Upload
laddie
View
35
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Case Study on Increasing the Transport Capacity of 220 kv d.c. OHL Iernut-Baia Mare by Reconductoring, using LM Technologies Dr. Ilie ARDELEAN 1 Marius OLTEAN 2 , Dr. George FLOREA 3 , Elena MATEESCU 4 , Daniel MĂRGINEAN 4 Prof. dr. Ştefan KILYENI 5 , As. dr. Constantin BĂRBULESCU 5 - PowerPoint PPT Presentation
Citation preview
Case Study on Increasing the Transport Capacity of 220 kv d.c. OHL Iernut-Baia Mare by Reconductoring,
using LM Technologies
Dr. Ilie ARDELEAN 1 Marius OLTEAN 2, Dr. George FLOREA 3, Elena MATEESCU 4, Daniel MĂRGINEAN 4
Prof. dr. Ştefan KILYENI 5, As. dr. Constantin BĂRBULESCU 5
1 Romanian Power Grid Company C.N.T.E.E. “Transelectrica” SA, Timişoara Subsidiary, Romania2 C.N.T.E.E. “Transelectrica” SA SMART SA, Sibiu Branch, 3 Tehnorob SRL, Bucharest, 4 Fichtner, Romania,
5 “Politehnica” University of Timişoara, Faculty of Electrical and Power Engineering, Power Systems Department
1/27
1. Introduction2. OHL identification in the West part of NPG, in which the reconductoring has maximum efficiency3. Adopted reconductoring solutions and types of conductors used4. LM technologies proposed for implementation5. Evaluation of economical efficiency of reconductoring6. Conclusions
Content
2/27
1. Introduction
New OHL - difficulties in obtaining land for clearway
Arguments for increased transport capacity of existing OHL - increasing power consumption - connection new renewable sources (wind) to NPG - network congestions
Solutions to increase transmission capacity of the OHL - uprating: - increasing the current value - increasing the voltage value - increasing both values of current and voltage
3/27
Summary of key methods and instruments used to increase OHL capacity - Table 1
1. Introduction
Table 1
4/27
2. OHL identification in the West part of NPG, in which the reconductoring has maximum efficiency
Software tool is designed in Matlab environment enjoying the entire characteristics specific to Microsoft Windows operating systems, having a user friendly interface
The flowchart is presented in Fig. 1
Fig. 1
5/27
2. OHL identification in the West part of NPG, in which the reconductoring has maximum efficiency
Report generated by the software application – Fig. 2
For the case of each congested branch, two kind of information are available:
- the sample containing the congested branch - the scenarios leading to the issues pointed-out
Fig. 2
6/27
2. OHL identification in the West part of NPG, in which the reconductoring has maximum efficiency
XPF_ DJ1185
P.D.FIE28004
P.D.F.B28046
TR.SEV28048
CETATE128050
CALAFAT28051
TR.S.ES28719
CETATE29102
CALAFAT28709
RESITA28052
IAZ 1
RESITA B28730
IAZ A28736
28054
TIMIS28071
TIMIS A
1 2
SACALAZ28070
SACALAZ28756
ARAD28069
ARAD28008
XSA_ AR1175
ARAD B28775
ARAD A28774
URECHESI28002
URECHESI28045
