31402036 Dec 09

  • Upload
    cnghia

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 31402036 Dec 09

    1/58

    PETRONAS TECHNICAL STANDARDS

    DESIGN AND ENGINEERING PRACTICE

    TECHNICAL SPECIFICATION

    WELDABLE MARTENSITIC STAINLESS STEELLINE PIPE FOR USE IN OIL AND GAS OPERATIONS(AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC)

    PTS 31.40.20.36

    DECEMBER 2009

    2010 PETROLIAM NASIONAL BERHAD (PETRONAS)All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic,

    mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

  • 8/13/2019 31402036 Dec 09

    2/58

  • 8/13/2019 31402036 Dec 09

    3/58

    Revision History

    Rev No. Reviewed by Approved by Date

    1 Noor Syamiza Abdul MalikSyahrizad Mohd Yunus

    Abu Bakar Mohd Arif

  • 8/13/2019 31402036 Dec 09

    4/58

    PREFACE

    PETRONAS Technical Standards (PTS) publications reflect the views, at the time of

    publication, of PETRONAS OPUs/Divisions.

    They are based on the experience acquired during the involvement with the design,

    construction, operation and maintenance of processing units and facilities. Where

    appropriate they are based on, or reference is made to, national and international standards

    and codes of practice.

    The objective is to set the recommended standard for good technical practice to be applied

    by PETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants,

    chemical plants, marketing facilities or any other such facility, and thereby to achieve

    maximum technical and economic benefit from standardisation.

    The information set forth in these publications is provided to users for their consideration

    and decision to implement. This is of particular importance where PTS may not cover every

    requirement or diversity of condition at each locality. The system of PTS is expected to besufficiently flexible to allow individual operating units to adapt the information set forth in

    PTS to their own environment and requirements.

    When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for

    the quality of work and the attainment of the required design and engineering standards. In

    particular, for those requirements not specifically covered, the Principal will expect them to

    follow those design and engineering practices which will achieve the same level of integrity

    as reflected in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without

    detracting from his own responsibility, consult the Principal or its technical advisor.

    The right to use PTS rests with three categories of users :

    1) PETRONAS and its affiliates.

    2) Other parties who are authorised to use PTS subject to appropriate contractual

    arrangements.

    3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with

    users referred to under 1) and 2) which requires that tenders for projects,

    materials supplied or - generally - work performed on behalf of the said users

    comply with the relevant standards.

    Subject to any particular terms and conditions as may be set forth in specific agreements

    with users, PETRONAS disclaims any liability of whatsoever nature for any damage (including

    injury or death) suffered by any company or person whomsoever as a result of or inconnection with the use, application or implementation of any PTS, combination of PTS or

    any part thereof. The benefit of this disclaimer shall inure in all respects to PETRONAS

    and/or any company affiliated to PETRONAS that may issue PTS or require the use of PTS.

    Without prejudice to any specific terms in respect of confidentiality under relevant

    contractual arrangements, PTS shall not, without the prior written consent of PETRONAS, be

    disclosed by users to any company or person whomsoever and the PTS shall be used

    exclusively for the purpose they have been provided to the user. They shall be returned after

    use, including any copies which shall only be made by users with the express prior written

    consent of PETRONAS. The copyright of PTS vests in PETRONAS. Users shall arrange for PTS

    to be held in safe custody and PETRONAS may at any time require information satisfactoryto PETRONAS in order to ascertain how users implement this requirement.

  • 8/13/2019 31402036 Dec 09

    5/58

    TABLE OF CONTENTS

    PART I INTRODUCTION

    1.1 SCOPE

    1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS

    1.3 DEFINITIONS

    1.4 ABBREVIATIONS

    1.5 CROSS-REFERENCES

    1.6 ITEMS TO BE SPECIFIED/AGREED BY THE PRINCIPAL

    PART II AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC

    1. SCOPE

    1.1 COVERAGE

    1.2 METRIC UNITS

    1.3 MEASURING DEVICES

    1.4 SPECIAL PROCESSES

    1.5 CERTIFICATION

    1.6 QUALITY SYSTEM

    2. REFERENCED STANDARDS

    2.1 GENERAL

    2.3 EQUIVALENT STANDARDS

    3. DEFINITIONS AND TERMS

    3.1 HEAT

    3.4 INSPECTION LOT

    3.5 INSPECTION LOT SIZE

    4. MISCELLANEOUS - RETENTION OF RECORDS

    5. PROCESS OF MANUFACTURE AND MATERIAL

    5.1 PROCESS OF MANUFACTURE

    5.2 COLD EXPANSION

    5.3 HEAT TREATMENT

    5.4 TRACEABILITY

  • 8/13/2019 31402036 Dec 09

    6/58

    6. CHEMICAL PROPERTIES AND TESTS

    6.1 COMPOSITION

    6.2 HEAT ANALYSES

    6.3 PRODUCT ANALYSES

    6.6 CHEMICAL ANALYSES PROCEDURE

    7. MECHANICAL PROPERTIES AND TESTS

    7.1 MECHANICAL PROPERTIES

    7.2 TENSILE TESTS - GENERAL

    7.3 TENSILE TESTING

    7.4 LONGITUDINAL TENSILE TESTS

    7.5 TRANSVERSE TENSILE TESTS

    7.6 WELD TENSILE TESTS

    7.13 FLATTENING TESTS

    7.15 GUIDED-BEND TEST

    7.17 WELD DUCTILITY TEST FOR ELECTRIC-WELDED PIPE

    7.19 CENTRIFUGALLY-CAST HOMOGENEITY TEST

    7.20 HARDNESS TESTS

    7.21 RETESTS (HARDNESS)

    7.22 CHARPY IMPACT TESTING

    7.23 CHARPY RETESTS

    8. SPECIAL TESTS

    8.1 CTOD TESTING

    8.2 RESIDUAL MAGNETISM

    9. HYDROSTATIC TESTS

    9.1 INSPECTION HYDROSTATIC TEST

    9.3 TEST PRESSURES

    9.4 SUPPLEMENTARY HYDROSTATIC TESTS

    10. DIMENSIONS, WEIGHTS, AND LENGTHS

    10.1 DIMENSIONS AND WEIGHTS

    10.2 DIAMETER

  • 8/13/2019 31402036 Dec 09

    7/58

    10.3 WALL THICKNESS

    10.5 LENGTH

    10.7 JOINTERS

    10.8 PIPE ENDS

    11. NON-DESTRUCTIVE INSPECTION

    11.1 INSPECTION METHODS FOR WELDED PIPE

    11.2 INSPECTION METHODS FOR SEAMLESS PIPE

    11.3 INSPECTION METHODS FOR CENTRIFUGALLY-CAST PIPE

    11.4 RADIOLOGICAL INSPECTION EQUIPMENT

    11.5 FLUOROSCOPIC OPERATOR QUALIFICATION

    11.6 OPERATOR CERTIFICATION

    11.7 REFERENCE STANDARD

    11.8 ISO WIRE PENETRAMETER

    11.9 FREQUENCY

    11.10 PROCEDURE FOR EVALUATING IN-MOTION OPERATION OF THE FLUOROSCOPE

    11.11 ACCEPTANCE LIMITS

    11.12 IMPERFECTIONS

    11.13 DEFECTS

    11.14 WELD REPAIR

    11.15 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF WELDED PIPE

    11.16 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF SEAMLESS PIPE

    11.17 ULTRASONIC INSPECTION OF CENTRIFUGALLY-CAST PIPE

    11.18 TESTING OF BEVEL FACES

    11.19 NDT PERSONNEL QUALIFICATION

    12. WORKMANSHIP, VISUAL INSPECTION, AND REPAIR OF DEFECTS

    12.2 PURCHASER INSPECTION

    12.4 VISUAL INSPECTION

    12.5 DEFECTS

    12.6 REPAIR OF DEFECTS

    12.7 PROCEDURE FOR REPAIR OF WELD SEAMS OF SUBMERGED-ARC WELDED PIPE

  • 8/13/2019 31402036 Dec 09

    8/58

    12.8 PROCEDURE FOR REPAIR OF WELD SEAMS OF ELECTRIC-WELDED AND INDUCTION-

    WELDED PIPE

    12.9 PROCEDURE FOR REPAIR OF WELD SEAM OF GAS METAL-ARC WELDED PIPE

    12.10 GAUGE PIG

    13. MARKING AND SURFACE TREATMENT

    13.1 MARKING - GENERAL

    13.2 LOCATION OF MARKINGS

    13.3 SEQUENCE OF MARKINGS

    13.5 DIE STAMPING

    13.6 SURFACE TREATMENT

    14. STORAGE, HANDLING, AND PACKING

    14.1 HANDLING

    14.2 STORAGE

    14.3 PACKAGING

    14.4 TRANSPORTATION

    15. DOCUMENTATION

    15.1 LANGUAGE

    15.2 PRE-MANUFACTURING DOCUMENTATION

    15.3 SHIPPING DOCUMENTATION

    16. FIRST-DAY-PRODUCTION TESTS

    16.1 GENERAL

    16.2 NON-DESTRUCTIVE TESTING

    16.3 CHEMICAL COMPOSITION

    16.4 MECHANICAL TESTING

    16.5 SPECIAL TESTS

    APPENDIX A REPAIR WELDING PROCEDURE

    A.1 GENERAL

    A.2 REPAIR WELDING PROCEDURE QUALIFICATION

    APPENDIX F PURCHASER INSPECTION

    PART III REFERENC

  • 8/13/2019 31402036 Dec 09

    9/58

    PART I INTRODUCTION

    1.1 SCOPE

    This new PTS specifies requirements and gives recommendations for the purchase of

    both seam-welded and seamless weldable martensitic stainless steel (known

    generically as weldable 13Cr and weldable Super 13Cr) line pipe for use in oil and

    gas operations. The requirements are considered necessary to maintain technical

    integrity of pipelines and to ensure that a suitable specification exists in the absence

    of standardised grades of these materials.

