Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
: 2 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
01. (a)
Sol:
Axial load on column P = 1800 kN
Permissible bearing stress on concrete
cc = 5 N/mm2
Permissible bending stress in slab base bs
= 189 N/mm2.
Area of slab base required A =cc
P
=5
101800 3
= 360000 mm2
Depth of steel column D = 250 + 25 + 25
= 300 mm
Width of steel column bf = 300 mm
Let L, B and ts be the length, width and
thickness of slab base respectively
To have optimum (minimum) thickness of
slab base, the bigger and lesser projections of
the slab base should be equal
The column shape with cover plates is square.
Hence the square shape slab base can be
provided to have equal projections
Side of square slab base L= B = A
L= B = 360000 = 600mm
Upward pressure from concrete pedestal
below the slab base
w =1A
P=
600600
101800 3
= 5 N/mm2 ≤ cc = 5 N/mm2
Hence concrete pedestal is safe
Projections of slab base beyond the steel
column a = b
mm1502
300600
2
DLba
Thickness of base plate
ts=
4
ba
w3 22
bs
=
4
150150
189
53 22
= 36.59 mm 38 mm
Therefore a slab base 600 × 600 × 38 may
be used at the finished end of the column.
4545
P = 1800 N
L
B
b
a300 mmab
300 mm
b
: 3 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
: 4 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(b) (i)
Ans:
1. The main difference is that the position
of the bucket is the reverse to that of
the power shovel;
2. It is designed to dig below the level of
the machine
3. It digs by pulling the load toward the
power unit
4. It is used for digging narrow pits
formation
5. Its prime mover capacity is less
compared to power shovel.
(ii)
Sol:
Net cutting blade volume capacity
=25.1
25= 20m3
Probable round-trip time:
Pushing 30m @ 2.4 km/hr =4.2
601000
30
= 0.75 min
Returning 30m@ 4.8 km/hr
=8.4
601000
30
= 0.375 min
Fixed time for gear shift = 0.88 min
Total time = 0.75 + 0.375 + 0.88
= 2.005 min
Trip per hour =005.2
50= 25 trips per hour
(rounded figure)
Bull Dozer output per hour = 25 20
= 500 m3/hr
(c)
Sol:
Factored axial compressive load
P = 1350 kN
For Fe410 grade steel, fu = 410MPa &
fy = 250MPa
For grade 6.8 bolt, fub = 600MPa
For ISHB 350 @ 576.8 N/m; D = 350mm &
bf = 250mm
When column ends are machined for
complete bearing, it is assumed that 50%
of factored axial compressive load is
transferred through bearing action and splice
should be designed for 50% factored axial
compressive load
Factored axial load on splice
P1= kN6252
1350
Factored axial load on each side of splice
P2 = kN5.3122
625
Area of splice plate
A = moy
2
/f
P
= 2
3
mm01.13751.1/250
105.312
: 5 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
Thickness of splice plate ts =250
01.1375
= 5.5mm
Assume width of splice plate B = 250mm
Adapt size of splice plate 250mm 6mm
Assume shank diameter of bolt
d = 6.01 t = 6.01 6 = 14.72 mm
≃ 16mm
Number of bolts required on each side of
splice
db
2
V
P
boltoneofStrengthDesign
spliceofsideeachonloadaxialFactoredn
Design strength of one bolt
Vdb = Minimum of Vdsb or Vdpb
Design shear strength of one bolt in single
shear (Assuming thread of the bolt is
intercepting the shear plane)
Vdsb= )AnAn(3
fsbsnbn
mb
ub
=25.13
600
(1×10.78
π4
(16)2 + 0)
= 43.46 103 N = 43.46 kN
Minimum pitch p = 2.5 d = 2.5 16
= 40mm ≃ 50mm
Minimum end distance, emin = 1.5do
= 1.5 18 = 27mm ≃ 30mm
Design bearing strength of one Bolt
Vdpb = 2.5×Kb× d× t×mb
ubf
Where Kb is bearing factor is lesser of
74.0183
40
d3
e
o
67.025.0183
5025.0
d3
p
o
46.1410
600
f
f
u
ub
1.0
Hence bearing factor Kb = 0.67
Vdpb = 2.5 0.67× 16 6 410 /1.25
= 52.74 103 N = 52.74 kN
Design strength of one bolt, Vdb = 43.46 kN
No of bolt required
n =46.43
5.312
V
P
db
2 =7.19 ≃ 8 No’s
Provide 8 No’s of M16 bolts for connection
of each side of splice plate.
