35
A3.2.4 GEOMETRIC SURVEY REPORT Date: 25/8/2020 Prepared by: Royal Scientific Society - CSBC Status: Final Version: V 1.0 This project is funded by the EU under the ENI CBC Med Programme

A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

A3.2.4 GEOMETRIC SURVEY REPORT

Date: 25/8/2020

Prepared by: Royal Scientific Society - CSBC

Status: Final

Version: V 1.0

This project is funded by the EU under the ENI CBC Med Programme

Page 2: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 2

Index

1. CHANGE RECORDS ........................................................................................................ 3

2. GENERAL INFORMATION .............................................................................................. 3

3. INTRODUCTION ............................................................................................................ 4

3.1. Existing geometrical documentation on the building ................................................... 4

3.2. Type of survey adopted ................................................................................................. 5

4. SITE CONDITIONS ......................................................................................................... 5

5. PRE PLANNING ACTIVITIES ............................................................................................ 7

5.1. Pre planning activities description ................................................................................ 7

5.2. Equipment ..................................................................................................................... 7

5.3. Personnel ....................................................................................................................... 8

6. DATA ACQUISITION ...................................................................................................... 8

6.1. Description of the performed data acquisition activities ............................................. 8

6.2. Site Visits Results ........................................................................................................... 8

7. POST PROCESSING ...................................................................................................... 13

8. RESULTS ..................................................................................................................... 13

8.1. Survey Work results .................................................................................................... 13

9. ANNEXES ................................................................................................................... 14

9.1. Technical documentation of the building (Traditional Survey) ................................... 14

9.2. Photogrammetric documentation .............................................................................. 14

Page 3: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 3

1. CHANGE RECORDS

Version Date Author Changes

Version 01 25 Aug 2020 RSS - CSBC -

2. GENERAL INFORMATION

Name of Building: Guests House\ AL- Karak Municipality

Location: AL-Karak governorate – South Jordan

Floor area: 240 m2

Volume: 2025.12m3

Original use – present or future use: The building was constructed since more than 100 years and used as a municipal building. Around med of the 19th century a new larger building was constructed to be used as the main municipal building, while the old one (the case study) has been used for hosting the guests of the municipality and also used for organizing the main events & different activities.

Year: 1893 – 2020

Picture 1: Front Elevation\ Southern Elevation of the mentioned building, June 2020

Page 4: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 4

3. INTRODUCTION

A specialized team from the Construction and Sustainable Buildings centre (CSBC) at the Royal Scientific Society made several visits to the mentioned site in the extended period from 29 June to 7 July 2020, as they conducted a careful visual inspection of the building and its surroundings. The team recorded the internal / external dimensions of the buildings in order to prepare as-built drawings that represent the reality of the building as much as possible by using modern surveying instruments (Total station and Level).

3.1. Existing geometrical documentation on the building

Architectural plans for the mentioned building were presented by Karak Municipality as AutoCAD file, Most of these documents that was provided by Karak municipality can be summarized as:

Basement Plan

Ground Floor Plan

First Floor Plan

General site map

All presented files weren’t completely accurate according to the visual inspection and the results of the survey work which is done by CSBC, so new architectural plans have been prepared for the mentioned building (as-built drawings) as possible and as circumstances permit.

All new prepared drawings are included in the annexes.

Figure 1: Basement floor, Ground floor, First Floor plans which were provided by Karak Municipality.

First Floor Ground Floor Basement Floor

Page 5: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 5

3.2. Type of survey adopted

In order to carry out suitable accuracy of the existing architectural survey, the adopted survey types by CSBC are through using modern survey instruments, mainly Laser Total station, Level, in order to prepare as-built drawings that represent the reality of the building as much as possible, besides using image-based survey (photogrammetry). This type of survey could also help the team to conceptualize and prepare accurate plans to represent the building, in addition of that, it is considered as the most suitable/ flexible method to deal with the privacy of the site and its precise details, especially due to the presence of narrow places and the presence of a mixture of old stone and new stone also the historical value of the building.

4. SITE CONDITIONS

The building was constructed in 1893 at Al-Karak city which lies about 140 km to the south of Amman on the ancient king’s highway. It is located in AL-Karak Governorate, specifically opposite the ancient Karak Castle, on an area of about (240) square meters (Picture 2 + Drawing 1). The building was constructed on two stages as the follow:

1- Stage No. 1 in 1893 (Othman Era):

The basement floor was constructed from true arches and vault made of limestone.

