Upload
shashankmehta7
View
224
Download
0
Embed Size (px)
Citation preview
8/6/2019 CERC Staff Paper
1/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
1|18
CentralElectricityRegulatoryCommission
NewDelhi
GRIDSECURITYNEEDFORTIGHTENINGOFFREQUENCYBAND
&OTHERMEASURES
CERCSTAFFPAPER
March2011
8/6/2019 CERC Staff Paper
2/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
2|18
GRIDSECURITYNEEDFORTIGHTENINGOFFREQUENCYBAND
&OTHERMEASURES
CERCSTAFFPAPER
1. IntroductionPower frequency reflects the loadgenerationbalance in thegridataparticular instant.Frequency is
oneofthemostimportantparametersforassessmentofthesecurityofpowersystemandthequality
ofpowersupplyinanygrid.Itistobemaintainedwithinthespecifiedrangeinwhichalltheelectrical
equipmentsaredesignedtoperformsafelyandefficiently.Handling imbalances isan integralpartof
market design. In India, the balancing market is frequency dependent and market design must
complementreliability.Thisdiscussionpaperfocusesongridfrequencyandotherissuesrelatedtogrid
securityinIndia.
2. PowerSupplyScenarioinIndiaIndiaisoneofthelargestsynchronousinterconnectionsintheworld.Theinstalledgenerationcapacity
ason31stJan2011 is170.23GW.Therevisedtargetforgenerationcapacityaddition in11thfiveyear
plan is 62 GW. The projected peak shortage and energy shortage in March 2012 is 6.5% and 2%
respectively.
8/6/2019 CERC Staff Paper
3/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
3|18
Table1:AnticipatedPowerSupplyScenarioin2012
Period Peak
Demand
(MW)
Peak
Availability
(MW)
Deficit()/
Surplus(+)
(MW)
Deficit()/
Surplus(+)
(%)
201112 152746 142765 9981 6.5
Energy
Requirement
(MU)
Energy
Availability
(MU)
Deficit()/
Surplus(+)
(MU)
Deficit()/
Surplus(+)
(%)
201112 968659 948836 19823 2%
Demandasper17th
ElectricPowerSurvey
Source:PowerScenarioataGlance,January2011, CEA
3. StandardsforPowerFrequencyinIndiaAspertheIndianElectricityRules1956(amendedupto25
thNov2000),thepermissiblerangeforgrid
frequency was +/ 3 % of nominal i.e. 48.5 Hz to 51.5 Hz. The permissible frequency ranges (by
manufacturers) for operation of various makes of steam turbine are shown in Figure 1. The nominal
frequencyofoperationinIndiangridis50.0HzandthepermissiblefrequencybandspecifiedbyIndian
ElectricityGridCode(IEGC)is49.5Hzto50.2Hzw.e.f3rd
May2010.
8/6/2019 CERC Staff Paper
4/18
8/6/2019 CERC Staff Paper
5/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
5|18
Thenormaloperatingfrequencyrangeallowedbythe IndianElectricityGridCodetill31stMarch2009
was49.0to50.5Hz.ThefrequencybandwastightenedbyCERC insubsequentamendmentsto IEGC.
Thefrequencybandw.e.f3rd
May2010is49.5Hzto50.2Hz.
Table3:OperatingrangeforfrequencyspecifiedinIEGC
SNo. Period OperatingRange(inHz)
1 Till31stMarch2009 49.0to50.5
2 1stApril2009to2
ndMay2010 49.2to50.3
3 w.e.f3rd
May2010 49.5to50.2
SimilarlytheUImechanismhasbeenrevisedseveraltimesinthepasttoimprovethefrequencyprofile
inthegrid.ThevariousstagesofevolutionoftheUImechanismhasbeendisplayedasAnnexure.The
continuousimprovementinthegridfrequencyprofileisevidentfromthefrequencyprofilerecordedin
theNorthEastWestgridinthepastfewyearsasdisplayedinfigure2and3below.
