Upload
andren
View
33
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Interconnection of the Cycladic islands of Syros, Tinos, Mykonos, Paros and Naxos to the Mainland System via submarine cables. A. Koronides, S. Efstathiou G. Koutzoukos, N. Boulaxis. Background. - PowerPoint PPT Presentation
Citation preview
11
Interconnection of the Cycladic Interconnection of the Cycladic islands of Syros, Tinos, Mykonos, islands of Syros, Tinos, Mykonos, Paros and Naxos to the Mainland Paros and Naxos to the Mainland
System via submarine cablesSystem via submarine cables
A. Koronides, S. Efstathiou G. Koutzoukos, N. Boulaxis
22
The Interconnection of the Northern Cycladic Islands has been considered as early as the early 90‘s because of: Rapid growth of their consumption
(development due to tourism) Building new Generating Capacity was always
very difficult very difficult due to environmental constraints (all existing in proximity to the main towns)
High operating cost using diesel and heavy fuel
BackgroundBackground
33
Area of ConcernArea of Concern
44
0
20
40
60
80
100
120
140
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
Year
Pea
k L
oad
[M
W]
Paros-Naxos Mykonos Syros Andros-Tinos Total
0
50
100
150
200
250
300
350
400
450
500
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
Year
En
erg
y D
eman
d [
GW
h]
Paros-Naxos Mykonos Syros Andros-Tinos Total
Evolution of DemandEvolution of Demand
Evolution of Energy demand (1980-2004)
Evolution of Peak load (1980-2004)
Year of connection of Andros-Tinos to the Mainland
2005
55
Load ForecastLoad Forecast
Forecasted Energy demand (2005-2025)
Forecasted Peaks (2005-2025)
0
100
200
300
400
500
600
700
800
900
1000
11002
00
6
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
Year
En
erg
y D
em
an
d [
GW
h]
Paros Naxos Mykonos Syros Andros Tinos Total
020406080
100120140160180200220240260280300
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
Year
Pe
ak
Lo
ad
[M
W]
Paros Naxos Mykonos Syros Andros Tinos Total
66
0
10
20
30
40
50
60
70
80
90
Local GenerationLocal Generation
12.324
34
548
6
11
15
20 (30)
Andros Syros Mykonos Paros
Current capacity Planned Expansion Possible additional capacity
[MW]
77
Introduced in the late 80’s to be implemented in early 90’s :
weak interconnection to the Mainland by single cable
OHL on the islands and submarine cables between them (shortest distances)
development of new geothermal power plant in Milos
Foreseen implementation in two phases:
Phase A: interconnection of Andros,Tinos, Mykonos and Syros to the Mainland
Phase B: expansion of the connection to Milos (reaching the Geothermal Field) and installation of Geothermal Power Plant in Milos
Initial Interconnection PlanInitial Interconnection Plan
88
Initial Plan (made in1989)Initial Plan (made in1989)
New 150kV OHL
New 150kV submarine cable
New 66kV OHL
New 66kV submarine cable
Existing 150kV substation
New 150kV substation
New 66kV substation
Existing PS
New PS (geothermal)
PHASEPHASE Α Α
PHASEPHASE Β Β
99
By the end of the 90´ were installed the cables (mid 90’s ) :
• Main System – Andros
• Andros – Tinos
• Tinos – Syros
• Tinos – Mykonos the OHL over Andros (late 90’s)
What has been done (1/2)What has been done (1/2)
1010
In the meantime :
Local Reaction against construction of OHL (150kV, 66kV) on the islands has escalated
also
Local Reaction against Geothermal plant in Milos started
However, a new interconnection plan was prepared
What has been done (2/2) What has been done (2/2)
1111
Revision of Initial Plan (2001)Revision of Initial Plan (2001)
Existing 150kV OHL
New 150kV OHL
Existing 150kV submarine cable
New 150kV submarine cable
New 66kV OHL
Existing
New 66kV submarine cable
Existing 150kV substation
New 150kV substation
New 66kV substation
Existing PS
New PS (Diesel)
1212
Expansion of the Interconnection to Paros and Naxos
Revised plan for installation of new “big scale”“big scale” thermal station in Naxos
Expectations to overcome local reactions
Sitting of thermal station in Naxos considered possible
Revision of Initial Plan (2001)Revision of Initial Plan (2001)
1313
