Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
REQUEST FOR TENDER
General Contracting Services for
Performance Centre Renovations and Addition
Alumni Stadium – Building 178 Project No. 504042
ADDENDUM 3
January 31, 2020
Addendum 3 Request for Tender Performance Centre Renovations and Addition University of Guelph Project No. 504042
2
Part 1 - GENERAL
A3.1 The following is provided to bidders as additional information and/or clarification and/or in response to questions.
A3.2 This Addendum shall form an integral part of the Contract Documents and amends the original Specifications and Drawings and shall be read in conjunction with the Request for Tender dated January 16, 2020. This Addendum shall take precedence over all requirements to the aforementioned Tender with which it may prove to be at variance.
A3.3 Receipt of this Addendum shall be acknowledged on the Bid Form as a part of your submission. Failure to do so may subject the Proponent to disqualification.
A3.4 Ensure that all affected parties are aware of the items noted and include any and all cost impacts in the Tender submission.
A3.5 This Addendum contains:
.1 Part 1 – GENERAL
.2 Part 2 – CLARIFICAITONS Extension to Tender Close
Specifications
Questions/Answers
Part 2 – CLARIFICATIONS EXTENSION TO TENDER CLOSE
A3.6 The tender closing date is extended to February 20, 2020 at 3:00:00 PM local time. Refer to revisions to specifications below.
SPECIFICATIONS
A3.7 SECTION 00 21 07 – INSTRUCTIONS TO BIDDERS
.1 REVISE: Article 11.2 to read as follows: “Bids must be received before and not later than 3:00:00 PM local time on February 20, 2020. The term “local time” shall mean the time as measured by MERX EBS system.”
A3.8 SECTION 00 41 07 – BID FORM .1 DELETE: Section 00 41 07 in its entirety. .2 ADD: Section 00 41 07 as attached and dated January 30, 2020.
A3.9 SECTION 08 80 50 – GLAZING .1 REVISE: Article 2.1.7.4.1 to read as follows: “Dot pattern: 3% to 30% grey digitally
printed/W Prelco’s jet printer STD gray frit #3.” .2 REVISE: Article 2.1.8.6.2.1 to read as follows: “Spandrel glass: Dot patterns 30% gray
digitally printed/W Prelco’s jet printer STD gray frit #3” .3 DELETE: Article 2.1.8.6.2.2 in its entirety.
Addendum 3 Request for Tender Performance Centre Renovations and Addition University of Guelph Project No. 504042
3
A3.10 SECTION 01 21 01 – ALLOWANCES .1 REVISE: Article 1.2.9.4.1 to read as follows: “Allowance: $10,000.00”
QUESTIONS / ANSWERS
A3.11 Q1: Triple glazed units are noted in sect. 2/A61 and details on A2. I’m assuming they are double glazed?
A1: As per Specification Section 08 80 50, Part 2.1.6 - double glazed units
A3.12 Q2: Will elevated work platforms (ie. Skyjack) be permitted on 2nd floor to reach mechanical work? A2: Any elevated work platform must comply with design loads on the structure. This is the
Contractor’s responsibility either through providing shoring for the ground floor or ensuring that any equipment used does not overload the slab.
A3.13 Q3: Will the main use of synthetic turf be for practice, for example with a high level soccer team,
requiring the synthetic turf to play like a natural field? Or, is the synthetic turf surface being used for traditional training methods, for example, speed + agility training, pushing sleds, and/or plyometric work?
A3: The turf will be used by the university football team for indoor tactical and physical training, including pushing sleds.
A3.14 Q4: What are the dimensions and adjusted heights of the two “partial remove concrete foundation
wall” on drawing S10, detail 1? A4: The intention at these locations is to build an F6 (3’-4” x 3’-4” x 10”) footing and a P1 pier (1’-
2” x 1’–2”) to match the existing bearing surface foundation (depth = 7’-0”). The contractor should use their own judgment to determine the required clearance for the excavation and demolition.
A minimum 15-degree angle in the vertical direction for making the partial excavation (it may define an excavation plan of 7’-0” x 7-0”) and a minimum of 4’-0” length of foundation wall to be demolished.
As per the structural drawings, shoring shall be installed to protect all structure to remain, new excavation, etc.
A3.15 Q5: Please provide bearing capacity of soil for shoring/underpinning.
A5: The bearing soil capacity is to be taken as 194 Kpa (4000 psf) as per “Foundation and Backfill” note #10 on drawing S00.
A3.16 Q6: Please provide anticipated building loads to determine shoring/underpinning requirements.
A6: Please, refer to “Drawing Notes” on drawing S01 for the considered design loads at roof and second levels.
A3.17 Q7: Please provide soils report, including material test to determine disposal requirements.
A7: A previous Geotechnical Investigation report for the “Proposed Alumni Stadium Improvements” by Peto MacCallum Ltd. consulting Engineers dated on January 21, 2009 is attached.
Addendum 3 Request for Tender Performance Centre Renovations and Addition University of Guelph Project No. 504042
4
A3.18 Q8: According to LEX DSS report, When drilling is performed in any cinder block wall it will be
required Type II with HEPA attachment abatement procedure due to the presence of contaminated vermiculite. Because we don't know how many drilling operations will be required, is it possible to include a cash allowance for this part of work or establish a unit price per hole so the abatement contractors can have the same scope to price?
A8: This type of work is to be included under the abatement allowance. See above specification modifications.
END OF ADDENDUM NO. 3