ER / NEW GRID MAXIMUM AND MINIMUM FREQUENCY JANUARY'98 ONWARDS
47.0
47.5
48.0
48.5
49.0
49.5
50.0
50.5
51.0
51.5
52.0
52.5
53.0
53.554.0
Jan-
98
Jan-
99
Jan-
00
Jan-
01
Jan-
02
Jan-
03
Jan-
04
Jan-
05
Jan-
06
Jan-
07
Jan-
08
Jan-
09
Jan-
10
Jan-
11
Date -->
Hz-->
MAXIMUM MINIMUM
Figure1:MaximumandminimumfrequencyrecordedinNEWgrid
MaximumFrequency
MinimumFre uenc
8/6/2019 CERC Staff Paper
6/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
6|18
SR GRID MAXIMUM, MINIMUM FREQUENCY PLOT FROM APRIL-2001 ONWARDS
47.5
48.0
48.5
49.0
49.5
50.0
50.5
51.0
51.5
Apr-01
Sep-01
Mar-02
Sep-02
Mar-03
Sep-03
Mar-04
Sep-04
Mar-05
Sep-05
Mar-06
Sep-06
Mar-07
Aug-07
Feb-08
Aug-08
Feb-09
Aug-09
Feb-10
Aug-10
Feb-11
DAY ---->
FREQUENCY
IN
HZ--->
MAXIMUM MINIMUM
Figure2:MaximumandMinimumfrequencyrecordedinSRgrid
5. SignificantdevelopmentsandconcernsinIndiangridinnearfutureThepowersysteminIndiaisexpandingatafastpacetomeettherequirementsofIndianeconomy.Few
significantdevelopmentsinthepowersystemthatnecessitatediscussiononthefrequencystandardsin
theIndiangridhavebeenhighlightedbelow.
a) GrowingsizeofInterconnectionIndian grid is presently demarcated into five regional grids. Four out of the five grids (except
Southern Grid) are operating in synchronism since August 2006. There are plans to integrate the
Southern Grid with the rest of the grid through synchronous ties in near future (presently it is
through asynchronous HVDC link). Indian grid is also striving to expand by establishing
interconnectionwithneighbouringcountries.Bhutanisalreadysynchronouslyinterconnectedwhile
NepalhasseveralasynchronoustieswiththeIndiangrid(ACradiallinks).Aprojectforestablishing
asynchronous ties with Bangladesh through HVDC backtoback link is already under progress. A
MaximumFre uenc
MinimumFrequency
8/6/2019 CERC Staff Paper
7/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
7|18
tighter operating band for frequency is essential for secure operation of a large synchronous
interconnection.
b) SizeofGeneratingUnitsandgenerationcomplexPresently the size of the largest generating unit in India is 660 MW and very soon 800 MW unit
(Mundra UMPP) and 1000 MW unit (Nuclear unit at Kudunkulam) are also expected to be
synchronized.
Table4:Populationofdifferentsizeofgenerators
SNo. UnitSize Numberofunits
1 800MW and>800MW Expectedsoon
2 660MW 2
3 600MW 4
4 540/500/490MW 45
5 300/330/380MW 13
6 250/210/200MW 244
7 140/150/170/185MW 74
8 100/110/120MW 205
9 Lessthan100MW 983
10 Total 1570
Table5:Numberoflargegenerationcomplex
SNo. Sizeofgenerationcomplex Number
1 4000MWandabove UMPPsexpectedsoon
2 2000MWto4000MW 7
3 1000MWto2000MW 36
4 Below1000MW 325
5
Total
368
8/6/2019 CERC Staff Paper
8/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
8|18
Table6:Incidentsofcompletepowerstationtrip(May2010toJan2011)
S
No.
Generation
loss Number
of
instances
1 >2000MW TrippingofstationssuchasKorbaand
VindhyachalbeforeMay2010
2 1000MWto2000MW 4
3 500MWto1000MW 3
The system is generally planned for outage of single largest unit outage. However number of
incidentswherethecompletepowerstationhastrippedisalsosignificantlyhigh.Infactalmostall
largepowerstationsinthecountryhavegoneunderforcedoutageatleastonce.Thegridfrequency
needs to be maintained at level so that the system is able to bear the impact of such large but
credible contingencies, even if it is with the help of suitable protection schemes such as load
sheddingschemes initiatedbyUnder frequency,RateofChangeof frequencyandUnderVoltage.
Thesettingofautomatic loadsheddingthroughunderfrequencyandrateofchangeoffrequency
relaysisshowninTablesbelow.
Table7:UnderFrequencyRelaysettingsadoptedinIndia
Region StageI StageII StageIII
NorthernRegion 48.8 Hz 48.6Hz 48.2Hz
WesternRegion 48.8Hz 48.6Hz 48.2Hz
EasternRegion 48.5Hz 48.2Hz 48.0Hz
Northeasternregion 48.8Hz 48.5Hz 48.2Hz
SouthernRegion 48.8Hz 48.5Hz 48.2Hz
8/6/2019 CERC Staff Paper
9/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
9|18
Table8:RateofChangeofFrequencyRelaysettingadoptedinIndiangrid
Region StageI StageII StageIII
NR 0.1Hzpersecand49.9Hz 0.2Hzpersecand49.9Hz 0.2Hzpersecand49.9Hz
WR 0.1Hzpersecand49.9Hz 0.2Hzpersecand49.9Hz
SR 0.3Hzpersecand49.5Hz
(Alarm)
0.3Hz persecand49.3Hz
(Trip)
c) GrowingexpectationsofconsumersAlargeinterconnectioncaterstoadiversecategoryofconsumers.Anarrowoperatingrangeforgrid
frequency significantly reduces wear and tear in electrical machines and thus increases their life.
