Alcatel BSS G2 BSC Commissioning Manual Commissioning Manual Release B7 3BK 17416 3001 RJZZA Ed.03

BSC commissioning B7

Embed Size (px)

Citation preview

Page 1: BSC commissioning B7

Alcatel BSS

G2 BSC Commissioning Manual

Commissioning Manual

Release B7

3BK 17416 3001 RJZZA Ed.03

Page 2: BSC commissioning B7

Status RELEASED

Short title Com

All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel/Evolium.

BLANK PAGE BREAK

2 / 61 3BK 17416 3001 RJZZA Ed.03

Page 3: BSC commissioning B7

Contents

Contents

Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1 General Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Hardware Description - Racks Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.2 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.3 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.4 Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.5 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.6 Operating Principle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.7 Time Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171.8 Information Required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181.9 Conventions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

2 Preliminary Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.1 Before Leaving for the Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2 Before Starting (on Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

3 Hardware Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

4 Checking the Power Supply and Powering Up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234.1 Check the Rating of the Fuses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244.2 Discharge the Capacitors in the Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244.3 Check the Polarity of the Power Supply Line, Branch A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244.4 Check the Polarity of the Power Supply Line, Branch B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244.5 Power up the BSC Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

5 Installing the BSC Terminal and BSS SW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 275.1 Installing the BSC Terminal Software and the X.25 Communication Board . . . . . . . . . . . . . . . 28

5.1.1 Install EICON C31 Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285.1.2 Install Windows BSC Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

5.2 Installing the Craft Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285.3 Installing the BSS Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

5.3.1 Case 1: Build is Delivered on Floppy Disks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285.3.2 Case 2: Build is Delivered on IOMEGA ZIP Disk . . . . . . . . . . . . . . . . . . . . . . . . . . 29

6 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 316.1 Relocation of System-CPRCs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 326.2 Loading and Activating the BSC Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

6.2.1 Prepare X.25 Configuration Link . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 326.2.2 Configure the Rack’s First BIUA with the Generic File . . . . . . . . . . . . . . . . . . . . . . 346.2.3 Check and Upgrade the TSCA FW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 356.2.4 Format Disk A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 376.2.5 Load the BSS Software onto Disk A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 376.2.6 Check the Content of Disk A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 386.2.7 System Initialization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 386.2.8 Set to "OPR" the SBLs of the Declared BTSs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 396.2.9 Check Board Status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 396.2.10 Format Disk B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.2.11 Copy the BSS Software to Disk B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.2.12 Check the Content of Disk B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.2.13 Activate Disk B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

6.3 Checking Battery Backup of S-CPRC Boards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 416.4 Correcting the BSC Date and Time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 426.5 Option: Testing the External Alarms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42

7 Option: Hardware Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43

7.1 BSC Hardware Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 447.2 Reboot the BSC in OPERATIONAL Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46

3BK 17416 3001 RJZZA Ed.03 3 / 61

Page 4: BSC commissioning B7

Contents

8 Option: Checking the BSC-TC Link . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

9 Setting and Checking the BSC - OMC-R Link . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49

10 Finishing Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

Appendix A : Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

Appendix B : List of items required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55

Appendix C : Example of Inter-Rack Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57

Appendix D : Disabling / Enabling Alarm Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59

Appendix E : Workaround: Exit/Connect WinBSC Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61

4 / 61 3BK 17416 3001 RJZZA Ed.03

Page 5: BSC commissioning B7

Preface

Preface

Purpose This document describes the commissioning procedure for BSC G2, releaseB7, of the ALCATEL BSS.

What’s New In Edition 03References to new ITL Catalogue (3DF 00462 0004 AAAGA) and IO Catalogue(3DF 00462 0004 UAZZA) were updated in List of Documents Required.In Edition 02Update for TSCA FW upgrade in Check and Upgrade the TSCA FW.

Audience This document is intended for:

Site administrators

Project managers

Field service technician

Supervisors

Occasional users (e.g. subcontractors).

Assumed Knowledge You must have a basic understanding of the following:

ALCATEL Operations & Maintenance (O&M) concepts for the Base StationSubsystem (BSS)

Commissioning tools

Personal Computers (PCs) using the Windows environment

3BK 17416 3001 RJZZA Ed.03 5 / 61

Page 6: BSC commissioning B7

Preface

Conventions: Press [ Enter ] means press the Enter key

Click [ OK ] means click the button OK with the mouse

Operator input is indicated after a double right-pointing arrow in Courier fontOperator input

To describe a menu path, the menu options are linked as follows:Tools ⇒ Options ⇒ Printer ⇒...

A message is indicated in Courier font:Message

6 / 61 3BK 17416 3001 RJZZA Ed.03

Page 7: BSC commissioning B7

1 General Description

1 General Description

This chapter provides general information about the operating principle andrequirements of the procedure

Hardware Description - Racks Configuration

Restrictions

Prerequisites

Initial State

Final State

Operating Principle

Time Schedule

Information Required

Conventions

3BK 17416 3001 RJZZA Ed.03 7 / 61

Page 8: BSC commissioning B7

1 General Description

1.1 Hardware Description - Racks ConfigurationFigures 1 to 6, which show the layout of the equipment fitted in each rack foreach BSC configuration, are provided to assist the visual check procedure.

The key used in the figures is as follows:

CE number at a CPRC unit = Network address

AB = OSI- CPRC

AC= SYS- CPRC

AA= BC- CPRC

number at a DTCC unit = Network address

number at a TCUC unit = Network address

NE number at an QA unit = Qmux address

SWCH number at a AS unit AS = Access Switch Number

number at a GS unit GS1/n = Group Switch Stage 1/Plane +SwitchElement Number

GS2/n = Group Switch Stage 2/Plane +SwitchElement Number

number at a BCLA unit SYS = System Variant

M = Master

RACK = Rack Variant

S = Slave

8 / 61 3BK 17416 3001 RJZZA Ed.03

Page 9: BSC commissioning B7

1 General Description

Figure 1: Rack Layout Rack 1, Configuration 1

3BK 17416 3001 RJZZA Ed.03 9 / 61

Page 10: BSC commissioning B7

1 General Description

Figure 2: Rack Layout Rack 1, Configuration 2, 3, 4, 5, 6

10 / 61 3BK 17416 3001 RJZZA Ed.03

Page 11: BSC commissioning B7

1 General Description

Figure 3: Rack Layout Rack 2, Configuration 3

3BK 17416 3001 RJZZA Ed.03 11 / 61

Page 12: BSC commissioning B7

1 General Description

Figure 4: Rack Layout Rack 2, Configuration 4, 5, 6

12 / 61 3BK 17416 3001 RJZZA Ed.03

Page 13: BSC commissioning B7

1 General Description

Figure 5: Rack Layout Rack 3, Configuration 5

3BK 17416 3001 RJZZA Ed.03 13 / 61

Page 14: BSC commissioning B7

1 General Description

Figure 6: Rack Layout Rack 3, Configuration 6

14 / 61 3BK 17416 3001 RJZZA Ed.03

Page 15: BSC commissioning B7

1 General Description

1.2 RestrictionsThere are no restrictions in applying this document.

1.3 Prerequisites

The site must comply with the "safety rules" (see “BSS Methods Handbook”).