    NOTE: This PTS applies under non-sour conditions. The PETRONAS definition of sour service is given in PTS

    31.22.20.31, however, as the application limits of these materials have not yet been determined, qualification

    testing in project-specific environments may be required even when the expected H2S is

    insufficient to give a sour service definition.

    Part II of this PTS gives amendments and supplements to API Spec 5LC Third EditionJuly 1998 (Reaffirm 2006) and shall be read and used in conjunction with that

    document. The section numbering in Part II follows that of API Spec 5LC. Where

    sections of API Spec 5LC are not amended or supplemented by this PTS, they shall

    apply as written.

    NOTE: Both API Spec 5LC and this PTS adopt sampling as a method to determine batch compliance.

    Nevertheless, all pipes supplied shall meet all requirements of this PTS.

    1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS

    Unless otherwise authorised by PETRONAS, the distribution of this PTS is confined tocompanies forming part of the PETRONAS Group or managed by a Group company,

    and to Contractors and Manufacturers/Suppliers nominated by them.

    This PTS is intended to be used for the purchase of line pipe for the construction of

    oil and gas production flowlines and related facilities.

    If national and/or local regulations exist in which some of the requirements may be

    more stringent than in this PTS, the Contractor shall determine by careful scrutiny

    which of the requirements are the more stringent and which combination of

    requirements will be acceptable as regards safety, environmental, economic and

    legal aspects. In all cases the Contractor shall inform the Principal of any deviation

    from the requirements of this PTS which is considered to be necessary in order to

    comply with national and/or local regulations. The Principal may then negotiate with

    the Authorities concerned with the object of obtaining agreement to follow this PTS

    as closely as possible.

  • 8/13/2019 31402036 Dec 09

    10/58

    1.3 DEFINITIONS

    1.3.1 General definitions

    The Contractor is the party, which carries out all or part of the design, engineering,

    procurement, construction, commissioning or management of a project, or operation ormaintenance of a facility. The Principal may undertake all or part of the duties of the

    Contractor.

    The Manufacturer/Supplier is the party, which manufactures or supplies equipment and

    services to perform the duties specified by the Contractor.

    The Principalis the party, which initiates the project and ultimately pays for its design and

    construction. The Principal will generally specify the technical requirements. The Principal

    may also include an agent or consultant authorised to act for, and on behalf of, the Principal.

    The word shall indicates a requirement.

    The word shouldindicates a recommendation.

    1.3.2 Specific definitions

    Defect (in NDT) A discontinuity or group of discontinuities whose indication(s)

    do not meet specified acceptance criteria.

    Electric welded Term used in API 5LC, which shall be understood to mean HFW.

    Imperfection (in NDT) An interruption, which may be either intentional or

    unintentional, in the physical structure or configuration of a

    pipe.

    Indication (in NDT) Evidence of an imperfection that requires interpretation to

    determine its significance.

    Pipe end Complete pipe segment of 100 mm length measured from the

    end face of the finished pipe.

    Plate or strip The flat starting material for welded pipe before forming into

    the shape of a pipe.

    Purchaser Term used in API Spec 5LC, which has the same meaning as

    Principal.

    Qualified Manufacturer A Manufacturer whose product has been previously

    demonstrated to be suitable for the intended service, and

    formally accepted by the Principal.

    Radiological Term used in API Spec 5LC which has the same meaning asradiographic. The term radiographic is used in this PTS.

  • 8/13/2019 31402036 Dec 09

    11/58

    1.4 ABBREVIATIONS

    CTOD -Crack Tip Opening Displacement

    DN -Nominal Diameter

    FL -Fusion Line

    GTAW -Gas Tungsten Arc Welding

    HAZ -Heat Affected Zone

    HFW -High Frequency Welded

    ID -Internal Diameter

    KV -Charpy V-notch impact energy

    LBW -Laser Beam Welded

    MT -Magnetic particle testing

    NDT -Non-destructive testing

    OD -Outside Diameter

    PAW -Plasma Arc Welded

    PT -Liquid penetrant testing

    RT -Radiographic Testing

    SAW -Submerged Arc Welding

    SMAW -Shielded Metal Arc Welding

    UT -Ultrasonic Testing WCL -Weld Centreline

    WPS -Welding Procedure Specification

    1.5 CROSS-REFERENCES

    Where cross-references to other parts of this PTS are made, the referenced section

    is shown in brackets. Other documents referenced by this PTS are listed in (Part III).

  • 8/13/2019 31402036 Dec 09

    12/58

    1.6 ITEMS TO BE SPECIFIED/AGREED BY THE PRINCIPAL

    The following information should be provided by the Principal at the enquiry stage

    of the order:

    -Nominal ID (and whether constant ID is required);

    -Minimum design temperature; -Maximum design temperature;

    - Design pressure;

    -Service environment (gas, oil, water, multiphase, sour, non-sour);

    -End preparation required if different from the standard API bevel;

    -Whether pipe is to be used as mother pipe for induction bends;

    -Whether mechanical property restrictions for reeling are to be applied;

    -Whether elevated temperature tensile testing is required and the acceptance

    criteria;

    -Requirement for mechanical tests in simulated post-weld heat-treated condition;

    -Length requirements if different from (Part II - 10.5) of this PTS;

    -Whether supply of jointers is acceptable and the welding requirements if different

    from this PTS;

    -Whether the passage of a gauge pig is necessary; -Which of the

    Manufacturer/Suppliers quality control procedures are to be submitted for

    agreement;

    -Time period for submission of contract quality plan;

    -Level of inspection to be deployed by the Principal;

    -Whether inspection reports in accordance with ISO 10474 type 3.2 are required

    instead of inspection certificates in accordance with ISO 10474 type 3.1.B;

    -Specific marking requirements;

    -Specific packaging requirements;

    -Other specific requirements amending or supplementing this PTS.

  • 8/13/2019 31402036 Dec 09

    13/58

    PART II AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC

    1. SCOPE

    1.1 COVERAGE

    Delete this section and replace with the following:

    This specification covers the supply of proprietary grades of welded and seamless

    martensitic stainless steel line pipe by qualified Manufacturers/Suppliers. The

    primary product is bevelled pipe having a standard API bevel. Should a different end

    finish be required, it shall be clearly stated by the Principal in the contract document.

    Manufacturers/Suppliers should have satisfactorily qualified their products in

    accordance with the upstream qualification requirements detailed in report SIEP 97-

    5763. Alternative data may also be considered by the Principal for qualifying a

    Manufacturer/Supplier.

    1.2 METRIC UNITS

    Replace first paragraph with the following:

    Metric units are used throughout this specification.

    1.3 MEASURING DEVICES

    Delete this section and replace with the following:

    The Manufacturer/Supplier shall control measuring devices within the requirements

    of ISO 10012-1.

    1.4 SPECIAL PROCESSES

    Delete the part of the table pertaining to centrifugally-cast pipe. Delete reference to

    repair welding procedures and add the following text:

    Applicable special processes shall also include those identified and documented in

    the quality assurance system of the Manufacturer/Supplier. Procedures for all special

    processes shall be produced by the Manufacturer/Supplier and supplied to the

    Principal (see Part IISection 15) when requested.

    1.5 CERTIFICATION

    Delete this section and replace with the following:

    Inspection certificates in accordance with ISO 10474 type 3.1.B shall be supplied

    unless the Principal specifies inspection reports in accordance with ISO 10474 type

    3.2., in which case the Manufacturer/Supplier shall issue and validate the inspection

    reports and they shall be counter-validated by the Principals authorised

    representative. The Manufacturer/Supplier shall provide a listing of all pipes supplied

    detailing for each pipe the unique pipe number, heat number, test number,

  • 8/13/2019 31402036 Dec 09

    14/58

    certificate number, length and weight. These data shall also be supplied to the

    Principal on a computer disc in an agreed format.

    Add new section:

    1.6 QUALITY SYSTEM

    The Manufacturer/Supplier should maintain and operate a quality management

    system in accordance with ISO 9001 or ISO 9002 or an alternative standard if

    approved by the Principal.

    The quality assurance system shall employ statistical process control and have

    documented procedures for its application.

  • 8/13/2019 31402036 Dec 09

    15/58

    2. REFERENCED STANDARDS

    2.1 GENERAL

    Add the following: See also (Part III) of this PTS.

    2.3 EQUIVALENT STANDARDS

    Delete this section.

  • 8/13/2019 31402036 Dec 09

    16/58

    3. DEFINITIONS AND TERMS

    3.1 HEAT

    Add to the existing section:

    Where the size of the secondary refining vessel is less than that of the primary steel

    producing vessel, the heat shall be considered to be the metal produced by a single

    cycle of the secondary refining vessel.

    3.4 INSPECTION LOT

    Delete this section and replace with the following: A unit of pipes from the same heat

    and, for batch heat treatment, heat treatment batch,

    having the same dimensions.

    3.5 INSPECTION LOT SIZE

    Delete this section and replace with the following: For pipes with OD < 508 mm, the

    maximum lot size shall be 100 pipes. For other sizes, the maximum lot size shall be

    50 pipes.

