Anglophone East School District(ASD-E)

Multi-year infrastructure planningTantramar Community Schools

New Brunswick Department of Educationand Early Childhood Development (EECD)

Page 2: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 2

Table of Contents

Executive Summary 3Scope and Context 7Dorchester Consolidated School Sustainability Review 13ASD-E Perception Survey 14New K-5 School Scenario Results 15Other K-5 Options 18New 6-12 School Scenario Results 19Mid-Life Upgrade Tantramar Regional Scenario Results 22New K-12 School Scenario Results 24Review of Pedagogical Space 27Appendix A – Aerial View of Schools 28Appendix B – School Boundaries and Bussing 33

Page 3: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 3

Executive Summary (1 of 4)

Background and scope:Multi-year infrastructure planning options were prepared for ASD-E to address aging schoolinfrastructure located within the Tantramar Community. The District Education Council (DEC)voted to have an infrastructure review performed for the following four schools:

In particular, the review was to explore options with respect to closing Marshview Middle Schooland moving the students to Tantramar Regional High School. The school was to be reconfiguredto a 6-12. In addition, the DEC wanted to examine Salem Elementary (reconfigured to K-5) andDorchester Consolidated schools to determine how the elementary feed schools fit into the plan.

Objectives:Summarize the results so the District and DEC can review, choose a scenario and build abusiness case for the development of a capital plan considering both pedagogical and fiscalrequirements. Considerations were to include topography, building age, floor plans/size, assetcondition, current/projected enrolments, transportation, pedagogy and operational/capital costs.

Sackville:§ Salem Elementary School (K-4)§ Marshview Middle School (5-8)§ Tantramar Regional High School (9-12)

Dorchester:§ Dorchester Consolidated School (K-8)

Page 4: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 4

Executive Summary – Results (2 of 4)

§ The primary supporting factors of the business case would be the initiation of a revitalizationplan and improvements of infrastructure to support pedagogical needs. The decliningenrolments in the Tantramar area have resulted in Marshview Middle and Tantramar RegionalHigh schools being classified as small schools. This has resulted in an overall surplus ofpedagogical space compared to the current EECD Planning Guidelines, which will onlyincrease as the enrolments are projected to decline out to 2031-32.

§ Operational costs are high when compared to maintaining the space specified in theguidelines (e.g. Marshview Middle School has a floor that is not used by the school. Some ofthis space is used for District storage and by some community groups including the GirlGuides, Gymnastics Club, Archery Club and the Sackville Citizen’s Band. It was noted thatMarshview’s gymnasium and cafeteria were used almost every night of the week andweekends for public school use).

§ The Facility Condition Index (FCI) rating is Poor for three of the schools, and TantramarRegional High School is rated Fair. The total deferred maintenance cost for the four schoolswas identified as $7.7M in the EECD School Physical Plant Status Report.

§ Busses already commute from the Dorchester Consolidated School to the Sackville area forthe Early French Immersion Program. The District anticipates minimum changes in studenttransportation and associated costs due to the close proximity of the Sackville schools.

§ Reconfiguring to a standard grade configuration of K-5 and mixed school of 6-12 would requirean addition or a new K-5 school to replace Salem Elementary School.

Note: A FCI rating of Poor or Fair does not mean a building is unsafe or unfit for use. Older buildings often have more deferred maintenance than newer buildings.

Page 5: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 5

Included inScenario

Excluded fromScenario

Included inScenario

Excluded fromScenario

Included in Scenario Excluded from Scenario Included inScenario

Excluded fromScenario

Projected Peak Enrolment after Construction 444 409 722 697 722 697 1,138 1,082Projected 2031-32 Enrolment 354 324 589 568 589 568 943 892Does the School Fall Within Recommended Sizing? Yes Yes Yes Yes Yes Yes No NoClass "D" Estimate* for Scenario $19.3M – $20.3M $18.9M – $19.9M $29.3M – $30.3M $28.8M – $29.8M $7.0M $6.8M $41.7M – $42.7M $39.5M – $40.5MDeferred Maintenance Avoided $3.2M $1.4M $4.5M $4.5M $2.5M $2.5M $7.7M $5.9MEstimated School Footprint 6,798 m2 6,636 m2 12,233 m2 12,015 m2 13,991 m2 13,991 m2 18,629 m2 17,609 m2

District Footprint: Increased By (Decreased By) 123 m2 2,283 m2 (8,494 m2) (8,712 m2) (6,736 m2) (6,736 m2) (8,773 m2) (6,451 m2)Operating Costs (Excluding Staffing): Increased By(Decreased By)

($48K) $42K ($344K) ($352K) ($214K) ($214K) ($399K) ($343K)

Number of Mobile Classrooms Eliminated 2 2 0 0 0 0 2 2All Accessibility Deferred Maintenance Eliminated Yes No Yes No Yes No Yes NoAll Classrooms Sized to Guideline Specification Yes No Yes No No No Yes NoAdditional Travel Time for Bussing Students(approximately 13.2 km; additional 12 minutes fromDorchester Consolidated to Sackville)

Yes Minimal Yes Minimal Yes Minimal Yes Minimal

Community Loss of Localized School and Not Replaced Yes No Yes No Yes No Yes NoIntangible Benefits from New Modern Infrastructure(e.g. Improvements in Natural Lighting, LearningEnvironment) for Sackville/Dorchester Students

Yes Partially Yes Partially No No Yes Partially

Dorchester Consolidated Dorchester Consolidated Dorchester Consolidated Dorchester ConsolidatedConstruction of a New K-5 School Construction of a New 6-12 School Mid-life Upgrade to Tantramar Regional (6-12) Construction of a New K-12 School

Executive Summary – Scenario Results (3 of 4)

§ A high-level review determined the costs of a new addition and renovations would beapproximately 44% of a new K-5 school and 27% of a new K-4 school for Salem Elementary.There is little room on the property for an addition without a land purchase or removing theplayfield. The plan for a combined middle school would have to be changed from a 6-12 to a5-12 (not a standard school configuration) if a K-4 addition were selected for revitalization.

§ Excluding Dorchester Consolidated School from the Sackville scenarios means the schoolwould eventually require a mid-life upgrade to address life-cycle maintenance costs ($1.8M indeferred maintenance) that is not included in the scenario cost estimates.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Estimates will be adjusted whenEECD Infrastructure and project team establish the actual space allocation. (The number of general classrooms in the scenarios were based on those levels provided for

Note: Actual costs would depend onimplementation year due to the decliningenrolment projections.

2016-17 in the high school. This conservative approach was taken to provide enough general classroom space to preserve the current curriculum. TantramarRegional is considered a small high school based on the enrolment and is a combined school. This could affect the calculation of home rooms typicallyused for high school planning).

Page 6: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 6

Included inScenario

Excluded fromScenario

Included inScenario

Excluded fromScenario

Included inScenario

Excluded fromScenario

Does the School Fall Within Recommended Sizing? Yes Yes Yes Yes No NoClass "D" Estimate* $48.6M – $50.6M $47.7M – $49.7M $26.3M – $27.3M $25.7M – $26.7M $41.7M – $42.7M $39.5M – $40.5MDeferred Maintenance Avoided $7.7M $5.9M $5.7M $3.9M $7.7M $5.9MDistrict Footprint: Increased By (Decreased By) (8,371 m2) (6,429 m2) (6,613 m2) (4,453 m2) (8,773 m2) (6,451 m2)Operating Costs (Excluding Staffing): Increased By(Decreased By)

($392K) ($310K) ($262K) ($172K) ($399K) ($343K)

Number of Mobile Classrooms Eliminated 2 2 2 2 2 2

Option 1: New K-5 and New 6-12 Option 2: New K-5 and Mid-LifeUpgrade 6-12 at Tantramar Regional

Option 3: New K-12 School

Dorchester Consolidated Dorchester Consolidated Dorchester Consolidated

Executive Summary – Scenario Results (4 of 4)

§ Option 2 includes the mid-life upgrade of Tantramar Regional. The estimated cost of $7.0Mincludes renovation of classroom and speciality space for middle school, an addition for gymspace and the currently identified deferred maintenance. This is approximately 24% of theestimated cost of a new 6-12 school, and does not include any refurbishment/ beautification ofhigh school space that is not on the deferred maintenance list.

§ The deferred maintenance list is not all inclusive. If option 2 is selected as the preferredsolution, it is recommended that a building assessment be performed to confirm the estimatedcost of the renovations compared to the cost of an entirely new school.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Estimates will be adjusted whenEECD Infrastructure and project team establish the actual space allocation. (The number of general classrooms in the scenarios were based on those levels provided for

Note: Actual costs would depend onimplementation year due to the decliningenrolment projections.

