction by creating a thin film(Clearance) between moving

    parts (Bearings and journals)

    Cool: Picks up heat when moving through the engine and then drops into the

    cooler oil pan, giving up some of this heat.

    Seal: The oil helps form a gastight seal between piston rings and cylinder walls

    Clean: As it circulates through the engine, the oil picks up metal particles and

    carbon, and brings them back down to the pan

    Absorb Shock: When heavy loads are imposed on the bearings, the oil helps to

    cushion the load.

    Absorb Contaminants: The additives in oil helps in absorbing the contaminants that

    enter the lubrication system.

    The checklist for maintenance of HP-LP Bypass System

    S.

    No.

    Description OK/Not OK Values & Condition

    1. Check Nitrogen Pressure of

    all Accumulators

    Charging Pressure

    for 10L and 32L

    Accumulators=80

    Bar, and for 50L=120

    Bar

    2. Change all filters on P1 line Every 6 months

    3. Check all wear outs, cuts and

    abrasion of all hoses

    4.

    Check for oil leaks from

    Actuator seals, Servo valves,

    Blocking units, Fast closing

    and opening devices

  • 5.

    Check for any steam and

    water leaks from any steam

    and water valves

    6.

    Check tightness of coupling

    bolts, bolts of locking

    arrangement & bolts of

    antirotation device on HPBP

    valve

    Torque tightness oh

    HP coupling bolts:

    Torque tightness of

    HP indicator bolts:

    Torque tightness of

    antirotation device

    bolts:

    7.

    Measure gap of both sides of

    T-end of antirotation device

    on HPBP Coupling

    Mention previous

    readings:

    (north):

    (south):

    8. Check filtering of HSU filter

    pump in oil taking out mode

    9.

    Check cut-in and cut-out

    pressure of Pp. and time of

    cut-in and cut-out

    Monthly check list for Cooling Tower Fan

    Description Job Done Remark

    1.Check tightness of coupling bolts between

    gear and motor

    2. Check condition of above coupling bushes.

    3. Check tightness of base bolts of gear box,

    motor and base frame

    4. Check tightness of fan blades& U bolts

    5. Check gear teeth condition

    6. Check the end play

    7. Measure the blade (pitch) angle~ should be

    6.5 or 15

  • 8. Check the track variation

    9. Check condition of leading & trailing edge of

    blade

    10. Clear the drain hole at tip of the blade

    11. Record tip clearance of all blades

    12. Check match mark on blades, U bolts,

    clamp, hub plate

    13. Check condition of blade

    14. Check oil leakage, level & oil condition

    15. Check oil quality

    16. Check condition of cap on oil filling pipes

    17. Check play in the output shaft by hand

    feeling

    18. Clean Breather of the gear box

    ELECTRICAL & INSTRUMENT DEPARTMENT

    B.B.G.S. Generator

    Unit 1&2 Unit 3

    Maximum Continuous Rating 250 MW 250 MW

    Maximum Continuous Rating 294 MVA 294 MVA

    Rated Power Factor 0.85 0.85

    Rated Terminated Voltage 16500V 16500V

    Rated Current 10291A 10291A

    Frequency 50 Hz 50 Hz

  • Number of phases 3 3

    The generators at BBGS are hydrogen and DM water cooled type. The outer part of the

    cylinder has hydrogen operated coolers white the inner part has the core and the

    windings. DM water is circulated all along the cylinder by two AC pumps. The stator

    core and the rotors are cooled by hydrogen circulated by centrifugal pumps mounted

    on each side of the generator.

    The rotor is made with alloy forgings with steel at the exciter end. The rotor windings

    are formed from copper strips. Each end of rotor shaft is supported by journal

    bearings, lubricated from Turbine Lube Oil system. Exciter end bearing pedestal is fully

    insulated to prevent eddy current circulation through bearing and oil films.

    The generator field current is supplied by a static excitation system. The current is

    supplied by an excitation transformer and a thyristor controlled rectifier.

    The turning gear drive is coupled to the generator rotor and when meshed, allows

    turbine and generator shafts to be rotated slowly before run up and after shut down to

    prevent rotor distortion due to uneven heating.

  • There are 3 types of transformers in the plant namely GT(Generator

    Transformer),ST(Station Transformer),UT(Unit Transformer).The GT is used to step up

    the voltage generated(16.5KV) to 132KV in case of unit#1 &2,16.5KV to 220KV as the

    voltage generated(16.5KV) to 132KV in case of unit#1 &2,16.5KV to 220KV as

    mentioned earlier. The ST & UT are used for in-plant power of BBGS for meeting the

    power requirements of the auxiliaries such as FD Fan, PA Fan, ID Fan, coal mills,

    conveyors, centrifugal pumps, CW Pump etc as well as the lighting loads of the various

    buildings of the plant. The start up power of the plant is provided by the UT which

    steps down the voltage from 16.5KV to 6.6K whereas the ST taps voltage from the Bus-

    Bars.