  • 8/13/2019 31402036 Dec 09

    17/58

    4. MISCELLANEOUS - RETENTION OF RECORDS

    Amend the second sentence of the first paragraph as follows:

    Contract records, and any others requiring retention by the Manufacturer/Supplier's

    quality assurance system, shall be retained by the Manufacturer/Supplier and shallbe made available to the Principal upon request for a period of five years after

    completion of the order.

  • 8/13/2019 31402036 Dec 09

    18/58

    5. PROCESS OF MANUFACTURE AND MATERIAL

    PROCESS OF MANUFACTURE

    Delete the first paragraph and replace with the following: Pipe furnished to this

    specification shall be seamless or welded manufacture as defined below. Weldedpipe shall be welded using the processes described below. Combination welded pipe

    shall be subject to the limitations given in item 6.

    The manufacturing process shall be described in accordance with the requirements

    of (15.2.2) and the material produced by the process shall have been prequalified in

    accordance with SIEP 97-5763.

    Plates or strip shall be formed into pipe at ambient temperature.

    a. Seamless and Centrifugally-Cast.

    1. Seamless is defined as wrought tubular product made without a welded seam. It is

    manufactured by hot working steel or, if necessary, by subsequently cold finishing

    the hot worked product.

    b. Welded processes

    1. Without filler metal

    Place the existing text under a new sub-heading:

    a. High Frequency Welding

    The HFW process shall employ a minimum frequency of 150 kHz.

    b. Laser beam welding

    A welding process that produces coalescence with the heat from a laser beam

    focussed on the joint. The beam provide a concentrate heat source for narrow , deep

    welds and high welding rates.

    NOTE Some Manufacturer/Suppliers may use HFW equipment to provide preheating for the laser welding

    process.

    2. With filler metal

    Delete sub-section (b) relating to Gas Metal-Arc Welding.

    c. Pipe making processes

    2. Centrifugally cast

    Delete this sub-section.

  • 8/13/2019 31402036 Dec 09

    19/58

    4. Submerged-arc.

    Submerged-arc welded pipe is defined as having one longitudinal seam produced by

    the automatic submerged-arc welding process as defined in 5.1.b.2.a. At least one

    pass shall be deposited on the inside and one pass on the outside. The full length of

    the weld seam shall be made by the automatic submerged-arc process, using run-on

    and run-off tabs.

    6. Combination welding

    Delete or double and add the following to this section: Only PAW/GTAW

    combination welded joints are permitted by this specification.

    7.0 Double seam

    Double seam welded pipe is not permitted.

    Add new sub-section 8. as follows:

    8. Laser beam welding.

    Laser beam welded pipe is defined as having one longitudinal seam produced by the

    LBW process as defined in (5.1.b.1.b).

    d. Tack welding

    Add the following: Tack welding shall be continuous. Add new item as follows:.

    e. Jointer weld

    A jointer weld is a circumferential seam weld that joints two piece of pipes together

    f. Strip end weld

    A strip end weld is a weld that joins strip ends together thus permitting continuous

    longitudinal welding of the strip. Strip end welds shall not be included in the final

    pipe length.

    Table 2

    Delete this table.

  • 8/13/2019 31402036 Dec 09

    20/58

    5.2 COLD EXPANSION

    Delete this section and replace with the following:

    Where appropriate, welded pipe shall be subjected to cold mechanical expansion.

    Expansion shall be maintained between 0.8 % and 1.5 %.

    The % expansion is defined as follows:

    Da= OD (ID) after expansion

    Db= OD (ID) before expansion

    Sizing of seamless and welded pipe by cold reduction shall be limited to 1.5 %.

    5.3 HEAT TREATMENT

    Delete this section and replace with the following:

    All pipe shall be supplied in the quenched and tempered condition.

    The coiled strip and/or pipe shall be heat treated in accordance with the

    Manufacturer/Supplier's documented heat treatment procedure. Pipe temperatures

    shall be verified by recorded measurement and the measurements shall be included

    in the quality records.

    The coiling temperature shall be agreed between the Principal and the

    Manufacturer. The tolerance on the tempering soaking temperature shall be 15 C.

    5.4 TRACEABILITY

    Add the following:

    The Manufacturer/Supplier's procedure shall be documented and shall ensure that

    any length of pipe can be traced to the correct heat/lot and the associated

    inspection certificates. Each pipe shall be assigned a unique identification number,

    which shall either be stamped at both ends with low stress die stamps or stencilled

    onto the pipe as specified by the Principal.

    NOTE: Attention is drawn to clause 4 of ISO 10474 regarding supply of certificates by an intermediary processor.

  • 8/13/2019 31402036 Dec 09

    21/58

    6. CHEMICAL PROPERTIES AND TESTS

    6.1 COMPOSITION

    Delete this section and replace with the following:

    The composition of the pipe determined by heat and product analysis shall be in

    accordance with that specified by the Principal in the contract document. The

    Principal shall specify a composition previously qualified by the

    Manufacturer/Supplier in accordance with SIEP 97-5763. The primary elements,

    which shall be determined, are:

    C, Mn, P, S, Si, Ni, Cr, Mo, N, Cu, intentional additions.

    6.2 HEAT ANALYSES

    Delete first sentence and replace with the following:

    The Manufacturer/Supplier shall furnish a certificate giving the heat analysis for

    each heat of material applied to the order.

    6.3 PRODUCT ANALYSES

    Delete this section and replace with the following:

    Product analyses shall be provided to the Principal in the inspection document. The

    frequency shall be two pipes per heat. Samples shall be taken from formed pipe or

    tensile tests specimens extracted from formed pipe.

    In addition to the base metal chemical analyses, an analysis shall be performed on

    the weld metal of pipe welded with filler metal. This test shall be performed on the

    first-dayproduction test pipes and once every 100 pipes during production.

    The composition shall comply with that specified by the Principal in the contract

    document within the permissible variations in product analysis given in (Table 3).

  • 8/13/2019 31402036 Dec 09

    22/58

    Table 3

    Delete existing Table 3 and replace with the following:

    Table 3. Permissible variations for product analysis of 13 % Cr line pipe

    Element Permissible variation

    C 0.01

    Mn 0.04

    Si 0.05

    P 0.005

    S 0.005

    Cr 0.15

    Ni 0.10

    Mo 0.10

    N 0.03

    Other alloying elemens 0.02

    6.6 CHEMICAL ANALYSES PROCEDURES

    Methods of Analysis methods and practices relating to chemical analysis shall be

    performed in accordance with ASTM A751, Standard Methods, Practices and

    Definitions for Chemical Analysis of Steel Products .Calibrations performed shall be

    traceable to established standards.

  • 8/13/2019 31402036 Dec 09

    23/58

    7. MECHANICAL PROPERTIES AND TESTS

    7.1 MECHANICAL PROPERTIES

    Delete this section and replace with the following:

    The pipe material shall conform to the following mechanical property requirements

    at room temperature:

    Tensile requirements

    Yield

    strength

    (Rt0.5) range

    Tensile strength

    minimum

    MPa

    Elongation

    minimum

    %

    Yield-to-tensile

    ratio

    maximum

    550 - 700 700 20 0.90

    NOTE: Rt0.5is the yield strength for 0.5 % total elongation.

    7.2 TENSILE TESTS - GENERAL

    Add the following:

    Where guaranteed elevated-temperature properties are required, the Principal shall

    state the test temperature and the property requirements in the contract

    document. If post-weld heat treatment of field welds will be performed, additional

    specimens shall be tested in the simulated post-weld heat-treated condition. Theacceptance criteria shall be as specified in (7.1). The Principal shall indicate whether

    post-weld heat treatment is to be performed in the contract document. The

    Manufacturer/Supplier shall advise the Principal of the correct post-weld heat-

    treatment thermal cycle to maintain the required properties, including elevated-

    temperature properties, of the pipe material.

    7.3 TENSILE TESTING

    a. Frequency

    Delete this sub-section including Table 7, and replace with the following:

    One transverse and one longitudinal tensile test from each first-day-production test

    pipe and one pipe per lot shall be performed at room temperature.

    In addition, if elevated-temperature testing is specified by the Principal, one

    elevated-temperature transverse tensile test shall be performed on each first-day-

    production test pipe and on one pipe per lot.

  • 8/13/2019 31402036 Dec 09

    24/58

    7.4 LONGITUDINAL TENSILE TESTS

    Delete this section and replace with the following:

    Longitudinal tensile test specimens shall be either non-flattened strip or round bar.

    7.5 TRANSVERSE TENSILE TESTS

    Delete first paragraph and items a. and b. and replace with the following:

    Transverse tensile properties shall be determined by flattened strip specimen.

    Where pipe dimensions preclude the use of a strip specimen, round bar specimens

    may be used with the agreement of the Principal.

    7.6 WELD TENSILE TESTS

    Delete "as specified in Table 7" from the first sentence.

    Delete the second sentence and replace with the following:

    All weld reinforcement shall be removed.

    7.13 FLATTENING TESTS

    Add the following to the second paragraph: The acceptance criterion for the second

    stage flattening shall be no evidence of lamination or other imperfections.

    7.15 GUIDED-BEND TEST

    Amend the equation in Figure 5 as follows:

    7.17 WELD DUCTILITY TEST FOR ELECTRIC-WELDED PIPE

    Delete section from the start of the 4th sentence and replace as follows:

    No cracks or breaks shall occur in the weld or parent material during flattening of

    the test specimen to 50 % of its original OD. Liquid Penetrant or microscopic

    examination shall be used to confirm the absence of cracking. Cracks which originate

    from the edge of the specimen and which are less than 6 mm long shall not be cause

    for rejection. The test frequency shall be once per lot of pipes.

