Upload
ahmadranjha
View
220
Download
0
Embed Size (px)
Citation preview
8/9/2019 Cap Bud Techniques
1/36
A Comparison of Capital Budgeting Techniques
With definitions and exemplifications
8/9/2019 Cap Bud Techniques
2/36
Capital budgetingCapital budgeting
Cost/benefit analysis:Cost/benefit analysis:
Estimating the value of investment projectsEstimating the value of investment projects
Making informed choicesMaking informed choices
8/9/2019 Cap Bud Techniques
3/36
Capital Budgeting Techniques
A collection of methods allowing the manager to choose among a
variety of investment projects.
8/9/2019 Cap Bud Techniques
4/36
P
roblem
Value, rank and select investment projects
8/9/2019 Cap Bud Techniques
5/36
Exemplification
Project : Project : Project :
R q ir r t 7.7% 3% 6%
r 1: $400 $100 $5,200
r 2 $1,250 $200 $4,000
r 3 $900 $150 $1,000
r 4 $3,000 $100 $200
r 5 $1,000 $50 $100
I iti l C st $5,045 $490.67 $9,687.23
8/9/2019 Cap Bud Techniques
6/36
Clarifications
Re uired rate: a fair discount rate given each projects risk
8/9/2019 Cap Bud Techniques
7/36
MethodsMethods
Average Accounting ReturnAverage Accounting Return PaybackPayback
Discounted paybackDiscounted payback Internal Rate ofReturnInternal Rate ofReturn Modified Internal Rate ofReturnModified Internal Rate ofReturn Net Present ValueNet Present Value Profitability IndexProfitability Index
8/9/2019 Cap Bud Techniques
8/36
Average Accounting Return
AAR is the ratio of the Average Net Income to the Average Book Value.
Decision rule
Take the project ifAAR is greater than some target ratio set by accountants.
Disadvantages
It has too many flaws, don't ever use it.
8/9/2019 Cap Bud Techniques
9/36
P
ayback period
PB is the time it takes to recover the initial cost of theinvestment
8/9/2019 Cap Bud Techniques
10/36
Payback period
Decision rule
Take the project with the shortest payback period
Disadvantages
Ignores time value of money Ignores risk
Ignores cash inflows beyond the cutoff point
8/9/2019 Cap Bud Techniques
11/36
Payback period
In our example:
project C: . years
project B: . years
projectA: . years
All three projects are viable
8/9/2019 Cap Bud Techniques
12/36
Discounted payback period
DPB is the time it takes to recover the initial cost of the investment
PB uses nominal CF DPB uses discounted CF
8/9/2019 Cap Bud Techniques
13/36
Discounted payback period
Decision rule
Take the project with the shortest discounted payback period.
Disadvantages
DPB ignores cash inflows beyond the cutoff point
8/9/2019 Cap Bud Techniques
14/36
8/9/2019 Cap Bud Techniques
15/36
Internal Rate of Return
IRR is the discount rate that makes the present value of theproject e ual to its initial cost.
8/9/2019 Cap Bud Techniques
16/36
Internal Rate of Return
Decision rule
Take the project If the IRR exceeds the re uired rate of return
Disadvantages
Reinvestment rate assumption is unrealistic Multiple IRR
IRR cannot rank mutually exclusive projects
8/9/2019 Cap Bud Techniques
17/36
Internal Rate of Return Calculation
Set: Initial cost = PV(project)$5,045 = $400/(1+r) +$1,250/(1+r)2 +$900/(+r)3 +$3,000/(1+r)4 +$1,000/(1+r)5
r = .
8/9/2019 Cap Bud Techniques
18/36
Internal Rate of Return
IRR(A) =
IRR(B) =IRR(C) = .
Only A andB are viable
8/9/2019 Cap Bud Techniques
19/36
Modified Internal Rate of Return
MIRR is the discount rate that makes the future value of the projecte ual to its initial cost.
MIRRrequires a reinvestment rate.
8/9/2019 Cap Bud Techniques
20/36
Modified Internal Rate of Return
Decision rule
Take the project if MIRR is larger than the re uired rate.
Disadvantages
MIRR cannot rank mutually exclusive projects.
8/9/2019 Cap Bud Techniques
21/36
MIRR calculation
Project A
Set FV(at ) = , (1+MIRR)
MIRR =
8/9/2019 Cap Bud Techniques
22/36
MIRR calculation
MIRR(A) =
MIRR(B) = .
MIRR(C) =
Only A andB are viable
8/9/2019 Cap Bud Techniques
23/36
NPV
Net Present Value is the difference between the present value of aproject and its initial cost
NPV = PV - Initial cost
8/9/2019 Cap Bud Techniques
24/36
NPV
Decision rule
If NPV is positive, take the project.
Disadvantages
Very complex analysis, too many variables to forecast
8/9/2019 Cap Bud Techniques
25/36
NPV:Corollary
Required Rate = IRR NPV = 0
and vice-versa.
8/9/2019 Cap Bud Techniques
26/36
NPV calculation
projectA:
PV =$400/(1.077) +$1,250/(1.077)2 +$900/(1.077)3 +$3,000/(1.077)4 +$1,000/(1.077)5
PV=$5,089.36
NPV= Present value - Initial Cost
NPV = , . - , = .
8/9/2019 Cap Bud Techniques
27/36
NPV calculation
NPV(A)= +$44.
NPV(B)= +$64.17
NPV(C)= -$148.81
Only A andB are viable
B is better because it adds more value
8/9/2019 Cap Bud Techniques
28/36
The Profitability Index
The profitability index is the ratio of project PV to initial cost
PI = PV/Initial cost
8/9/2019 Cap Bud Techniques
29/36
The Profitability Index
Decision rule
Take the project if PI > 1
Disadvantages
PI cannot rank mutually exclusive projects.
8/9/2019 Cap Bud Techniques
30/36
PI calculation
Project A:
PI(A) = PV(A)/Initial cost = , 89. 6/$5, 45
PI(A) = 1. 88
8/9/2019 Cap Bud Techniques
31/36
PI Calculation
PI(A) = 1. 88
PI(B) = 1.131
PI(C) = .9846
Only A andB are viable
8/9/2019 Cap Bud Techniques
32/36
Why cant PI rank the projects?
Exemplification
P r o j e c t x P r o j e c t y
P r e s e n t a l e $ 2 5 ,0 0 0 ,0 0 0 $ 3 ,0 0 0
In i t ia l c o s t $ 2 4 ,0 0 0 ,0 0 0 $ 1 ,0 0 0
P I 1 .0 4 2 3
N P $ 1 ,0 0 0 ,0 0 0 $ 2 ,0 0 0
8/9/2019 Cap Bud Techniques
33/36
8/9/2019 Cap Bud Techniques
34/36
Answer
NPV rules.
Always.
8/9/2019 Cap Bud Techniques
35/36
Important side note
In project valuation, measures of absolute wealth are moreappropriate than measures of relative efficiency.
8/9/2019 Cap Bud Techniques
36/36
j j j
i 7.7% % %
$5, 5 $490. 7 $9,6 7.2
l $5,089. 6 $554.84 9,5 8.42
F l (5% $7,075.45 $67 .45 $12,363.5
i 3.83 3.41 2.49 *
i 4.94 3.76 * N/A
IRR 8%* 8%* 5%
MIRR 7%* 6.54%* 5%
N l $44.36* $64.17* ($148.81
i ili i x 1.0088* 1.131* 0.9846