2016-17 in the high school. This conservative approach was taken to provide enough general classroom space to preserve the current curriculum. TantramarRegional is considered a small high school based on the enrolment and is a combined school. This could affect the calculation of home rooms typicallyused for high school planning).

§ Based on the scope criteria of standardizing to a K-5 and 6-12 scenario, and the potential toexceed the cost threshold of 50% of a new K-5 building in an elementary school extension fora reconfiguration, it is recommended that the district and DEC consider the following optionsto select the best solution:

Page 7: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 7

Scope – The District requested EY to perform a multi-scenario review of Tantramar Community Schools toassist in the long-term infrastructure planning processMulti-year infrastructure planning options were prepared for ASD-E to address aging schoolinfrastructure located within the Tantramar Community. Determine the business casesupporting the projects considering both pedagogical and fiscal requirements:

► Scenario: Construction of a new 6-12 school§ Closing Marshview Middle School (5-8) and Tantramar Regional High School (9-12) and

reconfiguring the new mixed school (6-12).§ Develop a Class "D" estimate (± 30%) for the construction costs of a new 6-12 school

based on the space requirements identified in the EECD Planning Guidelines forEducational Facilities.

► Scenario: Reconfiguration of Tantramar Regional High to a 6-12 school§ Closing Marshview Middle School (5-8), and reconfiguring Tantramar Regional High

School to a 6-12 school. Consolidation plan to include a mid-life upgrade to extend theservice life of the school (include all the projects within the deferred maintenance list).

► Scenario: Construction of a new K-12 school§ Closing Dorchester Consolidated (K-8), Salem Elementary School (K-4), Marshview

Middle School (5-8) and Tantramar Regional High School (9-12).§ Develop a Class "D" estimate (± 30%) for the construction costs of a new K-12 school

based on the space requirements identified in the EECD Planning Guidelines forEducational Facilities.

Page 8: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 8

Scope (continued) – The District requested EY to performa multi-scenario review of Tantramar Community Schools

► Scenario: Determine how the elementary feed schools align to previous scenarios§ The District noted that the DEC wanted to examine how the elementary feed schools

Dorchester Consolidated School (K-8) and Salem Elementary School (K-4) fit into thelong-term plan (Port Elgin Regional School was out of scope).

§ Options may include boundary re-alignment or grade re-configuration, amalgamation,renovation or a new K-5 school.

§ Develop a Class "D" estimate (± 30%) for the construction costs of the a new K-5 schoolbased on the space requirements identified in the EECD Planning Guidelines forEducational Facilities.

► The District and DEC wanted the scenarios prepared at a high-level for consideration inpotential business case development of future project(s).

► The District anticipates minimum changes in student transportation and associated costsdue to the close proximity of the three schools in Sackville. Additionally, there is alreadybussing from the Dorchester Consolidated School boundary into the Sackville schools forstudents taking Early French Immersion.

Page 9: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 9

Context – Dorchester Consolidated School is 13.2 kmaway from Salem Elementary School, and both are a partof the feeder system into Tantramar Regional High School

Tantramar Community SchoolsAverage age of the four schools in scope:54 yearsDorchester French Immersion students attendSalem Elementary School and then MarshviewMiddle School.Port Elgin Regional School was excluded fromthe scope of this review.

Note: The District school map notes that Dorchester ConsolidatedSchool was built in 1949. However, the District confirmed the schoolwas built in 1956 and had upgrades in 1961.

Source: EECD sub-district map 2 for ASD-E.

Page 10: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 10

Context – Overall average FCI* is rated Poor for the fourschools included within the review► Replacement value for all four existing school structures is approximately $73.7M.

§ Based on current floor area and replacement cost of $2,690/m2.

► Overall average asset condition for the four schools included within the scenario is ratedPoor at 0.15, based on FCI* ranges that are recommended in the APPA Book ofKnowledge (2009) for Facilities Management:

► Note: FCI is a measure for Facility Planners to equate the amount of deferredmaintenance to the space of a building for comparison. A rating of Poor or Fair does notmean a building is unsafe or unfit for use. Older buildings often have more deferredmaintenance than newer buildings (e.g. the deferred maintenance can require upgradesto modernize heating, ventilation and control systems that did not exist when the buildingwas constructed).

► The total deferred maintenance cost for the four schools was identified as $7.7M in theEECD School Physical Plant Status Report.

*FCI: Facility Condition Index with the following ranges: Poor (>0.10), Fair (0.05 to 0.10) and Good (<0.05).

Tantramar Community Schools FCI* Rated condition

Dorchester Consolidated School 0.29 PoorMarshview Middle School 0.13 PoorSalem Elementary School 0.12 PoorTantramar Regional High School 0.06 Fair

Average school condition 0.15 Poor

Page 11: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 11

Context – Visual comparison of space types in the schoolsillustrates both some of the extra and/or missing pedagogicalspace compared to the EECD Planning Guidelines

Tantramar Regional High School(9-12), built in 1968

Dorchester Consolidated School(K-8), built in 1956

Salem Elementary School(K-4), built in 1980

Marshview Middle School(5-8), built in 1949

School entrance – with no accessibility

• Tantramar Regional High School’s cafeteria is significantly oversized(originally designed for a capacity of 1,021, current enrolment is 426).

• Dorchester Consolidated School and Marshview Middle School: theaverage sized classroom is smaller than EECD Planning Guidelinesspecify for the middle school grades.

• The gyms are undersized compared to the EECD Planning Guidelinesat Salem Elementary School and Marshview Middle School.

• Accessibility has been identified on the deferred maintenance list forall: Dorchester Consolidated (ramps and lift), Salem ElementarySchool (lift), Marshview Middle School (ramps) and TantramarRegional High School (lift).

CafeteriaGuidelines: 256 m2 / Actual 853 m2

Single Gymnasium (Middle)Guidelines: 591 m2 / Actual 494 m2

General ClassroomGuidelines: 81 m2 / Average 64 m2

Double Gymnasium (Elementary)Guidelines: 591 m2 / Actual 446 m2

Music ClassroomGuidelines: 110 m2 / Actual 117 m2

Single Gymnasium (K-8)Guidelines: 380 m2 / Actual 362 m2

General ClassroomGuidelines: 70 m2 / Average 65 m2

General ClassroomGuidelines: 81 m2 / Average 73 m2

Double Gymnasium (High School)Guidelines: 821 m2 / Actual 850 m2

Source: ASD-E School site visits, EECD school drawings, EECD Planning Guidelines for Educational Facilities, and ASD-E School Utilization Review (May 2015).

Page 12: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 12

Context – Total K-12 enrolment has been decreasing forthe schools at an average annual rate of 1.26% since 2010and is projected to decrease at a slower rate to 2029► Aggregate floor area is 27,402 m2, or 11.2% of District total of 245,549 m2.

► Age of school assets ranges from 68 years (Marshview Middle School) to 37 years (SalemElementary School).

► Total 2016-17 enrolment for the four schools in scope is 1,091 students.

► 2016-17 enrolment is 45% of original design capacity of 2,424 for the four schools.

§ From 2010 to 2016, enrolment decreased by 7.5% (annual average decrease of 1.26%).

§ Projections from 2016 to 2023 from the Baragar software indicated K-12 enrolment isexpected to increase by 4.3% (annual average increase of 0.61%).

§ The peak enrolment is projected at 1,138 students in the year 2023-24 for K-12.

§ Projections from 2023 to 2029 indicate K-12 enrolment is expected to decrease by 14.3%(annual average decrease of 2.54%). The total percentage decrease in enrolmentbetween 2016 and 2029 would be 10.6% (annual average decrease of 1.04%).

Source: ASD-E enrolment projection software – Baragar Systems, EECD Policy, Planning Summary Statistics and ASD-E School Utilization Review (May 2015).