  • 8/13/2019 31402036 Dec 09

    25/58

    7.19 CENTRIFUGALLY-CAST HOMOGENEITY TEST

    Delete this section.

    7.20 HARDNESS TESTS

    Delete this section and replace with the following:

    7.20.1 Seamless pipe

    A full circumferential section shall be taken as a sample from each first-day-

    production test

    pipe and from one pipe representing each lot. Hardness measurements shall be

    performed in accordance with ISO6507-1 on three polished and etched specimens

    taken at 120o

    intervals around the circumference of the sample. Traverses shall be as

    shown in Figure 6 of API Spec 5LC.

    For pipe with wall thickness of 8 mm and greater, three hardness traverses shall be

    made on each specimen: 2 mm from the outer surface; mid-thickness; and 2 mm

    from the inner surface. Each traverse shall contain three readings spaced at 5 mm

    intervals. The average of each of the three readings shall be the hardness value. For

    pipe with wall thickness less than 8 mm only two traverses, each 2 mm from the

    surfaces shall be required.

    The acceptance criterion shall be a maximum hardness value of 325 HV10.

    7.20.2 Longitudinally welded pipe

    a. Macrographic examination

    Two full thickness transverse samples shall be extracted from the longitudinal weld

    from each first-day-production test pipe and from one pipe representing each lot.

    Test pieces from the samples shall be polished and etched for macro-examination in

    accordance with ASTM E 340. The examination shall be performed at a minimum

    magnification of x5. The acceptance criterion shall be no defects as defined by this

    PTS. Photomacrographs shall be included in the inspection documents.

    b. Hardness testing

    A series of Vickers HV10 hardness indentations shall be made in accordance with EN

    1043-1 on one of the test pieces prepared for macro-examination from each of the

    first-day-production test pipes and from one pipe representing each lot. The

    hardness indentation locations shall be agreed by the Principal. The indentations

    shall be visible in the photomacrographs.

    For pipe with wall thickness of 8 mm or greater, three traverses shall be made, one 2

    mm from the outer surface, the second across the centreline of the weld and the

    third 2 mm from the inner surface. The centreline traverse may be omitted for pipe

  • 8/13/2019 31402036 Dec 09

    26/58

    of wall thickness less than 8 mm. The indentations shall be visible in the

    photomacrographs. No individual hardness value shall exceed the following:

    Base material 325 HV10 Weld metal and HAZ 350 HV10.

    Add new section:

    7.21 RETESTS (HARDNESS)

    Should a maximum of one hardness value per pipe exceed 325 HV10, a further three

    indents shall be made in the proximity of the original indents so that there is no

    interference between them. All three extra readings shall have a hardness value less

    than 325 HV10. Should any of these extra readings exceed 325 HV10 then a further

    test ring shall be cropped from the pipe for hardness testing and, in addition, two

    further pipes from the heat shall be hardness-tested. Should any of these further

    readings exceed 325 HV10, then the heat shall be rejected or all individual pipes

    shall be tested for acceptance.

    Add new section:

    7.22 CHARPY IMPACT TESTING

    One pipe per lot shall be subjected to Charpy impact testing in accordance with ISO

    148-2. Both absorbed energy and percentage shear area shall be measured. The test

    specimens may be extracted from the test rings taken for tensile and hardness

    testing. If stress relieving of the pipe is required by the Principal, the tests shall also

    be performed on pipe in the stress-relieved condition.

    Tests shall be performed on specimens taken from the mid-thickness position at the

    locations shown in the following table:

    Pipe type Location

    Base

    meta

    WCL FL FL+2 FL+5

    Seamless X

    SAW X X X X X

    HFW (1) X X X

    PAW &

    GTAW

    X X X X

    LBW (1) X X X

  • 8/13/2019 31402036 Dec 09

    27/58

    (1) For HFW and LBW pipe, the FL+2 tests may be replaced by tests taken from the WCL+2 position

    A set of three specimens from each pipe shall be tested at the following test

    temperature:

    Nominal Pipe WallThickness t Test TemperatureoCMax TestTemperature

    t < 16 T 0

    16 < t < 25 T-10 0

    25 < t < 32 T-20 0

    t > 32 T-30 0

    If T is not specified by the Principal in the contract document, the test temperature

    shall be taken as 0 C.

    The descending hierarchy of specimen size and orientation shall be as follows:

    Choice Orientation Size mm1 Transverse 10 x 10

    2 Transverse 10 x 7.5

    3 Transverse 10 x 5

    4 Longitudinal 10 x 10

    5 Longitudinal 10 x 7.5

    6 Longitudinal 10 x 5

    Lower choice specimens shall only be used when the higher choice is impractical.

    For pipe of wall thickness less than 5 mm, Charpy testing may be omitted.

    The acceptance criteria for the different specimen sizes and orientations shall be as

    follows:

    Size

    mm

    Orientation Min. average

    absorbed energyJ

    Min. individual

    absorbed energyJ

    10 x 10 Transverse 60 45

    10 x 7.5 Transverse 48 36

    10 x 5 Transverse 33 25

    10 x 10 Longitudinal 90 68

    10 x 7.5 Longitudinal 72 54

    10 x 5 Longitudinal 50 38

  • 8/13/2019 31402036 Dec 09

    28/58

    The individual minimum shear area for base metal shall be 100 %. For weld metal

    and HAZ specimens, the individual minimum shear area shall be 50 %.

    Add new section:

    7.23 CHARPY RETESTS

    If tests fail to meet the specified requirements, the sampled pipe shall be rejected.

    Two further pipes from the lot shall then be tested. If the results of both of these

    further tests are satisfactory no further testing is required and the lot shall be

    accepted. Should one or both pipes be unsatisfactory, the lot of pipes shall be

    rejected.

  • 8/13/2019 31402036 Dec 09

    29/58

    8. SPECIAL TESTS

    Delete this section and replace with the following:

    8.1 CTOD TESTING

    If the pipe wall thickness exceeds 12.5 mm, CTOD testing shall be performed on the

    three pipes selected for first-day-production tests. The test method shall be in

    accordance with BS 7448 Parts 1 and 2. Rectangular Bx2B specimens shall be used

    where B shall be as close to the full wall thickness as possible allowing for machining

    requirements. The specimen orientation shall be NP. One set of three test pieces

    shall be cut from each pipe with the notches placed at the weld centreline. A further

    set of three specimens shall be cut with the notch placed in unaffected base

    material.

    If the pipe diameter prevents the extraction of 10 mm thick specimens, the

    requirement for CTOD testing shall be waived.

    The test temperature shall be T or 0 C whichever is lower. The acceptance criterion

    shall be a minimum CTOD value of 0.15 mm.

    8.2 RESIDUAL MAGNETISM

    Three pipes per heat shall be tested for residual magnetism in their final delivery

    condition. The maximum value of residual magnetism shall be 20 Gauss. Where the

    residual magnetism of any sampled pipe exceeds 20 Gauss, the pipe shall be

    subjected to degaussing operations and all remaining pipes from the heat shall thenbe checked and degaussed as necessary. The results of residual magnetism checks

    shall be recorded and included as part of the inspection documentation.

  • 8/13/2019 31402036 Dec 09

    30/58

    9. HYDROSTATIC TESTS

    9.1 INSPECTION HYDROSTATIC TEST

    Delete this section and replace with the following:

    Each length of pipe shall withstand, without leakage, an inspection hydrostatic test

    to at least the pressure specified in (9.3). The test pressure shall be held for a

    minimum of 15 seconds for all pipes. For all pipes, hydrostatic testing shall take

    place after sizing operations and final heat treatment. For welded pipe, hydrostatic

    testing shall be performed before non-destructive testing.

    The water used for hydrostatic testing shall have a maximum chloride ion

    concentration of 50 ppm. The Manufacturer/Supplier shall include the details of

    monitoring and control of hydrotest water in a documented hydrotest procedure.

    9.3 TEST PRESSURES

    Delete this section and replace with the following:

    The test pressure for all sizes of pipe shall be such that the hoop stress calculated on

    the basis of the minimum allowable wall thickness and including stresses from end

    loading is at least 95 % of the specified minimum yield strength at room

    temperature.

    The Manufacturer/Supplier shall define the end load compensation factor in the

    hydrotest procedure.

    9.4 SUPPLEMENTARY HYDROSTATIC TESTS

    Delete this section.

  • 8/13/2019 31402036 Dec 09

    31/58

    10. DIMENSIONS, WEIGHTS, AND LENGTHS

    10.1 DIMENSIONS AND WEIGHTS

    Modify Note 2 as follows: The Manufacturer/Supplier shall state the plain-end

    weight correction factor in the weighing procedure.

    Add the following:

    Dimensional and weight inspection shall be performed on pipes after all other

    operations have been performed.

    10.2 DIAMETER

    Delete this section and replace with the following: The diameter of the pipe shall be

    within the tolerances specified in Table 9 as amended below.

    Table 9 TOLERANCES ON DIMENSIONS AND WEIGHTS

    Outside Diameter D

    Pipe body

    Delete the existing text and replace with the following:

    For welded pipe, the outside diameter of the pipe body, as determined by taping the

    circumference, shall not deviate by more than 0.75 % or 3 mm, whichever is less,

    from the value given in Metric Table C-1 in Appendix C. For seamless pipe, the OD

    tolerance shall be 3 mm.

    Pipe ends

    Delete the existing text and replace with the following:

    For welded pipe of diameter greater than DN 200 (8 inch), the average internal

    diameter shall not deviate from the nominal internal diameter by more than 0.5 %

    or 2.0 mm, whichever is less. For seamless pipe, the tolerance on average ID shall be

    2.0 mm.

