35
Borough of Hanover The Case Study of a Phased, Complete System Upgrade Michael J. Mehaffey, P.E. Trisha L.K. Graves, P.E. May 12, 2016

Borough of Hanover The Case Study of a Phased, Complete

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Borough of Hanover The Case Study of a Phased, Complete

Borough of Hanover

The Case Study of a Phased, Complete System Upgrade

Michael J. Mehaffey, P.E.Trisha L.K. Graves, P.E.

May 12, 2016

Page 2: Borough of Hanover The Case Study of a Phased, Complete

System Description

• Area Served by Hanover Water: – York and Adams County, PA - Conewago Twp.,

Hanover Borough, McSherrystown Borough, Penn Twp.

• Approximately 40,000 individuals served• Over 50% of water is used for commercial

and industrial• Source Water:

– Primary – South Branch Conewago Creek (Sheppard Myers Dam, Lawrence Baker Sheppard Dam)

– Secondary – Slagles Run

Page 3: Borough of Hanover The Case Study of a Phased, Complete

System Description (con’t)

• Pre-Sedimentation:– Clear Lake Reservoir – 66 MG man-made lake

• Water Treatment Plant– Two parallel conventional treatment process trains,

“Old Plant” and “New Plant”

• Distribution System and Storage– 202 miles of piping from 4” to 20”– Two elevated storage tanks (750,000 gallons total)– Parr’s Hill reservoirs (13 MG storage)– Parr’s Hill Pump Station (Max 1,230 gpm to high

service zone)

Page 4: Borough of Hanover The Case Study of a Phased, Complete

Initial Evaluations/Permitting

• Water Allocation Permit– Renewal of 1990 permit submitted in 2013

• Dam Inspections– Completed for all 3 dams annually beginning in 2012– Numerous “red flags” noted during inspections

• Water Treatment Plant Evaluation– Completed in mid-2013

• Parr’s Hill Evaluation – Completed in early 2013

Page 5: Borough of Hanover The Case Study of a Phased, Complete

Initial Condition Assessment

Base Map Morning Glory Intake Tower

Auxiliary Spillway Ogee Crest

Auxiliary Spillway Chute

Sheppard-Myers Reservoir

Principal Spillway Wasteway Channel

Unnamed Tributary

South Branch Conewago Creek

Page 6: Borough of Hanover The Case Study of a Phased, Complete

Sheppard Myers Dam Evaluation

• Evaluation Completed June 2013– Demolish existing spillway and

construct a new labyrinth spillway and stilling basin

– Embankment modifications– Construct new headwall structure– Install new drainage along

embankment– Install toe drain weir box to measure

seepage

Page 7: Borough of Hanover The Case Study of a Phased, Complete

Sheppard Myers Dam Evaluation

• Design anticipated to begin in 2016• Construction Cost Estimate - $6 million

Page 8: Borough of Hanover The Case Study of a Phased, Complete

Parr’s Hill Reservoir & Pump Station

• 13 million gallons finished water storage• New cover and liner installed • New pump station for vertical can pumps• Existing pump station reused to house stand-

by generator

Page 9: Borough of Hanover The Case Study of a Phased, Complete

2014 Parr’s Hill Reservoir & Pump Station Improvements

Existing Pump Station New Pump Station

Liner Cover

Page 10: Borough of Hanover The Case Study of a Phased, Complete

Raw Water Conveyance/Pre-Sedimentation

• Kitzmiller Raw Water Project

• Description of Clear Lake

Page 11: Borough of Hanover The Case Study of a Phased, Complete

Existing WTP Facility Existing WTP

Page 12: Borough of Hanover The Case Study of a Phased, Complete

Total permitted capacity is adequate to supply current and projected future demands (2040)

• WTP Permitted Capacity (11.6 mgd) is Adequate for Projected Demands

• Historical Production (2003 – 2012)– Average Daily 5.2 mgd– Maximum Day 7.3 mgd– Maximum Day 6.4 mgd (since 2008)

• Projected 2040 Demand (Planning Study)– Average Daily 6.4 mgd– Maximum Day 9.1 mgd

Old Plant,

3.6New

Plant, 8

Page 13: Borough of Hanover The Case Study of a Phased, Complete

Phased Improvement Plan

• Phase 1– Old Plant Improvements, BW Recycle

Modifications, Chemical Systems, Safety, Security, Portions of Electrical and SCADA/I&C Improvements

• Phase 2– New Plant Improvements, High Service

Pumping, Portions of Electrical and SCADA/I&C Improvements

Page 14: Borough of Hanover The Case Study of a Phased, Complete

Clearlake – Phase 2

• Improvements to outlet structure • Influent and effluent control valves added• Level monitoring