At least two Atermux PCM links must be available

1.4 Initial State

The BSC racks are installed and wired on the customer’s site.

The power supply is connected and powered up, but the racks are notpowered up (all circuit breakers at the top of each rack must be in the

"OFF" position)

1.5 Final State

The BSC is powered up and downloaded with the build requested by

the customer.

The BSC is connected to TC and OMC-R, ready for physical connection

of the BTSs.

3BK 17416 3001 RJZZA Ed.03 15 / 61

Page 16: BSC commissioning B7

1 General Description

1.6 Operating Principle

Before leaving for the site

Before starting (on arrival at the site)

Hardware check

Checking the power supplyand powering up

Installing the BSC Terminaland X.25 board

Installing the BSS SW from floppy disks

Build delivery ?IOMEGA zipFloppy disks

Installing the BSS SW from IOMEGA zip disk

Relocation ofsystem CPRCs

Loading and activatingthe BSC software

Checking battery backupof S−CPRC boards

Correcting the BSCdate and time

Alarm cablesare installed ?

YESNO

Testing the externalalarms

BSC configurationmore than 2 ?

YESNO

BSC hardware test

Setting and checkingBSC − OMC−R link

Finishing commissioning

Checking BSC − TClink

16 / 61 3BK 17416 3001 RJZZA Ed.03

Page 17: BSC commissioning B7

1 General Description

1.7 Time Schedule

Duration (min) 1st person 2nd person

Preliminary checks

Preparation before leaving for the site 20 20

Before starting (on arrival at the site) 20 20

Hardware check (1) 10–60(2) 10-60(2)

Checking the Power Supply and Powering Up (1) 25 25

Installing the BSC Terminal and BSS SW

Installing the BSC Terminal software and X.25 communication board 45 –

Installing the Craft Terminal 10 –

Installing the BSS software 10–20(3) –

Commissioning tests

Relocation of system-CPRCs 2 –

Loading and activating the BSC software 90 –

Checking battery backup of S-CPRC boards 30 –

Correcting the BSC date and time 2 –

Option: Testing the external alarms 10 10

Option: Hardware test 40 –

Checking BSC - TC link 20 –

Setting and checking the BSC - OMC-R link 30 –

Finishing commissioning 20 –

6h24-7h24 1h25-2h15

(1) tasks where two persons are mandatory for execution(2) depending on BSC configuration (1-6)(3) 10 min from IOMEGA zip, 20 min from floppy disks

The duration given is based on technical constraints, not taking into accountsafety parameters.

3BK 17416 3001 RJZZA Ed.03 17 / 61

Page 18: BSC commissioning B7

1 General Description

1.8 Information Required

1. SiteDDF map

2. Equipment configuration

Rack configuration number (1 to 6)

X.25 routing:

extraction at BSC site

extraction on TRCU modules via X.25 packet switch

X.25 routed through MSC

BSS topology

BSS software version

3. Other

Version of TSC firmware (B5, B6 or higher)

Status of A interface cables at the TC side (connected to MSC or looped)

Which A interface cables are connected at the MSC (if applicable)

External alarm cables (available or not)

1.9 ConventionsThe following conventions are used in this document

Press [ Enter ] means press the Enter key

Click [ OK ] means click the button OK with the mouse

Operator input is indicated after a double right-pointing arrow in Courier fontOperator input

To describe a menu path, the menu options are linked as follows:Tools ⇒Options ⇒Printer ⇒...

A message is indicated in Courier font:Message

18 / 61 3BK 17416 3001 RJZZA Ed.03

Page 19: BSC commissioning B7

2 Preliminary Checks

2 Preliminary Checks

This chapter describes preparation for the operation in two steps:

at base

on arrival at the site.

3BK 17416 3001 RJZZA Ed.03 19 / 61

Page 20: BSC commissioning B7

2 Preliminary Checks

2.1 Before Leaving for the Site

Check that prerequisites have beensatisfied

See Prerequisites (Section 1.3)

Check availability of all InformationRequired

See Information Required (Section 1.8)

Check availability of documentation See List of Documents Required (in appendix B) , checkthe edition and release of the documents.

Check availability of tools See List of tools required (in appendix B), refer to the“Tools catalogue“ for checking the content

Check availability and version of software See List of Software Required (in appendix B), refer to thecorresponding documents for checking the SW version

2.2 Before Starting (on Arrival at the Site)

Check applicable notifications andoperation instructions

Refer to Catalogue of Technical and Logistic Information(ITL) to check whether notifications are to be applied duringthe operation

Refer to Catalogue of Instruction Operation (IO) to checkwhether operation instructions are to be applied during theoperation

Check that the safety instructions havebeen applied

Refer to BSS Methods Handbook to check that the safetyprecautions have been taken in accordance with the safetyinstructions

Read instructions to be applied in theevent of anomaly

Refer to BSS Methods Handbook for instructions

Complete premises inspection form Refer to BSS Site Premises Inspection, Post Handover andcomplete Premise Inspection Form (CEL).

Fill in completion check list • Complete the header field of the Completion Check List.

• Note the type of the BTS in the CCL, see HardwareDescription - Racks Configuration (Section 1.1).

• The CCL is to be completed as each instruction is carriedout

Check the antistatic wrist strap Check that the resistance of the antistatic wrist strap isgreater then 1 Mohm.