Schools 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30Dorchester Consolidated School 69 58 54 62 64 58 58 63 62 55 59 56 56 56 55 56 50 51 54 51Salem Elementary School 323 300 306 318 315 336 367 374 382 372 365 347 330 310 292 267 266 266 266 266Marshview Middle School 302 304 307 285 278 252 240 260 270 297 328 328 329 324 309 313 293 271 254 228Tantramar Regional High School 485 474 451 482 452 439 426 412 406 389 380 403 411 448 463 465 457 443 435 430Total 1,179 1,136 1,118 1,147 1,109 1,085 1,091 1,109 1,120 1,113 1,132 1,134 1,126 1,138 1,119 1,101 1,066 1,031 1,009 975

Enrolment History and Projections

Page 13: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 13

Dorchester Consolidated (a trigger school*) had asustainability study performed in 2015; Baragar enrolmentprojections indicate school will remain below 100 students

► In February 2015, the DEC voted in favour of performing a sustainability study for DorchesterConsolidated School (K-8), which had been identified as a trigger school* (2015-16 enrolmentwas 58 students – 41 students in K-5 and 17 students in 6-8). The DEC voted in favour ofkeeping Dorchester Consolidated School open after the study was completed.

► Baragar enrolment projections (done up to 2031-32) for Dorchester Consolidated indicatedthat the school will remain well below 100 students for the foreseeable future.

► A Perception Survey was conducted at the schools for ASD-E by The Learning Bar Inc. in2015-16 and each school was scored for 20 indicators in elementary school (grades 4 and 5)and 35 indicators in middle school (grades 6-8) based on research for school and classroomeffectiveness. The indicators were grouped by social-emotional outcomes, academicoutcomes, drivers of student outcomes and demographic factors.

► The results for Dorchester Consolidated School have the potential to be skewed by outliers ata small school. There were 15 respondents for the elementary survey and 13 respondents forthe middle school portion. Salem Elementary is a K-4 school, and the survey was for grades 4to 5. As a result, there were only 12 respondents in the survey, which has potential to skewthe results.

► Results of indicators for Dorchester Consolidated School and the Sackville schools are notcomparable on an individual basis because there were fewer than 30 students surveyed inDorchester (Central Limit Theorem for Normal Distribution – to make inferences, the samplesize should be large enough, i.e. 30 data points or more, which was not the case here).*A trigger school has fewer than 100 students or less than 30% capacity and requires a feasibility study (as defined in a statement by the Minister of Education and EarlyChildhood Development dated 27 March 2015).

Page 14: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 14

For consideration, ASD-E had a Perception Survey*conducted by The Learning Bar Inc. comparing pedagogicalindicators to Canadian norms based on a student survey

► The elementary results for Dorchester Consolidated indicated the school was at or above theCanadian school norms for all 20 indicators, and the middle school results were at or abovethe Canadian school norms for 31 of the 35 indicators. The three indicators that deviated themost negatively from the norms included:§ Student participation in school sports,§ Students with positive relationships at school, and§ Students planning to finish high school.

► The survey results for Salem Elementary was at or above the Canadian school norms for 17of the 20 indicators. Those identified with lower than norms included:§ Students with a positive sense of belonging,§ Students that value schooling outcomes, and§ Feel safe attending school (both onsite and travel to and from school).

► Marshview Middle School (5-8) had a high respondent rate with 163 respondents in total. Thesurvey results for Marshview were near or above the Canadian school norms for 27 of the 35indicators. The three indicators that deviated the most negatively from the norms included:§ Student participation in school clubs,§ Students with positive homework behaviours, and§ Feel safe attending school (both onsite and travel to and from school).*ASD-E Perception Survey- 2015 Report on Student Outcomes and School Climate NB Schools by The Learning Bar Inc., available onhttp://www.gnb.ca/0000/results/district_east.asp.

Page 15: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 15

Year K 1 2 3 4 5 Total2016-17 69 82 77 80 87 61 4562017-18 78 70 87 85 85 87 4922018-19 74 81 74 94 89 83 495 Year 1 Estimated new2019-20 67 74 83 78 97 88 487 Year 2 school construction2020-21 80 68 77 87 82 96 490 Year 32021-22 56 81 70 80 90 82 459 Year 4 (depending on start time)2022-23 56 56 83 75 84 90 4442023-24 56 56 58 87 78 83 4182024-25 56 56 58 59 91 77 3972025-26 56 56 58 59 63 91 3832026-27 56 56 58 59 62 63 3542027-28 56 56 58 59 62 63 3542028-29 56 56 58 59 62 63 3542029-30 56 56 58 59 62 63 3542030-31 56 56 58 59 62 63 3542031-32 56 56 58 59 62 63 354

Review of 10-year planning horizonProjections used for school design in review

Projections for New K-5 School (Based on ASD-E Baragar Software)

Based on ASD-E enrolment projection software results, a newK-5 school for Tantramar Community would be sized for 444students and have 24 classrooms (depending on start time)

§ Enrolment projections made using theBaragar Systems software indicate asteady decline in K-5 student populationduring the 10-year planning horizon.

§ 2022-23 was projected with the moststudents (444) after potential construction.

§ The projected utilization for a new K-5school based on the design of 444students is 76.6%, with 24 classrooms.

§ This is a typically sized K-5 school. ThePlanning Guidelines note a regularelementary school is typically sizedbetween 200 and 500 students.

§ For comparison, based on 2015-16school statistics, GNB had 89 K-5schools; 47 of these schools wereconsidered regular sized schools. Theaverage student enrolment for this sizedschool is 349, with the largest being 627at École Anna-Malenfant.

Source: ASD-E enrolment projection software – Baragar Systems, EECD Policy, Planning Summary Statistics and Collective Agreement with the NB Teachers’ Federation.*Sackville Schools 2020 is a community-based group working to transform K-12 education in Sackville, NB (www.sackvilleschools2020.com).

Project start-upwould depend onDEC and GNBapproval

Note: The school would be designed for the peak enrolment (depending on start time).The utilization would drop to 61% based on 2026-27 enrolment projections of 354students. The District noted that Sackville Schools 2020* have identified that investingin new infrastructure rather than repairing older school buildings would help revitalizetheir community (may be viewed as a potential catalyst for growth to the community).

Grades SizeLimit

Total ClassRooms

MaximumCapacity

K 21 19 19 18 56 3 631 21 13 12 16 15 56 4 842 21 19 18 16 15 15 83 5 1053 26 15 14 23 23 75 4 1044 28 19 19 23 23 84 4 1125 28 23 22 23 22 90 4 112

Empty 29 0 0 0Total: 444 24 580

Projected Utilization: 76.6%

Space Requirements

Regular Program French Immersion

Design Capacity for the New K-5 School (444 Students)

New K-5 school scenario

Page 16: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 16

A Class “D” estimate* of $19.3M to $20.3M would be requiredfor the construction of a new K-5 school, with a costavoidance of $3.2M in deferred maintenance

► Class “D” estimate* for a new K-5 school (444 students) is approximately $19.3M to $20.3M,depending on the cost of land and any topographical challenges.

► The new school is estimated to be 6,798 m2 based on the current EECD Planning Guidelines.► If Dorchester Consolidated School was removed from this scenario, the savings for the new

K-5 school would be small (2% – $435K) compared to the cost with the school included.There would be approximately 162 m2 less in the new school footprint (including one fewerclassroom and small reductions to the size of the library, dining and staff areas).

► EECD Planning Guidelines recommend a site size of 22.5 acres for a K-5 school of444 students (Note: In urban areas, site size may be reduced when land is at a premiumand/or existing community field/facilities are used offsite).

► The cost avoidance for deferred maintenance at the two proposed amalgamated schools wasidentified as $3.2M in the EECD School Physical Plant Status Report.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Estimates will be adjusted whenEECD Infrastructure and project team establish the actual space allocation.

New K-5 school scenario

School Grade Levels Reconfigured: K-5Total Number of K-5 Students Projected Within New School's Boundary (2022-23): 444New K-5 School Estimated CostNew 444 Student K-5 School (6,798 m2) $18.3MLand Purchase (depending on cost of land and location): $1M – $2MEstimated Cost for New K-5 School: $19.3M – $20.3MDeferred Maintenance to be Avoided for School Amalgamations Cost AvoidedDorchester Consolidated School Deferred Maintenance $1,812,000Salem Elementary School Deferred Maintenance $1,450,000Estimated Cost Avoidance for Deferred Maintenance: $3.2M

Page 17: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 17

MarshviewMiddleSchoolA.

Lou MacNarinSchoolB.

LewisvilleMiddleSchoolC.

Edith CavellSchoolD.

BessboroughSchoolE.

Total for referenceschool closuresF= (A + B + C + D + E)

Projected OperationalCosts for new K-5 School(based on historical costper square metre) G.

