MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

ASIAN PACIFIC ENERGY FORUM

Bangkok, December 17-19, 2013

ACCESS TO ENERGY

IN TIMOR-LESTE

Presented by:

Virgilio F. Guterres

General Director of Electricity

Page 2: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Map of Timor-Leste

Page 3: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Country profilePopulation (2012): 1.1 million

Pop. growth rate (%/yr): approx.2.1

Area (km2): 14.874 sqkm

Urbanisation rate (%): 30

GDP (M$ 2012): 4,173

GDP per capita ($ 2012): 3,730

Page 4: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Government energy policy

Reliable and modern sources of energy:

to reduce poverty,

to improve the health of population and

to promote economic growth

Through the following strategic actions:

increase of power generation capacity

construction of a reliable power grid

electrification covering the whole country

use of new and renewable energy sources

Page 5: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Purpose of the National Energy policy

- To reduce the level of dependence on the importation of energy sources through the use of renewable energysources

- To promote the development of the governance of renewable energy and the National System of RenewableEnergy (SNER)

- To promote the development and the use of multi-purpose hydroelectric facilities for energy production and the sustainable use of water

- To regulate the exploitation and use of non renewable energy sources

Page 6: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Purpose of the National Energy Policy

- To provide universal access to energy to all the people, especially those living in remote areas of Timor-Leste

- To create appropriate regulation so that the nationals of Timor-Leste play a major role in the governance of energy sources

- To develop balanced energy security standards to ensure the continuity of exploration , production and supply

- To develop training and education programs for operators and consumers in order to encourage the sustainable use and consumption of energy sources

Page 7: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Access to Electricity

Page 8: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Power generation

Page 9: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Rural electrification

Page 10: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Electricity in Timor-Leste

Facts and Targets: 2008 2013 2015 2018

Generation capacity (MW) 40 286 300

Transmission line (km) 0 603

Generated energy (GWh) 318 385

Electrification rate 22 62 75 100

Supply hours in distr.(h/day)6 24

National Dispatching Center since 2011

Page 11: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Fuel

Engines are designed for LFO and HFO fuels

In 2013, only LFO is burnt

Conversion to dual-fuel to use LNG /LPG is planned

In the next years LFO, LNG and LPG will be produced in Timor-Leste

Page 12: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Electricity medium-term targets

Electricity Master Plan

Human resources empowering

Planning and standardization

From isolated to integrated system (Oecussi)

Rural electrification

Page 13: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Electricity for the development

Electricity to boost the development

Reffinery, supply base, LNG on-shore

Cement factory

Mining

Brewery

Food industry

Small & Medium Industries

Services: ports, hotels

Page 14: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Renewable Power Potential Identified

Solar: 7 MW

Hydro: 351 MW

Wind: 81 MW

Page 15: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Use of renewable energy 2017

Solar from 0.75 to 1.25 MW

Hydro from 0.34 to 23 MW

Wind from 0 to 42.5 MW

Page 16: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Renewable energy actual and targets

Facts and targets: 2012 2017

Solar (MW): 0,75 1,25

Wind (MW) 0 42,6

Hydropower(MW) 0.34 23

Targets as per the Governement Strategic Development Plan

Page 17: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Access to renewable energy

Achievements:

- Photovoltaic 13,000 installations (0.75 MWp)

- Microhydropower approx. 0.34 MW

Targets:

Reduction of fossil fuel through exploitation of:

- Wind: 81 MW

- Solar 7 MW

- Hydro 351 MW

Page 18: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Customers in 2013

Our daily work is focused on satisfaction of our customers

Conected to National power grid: 105,522

- Dili 39,407 (37.3%)

- Districts & sub-districts 66,115 (62.7%)

Solar: 13,000

Micro-hydro 240

Total: 118,762

Page 19: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Targets up to 2017

Target 1:

The customers provided with reliable electricity from the national grid down to the sub-district level and in the targeted villages

Target 2:

21,300 customers provided with reliable electricity from off grid (solar panels)

Page 20: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste

Targets up to 2017 (Contd)

Target 3:

Dependency on imported fossil fuel reduced by supplying 65 MW into the national grid from new and renewable sources

Target 4:

The customers down to the sub-district level are provided either with a prepayment facility or with regular bills for electricity use and have convenient methods for making payment

Page 21: ACCESS TO ENERGY IN TIMOR-LESTE - unescap.org · ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste Targets up to 2017 (Contd) Target 3: Dependency on imported fossil

MINISTÉRIO DAS OBRÁS PÚBLICASSECRETERIA DE ESTADO DA ELECTRICIDADE

ELECTRICIDADE DE TIMOR-LESTE Avenida Caicoli, Dili, Timor-Leste