12
1 Andrews v ANZ and penalty clauses © Philip Davenport 2012 1 This paper was presented at the seminar of the Adjudication Forum on 13 November 2012. Andrews v Australia and New Zealand Banking Group [2012] HCA 30 decided on 6 September 2012 will have most profound implications for construction law and adjudication. For construction law, it is the most important case since Pavey & Matthews v Paul (1986) 162 CLR 221 recognised that unjust enrichment is part of the common law of Australia. Soon Andrews will be the case most often cited by claimants in adjudication. Construction contracts are replete with penalty clauses. In particular, time bar clauses have been used to penalise contractors and subcontractors. Examples of other penalty clauses are considered below. The message this paper is intended to convey is that contractors and subcontractors should not submit to such penalties. Penalty provisions are void. At present, I find that the case most often cited in adjudications is John Goss Projects v Leighton Contractors [2006] NSWSC 798. In that case McDougall J considered a clause that provided that the respondent Leighton would not be liable upon any claim by the contractor John Goss in respect of any matter arising out of the contract including but not limited to variations and claims for damages unless the claim together with full particulars thereof was lodged with Leighton not later than ten business days after the date the contractor became aware or should reasonably have become aware of the occurrence of the events or circumstances on which the claim is based. The contractor argued that the clause was rendered void by s 34 [No contracting out] of the Building and Construction Industry Security of Payment Act 1999 (NSW) because clause 45 provided a time limitation for the making of claims under the Act which was inconsistent with s 13(4) of the Act which allows a claimant to serve a payment claim within of 12 months after construction work was last carried out. McDougall J found that the time bar was effective and was not inconsistent with the Act. He said: 80 Where John Goss wishes to claim an amount over and above the Contract Amount (for example, for a variation, or for delay or disruption costs), it is required, as a precondition of such a claim, to give notice under, and complying with the terms of, cl 45. It is obvious why a head contractor in Leighton’s position might stipulate for such notice. Firstly, it will enable the claim to be investigated promptly (and, perhaps, before any work comprised in it is rebuilt, or built over). Secondly, it will enable Leighton to monitor its overall exposure to the subcontractor. Thirdly, it will enable Leighton to 1 Philip Davenport is a solicitor, adjudicator and an adjunct professor at UNSW. He is the author of Adjudication in the Building Industry 3 rd edn 2010 Federation Press and Construction Claims 2 nd edn 2006 Federation press. Adjudicaton in the Construction Industry 3rd edition by Philip Davenport All Rights Reserved The Federation Press

Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

Embed Size (px)

Citation preview

Page 1: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

1

AndrewsvANZandpenaltyclauses

©PhilipDavenport20121

ThispaperwaspresentedattheseminaroftheAdjudicationForumon13November2012.

AndrewsvAustraliaandNewZealandBankingGroup[2012]HCA30decidedon6September2012willhavemostprofoundimplicationsforconstructionlawandadjudication.Forconstructionlaw,itisthemostimportantcasesincePavey&MatthewsvPaul(1986)162CLR221recognisedthatunjustenrichmentispartofthecommonlawofAustralia.SoonAndrewswillbethecasemostoftencitedbyclaimantsinadjudication.Constructioncontractsarerepletewithpenaltyclauses.Inparticular,timebarclauseshavebeenusedtopenalisecontractorsandsubcontractors.Examplesofotherpenaltyclausesareconsideredbelow.Themessagethispaperisintendedtoconveyisthatcontractorsandsubcontractorsshouldnotsubmittosuchpenalties.Penaltyprovisionsarevoid.Atpresent,IfindthatthecasemostoftencitedinadjudicationsisJohnGossProjectsvLeightonContractors[2006]NSWSC798.InthatcaseMcDougallJconsideredaclausethatprovidedthattherespondentLeightonwouldnotbeliableuponanyclaimbythecontractorJohnGossinrespectofanymatterarisingoutofthecontractincludingbutnotlimitedtovariationsandclaimsfordamagesunlesstheclaimtogetherwithfullparticularsthereofwaslodgedwithLeightonnotlaterthantenbusinessdaysafterthedatethecontractorbecameawareorshouldreasonablyhavebecomeawareoftheoccurrenceoftheeventsorcircumstancesonwhichtheclaimisbased.Thecontractorarguedthattheclausewasrenderedvoidbys34[Nocontractingout]oftheBuildingandConstructionIndustrySecurityofPaymentAct1999(NSW)becauseclause45providedatimelimitationforthemakingofclaimsundertheActwhichwasinconsistentwiths13(4)oftheActwhichallowsaclaimanttoserveapaymentclaimwithinof12monthsafterconstructionworkwaslastcarriedout.McDougallJfoundthatthetimebarwaseffectiveandwasnotinconsistentwiththeAct.Hesaid:

80WhereJohnGosswishestoclaimanamountoverandabovetheContractAmount(forexample,foravariation,orfordelayordisruptioncosts),itisrequired,asapreconditionofsuchaclaim,togivenoticeunder,andcomplyingwiththetermsof,cl45.ItisobviouswhyaheadcontractorinLeighton’spositionmightstipulateforsuchnotice.Firstly,itwillenabletheclaimtobeinvestigatedpromptly(and,perhaps,beforeanyworkcomprisedinitisrebuilt,orbuiltover).Secondly,itwillenableLeightontomonitoritsoverallexposuretothesubcontractor.Thirdly,itwillenableLeightonto

1PhilipDavenportisasolicitor,adjudicatorandanadjunctprofessoratUNSW.HeistheauthorofAdjudicationintheBuildingIndustry3rdedn2010FederationPressandConstructionClaims2ndedn2006Federationpress.