Operating Costs* $234,035 $283,105 $257,785 $254,391 $231,974 $1,261,290 $266,618Square Metres 7,245 6,121 6,008 5,908 5,694 30,976 6,798Cost Per Square Metre $32.30 $46.25 $42.91 $43.06 $40.74 $40.72After Energy Savings Adjustment $30.80 $44.75 $41.41 $41.56 $39.24 $39.22 $39.22

G Operating - F Operating

(47,624)$

Based on May 2015 ASD-E School Utilization Review

Operating Costs* of Schools InScope

$314,242

DorchesterConsolidatedSchoolA.

SalemElementarySchoolB.

Total forproposedschool closuresC= (A + B)

Projected OperationalCosts for new K-5 School(based on historical costper square metre) D.

Operating Costs* $95,521 $218,721 $314,242 $309,836Square Metres 2,322 4,353 6,675 6,798Cost Per Square Metres $41.14 $50.25 $47.08 $45.58

Old Schools ($/m2) $17.97 $17.97 $17.97New Schools ($/m2) $16.47 $16.47 $16.47Energy Savings Adjustment $1.50 $1.50 $1.50 D Operating - C Operating

Total $39.64 $48.75 $45.58 (4,406)$

Based on May 2015 ASD-E School Utilization Review

EECD Estimated Savings ForUtility Efficiency:

For a new K-5, the District’s operational costs woulddecrease by approximately $48K (excluding staffing) basedon historical costs for schools of similar size and efficiency► The school footprint would see an increase in net

square metres of 123 m2 for a new K-5 school.► Operational costs (excluding staffing) would

decrease by approximately $5K for the newschool, if based on the historical costs of theschools in scope. However, this isunderestimated when compared toother schools of similar size.

► A review of operating costsfor schools of a similarsize/scale indicates thedecrease would beapproximately $48K (thisaccounts for economy ofscale factors).

Schools (For K-5 Scenario) Area (m2)Dorchester Consolidated School 2,322Salem Elementary School 4,353Total for potential school closures: 6,675New K-5 school 6,798Total new space for schools: 6,798Increase in total m2: 123

Note: For comparison oftotal square metres beforeand after this scenario,Salem Elementary iscurrently a K-4 school.The new school has spacefor grade 5 students fromMarshview Middle School.

New K-5 school scenario

Source: ASD-E School Utilization Review (May 2015), and EECD School Asset Data. *Operating costs include electricity, natural gas, oil, garbage and snow removal,custodial salaries, telephone, water and sewer, minor repairs, cleaning supplies, alarms, inspections and vandalism repairs. The energy savings adjustment is the

savings estimated by EECD Infrastructure Planning for comparing older to newer energy efficient buildings ($17.97/m2 and $16.47/m2).

Page 18: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 18

Planning GuidelinesSizing to Projection (B)

Dorchester Consolidated School 58 62 2,322 2,799 477 $1.3M $1.8M $1.8M $7.5M 24.0%Salem Elementary School (K-4) 367 330 4,353 5,296 943 $2.5M $1.4M $3.9M $14.3M 27.3%Salem Elementary School (K-5) 367 409 4,353 6,636 2,283 $6.2M $1.4M $7.6M $17.9M 42.5%

School Projection Existing(A)

High Level Estimatefor Addition (B - A)

For Addition(C)

$8.0M $18.3M 43.7%

Enrolment Area (m2) High-Level Estimated Cost*Current

(2016-17)Deferred

Maintenance (D)Total Cost(C) + (D)

Cost for NewSchool

Percentage of Cost(C+D to New School)

4,353 6,798 2,445 $6.6M $1.4MSalem Elementary School (K-5)(with Dorchester Consolidated K-5)

367 444

Other K-5 options for the elementary feed schools are limitedfor revitalization, due to the deficiency of space to currentguidelines and poor FCI scoring compared to a new school

► High-level estimates were used to determine if an addition could be utilized at one of theexisting schools instead of building a new K-5 school for Tantramar infrastructure revitalization.

► EECD planning “rule of thumb” in determining the tipping point between building a new schoolor renovating an existing school/new addition is when the cost of the deferred maintenanceand new addition exceeds 50% of the cost of a new building. Two of the four scenarios are inthe 40% range, with potential risk to reach 50% from “new discoveries” during the inspectionand or construction phase. Additionally, the Deferred Maintenance List is not all inclusive.

► A business case for a mid-life upgrade of Dorchester Consolidated School to EECD PlanningGuidelines would have poor financial considerations resulting from the FCI rating (0.29) andthe small enrolment and compared to costs for the inclusion in a new K-5 elementary scenario.

► An addition to Salem Elementary School as a K-4 is a potential scenario based on a high-levelestimate. However, there is little room on the property for an addition without a land purchase(or removing the playfield). The plan for the middle-high school would have to change to a5-12 (not a standard school configuration), and this does not address the life-cyclemaintenance costs (existing and future) for Dorchester Consolidated School.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Source: EECD Planning Guidelines forEducational Facilities, EECD School Asset Data, School Physical Plant Status Report for Deferred Maintenance and APPA Book of Knowledge (2009) for Facilities

Management. The space deficiencies to Planning Guidelines at Dorchester Consolidated are mostly rated to under-sizing of space, as opposed to missingspace. Therefore, no addition was included in that calculation. Other K-5 school options scenario

Page 19: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 19

Grades SizeLimit Total

HomeRooms

MaximumCapacity

6 28 20 20 22 22 84 4 1127 29 24 23 22 22 91 4 1168 29 19 19 23 23 84 4 1169 29 23 22 22 29 28 124 5 145

10 29 23 23 22 25 25 118 5 14511 29 28 27 27 29 111 4 11612 29 28 27 27 27 1 110 5 145

Empty 29 0 0722 31 895

Design Capacity for the New 6-12 School (722 Students)

80.7%Projected Utilization:Total:

Space Requirements

Regular Program French Immersion

Year 6 7 8 9 10 11 12 Total2016-17 67 74 68 101 100 102 123 6352017-18 62 68 75 94 96 100 122 6172018-19 88 63 68 115 88 94 109 625 Year 1 Estimated new2019-20 84 89 64 94 109 83 103 626 Year 2 school construction2020-21 89 85 88 103 88 104 85 642 Year 32021-22 96 90 86 115 96 83 109 675 Year 4 (depending on start time)2022-23 84 97 90 125 107 93 86 6822023-24 90 84 98 126 118 104 100 7202024-25 84 91 84 124 118 111 110 7222025-26 78 84 91 121 117 113 114 7182026-27 92 79 84 115 113 109 120 7122027-28 63 93 78 117 108 106 112 6772028-29 63 64 93 116 109 101 109 6552029-30 63 64 64 117 108 102 103 6212030-31 63 64 64 102 109 103 106 6112031-32 63 64 64 92 95 103 108 589

Review of 10-year planning horizonProjections used for school design in review

Projections for New 6-12 School (Based on ASD-E Baragar Software)

Based on ASD-E enrolment projection software results, a new6-12 school for Tantramar Community would be sized for 722students and have 31 home rooms (depending on start time)

§ Enrolment projections made using theBaragar Systems software indicate asteady decline in 6-12 student populationafter 2024-25.

§ 2024-25 was projected with the moststudents (722) after potential construction.

§ The projected utilization for a new 6-12school based on the design of 722students is 80.7%, with 31 home rooms.

§ This is within recommended sizing for a6-12 school. The Planning Guidelinesnote a combined school is recommendedwhen enrolment falls below 300 for amiddle school or 500 for a high school. Acombined school is generally favouredover the creation of small schools.

§ For comparison, based on 2015-16school statistics, GNB had ten 6-12schools, with the largest being 624students at École Sainte-Anne.

Source: ASD-E enrolment projection software – Baragar Systems, EECD Policy, Planning Summary Statistics and Collective Agreement with the NB Teachers’ Federation.*Sackville Schools 2020 is a community-based group working to transform K-12 education in Sackville, NB (www.sackvilleschools2020.com).

Project start-upwould depend onDEC and GNBapproval

Note: The school would be designed for the peak enrolment (depending on start time).The utilization would drop to 66% based on 2031-32 enrolment projections of 589students. The District noted that Sackville Schools 2020* have identified that investingin new infrastructure rather than repairing older school buildings would help revitalizetheir community (may be viewed as a potential catalyst for growth to the community).

New 6-12 school scenario

Page 20: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 20

A Class “D” estimate* of $29.3M to $30.3M would be requiredfor the construction of a new 6-12 school, with a costavoidance of $4.5M in deferred maintenance

► Class “D” estimate* for a new 6-12 school (722 students) is approximately $29.3M to $30.3M,depending on the cost of land and any topographical challenges.