Length of splice plate L =2×[(350)+ (240)]
= 460mm
Provide two numbers of splice plates of size
460 2506 mm on each side of splice
: 6 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(d)
Ans:
Seasoning of Timber: When a tree is newly
felled, it contains about 50 percent or more of
its own dry weight as water. This water is in
the form of sap and moisture. The water is to
be removed before the timber can be used for
any engineering purpose. In other words, the
timber is to be dried. This process of drying
of timber is known as the seasoning of timber
and the moisture should be extracted during
seasoning under controlled conditions as
nearly as possible at a uniform rate from all
parts of the timber.
Preservation of Timber: The art of treating
the timber with same chemical so as to
increase its life is called preservation of
timber.
Proper seasoning is the most effective means
of preservation, the objective of preservative
treatment of timber with chemicals is to
prolong it’s life and to increase its durability.
Methods for preservation of timber:
Following are the six methods adopted for
preservation of timber:
(i) Brushing (ii) Charring
(iii) Dipping and steeping
(iv) Hot and cold open tank treatment
(v) Injecting under pressure
(vi) Spraying.
Charring: This method of charring is rather
very old and as such, no preservative is used
in this method. The surface to be charred is
kept wet for about half an hour and it is then
burnt upto a depth of about 15 mm over a
wood fire. The charred portion is then cooled
with water. Due to burning, a layer of coal is
formed on the surface. This layer is not
affected by moisture and it is not attacked by
white ants, fungi, etc.
The disadvantages of this method are:
(a) The charred surface becomes black in
appearance and hence it cannot be used
for exterior work.
(b) There is some loss of strength of timber
as the cross-section is reduced due to
charring.
The process of charring is generally adopted
for lower ends of posts for fencing,
telephone, etc. Which are to be embedded in
the ground or to be inserted in moist soil.
(e)
Ans:
Composition of Good Brick Earth:
Following are the constituents of good brick
earth:
(1) Alumina: It is the chief constituent of every
kind of clay. A good brick earth should
contain about 20% to 30% of alumina. This
constituent imparts plasticity to the earth so
: 7 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
that it can be moulded. If alumina is present
in excess, with inadequate quantity of sand,
the raw bricks shrink and warp during drying
and burning and become too hard when
burnt.
(2) Silica: It exists in clay either as free or
combined. As free sand, it is mechanically
mixed with clay and in combined form, it
exists in chemical composition with alumina.
A good brick earth should contain about 50
percent to 60 percent of silica. The presence
of this constituent prevents cracking,
shrinking and warping of raw bricks. It thus
imparts uniform shape to the bricks. The
durability of bricks depends on the proper
proportion of silica in brick earth. The excess
of silica destroys the cohesion between
particles and the bricks become brittle.
(3) Lime: A small quantity of lime not
exceeding 5 percent is desirable in good
brick earth. It should be present in a very
finely powdered state because even small
particles of the size of a pin-head cause
flaking of the bricks. The lime prevents
shrinkage of raw bricks. The sand alone is
infusible.
(4) Oxide of iron: A small quantity of oxide of
iron to the extent of about 5 to 6 percent is
desirable in good brick earth. It helps as lime
to fuse sand. It also imparts red colour to the
brick. The excess of oxide of iron makes the
bricks dark blue or blackish. If, on the other
hand, the quantity of iron oxide is
comparatively less, the bricks will be
yellowish in colour.
(5) Magnesia: A small quantity of magnesia in
brick earth imparts yellow tint to the bricks
and decreases shrinkage. But excess of
magnesia leads to the decay of bricks.
: 8 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
0
01
A
6
626
B30
336
76
F80
116
156
5 H14
1708170
I12
158
158
138
1386 20
G
12E
4126
126
120D
C10
J
24
194
1949
7
02. (a)
Sol:
EventsACT
MM
Duration
(d)EST LST EFT LFT TF
1 – 2 A 6 0 0 6 6 0
2 – 3 B 30 6 46 36 76 40
2 – 6 C 10 6 128 16 138 122
2 – 4 D 120 6 6 126 126 0
4 – 6 E 12 126 126 138 138 0
3 – 5 F 80 36 120 116 156 40
6 – 7 G 20 138 138 158 158 0
5 – 8 H 14 116 156 130 170 40
7 – 8 I 12 158 158 170 170 0
8 – 9 J 24 170 170 194 194 0
EFT Earliest Finish Time
EST Earliest Start Time
LFT Latest Finish Time
LST Latest Start Time
LST = LFT – Duration LFT – d
EFT = EST + Duration EST+ d
Total float = TF = LST – EST = LFT – EFT
For which ever activity total float is zero that activity is on critical path
1 – 2 – 4 – 6 7 – 8 – 9
A – D – E – G – I – J is the critical path
: 9 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
: 10 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(b)
Sol:
Allowable bearing stress, p = 187.5 N/ mm2
End reaction = 900 kN
Bearing area required end-bearing stiffener
Ae =5.187
10900 3= 4800 mm2
Try 4 ISA 130×130×10 of two on either side
of web as shown in figure.