2- Stage No. 2 (from 1913-1926): The ground and first floors was constructed from true arches and vault made of limestone with steel/ I-Beams embedded in the slab supported by stone columns in the first floor.

The whole building was renovated several times, the first was in 1950, and the last time was in 2003.

Picture 2 Drawing 1

Page 6: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6

The facades of the building are clad in old stone and new stone [Pic.s (1, 3 & 4)], the building is surrounded by a pavement from the front side (street side) containing some plant tubs, in addition to the presence of dirt portion from the back of the building [Pic. (4)]. in the eastern side of the building, there is a stair which leads into the basement [Pic.5]; the roof floor is isolated by asphalt rolls [Pic.s (1, 3 & 4)/ Drawing No.2]. The building is located in AL-Karak Governorate, in the area opposite to AL- Karak Castle. there is a public street from the front façade of the building with a tiled pavement for pedestrian [Pic.1], while there is a nearby building on both sides (western and eastern sides) of the building, and a dirt portion from the back side of the mentioned building, with a staircase leads to the basement in the eastern corridor of the building. There is a raised plant tub is connected to the building from the backside contains a big tree [Pic.4].

Picture 3 Picture 4

Picture 5

Drawing 2

Page 7: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 7

5. PRE PLANNING ACTIVITIES

5.1. Pre planning activities description

According to the correspondence between the National Energy Research Centre (NERC) and Construction and Sustainable Buildings Centre (CSBC) at Royal Scientific Society, The National Energy Research Centre (NERC) assigned “the Construction and Sustainable Buildings Centre (CSBC)’’ to provide a complete georeferenced geometric survey of the exterior and interior of the building by using the traditional-direct instrumental survey methods and photogrammetry, in order to obtain a complete representation of the building, ground and/or aerial scans (as-built drawings).

A specialized team from the Construction and Sustainable Buildings centre (CSBC) made several visits to the mentioned site in the extended period from 29 June to 7 July 2020, as they conducted a careful visual inspection of the building and its surroundings, and they recorded the internal / external dimensions of the buildings in order to prepare as-built drawings that represent the reality of the building as much as possible by using modern surveying instruments (Total station and Level).

Accordingly, drawings were prepared representing the reality of the mentioned building as much as possible, recording all observations in the building and its surroundings and including the results in this technical report.

5.2. Equipment

The Survey Instruments were used in survey works consists mainly of:

Laser Total Station (geo-FENNEL): - Provide efficient and easy solutions for setting out. - Three-dimension measurements of coordinates. - Visible laser pointer to improve targeting accuracy and allowing measurements

to be taken without looking through the telescope. - Measuring range of up to 200m in the reflector less mode.

Level: - Provide accurate levels and giving a general view of the Topography of the land

surrounding the building.

Cameras: - Using different type of cameras with clear\ proper resolution.

Page 8: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 8

5.3. Personnel

# Name Position

1 Eng. Mazen Tahrawy Senior Specialist\ Studies\CSBC

2 Eng. Zaid Alkhandak Specialist\ Studies \CSBC

3 Eng. Ali Abu Othman Specialist\ Studies\CSBC

6. DATA ACQUISITION

6.1. Description of the performed data acquisition activities

A specialized team from the Construction and Sustainable Buildings centre (CSBC) made several visits to the mentioned site in the extended period from 29 June to 7 July 2020, as they conducted a careful visual inspection of the building and its surroundings, and they recorded the internal / external dimensions of the buildings in order to prepare as-built drawings that represent the reality of the building as much as possible by using modern surveying instruments (Total station and Level).

6.2. Site Visits Results

6.2.1 Site Plan (Drawing 3)

The building is located in Karak Governorate, in the area opposite Karak Castle. And there is a public street from the front façade of the building with a tiled pavement for pedestrian [Pic.2], while there is a nearby building on both sides (western and eastern sides) of the building, and a dirt portion from the back side of the mentioned building, with a staircase leads to the basement in the eastern corridor of the building.

There is a raised plant tub is connected to the building from the back side contains a big tree [Pic.4].

Drawing 3

Page 9: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 9

6.2.2 Basement Floor (Drawing 4) The building contains a basement from the eastern side with an estimated area (47m2); and can be accessed via a tiled stairway in the eastern corridor of the aforementioned building [Pic.5]; the basement’s inside elevation is as stone Arche With a max. Height from the middle about (2.7m) [Pic.6], the thickness of the walls at the entrance to the basement ranges around (1.4 – 1.6) m [Pic.7], there is another basement on the backside of the building but it is closed/ cancelled [Pic.8].