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 2: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

2

assessitsownpositionvisavisitsprincipal.Nodoubt,thereareothergoodreasonsforstipulationsofthekindfoundincl45.

81Itiscorrecttosaythatcl45operatestobarclaimsifthenoticeprovisionsinitarenotfollowed.Butitdoesnotfollowthatcl45istherebyinconsistentwiththerightsgivenundertheAct,soastoattracttheoperationofoneorotherofthealternativessetoutins34(2).

Mostmajorconstructioncompaniesnowhavesimilartimebarsintheirconstructioncontractsandinadjudicationtheyinvokethetimebarstoavoidpayingasubcontractorwhatwouldotherwisebethesubcontractor’sentitlement.Theyalsousethetimebar(whentheclaimanthasfailedtoclaimanextensionoftimewithintheprescribedperiod)toenablethemtorecoupliquidateddamageseventhoughtheyhavedelayedtheclaimant.Onemajorcontractorhasgeneralconditionsofsubcontractthatprovidethatthesubcontractorhasnoentitlementtoanextensionoftimeunlessthesubcontractorhasgivenawrittennoticeofclaimwithin3businessdaysaftertheeventcausingthedelayfirstoccurs.Thosesamegeneralconditionsprovidethatthesubcontractormustcomplywithanydirectionofthecontractorandifthesubcontractordoesnot,beforecomplyingwiththedirectionandwithin3businessdaysofthedirection,provideawrittennoticeofaclaimforadditionalpaymentandanextensionoftime,thesubcontractorwillnotbeentitledtoanyadditionalmoneyortimeforcomplyingwiththedirection.WhentheissueofatimebararisesinadjudicationtherespondentalmostinvariablycitesJohnGossProjectvLeightonasauthorityfortheeffectivenessofthetimebar.Whatwasnotconsideredinthatcasewaswhethertheeffectofthetimebarwastoimposeapenalty.Todate,Ihavenotfoundanyclaimantwhohasattackedthetimebarclauseonthegroundthatitisapenalty.However,followingtheHighCourtdecisioninAndrews,Ianticipatethatthatwillbecomeamajorissueinadjudication.Andrewshasnotchangedthelaw.Itmerelyclarifiesthelawonpenalties.AstheCourtacknowledgesat[38],eveninRomanlawapenaltymightbereducediffoundtobeexcessive.PriortoAndrewstherewasawidespreadbeliefthatacontractprovisioncouldonlybeapenaltyifitpunishedapartyforbreachingthecontract.Forexample,inInterstarWholesaleFinancevIntegralHomeLoans[2008]NSWCA310theCourtofAppealat[106]heldthatthedoctrineofpenaltiesislimitedtothecircumstancesofbreachofcontract.InAndrewsat[50]theHighCourtsaidthattheCourtofAppealmisunderstoodthescopeofthepenaltydoctrine.Interstarwasinthebusinessoflendingmoneyonthesecurityofmortgages.IntegralcontractedwithInterstartointroduceborrowersandtomanagetheloans.Thereweretwocontracts.InterstarterminatedthecontractsonthebasisthatIntegralhadengagedindeceptiveactivityinrelationtoloanapplicationfiles.Thevalidityoftheterminationwasnotinissue.Clause20ofthecontract

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 3: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

