Upload
trankiet
View
215
Download
2
Embed Size (px)
Citation preview
CCAARRIIBBBBEEAANN CCEENNTTRREE FFOORR DDEEVVEELLOOPPMMEENNTT AADDMMIINNIISSTTRRAATTIIOONN ((CCAARRIICCAADD))
CARIFORUM/EDF Project 8ACP/RCA 005
STRATEGIC PLANNING IN PUBLIC SERVICES
CASE REPORT
The application of Strategic Planning in the Office of the Chief Personnel Officer,
Trinidad and Tobago
A PROJECT OF CARFIORUM FUNDED UNDER THE 8TH EUROPEAN DEVELOPMENT FUND
ii
ACKNOWLEDGEMENT The CARIFORUM/EDF Project on Strategic Planning in Public Services is a three year project developed on behalf of the fifteen (15) independent countries in the Caribbean region1, known as the Forum of the Caribbean ACP States (CARIFORUM.) to support the enhancement and strengthening of institutional capacity within public service organisations for the application of strategic planning and management in order to enhance and improve the formulation, coordination and implementation of development policies and programmes The Project is funded by the 8th European Development Fund (FUND) for Regional Co-operation in the Caribbean and is managed by the European Commission Delegation in Barbados and the CARIFORUM Secretariat in Guyana. The Project is implemented by the Caribbean Centre for Development Administration (CARICAD). This Report was prepared by Mrs. Margaret Richardson of Trinidad and Tobago. The opinions expressed in the Report are those of the Consultant, and do not necessarily reflect the views of CARICAD, the European Commission Delegation, CARIFORUM, or any particular Government.
1 CARIFORUM Member States: Antigua and Barbuda, The Bahamas, Barbados, Belize, Dominica, Grenada, Guyana, Haiti, Jamaica, Saint Kitts and Nevis, Saint Lucia, Saint Vincent and the Grenadines, Suriname and Trinidad and Tobago.
iii
TABLE OF CONTENTS
Page Acknowledgement
Executive Summary i
Introduction Terms of Reference Format of study Governmental policy Background to policy
1
Strategic Planning in the Personnel Department Funding Stakeholders Level of participation Implementation Approach to the strategic planning activity Time frame for the activity
5
Strategic Plan of the Personnel Department Achieving results and evaluating progress Measurement of outcomes Benefits Unexpected outcomes Use and impact of strategic planning in the Personnel
Department Communicating the Plan Future of the project and its benefits Costs of strategic planning Lessons learnt Next steps
10
Recommended criteria for a common approach to Strategic Planning in the Public Service of Trinidad and Tobago
16
Conclusion
18
Appendices 19
CASE REPORT
The application of Strategic Planning in the Personnel Department (Office of the Chief Personnel Officer),
Trinidad and Tobago Executive Summary
The Personnel Department (Office of the Chief Personnel Officer) Trinidad
and Tobago commenced a strategic planning exercise in 2001. The objective
of the exercise, which began in January 2001, was to produce a three-year
Strategic Plan that would identify and describe the set of programmes and
projects in which the Department would be engaged during the life of the
Plan.
The exercise was set within an environment of public sector and national
transformation. In addition to its traditional role of managing industrial
relations issues in the Public Service, the Personnel Department had been
entrusted with responsibility for directing change in the Public Service in the
area of human resource management and had set itself the task of
transforming its own structure and operations in order to provide the
leadership and support that line agencies required to bring about their own
transformation. This led to a re-examination of the Department’s primary role
and functions and the technologies it utilised to achieve its objectives. In
other words, the Personnel Department needed to take whatever action was
necessary to stay relevant.
The Personnel Department is a conservative organisation, committed to
efficiency in the performance of its functions. The completion of a Strategic
Plan was viewed as a first step in ensuring that, as a central Human Resource
Agency, the Department was poised to provide the services that line agencies
required. In embarking on the process of strategic planning, the Personnel
Department utilised in-house resources: personnel who had the advantage of
ii
knowing, first hand, the people and the culture of the organisation and could
easily garner the trust of internal stakeholders.
The small team of officers designed and implemented an initial strategic
planning workshop with participants drawn from the Department’s leadership
structure. In an iterative process, inter-divisional meetings were planned to
obtain contributions from every member of staff and the information thus
generated formed the basis for the documentation that drove the process.
The CARIFORUM-sponsored Regional Workshop on Strategic Planning took
place during the period when the first draft of the Plan was being prepared,
and key information gleaned from the activity was imported into the Personnel
Department’s model to enhance the Department’s capacity to produce an
output that would achieve the long-term objective.
It was not the first time that the Personnel Department had attempted to
produce a Strategic Plan, nor was the idea of total staff participation new.
What was novel was the iterative approach which, though a time-consuming
and often frustrating experience, produced a result that was ultimately
satisfying and which sought to adhere faithfully to the suggestions and
recommendations made by staff members at all levels of the organisation.
The process began with workshops in which top management and senior
supervisors of the Department provided the preliminary inputs to the Plan.
Subsequent meetings at the division level added and refined information
which became part of the final document.
The Personnel Department’s Strategic Plan was presented in a project format
that displayed, at a glance, a listing of:
primary and functional sub-objectives;
performance goals;
time frames for implementation;
action plans;
responsibility centres;
iii
required resources; and
intended impact/outcomes.
The format (see Appendix III) made it easy to identify delays in the
achievement of stated objectives as it provided a road map to implementation.
Following the launch of the Strategic Plan, every Division identified as a
responsibility centre was required to prepare an implementation plan for the
coming year, identifying the steps and strategies planned for achieving the
outcomes listed.
Ownership of the preparatory process, subsequent implementation and
follow-up activities are critical for success. Ownership was provided by the
Chief Personnel Officer. Also important is the provision of resources
dedicated to monitoring and reporting on the performance of programmes and
projects. The resources came in the form of two in-house teams: the
Strategic Plan Monitoring Team (SPMT) and the Process Improvement Team
(PIT), both comprising representatives from all Divisions of the Personnel
Department. Both teams meet monthly under the leadership of the Deputy
Chief Personnel Officer and formulate plans to bring effectiveness to the
Strategic Plan implementation process.
The benefits of strategic planning to the Personnel Department cannot be
overstated. At the operational level, programme planning has become more
focussed and consistent. At the financial level, justification for requesting
funding for programmes and projects is more credible so that the Ministry of
Finance provides funds more readily. At the personal and professional levels,
new skills have been learnt that can be applied to a range of other functions;
attitudes and approaches to strategic and long-term planning have changed to
create employees who are better equipped to manage their own activities and
support the growth and development of the organisation.
iv
At the same time, however, there were flaws in the process that slowed
implementation. Assumptions were made that adequate staffing would be
available; this did not materialise, as plans to acquire additional
accommodation fell through. Another assumption was that all “leaders” in the
organisation were in agreement with the planned direction. This erroneous
assumption led to the Department’s devoting inadequate time and resources
building commitment to the implementation of critical activities.
