600 mw stator bar training report

Embed Size (px)

Citation preview

  • 7/22/2019 600 mw stator bar training report

    1/21

    MANUFACTURING PROCESS OF 500 MW

    TURBO GENERTOR STATOR WINDING

    BAR

    HARSHIT AGARWAL

    08070105022

    AT BHEL HARIDWAR

  • 7/22/2019 600 mw stator bar training report

    2/21

    INTRODUCTIONIn 1956 India took a major step towards the establishment of itsheavy engineering industry when BHEL, the first heavy electrical

    Manufacturing unit of the country was set up at Bhopal.

    BHEL's Heavy Electrical Equipment Plant (HEEP) was set up

    in technical collaboration with USSR, for the manufacturing of

    power plant equipment.

    In 1976, BHEL entered into a collaboration agreement with

    M/s Kraftwerk Union, AG of Germany for design,

    manufacturing, erection and commissioning of large size

    steam turbines.

    More than 40 percent of the country's electrical energy is

    generated from the power equipment supplied by BHEL,

    Haridwar.

  • 7/22/2019 600 mw stator bar training report

    3/21

    MANUFACTURING BLOCKS:

    .

    BLOCK I: ELECTRICAL MACHINE BLOCK, IS DESIGNED TO

    MANUFACTURING OF TURBOGENERATORS

    BLOCK II: FABRICATION BLOCK

    BLOCK III: TURBINE BLADE BLOCK

    BLOCK IV: COIL & INSULATION MANUFACTURING &

    APPARATUS & CONTROL GEAR MANUFACTURINGBLOCK

    BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION

    AND FORGE BLOCK

    BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCKBLOCK VII: WOODWORKING BLOCK

    BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO

    MANUFACTURE HEAT EXCHANGER UNIT FOR

    STEAM TURBINES.

  • 7/22/2019 600 mw stator bar training report

    4/21

    COIL & INSULATION MANUFACTURINGSHOP (BLOCK-IV)Block-4 is a feeder block for insulating items,

    winding with class-B Bituminous insulation and sheet

    metal components for all the products of Block-1 i.e.

    Turbo-generators, Hydro-generators, A.C. and D.C.machines

    There are three BAYS in this block each bay

    manufactures stator bars and coils for differentmachines

  • 7/22/2019 600 mw stator bar training report

    5/21

    BAY-I: Bar winding shop: manufacturing of stator winding

    bars of generator

    BAY-II: Manufacturing of heavy duty generator stator bars

    with New CNC M/c

    BAY-III: Insulation detail shop: Manufacturing of hard

    insulation & machining of hares insulation part (Glass Textolite)

    such as packing, washer, insulation box, wedges etc

    Bar Shop: This shop is meant for manufacturing of stator

    winding coils of turbo-generator and hydro generator

  • 7/22/2019 600 mw stator bar training report

    6/21

    Layout of CIM, Block-IV

  • 7/22/2019 600 mw stator bar training report

    7/21

    Sections in Block IV1) Assembly Section

    It is equipped with small size

    Drilling machines

    Welding sets

    Hydraulic testing equipmentfor manufacturing turbo-

    generator mechanical

    assemblies.

    2) Stator Bar Winding SectionIt is equipped with

    Conductor cutting, insulation and

    transposition section.

    Stack consolidation section,forming and lug brazing sections.

    Insulation taping sections with

    automatic taping facilities in air-

    conditioned

    3) Impregnation Section

    It is equipped with

    Impregnation tank

    Ovens for impregnation of DC pole coils.

  • 7/22/2019 600 mw stator bar training report

    8/21

    4) Armature Winding, Rotor coil and Stator bar Section

    It is equipped with

    Conductors cutting.

    U- bending and terminal conductor cutting machines.

    Semi-automatic winding machine.

    Planking, boat pulling and diamond pulling machine. Insulation and pressing of AC coils.

    5) Insulation Section

    It is equipped with

    Small size lathes. Milling and radial drilling machines.

    Jet cutting saw.

    Electrical ovens & Hydraulic presses.

    Plastic Molding Section

  • 7/22/2019 600 mw stator bar training report

    9/21

    Types of GeneratorsThe generator may be classified based upon the cooling

    system used in the generators such as: THRI, TARI, THDI,

    THDD, THDF, THFF, and THW

    Standsfortypeofgenerator

    T-TurboGenerator

    H-HydroGenerator

    Standsforthecoolingmedia

    forRotor

    H-Hydrogengas

    A-Air

    Standsforthetypeofcooling

    forRotor

    R-Radial

    D-Direct

    F-Forced I-Indirect

    Standsfortypeofcoolingfor

    Stator

    I-Indirect

    D-Direct

    F-Forced

    StandsforcoolingmediausedforStator

    coil

    W-Water

  • 7/22/2019 600 mw stator bar training report

    10/21

    It is quite difficult (rather impossible) to manufacture, handle

    and wind in the stator slot of generator of higher generation

    capacity because of its bigger size and heavy weight. That is

    why we make coil in two parts. One part its bottom part of coil

    called bottom or lower bar and other part of coil is called topbar or upper bar.

    Why do we call it bar?