    The specifications of the various generators of unit#1 &2 are as follows :

    GT#1,GT#2(Generator Transformer) :

    315 MVA,138/16.5 KV

  • X=12-15% Yd 11

    The GT is having vector notation Yd 11(30deg lag between prim. & sec.

    side) which is used generally as a convention

    The alternators(3-phase)of the Turbine-Generator set is Wye-connected so

    that during earth fault the fault current(the sum of the currents in the 3 phases is not

    equal to zero during earth fault) flows into the ground through the neutral wire

    without hampering the generator.

    The LV side (16.5KV) of the GT is delta connected. This is because if there

    is an earth fault on the LV side of the GT then using Wye connection will cause the fault

    current to flow through the neutral wire. This fault current may enter into the

    generator circuit through the neutral wire of the Wye connected generator & hamper

    the generator. To avoid such a situation LV side(16.5KV) of the GT is delta connected.

    The HV side of the GT which is connected to the transmission line is Wye

    connected.

    The neutral wire for bypassing the fault current is connected to

    NGT(Neutral Grounding Transformer) which steps down the current to a smaller value

    so that the fault current does not hamper any devices.

    Unit Transformer : (UT#1)

    HV/LV1/LV2

    40/25/15MVA

    16.5/6.5/6.5 KV

    ON LOAD TAP + 8*1.25%

    X= [ HV-LV1= 15%,HV-LV2=11.5%,LV1-LV2=22.5%(MIN)]

    (ALL IMPEDANCE ON 40MVA BASE)

    HV

    UT-1

    LV 1 LV 2

  • To UB-1B Incomer To UB-1A Incomer

    Station Transformer: (ST#1)

    HV/LV1/LV2

    60/30/30MVA

    132/6.9/6.9KV

    ON LOAD TAP +6-1.0 * 1.0 %

    X= [HV-LV1=32.7%, HV-LV2=19.6%,LV1 -LV2=48.8%(MIN)] (ALL IMPEDANCE ON 60MVA BASE)

    HV

    ST-1

    LV 1 LV 2

    To SB-1B Incomer To SB-1A Incomer

    The UT has two LV sides namely LV1 & LV2 having voltage rating of 6.5KV

    each.These two LV sides are used to charge the UB-1A & UB-1B(Unit Board) through the

    incomers which are connected to UT-1.The UT is used to charge the UB-1A & UB-1B.

    The UB-1A consists of two portions:

    UB#1A(1st portion):

    The auxiliaries connected to this portion are as follows:

    ID FAN# 1A 1*1580 KW

    PD FAN# 1A 1*1182 KW

    PA FAN# 1A 1*940 KW

    COAL MILL# 1A/B/C 3*409 KW

    CEP# 1A 1*760 KW

    A.C.W PP# 1A 1*290 KW

  • SPARE FDR 1*1580 KW

    CW PP #1A 1*1420 KW

    UB#1A(2nd portion) :

    ID FAN# 1B/1C 2*1580 KW

    FD FAN# 1B 1* 1182 KW

    PA FAN# 1B 1*940 KW

    COAL MILL# 1D/E/F

    CW# 1B 1*1440 KW

    UB #1B:

    BFP# 1A 1*8800 KW

    The UB#1A & UB#1B are charged by UT- 1.The SB# 1A & SB#1B are charged

    by the ST-1.Similar is the case for unit# 2.The UB caters to the independent drives (coal

    mills, CW PP, FD FAN, ID FAN etc) which are different for each unit whereas the SB

    caters to the dependent drives (Intake PP, coal plant etc) which are the same for all the

    units.

    We observe that UB#1A caters to a number of auxiliaries such as PD FAN, ID

    FAN, COAL MILL, CW PP, ACW PP etc whereas the UB#1B caters to BFP only. This is

    because the BFP is rated with high wattage consumption whereas the other auxiliaries

    are of considerably lower power consumption. Thus is BFP & the other auxiliaries are

    present on the same UB then the total power available on the UB will the consumed by

    the auxiliaries itself leaving the BFP un-operated. Thus the BFP is present in a separate

    UB.

    Now if due to shutdown or failure of the UT#1,the LV sides of the UT are

    unable to charge the UB#1A & UB#1B,then the SB#1A(Station Board 1A) & the

    SB#1B(Station Board 1B) are used to charge the UB#1A & UB#1B respectively with the

    help of a tie between the SB & UB.

    A large number of circuit breakers are used in the total electrical system

    like SF6 gas circuit breaker(6.6 KV),Air circuit breaker(415 V) as well as a number of

    isolators, insulators, earth switches, CT(Current Transformer),PT(Potential

    Transformer) ,overload protection, Bus Coupler Breakers are used.

    The 3.5m level consists of all the boards which consists of a large number

    of relays, circuit breakers etc which delivers power to the various auxiliaries. Some of

    the specifications are given as follows:

    INCOMER FROM ST1-LV1 :

    The relays are Combiflex Relays, Trip Circuit Relay, Tripping Relay, O|C & EF Prot.