A = 2512 mm2;
Ixx= Iyy = 405.3×104 mm4;
Cxx = Cyy=35.9mm
Bearing area provided by outstanding legs
= 4 × (130–10)×10 = 4800 mm2
Effective area of the stiffener
A = 6130225124 = 11608 mm2
Moment of inertia of bearing stiffener about
centre of web
12
3626029.3512321124103.4054
minI
= 42.25106 mm4
Minimum radius of gyration, rmin
11608
1025.42
A
I 6min = 60.33 mm
Effective length of bearing stiffener
= 0.7(2000212) = 1383.2 mm
Slenderness ratio of bearing stiffener
92.2233.60
2.1383
rmin
Permissible compressive stress
ac= 2092.22
2030
139145145
=143.25 N/mm2
Area required =25.143
10900 3
= 6282 mm2 ≯ 11608 mm2
Which is safe.
Assume nominal diameter of rivet = 20 mm
Gross (or) effective diameter of rivet,
d = 20 + 1.5 = 21.5mm
vf = 100 MPa; pf = 300 MPa
Shear strength of one rivet in double shear
1005.214
2d4
2P 2vf
2s
= 72.61 103 N = 72.61 kN
Strength of one rivet in bearing
Pb = d t pf = 21.5 6 300
= 38.7 × 103 N = 38.7 kN
Rivet value Rv = Smaller of Ps and Pb
= 38.7 kN
No of rivets required
2425.237.38
900
valueRivet
reactionEndn
Provide 12 No's- 20mm diameter of PDS
rivets @120 mm C/C on each pair of end
stiffener.
130 mm
Web plate
Filler Plate 12 mm
Bearing Stiffener
20 × 6 = 120 mm 20 × 6 = 120 mm
: 11 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(c)
Ans:
Soundness: The purpose of this test is to
detect the presence of uncombined lime in
cement. This test is performed with the help
of Le Chatelier apparatus as shown in fig. It
consists of a brass mould of diameter 30mm
and height 30mm. There is a split in mould
and it does not exceed 0.50mm. On either
side of split, there are two indicators with
pointed ends. The thickness of mould
cylinder is 0.50mm.
Following procedure is adopted.
(i) The cement paste is prepared. The
percentage of water is taken as
determined in the consistency test.
(ii) The mould is placed on a glass plate and
it is filled by cement paste.
(iii) It is covered at top by another glass
plate. A small weight is placed at top
and the whole assembly is submerged in
water for 24 hours the temperature of
water should be between 24oC to 34oC.
(iv) The distance between the points of
indicator is noted. The mould is again
placed in water and heat is applied in
such a way that boiling point of water is
reached in about 30 minutes. The
boiling of water is continued for one
hour.
(v) The mould is removed from water and it
is allowed to cool down.
(vi) The distance between the points of
indicator is again measured .The
difference between the two readings
indicates the expansion of cement and it
should not exceed 10 mm.
03. (a)
Sol:
DaysActivity
t0 tm tp te
variance
2
1 – 2 2 4 6 4 2/3 4/9
1 – 3 2 3 4 3 1/3 1/9
2 – 3 6 8 10 8 2/3 4/9
2 – 4 4 10 16 10 2 4
3 – 5 7 10 19 11 2 4
4 – 5 3 6 9 6 1 1
30 mm
165 mm
Split 0.5 mm max0.5mmA
A
Top view without glasssheets
30mm
Glass sheet
Glass sheet
Le chatelier apparatus
: 12 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
1
0
0
3
4
4
42
312
12
11 23
235
6
174
10
10
8
estimateTime6
tt4tt pm0
e
deviationdStandar6
tt 0p
ancevari6
tt2
0p2
Critical path 1–2–3–5
Duration TE = 23 days
(variance)cp = (var)1-2 + (var)2-3 + (var)3-5
= 494
94
=944
93644
Standard deviation of critical path
= pcpc var
= 9/44 = 2.211 days
Desired completion date = D = 28 days
Critical path time estimate = TE = 23 days
26.2211.2
2328TDZ
pc
e
61.982.2
93.983.2obPr26.2
dz = 0.1 dp = 0.32
dz1=0.04 dp1 = ?