6.2.3 Ground Floor (Drawing 5)

The ground floor consists of a group of shops (4 shops with different areas) [Pic. (9+10)] , with a thickness of about (0.75)m for external wall and includes a mixture of old and new stone [Pic.11] , the western side from inside some of the shops/ ground floor contains antique/ ancient columns and some interior brick walls/ partitions [Pic. (12+13)].

The total height of the ground floor is about (4.3)m, and some shops contains mezzanine [Pic.12], on the ground floor there is a staircase leading to the first floor, located/ entrance in the middle of the front facade of the building [Pic.14] .

Picture 7 Picture 8

Drawing 4

Page 10: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 10

Picture 9 Picture 10

Picture 12

Picture 14 Picture 13

Picture 11

Drawing 5

Page 11: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 11

6.2.4 First Floor (Drawing 6)

The first floor contains an office, meeting room, and facilities, all of which are affiliated to the Municipality of Karak [Pic. (15-18)]. the thickness of the external walls of this floor is about (0.55) m [Pic.19], and there is some interior brick walls/ partitions as shown in drawing No. (4), the height of this floor is about (3.8) m, and there is a mezzanine room above the front side of the main stair [Pic.20].

It is noticed that there are reinforcement works for this floor slab and the upper/ roof slab through the presence of clear steel sections under mentioned slabs [Pic. (21-23)].

Picture 15 Picture 16

Picture 17 Picture 18

Picture 19 Picture 20

Drawing 6

Page 12: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 12

6.2.5 Roof Floor [Drawing No.2]

The roof floor is insulated with asphalt rollers along its length [Pic.24], in addition of that, there is a water tanks on the back west side of the roof floor [Pic.25], and there is a skylight/glass specifically in the area above the landing of the main stairs [Pic.26].

The roof floor contains some gutters to drain rainwater, and the only access way to get to the roof floor is by steel fixed loft ladder, which is located in the cantilever of the first floor from the eastern side [Pic.27]. And the parapet of the roof floor rises about (0.4) m with a thickness about (0.4) m surrounding the mentioned floor [Pic.28].

Picture 21 Picture 22 Picture 23

Picture 24 Picture 25 Picture 26

Picture 28 Picture 27 Picture 29

Picture 30

Drawing 2

Page 13: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 13

7. POST PROCESSING

The following post-processing steps have been followed:

1. All data collected on the site moved to the office work stage, all the required data, which is done by Total Station, was downloaded to be prepared and equipped according to the followed work steps.

2. All the data of the topographic\ Levelling work have been collected and prepared to complete the office work on them according to the work steps.

3. Work on preparing the technical report that includes all the steps in cooperation between the field work team and the administrative supervision in the office

8. RESULTS

8.1. Survey Work results

Some necessary survey investigations (mainly Levelling) were conducted on the area surrounding the building [Pic. (29+30)]; the following are the most important results of the mentioned investigations:

– From the front side of the building, the levels drop towards the east in line with the decrease in the level of the opposite street naturally, without noticing any significant settlement.

– The level of the side lanes of the building decreases from the eastern side and the western side of the building towards the north/ backside of the building, taking into account the presence of external stairs from both sides.

– The levels of the backside of the aforementioned building/ dirt portion decrease towards the north / away from the building (The level of the natural earth).

Page 14: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 14

9. ANNEXES

9.1. Technical documentation of the building (Traditional Survey)

A 1: Drawings

1. Site Plan

2. Roof Floor

3. Basement Floor

4. Ground Floor

5. First Floor

6. Survey Work (Leveling)

9.2. Photogrammetric documentation

A 2: Pictures (1-30)

Page 15: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 16: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 17: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 18: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 19: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 20: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad
Page 21: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (1)

Picture (2)

Page 22: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (3)

Picture (4)

Page 23: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (5)

Picture (6)

Page 24: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (7)

Picture (8)

Page 25: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (9)

Picture (10)

Page 26: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (11)

Picture (12)

Page 27: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (13)

Picture (14)

Page 28: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (15)

Picture (16)

Page 29: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (17)

Picture (18)

Page 30: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (19)

Picture (20)

Page 31: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (21)

Picture (22)

Page 32: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (23)

Picture (24)

Page 33: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (25)

Picture (26)

Page 34: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (27)

Picture (28)

Page 35: A32.4 GEOMETRIC SURVEY REPORT · 2020. 12. 17. · BEEP Interim Report 1: A.3.2.5. Geometric Survey Report - Jordanian case study -RSS/NERC 6 . The facades of the building are clad

Picture (29)

Picture (30)