Local Reactions Escalated State Council Decision was issued againstagainst
construction of new High Voltage Lines on the Islands
Sitting of new thermal stations almost impossible
Nevertheless in 2003 the construction of an AIS in Andros was completed
Court Decisions Court Decisions (2001-2004)(2001-2004)
1414
Facing said facts, a more “pragmatic” design was done
No new OHL over the islands
No new thermal stations on the islands
Use of existing thermal plants only as cold reserve - No thermal Production on the islands
Possibility to exploit significant wind capacity (installation of W/F)
New Design New Design (2004 - 2005)(2004 - 2005)
1515
Final Plan (2005)Final Plan (2005)
Existing 150kV OHL
New 150kV OHL
Existing 150kV submarine cable
New 150kV submarine cable
Existing 66kV cable
Existing 150kV substation
New 150kV substation
Existing PS
1616
ProsPros Secure power supply of the Islands (from the mainland interconnected grid) Long-term solution – no new local generation every 2-3 years Substitution of power (Diesel) from existing local PS (gradual
decommissioning) with power from the Interconnected System Economic and Environmental benefits
Increase of wind power penetration on the interconnected islands Possible future extension of the Interconnection to the Southern Cycladic
Island (further exploitation of considerable wind and geothermal potential of the islands)
More economical than feeding the islands by diesel stations in the long run ConsCons
Considerable initial investment cost:• submarine cables• advanced interconnection technology (DC with VSC, GIS substations,)
Long amortization period Use of new innovative, but not sufficiently proven technologies (long
XLPE* submarine cables, DC control in abnormal situations e.t.c).
* XLPE cables have low MVAR/km than OIC (1,5 vs 2,5)
Pros and Cons Pros and Cons of the Interconnectionof the Interconnection
1717
Technical DescriptionTechnical Description 4 new GIS Substations 150/20kV in Syros, Mykonos, Paros and
Naxos Submarine Interconnection of above substations
(cables 1×3phase / AC / XLPE / 150kV / 200MVΑ): Syros - Mykonos 36km Syros - Paros 50km Paros - Naxos 16km Naxos - Mykonos 40km Syros - Andros 32kmReactive compensation (reactors) of the cables is required
Submarine Interconnection of Syros to the Mainland (Lavrion EHV Substation). Two alternative technologies:
D.C. Interconnection: Submarine D.C. interconnection Lavrion - Syros ~100km 250ΜW
(2+1 cables) An AC/DC converter station at each end of the interconnection
(-50/+150ΜVA) A.C. Interconnection:
Submarine A.C. interconnection Lavrion - Syros ~110km 250ΜW (2×3phase / AC / XLPE / 150kV / 200MVΑ).One stop at Kythnos for junction and reactive compensation with SVC in Syros ~ +/- 150 MVAR
1818
Basic Economic and Basic Economic and Technical assumptionsTechnical assumptions
Πηγή: ΔΕΗ/ΔΣΠ
* Price in 2006 570€/lt
Basic economic assumptions (in 2005 prices)
Inflation 3%
Rate of fuel price variation above Inflation 2%
Cost of FuelDiesel 410 €/t*
Heavy oil 190 €/t
Cost of Energy from Interconnected System 54 €/MWh
Cost of Energy from local PS 80 €/ΜWh
O&M cost of old local PS 96.03 €/KW&year
O&M cost of expansion of existing local PS 38.41 €/KW&year
Investment Cost (after taxes) 7%-9%
Basic technical assumptions (in 2004 prices)
CO2 emissions 8-20 €/ton CO2
Efficiency of new PS (diesel) 42%
Investment Cost (new PS) 1100 €/KW&year
Cost of Expansion of old PS 825 €/KW&year
1919
Comparative Cost AnalysisComparative Cost Analysis(estimates with 2005 prices(estimates with 2005 prices
in MEuros)in MEuros)
* new OHL over the islands, submarine cables between the islands, connection with new cables and lines to the north
** New prices increase 40%
Cost Component [MW]Final
SolutionExpansion of existing PS
No further interconnectionLeast Cost Approach*
Investment Cost 170 ~230 133.03 101.26
Cost of Fuel (Diesel)** 0 472.74 0
Cost of Energy from Interconnected System
380 61.62 380.72
CO2 emissions 0 11.86 0
Fixed O&M Costs 10 ~ 75 49.53 48.62
Total Cost 560-685 728.77* 530.6
new oil prices
2020
ΑΝDROS 150kV
Lavrion EHV400kV