dpdzdz
P93.981
1
= 128.032.01.0
04.0
P1 = Probability of completion
= 98.93 – 0.128 = 98.8
21.981.2
61.982.25.981Z
dz = 0.1; dp = 0.4
dz1 = ? dp1 = 0.11
dz1 = dzdpdp1
0275.01.04.011.0
z2.2 1
1725.20275.02.2z1
pc
e1
TDz
211.223D
1725.2
D = 23 + 2.211 ×2.1725
= 23 + 4.8 = 27.8 days
(b)
Sol:
Effective span of beam l = 6 m
Uniformly distributed load w = 21.5 kN/m
Permissible bending tensile and bending
compressive stress bt = bc = 165 MPa
Permissible average shear stress
τvf=100 MPa
: 13 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
Maximum bending moment,
M=8
65.21
8
w 22
l= 96.75 kN-m
Maximum shear moment
V =2
65.21
2
w
l= 64.5 kN
Section modulus required Zr =btbc or
M
=165
1075.96 6
= 586.36103 mm3
Choosing ISLB 325 @422.8 N/m
Zxx = 607.7103 mm3
Ixx = 9874.6 104 mm4
tw = 8.8 mm & tf = 9.7 mm
Check for bending stress
Calculated maximum bending compressive
or bending tensile stress
bc cal = bt cal = yI
M
xx
= )2/325(106.9874
1075.964
6
= 159.21 N/mm2 <165MPa
(beam section is safe against bending
moment)
Check for shear stress
Calculated average shear stress τva cal
=wt.h
V
8.8325
105.64 3
= 22.55 N/mm2 τva =100 N/mm2
Section is safe against shear
Check for deflection
Allowable (or) Maximum deflection for a
simply supported beam
mm46.18325
6000
325max
Calculated maximum deflection =EI384
w5 4l
=45
4
106.9874102384
60005.215
= 18.37 mm < 18.46 mm
Section is safe against deflection
(c)
Ans:
Requirements of a Good Aggregate:
Following are the desirable properties or
requirements of a good aggregate.
(1) Adhesion (2) Cementation
(3) Durability (4) Hardness
(5) Shape (6) Strength
(7) Toughness
(1) Adhesion: The aggregates which are to be
used for the construction should have less
affinity with water as compared with the
binding material. If this quality is absent in
the aggregate, it will lead to the separation of
bituminous or cement coating in the presence
of water.
(2) Cementation: The binding quality of the
aggregate depends on its ability to form its
own binding material under different loading
so as to make the rough broken stone pieces
grip together to resist displacement.
: 14 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(3) Durability: The durability of an aggregate
indicates its resistance to the action of
weather and is largely dependent upon its
petrological composition. The metal is
subjected to the oxidizing influence of air
and rain water. It is therefore desirable that
the aggregate should possess sufficient
soundness to resist the action of weather and
age so that the life of the structure made with
it may be prolonged.
(4) Hardness: The aggregates should be
reasonable hard to offer resistance to the
actions of abrasion and attrition. The
aggregates are always subjected to the
constant rubbing action. It is known as
abrasion and it will be increased due to the
presence of abrasive material like sand
between the exposed top surface and the
tyres of moving vehicles. The abrasive action
is very severe for roads which are used by the
steel tyred vehicles. The mutual rubbing of
stones is known as attrition and it may also
cause a little wear in the aggregates.
(5) Shape: The shape of aggregates may be
rounded, cubical, angular, flaky or elongated.
The flaky and elongated particles possess
less strength and durability and their use in
the construction should be avoided as for as
possible. The rounded particles are preferred
in cement concrete construction. But they are
unsuitable in W.B.M. construction,
bituminous construction and in granular base
course because their stability due to
interlocking in less. The angular particles are
preferred in such types of construction.
(6) Strength: The aggregates should be
sufficiently strong to withstand the stresses
developed due to the wheel loads of the
traffic. This property is especially desirable
for the road aggregates which are to be used
in top layers of the pavement. Thus, the
wearing course of road should be composed
of aggregate which possess enough strength
in addition to enough resistance to crushing.
(7) Toughness: The toughness of an aggregate is
that property which enables the aggregate to
resist fracture when struck with a hammer
and it is necessary in a metal to withstand the
impact blows caused by traffic. The
magnitude of impact is governed by the
roughness of surface, speed of the vehicle
and other vehicular characteristics. It is
desirable that the aggregate is reasonably
tough.