Moreover, with the increase in the proportion of sophisticated consumer loads such as process
industries,tractionlocomotivesandsiliconloadstheexpectationofabetterpowerqualityfromthe
gridisalsorising.
d) ImpactoffrequencyonvoltageIt has been observed from studies that increase in frequency results in increase in voltage and
decreaseinfrequencyresultsindecreaseinvoltage.InNortherngridithasbeenobservedthatone
Hzfrequency increase/decrease isequivalentto8kV increaseordecrease involtage. Thiswould
haveasignificantimpactontransmissionlossesandefficiencyinthegrid.
8/6/2019 CERC Staff Paper
10/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
10|18
Figure3:Impactofgridfrequencyongridvoltage
a) FrequencyfluctuationsandprimaryresponsefromgeneratorsIthasbeenobservedthat thepowernumber inNEWgridandSRgrid is1800MWperHertzand
1020MW per Hertz respectively. Tighteningof frequencyband by0.1 Hz may imply reduction in
demand met by approximately 180 MW in NEW Grid and approximately 102 MW in SR Grid.
However, grid operation within a narrow range would encourage utilities to provide primary
responsefromtheirgenerators.Thiswouldhelp inarrestingthewidevariations infrequencyand
network loadings during sudden change in injection/withdrawal from the grid. Thus improved
securityandefficiencygainsobtainedthroughtighteningoffrequencybandaremuchlarger.
b) VolumeofunscheduledInterchangeAfrequencydependentunscheduled interchangemechanism is inplace inthe Indiangrid.Awide
operating range of frequency creates room for large volume of unscheduled interchanges. The
volumeofUIandtheScheduledInterchangesisshowninfigurebelow.
8/6/2019 CERC Staff Paper
11/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
11|18
Figure4:VolumeofScheduledinterchangeandUnscheduledInterchange
Several market players participate in the Indian market with a highly unbalanced portfolio. The
unpredictability inthebehaviourofsuchmarketplayershasserious implications forgridsecurity.
ThereforeCERChastakenseveralinitiativestoencouragemarketplayerstoshiftfromUnscheduled
InterchangetoScheduledInterchange.
8/6/2019 CERC Staff Paper
12/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
12|18
Figure5:TrendofweightedAveragePrices
A comparison of UI rate with the weighted average energy price in the bilateral and collective
transactions intheNEWgridrevealsthattheUIratehasbeen lowerthanthenegotiatedprice in
bilateral transactions and the discovered price in the Power Exchange. This is a positive
developmentandimpliesthatbuyersarewillingtopayapremiumforscheduledinterchangethat
provides higher certainty. Therefore it is desirable to encourage the reliance on scheduled
interchange through the available price signals and by enforcement of the UI volumes cap as
mandated in the CERC regulations on Unscheduled Interchanges. The SERCs could also consider
similarmeasures.
c) IntegrationofrenewableenergyIntegrationofrenewableenergyinthegridisoneofthebiggestthrustareas.Thecontributionfrom
windenergyishighestintherenewableportfolio.Theinstalledwindgenerationcapacityason30th
Sep 2010 is 6070 MW. This is expected to be 13065 MW by Dec 2012. Considering the high
8/6/2019 CERC Staff Paper
13/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
13|18
variabilityandunpredictabilityofgenerationfromrenewable,theinjectionfromwindenergycanbe
safelyabsorbedinthegridonlyifthefrequencyinthegridismaintainedinacomfortablerange.
d) SimulationandmodellingThe focus in power system and electricity market operation planning is gradually shifting from
empiricalstudiestoquantitativeanalysisusingsimulationsstudies.Thesoftwareusedinmodelling
generally assumes a stable frequency. A stable frequency regime would facilitate comparison of
simulatedandactualsystembehaviour.
2. ComparisonofpermissiblefrequencyinothercountriesandviewsinIndiaIt is evident from the previous sections that the wide range of permissible frequency by design has
economicaswellassecurityconcerns ina largegrid. Inthiscontext itthepermissibledeviationfrom
thenominalfrequencyprevailinginothercountrieshasbeenexaminedandisshownisTablebelow.
