15
Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Embed Size (px)

Citation preview

Page 1: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Building for Learning ProjectPhoto Progress Report

October 2009

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

New roof going up (over rooms 4 and 5)

If you look closely, you will see the old

wooden shingles which were the original roof dating back to the late

1890’s

1st Oct 2009

Page 3: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Admin empty ready for refurbishment to begin by 19th Oct2nd Oct 2009

Page 4: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

New roof being added to original school building dating back to 1874 – 2nd Oct 2009

Page 5: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Major roof works completed – 5th Oct 2009

Page 6: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Internal Demolition Begins 6th Oct 2009

Page 7: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Classrooms 6-9 Demolition continues Oct 2009

Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor

Page 8: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Racking construction for refurbishment storage 14th Oct 2009

Page 9: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Demolition continues Oct 2009

Page 10: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Corporate Services area refurbishment 19th Oct 2009

Windows removed Ceiling Fans replaced

Page 11: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Floor demolition 19th Oct 2009

Page 12: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Graeme Connelly supervising wall demolition 21st Oct 2009

Page 13: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Internal framing and windows being cut in 27th Oct 2009

Page 14: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Framing and floors added 28th Oct 2009

Staff inspections of works

Page 15: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009

Outside area demolition ready for major works to begin 29th Oct 2009