150kV XLPE AC 1×3 200MVA40km
~
150kV XLPE AC1×3 200MVA36km
150kV XLPE AC1×3 200MVA16km
150kV XLPE AC1×3 200MVA50km
~
150kV XLPE AC1×3 200MVA32km
DC (2+1 cables)250MW100km
1×16MVAr1×9MVAr
1×16MVAr1×9MVAr 1×9MVAr
1×16MVAr 1×16MVAr
1×9MVAr
1×18MVAr
1×18MVAr
1×16MVAr
~
1×18MVAr
1×19MVAr
1×16MVAr
1×16MVAr
1×16MVAr
D.C. SolutionD.C. Solution
AC/DC Converter station-50/+150MVAr
AC/DC Converter station-50/+150MVAr
MYKONOS 150kV
NAXOS 150kV
SYROS 150kV
PAROS 150kV
2121
PAROS150kV
MYKONOS150kV
SYROS150kV
150kV XLPE AC 1×3 200MVA40km
~
150kV XLPE AC1×3 200MVA36km
150kV XLPE AC1×3 200MVA16km
150kV XLPE AC1×3 200MVA50km
~
150kV XLPE AC 1×3 200MVA32km
150kV XLPE AC2×3ph/280MVA110km
1×16MVAr1×9MVAr
1×16MVAr1×9MVAr 1×9MVAr
1×9MVAr1×18MVAr
1×9MVAr2×18MVAr
(junction at Kythnos)
1×18MVAr
1×16MVAr 1×16MVAr
1×9MVAr
1×18MVAr
1×18MVAr
1×16MVAr
~
1×18MVAr
1×18MVAr
1×16MVAr
1×18MVAr
1×16MVAr
SVC-50/+150MVAr
Transformer 400/150kV
150kV
ANDROS 150kV
1×18MVAr
A.C. SolutionA.C. SolutionLavrion EHV400kV
Junction point in the island of Kythnos
2222
Expansion of the Network (Overhead Lines) Faces huge local Reaction
Generalized use of Cables is not realistic:
Huge Cost
Technical Problems (reactive capacitance)
Use of Cables in the mainland is restricted to very specific cases involving heavily populated areas
Conclusions 1/5Conclusions 1/5
2323
The Cycladic Islands are the closest islands of the Aegean Archipelago to the mainland.
They represent a significant load with high rate of increase.
Development of local generating units is associated with high operational cost and practical difficulties to find new locations.
A submarine “cable” connection to the mainland is the only “pragmatic” solution.
Conclusions 2/5Conclusions 2/5
2424
The least cost solution, would involve several overhead HV lines on islands and new ~70km in the mainland in Evia
New OHL on the Islands would “insult” dramatically the aesthetically sensitive landscape of the islands and was denied by the State Council
Licensing of new long OHL in Evia considered impossible
Conclusions 3/5Conclusions 3/5
2525
Solution Chosen :
Long Submarine Connection of the central island of Syros to the Lavrio production center in the mainland and,
DC converters and cables or
AC XLPE Cables and junction in island in about half distance plus SVC in Syros
Connection to other Islands by AC XLPE cables
Conclusions 4/5Conclusions 4/5
2626
Solution Chosen
Has high initial investment cost
But is economically feasible in the long run
Is environmentally friendly, therefore is pragmatic
Allows installation of Wind Power up to about the peak load of the islands (otherwise very limited)
Is acceptable by the local communities
Conclusions 5/5Conclusions 5/5
2727
Other interesting cases experienced by HTSO Other interesting cases experienced by HTSO (1/4)(1/4)
Corfu
South Evia
2828
Other interesting cases experienced by HTSO Other interesting cases experienced by HTSO (2/4)(2/4)
In the Island of Corfu a second 150 kV submarine cable was planned to satisfy the reliability needs for the island (N-1 criterion )
Total length ~ 17 km submarine
To ease the local reaction the 3 km OHL line on the island was designed as underground cable
Nevertheless the project faces big delays since reaction appeared requesting transferring of the local Substation (existing for many decades) to a new location and use of GIS technology.
2929
Other interesting cases experienced by HTSO Other interesting cases experienced by HTSO (3/4)(3/4)
A new Connection of Evia to the mainland was designed to support Wind Energy
Initially least distance submarine cable solution was chosen (~17 km OHL and ~8 km submarine cable)
It was rejected and replaced by a solution with
~ 20 km submarine cable and 2 km underground cable through a small town
Recently, local reaction appeared against the underground cable through the town.
3030
Other interesting cases experienced by HTSO Other interesting cases experienced by HTSO (4/4)(4/4)
Lesson Learned :
Use of cables,
Although is expected to be acceptable by the local societies
might bring new reaction and
further requests.