The Department must now begin to review its direction in light of the fact that
the change in political administration has brought with it a new philosophy and
different time horizons. Preparations for the new Strategic Plan must begin
now.
The Personnel Department has learnt several lessons from this experience;
primary among them is the need to develop strategies and instruments to
measure each phase of the process, and to plan for resistance from core
groups. The Department has also learnt the value of dedicating resources
exclusively to the exercise from planning through documentation to follow-up
and evaluation.
CASE REPORT
The application of Strategic Planning in the Personnel Department (Office of the Chief Personnel Officer),
Trinidad and Tobago Introduction The traditional role of the Personnel Department is enshrined in legislation.2
The Department’s responsibilities as stated in the Civil Service Act are:
1. to maintain the classification of the Civil Service and to keep under
review the remuneration payable to civil servants;
2. to administer the general regulations respecting the Civil Service;
3. to provide for and establish procedures for consultation and
negotiation between the Personnel Department and an appropriate
association or associations in respect of:
i. the classification of offices;
ii. any grievances;
iii. remuneration; and
iv. the terms and conditions of employment.
For most of its existence, the Department maintained a structure that
supported the discharge of those responsibilities and a cadre of employees
skilled in the functions. The Department’s mandate was for the management
and administration of Industrial Relations, primarily engaging in negotiations
with recognised Associations/Unions representing Public Officers. In 1997,
Cabinet approved a new organisational structure for the Department,
designed to allow it to function as a Central Human Resource Management
Agency. The new role involved a transition from the responsibilities listed
above to those related to the formulation of human resource policy and the
provision of advisory, consultative and monitoring functions in respect of the
Human Resource Management Units being established in line agencies
throughout the Public Service. The responsibilities associated with this new
role are as follows: 2 For further information, see the Civil Service Act, Chapter 23:01 of the Laws of the Republic of Trinidad and Tobago.
2
• To formulate policy in all areas of human resource management,
including those which had not been addressed previously, such as
Human Resource Planning, Succession Planning and Career
Planning.
• To establish/review the legal and regulatory framework for human
resource management in the Public Service.
• To provide advisory and consultative services in the sphere of
human resource management to line agencies.
• To monitor and audit the practice of human resource management
by the human resource management units established in line
agencies.
Carrying out the range of new functions required a shift in thinking at the
strategic level and the development of new technologies and competencies to
effect operational effectiveness.
Terms of Reference
In 2001, one of a series of regional training activities, sponsored by CARICAD
under its Strategic Planning in Public Services Project, was conducted in
Trinidad and Tobago to provide participants, drawn from the public service
agencies of seven territories, with the knowledge and basic tools needed for
the development of strategic plans in their Ministries/Departments.
The specific objectives of the training workshop were:
1. to review and examine major principles in the area of strategic
planning;
2. to provide hands-on experience with the various components of
strategic planning;
3. to explore the benefits and consequences of strategic planning
methods and systems applied to public sector institutions;
3
4. to identify critical success factors which ought to be considered when
promoting the adoption of strategic planning methods in public sector
institutions/agencies;
5. to present relevant experiences on the impact of strategic planning
methods on organisation and individual performance of public sector
and/or private sector organisations.
At the time of the workshop, the Personnel Department had already embarked
on the exercise of developing a strategic plan for the agency. New
information and different areas of focus gleaned from the training were
incorporated into the activity and complemented the end product.
This case study outlines the Personnel Department’s strategic planning
process, taking into account the impact of the training provided by CARICAD,
and examining the successes and challenges of the exercise.
Format of the study
This case study will discuss the factors that led the Personnel Department to
embark on a course of strategic planning and the activities that culminated in
the production of a Strategic Plan encompassing a set of programmes for
whose accomplishment Divisions of the Department had responsibility.
Government’s policy
In 1996, Cabinet directed all public service agencies to conduct a strategic
review to give consideration to rationalisation, restructuring and
decentralisation. The review, which was to be self-administered, though
guided and supported by the consultancy arms of the Ministry of Public
Administration and Information, would remain under the management of the
individual Ministry and Department, which would take responsibility for its own
4
outputs and outcomes.3 A successor Cabinet Minute in 1999 mandated the
use of the results of the strategic review to aid the practice of Strategic
Human Resource Management throughout the Public Service.4
Ministries and Departments had also been mandated, in 1998, to develop
strategic plans as a prerequisite to submitting requests to the Ministry of
Finance for the allocations of operating budgets for subsequent fiscal years.
The Ministry of Finance Call Circular of 1998 advised the Heads of Ministries,
Departments and other Government agencies that their budget proposals
must be linked to their 1999 plans, programmes and projects. The plans,
“whether described as Strategic Plans, Operational Plans or Action Plans”
had to “reflect serious and studied attention to the Medium Term Macro
Economic Planning Framework 1998-2000 and to the Public Sector
Investment Programme as Government’s priorities and strategic direction for
socio-economic development of the country”.5
Background to the policy
Prior to 1996, submissions for funding from the Ministry of Finance under the
annual recurrent budget were, for the most part, arbitrary, with most Ministries
and Departments repeating the previous year’s requests and adding a small
percentage increase to cater for inflation and the practice of the Budget
Division to reduce allocations. The continued use of line item budgeting
allowed for the submission of annual “shopping lists” that often bore little
resemblance to the reality of an agency’s strategic and/or operational
objectives for the fiscal year.
3 For more information, see Cabinet Minute No. 2147 dated August 22, 1996: “Strategic Review of the Public Service involving Considerations of Rationalization, Restructuring and Decentralization”. Cabinet Secretariat, Office of the Prime Minister, Trinidad and Tobago, 1996. 4 Cabinet Minute No. 1462 dated June 10, 1999: “Cost Effective Human Resource Management in Line Ministries/Departments in the Context of the Strategic Review of the Public Service”. Cabinet Secretariat, Office of the Prime Minister, Trinidad and Tobago, 1999. 5 Minister of Finance: Circular No. 5. “Draft Estimates of Revenue and Expenditure including the Income and Expenditure of Statutory Boards and similar Bodies and of the Tobago House of Assembly for the year 1999”. Ministry of Finance. Port of Spain, Trinidad and Tobago, May 20, 1998.