3

providedthatuponterminationIntegralwouldhavenorighttoanyfees.TheconsequencewasthatIntegralcouldnotearnfeeswhichhadnotaccruedatthedateofterminationbutwouldhavebeenearnedbutfortermination.TheCourtofAppealfoundthattherewasnoforfeitureofearnedamountsandnorelevantbreachofcontractthatcouldengagethelawofpenalties.InInterstarthecontractorprovidedservicesbutthetimeforpaymenthadnotyetarrivedbecausetheserviceswereincomplete.Theprincipalclaimedthatthecontractor’sentitlementtopaymentwasextinguishedbytheterminationofthecontract.InJohnGossthesubcontractorhadcarriedoutwork.Theprincipalcontendedthatthesubcontractor’sentitlementtopaymentwasextinguishedwhenthesubcontractorfailedtogiveanotice.Bothareinstancesoftheforfeiturebyonepartyofanentitlementtomoneywheretheamountforfeitedborenorelationshiptothedamagessufferedbytheotherparty.InAndrews,theHighCourtfoundthatInterstarwaswronglydecided.Forthesamereason,JohnGosswaswronglydecided.Granted,theclaimantinJohnGossfailedtoraisetheargumentthatthetimebarwasapenalty.However,thetimebarclearlypenalisedJohnGoss,Leighton’ssubcontractor.Nowanyclaimantfacedwithsuchatimebarclauseshouldarguethatthetimebarisapenalty.ThereasonsgivenbyMcDougallJforupholdingthevalidityofthetimebararenotgoodlaw.AndrewsinvolvedaclassactionbycustomersagainsttheANZBank.TheargumentoftheBankcustomerswasthatcertainfeeschargedbytheBankwerevoidbecausetheywereapenalty.Thefeeswerenotpayableforbreachbythecustomersoftheircontractswiththebank.Ifan‘instruction’[forexampleachequeororderforaperiodicalpayment]totheBankbyacustomerwouldhavetheeffectofoverdrawingthecustomer’saccount,theBankcouldeitherhonourtheinstruction[allowtheaccounttobeoverdrawn]ordishonourit.TheBankwouldthenchargethecustomeran‘HonourFee’forhonouringtheinstructionoran‘OutwardDishonourFee’fordishonouringtheinstruction.Thecustomersarguedthatthesefeeswereapenaltyandwerethereforeunenforceable.TheyarguedthatthefeeswereimposeduponorindefaultoftheoccurrenceofstipulatedeventsbutwereoutofallproportiontothelossordamagewhichmighthavebeensustainedbytheBankbyreasonoftheoccurrenceoftheevents.(Andrewsat[27]).TheBankarguedthatsincethefeeswerenotchargedforbreachofcontract,theycouldnotbeapenalty.TheprimaryjudgefollowedtheCourtofAppealdecisioninInterstarandfoundthatthefeeswerenotapenalty.TheHighCourtsaidthatInterstarwaswronglydecidedand,consequently,theprimaryjudgeerredinconcludingthatintheabsenceofacontractualbreachthefeescouldnotbecategorisedaspenalties(Andrewsat[78]).ThepenaltydoctrineisdescribedinAndrewsat[10]asfollows:

Ingeneralterms,astipulationprimafacieimposesapenaltyonaparty(“thefirstparty”)if,asamatterofsubstance,itiscollateral(oraccessory)toa

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 4: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

4

primarystipulationinfavourofasecondpartyandthiscollateralstipulation,uponthefailureoftheprimarystipulation,imposesuponthefirstpartyanadditionaldetriment,thepenalty,tothebenefitofthesecondparty.Inthatsense,thecollateraloraccessorystipulationisdescribedasbeinginthenatureofasecurityforandinterroremofthesatisfactionoftheprimarystipulation.Ifcompensationcanbemadetothesecondpartyfortheprejudicesufferedbyfailureoftheprimarystipulation,thecollateralstipulationandthepenaltyareenforcedonlytotheextentofthatcompensation.Thefirstpartyisrelievedtothatdegreefromliabilitytosatisfythecollateralstipulation.

Iwillparaphrasethepenaltydoctrineinthecontextofaconstructioncontract.Assumethataconstructioncontractprovidesthatthecontractormayormustdosomething.Thatisaprimarystipulation.Ifthecontractordoesnotdothat,thentheprimarystipulationhasfailed.Ifthenthecontractimposesuponthecontractoranadditionaldetrimenttothebenefitoftheotherparty,theadditionaldetrimentisacollateraloraccessorystipulationandthatsecondstipulationmaybeapenalty.Ifcompensationcanbemadetotheotherpartyfortheprejudicesufferedbythefailureofthecontractortodothethingfirststipulated,theadditionaldetrimentcanonlybeenforcedtotheextentthatthatisnecessarytocompensatetheotherparty.Totheextentthattheadditionaldetrimentexceedsthatcompensation,itisapenaltyandunenforceable.ConsiderthatdoctrineinthecontextoftheJohnGosscase.Leighton’ssubcontractprovidedthatthesubcontractorJohnGosscouldmakeaclaimfordamagesordelayprovidedthattheclaimtogetherwithfullparticularsthereofwaslodgedwithLeightonnotlaterthantenbusinessdaysafterthedatethecontractorbecameawareorshouldreasonablyhavebecomeawareoftheoccurrenceoftheeventsorcircumstanceonwhichtheclaimisbased.Thatwasaprimarystipulation.Acollateralstipulation[thebarringofanyclaimnotnotifiedwithintime]imposeduponthesubcontractoranadditionaldetrimenttothebenefitofLeighton.ThepenaltydoctrineprovidesthatifcompensationcanbemadetoLeightonfortheprejudicesufferedbythefailureofthesubcontractortogivethenoticewithintime,theadditionaldetrimentcanonlybeenforcedtotheextentthatthatisnecessarytocompensateLeighton.Iftheadditionaldetrimentexceedsthatcompensation,itisapenaltyandunenforceable.Ifthenoticeofclaimisonedaylate,willLeightonincuranydamage?Ifitisamonthlatewhatdamage,ifany,willLeightonincur?Thecollateralstipulationwouldresultintheforfeitureofanentitlementtopaymentofthesameamountwhetherthedelayisonedayoronemonthoranyotherperiod.Similarly,alumpsumforliquidateddamagesfordelaywouldbeapenaltyifthesameamountwaspayableirrespectiveofthelengthofthedelay.InJohnGossat[80]McDougallJsaid:

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 5: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

5

ItisobviouswhyaheadcontractorinLeighton’spositionmightstipulateforsuchnotice.Firstly,itwillenabletheclaimtobeinvestigatedpromptly(and,perhaps,beforeanyworkcomprisedinitisrebuilt,orbuiltover).Secondly,itwillenableLeightontomonitoritsoverallexposuretothesubcontractor.Thirdly,itwillenableLeightontoassessitsownpositionvisavisitsprincipal.