    The nominal internal diameter is defined as the outside diameter D, given in Metric

    Table C-1, minus twice the nominal wall thickness.

    The internal diameter shall be measured using an internal gauge or a measuring

    tape inside the pipe.

    For pipe of DN 200 (8 inch) and below, the diameter tolerance may apply to the

    outside diameter.

  • 8/13/2019 31402036 Dec 09

    32/58

    Out-of-roundness

    Delete the existing text and replace with the following:

    The ends of each pipe shall be tested for out-of-roundness using an internal ring

    gauge of diameter 4.0 mm less than the nominal internal diameter. The gauge shallpass freely into each end of the pipe for a distance of 100 mm when held normal to

    the pipe axis.

    Out-of-roundness of the pipe body shall be determined from measurement of the

    maximum and minimum OD at the same pipe cross-section. The acceptance

    criterion shall be:

    ODmax- ODmin < 3 mm

    Add the following to Table 9:

    Local irregularity of seam welds

    The pipe ends and three positions equidistant along the pipe length shall be checked

    for non-circularity at the position of the longitudinal weld using a template gauge to

    be agreed with the Principal. The chord length of the template shall be a minimum

    of 25 % of the OD or ID as applicable, up to a maximum of 300 mm.

    At the pipe ends, the gauge shall be located internally. The local irregularity in

    profile shall not exceed 1.5 mm measured between the gauge and the pipe.

    10.3 WALL THICKNESS

    Delete the second sentence and replace with the following: The tolerance on the

    nominal wall thickness shall be: Seamless pipe -10 % +15 % Welded pipe -5 % +10 %

    10.5 LENGTH

    Delete this section and Table 10 and replace with the following:

    Onshore lines: 95 % of shipped pipes for the order shall be between 11 and 12.2 m

    long.

    No pipe shall be shorter than 8 m.

    No pipe shall be longer than 12.5 m.

    Offshore lines: The average length of shipped pipes for the order shall be 12.2 m.

    95 % of shipped pipes shall be between 11.9 and 12.5 m long.

    No pipe shall be shorter than 11.6 m.

    No pipe shall be longer than 12.8 m.

  • 8/13/2019 31402036 Dec 09

    33/58

    10.7 JOINTERS

    Delete first two sentences and replace with the following: Jointers shall only be

    supplied when specified by the Principal.

    10.8 PIPE ENDS

    Add to this section:

    The pipe shall be supplied with pipe ends cut perpendicular to the pipe axis. The

    maximum deviation from the perpendicular shall be 0.5 % of the nominal outside

    diameter, with a maximum of 1.5 mm. The entire end bevel shall be machined and

    root faces shall not be brought into tolerance by filing and/or grinding.

  • 8/13/2019 31402036 Dec 09

    34/58

    11. NON-DESTRUCTIVE INSPECTION

    11.1 INSPECTION METHODS FOR WELDED PIPE

    Add the following to the first paragraph:

    Non-destructive inspection for acceptance purposes shall be performed after

    hydrostatic testing of the pipe.

    Delete items a. and b. and replace with the following:

    Welded pipe shall be inspected full length in accordance with the standards

    nominated in (Table A). Where the system leaves untested portions at the pipe

    ends, these portions shall be subjected to a manual or semi-automatic UT

    examination based on the same technique, test sensitivity, and test parameters as

    used for the main test. For manual scanning, the scan speed shall not exceed 100

    mm/s.

    For HFW and LBW pipe, the shear wave probe angle shall be 45 3 and the

    number and arrangement of probes shall be in accordance with the following:

  • 8/13/2019 31402036 Dec 09

    35/58

    Wall

    thickness

    range

    mm

    Number of probes for zone of weld

    (at both sides of the longitudinal weld)

    inner zone mid portion outer zone

    11.9 one none One

    12.0 to

    17.9

    one one pair in

    tandem centered

    at midwall position

    One

    18.0 to

    23.9

    one two pairs in

    tandem centered

    at 40 % and 60 %

    of thickness

    one

    mode of

    operation

    pulse echo tandem pulse echo

    reference

    reflector

    N10 notch 3.0 mm

    flat bottom hole

    N10 notch

    For SAW pipe, the number and arrangement of probes shall be in accordance with the

    following:

    Wall

    thickness

    rangemm

    Number of probes for zone of weld

    (at both sides of the longitudinal weld)

    inner zone mid portion outer zone

    11.9 one none one

    12.0 to

    17.9

    one one centered at

    midwall position

    one

    18.0 to

    23.9

    one two centered at

    40 % and 60 % of

    thickness

    one

    24.0 to29.9

    onethree centred at30 %, 50 %, and

    70 % of thickness

    mode of

    operation

    pulse echo pulse echo

    (NOTE 1)

    pulse echo

    reference

    reflector

    N10 notch 3.0 mm flat

    bottom hole

    N10 notch

    NOTE 1: The angle of the mid portion probes shall be perpendicular to the weld bevel with a tolerance of 3.

    Where the weld bevel is less than 15 (half aperture), the probes shall be used in the tandem arrangement. For

    these steep angles, the probe angle shall be 45 3. Probe angle requirements are also shown in the standardslisted in Table

  • 8/13/2019 31402036 Dec 09

    36/58

    11.2 INSPECTION METHODS FOR SEAMLESS PIPE

    Delete this section and replace with the following:

    Seamless pipe shall be inspected full length in accordance with the standards

    nominated in (Table A).

    Where the system leaves untested portions at the pipe ends, these portions shall be

    subjected to a manual or semi-automatic UT examination based on the same

    technique, test sensitivity, and test parameters as used for the main test. For

    manual scanning, the scan speed shall not exceed 100 mm/s.

    11.3 INSPECTION METHODS FOR CENTRIFUGALLY-CAST PIPE

    Delete this section.

    11.4 RADIOLOGICAL INSPECTION EQUIPMENT

    Delete this section and replace with the following:

    Radiographic testing of welds shall be performed with X-ray equipment using fine-

    grain type film and lead intensifying screens. The radiographic technique shall be in

    accordance with ISO 12096. The image quality class shall be R1.

  • 8/13/2019 31402036 Dec 09

    37/58

    11.5 FLUOROSCOPIC OPERATOR QUALIFICATION

    Delete this section.

    Table AStandards for non-destructive inspection

    Non-destructive inspection Specification Cross-

    reference

    Notes

    All pipe

    Ultrasonic testing for laminar

    imperfections at pipe ends

    ISO 11496 (11.15)

    Magnetic Particle or Liquid

    Penetrant testing of bevel faces

    ISO 13664 or

    ISO 12095

    (11.18)

    Seamless pipe

    Ultrasonic testing for longitudinal

    imperfections

    ISO 9303 (11.15) &

    (11.16)

    Ultrasonic testing for transverse

    imperfections

    ISO 9305 (11.15) &

    (11.16)

    Ultrasonic testing of wall thickness ISO 10543 (11.15) &

    (11.16)

    Ultrasonic testing for laminar

    imperfections in the pipe body

    ISO 10124 (11.15) &

    (11.16)

    Welded pipe (except HFW)

    Ultrasonic testing for longitudinal and

    transverse imperfections in the weld seam

    ISO 9765 (11.15) 1.4

    Ultrasonic testing for laminar

    imperfections in the pipe body

    ISO 12094 (11.15) 2.5

    Ultrasonic testing for laminar

    imperfections in the plate/strip

    edges adjacent to the weld

    ISO 13663 (11.15) 3.5

    Testing of the weld seam at pipe ends

    not covered by automatic testing: manual

    UT or RT

    ISO 9765 or ISO

    12096

    (11.15) or

    (11.4) and

    (11.11)

    HFW pipe

    Ultrasonic testing for longitudinal

    imperfections in the weld seam

    ISO 9303 or ISO

    9764

    (11.15)

    Ultrasonic testing for laminar

    imperfections in the pipe body

    ISO 12094 (11.15) 2

    Ultrasonic testing for laminar

    imperfections in the plate/strip

    edges adjacent to the weld

    ISO 13663 (11.15) 3

    Ultrasonic testing for longitudinal

    imperfections in the pipe body

    ISO 9303 (11.15)

  • 8/13/2019 31402036 Dec 09

    38/58

    NOTES: 1. Full length RT of the weld seam in accordance with this PTS may be substituted.

    2. The test may be performed on the plate/strip body prior to forming into pipe with a minimum

    coverage of 25 %.

    3. The test may be performed on the plate/strip edges in accordance with ISO 12094 prior to forminginto pipe.

    4. Angle beam shear wave as follows: for longitudinal defect detection 50 to 70o

    ; for transverse defect

    detection, X or K transmission, one pair of 50 to 70o

    probes up to 11.9 mm thickness, two pairs of probes

    for greater wall thickness. For on-bead scanning, the probe angle shall be 45 3o

    .

    5. Using a twin crystal probe with a focal length of between 25 % and 75 % of the thickness. The dead

    zone shall be less than 25 % of the thickness at operational amplification.

    11.6 OPERATOR CERTIFICATION

    Delete this section.

    11.7 REFERENCE STANDARD

    Delete this section and replace with the following:

    The reference standard shall be a wire penetrameter in accordance with ISO 1027.

    11.8 ISO WIRE PENETRAMETER

    Delete this section and replace with the following:

    The penetrameter shall be selected in accordance with the requirements of ISO

    12096

    Table 1. Image class R1.

    11.9 FREQUENCY

    Delete this section.