► The new school is estimated to be 12,233 m2 based on the current EECD Planning Guidelines.► If Dorchester Consolidated School was removed from this scenario, the savings for the new

6-12 school would be small (1.8% – $501K) compared to the cost with the school included.There would be approximately 218 m2 less in the new school footprint (including one fewer artroom and small reductions to the size of the library, and dining areas).

► EECD Planning Guidelines recommend a site size of 26 acres for a 6-12 school of722 students (Note: In urban areas, site size may be reduced when land is at a premiumand/or existing community field/facilities are used offsite).

► The cost avoidance for deferred maintenance at the two proposed amalgamated schools wasidentified as $4.5M in the EECD School Physical Plant Status Report.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Economy of scale has been assumed,with construction costs lowered from $2,690/m2 to $2,300/m2 (as per EECD “rules of thumb”). Estimates will be adjusted when EECD Infrastructure and project team establish

the actual space allocation.

Note: The estimated cost does notinclude space for the SackvilleEducation Centre, the Daycare orthe Wetlands Centre (currently inTantramar Regional High School),which are not in the 6-12 EECDPlanning Guidelines. The Districtnoted that the location of apotential new 6-12 is unknownand/or if the school would belocated too far away from SackvilleWaterfowl Park. It was determinedto leave this space out of the newschool scenario.

New 6-12 school scenario

School Grade Levels Reconfigured: 6-12Total Number of 6-12 Students Projected Within New School's Boundary (2024-25): 722New 6-12 School Estimated CostNew 722 Student 6-12 School (12,233 m2) $28.3MLand Purchase (depending on cost of land and location): $1M – $2MEstimated Cost for New 6-12 School: $29.3M – $30.3MDeferred Maintenance to be Avoided for School Amalgamations Cost AvoidedDorchester Consolidated School Deferred Maintenance (included with K-5 Scenario) $0Marshview Middle School Deferred Maintenance $2,474,000Tantramar Regional High School Deferred Maintenance $1,995,000Estimated Cost Avoidance for Deferred Maintenance: $4.5M

Page 21: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 21

RiverviewEast SchoolA.

BerniceMacNaughtonHigh SchoolB.

HarrisonTrimbleHigh SchoolC.

RiverviewHigh SchoolD.

Moncton HighSchoolE.

Total for referenceschool closuresF= (A + B + C + D + E)

Projected OperationalCosts for new 6-12School (based onhistorical cost per squaremetre) G.

Operating Costs* $301,987 $542,574 $546,544 $679,475 $734,484 $2,805,064 $453,844Square Metres 10,228 15,107 15,653 17,230 17,391 75,609 12,233Cost Per Square Metre $29.53 $35.92 $34.92 $39.44 $42.23 $37.10 $37.10

G Operating - F Operating

(344,366)$

Based on May 2015 ASD-E School Utilization Review

Operating Costs* of SchoolsIn Scope

$798,210

DorchesterConsolidated(See K-5)A.

MarshviewMiddleSchoolB.

TantramarRegional HighSchoolC.

Total forproposedschool closuresD= (A + B + C)

Projected OperationalCosts for new 6-12School (based onhistorical cost per squaremetre) E.

Operating Costs* $234,035 $564,175 $798,210 $452,751Square Metres 7,245 13,482 20,727 12,233Cost Per Square Metre $32.30 $41.85 $38.51 $37.01

Old Schools ($/m2) $17.97 $17.97 $17.97New Schools ($/m2) $16.47 $16.47 $16.47Energy Savings Adjustment $1.50 $1.50 $1.50 E Operating - D Operating

Total $30.80 $40.35 $37.01 (345,459)$

Based on May 2015 ASD-E School Utilization Review

EECD Estimated Savings ForUtility Efficiency:

For a new 6-12, the District’s operational costs woulddecrease by approximately $344K (excluding staffing) basedon historical costs for schools of similar size and efficiency► The total school footprint would see a decrease in net

square metres of 8,494 m2 for a new 6-12 school.► Operational costs (excluding staffing) would

decrease by approximately $345K for the newschool, if based on the historical costs of theschools in scope.

► A review of operating costs forschools of a similar size/scaleindicates the decrease wouldbe approximately the same at$344K. This was a check foreconomy of scale factors,which were within range forthe first calculation.Note: Energysavings adjustmentwas not applied tothe larger schoolanalysis, as someof the schools arenew and aredesigned forenergy efficiency.

New 6-12 school scenario

Source: ASD-E School Utilization Review (May 2015), and EECD School Asset Data. *Operating costs include electricity, natural gas, oil, garbage and snow removal,custodial salaries, telephone, water and sewer, minor repairs, cleaning supplies, alarms, inspections and vandalism repairs. The energy savings adjustment is the

savings estimated by EECD Infrastructure Planning for comparing older to newer energy efficient buildings ($17.97/m2 and $16.47/m2).

Schools (For 6-12 Scenario) Area (m2)Dorchester Consolidated (in K-5 scenario) 0Marshview Middle School 7,245Tantramar Regional High School 13,482Total for potential school closures: 20,727New 6-12 school 12,233Total new space for schools: 12,233Decrease in total m2: (8,494)

Page 22: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 22

A Class “D” estimate* identified approximately $7.0M wouldbe required for the mid-life upgrade/school addition toreconfigure Tantramar Regional to a 6-12 school

► Class “D” estimate* for a mid-life upgrade of Tantramar Regional and reconfiguring to a 6-12school (722 students) is approximately $7.0M, with a risk of newly identified maintenance costsonce renovations are implemented.

► This is approximately 24% of the estimated cost for a new 6-12 school. It is recommended thata building assessment be performed to confirm the estimated cost of the renovationscompared to the cost of an entirely new school.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities and the current classroom utilization and curriculum offered as an estimatefor this report only. Estimates will be adjusted when EECD Infrastructure and project team establish the actual space allocation and number of classrooms during planning stage.

Note: The estimated cost includes repurposingspace within the school after reviewing the 6-12EECD Planning Guidelines. The followingidentifies groups that would potentially need tofind space after the school renovation andspaces that would be combined:1) Sackville Education Centre,2) Daycare (could be relocated in a new K-5school scenario),3) Tantramar Health Centre,4) District IT (storage and repair),5) Vocational Metal/Auto shop (is combined withWoodworking Shop for a mixed school), and6) Middle School Technology (MSTE) andBroad-Based Technology (BBT) (are combinedfor middle/high schools).The Wetlands Centre would stay at its currentlocation due to the close proximity to theSackville Waterfowl Park.It is possible to group general classrooms formiddle school (ground and first floor) and highschool (majority on the second floor), whilesharing some speciality and supporting spaces.

School Grade Levels Reconfigured: K-5 and 6-8Total Number of Students Grade 6-12): 722Deferred Maintenance (EECD School Physical Plant Status Report) Estimated CostBuilding Envelope and Site Work $525,000Interior Finishes and Renovations $845,000Heating, Ventilation and Lighting $580,000Interior Accessibility $45,000Estimated Cost* for Completion of Deferred Maintenance: $2.0MRenovation Costs for Tantramar Regional (6-12 School)Renovation for Middle School Classroom Space (1,328 m2) $2.6MRepurposing of Existing Space in Middle School Speciality Classrooms (468 m2): $1.0MEstimated Cost* for School Renovations: $3.6MSchool Addition Based on EECD Planning GuidelinesMulti-purpose gym and Supporting Ancillary Space (372 m2): $1.0MVisiting Professionals Office Space and Student Government Space (67 m2): $0.2MTwo Resource Spaces (70 m2): $0.2MEstimated Cost* for New School Addition: $1.4M

Total Estimated Cost*: $7.0MDeferred Maintenance to be Avoided for School Amalgamations Cost AvoidedDorchester Consolidated School Deferred Maintenance (Included with K-5 Scenario) $0Marshview Middle School Deferred Maintenance $2,474,000Estimated Cost Avoidance for Deferred Maintenance: $2.5M

Reconfiguration of Tantramar Regional school scenario

Page 23: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 23

For a reconfigured 6-12 Tantramar Regional School, theDistrict’s operational costs would decrease by approximately$214K (excluding staffing) based on historical costs► The total school footprint would see a decrease in net

square metres of 6,736 m2 for a reconfigured 6-12school.

► Operational costs (excluding staffing) would decreaseby approximately $214K for the reconfigured school ifbased on the historical costs of the schools in scope.

► Note: The energy savings adjustment for the new schooladdition was applied to the historical operational costs ofTantramar Regional High School to estimate the increasedoperational costs for the addition (509 m2).