Page 15: Borough of Hanover The Case Study of a Phased, Complete

Rapid Mix Improvements

Install Mixerand Baffles in

Existing Chamber

Old Plant(Phase 1)

New Plant (Phase 2)

Page 16: Borough of Hanover The Case Study of a Phased, Complete

Low Duty Pumping Improvements

Old Plant (Phase 1) New Plant (Phase 2)New Pumps and VFDs

New Motors and VFDs

Page 17: Borough of Hanover The Case Study of a Phased, Complete

Old Plant Filter Improvements - Phase 1

• Filtration Process Rebuild– Replaced Underdrain– Install Dual Media– Install Air Scour Equipment– Coat Interior of Filter Boxes– Construct Curbs– Install PLC Controls, MOVs, Instrumentation,

Replace Filter Gallery Piping– Pressure Inject Cracks, Coat Exterior of Boxes

Page 18: Borough of Hanover The Case Study of a Phased, Complete

Old Plant Filter Improvements - Phase 1

Page 19: Borough of Hanover The Case Study of a Phased, Complete

New Plant Filter Improvement - Phase 2

Page 20: Borough of Hanover The Case Study of a Phased, Complete

Backwash Recycle Improvements - Phase 1

Page 21: Borough of Hanover The Case Study of a Phased, Complete

New Roof on Clearwell - Phase 1

Page 22: Borough of Hanover The Case Study of a Phased, Complete

New Chemical Building – Phase 1

• Storage and feed equipment for:– Chlorine (sodium hypochlorite)– Fluoride– Caustic Soda– Sodium Permanganate

• PLC controls and instrumentation• Chemical delivery area• Safety equipment (eyewash and safety

showers)

Page 23: Borough of Hanover The Case Study of a Phased, Complete

Chemical Storage and Feed Systems – Phase 1

Existing New Chemical Building

Page 24: Borough of Hanover The Case Study of a Phased, Complete

pH Adjustment Soda Ash to Caustic Soda

Page 25: Borough of Hanover The Case Study of a Phased, Complete

Gas Chlorine to Sodium Hypochlorite

Page 26: Borough of Hanover The Case Study of a Phased, Complete

Fluoride Drum Storage to Bulk Storage

Page 27: Borough of Hanover The Case Study of a Phased, Complete

High Service Pump Station Improvements (Phase 2)

Page 28: Borough of Hanover The Case Study of a Phased, Complete

Instrumentation, Controls, and Data Acquisition Systems will Improve WTP Performance

• Existing I&C is minimal

• Data acquisition, analyses, control primarily manual

Page 29: Borough of Hanover The Case Study of a Phased, Complete

Instrumentation & Controls – Phase 1

• Primary Control Station & SCADA Programming• Old Plant filter PLC, MOV, instrumentation• Communications network• Backwash water tank controls and

instrumentation• Chemical facilities controls and instrumentation

Page 30: Borough of Hanover The Case Study of a Phased, Complete

Total System Integration - Phase 2

Future Remote System Connections

Page 31: Borough of Hanover The Case Study of a Phased, Complete

Impacts of Phased Approach on WTP

• Old Plant will be in service during construction of New Plant

• Relocation of existing generator• Instrumentation Capabilities

– Local Automated Control – Phase 1– Remote Automated Control – Phase 2

• Construction Sequence of High Service PS• Permitting Impacts

Page 32: Borough of Hanover The Case Study of a Phased, Complete

Outlet Works Intake Tower

Spillway Ogee Crest

Spillway Chute

Long Arm Reservoir

Outlet Works Conduit Outlet

Long Arm Creek

Access Bridge

Flow Gauging Station

Access Road

Benches

Dam Crest

Access Road

Access Gate

Stilling Basin

Caretaker’s House & Maintenance Shed

Page 33: Borough of Hanover The Case Study of a Phased, Complete

Lawrence Baker Sheppard Dam Evaluation

• Evaluation completed January 2016

• Minor Improvements scheduled for summer of 2016

Page 34: Borough of Hanover The Case Study of a Phased, Complete

Kitzmiller Dam

• Evaluation Completed February 2014

• Minor Improvements to be scheduled

Page 35: Borough of Hanover The Case Study of a Phased, Complete

Final Thoughts

• Keeping up with the improvements required for aging infrastructure is a challenge.

• Holistic review of system improvements is important.

• Engaging all stakeholders is critical.• Phasing designs should be used after careful

consideration.

Questions?? [email protected]@gfnet.com