5
The intention of the directive was to:
• develop a strategic planning culture in the Public Service;
• provide support for proposed changes to the financial management
system away from line item budgeting;
• initiate the practice, in Ministries and Departments, of costing all
activities to be undertaken over a defined period.
The operations of the Public Service of Trinidad and Tobago were still, at that
time, set against the backdrop of structural adjustment and the Government’s
need to comply with the conditionalities of the international financial
institutions which included reductions in the cost of managing the public
sector. The reality of debt servicing, a lower foreign exchange reserves and
other financial and social stringencies associated with structural adjustment
imposed upon the government and the management of the Public Service
responsibility for the establishment of mechanisms for efficiency and cost-
effectiveness in the sector.
Public Sector Reform activities were in train; discussions were being held with
key stakeholders to bring about changes in financial management,
administrative management and human resource management. It is to be
noted, however, that Human Resource Management, rather than Financial
Management, was the platform upon which the Public Sector Reform
movement was located.
Strategic Planning in the Personnel Department
Early approaches
Prior to the 1990s, strategic/corporate planning was not an activity in which
public service agencies routinely engaged, although it was understood to be
part of normal planning behaviour in the private sector. At that time, however,
the leadership of the Personnel Department began focussing on “new”
strategies for the management of the Department and the Public Service.
6
In 1991, the Department took the bold step of formulating its first strategic
plan to guide the organisation’s direction for a period of three years. The
planning began with an off-site Retreat in which all staff members met in
groups and engaged in structured interactive activity to analyse the
organisation and develop a focus for its future operations. At the end of the
Retreat, a team was formed to generate a document describing the planned
modernisation of the structure and operations of the Personnel Department
and to identify strategies (internally and externally focussed) for bringing
about the changes that would be necessary. In 1990/91, the Personnel
Department embarked on its first strategic planning exercise. The activity
began with a structured staff retreat aimed at generating the views of
members of staff and culminated in the development of a Mission Statement6
and a set of activities to be carried out during the life of the Plan.
The strategies depended heavily on the inputs of other public service
agencies that held responsibility for functions upon which the Personnel
Department’s activities were contingent. It also sought to formally address
issues of succession planning and career development, and paid particular
attention to the review of legislation to give effect to new structural
arrangements.
The Public Service Reform activities of the 1990s led to considerations of the
core staff agencies of the Public Service, namely the Service Commissions
Department and the Personnel Department, being designated Central Human
Resource Management Agencies, responsible primarily for policy formulation.
The Personnel Department decided to embark on a restructuring of the
organisation and its functions.
6 Mission statement: The mission of the Personnel Department is to develop and administer policies designed to provide adequate and equitable reward and compensation systems for Public Service employees, to satisfy their well-being, and to enable them to achieve desired performance levels. Strategic Plan of the Personnel Department 1991-1993. Port of Spain, Trinidad and Tobago.
7
In 1997, a series of workshops were conducted to pave the way for the
changes that were to be effected in the Personnel Department. These
workshops, internally co-ordinated, but facilitated by an external consultant,
were intended to assist, first the senior executives and, later, representatives
of staff groups in the organisation, in focussing their attention, not only on the
new set of functions to be performed in the restructured organisation, but also
on new approaches to performing traditional functions.7 The objective was to
“explore issues of transformation and to develop a vision and strategic
objectives for the Personnel Department”. Although there was, immediately,
little apparent outcome, the workshop, entitled “Charting the Way Forward”,
was instrumental in softening the attitudes of a large number of staff members
towards the changes that were imminent.8
Cabinet approved the plan for restructuring the Personnel Department in 1997
and the new structure became operational in 1998. A number of traditional
Personnel Department functions were devolved to line agencies, at about the
same time that the Public Service Commission began its approach to
delegating some of its own functions. In 1998, as well, Cabinet accepted the
report of a Committee appointed by the Minister of Public Administration and
Information to “facilitate the operationalising of Human Resource
Management Divisions in Ministries and Departments”9. The Personnel
Department and the Service Commissions Department were formally
designated Central Human Resource Management Agencies with
responsibility for creating the policies10 that would be implemented on the line,
and for monitoring and reviewing their implementation.
7 “Charting the Way Forward: a Workshop for Senior Executives and Staff of the restructured Personnel Department”. Personnel Department: Employee Development Division. Port of Spain, Trinidad and Tobago, 1997. 8 Ibid. At the end of the workshop, a small team of officers was mandated to compile all the information generated in the workshops and develop Vision and Mission statements and a set of Strategic Objectives for the Personnel Department. 9 See Cabinet Minute No. 600 of March 12, 1998. 10 The five Service Commissions (Public, Police, Teaching, Judicial and Legal and Statutory Authorities) have responsibility for staffing, discipline and termination of employment in respect of monthly-paid officers of the Public Service. The Personnel Department is responsible for the other human resource management functions.
8
Funding
The activities leading to the development of a Strategic Plan in the Personnel
Department were internally funded, that is, monies expended on sensitisation
seminars and other training activities were taken from the recurrent budget of
the Department. The individuals who led the effort were public officers who
either had ties to, or were staff members of, the Personnel Department.
Stakeholders
The immediate stakeholders of the exercise were staff members of the
Department. However, the stakeholders of the Personnel Department are
several. Like all public service agencies, Parliament and the Cabinet are
major stakeholders, as are Permanent Secretaries and staff members of all
Ministries, Departments and Statutory Authorities. The Personnel Department
has little direct association with members of the general public but, because of
the responsibilities legally assigned to it, the several Associations and Unions
representing public officers, the Ministry of Labour and the Industrial Court,
and the constitutional and other Commissions/Committees for which the
Department provides secretariat services are also critical stakeholders.
Level of participation in the process
The most recent strategic planning process of the Personnel Department was
a collaborative effort that allowed for the input of every member of staff of the
Personnel Department. The exercise commenced with the holding of a
Strategic Planning Workshop which targeted the top leadership levels and
staff representatives selected by their peers. All members of staff were
informed of the purpose of the workshop prior to its commencement and
requested to give consideration to issues pertaining to the strategic direction
for the Department.
At the workshop, environmental and organisational analyses of the Personnel
Department were conducted, utilising the tools of a stakeholder analysis and a
SWOT analysis. Draft statements of Vision, Mission and Core Values (the
Strategic Model) were generated, as well as preliminary conceptions of
strategic objectives. Subsequently, within each Division, the findings of the
9
workshop were disseminated and discussed, and suggested amendments put
forward. There followed an iterative process involving cycles of examination
and refinement of the Strategic Model by the target group of the workshop
(which then constituted the Strategic Planning Team), informed by
discussions held within Divisions. Out of that process was born the Strategic
Implementation Plan, designed to bring into reality the strategic model for the
Personnel Department.