Reconfiguration of Tantramar Regional school scenario

Source: ASD-E School Utilization Review (May 2015), and EECD School Asset Data. *Operating costs include electricity, natural gas, oil, garbage and snow removal,custodial salaries, telephone, water and sewer, minor repairs, cleaning supplies, alarms, inspections and vandalism repairs. The energy savings adjustment is the

savings estimated by EECD Infrastructure Planning for comparing older to newer energy efficient buildings ($17.97/m2 and $16.47/m2).

Schools (For 6-12 Reconfiguration) Area (m2)Dorchester Consolidated (in K-5 scenario) 0Marshview Middle School 7,245Total for potential school closures: 7,245Tantramar Regional High School Addition 509Total new space for schools: 509Decrease in total m2: (6,736)

DorchesterConsolidated(See K-5)A.

MarshviewMiddleSchoolB.

TantramarRegional HighSchoolC.

School additionD= C EnergySavingsAdjustment xSQM

Projected OperationalCosts for reconfigured6-12 School (based onhistorical cost per metre)E = C + D

Operating Costs* $234,035 $564,175 $20,536 $584,711Square Metres 7,245 13,482 509 13,991Cost Per Square Metre $32.30 $41.85 $40.35Energy Savings Adjustment $1.50 B Operating - D Operating

Total $32.30 $40.35 Savings: 213,499$

Based on May 2015 ASD-E School Utilization Review

Page 24: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 24

Grades SizeLimit

Total HomeRooms

MaximumCapacity

K 21 19 19 18 56 3 631 21 13 12 16 15 56 4 842 21 13 13 16 16 58 4 843 26 19 18 25 25 87 4 1044 28 17 17 22 22 78 4 1125 28 19 19 23 22 83 4 1126 28 23 23 22 22 90 4 1127 29 19 18 24 23 84 4 1168 29 26 25 24 23 98 4 1169 29 24 24 24 27 27 126 5 14510 29 22 21 21 27 27 118 5 14511 29 26 26 26 26 104 4 11612 29 25 25 25 24 1 100 5 145

Empty 29 0 0Total: 1,138 54 1,454

Projected Utilization: 78.3%

Space Requirements

Regular Program French Immersion

Design Capacity for the New K-12 School (1,138 Students)

Based on ASD-E enrolment projection software results, a newK-12 for Tantramar Community would be sized for 1,138students and have 54 home rooms (depending on start time)

§ Enrolment projections made using theBaragar Systems software indicate asteady decline in K-12 student populationafter 2023-24.

§ 2023-24 was projected with the moststudents (1,138) after potentialconstruction.

§ The projected utilization for a new K-12school based on the design of 1,138students is 78.3%, with 54 home rooms.

§ This is outside recommended sizing for aK-12 school. The Planning Guidelinesnote a combined school is recommendedwhen enrolment falls below 200 for anelementary school (K-5 is 418 students).

§ For comparison, based on 2015-16school statistics, GNB had 16 K-12schools, with the largest being 626students at Centre Scolaire Samuel-de-Champlain (close to half the size).

Source: ASD-E enrolment projection software – Baragar Systems, EECD Policy, Planning Summary Statistics and Collective Agreement with the NB Teachers’ Federation.

Project start-up would depend on DEC and GNB approval. Year 4 of the estimated construction wouldbe 2021-22 (depending on start time).

Year K 1 2 3 4 5 6 7 8 9 10 11 12 Total2016-17 69 82 77 80 87 61 67 74 68 101 100 102 123 1,0912017-18 78 70 87 85 85 87 62 68 75 94 96 100 122 1,1092018-19 74 81 74 94 89 83 88 63 68 115 88 94 109 1,1202019-20 67 74 83 78 97 88 84 89 64 94 109 83 103 1,1132020-21 80 68 77 87 82 96 89 85 88 103 88 104 85 1,1322021-22 56 81 70 80 90 82 96 90 86 115 96 83 109 1,1342022-23 56 56 83 75 84 90 84 97 90 125 107 93 86 1,1262023-24 56 56 58 87 78 83 90 84 98 126 118 104 100 1,1382024-25 56 56 58 59 91 77 84 91 84 124 118 111 110 1,1192025-26 56 56 58 59 63 91 78 84 91 121 117 113 114 1,1012026-27 56 56 58 59 62 63 92 79 84 115 113 109 120 1,0662027-28 56 56 58 59 62 63 63 93 78 117 108 106 112 1,0312028-29 56 56 58 59 62 63 63 64 93 116 109 101 109 1,0092029-30 56 56 58 59 62 63 63 64 64 117 108 102 103 9752030-31 56 56 58 59 62 63 63 64 64 102 109 103 106 9652031-32 56 56 58 59 62 63 63 64 64 92 95 103 108 943

Review of 10-year planning horizonProjections used for school design in review

Projections for New K-12 School (Based on ASD-E Baragar Software)

New K-12 school scenario

Page 25: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 25

A Class “D” estimate* of $41.7M to $42.7M would be requiredfor the construction of a new K-12 school, with a costavoidance of $7.7M in deferred maintenance

► Class “D” estimate* for a new K-12 school (1,138 students) is approximately $41.7M to$42.7M, depending on the cost of land and any topographical challenges.

► The new school is estimated to be 18,629 m2 based on the current EECD Planning Guidelines.► If Dorchester Consolidated was removed from this scenario, the savings for the new K-12

school would be 5% ($2.2M) compared to the cost with the school included. There would beapproximately 1,020 m2 less in the new school footprint (two fewer classrooms, art room, multi-purpose gym/ancillary space and small reductions to the size of the library, and dining areas).

► EECD Planning Guidelines recommend a site size of 30 acres for a K-12 school of1,138 students (Note: In urban areas, site size may be reduced when land is at a premiumand/or existing community field/facilities are used offsite).

► The cost avoidance for deferred maintenance at the two proposed amalgamated schools wasidentified as $7.7M in the EECD School Physical Plant Status Report.

*Note: Class "D" estimate (± 30%) based on the EECD Planning Guidelines for Educational Facilities, as an estimate for this report only. Economy of scale has been assumed,with construction costs lowered from $2,690/m2 to $2,185/m2 (as per EECD “rules of thumb”). Estimates will be adjusted when EECD Infrastructure and project team establish

the actual space allocation.

Note: The estimated cost does notinclude space for the SackvilleEducation Centre, or the WetlandsCentre (currently in TantramarRegional High School), which arenot in the K-12 EECD PlanningGuidelines. The District noted thatthe location of a potential newK-12 is unknown and/or if theschool would be located too faraway from Sackville WaterfowlPark. It was determined to leavethis space out of the new schoolscenario.

New K-12 school scenario

School Grade Levels Reconfigured: K-12Total Number of K-12 Students Projected Within New School's Boundary (2023-24): 1,138New K-12 School Estimated CostNew 1,138 Student K-12 School (18,629 m2) $40.7MLand Purchase (depending on cost of land and location): $1M – $2MEstimated Cost for New K-12 School: $41.7M – $42.7MDeferred Maintenance to be Avoided for School Amalgamations Cost AvoidedDorchester Consolidated School Deferred Maintenance $1,812,000Salem Elementary School Deferred Maintenance $1,450,000Marshview Middle School Deferred Maintenance $2,474,000Tantramar Regional High School Deferred Maintenance $1,995,000Estimated Cost Avoidance for Deferred Maintenance: $7.7M

Page 26: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 26

DorchesterConsolidatedSchoolA.

SalemElementarySchoolB.

MarshviewMiddleSchoolC.

TantramarRegional HighSchoolD.

Total for proposedschool closuresE= (A + B + C + D)

Projected OperationalCosts for new K-12 School(based on historical costper square metre) F.

Operating Costs* $95,521 $218,721 $234,035 $564,175 $1,112,452 $728,394Square Metres 2,322 4,353 7,245 13,482 27,402 18,629Cost Per Square Metre $41.14 $50.25 $32.30 $41.85 $40.60 $39.10

Old Schools ($/m2) $17.97 $17.97 $17.97 $17.97 $17.97New Schools ($/m2) $16.47 $16.47 $16.47 $16.47 $16.47Energy Savings Adjustment $1.50 $1.50 $1.50 $1.50 $1.50 F Operating - E Operating

Total $39.64 $48.75 $30.80 $40.35 $39.10 (384,058)$

Based on May 2015 ASD-E School Utilization Review

EECD Estimated Savings ForUtility Efficiency:

For a new K-12, the District’s operational costs woulddecrease by approximately $399K (excluding staffing) basedon historical costs for schools of similar size and efficiency► The total school footprint would see a decrease in net

square metres of 8,773 m2 for a new K-12 school.

