Part-No. 986988 ProMinent Dosiertechnik GmbH • 69123 Heidelberg • Germany BA vT 013 03/06 GB Operating instructions Magnetically coupled centrifugal pump ProMinent ® von Taine ® 2323 PP and PVDF von Taine ® 2323 PP von Taine ® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM Serial-No. Please enter type + serial number of the pump here ! Please read the manual instructions completely before bringing the machine into service! Do not throw it away! Damage caused by an operator´s error will cancel the right to all warranty claims!

BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Part-No. 986988 ProMinent Dosiertechnik GmbH • 69123 Heidelberg • Germany BA vT 013 03/06 GB

Operating instructions

Magnetically coupled centrifugal pumpProMinent® von Taine® 2323 PP and PVDF

von Taine® 2323 PP

von Taine® 2323 PVDF

Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Serial-No.

Please enter type + serial number of the pump here !

Please read the manual instructions completely before bringing the machine into service!Do not throw it away!

Damage caused by an operator´s error will cancel the right to all warranty claims!

Page 2: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Imprint

Page 2

Imprint:

Operating instructions Magnetically coupled centrifugal pumpProMinent® von Taine® 2323 PP and PVDF© ProMinent Dosiertechnik GmbH, 2010

ProMinent Dosiertechnik GmbHIm Schuhmachergewann 5-1169123 HeidelbergGermany

[email protected]

Specifications subject to change without notice !Printed in Germany

Page 3: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Table of contents

Page 3

TABLE OF CONTENTS

1 General information ........................................................................................... 51.1 Authorized use of the pump ........................................................................................5

1.2 Sound intensity level ...................................................................................................5

2 Safety................................................................................................................... 52.1 Identification of safety instructions in the operating manual........................................5

2.2 Qualification and training of operating personnel........................................................6

2.3 Hazards in the event of non-compliance with safety instructions................................6

2.4 Compliance with regulations pertaining of safety work ...............................................6

2.5 Safety instructions relevant for operation....................................................................6

2.6 Safety instructions relevant for maintenance, inspection and assembly work ............6

2.7 Unauthorized alterations and production of spare parts .............................................7

2.8 Unauthorized modes of operation ...............................................................................7

3 Transportation and storage ............................................................................... 73.1 Transportation .............................................................................................................7

3.2 Storage........................................................................................................................7

3.3 Ambient conditions required for transportation and storage .......................................7

4 Functional characteristics ................................................................................. 74.1 General description .....................................................................................................7

4.2 Design .........................................................................................................................7

4.3 Materials......................................................................................................................8

5 Mounting and installation .................................................................................. 85.1 Examples of mounting.................................................................................................8

5.2 Hoses and tubes .........................................................................................................85.2.1 The suction line.................................................................................................................. 85.2.2 The delivery line................................................................................................................. 8

5.3 Electrical connection ...................................................................................................9

6 Starting and shutdown procedures .................................................................. 96.1 Preparations for starting..............................................................................................9

6.2 Starting procedure.....................................................................................................10

6.3 Operation ..................................................................................................................10

6.4 Shutdown procedure .................................................................................................10

6.5 Safe disposal of waste parts .....................................................................................10

7 Maintenance...................................................................................................... 107.1 General information...................................................................................................10

7.2 Preventive maintenance............................................................................................11

Page 4: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Table of contents

Page 4

7.3 Disassembly of the pump..........................................................................................12

7.4 Re-assembly of the pump .........................................................................................13

8 Troubleshooting ............................................................................................... 159 Technical data................................................................................................... 1610 Spare parts ....................................................................................................... 17

10.1 Exploded view ...........................................................................................................17

10.2 Bill of materials von Taine® 2323 PP/FKM ...............................................................18

10.3 Bill of materials von Taine® 2323 PVDF/FKM ..........................................................18

10.4 Bill of materials von Taine® 2323 PP/EPDM ............................................................19

10.5 Bill of materials von Taine® 2323 PVDF/EPDM .......................................................19

11 Appendix........................................................................................................... 2011.1 Dimensional drawing von Taine® 2323 PP and PVDF .............................................20

11.2 Characteristic curves.................................................................................................21

11.3 Motor data sheet .......................................................................................................22

11.4 EC Declaration of Conformity....................................................................................23

Page 5: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 5

1 General informationThe pump may only be used in the rangeof applications authorized by themanufacturer. In case of modifiedoperating conditions, please consult yoursupplier and / or the manufacturer.

