A2A Training Modules 4 to 5.2

Embed Size (px)

Citation preview

  • 8/20/2019 A2A Training Modules 4 to 5.2

    1/67

    This module explains the concept of an energy balance. It is an important methodology

    that the tool uses to derive the breakdown of energy among the different end-uses

    within a plant. This background theory will help you understand the way the technical

    assessment tools works, and why it requires the information it does for the various fuels

    and equipment. In the exercise you will perform an energy balance manually. The toolkit

    does the calculations automatically, but the exercise will ensure a good understanding of

    the concept.

    1

  • 8/20/2019 A2A Training Modules 4 to 5.2

    2/672

  • 8/20/2019 A2A Training Modules 4 to 5.2

    3/67

    Study boundary The boundary of the study is defined by the energy purchased and utilized within the

    process of Ammonia production

    Energy purchased and sold Energy purchased accounts for energy utilized as a fuel only. Energy used for

    feedstock production (such as ammonia) is not utilized in the energy balance, but inthe energy intensity determination to be discussed in module 8

    On-site energy generation, such as renewable energy from wind, solar, biomass isincluded

    Energy sold or sent to another process train is accounted for in the assessment, onlyif it uses one of the purchased fuels to generate it (eg. Natural gas generating steam,of which some is used and the remaining sent to another process train)

    Utilized energy Equipment capacity, operating hours and number of equipment define the utilized

    energy The variable conditions such as the operation of maximum capacity is required Equipment with large capacity are detailed and for smaller pieces of equipment,

    such as ½ hp motors, the averages of the operating hours and capacities arepreferred

    For smaller or numerous equipment with similar characteristics, averages ofequipment load, such as on-off time, partial load applied to motors are used todetermine the average capacity or average operating hours

    Losses during equipment operation are not included in this study

    3

  • 8/20/2019 A2A Training Modules 4 to 5.2

    4/67

    This figure shows the flow of energy within the study boundary.

    4

  • 8/20/2019 A2A Training Modules 4 to 5.2

    5/67

    For the Energy Balance, it is important to ONLY list energy used as fuel, and EXCLUDE

    energy used as feedstock in the production of ammonia.

    5

  • 8/20/2019 A2A Training Modules 4 to 5.2

    6/67

    The energy balance accounts for where the energy flows within a plant. As the graph

    demonstrates the energy entering the plant (on the left) is equal to the amount of

    energy used by various equipment within a plant (on the right). The energy balance uses

    this comparison of purchased energy to energy consumed to determine the energy

    used by each end-use or equipment type. The following slides explain that process in

    detail.

    6

  • 8/20/2019 A2A Training Modules 4 to 5.2

    7/67

    • The energy content of the purchased fuel is evaluated against the energy consumed by

    each end use.

    • The adjustment factor is the ratio of energy consumed to energy purchased.

    • The adjustment factor is calculated for each fuel type

    • Once the adjustment factor is determined, the gaps in the energy consumed by

    inventory of equipment can be noted.

    7

  • 8/20/2019 A2A Training Modules 4 to 5.2

    8/67

    The lower heating value (LHV) is required to determine the fuel energy content to use in

    the Energy Balance tab. The LHV for some fuels may vary in energy content so the

    default values in the toolkit can be overwritten if necessary.

    The sold energy is the summation of the energy content of the sold fuels. For sold

    energy products such as steam, the energy value of the steam is allocated to the type of

    fuel used to generate the steam, with an adjustment applied to account for the

    conversion of fuel to steam. This adjustment is assumed to be 0.9, which is typical of

    boilers and reformer conversion.

    8

  • 8/20/2019 A2A Training Modules 4 to 5.2

    9/679

  • 8/20/2019 A2A Training Modules 4 to 5.2

    10/67

    •Self-generated energy is the total steam and electricity generated on-site.

    •Net-imported energy is the net purchased energy minus self-generated energy

    •The energy used by fuel type is determined by summing the energy use per equipment

    end-use for that fuel type.

    The adjustment factor  is the ratio of net imported fuel to utilized fuel for each fuel, and

    should always be less than one.