Fineness modulus: Fineness Modulus is a
ready index of coarseness or fineness of the
material. Fineness modulus is an empirical
factor obtained by adding the cumulative
percentages of aggregate retained on each of
the standard sieves ranging from 80 mm to
: 15 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
150 micron and dividing this sum by an
arbitrary number 100. The larger the figure,
the coarser is the material.
Many a time, fine aggregates are designated
as coarse sand, medium sand and fine sand
may be really medium or even coarse sand.
To avoid this ambiguity fineness modulus
could be used as a yard stick to indicate the
fineness of sand.
The following limits may be taken as
guidance:
Fine sand: Fineness Modulus: 2.2 – 2.6
Medium sand: F. M. : 2.6 – 2.9
Coarse sand : F. M. : 2.9 -3.2
A sand having a fineness modulus more than
3.2 will be unsuitable for making satisfactory
concrete.
04. (a) (i)
Ans:
Properties of good Mortar Mix And Mortar:
The important properties of a good mortar
mix are mobility, placeability and water
retention.
1) Mobility: The term mobility is used to
indicate the consistency of mortar mix
which may range from stiff to fluid. The
mobility of mortar mix depends on the
composition of mortar and the mortar
mixes to be used for masonry work,
finishing work, etc. are made sufficiently
mobile.
2) Placeability: The placeability or the
ease with which the mortar mix can be
placed with minimum cost in a thick and
uniform layer over the surface depends
on the mobility of the mortar. The
placeability of mortar mix should be
such that a strong bond is developed
with the surface of the bed.
3) Water retention: A good mortar mix
should posses the ability of retaining
adequate humidity during transportation
and laying over the porous bed. If water
retention power of mortar mix is low, It
separates into layers during
transportation and when it comes into
contact with porous bed such as brick,
wood, etc., it gives away its water to that
surface. Thus the mortar becomes poor
in amount of water and the remaining
water proves to be insufficient for its
hardening. Hence the required strength
of mortar will not be achieved with such
a mortar mix.
Properties of a good mortar:
Following are the properties of a good
mortar:
(i) It should be capable of developing
good adhesion with the building units
such as bricks, stones, etc.
(ii) It should be capable of developing the
designed stresses.
(iii) It should be capable of resisting
penetration of rain water.
: 16 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(iv) It should be cheap.
(v) It should be durable.
(vi) It should be easily workable.
(vii) It should not affect the durability of
materials with which it comes into
contact
(viii) It should set quickly so that speed in
construction may be achieved.
(ix) The joints formed by mortar should
not develop cracks and they should be
able to maintain their appearance for a
sufficiently long period.
Uses of Mortar:
Following are the uses of mortar:
(i) To bind the building units such as
bricks, stones, etc, into a solid mass.
(ii) To carry out pointing and plaster
work on exposed surfaces of
masonry
(iii) To form an even and soft bedding
layer for building units
(iv) To form joints of pipes
(v) To improve the general appearance
of structure,
(vi) To prepare moulds for coping,
corbels, cornice, etc.,
(vii) To serve as a matrix or cavity to
hold coarse aggregates, etc.,
(viii) To distribute uniformly the super
incumbent weight from upper layer
to lower layer of bricks or stones,
(ix) To hide the open joints of brick
work and stonework,
(x) To fill up the cracks detected in the
structure during maintenance
processes, etc.
(ii)
Ans: Schmidt’s rebound hammer developed in
1948 is one of the commonly adopted
equipments for measuring the surface
hardness.
It consists of a spring control hammer that
slides on a plunger within a tubular housing
When the plunger is pressed against the
surface of the concrete, the mass rebound
from the plunger, it retracts against the
force of the spring. The hammer impacts
against the concrete and the spring control
mass rebounds, taking the rider with it
along the guide scale. By pushing a button,
the rider can be held in position to allow the
reading to be taken. The distance traveled
by the mass, is called the rebound number.
It is indicated by the rider moving along a
graduated scale.
Plunger
Spring
LatchBody
indicator
Hammer
(a)
MassRelease Button
Concrete
: 17 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
Limitation: Although, rebound hammer
provides a quick inexpensive means of
checking uniformity of concrete it has
serious limitations and these must be
recognized. The results are affected by:
a) Smoothness of surface under test.
b) Size, shape and rigidity of the specimen
c) Age of specimen
d) Surface and internal moisture condition
of the concrete
e) Type of coarse aggregate
f) Type of cement
(a), (b), (c) & (d) indicates the following
(a) Instrument ready for test
(b) Body pushed toward test object
(c) Hammer is released
(d) Hammer rebounds
(b)
Ans: The following common factors needs to
consider while selecting construction
equipment for a dam construction project.