Table9:PermissibleFrequencybandinothercountries
Country/Interconnection Nominal
frequency
(Hz)
PermissibleFrequency
Band(Hz)
Permissible
Deviation(%)
EasternInterconnection(US) 60 59.95 60.05 +/0.083%
Nordiccountries 50 49.9 50.1 +/ 0.2%
WesternInterconnection(US) 60 59.856to60.144 +/0.24%
Europe 50 49.8 50.2 +/ 0.4%
India 50 49.550.2 1%/+0.4%
OtherSAARCcountries 50 49.5 50.5 +/ 1%
The intent of CERC on the desirable frequency band as mentioned in CERC order on ABT dated 4th
January2000.
8/6/2019 CERC Staff Paper
14/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
14|18
Quote
5.9.8Anotherpointforconsiderationiswhetherchargesforoverdrawalshouldbethesameat49.0
Hzandevenbelow49.0Hz. It shouldbenoted that thedeclaredfrequency in India is50Hz.An
integratedpowersystemshouldoperatewithagridfrequencyhoveringaround50Hz. Inpractice
however, thefrequency range in India has been 48.5 Hz to 50.00 Hz. This is not desirablefor
achieving interconnected/integrated operation of the grid. With the additions to generation
capacities, it ishopedthattheremaynotbeadropbelow49Hz.. Infacttheattempt
should be to further narrow down the range with more generating capacities coming up and
redundancycreated.
Unquote
The issue also finds a mention in the Minutes of Meeting of 4th Coordination Forum held on 17th
August2009
Quote
It was highlighted in the presentation that low frequency situations are also resulting in sub
standardgridvoltages.Afterthediscussion,it was generallyfeltthattherewasaneedtofurther
narrowdownthepermissiblefrequencyrangefrom49.5Hzto50.3Hzw.e.f.January2010andfrom
49.8Hzto50.2Hzw.e.f.January2011.
Unquote
3. IssuesfordiscussionwithrespecttotighteningoffrequencybandTheissuesthatneedtobediscussedareasbelow:
a) Tighteningofoperatingfrequencybandisdesirable Whatshouldbenextoperatingrangeforfrequency?
Presentlytheoperatingrangeis49.5to50.2Hz
8/6/2019 CERC Staff Paper
15/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
15|18
SuggestedsolutionbyCERCstaff
Inyear2011 : 49.7to50.2HzwithaStepSizeof0.01Hz
Inyear2012 : 49.8to50.1HzwithaStepSizeof0.01Hz
DeviationsfromscheduleareinevitableandthedeviationsfromschedulewouldbesettledattheUIrate.WhatshouldbethepermissiblevolumeofUnscheduledInterchangeforacontrol
areaasapercentageofitsschedule?
Nochangeproposed.
4. OtherissuesrelatedtogridsecurityPowerSystemvisualizationandsituationalawarenessarevitalfordecisionmakingatthecontrolcentre.
This requires reliable and fast communication between the generating stations/substations and the
control centre. With the rapid expansion in the power system infrastructure in India a robust
communicationinfrastructureisalsorequiredforpowersystemoperationandcontrol.Themajorissue
inthisregardistheurgentneedforanexclusiveRegulationoncommunicationsystemforPowerSector
x
8/6/2019 CERC Staff Paper
16/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
16|18
References
a. CEA,17thElectricPowerSurveyb. CEA,PowerScenarioataGlance,January2011c. IndianElectricityRules1956,asamendedupto25thNovember2000d. CERC,IndianElectricityGridCodeRegulation2010,April2010e. CERC,UnscheduledInterchangechargesandRelatedMattersregulations,2010f. NREB,ReportoftheTaskForceonFrequencyControl,December1992g. DwarkaNath,UnderfrequencyTrendrelayasPowerSystemSaviour,InternationalSeminaronGridStabilityandLoad
Management,Nagpur,January1996
h. NRPC,ReportoftheSubgroupconstitutedbyNorthernRegionOperationCoordinationSubcommitteetoreviewUnderFrequencySchemeinNorthernRegion,January2005
i. CERC,AnnualReportoftheMarketMonitoringCellofCERC,2009j. S.K. Sooneeetal., FrequencyResponseCharacteristicsofan InterconnectedPower SystemACase StudyofRegional
GridsinIndia,6thInternationalR&DConferenceonSustainableDevelopmentofWaterandEnergyResources,February
2007
k. S.K.Sooneeetal.,ReactivePowerandSystemfrequencyRelationshipaCaseStudy,7thInternationalR&DConference,February2009
l. CERCorderonABT,January2000m.Minutesof4thCoordinationCommitteeMeeting,August2009
8/6/2019 CERC Staff Paper
17/18
8/6/2019 CERC Staff Paper
18/18
GridSecurityNeedForTighteningofFrequencyBand&OtherMeasure
18|18