    10

  • 8/20/2019 A2A Training Modules 4 to 5.2

    11/6711

  • 8/20/2019 A2A Training Modules 4 to 5.2

    12/67

    The adjustment factor  is the ratio of net imported fuel to utilized fuel for each fuel, and shouldalways be less than one because of the following assumptions:

    •Equipment is assumed to be 100% efficient.•The hours of operation are applied directly to operating time without adjustment forload factors applied to equipment.

    •Equipment capacity is assumed to be the rated capacity.

    If the adjustment factor  is much greater than one, the following should be reviewed to addressthis:

    •Review quantity of purchased energy (may be too high).•Review the hours of operation of equipment using the fuel with the discrepantadjustment factor.

    •Review the capacity rating of equipment using the fuel with the discrepant adjustmentfactor.

    •Review the quantity of equipment using the fuel with the discrepant adjustment factor.•Review the firing time and efficiency of equipment where this is reported, such as forboilers and ovens.•Investigate whether all equipment using this fuel have been accounted for.

    When the adjustment factor is close to one, then all purchased energy is being accounted for byall reported equipment.

    If the adjustment factor  

    for steam as a fuel is much greater or less than one, review thefollowing:

    •That the source of the steam has been correctly identified in TA2•That the fuel used as steam has not been generated using another source fuel

    accounted for elsewhere (e. g. natural gas generated steam) and therefore added twicein the energy balance

    12

  • 8/20/2019 A2A Training Modules 4 to 5.2

    13/6713

  • 8/20/2019 A2A Training Modules 4 to 5.2

    14/6714

  • 8/20/2019 A2A Training Modules 4 to 5.2

    15/6715

  • 8/20/2019 A2A Training Modules 4 to 5.2

    16/6716

  • 8/20/2019 A2A Training Modules 4 to 5.2

    17/6717

  • 8/20/2019 A2A Training Modules 4 to 5.2

    18/67

    Link:

    02 A2A Training module 4 activity 

    18

    http://exercises/02%20A2A%20Training%20module%204%20activity.xlshttp://exercises/02%20A2A%20Training%20module%204%20activity.xlshttp://exercises/02%20A2A%20Training%20module%204%20activity.xlsx

  • 8/20/2019 A2A Training Modules 4 to 5.2

    19/67

    Notes:

    - useful conversion factors are provided on the same worksheet.

    - Enter answers into shaded cells in Tab A.4.1

    19

  • 8/20/2019 A2A Training Modules 4 to 5.2

    20/6720

  • 8/20/2019 A2A Training Modules 4 to 5.2

    21/6721

  • 8/20/2019 A2A Training Modules 4 to 5.2

    22/6722

  • 8/20/2019 A2A Training Modules 4 to 5.2

    23/6723

  • 8/20/2019 A2A Training Modules 4 to 5.2

    24/67

    Note: results are also shown in tab B 4.1 of the Excel workbook

    24

  • 8/20/2019 A2A Training Modules 4 to 5.2

    25/6725

  • 8/20/2019 A2A Training Modules 4 to 5.2

    26/6726

  • 8/20/2019 A2A Training Modules 4 to 5.2

    27/6727

  • 8/20/2019 A2A Training Modules 4 to 5.2

    28/6728

  • 8/20/2019 A2A Training Modules 4 to 5.2

    29/6729

  • 8/20/2019 A2A Training Modules 4 to 5.2

    30/67

    In previous modules you have learned some of the theory and methodology used by the

    toolkit. In this module you will start using the toolkit as if you are doing an assessment

    for a plant. There will be a demonstration of how to fill in the technical assessment, and

    an exercise in which you will receive information from a hypothetical plant, and use that

    information to fill in the technical assessment.

    1

  • 8/20/2019 A2A Training Modules 4 to 5.2

    31/672

  • 8/20/2019 A2A Training Modules 4 to 5.2

    32/67

    The purpose of the technical best practice (TBPs) assessment is to determine which TBPs

    are implemented at the plant, and to develop benchmarks for the plant. The

    benchmarks highlights the areas where opportunities exist to implement TBPs, and

    indicate the potential that still exist to implement TBPs.

    3

  • 8/20/2019 A2A Training Modules 4 to 5.2

    33/67

    The technical best practice (TBPs) assessment is part of the first step in the Continuous

    Improvement Cycle.