1.1 Authorized use of the pump

• Delivery of low-viscosity liquidsresembling water.

• Delivery of acids, alcaline solutions etc.• Delivery of gaseous fluids.• No other than the authorized use nor

any conversion of the pump arepermitted.

WARNING

Make sure that the materials used forthe pump are resistant to the fluids

being delivered!(see the ProMinent list of resistances)

• If you deliver crystallising fluids, makesure that the fluid does not crystallisewithin the pump. Should this happen,carefully clean all parts being in contactwith the fluid once the pump has beenshut off.

NOTE

Disassembly of the pump will cancelthe right to all warranty claims!

1.2 Sound intensity level

The sound intensity level of this pump is <70 dB (A) according to DIN EN 12639(noise measurement of liquid pumps andpump units).

2 SafetyThis operating manual gives basicinstructions which are to be observedduring installation, operation andmaintenance of the pump. It is thereforeimperative that the manual be read by theresponsible personnel / operator prior toassembly and commissioning. It is alwaysto be kept available at the installation site.

It is not only the general safety instructionscontained under this main heading safetythat are to be observed but also thespecific information provided under theother main headings.

2.1 Identification of safetyinstructions in the operatingmanual

Safety instructions given in this manualnon-compliance with which would affectsafety are identified by the followingsymbol

(see DIN 4844-W9)

or where electrical safety is involved with

(see DIN 4844-W8)

Instructions non-compliance with whichwould give rise to malfunctioning of themachinery are identified by the word

WARNING

It is imperative that signs affixed to themachine, e.g.

arrow indicating the direction of rotationsymbols indicating fluid connectionWarnings to protect the pump from dry-running.

Page 6: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 6

be observed and kept legible.

2.2 Qualification and training ofoperating personnel

The personnel responsible for operation,maintenance, inspection and assemblymust be adequately qualified. Scope ofresponsibility and supervision of thepersonnel must be exactly defined by theplant operator. If the staff does not havethe necessary knowledge, they must betrained and instructed, which may beperformed by the machine manufacturer orsupplier on behalf of the plant operator.Moreover, the plant operator of theoperating manual are fully understood bythe personnel.

2.3 Hazards in the event of non-compliance with safetyinstructions

Non-compliance with the safetyinstructions may produce a risk to thepersonnel as well as to the environmentand the machine and results in a loss ofany right to claim damages.

For example, non-compliance may involvethe following hazards:

Failure of important functions of themachine / plant.Failure of specified procedures ofmaintenance and repair.Exposure of people to electrical,mechanical and chemical hazards.Endangering the environment owing tohazardous substances being released.

2.4 Compliance with regulationspertaining of safety work

When operating the pump, the safetyinstructions contained in this manual, therelevant national accident preventionregulations and any other service and

safety instructions issued by the plantoperator are to be observed.

2.5 Safety instructions relevant foroperation

If hot or cold machine componentsinvolve hazards, they must be guardedagainst accidental contact.Guards for moving parts (e.g. coupling)must not be removed from the machinewhile in operation.Any leakage of hazardous (e.g.explosive, toxic, hot) fluids must bedrained away so as to prevent any riskoccurring to persons or theenvironment. Statutory regulations areto be complied with.Hazards resulting from electricity are tobe precluded (see, for examgple, theVDE Specifications and the bye-laws ofthe local power supply utilities).

2.6 Safety instructions relevant formaintenance, inspection andassembly work

It shall be the plant operator´sresponsibility to ensure that allmaintenance, inspection and assemblywork is performed by authorized andqualified personnel who have adequatelyfamiliarized themselves with the subjectmatter by studying this manual in detail.