► Operational costs (excluding staffing) woulddecrease by approximately $384K for the newschool if based on the historical costs of theschools in scope. However, this isunderestimated when compared to otherschools of similar size.

► A review of operatingcosts for schools of asimilar size/scale indicatesthe decrease would beapproximately $399K (thisaccounts for economy ofscale factors).

Note: Energy savings adjustment wasnot applied to the larger schoolanalysis, as some of the schools arenew and are designed for energyefficiency.

New K-12 school scenario

Source: ASD-E School Utilization Review (May 2015), and EECD School Asset Data. *Operating costs include electricity, natural gas, oil, garbage and snow removal,custodial salaries, telephone, water and sewer, minor repairs, cleaning supplies, alarms, inspections and vandalism repairs. The energy savings adjustment is the

savings estimated by EECD Infrastructure Planning for comparing older to newer energy efficient buildings ($17.97/m2 and $16.47/m2).

Schools (For K-12 Scenario) Area (m2)Dorchester Consolidated School 2,322Salem Elementary School 4,353Marshview Middle School 7,245Tantramar Regional High School 13,482Total for potential school closures: 27,402New K-12 school 18,629Total new space for schools: 18,629Decrease in total m2: (8,773)

BerniceMacNaughtonHigh SchoolA.

HarrisonTrimbleHigh SchoolB.

RiverviewHigh SchoolC.

Moncton HighSchoolD.

Total for referenceschool closuresE= (A + B + C + D)

Projected OperationalCosts for new K-12 School(based on historical costper square metre) F.

Operating Costs* $542,574 $546,544 $679,475 $734,484 $2,503,077 $713,118Square Metres 15,107 15,653 17,230 17,391 65,381 18,629Cost Per Square Metre $35.92 $34.92 $39.44 $42.23 $38.28 $38.28

F Operating - E Operating

(399,334)$

Based on May 2015 ASD-E School Utilization Review

Operating Costs* of SchoolsIn Scope $1,112,452

Page 27: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 27

Enrolment

Schools (For Review) 2016-17 Existing By PlanningGuidelines

Shortage toGuidelines

PercentVariance

Dorchester Consolidated School 58 0 2,322 2,780 458 16.5%Salem Elementary School 367 2 4,353 6,053 1,700 28.1%Marshview Middle School 240 0 7,245 5,221 (2,024) -38.8%Tantramar Regional High School 426 0 13,482 8,221 (5,261) -64.0%Total 1,091 2 27,402 22,275 (5,127) -23.0%

Number of MobileClassrooms

Area (m2)

Schools are not standardized to a typical grade configuration(e.g. K-5/K-8) and there is an overall surplus of pedagogicalspace compared to current EECD Planning Guidelines

► A key component of a long-term infrastructure plan includes providing enough space to meetthe pedagogical needs of the District/community:§ Two schools are not standardized to a typical grade configuration (e.g. K-5, 6-8 or K-8).

Salem Elementary School is K-4 and Marshview Middle School is 5-8.§ EECD Planning Guidelines define Dorchester Consolidated as a small mixed school (less

than 300 students), Marshview as a small middle school (less than 300 students), andTantramar Regional as a small high school (less than 500 students). The Guidelines specifyless supporting space for small schools than for regular sized schools. When combined witha dropping historical enrolment, there is a surplus of space at the middle and high schoolscompared to the Guideline specifications.

§ The elementary schools were built under older guidelines, and there is pedagogical spacethat is missing compared to a modern school (e.g. break-out rooms, Early ChildhoodDevelopment, multi-function rooms, and performing arts). Based on 2016-17 enrolments,Salem Elementary would be 28% larger if constructed to the current Guidelines.

Source: ASD-E School Utilization Review (May 2015), and EECD School Asset Data.

Page 28: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 28

Appendix A – Aerial View of Schools

Page 29: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 29

B

C

A

Dorchester Consolidated School – Is the smallest K-8 schoolin ASD-E at 2,322 m2 and is undersized compared to EECDPlanning Guidelines (even with the current enrolment of 58)

Dorchester Consolidated School (K-8)• Dorchester Consolidated School is located

on the corner of Harrop Avenue and SchoolStreet.

• The school was originally built in 1956 andhad upgrades in 1961.

• The school is located approximately13.2 km away from Salem ElementarySchool and 15.6 km from TantramarRegional High School.

• Students from Dorchester ConsolidatedSchool boundary attend Salem ElementarySchool to take Early French Immersion.

• The net for out-of-zone students in thisschool boundary is a small gain (+4).

• Picture A: View of front side of school –Topography is sloping.

• Picture B: View of the west side of theschool property – Topography is flat withthe play area marking the property line.

• Picture C: View of the southeast side of theschool – Topography is flat.

A B C

Note: The school footprint is the smallest of the twelve ASD-EK-8 schools at 2,322 m2. For comparison: a replacement schoolbuilt to current EECD Planning Guidelines (for the same numberof students) would be approximately 2,780 m2 (assumingcombined classrooms are used due to the low enrolment).

Source: Google Maps and GeoNB Viewer: http://geonb.snb.ca/geonb/, site visit and EECD Planning Guidelines for Educational Facilities.

Page 30: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 30

Salem Elementary School is the fourth largest elementaryschool in ASD-E at 4,353 m2 and is undersized compared tocurrent EECD Planning Guidelines (has 2 mobile classrooms)

Salem Elementary School (K-4)• Salem Elementary School is located on

Queen’s Road in Sackville, NB.• The school was originally built in 1980.• The school is located approximately

13.2 km away from DorchesterConsolidated School and 650 m fromMarshview Middle School.

• Students from Dorchester ConsolidatedSchool boundary attend Salem ElementarySchool to take Early French Immersion.

• The school has two mobile classroomsattached with a breeze-way.

• The net for out-of-zone students in thisschool boundary is a small gain (+4).

• Picture A: Back side of the school – view ofthe mobile classrooms and playground.

• Picture B: View of the south side of theschool property – baseball field.

• Picture C: View of the west corner of theschool – the boarding field is elevatedhigher than the school property.

A B C

Note: The school footprint is the fourth largest in the ASD-Eelementary system at 4,353 m2. For comparison: areplacement school built to current EECD Planning Guidelines(for the same number of students) would be approximately6,053 m2.

Source: Google Maps and GeoNB Viewer: http://geonb.snb.ca/geonb/, site visit and EECD Planning Guidelines for Educational Facilities.

Richardson

Street

AB

C

MC

MC

Page 31: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 31

Marshview Middle School is considered a small middleschool in the EECD Planning Guidelines (less than 300students) and has excess space compared to the guidelines

Marshview Middle School (5-8)• Marshview Middle School is located on

Queen’s Road in Sackville, NB.• The school was originally built in 1949 and

had upgrades in 1956.• The school is located approximately

13.6 km away from DorchesterConsolidated School, 650 m from SalemElementary School and 3.1 km fromTantramar Regional High School.

• The net for out-of-zone students in thisschool boundary is a small gain (+5).

• Picture A: East side of the school – view ofthe elevation drop-off between theplayground and the play field.

• Picture B: East side of the school – view ofthe sloped driveway grade towards DufferinStreet.

• Picture C: View of south side of theschool – sited on property line close toQueen’s Road, with a school entrance nextto road.

A B C

Note: The school footprint is the second largest of the fourschools in the ASD-E middle system at 7,245 m2. Forcomparison: a replacement school built to current EECDPlanning Guidelines (for the same number of students) would beapproximately 5,221 m2 (considered a small middle school).

Source: Google Maps and GeoNB Viewer: http://geonb.snb.ca/geonb/, site visit and EECD Planning Guidelines for Educational Facilities.

A

B

C

Page 32: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 32

Tantramar Regional High School is considered a small highschool in the EECD Planning Guidelines (less than 500students) and has excess space compared to the guidelines

Tantramar Regional High School (9-12)• Tantramar Regional High School is located

on Main Street in Sackville, NB.• The school was originally built in 1968.• The school is located approximately 3.1 km

from Marshview Middle School.• Port Elgin Regional School (K-8) is a feeder

school for Tantramar Regional High, inaddition to the three other schools in scope.

• There is congestion for parent and bus dropoff with the parking lots (1 and 2) using thesame access.

• Picture A: Southeast side of the school –view of the football field (small slope downfrom school level) with Sackville WaterfowlPark in background.