    4

  • 8/20/2019 A2A Training Modules 4 to 5.2

    34/675

  • 8/20/2019 A2A Training Modules 4 to 5.2

    35/67

    The Energy Technical Assessment questionnaire collects information on energy

    purchased and the energy used by equipment in the plant. The questionnaire includes

    questions pertaining to the overall energy use, production, characteristics of the

    equipment, and the presence of energy efficiency measures. The Excel workbook

    includes the following sections:

    •Section A gathers general information regarding the facility production and

    procurement of energy.

    •Section B is specifically related to generic equipment, such as cooling, heating and

    motive power.

    •Section C outlines types of heating, ventilation and air conditioning systems specifically

    associated with occupancy comfort.

    •Section D is an overview of system practices, other major energy consuming

    equipment, and the implementation of emerging technologies.

    •Section E collects data on ammonia production practices only.

    6

  • 8/20/2019 A2A Training Modules 4 to 5.2

    36/67

    This is the index as seen on the tab labeled “Index”. Click the description to navigate

    directly to that tab.

    The end uses referred to in the Index Table are:

    •Process: Energy end uses applicable to the manufacturing processes and generic to

    different manufacturing plants.

    •Comfort: Energy end uses that support the comfort of the employees, such as lighting,

    space heating and cooling, and air ventilation to maintain appropriate air quality for

    employees.

    •Other: Energy end uses applicable to processes not covered by “process” and

    “comfort” end uses, and non-generic energy end uses specific to the processes in a

    specific manufacturing sector.

    7

  • 8/20/2019 A2A Training Modules 4 to 5.2

    37/67

    Link:

    Module 5.1 Video 

    8

    http://videos/Module%205.1%20Video.mp4http://videos/Module%205.1%20Video.mp4

  • 8/20/2019 A2A Training Modules 4 to 5.2

    38/679

  • 8/20/2019 A2A Training Modules 4 to 5.2

    39/67

    There may be numerous pieces of equipment under each type, and it is recommended

    to categorize this by size. Up to six ranges of equipment sizes can be entered, by

    providing weighted average equipment capacity values and average hours of operation

    for each range.

    For example, if there are 25 motors ranging in size from 0.3 to 0.5 kW, operating

    between 500 to 6000 hours per year, the average range of equipment capacity would

    be:

    Average range [kw] = ∑ (motor power *kw]) x (motor hours of operation [h])

    ∑ (hours of operation *h+) 

    The hours of operation entry would be the average hours for all the motors in that

    range.

    10

  • 8/20/2019 A2A Training Modules 4 to 5.2

    40/67

    Boilers require special consideration when grouping together. As can be seen in the

    boiler section of TA3, since boiler type /economizer must be selected from a drop-down

    menu, if there is more than one boiler for that line, they must be of the same

    type/economizer.

    However, it is rare that you will need to group boilers together, since there is sufficient

    space to enter information for four boilers and facilities rarely have more than four.

    11

  • 8/20/2019 A2A Training Modules 4 to 5.2

    41/6712

  • 8/20/2019 A2A Training Modules 4 to 5.2

    42/67

    Links:

    03 A2A Training module 5.1 activity 

    04 A2A Training module 5.1 activity – incomplete assessment 

    Notes:

    - The technical assessment is partially filled in, but not complete. You must use the

    missing information found on Tab A 5.1.1 to complete the technical assessment.

    - For the pumps: Two sizes ranges are missing in the TBP assessment. You must group

    the pumps together into size ranges, and calculate weighted values of the pump ratings,and finally enter this into the correct cells in the assessment

    - For the boilers: Five boiler sizes are given, therefore two of the boilers must be

    grouped together and weighted values of boiler ratings must be calculated. Also, for the

    economizer entry, you must decide if "ntf" or "no economizer" must be selected.