Implementation
The Strategic Plan of the Personnel Department 2001-2004 was launched in
November 2001 in the presence of all members of staff and key stakeholders,
including representatives of the Ministry of Finance. The document was
presented in a project format with action plans detailing key objectives,
performance goals, time frames for completion, action steps, and areas of
primary responsibility, a listing of required resources and intended impacts
and outcomes. Thereafter, the Heads of Divisions of the Department began
the process of implementation as highlighted in the document, and teams
developed to monitor implementation began their work.
At the start of each year of the Plan, Divisions are required to prepare an
Action Plan detailing their activities in support of the programmes and projects
outlined and identifying potential challenges to implementation. Two in-house
teams monitor and report on the successes and failures/challenges
associated with the Action Plans. This will be discussed later in the case
study.
Approach to the strategic planning activity
Taking into account the purpose and anticipated direction of the organisation,
the Strategic Success Model11 of strategic planning was selected. This
approach highlighted environmental, organisational and opportunity scanning,
11 See Albrecht, Karl: “The Northbound Train: Finding the Purpose, Setting the Direction, Shaping the Destiny of your Organization”. The American Management Association (amacom). USA, 1994.
10
the development of a Vision, a Mission and a set of Core Values, and an
approach to action planning that would support implementation.
The approach used by the Personnel Department was similar to the one
recommended in the training workshop. A deviation in the process was the
omission, in the Personnel Department’s model, of stakeholder assessments
by the stakeholders themselves. This oversight must be corrected in any
future Plan, since assumptions by insiders of the beliefs of stakeholders
external to the organisation may be fundamentally flawed and are likely to
result in planned strategic outcomes that are inaccurate.
Also absent from the Personnel Department’s planning process was the
identification of Critical Success Domains (CSDs). This omission may well be
a reason for some of the Plan’s failures.
Time frame
The strategic planning process, which resulted in the Strategic Plan
document, was completed within ten calendar months.
Strategic Plan of the Personnel Department Achieving results and evaluating progress
A detailed programme of activities contained a breakout of the key activities
that were to be undertaken to achieve the strategic objectives of the
organisation, over the three years of its life, with corresponding time frames,
responsibility centres, required resources and intended outcomes and impact.
The implementation of the plan was to be built upon a strong foundation of
intra-departmental communication, co-operation and cross-divisional
teamwork.
It was understood that the driving force for implementation had to be top
management (the Chief Personnel Officer, the Deputy Chief Personnel Officer
and Heads of Divisions) of the Personnel Department. They would “own” the
process and display the commitment needed to keep the process alive and
provide the impetus for change. However, in order to ensure close and
11
continuous monitoring of the Department’s progress towards the performance
goals set out in the Implementation Plan, a Strategic Plan Monitoring Team
(SPMT) was established. The Team, headed by the Deputy Chief Personnel
Officer, included a representative from each Division. Its role was to set up
mechanisms for liaisons with the responsibility centres to ensure adherence to
agreed timeframes and for resolving any difficulties encountered during
implementation. The team meets monthly and reports on the progress of
implementation.
A second team is the Process Improvement Team (PIT) whose role is to
examine work processes employed throughout the Department and to make
recommendations for their improvement and/or redesign. The Process
Improvement team also reports to the Deputy Chief Personnel Officer.
The strategic objectives outlined in the Plan can only be realised through the
utilisation of a variety of resources, primary among them being human and
financial resources. As a result, the maintenance of optimal staffing levels is
essential, as is the development of improved competencies through in-house
training and education programmes. To this end, the Department’s Training
(HRD) Plan was created as a supporting document.
To ensure availability of financial resources, especially for costly initiatives,
programmes were undertaken on a project basis and funds secured under the
Public Sector Investment Programme (PSIP).
Measurement of outcomes
No criteria were developed to measure the outcome and impact of the
Personnel Department’s Strategic Plan during its lifespan. The Department
has achieved a number of successes but, at the same time, a several planned
initiatives have not materialised. The development and use of measurement
criteria would have given early warning of weaknesses in the Plan.
12
Benefits
An obvious benefit of the strategic planning activities of the Personnel
Department has been improvements in funding both at the recurrent and the
project levels. A less overt benefit has been changes in the attitude of staff
members at all levels to the development of departmental initiatives. A
greater capacity for strategic thinking and action has been generated in staff
members at all levels, as has the recognition of how much can be achieved in
the Department. Interest has also grown in the conceptualisation and
documenting of projects,12 and greater attention is being paid to the
achievement of objectives and the realisation of outcomes.
Unexpected outcomes
An unexpected, though not negative outcome of the process has been an
increase in the generation of ideas for improvements in the Department and
implicit in that, the belief that those ideas will come to fruition. There has
been a greater demand for improved communication and, through the
Strategic Plan Monitoring Team (SPMT) and the Process Improvement Team
(PIT), a drive for the timely implementation of all initiatives.
Use and impact of Strategic Planning in the Personnel Department
Another outcome of strategic planning in the Department has been the
recognition of a need for further restructuring. Application of the Plan has
highlighted weaknesses in the Department’s structure and its ability to
achieve the objectives it has set itself. Weaknesses are also apparent in staff
size, levels of knowledge and skill, training and general competence. The
Department is currently engaged in the development of a restructuring plan as
part of the initial work of reviewing its strategic direction.
12 From 1999 to 2002 there has been focussed training on Project Documentation and Management, first at the level of the parent Ministry of Public Administration and Information and, later, the Personnel Department. The result has been the development of a cadre of officers at various levels of the Department who possess the capacity to design, document and manage social projects.
13
Communicating the Plan
Maintaining communication of strategic initiatives in a Department is seldom
easy, given the cultural and other dynamics that impact. In bringing the plan
to fruition, there were occasions when insufficient information was shared,
either because the rapid pace of activity left room for little else, or because
persons in the know deliberately sought to restrict the flow. In some
instances, there was obvious distortion of information that created
unnecessary fear and resistance in some sectors of the organisation.
Future of the project and its benefits
Strategic Planning in the Personnel Department is here to stay. The recent
change in the political administration has led to a corresponding change in the
strategic direction of the Public Service and the country. The new structure of
the Department, when implemented, will be complemented by the successor
Strategic Plan that will come into being in the latter part of 2004 and will, of
necessity, hinge on Government’s Vision 2020, the achievement of developed
country status by the year 2020. The Department will continue to grow and to
identify new avenues for its own development and that of the wider Public
Service. The role of the Personnel Department as a driver of Public Service
change demands flexibility and strength of purpose.