Any work on the machine shall only beperformed when it is at a standstill, it beingimperative that the procedure for shuttingdown the machine described in thismanual be followed.Pumps and pump units which conveyhazardous media must bedecontaminated. On completion of work allsafety and protective facilities must be re-installed and made operative again.

Prior to restarting the machine, theinstructions listed under ´Initialcommissioning´ are to be observed.

Page 7: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 7

The pump is magnetically coupled.Attention: Coming in contact with

permanent magnetic parts during repairor maintenance work dangerously

exposes to magnetic forces which, forexample, may influence pacemakers.

Keep your distance!

2.7 Unauthorized alterations andproduction of spare parts

Any modifications may be made to themachine only after concultation with themanufacturer. Using spare parts andaccessories authorized by themanufacturer is in the interest of safety.Use of other parts may exempt themanufacturer from any liability.

2.8 Unauthorized modes ofoperation

The reliability of the machine delivered willbe only guaranteed if it is used in themanner intended, in accordance withclause 1 of this manual. The limit valuesspecified in the data sheet mut under nocircumstances be exceeded.

3 Transportation and storage3.1 Transportation

The pump is delivered by themanufacturer in a ready-to-work state. Inthe event of damages occurring duringand due to transportation, the forwardingagent must make a factual statement. Thepump should always be transportedappropriately and according to the state ofthe art.

3.2 Storage

An eventual storage place must beabsolutely dry. Make sure that the interiorof the pump is protected from pollutants.

3.3 Ambient conditions requiredfor transportation and storage

Temperature range: -10°C to 50°C.Humidity of the air: max. 95 % relativehumidity, non-condensing.

4 Functional characteristics4.1 General description

This magnetically coupled centrifugalpump type von Taine® is a sucking single-stage centrifugal pump made of plasticsand designed in modular system forhorizontal mounting. The pump andelectric motor are connected by amagnetic clutch which transmits the drivepower to the impeller.

4.2 Design

The pump housing, impeller, impellermagnet, and magnet deviding housing aremade of plastics. In the standard version,the center shaft is constructed from oxideceramic whereas the bearings are made ofoxide ceramic. The magnet devidinghousing hermetically seals the fluidagainst all atmospheric influences. Due tothe magnetic power transmission, thecenter shaft needs not to be sealed. Incontrast to mechanically or gland sealedpumps, this system prevents any leakageof fluid at the shaft.

The pump housing parts are sealed bystatic o-rings. The impeller of the pump isa radial-flow wheel.Depending on the fluid to be delivered,each component of the pump is availablein various materials.

Page 8: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 8

NOTE

The materials used are listed on thename plate or the delivery note!

4.3 Materials

Type 2323 PP 2323 PVDFPump housing PP PVDFImpeller PP PVDFImpeller magnet PP PVDFRear casing PP PVDFCenter shaft oxide ceramicBearing oxide ceramicStatic packings FKM or EPDM

5 Mounting and installationThe pump should be installed at a placeallowing easy access at all times. Makesure to meet the following values:

Ambient temperature -10 °C up to +40 °C

Humidity of the air: 95 % relativehumidity, non-condensing

5.1 Examples of mounting

The pump is set up to be mountedhorizontally, but may also be mountedvertically, with the motor componentpointing upwards.

This pump is not self-priming andtherefore requires a feed supply.

[Fig. 5-1]

5.2 Hoses and tubes

The cross-sections of the tubes mustcorrespond to the suction and deliveryports. All suction and delivery tubes to thepump housing should be free of tensilestress. The weight of the tubes must notrest on the housing!

WARNING

Do not install any quick-acting stopvalves into the tubes! Pressure jerks

may damage the pump housing.

5.2.1 The suction line

The suction line must be a tube or hosewhich cannot be deformed by theresulting partial vacuum or by hightemperatures.The suction line must be a tube or hosewhich cannot be deformed by theresulting partial vacuum or by hightemperatures.When dimensioning the tubes, fittingsetc., make sure that the flowresistances are kept as low as possible.

The flow velocity within the pipedsuction line should not exceed the limitof 1m/s

5.2.2 The delivery line

The standard flow velocity within thesuction line is 3m/s.