    13

    http://exercises/03%20A2A%20Training%20module%205.1%20activity.xlshttp://exercises/04%20A2A%20Training%20module%205.1%20activity%20-%20Incomplete%20Assessment.xlshttp://exercises/04%20A2A%20Training%20module%205.1%20activity%20-%20Incomplete%20Assessment.xlshttp://exercises/04%20A2A%20Training%20module%205.1%20activity%20-%20Incomplete%20Assessment.xlshttp://exercises/04%20A2A%20Training%20module%205.1%20activity%20-%20Incomplete%20Assessment.xlshttp://exercises/03%20A2A%20Training%20module%205.1%20activity.xlshttp://exercises/04%20A2A%20Training%20module%205.1%20activity%20-%20Incomplete%20Assessment.xlshttp://exercises/03%20A2A%20Training%20module%205.1%20activity.xlsx

  • 8/20/2019 A2A Training Modules 4 to 5.2

    43/6714

  • 8/20/2019 A2A Training Modules 4 to 5.2

    44/6715

  • 8/20/2019 A2A Training Modules 4 to 5.2

    45/67

    Now that you have completed the training activity for module 5.1 on your own, the

    answers and issues will be reviewed.

    Some of the Technical Assessment that require data entry will be shown in the

    subsequent slides. You can also open the completed assessment to see the filled-in

    assessment:

    05 A2A Training module 5.1 activity - Completed Assessment 

    The solutions to the weighted average calculation are shown in Tab B 5.1.1 of “03 A2A

    Training module 5.1 activity” 

    16

    http://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xlshttp://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xlshttp://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xls

  • 8/20/2019 A2A Training Modules 4 to 5.2

    46/67

    The purchased energy information should be entered on tab TA2 as shown above.

    17

  • 8/20/2019 A2A Training Modules 4 to 5.2

    47/67

    The boiler section is filled in as shown. The 17.6 MW boiler is a weighted average of the

    15MW and 20MW closed fire tube boiler (see the weighted average calculations on tab

    B 5.1.1 of “03 A2A Training module 5.1 activity”). 

    18

  • 8/20/2019 A2A Training Modules 4 to 5.2

    48/67

    This screen shows the second table of boiler information to be entered.

    19

  • 8/20/2019 A2A Training Modules 4 to 5.2

    49/6720

  • 8/20/2019 A2A Training Modules 4 to 5.2

    50/67

    After reviewing all of the tabs of the technical assessment, these are some of the issues

    that could be found that should be brought up with plant personnel.

    21

  • 8/20/2019 A2A Training Modules 4 to 5.2

    51/67

    The issues found on the energy balance tab (TA 11) are shown in this slide.

    The high adjustment factor for natural gas indicates that the plant purchased much more

    natural gas than is being accounted for by the equipment natural gas consumption. This

    is an issue that should be discussed with plant personnel. It may be that some

    equipment was missed, equipment capacities or hours were incorrect, the quantity of

    natural gas purchased was incorrect, or other reasons.

    The energy balance showed that gasoline was purchased, however no equipment was

    entered that uses gasoline. This is another issue that should be discussed with the plant.

    22

  • 8/20/2019 A2A Training Modules 4 to 5.2

    52/67

    This module explains the ammonia specific components of technical assessment, and

    the ammonia specific library.

    1

  • 8/20/2019 A2A Training Modules 4 to 5.2

    53/672

  • 8/20/2019 A2A Training Modules 4 to 5.2

    54/673

  • 8/20/2019 A2A Training Modules 4 to 5.2

    55/674

  • 8/20/2019 A2A Training Modules 4 to 5.2

    56/67

    The ammonia subsector energy use and best practice assessment is presented in section

    E of the Energy Technical Assessment questionnaire. Up to five such types of equipment

    can be detailed, in order of energy use.

    5

  • 8/20/2019 A2A Training Modules 4 to 5.2

    57/67

    Link:

    Module 5.2 Video 

    6

    http://videos/Module%205.2%20Video.mp4http://videos/Module%205.2%20Video.mp4

  • 8/20/2019 A2A Training Modules 4 to 5.2

    58/67

    The library organizes energy efficiency technical best practices by end use and several

    process levels. Each energy savings measure is entered in a separate tab with its

    associated parameters, providing the energy savings, the fuel type saved, and a detailed

    description of the measure along with the reference sources of information.

    This section is intended to provide more detail and supplement Module 3. The focus will

    be specifically on the Ammonia library.

    7

  • 8/20/2019 A2A Training Modules 4 to 5.2

    59/67

    Profile type: each measure is classified as either technology, operating, behavioural or maintenance.