Costs of Strategic Planning
Strategic planning is a costly exercise. Many organisations hire an external
consultant to create the Plan; as professional as the resulting document
appears, however, this strategy often sacrifices staff goodwill, buy-in,
commitment. At the same time, there is seldom a sufficiency of organisational
resources to dedicate exclusively to the process. In the latter case, the result
is usually a less-than-perfect document put together by a group of employees
who have struggled to commit time and energy to the product while focussing
attention on their day-to-day work activities. In the long run, commitment to
implementation suffers and the Plan remains just a well-written document.
14
Lessons learnt
The process was not an easy one. Challenges of one kind or another
assailed its completion:
1. It was difficult to find internal resources to dedicate to the project, given
the varied set of competencies required.
2. The Department had to ensure that the individuals selected enjoyed the
trust of employees at all levels.
3. The level and constancy of communication required was difficult to
achieve and, where information sharing was slow, rumours surfaced that
could have easily derailed the activity.
4. In the early stages, resistance to the exercise was strong. Some
employees had no desire to accept the changes that would be generated;
others’ lack of trust in the entire process (based on earlier experiences)
led to attempts to interrupt the flow of activity.
5. The work involved in making the plan a reality was added to regular work
routines and resulted in team members’ having to devote a lot of personal
time to meeting deadlines for completion.
6. Iteration of elements of the process opened the team to a measure of
verbal abuse when individuals’ ideas were not accepted or when attempts
to achieve consensus led to unpopular changes in language or proposed
activities.
To ensure that completing the successor plan is less enervating, it may be
necessary to select a team that can be dedicated to the exercise for the
duration of its preparation. This team would have to be given the resources to
proceed and must possess the authority to require a response from all
members of staff.
15
It is necessary to build specific mechanisms for information into the process
from its inception and these mechanisms must be communicated to all staff.
Periodic information sessions must accompany the exercise and additional
funds applied to seminar-type activities. Electronic means of data gathering
would enhance information sharing.
Also necessary, throughout the process (but especially at the stakeholder
assessment phase) is the inclusion of the views of external stakeholders, so
that their input can be an integral part of plans and directions.
Next Steps
It is very easy and undeniably tempting to shut down once the document has
been completed and to take no further action on strategic planning until the
life of the current plan has all but expired and the time is nigh to focus on the
successor document. The pressures of daily work make it difficult to maintain
momentum and frequent ad hoc demands on everyone involved slow down
the implementation of projects and adherence to targets.
Although the strategic plan document includes methodologies and action
plans for implementation, the post-strategic planning phase requires a new
and different set of dedicated activities and resources, such as:
• a commitment to the achievement of stated objectives and the energy
to keep the process going;
• a focus on the future and an ability to recognise and analyse changes
in the environment that may point to a new direction;
• the ability and willingness to be sufficiently flexible to effect changes
and a level of objectivity that minimises adherence to personal opinions
and directions that may have lost their relevance.
Recommended criteria for common approach to strategic planning in the Public Service of Trinidad and Tobago It is difficult, and not always prudent, to apply common approaches to the
practice of strategic planning across agencies and embedded cultures,
although some existing rules of thumb ensure success.
16
1. One of the traditional weaknesses of the permanent Public Service of
Trinidad and Tobago has been a need by administrators to have action
legislated. As a result, initiative (and possible effectiveness) is often
sacrificed on the altar of efficiency, with senior managers refusing to move
unless and until written directives are given, either from the Cabinet or
one of the central agencies. A first step must be the development of a
culture that accepts the necessity to take calculated risks.
2. The conceptualisation and development of a Strategic Plan as a set of
programmes or projects moves the exercise away from pie-in-the-sky
visioning and creates a framework for implementation and measurement.
The statement of goals and purposes and the definition of specific
objectives, timeframes and targets provide visual clarity and aid in the
designation of responsibility centres and the early identification of
problems. The process of arriving at details of costing and assessing
assumptions and risks is an exercise that focuses the mind of the planner
on future activities and outcomes and mechanisms for controlling both.
3. A critical need in strategic planning is competence in planning and
forecasting. Competence cannot be developed during the exercise, nor
should an organisation attempt to engage in training immediately prior to
the commencement of the exercise. The organisation must, therefore,
develop a cadre of officers skilled in project development, documentation
and implementation who would form part of a team dedicated to the
exercise.
4. Mechanisms for continuous communication have to be developed early
and maintained throughout the process, as ignorance and/or uncertainty
by stakeholders will lead to resistance that can compromise the
effectiveness of the process and stall implementation.
5. Adequate time must be allocated to the process. If strategic planning is to
achieve a successful outcome, the organisation must be willing to devote
all the time necessary to ensure it. The iterative process requires
17
constant sharing of information, a willingness to allow stakeholders to
ruminate over all the elements that affect them, and openness to frequent
changes in information.
6. Strategic planning requires dedicated human, financial and material
resources from conceptualisation to implementation and evaluation. The
organisation must, therefore, be prepared to commit a team (or teams) to
the exercise and to provide all the resources they need for the task.
7. Mechanisms for implementation, review, evaluation and measurement of
the Plan, its processes and its outcomes must be written into the planning
process and the subsequent document.
8. No strategic planning exercise will be successful without the human
attributes that complement it, namely:
a. an open and flexible approach to change by strategic planners;
b. a willingness to halt the project and change direction if the
environment changes;
c. the possession of strong analytical skills;
d. the possession of strong communication skills, including writing
skills since lack of coherence, logic and analysis in a document
discourages reading.
Conclusion The focus of the Government of Trinidad and Tobago has changed; therefore,
the direction (and perhaps the activities) of the Personnel Department must
be amended. The successor Strategic Plan must take into account the
imperatives of Vision 2020, the Administration’s plan to achieve developed
country status by the year 2020. Other documents that fall out of a Strategic
Plan, viz. a Human Resource Plan and a Human Resource Development
Plan, must also take into account the changes in the environment.
18
APPENDIX I
Vision Statement of the Personnel Department; To be the model provider of contemporary human resource management
and industrial relations solutions in the Public Sector
Mission Statement of the Personnel Department
To excel in the development of quality Human Resource Management policies
and in the application of Industrial Relations best practices
and people management solutions
for the well-being of the Public Service and the Nation
Statement of Core Values The practice of Equity
We are firmly committed to the practice of equity
in our dealings with all Stakeholders
The provision of quality service
We believe in working together to provide consistently high quality service
to all our clients
Caring for staff members
We care about the well-being and development of every member
of the Personnel Department
A pro-active and innovative approach
We strive to be pro-active and innovative in meeting the needs of our clients
and in finding creative ways of satisfying those needs
19
APPENDIX II
List of Strategic Objectives
1. The development of a cohesive philosophy for Human Resource
Management in the Public Service
2. The revision of the legislative framework for Human Resource
Management in the Public Service to align with the approved philosophy
3. The development of policies, systems and mechanisms for improving
and/or modernising the practice of Human Resource management in the
Public Service
4. The implementation and monitoring of measures to enhance staff
development and the quality of work life in the Personnel Department
5. The development of systems to measure and manage organisational
performance in the Personnel Department
6. The development of a system for the improvement of organisational
communication within the Personnel department and between the
Personnel Department and its stakeholders
7. The development of systems for improving the efficiency of work
processes within the Personnel Department.