Thereisnothingwrongwithstipulatingforthenotice.AsMcDougallJsaid,theremaybegoodreasonsforsuchanotice.Thequestionisnotwhetherthestipulationforthenoticewasvalid.Thequestioniswhetherthecollateralstipulation[thebarringoftheclaim]isapenalty.ThecollateralstipulationimposesanadditionaldetrimentonthesubcontractortothebenefitofLeighton.ThepenaltydoctrineprovidesthatifcompensationcanbemadetoLeightonfortheprejudicesufferedbythefailureofthecontractortogivenoticewithintenbusinessdays,theadditionaldetrimentimposeduponthesubcontractorcanonlybeenforcedtotheextentthatthatisnecessarytocompensateLeighton.Iftheadditionaldetrimentexceedsthatcompensation,itisapenaltyandunenforceable.McDougallJidentifiesthreepossibleprejudicestoLeighton,namely,theinabilitytoinvestigatetheclaimpromptly,theinabilitytomonitoritsexposuretothesubcontractorandtheinabilitytoassessLeighton’spositionvisavisitsprincipal.AssumingthatLeightonsufferedtheseoranyotherprejudices,canthelosstoLeightoncanbequantifiedanddamagesassessed?Thedetrimentimposeduponthesubcontractorbearsnorelationshiptotheloss,ifany,sufferedbyLeighton.Consequently,ifthelosstoLeightoniscapableofassessmentthesecondstipulation[thebarringofthesubcontractor’sclaim]isapenaltyandunenforceable.TheHighCourtat[11]saidthatthepenaltydoctrinedoesnotapplywheretheprejudiceordamagetotheinterestsofthesecondparty[Leightonintheaboveexample]isinsusceptibleofevaluationandassessmentinmoneyterms.TheCourtsaid,‘Itistheavailabilityofcompensationwhichgeneratesthe“equity”uponwhichthecourtintervenes;withoutit,thepartiesarelefttotheirrightsandobligations.’NodoubtrespondentsinthepositionofLeightonsinJohnGosswillpointtothethreepossibleprejudicesidentifiedbyMcDougallJinJohnGoss,andotherallegedprejudices,andarguethattheprejudiceanddamagethattheywillsufferifnoticeofaclaimisnotgivenwithintheprescribedtimeisnotsusceptibletoassessmentinmoneyterms.Theywillarguethatthereforethepenaltydoctrinedoesnotapply.Thefactthatitisdifficulttoassessdamagesinmoneytermsdoesnotmeanthatthedamagesarenotassessableinmoneyterms.ThefirstofthethreepossibleprejudicesidentifiedbyMcDougallJistheinabilitytoinvestigatetheclaimpromptly.Hegivestheexampleofwheretheworkcompromisedisbuiltover.Byreasonofdelayinreceiptofthenotice,Leightonmayhaveadditionalcostofinvestigationoftheclaim.Thiscanbeassessedinmoneyterms.

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 6: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

6

TheotherpossibleprejudicesidentifiedbyMcDougallJaretheinabilityofLeightontomonitoritsexposuretothesubcontractorandassessitspositionvisavisitsprincipal.ThedelayinreceiptofthenoticeofaclaimmaymeanthatattimesLeighton’sexposuretothesubcontractormaybegreaterthatLeightonthinksitis.WillthisclauseanylosstoLeighton?Ifasaconsequenceofthedelayinreceiptofthenoticeofaclaim,Leighton’sexposuretothesubcontractororitspositionvisavistheprincipalchanges,itseemsthatthechangecanbemeasuredintermsofdamages.WhethertheprejudiceordamagetoLeightonisinsusceptibleofevaluationinmoneytermswouldbeamatterforevidence.Forthepenaltydoctrinetoapplytoatimebar,itisnotnecessarythatthereisanexpresscontractualrequirementfortheclaimanttogiveanoticewithinthespecifiedtime.Itissufficientthattheabsenceofanoticewithintheprescribedtimewillimposeupontheclaimantadetrimentthatisapenalty.SeeAndrewsat[67].Thedetrimentdoesnothavetobethepaymentbytheclaimanttotherespondentofasumofmoney.SeeAndrewsat[12].AwellknownandsoundauthorityonpenaltiesisGilbert‐Ash(Northern)vModernEngineering[1973]1BLR75.Paragraph3ofclause14ofthesubcontractthesubjectofthatcaseprovided:

IftheSub‐contractorfailstocomplywithanyoftheconditionsofthisSub‐contract,theContractorreservestherighttowithholdpaymentofanymoniesdueorbecomingduetotheSub‐contractor.