    11.10 PROCEDURE FOR EVALUATING IN-MOTION OPERATION OF THE FLUOROSCOPE

    Delete this section.

    11.11 ACCEPTANCE LIMITS

    Delete this section and replace with the following:

    Acceptance criteria shall be as specified in ISO 12096. The test report shall contain

    the details specified in ISO 12096. If the Principal specifies that the radiographic test

    procedure is to be agreed, items a to i of clause 9 of ISO 12096 may be stated in the

    procedure and only items j to l included in the test report. Item k in the test report

    shall include the actual sensitivity and density achieved.

  • 8/13/2019 31402036 Dec 09

    39/58

    11.12 IMPERFECTIONS

    Delete this section including Tables 12 and 13 and Figures 8 and 9.

    11.13 DEFECTS

    Delete this section.

    11.14 WELD REPAIR

    Delete this section and replace with the following: Any weld repairs shall be

    performed in accordance with the requirements of section 12.6 and shall be

    examined using the same technique used for examining the weld seam.

    11.15 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF WELDED PIPE

    a. Equipment

    Add the following:

    Automatic ultrasonic equipment shall incorporate:

    i. A facility for registration and recording of indications on paper and/or on a

    retrievable medium without intervention by the operator;

    ii. An automatic weld tracking system for correct positioning of the probes with

    respect to the weld centreline without operator intervention. To allow alternative

    systems, the Manufacturer/Supplier shall demonstrate that complete coverage is

    achieved even when the probe drifts away from the weld seam;

    iii. A device which monitors the effectiveness of the coupling. A deviation in excess

    of 10 dB from the acceptable coupling situation shall indicate a loss of coupling;

    iv. An audible warning/paint spray system that operates when the coupling is

    unsatisfactory;

    v. An automatic paint-marking device that activates when the ultrasonic echo

    received exceeds the trigger/ alarm level.

    From each pipe under test, an automatic "on-line" record shall be made without

    operator intervention. For every pipe, a summary record shall be made showing

    pipe identification number, time, examination results (including re-examinations)

    and effectiveness of acoustic coupling.

    b. Reference standards

    Delete this item, including Figure 10, and replace with the following:

    Reference standards and calibration shall be as specified in the appropriate ISO

    specification and this PTS. For automatic UT, calibration shall be performed using areference standard and shall also be checked dynamically.

  • 8/13/2019 31402036 Dec 09

    40/58

    Specific requirements for each NDT standard shall be as follows:

    ISO Standard Specific requirements

    ISO 9764 N10 notch shall be on both internal and external

    ISO 10124 Reference standard shall be a flat-bottomed

    ISO 11496 Tested band shall be a minimum of 50 mm and

    shall overlap automatic tested pipe body area by

    a minimum of 25 mm. Reference standard shall be

    ISO 12094 Minimum coverage shall be 25 %. Edge band

    shall be 25 mm from final plate/strip edge.

    Reference standard shall be a 6 mm flat-bottomed

    ISO 13663 Reference standard shall be a flat-bottomed

    c. Acceptance limits

    Delete this item, including Table 14, and replace with the following:

    ISO Standard Acceptance limit

    ISO 9303 L2C

    ISO 9764 L3

    ISO 10124 ISO 3183-3, Table D.2, sour

    ISO 11496 No trigger/alarm

    ISO 12094 B1 (body). E1 (edge)

    ISO 13663 ISO 3183-3, Table D.2

    11.16 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF SEAMLESS PIPE

    Delete this section and replace with the following:

    a. Equipment

    See (Part II11.15a).

    b. Reference standards

  • 8/13/2019 31402036 Dec 09

    41/58

    See (Part II11.15b) and the following:

    ISO Standard Specific requirements

    ISO 9305 Notch shall be on both internal and external

    c. Acceptance limits

    See (Part II - 11.15c) and the following:

    ISO Standard Acceptance limit

    ISO 9305 L2C

    ISO 10543 As per ISO 10543

    For ISO 9303 and ISO 9305, full coverage shall be achieved at the examination

    sensitivity level and under all scanning speeds.

    11.17 ULTRASONIC INSPECTION OF CENTRIFUGALLY-CAST PIPE

    Delete this section.

    Add new sections:

    11.18 TESTING OF BEVEL FACES

    Testing of bevel faces shall be performed using MT in accordance with ISO 13664.When agreed by the Principal, PT in accordance with ISO 12095 may be used. The

    acceptance criterion shall be no linear indications

    11.19 NDT PERSONNEL QUALIFICATION

    NDT personnel shall be qualified and certificated in accordance with ISO 11484 or an

    equivalent standard agreed by the Principal. The Manufacturer/Supplier's NDT

    operations shall be managed by personnel certificated to NDT Level 3 (UT being the

    main method). All NDT procedures shall show the approval and qualification

    number/expiry date of the NDT Level 3.

    Shift supervision and calibration activities shall be undertaken by personnel

    certificated to NDT Level 2 or higher in all of the methods being used by the

    Manufacturer/Supplier. All other personnel performing NDT operations shall be

    certificated to NDT Level 1 in the relevant method(s).

  • 8/13/2019 31402036 Dec 09

    42/58

    12. WORKMANSHIP, VISUAL INSPECTION, AND REPAIR OF DEFECTS

    12.2 PURCHASER INSPECTION

    Delete this section and replace as with the following:

    The requirements of Appendix F shall apply.

    12.3 WORKMANSHIP

    a. Dents

    Delete third sentence of this sub-section and replace with the following:

    All cold-formed dents with a sharp bottom gouge and all sharp gouges (without

    dents) deeper than 1.0 mm shall be considered as defects.

    b. Offset of plate edges

    Delete this sub-section and replace with the following:

    The maximum permitted radial offset shall be as follows:

    Wall thickness, t,

    mm

    Maximum radial offset

    mm

    HFW Other welding

    processes

    10 0.5 1.0

    10 < t 20 0.05 t 0.1 t

    >20 - 2.0

    d. Height of outside and inside weld beads - except ERW

    Delete tabulation after first paragraph and replace with the following: The bead

    height shall not lie outside the ranges specified below: -Outside: - 0, + 3 mm -Inside:

    - 0, + 2.5 mm The inside weld bead shall be ground flush with the parent material

    over the full length of the pipe end.

    e. Height of flash of electric-welded pipe

    Delete second paragraph and replace with the following:

    The inside flash of HFW pipe shall not extend beyond the prolongation of the

    original inside surface by more than 0.5 mm plus 5 % of the nominal wall thickness.

  • 8/13/2019 31402036 Dec 09

    43/58

    12.4 VISUAL INSPECTION

    Delete this section and replace with the following:

    The full internal and external surface of each finished pipe shall be visually examined

    for surface defects. For internal examination of pipe DN 600 and larger, theinspector shall pass through the bore of the pipe. The Manufacturer/Supplier shall

    control the visual inspection process with a documented procedure. The procedure

    shall be qualified in accordance with ASME Section V - Article 9.

    12.5 DEFECTS

    b. Laminations and inclusions

    Delete this sub-section and replace with the following:

    The complete internal and external pipe surface and bevel faces shall be free ofsurface breaking laminations and inclusions.

    Note : A lamination is defined as an internal metal separation creating layers

    generally parallel to the surface

    f. Disposition

    1. Add the following to this item:

    In all cases where repair by grinding has been carried out, the length of pipe

    containing each grinding repair shall be re-inspected after the grinding operation bythe same inspection methods as the original inspection and by MT. The inspection

    shall confirm freedom from defects and that the wall thickness is not less than the

    minimum specified. Where manual ultrasonic testing for wall thickness is performed

    it shall be in accordance with ASTM E 797.

    2. Amend this item as follows: Repaired in accordance with 12.6.

    3. Add the following to this item:

    Where surface breaking defects are found in the pipe bevel, the pipe shall be cut

    back and rebevelled. The new bevel shall be subjected to visual inspection and NDTin accordance with this PTS.

    12.6 REPAIR OF DEFECTS

    b. Weld seam of welded pipe

    Delete this sub-section and replace with the following:

    Defects in the weld seam of SAW pipe and pipe welded by GTAW or PAW using a

    filler metal may be repaired. Repair of defects in the weld seam of other forms of

    welded pipe shall not be permitted.

  • 8/13/2019 31402036 Dec 09

    44/58

    Repair welding is not acceptable within 200 mm of the ends of the seam weld.

    Repair welds shall be subjected to radiographic testing in accordance with (section

    11).

    No weld-repaired area shall be subjected to further repair.

    c. Heat-treated pipe

    Delete this sub-section and replace with the following: All repair welding (where

    permitted) shall be performed prior to final pipe heat treatment.

    Table 15

    Delete this table.

    12.7 PROCEDURE FOR REPAIR OF WELD SEAMS OF SUBMERGED-ARC WELDED PIPE

    Delete this section and replace with the following: PROCEDURE FOR REPAIR OF ARC-

    WELDED PIPE

    The defect shall be completely removed and the cavity thoroughly cleaned. The

    cavity shall be inspected by MT, or PT, to ensure that no remnants of the defect

    remain.

    The minimum length of the repair weld shall be 50 mm. The repair weld shall be

    made by either SMAW or GTAW. The welding procedure shall be qualified in

    accordance with Appendix A. Shielding gas containing hydrogen shall not be used.

    12.8 PROCEDURE FOR REPAIR OF WELD SEAMS OF ELECTRIC-WELDED AND INDUCTION-

    WELDED PIPE

    Delete this section.

    12.8 PROCEDURE FOR REPAIR OF WELD SEAM OF GAS METAL-ARC WELDED PIPE

    Delete this section.