20
IMPLEMENTATION PLAN: PROGRAMME OF KEY ACTIVITIES FOR THE PERIOD SEPTEMBER 1, 2001 – AUGUST 31, 2004
OBJECTIVE 1: Develop a cohesive philosophy for Human Resource Management in the Public Service
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
-
Approved philosophy for Human Resource Management in the Public Service developed
31/12/01 Develop draft philosophy for Human Resource Management
Conduct stakeholder consultations
Submit philosophy for Cabinet’s
approval
Director, Human Resource Policy, Planning and Research
Financial: $75,000.00 to host stakeholder consultations
Human: In-house
staff, Human Resource Policy, Planning and Research Division
21
OBJECTIVE 2: Review the legislative framework for Human Resource Management in the Public Service to ensure alignment with the approved
philosophy
-
New/revised legislation drafted and submitted for approval
30/09/02 Review existing legislation
Consult with Associations/Unions
Consult with Chief Parliamentary Counsel
Submit for Cabinet’s approval
Head, Legal Services Division, in collaboration with Director, Benefits Management Division
Human: In-house
staff, Legal Services Division, in collaboration with Benefits Management Division
22
OBJECTIVE 3: Modernise the Human Resource Management systems in the Public Service
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility
Resources Required
(1) Establish a modern philosophy and strategy for Human Resource Planning in the Public Service
Approved policy, strategy and guidelines for Human Resource Planning developed
31/12/01 Draft policy
Consult with stakeholders
Seek Cabinet’s approval
Disseminate to stakeholders
Director, Human Resource Policy Planning and Research Division
Financial: $75,000.00 to
host stakeholder
consultations
Human: In-house staff,
Human Resource Policy
Planning and Research
Division, in consultation
with staff of other relevant
Divisions
(2) Establish a modern system for the management of compensation
Revised Classification Plan for the Judicial and Legal Service
30/06/02
Monitor Consultant to ensure performance standards are met
Review Consultant’s report
Submit Report for Cabinet’s approval
Director, Compensation Management Division
Financial: $600,000 to
pay consultants
Human: In-house staff, Compensation Management Division
Revised Classification and Compensation Plan for the Protective Services
31/03/02 Review completed job descriptions
Complete market surveys
Consult with stakeholders
Director, Compensation Management Division
Human: In-house staff,
Compensation
Management Division
23
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(2) Establish a modern system for the management of compensation
Revised Classification and Wage structure for daily-rated occupations
31/07/02 Review existing classification wage structure
Finalise report and submit for Cabinet’s approval
Director, Compensation Management Division, in collaboration with Director, Benefits Management Division
Human: In house staff resources
Revised Classification structure and Compensation Plan for the Civil Service and Statutory Authorities subject to the Statutory Authorities Act Chapter 24: 01
31/08/04 Conduct orientation and start up activities
Conduct Pilot Study
Conduct review of jobs in wider Civil Service and Statutory
Authorities
Consult with stakeholders
Finalise Plan and submit report for Cabinet’s approval
Director, Compensation Management Division
Financial: $6.8
million for
consultancy services;
$2.9 million to pay
officers on contract
Human: Consultants and Job Evaluation Project staff
Revised pay system for the Defence Force
31/03/02 Establish Committee
Conduct review
Prepare report
Submit recommendations to Cabinet
Director, Compensation Management Division
Director, Human Resource Policy Planning and Research Division
Human: In house
staff, Compensation
Management and
Human Resource
Policy Planning and
Research Divisions
24
Research Divisions
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(2) Establish a modern system for the management of compensation
Mechanisms established for on-going measurement of the cost of the total rewards package
30/06/02 Establish Compensation and Benefits Analysis Team
Develop Terms of Reference
Conduct Analysis
Prepare report on analysis of findings
Director, Human Resource Policy Planning and Research Division, in collaboration with Directors, Compensation Management and Benefits Management Divisions
Human: In house
staff, Human
Resource Policy,
Planning and
Research Division, in
collaboration with
Compensation and
Benefits
Management
Divisions, as
necessary
Electronic database of
compensation packages for benchmark jobs in the Public Service and for comparable external jobs created
30/06/02 Identify benchmark jobs
Develop database
Establish links with external organisations
Director, Compensation
Management, in
collaboration with Directors, Human
Resource Policy
Planning and Research
Human: In house staff, Compensation Management Division and staff of Human Resource Policy Planning and Research, and Benefits Management
25
and Benefits
Management Divisions
Divisions IT Specialist
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Establish a modern system for the management of employee benefits in the Public Service
Service regulations revised and updated in conformity with changes in negotiated terms and conditions of service
31/12/03 Assess the scope of changes needed
Compile amendments
Consult with Chief Parliamentary Counsel
Head, Legal Services Division, in collaboration with Director, Benefits Management Division
Human: Staff of the Legal Services Division, in collaboration with Benefits Management Division
Holistic review of benefits package, policies and guidelines completed
30/06/02 (Teaching Service)
30/09/02 (Protective Services)
31/12/04 (Civil Service/Statutory Authorities)
Re-assess existing benefits packages, by services, in light of completed job evaluation and new compensation arrangements
Review existing policies and guidelines and develop new ones, as necessary
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division
Benefits policies on-line 30/06/03 Compile an information package on current benefits
Establish mechanisms for updating information base for inclusion on
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division and IT Specialist
26
Department’s website
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Establish a modern system for the management of employee benefits in the Public Service
Review policy for the management of devolved functions
30/06/02 Prepare report on devolved functions
Make recommendations
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division
Approved policy and guidelines for Employee Assistance Programmes developed
28/02/02 Draft policy
Consult with stakeholders
Seek Cabinet’s approval
Director, Benefits Management Division in collaboration with Director, Human Resource Management Services Division
Human: In-house staff, Benefits Management Division
Staff of Legal Services Division
Employee Assistance
Programme Pilot Project implemented
30/06/02 Consult with identified agencies
Communicate policy and guidelines
Develop and circulate list of service providers
Monitor implementation
Director, Human Resource Management Services Division
Human: In-house staff, Human Resource Management Services Division
Consultants
27
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Establish a modern system for the management of employee benefits in the Public Service
Employee Assistance Programmes implemented in wider public Service
31/12/03 Review policy and guidelines based on experience with Pilot Project
Consult with all Ministries and Departments
Communicate policy and guidelines
Advise/facilitate/monitor implementation
Director, Human Resource Management Services Division
Human: In-house staff, Human Resource Management Services Division
Consultants
(3) Establish a modern system for the management of employee benefits in the Public Service