20 / 61 3BK 17416 3001 RJZZA Ed.03

Page 21: BSC commissioning B7

3 Hardware Check

3 Hardware Check

This chapter describes how to check the BSC configuration and HTS of theboards inside the BSC.

3BK 17416 3001 RJZZA Ed.03 21 / 61

Page 22: BSC commissioning B7

3 Hardware Check

Purpose

To check that the BSC configuration corresponds to the customer’s order.

To verify that the hardware level of the boards inside BSC is as requested

by the customer, by taking the rack inventory.

Procedure 1. Verify the presence and position of the boards according to the requestedconfiguration.

See Information Required

See Hardware Description - Racks Configuration

2. Perform the rack inventory.

Refer to CI-08 Site Equipment Inventory.

Check that there are no alarms of type “NOT IN CAL”, when runningInventar for BTS. This ensures that the boards inside the BSC meet therequirements of a specific customer.

22 / 61 3BK 17416 3001 RJZZA Ed.03

Page 23: BSC commissioning B7

4 Checking the Power Supply and Powering Up

4 Checking the Power Supply and Powering Up

This chapter describes the tasks to perform to check the power supply andpower up the BSC.

3BK 17416 3001 RJZZA Ed.03 23 / 61

Page 24: BSC commissioning B7

4 Checking the Power Supply and Powering Up

4.1 Check the Rating of the Fuses

Procedure 1. On the customer power panel (cabinet), check for the existence of two DCpower supply distribution circuits. Each distribution circuit is provided with aDC circuit breaker (fuse holder).

2. On the site power panel, disconnect the two -48V power supply lines (line Aand B) at the rack fuse holders.

3. Check that the fuse ratings are in accordance with the SPP— 27 document.

4.2 Discharge the Capacitors in the Racks

Procedure 1. At the customer power panel, make sure the two -48 V power supply linesfor BSC are disconnected.

2. Close (ON position) all the rack (and extension rack if applicable) circuitbreakers for 10 seconds.

3. Open (OFF position) all the rack circuit breakers.

4.3 Check the Polarity of the Power Supply Line, Branch A

Procedure 1. At the BSC top rack filter units for each rack (basic rack and extension racksif applicable) remove the protection caps from the power supply terminals.

2. Connect the -48 V power supply (branch A) at the fuseholder.

Branch A is connected.

Branch A is associated with the fuseholder marked BAT A.

3. Using the multimeter, check the presence of -48V DC between BAT A andBATRET for all racks (basic and extensions).

Check that no voltage is present between BAT B and BATRET for all racks.

4. Switch all the rack circuit breakers ON.

The DC/DC converters A01-A09 for all racks are powered up.

The DC/DC converters B71-B78 for all racks are not powered up.

NOTE : Converters B72 and B78 are removed starting from rack variant3BK 06796 AAAC.

5. Switch all the rack circuit breakers OFF.

No board in the racks is powered up.

6. At the customer power panel, disconnect the -48 V power supply (branch A)at the fuseholder.

Branch A is disconnected.

4.4 Check the Polarity of the Power Supply Line, Branch B

Procedure 1. Discharge the capacitors in the rack.

See Discharge the Capacitors in the Racks (Section 4.2)

2. At the BSC top rack filter units for each rack (basic rack and extension racksif applicable) remove the protection caps from the power supply terminals.

3. Connect the -48 V power supply (branch B) at the fuseholder.

24 / 61 3BK 17416 3001 RJZZA Ed.03

Page 25: BSC commissioning B7

4 Checking the Power Supply and Powering Up

Branch B is connected.

Branch B is associated with the fuseholder marked BAT B.

4. Using the multimeter, check the presence of -48V DC between BAT B andBATRET for all racks (basic and extensions).

Check that no voltage is present between BAT A and BATRET for all racks.

5. Switch all the rack circuit breakers ON.

The DC/DC converters B71-B78 for all racks are powered up.

The DC/DC converters A01-A09 for all racks are not powered up.

NOTE : Converters B72 and B78 are removed starting from rack variant3BK 06796 AAAC.

6. Switch all the rack circuit breakers OFF.

No board in the racks is powered up.

7. At the customer power panel, disconnect the -48 V power supply (branch B)at the fuseholder.

Branch B is disconnected.

4.5 Power up the BSC Racks

Procedure 1. Switch ON the two power supply lines at the fuseholders.

2. Switch ON all the rack circuit breakers, powering up the racks.

3. All the boards take about 1 minute to run their self-tests.

Refer to BSS Methods Handbook to check LED states.

3BK 17416 3001 RJZZA Ed.03 25 / 61

Page 26: BSC commissioning B7

4 Checking the Power Supply and Powering Up

26 / 61 3BK 17416 3001 RJZZA Ed.03

Page 27: BSC commissioning B7

5 Installing the BSC Terminal and BSS SW

5 Installing the BSC Terminal and BSS SW

This chapter describes installation procedures for the following software:

BSC Terminal and X.25 communication board

Craft Terminal

BSS software

3BK 17416 3001 RJZZA Ed.03 27 / 61

Page 28: BSC commissioning B7

5 Installing the BSC Terminal and BSS SW

5.1 Installing the BSC Terminal Software and the X.25Communication Board

Purpose to install:

the X.25 communication board in Windows environment

the "BSC Terminal" software in Windows environment

5.1.1 Install EICON C31 Board

To install the EICON C31(for notebook) board in Windows environment, refer to“BSS Methods Handbook”.

5.1.2 Install Windows BSC TerminalProcedure To install BSC Terminal software for Windows, refer to BSS Methods Handbook .

5.2 Installing the Craft TerminalTo install the LMT-CT Craft Terminal program on the PC, refer to “BSS MethodsHandbook”.

5.3 Installing the BSS SoftwarePurpose To install the BSS software on the PC and to print the “CONTENTS.LST”

5.3.1 Case 1: Build is Delivered on Floppy Disks

Procedure 1. On the notebook create the following directory(ies):

C:\BUILDBSS\B7\’Name of the customer build’

2. Copy all the build delivery compressed files (gzip) from floppy disks to thenew created directory (all files in same directory).

3. Copy gzip.exe from C:\Program Files\Alcatel\WINBSC\B7 toC:\BUILDBSS\B7\”Name of customer build”

4. Open a command prompt window:

Start ⇒ Programs ⇒ Command Prompt

5. In the command prompt window enter the following commands:cd \BUILDBSS\B7\Name of customer buildgzip -dvN *.gz

Note: *.gz means all the files in the current directory with the extension gz.