Page 9: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 9

To be able to adjust the flow rate, werecommend the installation of a controlelement inside the delivery line.

5.3 Electrical connection

The motors should be connectedaccording to the following illustration:

[Fig. 5-2]

All electrical connections to the pumpmay only be performed by experts!

The direction of rotation indicated by anarrow on the pump must be respectedand controlled after installation.

[Fig. 5-3]

WARNING

Do not check the direction of rotationwithout having filled fluid in the pump!

The motor must be equipped with amotor protection switch.The power supply must have been cutfor at least 5 minutes before you maystart any work at the terminal box of thepump.Make sure that the data given onthe name plate corresponds to theexisting power supply.All electrical connections andinstallations of additional protectiondevices should be performed by anexpert in accordance with theinstructions of the local power suppliersand / or the Association of GermanElectrotechnical Engineers VDE.

6 Starting and shutdownprocedures

6.1 Preparations for starting

The pump housing and the suction linemust be filled with water or the fluid tobe delivered.

WARNING

Avoid any dry-running of the pump!

Page 10: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 10

NOTE

We recommend installing dry-runningprotection devices such as flowindicators, contact manometers,

differential pressure switches or levelcontrollers!

Tighten all screwed connections andfittings.

Entirely open all shut-off devices of thesuction and delivery lines.

6.2 Starting procedure

Switch on the motor.Check the direction of rotation of themotor by switching it on and off inimmediate succession. The direction ofrotation must be in accordance with thearrow figuring on the pump.Adjust the operating point by slowlyclosing the shut-off device of thedelivery line. If there is no shut-offdevice installed, the operating point willbe adjusted automatically inaccordance with the pump curve.

WARNING

Do not run the pump with a closeddelivery line for a longer period of time.

This may heat up the fluid inside thepump housing and thus damage

interior components of the pump!

WARNING

Always protect the pump from coarseimpurities and magnetisable metal

particles!

6.3 Operation

If the motor has been switched off by themotor protection switch, proceed asfollows:

Before switching on the motor again,check whether the impeller rotatesreadily.Make sure that the suction line and thepump housing are filled with fluid.Switch on the motor.

If the pump only delivers for a short periodof time and then stops delivering, themagnetic clutch has been disengaged.Proceed as described in chapter 8 below.

6.4 Shutdown procedure

Switch off the motor.Close all shut-off devices.In case some fluid remains within thepump, secure the shut-off devices toprevent an accidental opening.

6.5 Safe disposal of waste partsThis product as a whole as well as parts ofit must be disposed of in anenvironmentally safe way:

WARNING

Please comply with the respectiveregulations that are currently in force at

your place (especially with regard toelectronic scrap) !

As for Germany:Used parts that have been cleaned will beaccepted by the local public disposal sites.

7 Maintenance7.1 General information

The pump is designed for continousoperation and is therefore maintenance-free.

Page 11: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 11

7.2 Preventive maintenance

Clean the ventilator cowl at least onceper month in order to prevent themotor from overheating!!

Although bearings, center shaft andthrust rings are also designed forcontinuous operation, they shouldperiodically be inspected for choking. Ifdirty, silty or crystallising fluids aredelivered, then the pump should beinspected.

WARNING

Make sure there are no magnetisablemetal particles in the working area if

you assemble or disassemble thepump!

When the complete head of the pump isassembled or disassembled, magnetic

forces can cause serious injury!

Check the static sealings in regularintervals and replace them, ifnecessary.

Page 12: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 12

7.3 Disassembly of the pump

1. Remove the 6 screws (901.1) in the pumphousing (101).

2. Take the complete head of the pump (001)off the lantern (113).

Required tool: fork or ring spanner Required tool: tire lever

3. Take the pump housing (101) off thecenter shaft (211) and pull the impellermagnet (847.1) together with the impeller(230) out of the magnet deviding housing(161).

4. Remove the bearings (310.1 and 310.2)by forcing them backwards out of theimpeller magnet (847.1).

No tools required! Required tools: hand lever press + pinØ20mm!