Joint Employer-Union Health and Safety Committees established in the Public Service: a Central Committee and Departmental Committees
31/12/01 Finalise draft terms of reference
Issue instructions throughout the Public Service for the establishment of Departmental Health and Safety Committees
Determine membership of Central Committee and advise members accordingly
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division
28
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Establish a modern system for the management of employee benefits in the Public Service
Approved policy and guidelines on Employee Study Programmes prepared and circulated
31/12/02) Review existing policy on Employee Study Programmes
Prepare new draft policy and guidelines
Consult with stakeholders
Director, Benefits Management Division in collaboration with Director, Human Resource Management Services Division
Human: In-house staff, Benefits Management Division
Finalisation of the implementation of a Group Health Plan for daily-rated employees
31/12/01 Oversee and monitor compilation of database
Monitor the inputting of information on all employees on the system
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division and Management Committee
Implementation of a Pension
Plan for daily-rated employees 31/12/01 Oversee and monitor the compilation
of database of pensionable employees
Complete procedures for the installation of the Plan
Conduct information-sharing sessions
Establish Pensions Secretariat
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division
Management Committee
29
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Establish a modern system for the management of employee benefits in the Public Service
Implementation of a Group Health Plan for monthly-paid employees
31/12/02 Revisit existing proposals
Consult with Risk Management Services (RMS)
Consult with stakeholders
Prepare cost estimates
Draft proposals for submission to Cabinet
Director, Benefits Management Division
Human: In-house staff, Benefits Management Division
Management Committee
(4) Establish systems to enhance labour and industrial relations in the Public Sector
Policy and guidelines on Joint Consultative Committees (JCCs) revisited
Mechanisms created for establishing/regenerating Joint Consultative Committees
31/12/01 Conduct survey to facilitate the assessment of the performance of JCCs
Review existing policy on the establishment and management of JCCs
Create new draft policy
Consult with relevant stakeholders
Director, Industrial and Labour Relations Division in collaboration with Director, Benefits Management Division
Human: Staff of
Industrial and
Labour Relations
Division
30
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(4) Establish systems to enhance labour and industrial relations in the Public Sector
A strategy for the 2002-2004 Public Service Negotiations developed
31/12/2001
Debrief the 1999-2001 negotiations
Develop criteria for the conduct of negotiations for the next triennium
Director, Industrial and Labour Relations, in collaboration with Directors, Compensation Management, Benefits Management, and Policy Planning and Research Divisions
Human: In-house staff of relevant Divisions
Framework established for communication between the Employer and Unions/ Associations and between Employer and public officers
31/12/02 Design a communications framework
Plan consultation sessions
Design and conduct stakeholder surveys
Director: Industrial and Labour Relations, in collaboration with Directors, Compensation Management, Benefits Management, and Policy Planning and Research Divisions
Human: In-house staff, Industrial and Labour Relations Division; surveys conducted by staff of Policy Planning and Research Division
31
(4) Establish systems to enhance labour and industrial relations in the Public Sector
Management Information Systems developed on traditional HR weak spots, for example:
- the number of man days lost to unplanned absences
- areas of high staff turnover
- areas of high expenditure
31/12/02 Identify relevant sources of data/information
Design and test data capture instruments
Conduct necessary information gathering exercises
Establish systems for data analysis and reporting
Human Resource Policy, Planning and Research Division in collaboration with Director, Human Resource Management Services Division
Human: In-house staff
of the Human
Resource Policy,
Planning and
Research Division and
other relevant staff of
the Personnel
Department
(4) Establish systems to enhance labour and industrial relations in the Public Sector (cont’d)
Documented policy, guidelines and procedures established for all agencies under the purview of the Ministerial Committee
31/03/02 Prepare policy, procedures, guidelines, etc.
Develop strategies for information dissemination
Market the Labour and Industrial Relations Division
Director, Labour and Industrial Relations Division in collaboration with Directors of other relevant Divisions
Human: In-house
staff of the Industrial
and Labour Relations
Division, in
collaboration with the
Communications
Specialist
Electronic database of Industrial Relations best-practices
31/12/02
Compile information package on Public Sector Industrial Relations issues
Develop a mechanism for updating information base on website
Director, Industrial and Labour Relations
Human: In-house staff of the Industrial and Labour Relations Division and IT Specialist
32
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(4) Establish systems to enhance labour and industrial relations in the Public Sector
Electronic database of comparative remuneration and settled negotiation packages created to facilitate the provision of guidelines
30/06/02 Gather information
Establish database
Director, Industrial and Labour Relations in collaboration with IT Specialist
Human: In-house staff, Industrial and Labour Relations and IT Specialist
Quarterly roundtable sessions on key Labour and Industrial Relations issues planned and conducted
January 2002 to July 2004
Sessions planned and executed
Seminar documents printed, and circulated as follow-up
Director, Industrial and Labour Relations Division in collaboration with Director, Benefits Management Division
Human: Expert presenters
In-house staff of relevant Divisions
Completed surveys to track the state of Industrial and Labour Relations in the Sector
January 2002 to December 2003
Develop and conduct surveys
Publish survey findings
Director, Industrial and Labour Relations
Human: In-house staff, Industrial and Labour Relations Division
33
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(5) Develop a system to manage employee performance in the Public Service
Implementation of a system for managing employee performance by Human Resource Management Units
31/12/01 Liaise with Human Resource Units in line agencies Monitor units
Director, Human Resource Management Services Division
Human: In-house staff, Human Resource Management Services Division
Annual report on the management of employee performance in the Public Service completed
1st report by 31/12/01
Collect and collate data on employee performance Prepare report
Director, Human Resource Management Services Division
Human: In-house staff, Human Resource Management Services Division
(6) Establish a modern system for career development and succession planning in the Public Service
Philosophy, policy and guidelines created for career development and succession planning in the Public Service and agreed by the Service Commissions and relevant Associations
Policy, guidelines and supporting legislation accepted by Parliament
Procedures for training and development and continuous assessment agreed by relevant stakeholders
31/07/02 Review existing philosophy, policy and legislation on career development and succession planning in the Public Service
Develop new draft philosophy, policy and guidelines on career development and succession planning