    Add new section:

    12.10 GAUGE PIG

    If specified by the Principal, a gauge pig shall be passed through the following pipes

    in their supply conditions:

    i. All first-day-production test pipes.

    ii. Two pipes from each working shift, one at the beginning and one at the end.

    iii. First two pipes immediately after any adjustment or maintenance is carried out

    on the mechanical expander.

  • 8/13/2019 31402036 Dec 09

    45/58

    The gauge shall consist of two parallel, 6 mm thick circular plates each at least 98 %

    of minimum pipe ID separated by a rigid bar of which the length is twice the pipe ID.

    In order to pass the test, the gauge shall be passed through the pipe without

    damaging the gauge plates. The material of the gauge plates shall be 316L or duplex

    stainless steel or other material agreed by the Principal.

  • 8/13/2019 31402036 Dec 09

    46/58

    13. MARKING AND SURFACE TREATMENT

    13.1 MARKING - GENERAL

    b.

    Delete this sub-section and replace with the following: Marking of test pressure,

    sizes and weights shall be in metric units. Add new sub-section:

    c.

    For pipes of DN 100 and above, stencil markings shall be block capitals of minimum

    height 19 mm. For smaller pipe diameters, the character height shall be 10 mm or

    more. The stencil colour shall be white and the stencil fluid shall be free from

    chlorides.

    13.2 LOCATION OF MARKINGS

    b.

    Delete this sub-section and replace with the following:

    For pipe up to DN 400, paint stencilling shall be on the outer surface starting at a

    point between 450 mm and 750 mm from the end of the pipe. For larger pipe, the

    paint stencilling shall be on the inside surface, facing the pipe end, and finish 150

    mm or more from the pipe end. In both cases the marking sequence shall be as

    defined in (13.3).

    c.

    Delete this sub-section.

    13.3 SEQUENCE OF MARKINGS

    i. Supplementary requirements

    Delete this sub-section.

    Add the following new sub-sections:

    PTS 31.40.20.36

    Principal-specified markings

    Additional marking requirements if specified by the Principal.

    13.5 DIE STAMPING

    Delete this section and replace with the following:

    If specified by the Principal, the unique pipe identification number shall be die-

    stamped or vibro-etched on the bevel face at each end of the pipe. Low stress die

    stamps shall be used.

  • 8/13/2019 31402036 Dec 09

    47/58

    13.6 SURFACE TREATMENT

    Delete this section and replace with the following: The pipe shall be pickled or grit-

    blasted in accordance with the Manufacturer/Supplier's documented procedure.

    Add new section:

  • 8/13/2019 31402036 Dec 09

    48/58

    14. STORAGE, HANDLING, AND PACKING

    14.1 HANDLING

    During manufacture, storage and transportation, the pipes shall not come into

    contact with loose carbon steel (e.g. swarf, filings etc.). Nylon slings or rubber-coated hooks/supports etc. shall be used for all handling operations.

    14.2 STORAGE

    All pipe shall be stored and packed in accordance with the Manufacturer/Supplier's

    documented procedure which shall show calculations for stacking height and

    arrangement. The pipe shall be fitted with end caps and shall have a dedicated

    storage area fully segregated from other materials.

    14.3 PACKAGING

    Packaging shall be as specified by, or agreed with the Principal.

    14.4 TRANSPORTATION

    The transportation of pipe shall be as specified in the following:

    i. API RP 5LW for marine transportation

    ii. API RP 5L1 for railroad transportation The pipe shall not be transported by sea as

    deck cargo. Add new section:

  • 8/13/2019 31402036 Dec 09

    49/58

    15. DOCUMENTATION

    15.1 LANGUAGE

    All documentation submissions required by this PTS shall be in the English language.

    15.2 PRE-MANUFACTURING DOCUMENTATION

    The Manufacturer/Supplier shall submit to the Principal within the time period

    specified in the contract document, a contract-specific quality plan and procedures

    detailing all special processes, as described in (Part II1.4).

    NOTE: Review of this documentation at the enquiry stage of the contract may assist this process.

    15.2.1 Content of the quality plan

    The format and issue of the quality plan shall be consistent with the document

    control element of the Manufacturer/Supplier's quality system.

    The content of the quality plan should be based on ISO 10005 and shall include the

    following:

    1. Identification of the product and contract to which the plan is to be applied;

    2. Reference to API Spec 5LC and this PTS;

    3. Location of steel making and pipe production;

    4. Identification of the individuals responsible for controlling the activities

    defined in the plan;

    5. Identification of the individuals with the authority to interface directly with

    the Principal;

    6. Identification of all subcontractors;

    7. The quality plans of all subcontractors;

    8. All sequenced activities for the contract and references to the quality

    system procedures and work instructions which will be applied to these

    activities;

    9. Copies of all the quality system procedures and work instructions covering

    manufacturing production, test and inspection, special processes, control ofnonconforming product, handling, storage, packing, and shipping as

    requested by the Principal;

    10. Test and inspection frequency and acceptance criteria including the upper

    and lower process control limits where statistical process control is

    employed;

    NOTE: Process control for chemical composition and dimensional parameters is generally based on upper and

    lower control levels.

    11. The location of each inspection and test point in the process sequence;

    12. Points where the Principal has established its witnessing or verification

    requirements.

  • 8/13/2019 31402036 Dec 09

    50/58

    15.2.2 Special processes

    The Manufacturer/Supplier shall provide procedures for those manufacturing

    activities determined to be special processes and critical to the final mechanical and

    dimensional integrity of the pipe. This shall include the following:

    Seamless pipe

    -pipe forming procedure; -pipe heat treatment procedure; -hydrostatic test

    procedure;

    - NDT procedures

    HFW pipe

    -Strip manufacturing procedure including details of rolling and any specialised

    cooling or coil heat treatment. -Strip NDT procedures.

    -Pipe making method including details of methods for preparing the edges of the

    strip for welding and for control of misalignment of edges and pipe shape. Details of

    the sizing operation should also be given.

    -A detailed welding procedure specification which shall include the following:

    methods for automatic control of welding parameters;

    electrical or induction frequency;

    details of welding power unit;

    welding speed;

    welding temperature;

    shielding method/arrangement;

    weld profiling. -Weld seam (or full body) heat treatment procedure.

    Hydrostatic test procedure.

    NDT procedures.

  • 8/13/2019 31402036 Dec 09

    51/58

    LBW pipe

    -Strip and pipe manufacturing procedure as required above for HFW pipe.

    -A detailed welding procedure specification in accordance with ISO 9956-11. This

    shall include all details of the methods used for automatic control and monitoring ofthe welding parameters, gas shielding method/arrangement and weld profiling.

    -Pipe heat treatment procedure.

    -Hydrostatic test procedure.

    - NDT procedures.

    Arc welded pipe

    -Strip and pipe manufacturing procedure as required above for HFW pipe.

    -Plate rolling details for pipe to be supplied in the as-rolled condition.

    -Heat treatment procedure for plate heat treated before forming.

    -Pipe manufacturing procedure.

    -For SAW, GTAW and PAW pipe, a detailed welding procedure specification in

    accordance with ISO 9956-2.

    -Hydrostatic test procedure.

    - NDT procedures.

    The manufacturing procedures shall correspond with those used previously for the

    manufacturing qualification tests (in accordance with SIEP 97-5763).

    15.3 SHIPPING DOCUMENTATION

    Each shipment shall be accompanied by a packing list; a pipe tally list; and, where

    applicable, an original or certified copy of the Principal's inspection release note. The

    pipe tally list shall show the pipe numbers with their corresponding heat number,

    length, weight, and end dimensions.

    Add new section:

  • 8/13/2019 31402036 Dec 09

    52/58

    16. FIRST-DAY-PRODUCTION TESTS

    16.1 GENERAL

    At the commencement of production, three completely finished pipes of the first

    day's production shall be selected at random for testing to verify that the proposedmanufacturing procedure results in fully acceptable pipe.

    If more than one cast is used or pipes of more than one dimension are produced

    then the three pipes shall be taken from different heats or size range. For pipe made

    from coiled strip, the test pipes shall include pipes taken from each end of the coil.

    The Principal shall make the selection when a representative is deployed.

    The selected pipes shall be considered to be the production test pipes per lot as

    required in this PTS.

    These tests shall be repeated upon any change in manufacturing procedure or

    significant interruption to the production programme.

    16.2 NON-DESTRUCTIVE TESTING

    a. Visual examination

    All test pipes shall be examined visually for dimensional tolerances, and for surface

    defects, in accordance with (Part II10, 11 and 12) respectively.

    b. Magnetic particle testing

    For seamless pipe only, each test pipe shall be submitted to magnetic particle

    testing over the entire pipe body in accordance with ISO 13665. For welded pipe,

    the weld seam shall be submitted to magnetic particle testing along its entire length.

    Acceptance of indications shall be in accordance with test category M1 of ISO 13665

    with the exception that linear indications, other than acceptable undercut in welded

    pipe, shall be considered as defects.

    c. Ultrasonic testing

    The body of each pipe used for first-day production tests shall be examined byultrasonic testing in accordance with (Part II11).

    d. Radiographic testing

    For welded pipe, except HFW, the entire weld seam shall be inspected in accordance

    with (Part II11).

    16.3 CHEMICAL COMPOSITION

    The chemical composition of each test pipe and weld (if applicable) shall be

    determined in accordance with (Part II6).