All the gzip files are uncompressed.

6. Using a text editor (eg. Notepad) open the “CONTENTS.LST” file.

7. Check the BSC master file (i.e. bscmxtxx) version specified in“CONTENTS.LST” against the requested customer version.

Refer to “BSS software list”

28 / 61 3BK 17416 3001 RJZZA Ed.03

Page 29: BSC commissioning B7

5 Installing the BSC Terminal and BSS SW

5.3.2 Case 2: Build is Delivered on IOMEGA ZIP Disk

In this case it is mandatory for the notebook to have an IOMEGA ZIP driveinstalled.

Procedure 1. On the notebook create the following directory(ies):

C:\BUILDBSS\B7\’Name of the customer build’

2. Copy all the build delivery files from the IOMEGA ZIP disk to the newcreated directory.

3. Copy gzip.exe from C:\Program Files\Alcatel\WINBSC\B7 toC:\BUILDBSS\B7\”Name of customer build”

4. Open a command prompt window:

Start ⇒ Programs ⇒ Command Prompt

5. In the command prompt window enter the following commands:cd \BUILDBSS\B7\Name of customer buildgzip -dvN *.gz

NOTE : *.gz means all the files in the current directory with the extension gz.

All the gzip files are uncompressed.

6. Using a text editor (eg. Notepad) open the “CONTENTS.LST” file.

7. Check the BSC master file (i.e. bscmxtxx) version specified in“CONTENTS.LST” against the requested customer version.

Refer to “BSS software list”

3BK 17416 3001 RJZZA Ed.03 29 / 61

Page 30: BSC commissioning B7

5 Installing the BSC Terminal and BSS SW

30 / 61 3BK 17416 3001 RJZZA Ed.03

Page 31: BSC commissioning B7

6 Commissioning Tests

6 Commissioning Tests

This chapter describes the following tasks:

Relocation of system CPRCs

Loading and activating the BSC software

Checking battery backup of S-CPRC boards

Correcting the BSC date and time

3BK 17416 3001 RJZZA Ed.03 31 / 61

Page 32: BSC commissioning B7

6 Commissioning Tests

6.1 Relocation of System-CPRCsPurpose To move the S-CPRC PBAs from their transport positions to their operational

positions.

Use the antistatic wrist strap when working in contact with the BSCboards, otherwise permanent damage could be caused to the boards.

Procedure Move the S-CPRC PBAs from their transport positions to their operationalpositions as follows:

PBA in position 23 (transport) to position 21 (operational).

PBA in position 27 (transport) to position 25 (operational).

System CPRCs are in operational position. The boards run their self-testsfor about 1 minute. When the bottom LED is blinking they are requestingto be loaded.

Refer to BSS Methods Handbook for LEDs meaning

6.2 Loading and Activating the BSC SoftwarePurpose To prepare the X.25 link by downloading the minibuild

To configure the first BIUA module of each rack with a generic file

Option: To upgrade the TSCA firmware to B7

To load and activate the BSC software.

6.2.1 Prepare X.25 Configuration Link

Procedure 1. Connect the COM1 port of the BSC Terminal to the 9 pin connector of thesystem CPRC 1 (SAU 08 position 21) using the CPRC serial cable

Refer to Tools Catalogue for cable reference.

2. To run ‘BSC Terminal B7’, from the Taskbar, select:

Start ⇒ Programs ⇒ WinBSC ⇒ B7 ⇒ Windows BSC TerminalB7

The following window appears:

32 / 61 3BK 17416 3001 RJZZA Ed.03

Page 33: BSC commissioning B7

6 Commissioning Tests

3. Select serial connection and Logging in the ‘BSC Communication Control’window and click [ Connect ].

4. In the ‘Windows BSC Terminal’ window select:

Utilities ⇒ Minibuild Loading

The ‘Minibuild Loading’ window opens:

5. Give the path of the minibuild directory in the “Directory Path” field (as inthe figure) field using the Browse button. Select Available Files ‘bssmini.*’and click [ Go! ]

Refer to BSS Methods Handbook to monitor the progress of the downloadby observing the LEDs on the CPRC PBA.

The files are automatically downloaded.

When the download is complete, a successful report message appears.

Check the lower right corner in “Windows BSC Terminal” windows to monitorcommunication between PC and BSC equipment (’the message has been

sent to BSC...’ and a reply has been received).

6. Exit Windows BSC Terminal:

Click the shortcut exit button (top right corner in the “Windows BSCterminal” window)

Click [ Yes ] to confirm the close connection message below:

3BK 17416 3001 RJZZA Ed.03 33 / 61

Page 34: BSC commissioning B7

6 Commissioning Tests

6.2.2 Configure the Rack’s First BIUA with the Generic File

Procedure 1. Connect the LMT Terminal to the first BIUA PBA using LMT-CTTerminal/MMI cable.

2. Run ‘Craft Terminal B7’:

Double click the LMT Terminal SW icon.

When the password window appears, click the [ OK ] button.

The Alcatel Main Menu appears:

3. In the Alcatel Main Menu Select: Session ⇒ Connect

The Craft Terminal software establishes the connection with the BIUA board:

4. In the “BIUSC” Menu select:

Options ⇒ Data ⇒ Download

and in the “Write Block” window click [ Browse ].

5. In the “Open” window select, using “Folders” field, the transmission datafile corresponding to the module rack position:

⇒ LMT-CT ⇒ Setting...

See Hardware Description - Racks Configuration (Section 1.1)

34 / 61 3BK 17416 3001 RJZZA Ed.03

Page 35: BSC commissioning B7

6 Commissioning Tests

6. Click [ OK ].

In the “Write Block” window click [ OK ] again, and wait for the successful‘Report’ window below:

7. In the “BIUSC” Menu, disconnect the board link by selecting:

Session ⇒ Disconnect

The “Alcatel” menu is activated.

Disconnect the RS232 cable from BIUA board.

8. Repeat the section Configure the Rack’s First BIUA with the Generic File, forthe first BIUA module of each BSC rack.

6.2.3 Check and Upgrade the TSCA FW

This upgrade MUST be performed if the TSCA FW does not correspond torelease B6 or B7!