TG.J IU28062
URECHEST28694
PAROSEN28063
BARU M28064
HAJD OT.28065
BARU MA28800
HASDAT28795
2
1R.MARE28914
PESTIS28066
MINTIA B28068
PESTIS28792
MINTIA28003
MINTIA A28067
LOTRU28040
SIBIU28100
2
1
LOTRU28562
SIBIU28034
1
2
SIBIU S
SIBIU SB28537
28538
P.D.F.A28047
1 2
TR.SEV28049
28729RESITA A
IAZ 228053
IAZ B28737
28746 28747TIMIS B
ORAD I I28839
BAIA MA328484
BAIA MA28485
BAIA M.28093
ROSIORI28094
ORADEA28096
ROSIORI28039
XRO_ MU1184
1
2
VETIS28095
VETIS28491
GADALIN28037
CLUJ E28038CLUJ ES
28509
IERNUT28087
UNGHENI28086
IERNUT28036
UNGHE.A28459
UNGHE.B28460
IERNUT28524
CUPT.C.T28088
1
2
1
2
MINTIA28787
12
P.D.F 429192
P.D.F 329191
P.D.F 229190
P.D.F 529193
P.D.F 129189 P.D.F.6
29250
MINTIA 529169
MINTIA 329260
MINTIA 629262
PAROSEN28808
RETEZAT129162
ROVIN 529119
ROVIN 629120
ROVIN 329121
ROVIN 429238
ROVIN 729455
IERNUT 529159
IERNUT 629160
LOTRU 129232
LOTRU 229233
MINTIA 129167
111.5 MW 8.1 MVR 111.5 MW
8.1 MVR
-7 MVR 111.5 MW
-7 MVR 111.5 MW
-7 MVR 111.5 MW -7 MVR
111.5 MW
269 MW 109 MVR 109 MVR
229.6 MW 258.3 MW 47.2 MVR
0 MW 0 MVR
0 MW 0 MVR
327.9 MW -22.3 MVR
629.7 MW -66.4 MVR
91.2 MW 41.6 MVR
61.6 MW -16.6 MVR
228.4 MW 73.5 MVR
277.1 MW -14.9 MVR
123.2 MW 5.0 MVR
16.9 MVR 1.0 MW
99.0 MW -11.3 MVR
98.2 MW-11.4 MVR
193 MW 118 MVR
193 MW 111 MVR
72.3 MW -12.4 MVR
157.6 MW 21.9 MVR
150.8 MW 21.7 MVR
150.0 MW 22.1 MVR
0.0 MW 0.0 MVR
20 MVR
59.2 MW
21.3 MVR 39.3 MW 66.0 MW
0.4 MVR
-12 MVR 14.8 MW
3.4 MVR 7.4 MW 18.7 MW
-11.1 MVR
-27 MVR 81.8 MW
57 MW 15.2 MVR
26 MW 19.8 MVR
63.6 MW 7.1 MVR
75.0 MW 10.8 MVR
1.2 MW 0.6 MVR
79.2 MW 9.1 MVR
43.8 MW 3.6 MVR
53.8 MW 65.5 MVR
70 MW 6 MVR
84.8 MW 46.9 MVR
18.6 MW 6.1 MVR
25.7 MW -4.4 MVR
45.4 MW -8.0 MVR
8 MVR 39.8 MW
47.4 MW 7.2 MVR
6.2 MW -1.4 MVR
55.8 MW 9.5 MVR
15.9 MW 2.7 MVR
26.7 MW 3.9 MVR
59.2 MW 12.9 MVR
16.1 MW -0.7 MVR
71.0 MW 12.5 MVR
57.1 MW 12.3 MVR
50.6 MW -0.1 MVR 78.9 MW
18.2 MVR
52.1 MW 14.3 MVR
17.5 MW -11.7 MVR
85.1 MW 21.1 MVR
82.5 MW -3.2 MVR
0.6 MVR 113.8 MW
89.2 MW -1.4 MVR
0 MW -0.9 MVR
50.1 MW 19.1 MVR
48.9 MW 18.7 MVR
0.5 MW 0.0 MVR
87.2 MW 16.5 MVR
25.5 MW 4.7 MVR
51.7 MW 7.7 MVR
62.6 MW 22.8 MVR
23.8 MW 10.9 MVR
17.8 MW 9.9 MVR
-60 MVR 219.8 MW
-57.2 MVR
10.1 MW 1.5 MVR
21.9 MW 3.0 MVR
-100.6 MVR
-179.2 MVR
-96.6 MVR
86%
85%
The case study is carried-out for the West and South-West side of the Romanian Power System – Fig. 3
It has 88 buses and 107 branches The power system is operated by the
Romanian Power Grid Company Transelectrica, Timisoara Subsidiary and partially by Craiova and Cluj-Napoca subsidiaries.
Fig. 3
7/27
2. OHL identification in the West part of NPG, in which the reconductoring has maximum efficiency
The analyses have been performed for 1000 samples, each sample representing an individual operating condition. Based on the analyses the following OHLs have been selected:
- 220 kV OHL Iernut-Baia Mare;- 220 kV OHL Portile de Fier-Resita.