  • 8/13/2019 31402036 Dec 09

    53/58

    16.4 MECHANICAL TESTING

    Mechanical tests shall be carried out on each test pipe as required by (Part II7). In

    addition, for each first-day-production test pipe, a full Charpy impact transition

    curve shall be produced, showing impact energy in joules and percentage shear

    (fibrous) of the fracture surface, plotted against temperature, over a temperature

    range sufficient to produce fracture appearance from 10 % to 100 % fibrous shear.

    16.5 SPECIAL TESTS

    CTOD tests in accordance with (Part II - 8.1) and residual magnetism checks in

    accordance with (Part II8.2) shall be performed on each test pipe.

    APPENDIX A REPAIR WELDING PROCEDURE

    A.1 GENERAL Delete sub-sections a., b., and c. and replace with the following:

    Shielded metal-arc using low-hydrogen electrodes.

    Gas tungsten-arc. Add the following: The composition of the repair weld metal shall

    match that of the weld seam.

    A.2 REPAIR WELDING PROCEDURE QUALIFICATION

    Delete this section and replace with the following:

    A repair welding procedure specification shall be prepared in accordance with ISO

    9956-2. A fully simulated repair weld shall be made on a pipe piece of sufficient

    length to accommodate extraction of all the required test specimens. Qualification

    shall be by the visual, non-destructive, and destructive testing of the test weld seam

    as specified in this PTS for the original seam weld.

    Repair weld metal shall not be exposed on the inner surface of the pipe unless it has

    been heat-treated.

    A.2.2 Mechanical testing

    Delete this section and replace with the following:

    The repair welding procedure shall be subject to the same testing required for the

    original weld by (Part II - 7 and 8).

  • 8/13/2019 31402036 Dec 09

    54/58

    APPENDIX F PURCHASER INSPECTION

    F.1 INSPECTION NOTICE

    Delete this section and replace with the following: The Manufacturer/Supplier shall

    give five working days' notice to the Principal of the production run or inspection or

    test, which is to be witnessed. Add the following:

    F.5 SUMMARY OF PRINCIPAL'S INSPECTION PROFILES

    The Principal shall indicate the type of inspection to be performed in the contract

    document.

    SEQUENCE

    NO

    INSPECTION ACTION FULL

    RUNNING

    LIMITED

    RUNNING

    FULL

    FINAL

    LIMITED

    FINAL

    1.0 ATTENDANCE IN THE

    MILL DURING

    Yes Spot No No

    2.0 CONTRACT QUALITY PLAN RA RA RA RA3.0* PRE-

    MANUFACTURING

    E * E * E *

    4.0 MILL PRODUCTION

    4.1 Pipe rolling SWA SWA

    4.2 Heat treatment FW/RR FW/RR RR RR

    4.3 Sampling test pieces E E

    4.4 Physical properties FW/RC FW/RC RC RC

    4.5 Hydrostatic test FW/RC FW/RC RC RC

    4.6 NDT for acceptance FW/RR FW/RR RR/RC RR/RC

    4.7 Dimensional inspection SW/SE/RR SW/SE/RR SE/RR SE/RR

    4.8 Marking SW SW SW SW

    4.9 Packing SW SW SW SW

    5.0 DOCUMENT REVIEW

    5.1 Production records RR RR RR RR

    5.2 Tally lists RR RR RR RR

    5.3 Inspection reports RC RC RC RC

    5.4 Release note E E E E

    6.0 FIRST DAY

    PRODUCTION

    W/RC W/RC RC RC

    Abbreviations and notes:

    E Execution by Principal's Inspector.

    FW Witness first operation for compliance, including check of calibrations; subsequently random inspection, review document

    and endorse for acceptance.

    RA Review document and endorse for acceptance.

    RC Review certificate and endorse for acceptance.

    RR Review production records and endorse for acceptance.

    SE Random execution by Principal's Inspector.

    SW Random witness by Principal's Inspector.

    SWA Random witness applicable when pipe forming is part of finishing line (e.g. there is no additional heat treatment on a

    different line).

  • 8/13/2019 31402036 Dec 09

    55/58

    W Full witness.

    *If specified in the contract document.

    PART III REFERENCES

    In this PTS, reference is made to the following publications:

    NOTE: Unless specifically designated by date, the latest edition of each publication shall be used, together with any

    amendments, supplements, or revisions thereto.

    PETRONAS STANDARDS

    Index to PTS publications and standard specifications

    PTS 00.00.05.05

    Pressure vessels (amendments/supplements

    PTS 31.22.20.31

    ASME Section VIII, Division 1 and Division 2)

    Qualification test requirements for weldable 13Cr line pipe

    SIEP 97-5763, September 1997

    AMERICAN STANDARDS

    Specification for CRA line pipe API Spec 5LC, 3rd July 1998, Reaffirm Aug 2008

    Recommended practice for railroad transportation of line pipe API RP 5L1

    Recommended practice for transportation of line pipe on API RP 5LW

    barges and marine vessels

    Issued by: American Petroleum Institute

    Publications and Distribution Section

    1220 L Street, Northwest Washington, DC 20005

    USA.

    Boiler and pressure vessel code, Section V, ASME V

    nondestructive examinationIssued by: American Society of Mechanical Engineers

    345 East 47th Street New York NY 1001USA

    Standard test mthod for macro-etching metals and alloys ASTM E 340

    Standard practice for measuring thickness by manual ASTM E 797

    ultrasonic pulse-echo contact method

    Issued by: American Society for Testing and

    Materials

    100 Bar Harbor Drive, West Conshohocken, PA 19428-2959

    USA

  • 8/13/2019 31402036 Dec 09

    56/58

    BRITISH STANDARDS

    Fracture mechanics toughness tests - Part 1. BS 7448 Part 1

    Method for determination of KIC, critical CTOD

    and critical J values of metallic materials

    Fracture mechanics toughness tests - Part 2. BS 7448 Part 2

    Method for determination of KIC, critical CTOD, and

    critical J values of welds in metallic materials

    Issued by: British Standards Institution

    389 Chiswick High Road

    London W4 4AL

    UK

    EUROPEAN STANDARDS

    Destructive tests on welds in metallic materials. EN 1043-1

    Hardness testingPart 1: Hardness tests on arcwelded joints

    Issued by: Comit Europen de Normalisation

    Rue de Stassart 35

    1050 Brussels

    Belgium

    Copies can also be obtained from national standards organizations.

    INTERNATIONAL STANDARDS

    SteelCharpy impact test (V-notch) ISO 148

    Radiographic image quality indicators for non ISO 1027

    destructive testingprinciples and identification

    Petroleum and natural gas industriesSteel pipe for ISO 3183-3

    pipelinesTechnical delivery conditionsPart 3: Pipes of

    requirement class C

    Metallic materials - Vickers hardness test - Part 1: Test method ISO 6507-1

    Quality systems - Model for quality assurance in design, ISO 9001

    development, production, installation and servicing

    Quality systems - Model for quality assurance in production, ISO 9002

    installation and servicing

    Seamless and welded (except submerged arc-welded) steel tubes 1SO 9303

    for pressure purposes - Full peripheral ultrasonic testing for the

    detection of longitudinal imperfections

    Seamless steel tubes for pressure purposesFull peripheral ultrasonic 1SO 9305

    testing for the detection of transverse imperfections

  • 8/13/2019 31402036 Dec 09

    57/58

    Electric resistance and induction welded steel tubes for ISO 9764

    pressure purposes - Ultrasonic testing of the weld seam

    for the detection of longitudinal imperfections

    Submerged arc-welded steel tubes for pressure purposesUltrasonic ISO 9765

    testing of the weld seam for the detection of longitudinal and/or transverseimperfections

    Specification and approval of welding procedures for metallic materials ISO 9956-2

    Part 2: Welding procedure specification for arc welding, Amendment 1

    Specification and approval of welding procedures for metallic

    materialsPart 11: Welding procedure specification for laser beam welding ISO 9956-11

    Quality management - Guidelines for quality plans ISO 10005

    Quality assurance requirements for measuring equipment ISO 10021-1Part 1:Metrological confirmation system for measuring equipment

    Seamless and welded (except submerged arc-welded) steel tubes for ISO 10124

    pressure purposes Ultrasonic testing for the detection of laminar imperfections

    Steel and steel productsInspection documents ISO 10474

    Seamless and hot-stretch-reduced welded steel tubes for ISO 10543

    pressure purposes - Full peripheral ultrasonic thickness testing

    Steel tubes for pressure purposes - Qualification and certification of ISO 11484

    non-destructive testing (NDT) personnel

    Seamless and welded steel tubes for pressure purposesUltrasonic ISO 11496

    testing of tube ends for the detection of laminar imperfections

    Welded steel tubes for pressure purposes Ultrasonic testing for the ISO 12094

    detection of laminar imperfections in strips/plates used in the manufacture

    of welded tubes

    Seamless and welded steel tubes for pressure purposes ISO 12095

    Liquid penetrant testing

    Submerged arc-welded steel tubes for pressure purposes ISO 12096

    Radiographic testing of the weld seam for the detection of imperfections

    Welded steel tubes for pressure purposes Ultrasonic testing of the area ISO 13663

    adjacent to the weld seam for the detection of laminar imperfections

    Seamless and welded steel tubes for pressure purposesMagnetic particle ISO 13664

    inspection of the tube ends for the detection of laminar imperfections

  • 8/13/2019 31402036 Dec 09

    58/58

    Seamless and welded steel tubes for pressure purposes ISO 13665

    Magnetic particle inspection of the tube body for the detection of surface imperfections

    Issued by:

    International Organisation for Standardisation 1, rue de Varemb

    CH-1211 Geneve 20Switzerland

    Copies can also be obtained from national standards organizations