Consult with key stakeholders
Develop training programmes to support new policy
Director, Human Resource Management Services Division
Financial: Consultants
Human: In-house staff, Human Resource Management Services Division
34
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(7) Establish a system of Human Resource Auditing in the Public Service
Bi-annual audit of Human Resource Management function completed in each Ministry/ Department Annual report on the status of Human Resource Management in the Public Service completed
To commence by 02/01/02 1st report due by 30/06/02
Develop systems for the conduct of human resource audits Train staff in the conduct of human resource audits Collect, collate and analyse data from human resource audits in Ministries and Departments Complete and submit report
Director, Human Resource Management Services
Human: In house staff, Human Resource Management Services Division
35
OBJECTIVE 4: Implement and monitor measures for staff training and development and for the enhancement of the quality of work life in the Personnel Department
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(1) Acquire new office accommodation Redesign office layout and procure aids to employee comfort and well-being
New office building acquired to accommodate all staff of the Department Re-designed, comfortable office layout 50% of office furniture, furnishings, fittings and equipment acquired/replaced lp Tangible facilities for improving employee comfort and well being
31/12/03 31/10/02
Conduct infrastructure needs analysis Request new office accommodation Purchase new furniture, fittings and equipment Improve workplace security Upgrade air-condition system, elevator and lighting system Acquire new accommodation/ redesign existing office space Provide facilities for mid-morning liquid refreshment to staff Upgrade potable water system/install filtered water coolers
Director, Corporate Services, in consultation with Director, Property and Real Estate Services
Financial: Appropriate
funding to meet rental
costs
Human: Support from
Landlords and suppliers Support from Ministry of Infrastructure Development (Property and Real Estate Services Division)
(2) Acquire staff to fill existing vacancies
All Divisions of the Personnel Department optimally staffed
30/06/02 Advertise vacancies Consult with Service Commissions Department Arrange for the conduct of interviews
Director, Corporate Services Division
Financial: Provision of
adequate funds in the
2001/2002 budget
Human: Support from the Service Commissions
36
Department Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
(3) Develop internal policy for staff education, training and development
Personnel Department’s Training Plan operationalised
30/06/02 Review Personnel Department’s philosophy for staff training and development Explore mechanisms for staff training and development
Director, Corporate Services
Financial:
Adequate funding Human:
In-house staff, Corporate Services Division
(4) Develop and implement policy and systems for employee recognition
A viable mechanism for employee recognition in place
30/06/02 Research mechanisms for employee recognition Seek corporate funding and support Pilot an employee recognition event
Director, Corporate Services
Financial:
Adequate funding Human: In-house
Staff, Corporate Services Division Corporate sponsors
37
OBJECTIVE 5: Establish systems to measure and manage organisational performance in the Personnel Department
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility Resources Required
-
Organisation performance measures adopted Report on Department’s performance completed
30/09/02 1st report by 31/12/02
Conduct research into relevant systems Develop and implement performance measures Monitor Department’s performance Develop report
Strategic Plan Monitoring Team
Financial: $15,000.00 to procure materials Human: Strategic Plan Monitoring Team
OBJECTIVE 6:
Review/establish systems for the improvement of organisational communication within the Personnel Department
and between the Personnel Department and its stakeholders
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility
Resources Required
Improve communications with core business divisions of the Personnel Department, and with stakeholders
Corporate Communications Plan designed Personnel Department’s LAN installed and configured Personnel Department’s website in operation Personnel Department’s information available on-line
30/09/01 31/03/02 30/09/02 31/12/02
Develop and implement a Corporate Communications Plan Design and develop the Personnel Department’s website Conduct client satisfaction survey Monitor the implementation of the Freedom of Information Act 1999
Communications Specialist Information Technology Specialist in collaboration with the NISC
Financial
Adequate funding forthe purchase of computer hardware and software
Human: Trained
in-house staff
38
Qualified staff recruited Existing staff trained Databases commissioned
28/02/02 30/04/02 31/03/03
Acquire new staff Convert Department’s library into an Information/Documentation Centre Train staff in the use of the systems
Material
Computer equipmentand appropriate software
OBJECTIVE 7:
Develop and implement systems to improve the efficiency of work processes within the Personnel Department
Sub Objective
Performance Goals Time Frame Action Plan Primary Responsibility
Resources Required
Intended Impact/Outcome
Redesign work processes in all core functional areas of the Personnel Department
Process Improvement Team established Process improvement schedule developed Selected work processes in the Personnel Department reviewed and redesigned, as scheduled Selected work processes implemented
30/09/01 31/03/02 30/09/02 31/12/02
Develop Terms of Reference Appoint team members Undertake preliminary review of work processes Prioritise processes for improvement Institute process redesign activities Validate new processes Conduct training in the use of new processes
Management Team Process Improvement Team
Financial
$10,000.00 to procure materials Human
In-house staff trained in process re-design and database design and management
Increased production efficiency in the Personnel Department Improvements in service delivery Cost effective methods for resource utilisation
39
APPENDIX IV STRATEGIC PLAN OF THE PERSONNEL DEPARTMENT
(OFFICE OF THE CHIEF PERSONNEL OFFICER)
STEPS IN THE PROCESS 1. Communicate, to internal stakeholders, the Department’s intention to
embark on strategic planning activity; provide information on purpose and expected outcomes
2. Conduct strategic planning workshops to:
a. discuss the proposed direction of the Personnel Department b. conduct an environmental scan of the organisation c. draft statements of Mission, Vision and Core Values d. engage in a preliminary conceptualisation of Strategic
Objectives 3. Research theoretical and other information 4. Conduct iterative meetings/discussions to:
a. disseminate the findings of individual workshops b. amend information/documentation c. examine and refine elements of the Strategic Model
5. Identify and designate the individuals within the Department who would
create the Strategic Plan document 6. Draft the preliminary Strategic Plan document 7. Present a draft document to internal stakeholders for repeated
examination and refinement 8. Conduct a Seminar and make a PowerPoint presentation, to internal
stakeholders, of the final elements of the Strategic Plan (purpose; statements of Mission, Vision, Core Values; strategic objectives, etc.)
9. Revise/refine information 10. Agree the composition of monitoring teams 11. Prepare the final Strategic Plan document 12. Launch Strategic Plan 13. Embark on post-Launch activities:
a. Confirm and share information on SPMT and PIT membership b. Produce Divisional/Unit operational plans c. Monitor, evaluate and report on implementation activities and
the achievement of targets d. Recommend adjustments to targets/timeframes