    Indicators such as Autotrip circuit unhealthy, Gas pressure low, Breaker on, Breaker off, spring charged.

  • Number of switches are there such as Breaker open & Breaker close, Ammeter Switch(K, Y, B, Off),Emergency Trip,(Remote, Local, SWGR)

    DM WTR SYS TR# DMT-1: 1600 KVA

    SPARE TRANSFORMER FDR: 1600 KVA

    CT TRANSFRMR: 2000 KVA

    TRNSFRMR FOR IA PA COMP: 1600 KVA

    INTAKE WTR TRNSFRMR: 1600 KVA

    STN. AUXILIARY TRNS: 2000 KVA

    TR. FOR ADMIN BUILDING: 500 KVA

    TR. FOR SECURITY BUILDING: 500 KVA

    BUSDUCT TRNS. : 415 V, 250 A

    ASH HANDLING SWGR: 45 KW, 4A

    TIE TO ASH HANDLING SWGR: 6.6 KV

    CONVEYOR: 250 KW

    Dry Type Transformer :

    1600KVA

    Type of cooling- AN

    Temp- 90 deg C

    Insulation Class- F

    Insulation level HV 60 KVP|20 KVP rms

    Rated Current HV (amps) 139.96

    Rated current LV (amps) 2133.4

    Impedance volts % - 8 + IS Tol

    Model- Cast resin dry type

    Vector Group- Dyn 11

    Freq-50 Hz

    The stepped up voltage of 132 KV by GT#1 & 2,& 220 KV by GT# 3 are fed

    through CT to the Moose conductors(ACSR).For unit#1 & unit#2,there is one GT for

    each phase(R,P,Y) whereas there is only one GT for unit#3 supplying the R,Y,B phase.

    On the back of these transformers, NGTs are situated. The moose conductors from the GT enter the switchyard.

  • SWITCHYARD

    Switchyard is a very important part of the electrical circuit. It generally consists of

    three buses, which are the two main bus & one transfer bus. A portion of the transfer

    bus is connected with the generating transformers which are at 132KV for unit 1&2 and

    220KV for unit 3. Due to the inequality between the two voltages, they are connected

    with the interconnected transformer (ICT) to form a common bridge between the two

    transformers. The transfer bus is connected in series with the main bus 1 or main bus

    2 or neither of them. The line first comes from the generating transformer and then

    through a series of isolators and circuit breakers main bus 1 or the main bus 2 is

    connected. Two main bus are used as one is kept in standby mode if a fault occurs in

    anyone of them then the other one can be used. The 132KV & 220KV line are also

    connected to the transmission line. When in one main bus bar a fault occurs and we

    need to transfer the bus, let in main bus 1 a fault occurs & we need to transfer it to

    main bus 2 then we first connect the transfer bus thus for a brief moment the feeder

    gets the voltage from both main bus 1 & transfer bus, then we open the main bus 1

    thus for that brief moment the feeder gets the voltage from the transfer bus only. Then

    we connect the main bus 2 also, thus for a brief moment the feeder gets the voltage

    from both main bus 2 & transfer bus, then we open the open the transfer bus and the

    feeder gets power from main bus 2 only. The main buses are connected with the

    station transformer, it steps down the voltage to about 6.9KV which is used to drive

    the plant during any plant failure. There are 3 station transformers one for each unit.

    When the plant will fail to generate, then the station transformer with the help of the

    switchyard gets the power from other unit and keeps the necessary machineries

    working at that time.

    The isolators in the switchyard have two functions, which are basically isolation of the

    feeders and also used to ground the system. Generally two motors are used one for

    isolating and another for grounding the isolator. The circuit breakers generally denoted

    by 52 are SF6 circuit breakers. These circuit breakers are used are SF6 is a very stable

    gas and arching doesnt occur that easily. When the main line carrying 132KV & 220KV

    enters or exits the switchyard it goes through current transformer which is in series

    with the line & capacitance coupled voltage transformer as potential transformer in

    parallel with the circuit, one end of the capacitance coupled voltage transformer is

    connected to the ground. The interconnecting transformer is a core type transformer,

    which is used as it is more economical & also because the ratio of voltages between low

    voltage & high voltage side is not more then 1:3.

  • CONCLUSION

    Working with Calcutta Electricity State Cooperation Limited (CESC Ltd) as a vacational

    training was a very nice experience. I learnt a lot about designing basic systems in

    electrical and how the importance of electrical power generation, maintenance and

    operation, in any project. I also practiced what I learnt in the college and applied it on

    field. Working with Electrical department enhanced my major understanding .In

    addition, I gained a good experience in term of self confidence, real life working

    situation, interactions among people in the same field and working with others with

    different professional background. I had an interest in understanding basic

    engineering work and practicing what has been learnt in the class. Also, the training

    was an opportunity for me to increase my human relation both socially and

    professionally.