Purpose To upgrade the TSCA FW from B5 to B6 (even if the commissioning of BSCis done in B7).

6.2.3.1 Check the FW Version of the TSCA Board

Procedure 1. Connect the LMT Terminal to the first TSCA PBA using LMT-CTTerminal/MMI cable.

2. Run Craft Terminal B6.2 (CTB62xx):

Double click the LMT Terminal SW icon.

When the password window appears, click the [ OK ] button.

The Alcatel Main Menu appears:

3BK 17416 3001 RJZZA Ed.03 35 / 61

Page 36: BSC commissioning B7

6 Commissioning Tests

3. In the Alcatel Main Menu Select:

TSC ⇒ Download Migration Software

4. If the connection is not established, the FW version is for release B6 orhigher and no FW upgrade is required .

5. If the Craft Terminal software establishes the connection with the TSCAboard an update of FW is required .

6. Upgrade TSCA firmware to FW B6, if applicable. (see InformationRequired )

6.2.3.2 If Applicable, Upgrade TSCA Firmware from B5 to B6

Install the SW on the PC 1. Create the directory TSC_FW on the PC.

2. Copy the firmware delivery for release B6 (TSCSAQxx.0xx – see “BSSSoftware List”) from the floppy disk into the TSC_FW directory.

3. Leave the diskettes of the installed software in the site documentation.

Upgrade TSCA to FW B6 1. The Craft Terminal sets up the connection with the TSCA board, followingthe command already given at LMT CT B6.2:

TSC ⇒ Download Migration Software

2. The following messages appear:’Waiting for Download Request from TSC...’Download of Both Code and Data Requested. Proceed?’

Click [ OK ]. The program asks for the TSC CODE file.

3. Select the file that you installed in the TSC_FW directory:C:/TSC_FW/TSCSAQxx.0xx

Choose this file and click [ OK ].

The following message appears:’TSC is currently erasing a page of memory.’

And then download starts.

4. ’Download of Data Requested. Proceed?’ appears.

Click [ OK ].

5. Select the file with data from the LMT CT directory:.../LMT_CT/B7/Settings/g2/tsca/empty_db.tsc

Choose this file and click [ OK ].

36 / 61 3BK 17416 3001 RJZZA Ed.03

Page 37: BSC commissioning B7

6 Commissioning Tests

6. Wait for the TSC to download successfully.

After the TSCA board has been downloaded wait approximately 10 minutes.

7. Manually reset the board.

After the TSCA board has been reset, the B6 firmware should be activeand will start sending a load request via TSL.

8. Apply the same procedure for each TSCA board.

6.2.4 Format Disk A

Set up the X.25Communication Link

1. Connect the X.25 number 0 port of the BSC Terminal to the 25 pin connectorof system CPRC 1 (SAU 08 position 21) using CPRC parallel cable.

Refer to Tools Catalogue for cable reference type.

2. Open a new session and select the X.25 link.

3. Select X.25 connection and Logging in the ‘BSC Communication Control’window and click [ Connect ].

If an “X25 Link” error message window appears verify the link with the BSCequipment and repeat the last two steps again.

Format Disk A 4. In the ‘Windows BSC Terminal‘ main menu select:

Commands ⇒ Disk operations ⇒ Format SSD

the ‘Format SSD’ window opens.

5. In the “Directory Path” field enter the full path to the BSS directory using the[ Browse ] button (e.g.: C:\BUILDBSS\BSSS7_1 ).

6. Select [ Disk A. ]

A list of files that can be used to format the SSD appears.

7. Select the BSS-masterfile xxxMxTxx . xxx and click [ Enter ].

8. Click [ Go! ] to initiate SSD formatting.

When SSD formatting is complete, a report appears showing the resultof the formatting.

6.2.5 Load the BSS Software onto Disk A

Procedure 1. In the ‘Windows BSC Terminal‘ main menu select:

Commands ⇒ Disk operations ⇒ File Transfer from PCto BSC

The BSS File Directory window opens:

3BK 17416 3001 RJZZA Ed.03 37 / 61

Page 38: BSC commissioning B7

6 Commissioning Tests

2. In the “Directory Path” field enter the full path to the BSS directory using the[ Browse ] button (e.g.: C:\BUILDBSS\BSSS7_1 )

3. Select the BSS-masterfile xxxMxTxx . xxx and click [ Enter ]

4. Specify the Destination Disk. Select [ Disk A ]

5. In the ‘Files To Transfer’ window the files to be transferred are displayed.

6. Click [ Go! ] to initiate the file transfer (Start Download)

7. Check the reports.

6.2.6 Check the Content of Disk A

Procedure 1. To generate and print out the content of disk A, from the ‘Windows BSCTerminal‘ main menu select:

Commands ⇒ Disk operations ⇒ Control SSD

2. Select the parameters as in the ‘Control SSD’ window below and thenclick [ OK ]

3. In the ‘Windows BSC Terminal’ window check the command reports

4. Compare the content of disk A, shown in the reports window, with theCONTENTS.LST file.

6.2.7 System Initialization

Procedure 1. In ‘Windows BSC Terminal‘ select the following menu path:

Commands ⇒ System Activation ⇒ System initialization

’System Initialisation’ window opens.

38 / 61 3BK 17416 3001 RJZZA Ed.03

Page 39: BSC commissioning B7

6 Commissioning Tests

2. Select the parameters as in the ‘System Initialisation’ window above andthen click [ OK. ]

All BSC boards, including NE and TSCA, upload the software stored inCPRC board.

The loading procedure is indicated by the LEDs on the board front panels.

Refer to BSS Methods Handbook describing the various LED states forthe different boards.

After the system initialization command the BSC Terminal loses the X.25connection with the BSC.After about 5 minutes, reestablish the link by closing and reopening BSCTerminal.

3. Wait about 20 min. for the successful report.

BSC is successfully initialized.

Verify that all CE’s are equipped. If CE missing, run Hardware Test toinvestigate.