Page 13: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 13

5. Remove the impeller (230) from theimpeller magnet (847.1).

6. Take the thrust ring (314.2) off theimpeller (230).

Required tool: tire lever! Required tools: tubular piece Øinside80mm; driftpin Ø6mm!

7.4 Re-assembly of the pump

1. Assemble the bearings (310.1 and 310.2). 2. Press the impeller (230) onto the impellermagnet (847.1).

Required tool: hand lever press! Required tools: hand lever press +plastic pressure diskØ80mm!

Page 14: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 14

WARNING

Once the complete head of the pumphas been assembled, the impeller andimpeller magnet (847.2) should be able

to slide axially on the center shaft (211)!

• Any other repair than the replacementof worn parts should be done by anexpert, since inappropriatemaintenance work usually results inunnecessary costs.

• If the pump will not be in operation fora longer period of time, it should becleaned carefully. Otherwise you riskthat residues remaining in the pumpmay harden and jam the impeller, oncethe pump is started again.

Page 15: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 15

8 Troubleshooting

Malfunction Causes Corrective action

Pump does not work whenswitched on

No voltage Test the voltage

Impurities in the pumphousing

Remove the impurities

Magnetic clutch isdisengaged

Specific gravity and/orviscosity of the fluid is toohigh

Reduce the delivery rate; usea stronger magnetic clutchand a more powerful motor

Pump was switched off, thenswitched on again before therotor stopped

The rotor should havestopped before the pump canbe switched on again

Motor is overheating Clogged ventilator cowl Clean the ventilator and thecowl

Pump is working, but notdelivering

Gas accumulation in the lines Evacuate the lines

Too much flow noise Cavitation Increase the suction linecross-sectionReduce the delivery ratecool down the fluid

Pump is not sucking No fluid in the pump Open the vaneAir in the system Evacuate the system

Delivery rate too low Suction and delivery linecross-sections are too small(significant losses)

Increase the suction anddelivery line cross-sections

Valve is not entirely open Entirely open the valveDelivery rate too high Pump losses are less

significant than presumedInstall a flow control valve inthe delivery line

Page 16: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 16

9 Technical data

Order-No. 1023094 1023100 1028566 1028572Pump type von Taine® 2323

PP/FKMvon Taine® 2323

PVDF/FKMvon Taine® 2323

PP/EPDMvon Taine® 2323

PVDF/EPDMHydraulic dataMaximum flow 22500 l/h 22500 l/h 22500 l/h 22500 l/hOperating range 120 - 22500 l/h 120 - 22500 l/h 120 - 22500 l/h 120 - 22500 l/hMaximum head 23,5 mWC 23,5 mWC 23,5 mWC 23,5 mWCMaximum systempressure at 20°C

5,0 bar 6,0 bar 5,0 bar 6,0 bar

Electrical dataMotor output 1,5 kW 1,5 kW 1,5 kW 1,5 kWRated voltage 50 Hz [V] 230/400 230/400 230/400 230/400Rated voltage 50 Hz [A] 5,6 / 3,25 5,6 / 3,25 5,6 / 3,25 5,6 / 3,25No. of revolutions 50 Hz[rpm]

2799 2799 2799 2799

cos φ 0,86 0,86 0,86 0,86Protection class IP 55 IP55 IP 55 IP55Temperature class F F F FFurther dataMaximumtemperature of themedium

80 °C 95 °C 80 °C 95 °C

Maximum viscosity <20 mPas <20 mPas <20 mPas <20 mPasMaximum ambienttemperature

40 °C 40 °C 40 °C 40 °C

Maximum density ofthe medium

1,0 - 2,0 kg/dm³ 1,0 - 2,0 kg/dm³ 1,0 - 2,0 kg/dm³ 1,0 - 2,0 kg/dm³

Suction port G 2 1/4 G 2 1/4 G 2 1/4 G 2 1/4Discharge port G 2 G 2 G 2 G 2Pump housing PP PVDF PP PVDFImpeller PP PVDF PP PVDFColour of delivery unit black white black whiteBearing oxide ceramic oxide ceramic oxide ceramic oxide ceramicCenter shaft oxide ceramic oxide ceramic oxide ceramic oxide ceramicThrust ring (impeller) teflon-graphite teflon-graphite teflon-graphite teflon-graphiteThrust ring (housing) oxide ceramic oxide ceramic oxide ceramic oxide ceramicSealing material FKM FKM EPDM EPDMColour of the motor RAL 2003 RAL 2003 RAL 2003 RAL 2003Weight 17,0 kg 17,7 kg 17,0 kg 17,7 kgDimensions LxTxH[mm]