TheHouseofLordsheldthatthatprovisionwasapenalty.LordSalmonsaid:

Paragraph3purportstoconfermuchmoreoncontractorsthanthelawallows.Accordingtothenaturalmeaningofitslanguage,itwouldenablecontractorstosuspendorwithholdpaymentofverylargesumsofmoneyduetothesub‐contractorsintheeventofthesub‐contractorscommittingsomeminorbreachofcontractcausingonlytrivialdamageinnowaycomparabletotheamountowedtosub‐contractors.Theparagraphis,therefore,unenforceablesinceitprovidesfortheextractionofapenalty.

ThefollowingisanextractfromthestandardformofsubcontractofamajorAustraliancontractor:

TheBuilderisnotobligedtomakeanypaymentundertheSubcontractuntiltheSubcontractorhas…providedevidencesatisfactorytotheBuilderthatasattherelevantdate,theSubcontractorisnotinbreachoftheSubcontract.

ThatisapenaltyclausesimilartothatinGilbertAsh.Thatsamesubcontractprovidesthataprogressclaimmustcomplywithnumerousrequirements,intheabsenceofanyofwhich,thecontractorisnotliabletomakeaprogresspayment.Onesuchrequirementisastatutorydeclarationbythesubcontractorthatthesubcontractorisnotinbreachofthesubcontractandthatallsecondarysubcontractors[iesubcontractorsandsupplierstothesubcontractor]havebeenpaidallamountsdueandpayableandtherearenodisputesinrelationtothosepersons.

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 7: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

7

Therequirementsforaprogressclaimareaprimarystipulation.Thedetrimentimposeduponthesubcontractorintheeventoffailureofthisprimarystipulationisthelossofarighttoaprogresspayment.Thatdetrimentbearsnorelationshiptothelosssufferedbytheheadcontractorbyreasonoftheprogressclaimnotcontainingallthestipulatedcontents.Consequently,thesecondstipulation[thebarringofthesubcontractor’sclaim]isapenaltyandunenforceable.WhileIamonthatsubcontract,Iwillpointoutsomeotherpenaltyprovisions.Theusualdefinitionof‘practicalcompletion’hasbeenexpandedsothatpracticalcompletionisnolongerthestagewhentheworksarepracticallycompleteandavailableforoccupation.‘Practicalcompletion’underthesubcontractisnotachieveduntilallpartsofthesubcontractworksincludingrectificationofanydefectsarecomplete.Theprimarystipulationisthatthesubcontractormustachieve‘practicalcompletion’byaspecifieddate.Thesecondarystipulationisthatifthesubcontractordoesnotachieve‘practicalcompletion’bythatdate,thesubcontractormustpayliquidateddamagesof$40,000perday.Thedetrimentwhichtheheadcontractorincursasaconsequenceofallpartsoftheworkincludingrectificationofanydefectsnotbeingcompletemaybenominal.Theliquidateddamagesarethereforeapenalty.Apartywhowantstoretaintherighttoliquidateddamagesforfailuretoachievepracticalcompletionbythedateforpracticalcompletionmustbecarefultoensurethat‘practicalcompletion’isnotdefinedtoincludemattersthatwillnotcauselosscommensuratewiththeamountofliquidateddamages.Thatsamesubcontractprovidesthatthesubcontractorisonlyentitledtoclaimanextensionoftimefordelayscausedbytheheadcontractor.Itprovidesthatifthesubcontractorwishestoclaimanextensionoftimeforpracticalcompletionthesubcontractormustwithinthreebusinessdaysgiveawrittennoticespecifyingvariousmatters.Thatisaprimarystipulation.Thecollateralstipulationisthatifthesubcontractordoesnotgivethatnoticewithintime,thesubcontractorisnotentitledtoanextensionoftime.Iftheconsequenceisthatthesubcontractorisbarredfromanentitlementtodelaycostsandliableforliquidateddamagesforaperiodofdelaycausedbytheheadcontractor,thesecondarystipulationwillresultinapenalty.Thesubcontractprovidesthatthesubcontractormustcomplywithalldirectionsoftheheadcontractorunderthesubcontract.Ifthesubcontractorbelievesthatcompliancewiththedirectionwillinvolveadditionalpayment,thesubcontractormustgivetheheadcontractoranoticeinwritingwithin3businessdays.Thatistheprimarystipulation.Thecollateralstipulationisthatifthesubcontractordoesnotgivethenoticewithinthattime,thesubcontractormustcomplywiththedirectionandwillnotbeentitledtoanypaymentfordoingso.Thiswouldapplynomatterhowlargeavariationdirectedbytheheadcontractormightbe.