The beginning of the works at 400 kV corridor Portile de Fier-Resita-Timisoara-Arad and the tie-line with the Serbian power system (Resita-Pancevo) represent a case in point
Iernut-Baia Mare 220 kV OHL has been selected having the maximum reconductoring efficiency
8/27
Structural characteristics of the selected OHL are:
• putting into operation 1969• total length 162.4 km• no.towers 480 pcs. (of which: normal suspension 387 pcs., special suspension 15
pcs., tension 78 pcs.)• towers names type SNY, SSY, ICNY, INY, ICN, ICT• active conductor Al/Ol 450/75 mm2
• shield conductors: 1-55 dead end and 64-122 dead end St 70 mm2; 55-64 terminals St 95 mm2
• insulation CTS 120-2P şi CTS 160 (glass insulators with 146 mm, respectively 170 mm heights).
3. Adopted reconductoring solutions and types of conductors used
9/27
3. Adopted reconductoring solutions and types of conductors used
HTLS types of conductors that are currently on the market, are summarized in Table 2
Table 2
10/27
3. Adopted reconductoring solutions and types of conductors used
On existing lines, increased transmission capacity is restricted by the existing structure security. To maintain safe operation of the line, reusing the towers and insulator chains, in case of using unconventional conductors (compact, HTLS), the next restrictions must be followed:
The new conductor diameter must be less or equal then the existing conductor diameter (29,25 mm)
The maximum horizontal traction of the new conductor, must not exceed the existing conductor traction (Tmax = 5362 daN), in order to reduce the impact against the poles and foundations
The final sag of the new conductor, at maximum operating temperature, to be limited to the final arrow of existing ACSR type conductor 450/75 mm2
The breaking force of the new conductor should be greater or at least equal with the existing conductor AlOl type 450/75 mm2
Electrical distances must be maintained
11/27
3. Adopted reconductoring solutions and types of conductors used
The main technical and physical data of conductors selected for analysis – Table 3
Table 3
12/27
3. Adopted reconductoring solutions and types of conductors used
Physical parameters for HTLS conductors – Table 4
Table 4
13/27
3. Adopted reconductoring solutions and types of conductors used
Real carrying capacity for HTLS conductors– Table 5
Table 5
14/27
4. LM technologies proposed for implementation
Critical circuits reconductoring, a solution with clear benefits, which may increase thermic capacity twice or more, faces two major obstacles:
involved towers, in most cases, have the life span very high (close to the lifetime) and if the maintenance works were not made under the rules, they will be repaired and strengthened
circuits which have the greatest need to be reconductorated are usually the most difficult to be withdrawn from operation.
If you can’t find a way to achieve LMT for the whole work, it is necessary to find combined technologies with which to achieve reconductoring works with the line withdrawn from service and into a short a period of time.
15/27
4. LM technologies proposed for implementation
Taking into account the existing technologies at this time in Romania and the existing facilities, there are imposed some restrictions in applying the live-line technologies to this line:
there can’t be done works at the towers on the middle phase on 220 kV single circuit OHL
there can’t be performed works on the energized upper phases, on double circuit segment of that line (towers 470-472)
For this reason the live-line technology will be applied only to two of the three phases of the line. Preparatory work that can be done under voltage:
vibration dampers removal clamps replacement at the lower roller yokes final work that can be done live-line:
- vibration damper installation- suspension clamps mounting (clamping)
16/27
4. LM technologies proposed for implementation
Reconductoring deployment sequence work and line status - Table 6
Table 6
17/27
4. LM technologies proposed for implementation
The live-line progress of work necessarily involves attending the following:
determining atmospheric conditions at the workplace by the Head of works preparation of ladder and chair equipping workers climbing on the poles with the conductive material suits and
shoes with electroconductive soles training employees in the team and the allocation of duties undervoltage working authorization signature by all team members mounting the trolley at climbing pole worker shift from the trolley to phase wire trolley movement, directed from the ground with rope guidance truck passing on a support pole removing the trolley at descent pole completion of the work
18/27
5. Evaluation of economical efficiency of reconductoring
For economic analysis of possible solutions of reconductoring with increased transportation capacity conductors were compared the variants with conductors who met the necessary technical conditions to achieve a corresponding increase in transmission capacity. In this analysis were examined two components: direct costs and maintenance total cost respectively cost of energy losses.