430x205x227 430x205x227 430x205x227 430x205x227

Page 17: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 17

10 Spare parts

10.1 Exploded view

Page 18: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 18

10.2 Bill of materials von Taine® 2323 PP/FKM

Serial-No:

Pos. Qty. Order-No. Designation Material Qty.

101 1 PUMA.18.0240.140 pump housing without thrust ring polypropylene113 1 PUMA.00.0750.010 lantern 60mm Al

161+314.3 1 PUMA.18.0240.017 rear casing 60mm with thrust ring polypropylene211 1 PUMA.18.0240.105 center shaft 60mm oxide ceramic230 1 PUMA.24.0340.025 impeller Ø135/3,8mm polypropylene

310.1 1 PUMA.18.0240.085 bearing oxide ceramic310.2 1 PUMA.18.0240.085 bearing oxide ceramic314.1 1 PUMA.18.0240.065 thrust ring (housing) oxide ceramic314.2 1 PUMA.18.0240.070 thrust ring (impeller) teflon-graphite400 1 PUMA.18.0240.039 flat packing (suction side) FKM

412.1 1 PUMA.18.0240.020 o-ring 160x3 FKM412.2 1 PUMA.18.0240.055 o-ring 40x5 FKM525 1 PUMA.18.0240.120 distance washer 2,2mm polypropylene

554.2 6 PUMA.18.0240.050 plain washer Ø8,4mm A2 - DIN125800 1 PUMA.04.B.07 0007 motor 1,5kW 230/400V 50Hz

847.1 1 PUMA.24.0340.075 inner magnet Ø135mm polypropylene847.2 1 PUMA.30.0350.010 drive magnet 60(60S)901.1 6 PUMA.18.0240.045 hexagon head cap screw M8x70 A2 - DIN931901.2 4 PUMA.00.0750.021 hexagon head cap screw M6x16 A2 - DIN933904 1 PUMA.05.0050.007 threaded pin M6x10 45H - DIN914940 1 PUMA.00.1100.035 feather 6x6x25

10.3 Bill of materials von Taine® 2323 PVDF/FKM

Serial-No:

Pos. Qty. Order-No. Designation Material Qty.

101 1 PUMA.18.0240.142 pump housing without thrust ring PVDF113 1 PUMA.00.0750.010 lantern 60mm Al

161+314.3 1 PUMA.18.0240.018 rear casing 60mm with thrust ring PVDF211 1 PUMA.18.0240.105 center shaft 60mm oxide ceramic230 1 PUMA.24.0340.029 impeller Ø135/3,8mm PVDF

310.1 1 PUMA.18.0240.085 bearing oxide ceramic310.2 1 PUMA.18.0240.085 bearing oxide ceramic314.1 1 PUMA.18.0240.065 thrust ring (housing) oxide ceramic314.2 1 PUMA.18.0240.070 thrust ring (impeller) teflon-graphite400 1 PUMA.18.0240.039 flat packing (suction side) FKM

412.1 1 PUMA.18.0240.020 o-ring 160x3 FKM412.2 1 PUMA.18.0240.055 o-ring 40x5 FKM525 1 PUMA.18.0240.121 distance washer 2,2mm PVDF

554.2 6 PUMA.18.0240.050 plain washer Ø8,4 A2 - DIN125800 1 PUMA.04.B.07 0007 motor 1,5kW 230/400V 50Hz

847.1 1 PUMA.24.0340.076 inner magnet Ø135mm PVDF847.2 1 PUMA.30.0350.010 drive magnet 60(60S)901.1 6 PUMA.18.0240.045 hexagon head cap screw M8x70 A2 - DIN931901.2 4 PUMA.00.0750.021 hexagon head cap screw M6x16 A2 - DIN933904 1 PUMA.05.0050.007 threaded pin M6x10 45H - DIN914940 1 PUMA.00.1100.035 feather 6x6x25

Page 19: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 19

10.4 Bill of materials von Taine® 2323 PP/EPDM

Serial-No:

Pos. Qty. Order-No. Designation Material Qty.