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 8: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

8

Ifthecollateralstipulation[thebaronanentitlementtobepaidforextrawork]imposesuponthesubcontractoradetrimentthatbearsnorelationshiptothelosssufferedbytheheadcontractorbyreasonofthefailureofthesubcontractortogivenoticewithintime,thecollateralstipulationisapenalty.Forthefailureofthesubcontractortogivenoticewithintime,theheadcontractorwouldonlybeentitledtocompensationthatisequivalenttothelossthatthesubcontractor’sdelayingivingnoticecausedtotheheadcontractor.Thesubcontractcontainsaclausetitled‘NotificationofClaims’whichstatesthatifanyprovisionofthesubcontractspecifiesatimelimitbywhichaclaimmustbemadeandthesubcontractorfailstobringtheclaimwithinthetimelimitspecified,thesubcontractorwillhavenoentitlementtobringtheclaim.Italsoprovidesthatifthereisnotimelimitspecifiedforaclaim,thesubcontractormustmaketheclaimwithin5businessdays.Otherwisethesubcontractorwillhavenoclaimforanymoney,extensionoftime,cost,expenseordamagewhatsoeverwhetherpursuanttothecontract,intort,understatuteorinrestitution.Thatisclearlyapenaltyclause.Theclauseprovidesthattheheadcontractorwillhave40daystoassesstheclaim.Ifthesubcontractordisputestheassessmentthesubcontractormustgiveanoticeofdisputewithin5businessdays.Ifthesubcontractorfailstodoso,theheadcontractorwillnotbeliableontheclaimandthesubcontractorwillbebarredfrompursuingtheclaim.Thatisanotherpenaltyclause.Anotherpenalprovisioninthissubcontractthatisalsofoundinmanyotherconstructioncontractsistherequirementthatbeforereleaseofthefinalpayment,retentionorsecurity[usuallyabankguarantee]thesubcontractormustgivetheheadcontractoradeedofrelease.Therequireddeedmustreleasetheheadcontractorandallassociatedcompaniesfromallpast,presentoffutureclaimsarisingoutoforinconnectionwiththesubcontractworks.Theprimarystipulationisthatthesubcontractorwillgivetheheadcontractorthedeed.Thecollateralstipulationimposesuponthesubcontractoradetriment[namely,thewithholdingoffinalpaymentandreleaseofsecurity]thatbearsnorelationshiptothelosssufferedbytheheadcontractorbyreasonofthefailureofthesubcontractortogivethedeed.Thecollateralstipulationisapenalty.Forfailuretoprovidethedeed,theheadcontractormaybeableclaimdamagesif,infact,theheadcontractorincursanydamages.Terminationclausesinconstructioncontractsarefrequentlypenal.ThesubcontractthatIhavebeenreferringtohasaprovisionthatifthesubcontractorcommitsanybreachofthesubcontract,theheadcontractorcansuspendpaymentandrequirethesubcontractortoshowcausewhytheheadcontractorshouldnottakethewholeoranypartoftheworksoutofthehandsofthesubcontractororterminatethesubcontract.Theclauseprovidesthatifbythetimespecifiedintheshowcausenoticethesubcontractorfailed‘inthediscretionoftheheadcontractor’,toshowcause,theheadcontractorcantakeworkoutofthehandsofthesubcontractor,andusethe

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 9: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

9

subcontractor’splant,materialsandsubcontractstocompletethework,orterminatethecontract.Itprovidesthatfollowingtermination,theheadcontractorisnotrequiredtomakeanyfurtherpaymentstothesubcontractor.Iwon’tbothercitingtherestoftheclause.Itsufficestosaythatforaminorbreachbythesubcontractor,thecollateralstipulationmayimposeuponthesubcontractoradetrimentthatbearsnorelationshiptothelosssufferedbytheheadcontractorbyreasonofthebreach.Thecollateralstipulationmaybeapenalty.Theheadcontractorwouldonlybeentitledtosuchdamagesasflowfromthebreachbythesubcontractor.Lossofbargaindamageswouldonlyberecoverablebytheheadcontractorwherethebreachbythesubcontractorissoseriousthatterminationbytheheadcontractorwasjustified.InAndrewsat[13]theHighCourtsaysthatthereisnodistinctioninprinciplebetweenastipulationupondefaultforthetransferoruseofpropertyandthepaymentofmoney.TheCourtreferredtoForestryCommissionofNewSouthWalesvStefanetto[1976]HCA3.InthatcasetheHighCourtconsideredaclausethatallowedtheprincipaltotakeoverandusethecontractor’splanttocompletetheworksupondefaultbythecontractor.Clause43.3providedthatnocompensationwouldbepayabletothecontractorfortheuseoftheplantbytheprincipal.TheCourtfoundthattheadditionalcosttotheprincipalofcompletionoftheworkwouldbereducedbytheuseoftheplant.Therewasnoevidencethattheprincipal’suseoftheplantwouldimposeanimpermissibleburdenorpenaltyonthecontractor.JacobsJat[6]said:

Theadditionalcostoftheworkstotheappellantpayablebytherespondentundercl.43.3wouldhavebeenreducedbythefactthattheappellanthadusedtheplantandmaterialsinsteadofincurringthecostofobtainingotherplantandmaterials.Inthepossiblebuthardlyprobableeventthattheworksshouldbecompletedforasumlessthantheoriginalcontractprice,thequestionwouldarise,andonlythenwouldarise,whetherequitywouldtreattheprovisionincl.43.3,thatnocompensationorallowanceshouldbemade,asimpermissiblypenalandwouldinterferebydeclaringthatprovisionvoidandwouldrequireuponafinalaccountthatcompensationorallowancefortheuseoftheplantandmaterialsbemadebytheappellanttotherespondent.Itmaybethatequitywouldnotallowtheappellanttomakeaprofitfromtherespondent’sbreachofcontract.Acourtofequitycanmoulditsreliefsothatthesubstantialpurposeofitsdoctrineofreliefagainstforfeitureandpenaltiesisachieved.Itcanleavethecontractualrighttousetheplantandmaterialsunaffectedandcanavoidthatpartandthatpartonlyoftheagreementbetweenthepartieswhichis,ormaybe,opentochallengeundertheequitabledoctrine.

Thisisanexampleofaclausethatwasanotapenaltyclausebut,nevertheless,shoulditeventuatethattheeffectoftheclausewouldbetoallowtheprincipaltomakeaprofitfromthecontractor’sbreach,thatwouldbeapenaltyandtheCourtcouldmakeordersthatwouldrelievethecontractorfromliability.Thatwouldsimplybeapplicationofthemaxim‘Forbreachofcontract,apersonisentitledtodamagesbutnottomakeaprofitfromthebreach’.InthesubcontractthatIhavebeenciting,thereisaclausetotheeffectthattheheadcontractormaynotifythesubcontractorofadefectinthesubcontract

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 10: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

10

worksandstatethattheheadcontractorintendstoacceptthedefect.Theclauseprovidesthattheheadcontractormaythen,initsdiscretion,deductorrecoverfromthesubcontractorthecosttorectifytheworksorthediminutioninvalueofthesubcontractwork‘havingnoregardtoanyresultingincreaseinvaluetotheheadcontractor’.Theheadcontractorisentitledtodamagesforthesubcontractor’sbreach[thedefectivework]butisnotentitledtomakeaprofit.Ifthereisanyincreaseinvalue,theheadcontractormust,despitethisclause,creditagainstdamagesanyincreaseinvalue.InHoenigvIssacs[1952]2AllER176thecontractor,aninteriordecorator,contractedtodecoratethedefendant’sflatfor£750.Thecontractorsubstantiallycompletedtheworkbutleftdefectsthatwouldcost£55tomakegood.Thedefendantrefusedtopaytheunpaidbalanceofthecontractprice,namely£350.TheCourtheldthatthedefendantwasboundtopay£350less£55forthecostofrectification.Whenaclaimanthascompletedalltheworkthataclaimantispreparedtocarryout,iftheworksaresubstantiallycomplete,therespondentisonlyentitledtowithholdpayment[orreleaseofretentionorsecurity]ofanamountequivalenttothedamagesactuallyincurredbytherespondentbyreasonoftheworknotbeingcomplete.However,itisnotuncommonforrespondentstowithholdmoreandtherebyseektomakeaprofitoutoftheclaimant’sbreach.Thatprofitwouldbeapenalty.UndertheparticularsubcontractIhavebeendiscussing,thedefectsliabilityperiodis52weeksandthereafteruntiltheheadcontractorissatisfiedthatalldefectshavebeenrectified.Thesubcontractprovidesthatfinalcompletionwillnotbeachieveduntilthewholeofthesubcontractworksisapprovedbytheheadcontractor.Releaseofretentionandthebankguaranteeissaidtobedependentuponrectificationbythesubcontractorofalldefects.Retentionis10%ofeachprogresspayment.Thiscouldbeaconsiderablesum.Theprimarystipulationisthatthesubcontractormustrectifyalldefects.Uponfailure,thecollateralstipulation[therightoftheheadcontractortowithholdthefinalpaymentandreleaseofsecurityandretentionmoneys]mayimposeuponthesubcontractoranadditionaldetrimentthatisoutofallproportiontothelosssufferedbytheheadcontractoronaccountofthedefects.Theadditionaldetrimentimposeduponthesubcontractorcanonlybeenforcedtotheextentthatthatisnecessarytocompensatetheheadcontractorforthedefect.Iftheadditionaldetrimentexceedsthatcompensation,itisapenaltyandunenforceable.Inanadjudicationwheretheclaimantclaimsthattherespondentisendeavouringtopenalisetheclaimant,therespondentmayraiseanargumentthatonlyacourtwithjurisdictioninequitycangrantreliefagainstapenalty.Itistruethatanadjudicatorcannotgrantequitablerelief.However,itdoesnotfollowthatanadjudicatormustallowtherespondenttopenalisetheclaimant.Ifit

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 11: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