All costs below are calculated for a kilometer of three-phase circuit, equipped with one conductor per phase.
In Table 7 are shown power losses calculation for different types of conductors.
Table 7
19/27
5. Evaluation of economical efficiency of reconductoring
Using a conductor with a specific resistance lower gives two advantages: lower losses and reduced operating temperature. Power losses values per unit in MW/km are shown in Fig. 4.
Fig. 4
20/27
5. Evaluation of economical efficiency of reconductoring
Taking into account (maximum) a carried power of 480 MVA for 8760 hours per year, present value of power losses for 30 years, with a discount rate of 8%, is shown in Fig. 5.
Fig. 5
1052218
1482856
12791091143439
913862
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
Eur
o/km
ACSS ZTACIR GZTACSR ACCR ACCC/TW
Actualized costs of power losses
21/27
5. Evaluation of economical efficiency of reconductoring
Total direct costs, including procurement, installation and maintenance upgrade, according to Fig. 6, are the lowest for ACSS conductor followed by GZTACSR.
Fig. 6
46980
8310089200
217000
144900
0
50000
100000
150000
200000
250000
Eu
ro/k
m
ACSS ZTACIR GZTACSR ACCR ACCC/TW
Conductor
Direct costs (Euro/km)
22/27
5. Evaluation of economical efficiency of reconductoring
Finally the comparison of total costs (cost of losses + direct costs), as shown in Fig. 7 reveals that the ACSS and ACCC/TW are the most recommended conductors suitable for the examined case.
Fig. 7
1099200
1566000
1368300 1360600
1058700
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
Eu
ro/k
m
ACSS ZTACIR GZTACSR ACCR ACCC/TW
Actualized total cost (direct + losses)
23/27
The software tool developed by the authors is designed for congestion management. It corresponds to the actual operating conditions, represented by the deregulated environment. Within the paper the results are used as an application for the reconductoring process
Based on the analyses performed using the software two OHLs have been identified as candidates. One of them is suitable for reconductoring, having the highest efficiency
The usage of HTLS type conductors on the 220 kV OHL Iernut-Baia Mare is technically feasible; all analyzed conductors, less TACSR, may be used, having a sag equal or less than the current one, but with a higher thermal current
Similar diameters of wires lead to wind forces similar to those for which the line was designed and achieve a minimal visual impact
The growth of thermal current implies an increase in the values of the magnetic field, but below the amount prescribed by the ICNIRP
6. Conclusions
24/27
The ACCC and ACCR conductors, composite types, have the best mechanical and electrical pair of values characteristics; they are relatively new products on the market, are not yet widely used, and the direct cost is higher compared to other types
ZTACIR type conductors are used mainly in Japan and Korea, and the direct cost for hese conductors is lower than that of the composites ones. Given the normal frost deposits on the analysed OHL, these types of conductors can be considered as a feasible solution
GZTACSR type conductors can be considered feasible, subject to a special installation, the need for a training and a high maintenance
ACSS type conductors have the lower direct costs correlated with a good electrical resistance, installation and maintenance comparable to conventional ACSR conductors
ZTACIR type conductors are used mainly in Japan and Korea, and the direct cost for these conductors is lower than that of the composites ones. Given the normal frost deposits on the analysed OHL, these types of conductors can be considered as a feasible solution
6. Conclusions
25/27
about the direct costs of procurement, installation and maintenance, the ACSS conductor type stands in first place, followed by the GZTACSR and ZTACIR conductor
related to the costs of energy losses, the ACCC, ACSS and ACCR conductor types are located on top, in this order
for reconductoring of the 220 kV OHL Iernut-Baia Mare is proposed the ACSS conductor type
combined technology proposed for completion of the 220 kV OHL Iernut-Baia Mare 3 reconductoring greatly reduces the time of withdrawal operation.
6. Conclusions
26/27
Thank you for your attention !
27/27
Thank you for your attention !