6.2.8 Set to "OPR" the SBLs of the Declared BTSs

Procedure 1. In ‘Windows BSC Terminal‘ select:

Commands ⇒ Equipment Handling ⇒ SBL Disable

2. Select the parameters as in the ‘SBL Disable’ window below:

3. In the "Unit number" field enter the parameter number from thecorresponding BTSs. (see Information Required)

4. Click [ OK ] and wait for the successful report.

6.2.9 Check Board Status

Procedure 1. To generate and print out the states of the faulty SBLs, in ‘Windows BSCTerminal’ select:

Commands ⇒ Equipment Handling ⇒ SBL State List

3BK 17416 3001 RJZZA Ed.03 39 / 61

Page 40: BSC commissioning B7

6 Commissioning Tests

2. Select the parameters as in the ‘SBL State List’ window below and thenclick [ OK ]

3. In the ‘Windows BSC Terminal’ window check the reports to verify that all theCPR, DTC, TCU, TSC and SWITCH SBLs of the BSC are "In Traffic". Theyshould not appear in the State List command report

The State List command displays the states of all SBLs that are not "In Traffic".In the ‘Windows BSC Terminal’ window use the mouse to double-click on thecompressed report message any time you want a “Full Report View”.

6.2.10 Format Disk B

Procedure 1. Disable Alarm Reports (Disabling / Enabling Alarm Reports (Appendix D))

If the sequence of operations is blocked at any time, apply Workaround:Exit/Connect WinBSC Terminal (Appendix E) for restarting the BSCTerminal.

2. In ‘Windows BSC Terminal’ select:

Commands ⇒ Disk Operations ⇒ Format Duplex SSD

3. In ‘Format Duplex SSD’ enter the "Source - Destination" parameter andclick [ 0K ]

4. Check the reports to see if the action was successful.

5. Wait for the final report “FILE TRANSFER RESULT”.

6.2.11 Copy the BSS Software to Disk B

Procedure 1. In ‘Windows BSC Terminal’ select the following menu path:

Commands ⇒ Disk Operations ⇒ File Transfer from BSCto BSC

40 / 61 3BK 17416 3001 RJZZA Ed.03

Page 41: BSC commissioning B7

6 Commissioning Tests

2. Enter the Source and Destination disk parameters, select “All Files” andclick [ OK ]

3. In the ‘Windows BSC Terminal’ window check the reports (check to see thatthe BOOTROOT file already exists on disk B).

6.2.12 Check the Content of Disk BProcedure Repeat the instructions in section 6.2.6 for Disk B.

6.2.13 Activate Disk B

Procedure 1. In the ‘Windows BSC Terminal’ main menu select:

Commands ⇒ Equipment Handling ⇒ SBL Initialise

2. Click [ 0K ]

3. Enable Alarm Reports (See Disabling / Enabling Alarm Reports (AppendixD))

4. Check the message report.

6.3 Checking Battery Backup of S-CPRC BoardsPurpose To check that the content of the S-CPRC disks is not altered (safeguarded by

the internal battery backup) by a loss of BSC power supply.

Procedure 1. At the customer power panel switch OFF the breakers for the two BSCbranches (A and B).

BSC is powered down.

2. At the customer power panel switch ON the breakers for the two BSCbranches (A and B).

BSC is powered up and starts initialization.

3. Wait for BSC initialisation to finish (follow the different LED states).

Refer to BSS Methods Handbook for LED states

3BK 17416 3001 RJZZA Ed.03 41 / 61

Page 42: BSC commissioning B7

6 Commissioning Tests

4. Check the board status as described in 6.2.9.

The respective SBLs are “IT”.

5. Check the content of the S-CPRC disks (A and B) against the“CONTENTS.LST” file.

Refer to the sections 6.2.6 and 6.2.12

The content of the S-CPRC disks was not altered by the loss of power supply.

6.4 Correcting the BSC Date and Time

Procedure 1. In ‘Windows BSC Terminal’ select the following menu path:

Commands ⇒ Date & Time ⇒ Modify Date & Time

2. Select the parameters as in the example ‘Modify Date and Time’ windowbelow and then click [ OK ]

6.5 Option: Testing the External AlarmsPurpose To verify the external alarms sent to the BSC Terminal..

If the external alarms are not looped at the DDF, the external alarms should beactive at the BSC Terminal.They will remain active until they are either connected or looped.If they are looped at the DDF, the procedure will entail checking that they arecorrectly sent to the BSC Terminal by opening them in turn.

Procedure 1. If the external alarms cables are installed, simulate the alarms, one by one,at the DDF side, by inserting disconnect terminals.

See Information Required

The corresponding alarms are reported at the BSC Terminal. Example:Alarm Class: 32 EnvironmentalAlarm type: 002-EXT-ALARM

2. Remove the disconnect terminals, one by one.

The corresponding alarms disappear.

42 / 61 3BK 17416 3001 RJZZA Ed.03

Page 43: BSC commissioning B7

7 Option: Hardware Test

7 Option: Hardware Test

This chapter describes the following sequence of hardware tests in “off-line”mode, applied for BSC configuration 3 or higher:

Network test

Broadcast test

Clock test

3BK 17416 3001 RJZZA Ed.03 43 / 61

Page 44: BSC commissioning B7

7 Option: Hardware Test

7.1 BSC Hardware Test

This test applies only for BSC configuration 3 or higher, to check theinter-rack cabling.For a BSC in configuration 1 or 2 the Hardware Test is not needed.

Purpose To perform the following sequence of hardware tests in “off-line” mode:

Network test to detect failures in the switching network cabling.

Broadcast test to detect failures in the broadcast bus cabling and faultyPBAs.

Clock test to detect failures in the clock distribution bus cabling. It also

detects faulty PBAs.

Before the BSC can be tested, it must be in the idle state ( software in all theControl Elements (CE) is running in the idle mode).

Preparing the BSCfor Test

1. Reboot the BSC in “off-line test” mode

From the ”Windows BSC Terminal” window main menu, select:Commands ⇒ Commissioning Tests ⇒ BSC System TestInitThe “BSC System Test Init” window opens.

Select the parameters as in the “BSC System Test Init” window below:

Click [ OK ]A message indicating that the command has been sent to the BSCappears in the lower left corner of the “Windows BSC Terminal” window.

Wait about 20 min. for BSC to run in the test mode. (Wait about 5min,

exit and reconnect the BSC Terminal).When the BSC is in test mode, both top LEDs are blinking fast.

Network Test 2. In the ”Windows BSC Terminal” main menu select:

Commands ⇒ Commissioning Tests ⇒ Test Facilities forG2 ⇒ Network Test

The “Network Test” window opens.