11

appearsthattherespondentispenalisingtheclaimant,theonusisontherespondenttosatisfytheadjudicatorthatthisisaninstancewhereacourtinequitywouldnotgrantrelieftotheclaimant.Iftheadjudicatorissatisfiedthatacollateralstipulationrelieduponbytherespondenttowithholdpaymenttotheclaimantwouldimposeupontheclaimantadetriment[tothebenefitoftherespondent]thatwouldexceedtheloss,ifany,thattherespondenthasdemonstrated,theadjudicatorshouldnotallowtherespondenttowithholdmorethanlossflowingfromthefailureoftheprimarystipulation.Theexcesswouldbeapenalty.Usuallytherespondentwhoreliesuponacollateralstipulationsuchasthetimebarsdiscussedabove,makesnoattempttoshowthatthefailureoftheprimarystipulation[eggivingofanoticewithinaprescribedtime]causedtherespondentanyloss.RespondentswillpointtoMusicovDavenport[2003]NSWSC977.InthatcaseMcDougallJquashedmydeterminationonthegroundthatIfailedtohaveregardtotherelevantprovisionsofthecontract.SeeMusicoat[119].Iconcludedthattheliquidateddamagesclausewasapenalty.At[107]McDougallJsaid:

Ifanadjudicatorismindedtocometoaparticulardeterminationonaparticulargroundforwhichneitherpartyhascontendedthen,inmyopinion,therequirementsofnaturaljusticerequiretheadjudicatortogivethepartiesnoticeofthatintentionsothattheymayputsubmissionsonit.

Itisthereforemostimportantthatifaclaimantconsidersthattherespondentisinvokingaprovisionofthecontracttopenalisetheclaimant,theclaimantshouldsaysointheadjudicationapplicationandsayhowtheclaimantisbeingpenalised.TheclaimantshouldrefertoAndrews.IhavegivenconsiderationtowhatfindinganadjudicatormightmakeifarespondentreliesuponatimebarasagroundforwithholdingpaymentandcitesJohnGossandtheclaimantassertsthatthetimebarisapenaltyandcitesAndrews.Inanyparticularadjudicationtheadjudicator’sfindingswouldbebaseduponthesubmissionsoftheparties.Consequently,thefollowingmerelyahypotheticalreasoningbyahypotheticaladjudicatoruponhypotheticalsubmissions:

Theclaimantclaimsanentitlementto$...for…Therespondentsaysthattheclaimisbarredbecausetheclaimantfailedtogivewrittennoticeoftheclaimwithinthetimeprescribedbyclause…ofthecontract.TherespondentcitesJohnGossProjectsvLeightonContractors[2006]NSWSC798at[80]‐[81]asauthorityfortheeffectivenessofatimebar.TheclaimantreliesuponAndrewsvAustraliaandNewZealandBankingGroup[2012]HCA30.Thetimebarisacollateralstipulationthatcomesintoeffectiftheclaimantfailstogivetheprescribednoticewithintime.InAndrewsat[10]theHighCourtsetoutingeneraltermsthatastipulationprimafacieimposesapenaltyontheclaimantifitiscollateraltoaprimarystipulationandthecollateralstipulation,uponthefailure

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press

Page 12: Andrews v ANZ and penalty clauses - Federation Press v ANZ and penalty clauses.pdf · Andrews v ANZ and penalty clauses ... Andrews v Australia and New Zealand Banking Group [2012]

AndrewsvANZandpenaltyclauses 

12

oftheprimarystipulation,imposesontheclaimantanadditionaldetriment[thepenalty]tothebenefitoftherespondent.TheCourtheldthatifcompensationcanbemadetotherespondentfortheprejudicesufferedbyfailureoftheprimarystipulation,thecollateralstipulationandthepenaltyareenforcedonlytotheextentofthatcompensation.Thisisaninstancewherethecollateralstipulation[thebartomakingaclaim]imposesupontheclaimantasubstantialdetrimentthatbearsnorelationshiptothelossthatthefailuretogivethenoticewithintheprescribedtimecouldcausetherespondent.Infact,therespondenthasnotdemonstratedwhatlossifany,therespondenthasincurredasaconsequenceofthedelaybytheclaimantingivingnoticeoftheclaim.InJohnGoss,itwasnotarguedthatthetimebarimposedapenalty.JohnGossisirrelevant.Andrewsismostrelevant.Iamsatisfiedthatbutforthecollateralstipulation[thetimebar],theclaimantwouldbeentitledtotheamountclaimed.Thecollateralstipulationwouldcauseseriousdetrimenttotheclaimant.Therespondentreliesuponthetimebar.Theonusisontherespondenttosatisfymethatthecollateralstipulationisenforceable.Therespondenthasfailedtodoso.Itappearstomethattofindtheclaimbarredbythetimebarwouldbetopenalisetheclaimant.Iamnotpreparedtodothat.Iamsatisfiedthattherespondentisnotentitledtorelyuponthetimebartodefeattheclaim.

AsfarasIamaware,thisisthefirstpapertoraisethepossibleimplicationsofAndrewsforconstructioncontracts.Ilookforwardtoalivelydebate.

Adjudicaton in the Construction Industry 3rd edition by Philip Davenport

All Rights Reserved The Federation Press