1. Scope of work:The time frame within
which the construction work is required
to be carried out, and the specification
of works will be of concern.
2. Use of available: For a work where full
utilization of equipment for its entire
working life and consequently unit cost
of work. Economic should be worked
out.
3. Suitability for job conditions: The
equipment selected should suit the
demands of the job conditions. Climate
of region and working conditions
should be kept in view.
4. Uniformity in type: It is desirable to
have minimum number of types so that
there is uniformity in the type of
equipment on a project.
5. Size of equipment: While large size of
machines are capable of giving large
outputs on full load, the cost of
production is usually greater than that
of smaller units if worked out on part
loads. Large size of equipment requires
corresponding large size of matching
equipment.
plunger
Spring
LatchBody
indicator
Hammer
(a)(b)
(c) (d)
: 18 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
6. Use of standard Equipment: Standard
equipment are commonly manufactured
and are commonly available and are
moderately priced. The spare parts of
standard equipment are easily available
and less expensive.
7. Unit cost production: The economics
is one of the most important
considerations in selection of
equipment. While working out owing
cost all items of expenses, such as
freight, packaging and forwarding,
insurance, erection and commissioning
etc., should be included with the price
paid to supplier.
8. Availability of spare parts: Down time
for want of necessary spare parts
commonly accounts for long idle periods
during working life of equipment,
especially of imported equipment.
9. Versatility: The equipment selected
should be if possible, be capable of
performing more than one function and
should have feature of inter
convertibility as far as possible.
10. Selection of manufacturer: It is
desirable to have equipment of the same
manufacturer on a project as far as
possible and to have minimum number
of different makes of equipment.
11. Suitability of local labour: Available
operators and technicians should be able
to handle selected equipment.
12. Technical consideration: The efficient
performance of any piece of equipment
and its service life are conditioned by
factors like Strength. Rigidity, Vibration
stability, Resistance to wear etc.
13. Balance of resources: A balance
between reliability, investment cost and
operating cost should be found since a
policy of selecting the lowest priced
equipment can often lead to higher life
cycle costs etc.
14. Economical Life of Construction
Equipment: The owner of construction
equipment look for obtaining the lowest
possible cost per unit of production, for
which different costs considered are: a.
Depreciation and replacement. b.
Investment. c. Maintenance and repairs
d. Downtime. e. Obsolescence. An
analysis of the effect which hours of
usage will have on each of these costs
will establish the time at which a
equipment should be replaced.
: 19 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
: 20 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
(c)
Sol: Effective span of beam L = 5.0 m
Yield stress of steel fy = 250 Mpa
` Factored U.D.L on beam is inclusive of self-
weight w = 50 kN/m
Let ‘W’ be the factored central concentrated
load in kN
Section classification
Section classification ε =250
250
f
250
y
=1.0
Outstand of flange, b = mm952
190
2
b f
Depth of web,
d = h–2×(tf+R1) = 550–2×(19.3+18)
= 475.4 mm
4.992.43.19
95
t
b
f
6744.422.11
4.475
t
d
w
Hence the section is plastic section
Since V≤ 0.6 Vd this is low shear case
Design bending strength of laterally
restrained beam
Md =mo
y
mo
ypb
fZe2.1
fZ
For plastic section b=1
10.1
2501098.27110.1M 3
d
10.1
250108.23592.1
fZe2.1 3
mo
y
= 616.35×106 N-mm ≤ 643.57×106 N-mm
= 616.35kN-m ≤ 643.57×106 kN-mm
Which is all right
Factored U.D.L on beam is inclusive of self-
weight w = 50 kN/m
Let ‘W’ be the central concentrated load in
kN
Design bending moment due to udl (w) and
Central concentrated load W
4
5W
8
)5(50
4
WL
8
wLM
22
zz
W25.125.156 kN-m
Equating Mzz = Md
156.25+1.25 W = 616.35
W = 68.08 kN ---- (1)
Design shear strength of joist,
mo
yw
mo
yvd
3
fth
3
fAV
10.13
2502.11550
kN31.808
Design shear force due to udl (w) and
Central concentrated load W
2
W
2
wLV = W5.0125W5.0
2
550
Equating V = Vd
125+0.5 W = 808.31
W = 1366.62 kN----(2)
Limiting deflection for a simply supported
beam (assuming brittle cladding)
: 21 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
mm66.16300
5000
300itlim
Calculated maximum deflection under
service loads
Service UDL on beam ws = w/γf
= 50/1.5 = 33.33 kN/m
EI48
WL
EI
Lw
384
5 34s
caitlim
61094.648
510248
35000)5.1/1000W(
61094.648
5102
4)5000(33.33
384
567.16
16.67=2.09+0.0133W
W = 1096 kN----(3)
Factored central concentrated load W
= 368.08 kN
Design shear force due to udl (w) and
Central concentrated load
kN04.30908.3685.0125W5.0125V ≤ 0.6 Vd = 0.6 ×808.31=484.98 kN
Hence this is low shear and assumption is
correct
Factored central concentrated load W
= 368.08 kN
05. (a) (i)
Ans:
1) Masonry in foundation and plinth:
Lime mortar and cement mortar are used in
the construction of foundation and plinth
2) Masonry in superstructure: Cement
mortar and lime mortar are used in super
structure.