Select the parameters as in the “Network Test” window below and click [ OK ]

44 / 61 3BK 17416 3001 RJZZA Ed.03

Page 45: BSC commissioning B7

7 Option: Hardware Test

Wait for the report message and try to fix the problem, if there is one.

note down the given address.

find the given address in the Inter Rack Cable List and check the

corresponding cables for their addresses on both racks.

Use the mouse to double-click the compressed report message any time youwant a “Full Report View”).

If one or more BSC test reports are not successful the report will providethe identities of the network addresses of the links on which the mosterrors were detected

Refer to “BSS Methods Handbook” for cable and plug descriptions.

See Example of Inter Rack Cabling in appendix

Broadcast Test 3. In the ”Windows BSC Terminal” main menu select:

Commands ⇒ Commissioning Tests ⇒ Test Facilities forG2 ⇒ Broadcast Test

The “Broadcast Test” window opens

Select the parameters as in the “Broadcast Test” window below and click[ OK ]

Wait for the successful report message.

Clock Test 4. In the ”Windows BSC Terminal” main menu select:

Commands ⇒ Commissioning Tests ⇒ Test Facilities forG2 ⇒ Clock Test

The “Clock Test” window opens.

Select the parameters as in the “Clock Test” window below and click [ OK ]

3BK 17416 3001 RJZZA Ed.03 45 / 61

Page 46: BSC commissioning B7

7 Option: Hardware Test

Wait for the successful report message.

If any hardware test fails, try to identify the problem and fix it. Repeat all thehardware tests if necessary. If the failure persists, check the cabling betweenthe racks (see BSS Methods Handbook)!

7.2 Reboot the BSC in OPERATIONAL Mode

Procedure 1. From the ”Windows BSC Terminal” window main menu, select:

Commands ⇒Commissioning Tests ⇒BSC System Test Init

“BSC System Test Init” windows opens.

2. Select the parameters as in the “BSC System Test Init” window below:

3. Click [ OK ]

A message indicating that the command has been sent to the BSC appearsin the lower left corner of the “Windows BSC Terminal” window.

4. Wait about 15 min. for BSC to run in operational mode. (Exit and reconnectthe BSC Terminal)

When the BSC is in operational mode both bottom LEDs are blinking fast.

5. Check board status. (See 6.2.9)

CPR, DTC, TCU, TSC and SWITCH SBLs are “IT”.

46 / 61 3BK 17416 3001 RJZZA Ed.03

Page 47: BSC commissioning B7

8 Option: Checking the BSC-TC Link

8 Option: Checking the BSC-TC Link

This chapter describes how to check the BSC - TC link.

3BK 17416 3001 RJZZA Ed.03 47 / 61

Page 48: BSC commissioning B7

8 Option: Checking the BSC-TC Link

Purpose To remove the loops at the DDF for AterMux PCMs on the BSC side andcheck the alarm reported by ASMB boards.

To check the state of A trunk SBLs.

Apply the following task only if the TC is installed and connected atthe DDF on the BSC site.

Remove the AterMuxLoops

1. At the DDF on the BSC side remove the loops for the AterMux PCMs thatare connected to TC equipment. (See Information Required)

2. Open the LMT Terminal application and connect the RS232 cable to thenotebook (COM).

Check the Alarms on theASMB Boards

3. For each ASMB board that corresponds to the removed loop at the DDF:

connect the serial cable to the board

Session ⇒ ConnectThe message ’SM2M connection established’ appears

Click [ OK ]

Choose: Services ⇒ Alarm Collection

Case 1: A interface cables are looped at TC site

See Information Required

Check that the message “No Alarms Detected ” appears, meaning that the TClink has no alarms.

Case 2: A interface cables are connected to MSC

See Information Required

Check that for the A tributaries connected to MSC there are no alarms. Alsocheck there are no alarms for the “Highway an control module”.

Check the Status of Atrunk SBLs

4. At the BSC Terminal:

Commands ⇒ Equipment Handling ⇒ SBL Read Status

Then enter the following:

Object class: > SBL

Unit Type: > BSC

Unit Number: > 1

SBL Type: > ATR

Nbr: > A trunk number

(corresponding to the number of the A trunk connected to the MSC orlooped at the TC)

SbNbr: > 255

5. Click [ OK ]

6. Check that the ATR SBL is “in traffic” in the report window.

7. Repeat steps 4 to 6 for all the A trunks that are connected to the MSC(corresponding to the AterMux PCMs connected to the TC).

48 / 61 3BK 17416 3001 RJZZA Ed.03

Page 49: BSC commissioning B7

9 Setting and Checking the BSC - OMC-R Link

9 Setting and Checking the BSC - OMC-R Link

This chapter describes how to set up the BSC - OMC-R link.

3BK 17416 3001 RJZZA Ed.03 49 / 61

Page 50: BSC commissioning B7

9 Setting and Checking the BSC - OMC-R Link

Purpose To set up the BSC - OMC-R link (only if the BSC is linked to the OMC via theX.25 network) and to test the connection.

Physical ConnectionThis part applies only if the BSC is linked to the OMC via the X.25 network.

1. Connect the modem to the 25-way connector (reference 3BK 07784 GLAA)on CPRC board C (subrack 8, slot 17).

On the modem LEDs 103 and 104 must be ON.

On the CPRC C board the top LED must be OFF.

2. At BSC Terminal verify the alarms.

The "Unsolicited Alarm Report" should appear.

This message indicates that the X.25 link has been reestablished.

Test the Communication 1. At OMC-R site ask the operator to check at OMC-R that the BSC - OMC-Rlink is operational.

The operator confirms the link is operational.

2. At BSC site check the X.25 SBL status.

The corresponding X.25 SBL is “IT”.

3. At OMC-R site perform a Software Audit of the BSS equipment.

Wait for the software audit report message.

4. At OMC-R site check for Communication Error Reports in the “BSS_xxFollow up” message window.

No communication errors must appear.

50 / 61 3BK 17416 3001 RJZZA Ed.03

Page 51: BSC commissioning B7

10 Finishing Commissioning

10 Finishing Commissioning

This chapter describes the tasks that have to be performed at the end ofcommissioning.

3BK 17416 3001 RJZZA Ed.03 51 / 61

Page 52: BSC commissioning B7

10 Finishing Commissioning

Purpose To ensure that commissioning is totally complete, and a copy of all reports fromthe commissioning of the BSC equipment is left with the equipment on site.