  • 7/22/2019 600 mw stator bar training report

    11/21

    Set Type Upper

    Ordinary

    Upper

    Terminal

    Lower

    Ordinary

    Lower

    Terminal

    Total

    Bars

    No. of

    Bus

    Bars

    500MWTHDF

    42 6 42 6 96 6

    210MW

    THW

    54 6 54 6 120 9

    250MW

    THRI

    48 12 48 12 120 9

    No. of Bars in current products

  • 7/22/2019 600 mw stator bar training report

    12/21

    Poor Resin or Micalastic insulation system

    In this type of insulation the bond content in the resin is 5

    7%and insulating material is prepared with accelerator treatment.

    The temperature control need is not required. The insulating

    material is applied on job and then same is impregnated (fully

    dipped) in the resin.

    Resin System: Rich Resin or Thermo-reactive insulation system:

    In this type of insulation system the bond content in resin is

    35 37 %. The raw materials are ready to use and require

    preservation and working on temperature 20 250C. Its shelf

    life is one year when kept at a temperature of 200C whichcould be increased when kept at temperature of 50C.

  • 7/22/2019 600 mw stator bar training report

    13/21

    INSULATION CLASSIFICATION:Class

    Y

    Upto90C

    Cotton,Silk,orPaper.

    ClassA

    Upto105C

    ReinforcedClass-Ymaterialswithimpregnatedvarnish.

    Class

    E

    Upto120C

    Cottonlamination&Paperlamination.

    ClassB

    Upto130C

    Inorganicmaterialishardenedwithadhesives.

    Class

    F

    Upto150C

    Class-Bmaterialsthatareupgradedwithadhesives.

    ClassH

    Upto180C

    Madeofinorganicmaterialgluedwithsiliconeresin.

    ClassC

    >180CUpto220C

    Madeof100%inorganicmaterial

  • 7/22/2019 600 mw stator bar training report

    14/21

    TranspositionTransposition means changing/shifting of position of each

    conductor in active core (slot) part.

    After cutting the required number of conductors

    The conductors are arranged on the comb in staggeredmanner and then bends are given to the conductors with the

    help of bending die at required distance.

    Then the conductors are taken out from the comb and die and

    placed with their ends in a line and transposition is carried out.This process is repeated for making another half of the bar

    which would be mirror image of the first half.

    The two halves of the bar are overlapped over each other and

    a spacer is placed between the two halves.

  • 7/22/2019 600 mw stator bar training report

    15/21

    Need of transposition.1. To reduce eddy current losses.

    2. Equalize the voltage generator.

    3. To minimize skin effect of ac current.

    Transposition is done in two ways:

    Half Pitch Transposition: In this transposition, the firstconductor at one end of the bar becomes the last conductor at

    the other end of the bar.

    Full Pitch Transposition: In this method of transposition, thefirst conductor at one end of the bar becomes the last

    conductor in the mid of the bar and then again becomes the

    first conductor at the other end of the bar.

  • 7/22/2019 600 mw stator bar training report

    16/21

    TestingTan test:

    This test is carried out to ensure the healthiness of dielectric(Insulation) i.e. dense or rare & measured the capacitance loss.

    Bar will act as capacitor when it is laid in the stator of the

    generator.

    Schearing Bridge which works on the principle of wheat-stone

    bridge is used to find the unknown capacitance of the bar.

    For good efficiency, capacitance of the bar should be high but we

    never approach pure capacitance.Bar is wrapped with aluminum to make the bar conductive

    throughout the outer surface of the bar. The two conductingmaterial i.e. the aluminum sheet and the conductors of the bar act

    as two plates of the capacitor and the insulation on the bar act as

    dielectric medium for the capacitor thus the capacitance is found.

    Of angle of deviation due to impurity in the insulation is obtained

    from the formula: C4 * R4 * 10^-4 = tan

  • 7/22/2019 600 mw stator bar training report

    17/21

    H.V. Test:

    Each bar is tested momentary at high voltage increased graduallyto three times higher than rated voltage.

    This test is also known as insulation test because this test is

    performed to check the insulation of the bar.

    For 500 MW the working voltage of the bar is 64.5 KV & for 210

    MW the working voltage of the bar is 63 KV.

    In this test the bar which is already wrapped with aluminum is

    used.

    High voltage is applied to the bar using auto-transformer and it is

    increased in steps according to the working voltage of thegenerator. If the insulation is weak the bar will puncture at the

    place of weaker insulation.

    If any of the bar fails this test i.e. bar is punctured at any point

    then the bar is sent back for re-insulation and all the processesare repeated again

  • 7/22/2019 600 mw stator bar training report

    18/21

    2-Pole machine with the following features:

    Direct cooling of stator winding with water.

    Direct hydrogen cooling for rotor.

    Micalastic insulation system.Spring mounted core housing for effective transmission of

    vibrations.

    Brushless Excitation system.

    Vertical hydrogen coolers

    500 MW Turbo generators at a glance

  • 7/22/2019 600 mw stator bar training report

    19/21

    Important dimensions & weights:

    Heaviest lift of generator stator : 255 Tons

    Rotor weight : 68 TonsOverall stator dimensions [L*B*H] : 8.83m*4.lm*4.02m

    Rotor dimensions(Dia. and length) : 1.15m and 12.11m

    Total weight of turbo generator : 428 Tons

    Salient techn ical data:

    Rated output: 588 MVA , 500 MWTerminal voltage: 21 KV

    Rated stator current: 16 KA

    Rated frequency: 50 Hz

    Rated power factor: 0.85 LagEfficiency: 98.55%

  • 7/22/2019 600 mw stator bar training report

    20/21

    Picture Of Bars

  • 7/22/2019 600 mw stator bar training report

    21/21

    THANK YOU