(3) Lime Plaster: In lime plaster mostly
fat lime should be used. Hydraulic
lime may contain particles which slake
slowly as and when they come in
contact with atmospheric moisture.
The result into blisters on the plastered
surface, known as blowing. If
hydraulic lime has to be used for
plastering, it should be ground dry
with sand. Thereafter, it is left for two
to three weeks. It is ground again
before use.
Cement Plaster: Cement plaster consists
of an intimate mixture of cement and clean
coarse angular river sand with suitable
amount of water. Proportions of cement
and fine aggregate may vary according to
the requirements of the plaster. But usual
proportions are 1:3 or 1:4. The materials in
the required proportion are stacked on a
watertight platform and thoroughly mixed
in dry condition. Before plastering, water is
added only to that such dry mix which
could be used in less than 30 minutes time.
Alternatively, dry mix is taken in pan and
water in required amount is added to the
pan itself and pan is carried to the mason
for use.
Cement plaster may be done in one coat or
two coats. Usually it is done in one coat
only.
: 22 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
4) Mortar for Pointing:
Pointing may be done in lime mortar or
in cement mortar. Cement mortar
pointing is mostly used as it is more
durable and weather resisting.
Lime Mortar: Lime mortar for pointing
is prepared by mixing lime and sand in
proportion of 1:1. The lime mortar
should be ground in mortar mills.
Cement Mortar: Cement mortar
consists of cement and fine sand in
proportion of 1:2 and 1:3.
Sand to be used for preparing lime or
cement mortar for pointing should be
clean, fine, and free from organic
impurities.
Method of Pointing:
Pointing is done in the following stages:
1. The mortar joints of the surface to be
pointed are raked out to a depth of about
13 mm.
2. Raked joints are cleaned from loose
mortar and thoroughly wetted.
3. Now mortar is taken in small flat
rectangular plates, made of iron. Plate
with mortar is held in one hand by the
mason, abutting the wall and with the
help of a small trowel in other hand
mortar is forced into the open spaces of
raked masonry joints. The mortar is
slightly pressed with trowel to bring it
into close contact with the masonry
mortar of the joint.
4. The pointing should be finished as per
the required finishing with the help of
specific tool. Finishing is done when
mortar is still green.
5. The pointed surface should be cured for
at least 3 days in case of lime mortar
and 10 days in case of cement mortar
pointing.
(ii)
Sol: Volume of concrete = 1 m3
Void ratio of cement, ec = 62%
Void ratio of Fine aggregate, eF.A = 41%
Void ratio of coarse aggregate, %45e A.C
Mix proportion = 1 : 2: 4
Weight of cement = Wc
Weight of Fine aggregate = WF.A
Weight of Course aggregate = WC.A
Weight of water = Ww
Concrete = Voids + water + Cement + Fine
aggregate + Coarse aggregate.