• Picture B: North side of the school – view ofthe sloped elevated grade to the soccerfield. On this side of the school there isoutside access to the Wetlands Centre andMetal Shop.

• Picture C: View of east side of the school –cyclone and outside access to wood shop.

A B C

Note: The school footprint is the smallest of the five schools inthe ASD-E high school system at 13,482 m2. For comparison: areplacement school built to current EECD Planning Guidelines(for the same number of students) would be approximately8,221 m2 (considered a small high school).

Source: Google Maps and GeoNB Viewer: http://geonb.snb.ca/geonb/, site visit and EECD Planning Guidelines for Educational Facilities.

A

BC

SackvilleWaterfowl Park

1

2

Page 33: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 33

Appendix B – School Boundaries and Bussing

Page 34: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 34

Dorchester

Sackv ille

PortElgin

Amherst

ROUTE 2

MARC PVT

ROUTE93

5

ROUT

E11

4

ROUT

E94

0

ROUTE 970

LA MONTAIN ST

FORT

BEA

USEJOU

RR

D

ROUTE 960

ROUTE

15

ROUTE 16

ANDERSON MILL ST (MEMRAMC OOK) MUL

LETT

LOO

P

LAVALLEE

ROUTE

ROUTE 106

MOUNT

WHA

TLEY

LOOP

JOH

NS

TRO

KES

MEMRAMCOOKRD E

POIN

TED

EBU

TE

LOO

P

CALHOUN STATION

BUNKER AL

FRONT WOOD'S BEACH LANE E

CHERRY BURTON RD

MIDDLEW

EST MARSHPVT

SCO

UTCH

ROUTE

106(D

OR

CHESTER)

PENNY PVT

CALHOUN BYE

SAMANTHACT

MIDGI

CRD

Marshview Middle School

Port Elgin Regional School

ABOUJAGAN

E RD(M

EM)

AIME RD

ALBERT MINES RD

ALICE ST

ALP

HEE

RU

AULACRD

BABC

OCK

RD

BARREN GROUND HILL

BASELINE RD (FAF)

BELLIV

EAU

RU

BLAIR ST

BOB

TR

ENH

OLM

RD

BOURGEOIS RU

BRIDGE RD

BRITISH SET RD

BROOKLYN

RD

BUCK

RD

CA

LHO

UN

RD

CAPE

RD

CARR

IAG

ECT

CATTAIL

RG

CHERRY BURTON RD BV

CH RISTOPHER RD

COBURGRD

COLE

SIS

LAND

RD

CONN

OLYRD

CO

OKV

ILL E

L OO

PR

D

CORO

NATI

ONAV

DES SCOUTS RD

DISC

OVER

YR

D

DORCHESTER

CAPERD

DU MARAIS RU

ETTER RIDGE RD

F AIRFIELD RD (SACKVILLE)

FEDERALGOVERNMENT RD

FORKSRD

FORT MONCT ON RD

GOOSE LAKE RD

GRUB RD (HILLSBOROUGH)

HAVELO

CKNOI

LES

RD

HIGH MARSH RD

JOB

ALLEN

RD

JOLICURE RD

KING ST (SACKVILLE)

LANDING RD

LEGE

RRU

LON

GLA

KE

RD

LUCIPHY RD

MAHONEYRD

MARIE RU

MICHEL

RD

O'H

EAR

NR

D

OVILA ST

PINEWOOD LN

PINK

ROCK

RD

PONT ROUGE RD

PRINCIPALE RU

QUEENS RD

RALP

HST

ILES

RD

READEQUARRYRD

ROCKLYNN RD

ROYALRDSARA RU

SECOND

WESTCOOK RD

TAYLO

RC

H

TOW

SERD

TRAN

SCA

NADA

HY

UP

PER

AB

OU

J AG

ANE

RD

WARDS SIDING RD

WH

ITE

BIRC

HRD

WATER

Dorchester Consolidated andSalem Elementary School Boundaries

1 2

3

4

5

6

7

8

Dorchester ConsolidatedSchool Boundary

Legend

1

2

3

4

5

6

7

8

Route 106 (Dorchester)

Woodhurst Road

Cape Road

Route 935

Baseline Road

Route 106

Ralph Stiles Road

Trans-Canada Highway

Salem ElementarySchool Boundary

Source: ASD-E school transportation software - Versatrans

8

Page 35: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 35

Students in Early French Immersion located in theDorchester Consolidated school boundary already travel toSalem Elementary (adds approximately 12 minutes for bus)

Impact of proposed new K-5 school boundaryamalgamating Dorchester Consolidated School

• Dorchester Consolidated School is centrally located within itsschool boundary. The school is 13.2 km away from SalemElementary School (approximately 12 minutes). The traveldistance for students living towards the outer school boundaryto the north, west and south was reviewed.

• Note: Students who are in Early French Immersion are travellingfrom this school boundary to attend Salem Elementary Schoolstarting in grade 3. GNB is lowering the start point for EarlyFrench Immersion to grade 1. Therefore, busses will already betravelling from the Dorchester Consolidated school boundary forboth elementary (except kindergarten) and middle school.

Northern Boundary (Route 106 – Dorchester)• Route 106 (Dorchester) to the Salem Elementary School via

NB-106 is approximately 21.4 km (18 minutes with no stops).• Route 106 (Dorchester) to Dorchester Consolidated School via

NB-106 is approximately 8.3 km (7 minutes with no stops).

Northern Boundary (Woodhurst Road)• Woodhurst Road to Salem Elementary School via Baseline

Road and King Street is approximately 11.9 km (16 minutes withno stops).

• Woodhurst Road to Dorchester Consolidated School via NB-106is approximately 6.5 km (9 minutes with no stops).

Source: Google Maps

Route 106(Dorchester)

NB-106

Woodhurst Road

Note: For estimation purposes only; actual distance and time willdepend on where the proposed K-5 school is sited.

1

1

2

NB-106

2

NB-106

DorchesterConsolidated

DorchesterConsolidated

SalemElementary

SalemElementary

Page 36: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

Page 36

With Dorchester Consolidated School centrally located,those students residing to the far northern part of the schoolboundary would be the farthest from Salem Elementary

Impact of proposed new K-5 school boundaryamalgamating Dorchester Consolidated School

• The students residing in the western and southern portions ofthe school boundary are closer to Salem Elementary School inSackville than those students living in the northern part of theschool boundary.

Western Boundary (Cape Road)• The majority of the students are clustered in the Cape Road

area, close to Dorchester Consolidated School.• Cape Road area to the Salem Elementary School via NB-106 is

approximately 14.1 km (12 minutes with no stops).

Southern Boundary (Route 935)• Route 935 area to Salem Elementary School via NB-935 and

NB-106 is approximately 18.2 km (17 minutes with no stops).• Route 935 area to Dorchester Consolidated School via NB-935

is approximately 4.8 km (6 minutes with no stops).

Source: Google Maps

CapeRoad

NB-106

Route 935

Note: For estimation purposes only; actual distance and time willdepend on where the proposed K-5 school is sited.

3

3

4

4

NB-106

DorchesterConsolidated

DorchesterConsolidated

SalemElementary

SalemElementary

NB-935

Page 37: Anglophone East School District (ASD-E) Multi-year ...web1.nbed.nb.ca/sites/ASD-E/dec/Documents/ASD-E 2017...Anglophone East School District (ASD-E) Multi-year infrastructure planning

EY | Assurance | Tax | Transactions | Advisory

About EY

EY is a global leader in assurance, tax, transaction and advisory services.The insights and quality services we deliver help build trust and confidencein the capital markets and in economies the world over. We developoutstanding leaders who team to deliver on our promises to all of ourstakeholders. In so doing, we play a critical role in building a better workingworld for our people, for our clients and for our communities.

EY refers to the global organization, and may refer to one or more, of themember firms of Ernst & Young Global Limited, each of which is a separatelegal entity. Ernst & Young Global Limited, a UK company limited byguarantee, does not provide services to clients.

For more information about our organization, please visit ey.com.

© 2017 Ernst & Young LLP. All Rights Reserved.A member firm of Ernst & Young Global Limited.

This publication contains information in summary form, current as of the date ofpublication, and is intended for general guidance only. It should not be regarded ascomprehensive or a substitute for professional advice. Before taking any particularcourse of action, contact Ernst & Young or another professional advisor to discussthese matters in the context of your particular circumstances. We accept noresponsibility for any loss or damage occasioned by your reliance on informationcontained in this publication.