101 1 PUMA.18.0240.140 pump housing without thrust ring polypropylene113 1 PUMA.00.0750.010 lantern 60mm Al

161+314.3 1 PUMA.18.0240.017 rear casing 60mm with thrust ring polypropylene211 1 PUMA.18.0240.105 center shaft 60mm oxide ceramic230 1 PUMA.24.0340.025 impeller Ø135/3,8mm polypropylene

310.1 1 PUMA.18.0240.085 bearing oxide ceramic310.2 1 PUMA.18.0240.085 bearing oxide ceramic314.1 1 PUMA.18.0240.065 thrust ring (housing) oxide ceramic314.2 1 PUMA.18.0240.070 thrust ring (impeller) teflon-graphite400 1 PUMA.18.0240.040 flat packing (suction side) EPDM

412.1 1 PUMA.18.0240.021 o-ring 160x3 EPDM412.2 1 PUMA.18.0240.056 o-ring 40x5 EPDM525 1 PUMA.18.0240.120 distance washer 2,2mm polypropylene

554.2 6 PUMA.18.0240.050 plain washer Ø8,4mm A2 - DIN125800 1 PUMA.04.B.07 0007 motor 1,5kW 230/400V 50Hz

847.1 1 PUMA.24.0340.075 inner magnet Ø135mm polypropylene847.2 1 PUMA.30.0350.010 drive magnet 60(60S)901.1 6 PUMA.18.0240.045 hexagon head cap screw M8x70 A2 - DIN931901.2 4 PUMA.00.0750.021 hexagon head cap screw M6x16 A2 - DIN933904 1 PUMA.05.0050.007 threaded pin M6x10 45H - DIN914940 1 PUMA.00.1100.035 feather 6x6x25

10.5 Bill of materials von Taine® 2323 PVDF/EPDM

Serial-No:

Pos. Qty. Order-No. Designation Material Qty.

101 1 PUMA.18.0240.142 pump housing without thrust ring PVDF113 1 PUMA.00.0750.010 lantern 60mm Al

161+314.3 1 PUMA.18.0240.018 rear casing 60mm with thrust ring PVDF211 1 PUMA.18.0240.105 center shaft 60mm oxide ceramic230 1 PUMA.24.0340.029 impeller Ø135/3,8mm PVDF

310.1 1 PUMA.18.0240.085 bearing oxide ceramic310.2 1 PUMA.18.0240.085 bearing oxide ceramic314.1 1 PUMA.18.0240.065 thrust ring (housing) oxide ceramic314.2 1 PUMA.18.0240.070 thrust ring (impeller) teflon-graphite400 1 PUMA.18.0240.040 flat packing (suction side) EPDM

412.1 1 PUMA.18.0240.021 o-ring 160x3 EPDM412.2 1 PUMA.18.0240.056 o-ring 40x5 EPDM525 1 PUMA.18.0240.121 distance washer 2,2mm PVDF

554.2 6 PUMA.18.0240.050 plain washer Ø8,4 A2 - DIN125800 1 PUMA.04.B.07 0007 motor 1,5kW 230/400V 50Hz

847.1 1 PUMA.24.0340.076 inner magnet Ø135mm PVDF847.2 1 PUMA.30.0350.010 drive magnet 60(60S)901.1 6 PUMA.18.0240.045 hexagon head cap screw M8x70 A2 - DIN931901.2 4 PUMA.00.0750.021 hexagon head cap screw M6x16 A2 - DIN933904 1 PUMA.05.0050.007 threaded pin M6x10 45H - DIN914940 1 PUMA.00.1100.035 feather 6x6x25

Subject to technical alteration!