    Level (1 to 5): further describe each measure based on which part of the plant and which category of equipment the

    measure is relevant to. This allows the user to filter the measure list on the Index tab by a variety of criteria.

    Relative implementation cost: each measure is rated as high, medium or low to indicate the relative cost ofimplementation: •High – there would be significant investment to implement the measure. A detailed economic feasibility studywould generally be required. Most measures in this category would involve the replacement of large equipment, orlarge retrofit projects.•Medium – may involve inexpensive equipment replacement or retrofits. An economic feasibility study is generallyadvisable.•Low – little or no capital cost would be required. Often involves behavioural changes and only a rudimentaryeconomic assessment may be needed.

    Relative implementation difficulty: each measure is rated as high, medium or low to indicate the relative difficulty ofimplementation:•High – the implementation of the measure involves complex change to the plant. The measure may involve redesign,and a detailed engineering feasibility assessment would be required.•

    Medium –

     may involve small equipment replacement or simple retrofits. A less extensive technical feasibilityassessment is usually required.•Low – relatively easy to implement the opportunities and most often involves maintenance related opportunitiesand/or behavioural changes. Technical feasibility studies are generally not required.

    Energy type: four energy types are listed: natural gas, electricity, refined petroleum products, and other. Measuresavings are shown for each fuel type. As illustrated in Exhibit 20 (boiler economizer), some measures show savingsfor more than one energy type. This indicates that there are multiple energy source options for the given end-use;the savings will be calculated for the energy source selected in the Technical Assessment, not all of the energysources listed in the library. For the measures which may save other types of energy than those listed, the fuel type isentered in the “Other fuel” line. 

    Savings percentage: the amount of energy that would be saved for that particular fuel type. The savings is given as apercentage of the end-use consumption (not the total plant energy use). Savings are dependent on site specificconditions and the savings indicated in the measure library provides only typical values, or ranges of savings forimplementation of a specific measure, as guidance. These values are reported in literature or obtained from industrialexperts. Savings are provided per opportunity and are not additive. Furthermore, interactive effects will reduce thetotal potential savings if more than one opportunity is implemented.

    8

  • 8/20/2019 A2A Training Modules 4 to 5.2

    60/67

    Description: explanation of the measure, and the means by which the measure saves

    energy.

    Reference Sources: the source of the savings percentage and measure life.

    9

  • 8/20/2019 A2A Training Modules 4 to 5.2

    61/67

    Links to libraries:

    08 A2A Training module 5.2 activity - Ammonia Library 

    09 A2A Training module 5.2 activity - Generic Library 

    The questions shown in the slide are also found in tab A 5.2.1 in the exercise file:

    07 A2A Training module 5.2 activity 

    10

    http://exercises/08%20A2A%20Training%20module%205.2%20activity%20-%20Ammonia%20Library.xlshttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlshttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/08%20A2A%20Training%20module%205.2%20activity%20-%20Ammonia%20Library.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlsxhttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/08%20A2A%20Training%20module%205.2%20activity%20-%20Ammonia%20Library.xls

  • 8/20/2019 A2A Training Modules 4 to 5.2

    62/67

    Links:

    05 A2A Training module 5.1 activity - Completed Assessment 

    09 A2A Training module 5.2 activity - Generic Library 

    07 A2A Training module 5.2 activity 

    11

    http://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xlshttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlshttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xlshttp://exercises/07%20A2A%20Training%20module%205.2%20activity.xlsxhttp://exercises/09%20A2A%20Training%20module%205.2%20activity%20-%20Generic%20Library.xlshttp://exercises/05%20A2A%20Training%20module%205.1%20activity%20-%20Completed%20Assessment.xls

  • 8/20/2019 A2A Training Modules 4 to 5.2

    63/67

    Note: the potential energy savings is calculated automatically by the report card (as will

    be seen in a subsequent module), however, it is important to understand the

    calculations and origins of the numbers used.

    12

  • 8/20/2019 A2A Training Modules 4 to 5.2

    64/6713

  • 8/20/2019 A2A Training Modules 4 to 5.2

    65/6714

  • 8/20/2019 A2A Training Modules 4 to 5.2

    66/6715

  • 8/20/2019 A2A Training Modules 4 to 5.2

    67/67