Procedure 1. Close the doors of the racks.

2. Leave the site tidy.

3. Close the site and hand the keys to the keyholder.

4. Return the completed forms and the inventory files relating to the operationto base.

52 / 61 3BK 17416 3001 RJZZA Ed.03

Page 53: BSC commissioning B7

Appendix A : Abbreviations

Appendix A: Abbreviations

ASMC Ater submultiplexer C

Ater Interface link between TC and BSC

BSC Base Station Controller

BSS Base station subsystem

DDF Digital distribution frame

CCL Completion check list

CPRC Control processor board

DDF Digital distribution frame

GSM Global System for Mobile communications

G2 Second generation

ITL-PRO Procedure technical and support information

IO Instruction Operation

NE Network Elements (i.e.: BIUA, ASMB ...)

PCM Pulse Code Modulation

SAU Subrack unit

SR Subrack

TC Transcoder

3BK 17416 3001 RJZZA Ed.03 53 / 61

Page 54: BSC commissioning B7

Appendix A : Abbreviations

54 / 61 3BK 17416 3001 RJZZA Ed.03

Page 55: BSC commissioning B7

Appendix B : List of items required

Appendix B: List of items requiredList of Documents

RequiredThe following table is used to check, at base, the availability of the necessarydocuments.

Document Title Reference

Catalogue of Technical and Logistic Information (ITL) 3DF 00462 0004 AAAGA

Catalogue of Instruction Operation (IO) 3DF 00300 0004 UAZZA

BSS Methods Handbook - release B7 3BK 17416 0002 PCZZA

Tools Catalogue for Field Activity 3BK 20458 0001 RJZZA

SPP-27, Specification for site preparation G2 BSC 8BL 00704 0016 DRBRA

BSS site premises inspections, post handover 8BL 00704 0016 DRBRA

Site premises inspections form (CEL) 8BL 00704 0015 DRBRA

Completion Check List (CCL) 3BK 17416 3001 QZZZA

CI-08 Site Equipment Inventory 3BK 17257 0001 RJZZA

BSS software list Depending of the software versionrequested by the customer

List of tools required The following table is used to check, at base, the availability of the necessarytools.

See Tools Catalogue for checking the content

Kit name Reference Calibration

Basic kit OUT 001 No

Test cables and plugs (G2 BSC) OUT 013 No

Digital multimeter DES 001 No

Utility PC (BTS LMT) DES 002 No

Inventory kit Nr. 7 OUT 017 No

3BK 17416 3001 RJZZA Ed.03 55 / 61

Page 56: BSC commissioning B7

Appendix B : List of items required

List of SoftwareRequired

The following table is used to check, at base, the availability and the versionof the necessary software.

Refer to the corresponding document for checking the SW version.

Name Version checking

Operating system See Tools Catalogue

BSC Terminal/BSCWATxxx BSS Software List

LMT_CT/CTxxx.exe BSS software list

TSCSAQxxx BSS software list

BSSBUILD BSS software list

EICON card driver for Windows NT BSS software list

56 / 61 3BK 17416 3001 RJZZA Ed.03

Page 57: BSC commissioning B7

Appendix C : Example of Inter-Rack Cabling

Appendix C: Example of Inter-Rack Cabling

Figure 7: Connecting extension loom

3BK 17416 3001 RJZZA Ed.03 57 / 61

Page 58: BSC commissioning B7

Appendix C : Example of Inter-Rack Cabling

1. Run the interconnection loom at the rear of the racks (fig.7). Use theaddresses written on the end cable labels (fig.7).

2. Connect the cables to the rear of the racks.

The addresses locate a locking latch (1 fig 8), and the connector mustbe plugged just below it (2 fig.8).

3. Tie the cables to the racks.

Example (fig.8) : 03::36BA03

Subrack 03

Slot 36

Board connector BA

Locking latch address 03

1

2

01

04

07

10

13

16

19

22

25

28

31

0103

07

10

13

16

19

22

25

28

31

AA

BA

Figure 8: Locking latch address

58 / 61 3BK 17416 3001 RJZZA Ed.03

Page 59: BSC commissioning B7

Appendix D : Disabling / Enabling Alarm Reports

Appendix D: Disabling / Enabling Alarm ReportsPurpose

To disable Alarm Reports during files transfers between PC and BSC

equipment. This measure is taken to avoid unsuccessful file transfers.

To enable Alarm Reports when file transfers are finished.

1 Disable Alarm Reports

Procedure 1. From the ‘Windows BSC Terminal’ main menu:

Commands ⇒ Alarm Handling ⇒ Enable PC Report

2. Select the parameters as in the window below and then click [ OK ]

3. In the ‘Windows BSC Terminal’ window check the report message.

2 Enable Alarm Reports

Procedure 1. From the ‘Windows BSC Terminal’ main menu:

Commands ⇒ Alarm Handling ⇒ Enable PC Report

2. Select the parameters as in the window below and then click [ OK ]

3. In the ‘Windows BSC Terminal’ window check the report message.

3BK 17416 3001 RJZZA Ed.03 59 / 61

Page 60: BSC commissioning B7

Appendix D : Disabling / Enabling Alarm Reports

60 / 61 3BK 17416 3001 RJZZA Ed.03

Page 61: BSC commissioning B7

Appendix E : Workaround: Exit/Connect WinBSC Terminal

Appendix E: Workaround: Exit/Connect WinBSCTerminal

Purpose To exit from the WinBSC Terminal interface any time the sequence ofoperations is blocked.

Procedure 1. To exit from Windows BSC Terminal, click the shortcut exit button (top cornercorner in the ‘Windows BSC Terminal‘ window)

2. The following message window appears:

3. To close the connection choose [ Yes ]

4. To run ‘BSC Terminal B7’, from the Taskbar, select:

Start ⇒ Programs ⇒ WinBSC ⇒ B7 ⇒ Windows BSC TerminalB7

The following window appears:

5. In the ‘BSC Communication Control’ window select:

X25 for “Link Selection” and the “Logging” option and click [ Connect ]

If an ’X25 Link error’ message window appears verify the link with the BSCequipment and repeat the last two steps again.

3BK 17416 3001 RJZZA Ed.03 61 / 61