Void ratio =solidsofVolume
VoidsofVolume
Volume of voids = void ratio volume of
Solids
=solidofdensity
solidofmassratiovoid
: 23 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
Concrete =
A.C
A.C
A.F
A.F
c
c
w
w
A.C
A.CA.C
A.F
A.FA.F
c
cc
WWWW
We
We
We
1600
W4
1700
W2
1440
W1000
W55.0
1600
W445.0
1700
W241.0
1440
W62.01
ccc
cccc
1000
W55.0
1600
W8.5
1700
W82.2
1440
W62.11 cccc
WC = 143.7 kg
WF.A = 287.4 kg
WC.A = 574.81 kg
(b)
Sol: Web stiffeners:
IS 800:1984 recommends to provide web
stiffeners as follows:
85andf
1344and
816oflesser
t
d
ycal,vaw
1
No stiffener is required
200and3200
oflessert
d
cal,vaw
2
Vertical stiffeners are provided
250and4000
oflessert
d
cal,vaw
2
Vertical stiffener + first horizontal
stiffener at a distance from compression
flange equal to two-fifth of distance from
compression flange to neutral axis
400and6400
oflessert
d
cal,vaw
2
Vertical stiffener + first horizontal
stiffener at a distance from compression
flange equal to two-fifth of distance from
compression flange to neutral axis + a
horizontal stiffener at neutral axis
d2 = 2 clear distance from compression
flange angle or plate to the neutral
axis.
In no case the greater clear dimension of a
web panel less than 270 tw and the lesser
clear dimension of the web panel less than
180 tw
(1) Transverse (stability or vertical) stiffener:
Intermediate transverse stiffener increases
buckling resistance of web against shear
Angle sections are provided for riveted or
bolted plate girders and flat or plate
section for welded plate girders
Minimum moment of inertia of transverse
stiffener
I ≥ 1.5 d13 t3 / c2
t = Minimum required thickness of web
c = the maximum permitted clear distance
between vertical stiffener for thickness tw
Maximum spacing of vertical stiffeners -
1.5d1.
Minimum spacing of vertical stiffness -
0.33d1.
: 24 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
If vertical stiffeners are subjected ti
external force, the moment of inertia
should be increased as
Bending moment on stiffener due to
eccentricity of vertical loading with
respect to vertical axis of web
4
w
2
cmtE
DM150IofIncrease
Lateral loading on stiffener
4
w
3
cmtE
DV3.0IofIncrease
M – Applied bending moment (kN-m)
D – Overall depth of girder (mm)
E – Young’s modulus (2 105 MPa)
tw – Thickness of web
V–Transverse force taken by stiffener
(kN)
(2) Longitudinal (Horizontal) stiffener:
Longitudinal stiffener increases buckling
resistance of web against bending
These are provided between transverse
stiffener
Minimum moment of inertia of first
longitudinal stiffener provided at 0.2d
from compression flange I ≥ 4c t3
Minimum moment of inertia of second
longitudinal stiffener provided at N.A
I ≥ d2 t3
d2 – 2 distance from compression flange
to N.A
(c) (i)
Sol:
Rolling resistance (neglect crawler weight)
= 45.5 (t) 50 (kg/t) = 2275 kgf
Grade resistance = (36+45.5) 1000 0.04
= 3260 kgf
Total resistance = 2275 + 3260 = 5532kgf
=54.27KN
Power wasted in resistance= Total Resistance
× Velocity of the equipment
= 5532×9.81×30×5/18
=452.24KW =615HP.
(ii)
Sol:
Path Duration
1–2–4 (A– D) 9
1–2–3–4(A–C–E) 18*
1–3–4(B–E) 10
ActivityCost slope =
JT
cc
CN
NC
A (300 – 200) /5–3 = 50
B (500 – 350) /4–3 = 150
C (450 – 300) /7–6 = 150
D (200 – 200) /4–4 = ----
E (400 – 300) /6–5 = 100
1
2
3
4B(4)
A(5)
C(7)
E(6)
D(4)
: 25 : Test – 7
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata
By crashing activity ‘A’ by 2 days, the new
network is as following
Path Duration
1–2–4 (A– D) 7
1–2–3–4(A–C–E) 16*
1–3–4(B–E) 10
By crashing actions ‘E’ by 1 day, the networks is
changed as following
Path Duration
1–2–4 (A– D) 7
1–2–3–4(A–C–E) 15*
1–3–4(B–E) 9
From the network, it is observed that crashing
possible activity is ‘C’; but it cannot be
crashed due to high crash cost slope-(cost
slope of activity ‘C’ is Rs 150)
Optimum project duration = 15 days
Total project cost = normal cost + crashing
cost + Indirect cost/day project duration
= (200 + 350 + 300 + 200 + 300) + crashing
cost of A+ crashing cost of E + Indirect
cost/day project duration.
= 1350 + 250 + 1 100 + 100 15
= 1350 + 100 + 100 + 1500 = 3050/-
1
2
3
4B(4)
A(3)
C(7)
E(5)
D(4)
1
2
3
4B(4)
A(3)
C(7)
E(6)
D(4)
: 26 : Civil Engg. _ ESE MAINS
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar| Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally |Kolkata