Page 20: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 20

11 Appendix11.1 Dimensional drawing von Taine® 2323 PP and PVDF

Page 21: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 21

11.2 Characteristic curves

von Taine® 2323 PP / PVDF

0,0

2,0

4,0

6,0

8,0

10,0

12,0

14,0

16,0

18,0

20,0

22,0

24,0

0 5000 10000 15000 20000 25000

Förderleistung / capacity [l/h]

Förd

erhö

he /h

ead

[mW

s]

0,20

0,60

1,00

1,40

1,80

2,20

2,60

Dic

hte

/ den

sity

[kg

/dm

³]

Dichte / density

NPSH

400

600

800

1000

1200

1400

1600

0 5000 10000 15000 20000 25000

Förderleistung / capacity [l/h]

Mot

orle

istu

ng /

mot

or o

utpu

t [W

]

0

10

20

30

40

50

60

0 5000 10000 15000 20000 25000

Förderleistung / capacity [l/h]

Wirk

ungs

grad

/ ef

ficen

cy [%

]

Page 22: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 22

11.3 Motor data sheet

Motor DatenblattMotor data sheet

Fiche technique pour moteur

Motor-Typmotor typetype du moteur

St. 126/80-3 Leistungsfaktor cosφpower factorfacteur de puissance

0,86 // 0,8

Maschinenarttype of machinedésignation

3-ph. Motor Wirkungsgradefficiencyrendement

77,0 %

Bauformmountingconstruction

IM B14 Wärmeklassetemperature classclasse d´isolement

F

Bemessungsleistungrated outputpuissance nominale

1,5 kW Anzugsstromstarting currentcourant de démarrage

5,6 fachfoldfois

Schutzartprotection classdegré de protection

IP55 Anzugsmomentstarting torquecouple de démarrage

2,9 fachfoldfois

Bemessungsspannungrated voltagetension nominale

220-240/380-415 // 255-277 /

440-480V

Kippmomentpull-out torquecouple de décrochage

2,93 fachfoldfois

Bemessungsstromrated currentcourant nominal

5,6 / 3,25 //5,0 / 2,9

Umgebungstemperaturambient temperaturetempérature ambiante

max.40 °C

Bemessungsfrequenzrated frequencyfréquence nominale

50 // 60Hz Schaltungconnectionbranchement

triangle/star

Bemessungsdrehzahlrated speedvitesse nominale

2799 // 3430 U/min.rpmt/mn

Identcodeidentcodecode d´identification

Pumpentyppump typetype de pompe

Magneticallycoupled

centrifugal pump

KondensatorCapacitorCondensateur

-

Die Daten entsprechen den Angaben der Motorenhersteller. Kenndatenfunktionsgleicher Motoren anderer Hersteller ändern sich nur unwesentlich.Angabe ohne Gewähr.

The data correspond to the details given by the motor manufacturers.Ratings of motors with the same functions made by other producers showinsignificant changes only. This information is supplied without liability.

Anmerkungcommentremarque

Les données techniques correspondent au descriptif du fabricant desmoteurs. Les données techniques de moteurs similaires chez d´autresfabricants varient très peu. Ces données sont d´ordre général.

Nr. / No.

ProMinent Dosiertechnik GmbH · 69123 Heidelberg · Germany Datum / Date12.04.2006

Page 23: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Operating instructions ProMinent ® von Taine ® 2323 PP/PVDF

Page 23

11.4 EC Declaration of Conformity

Page 24: BA vonTaine 2323 GB c - ProMinent€¦ · ProMinent® von Taine® 2323 PP and PVDF von Taine® 2323 PP von Taine® 2323 PVDF Type: 2323 PP/FKM 2323 PVDF/FKM 2323 PP/EPDM 2323 PVDF/EPDM

Anschriften- und Liefernachweis durch den Hersteller /Addresses and delivery by the manufacturer /Adresses et liste des fournisseurs fourniesa par le constructeur /Para informase de las direcciones de los distribuitores, dirigirse al fabricante

ProMinent® Dosiertechnik GmbHIm Schuhmachergewann 5-11 • 69123 HeidelbergGermanyTel.: +49 6221 842-0Fax. +49 6221 [email protected]