Background• Barmin/ Moneyline are small (developing) scale mines

producing 12 500 tons per month• Moneyline shaft is called Schaapkopje - MR 166• Barmin ( Pty) Ltd mines Waterval - MR 151 and Rietvlei Police

adit - MR 167. Funds for Projects from these two mine are mostly covered from the operating shaft Schaapkopje ( Moneyline 1705 ( pty) Ltd.

• The major purpose for the presentation is to display willingness to comply with all regulations in the Mining Charter and the MPRDA.

• All supporting documents of this presentation have been sent through or we have present with us.

Page 3: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Contents• Ownership• Compliance with Procurement• Employment Equity• Compliance with Human Resource Development• Community Development• Health and Safety• Environmental Management

Page 4: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Ownership• The Ownership is:74% Linda Christina Viljoen - White female26% Ntombikayise Esther Makhoere - Black female

• Directors are:Chris Viljoen - White maleRichard W Atkins - White male

Page 5: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Compliance with Procument• Moneyline uses a list of Suppliers that are BEE compliant.• Where there are no BEE compliant supplier for any particular

good or service, the company uses local non compliant suppliers.NAME OF SUPPLIER BEE LEVEL COPY OF BEE

CERTIFICATEPRODUCT /SERVICE SUPPLIED

Local not Local

MACDONALD STEEL SA 4 attached steel localMAXAM DANTEX SA (Pty) Ltd

8 attached Explosives and accessories not local

GOAL ARMATURE WINDERS cc

4 attached Motor rewinds and electrical spares

local

TRACTOR AND GRADER SUPPLIERS

6 attached Tractors and parts not local - Durban

KWAZULU GAS AND FIRE STOP cc

8 attached gas local

TPS HYRDAULICS cc - Non complaint – Accounting officer letter attached

Hoses and fittings, brake pipes

local

VRYHEID NISSAN (Pty) LTD

5 attached Fleet local

Bearing Man group -- Biggest supplier

3 attached Conveyor belting idlers and bearings

local

Page 6: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Proposed BBBEE / HDSA Procurement Strategy

Page 7: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Employment Equity

Page 8: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Employment Equity cont.• Gender: Admin females = 4 Males = 18 Shaft females = 6 Males = 82

Category African Coloured Indian White

Male Female Male Female Male Female Male Female

Top management             2  

Senior management 2 1         1  

Middle management 1           2  

Junior management 4           2 2 

Core & critical skills 2           4  

Page 9: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Human Resource Development• The company provide workplace training and stipends for 10

Apprentices on Mechanical Engineering. Learnerships done with Services Seta, Anneng cc.

• ABET was offered with No employees willing to attend BUT we are now busy introducing it again to the workforce using our future forum committee.

• 5 Bursaries were awarded to matriculants 2012 who qualified.• The current other school support we engaged in is Scholar

transportation assist.• Our company assists the surrounding school where possible at

all times, i.e building classrooms, kitchen, etc.

Page 10: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

  Year 1 2012/13 Year 2 2013/14 Year 3 2014/15 Year 4 2015/16 Year 5 2016/17

           

Planned RoM Tons (Financial Model) 180,000 180,000 180,000 180,000 180,000

Annual S & LP Funds (R/ RoM ton) 9.76 9.76 9.76 9.76 9.76

Total Funds Allocated (R/Annum)   1 756 800 1 756 800 1 756 800 1 756 800 1 756 800

Unused S & LP Funds accumulated          

Social Development ActivityMaximum

Nos. / AnnumRate / Annum

(2012)   (R)Proposed Allocation of Funds

Human Resources Development Programme    

Literacy and numeracy 60 1 000 0 63 000 66 300 69 930  50 000

Portable skills 20 6 830 0 0 0 136 600 136 000

Skills programmes 15 6 830 0 102 450 102 450 103 563 103 564

Learnership 2 39 420 0 43 362 47 670 52 470 57 700

Bursary 6 40,000 0 248 000 256 800 266 480   266 480

Internship 4 36,000 0 151 200 169 120 167 832 167 832

TOTAL BUDGET FOR HRD PER YEAR

    0 608 012

 

642 340

 

796 875 781 576

Page 11: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Community Development• The company considered the profiles of relevant communities

and identified credible leaders and consultation was done before any project implementation.

NAME OF THESCHOOL

ASSOCIATEDPROJECT WORK DONE

ESTIMATED NUMBEROF BENEFICARIES

ESTIMATEDCOST

Emandleni Police Station Building of R 800,000

4 classrooms 70

Admin block 240

Kitchen 240

Extend Toilets 240

Paving of walk areas 240

Painting of old

classrooms 240

Tholatemba Schaapkopje Admin block 140 R480,000

Kitchen 140

New Toilets 140

Estimated Total R1,280,000

Page 12: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Community Development cont

Page 13: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Health and Safety

Page 14: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Environmental Management• All correspondence with water affairs has been done and

continued consultations. Geohydrology studies have been conducted and continuous borehole monitoring is done.

• The mines utilizes off loading bays and only a day capacity explosives is delivered. Inspector of Explosives Newcastle, does all the necessary inspections.

• The Appointed Occupational hygienist does all the necessary measurements at all relevant points as per Mine Health and safety Act. Quarterly and Annual reports are submitted.

• No Rehabilitation has been done or required to be done to date. Our EMPR stipulates how and when will it be done upon closure of the mines.

Page 15: Barmin (Pty) Ltd/Moneyline 1705 (Pty) Ltd Mines MINING CHARTER BRIEFING

Conclusion• Continuous consultation with the relevant committees and

the Abaqulusi Municipality will be done as to continue building our surrounding communities.

• We give 100% to strive to comply with the Mining Charter, MPRDA and Mine Health and Safety Act.

• We will ensure a good working relationship with all governmental departments at all time ( i.e. DMR, Environmental affairs, etc.)