Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Accelerator Vacuum Systems at DESY
Part I:
Experiences with the operation of the PETRA III vac uum system
Part II:
Undulator chambers for PETRAIII, FLASH & XFEL
Lutz Lilje, Torsten WohlenbergDESY, 1.4.2014
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 2
Experiences with the Operation of the PETRA III Vac uum System
> PETRA III History
> 1976 built as an electron – positron collider
� 1978 to 1986 in this collider mode.
> 1988 to 2007
� PETRA II was used as a pre-accelerator for the HERA
> 2007 – 2008
� Conversion into a synchrotron light facility.� e+ operation (2009 – 2012)
• 2009 commissioning with beam
• 2010 “friendly users”,
• 2011 regular user operation
• 2012 regular user operation
� e- operation (started Jan 2013)• 2013 regular user operation
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 3
PETRA III Layout
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 4
PETRA III Future Plans
> PETRA III continues as a 3rd generation synchrotron light source with very high brilliance and very low emittance
> PETRA III Extension
� Currently, two more sectors are being upgraded from old FODO lattice to DBA cells for insertion devices
� In total 10 more experimental stations are being built
� Large user demand
� DORIS III switched off
> Increase availability
� Aimed for 95 %, achieved 94%• Close, but not good enough
• Mainly due to RF system
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 5
PETRA Extension: Halls North and East
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 6
„Vacuum“ Problems
> All of the subjects are related to the vacuum system
� Some of which are closely related ….
� … more or less in order of appearance
> “Stichabsorber”
> RF contacts
> Laser window
> Undulator
> Cavities
� Visual ports
� Couplers
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 7
“Stichabsorber”
> During commissioning sudden increases in pressure in in the new DBA sector
> Investigations show that a flange was too warm
> When beam orbit was slightly pointing upwards no heating observed
> Heating due to synchrotron light from upstream dipole
> Absorber design needs to be modified
ca. 4.5 Watt/mA
Synchrotron light fan can pass below the absorber
Shadow of “Stichabsorber“
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 8
“Stichabsorber“ Old design
New design
> Lesson learned (again)
� Beam physicist says: „Beam will always be in nominal orbit.“
� Engineer optimises for lowest power deposition
� Shallow angle solution
� Commissioning will prove physicist wrong
� Mike Seidel in OLAV1 2005
� “→ build your system passively safe if possible; any orbit that circulates will occur!”
Side view
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 9
RF-Contacts in RF-shielded Bellows
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 10
RF-Contacts in RF-shieldedBellows
> RF contacts on the inside are tricky
� Several tests were done beforehand tomake sure that contacts have contact
> But:
� Only when the RF-shielded bellow isoverextended RF fingers loose contact
> Re-Design needed
� RF-Fingers on the outside
> Limited the current in the 40 Bunchmode to 80 mA until 2012
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 11
Laser Window for Diagnostics
>2010 Leak in PETRA old section SWR
>Laser focal point in window plane
>Leak small
�Quick intervention withglue
>Exchange duringregular maintenance
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 12
Undulator Crash
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 13
Undulator Crash
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 14
Undulator Crash
> 2010
> Firmware upgrade to motorcontrol
> Hard end switches not in optimal position
> Chamber was still leak tight!
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 15
2011: Undulator Chamber has a dent…
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 16
Part of a Film Badge Found
> Counter measure:
> Visual Inspection of all undulatorpoles after maintenace daysbefore machine operation whengaps were opened
> Are there technical solutions tothis elsewhere?
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 17
RF Cavities and Couplers
> PETRA III Project re-used HERA- (and PETRA)-style cavities
� 500 MHz Hardware was available
� Best cavities and couplers moved to PETRA
> Problematic
� Original RF design not really for high currents but rather for large voltage
� High bunch charges and HOM issues
� Limiting the 40 bunch operation (sometimes)
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 18
Cavities
> Visual ports on cavities for coupler observation (comes next)
> Occurred once in 2011
� Attributed to wrong glas material> Re-occurred when 40 bunch mode
reached 100 mA beginning of 2013
> Size of the port is large enough for HOM RF (1-3 GHz)
> Heating up to 200°C
� Windows rated for 300°C> But when machine operation is
suddenly inhibited cooling rate too fast: >> 3°C/ min
> Implemented Copper mask to shield RF
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 19
RF Cavities
> Visual ports on cavities for coupler observation (comes next)
> Occurred once in 2011
� Attributed to wrong glas material> Re-occurred when 40 bunch mode
reached 100 mA beginning of 2013
> Size of the port is large enough for HOM RF (1-3 GHz)
> Heating up to 200°C
� Windows rated for 300°C> But when machine operation is
suddenly inhibited cooling rate too fast: >> 3°C/ min
> Implemented Copper mask to shield RF
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 20
RF Couplers
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 21
RF Couplers
> Optical sensor shows
� Clear evidence of plasma• Not necessarily a bad thing
� Clear evidence of local heating• Probably field emission
> Old RF system
� Cleaning methods cannot be compared to nowadays standards
� Several surface defects can be observed e.g. particles, drying stains etc.
> Improvement program started
� Dry-ice cleaning of RF components e.g. couplers• Was successfully tested for SRF cavities and normal-conducting RF-Guns
� Tests of freshly etched and rinsed cavities• Application of pure and ultra-pure water standards
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 22
END of part 1
Sven Lederer (MVS) Lutz Lilje (MVS) Torsten Wohlenberg (MVS)and many MVS colleagues DESY, HAMBURG
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan
Undulator vacuum chambers for PETRAIII,FLASH & XFEL
Undulator chambers for PETRAIII, FLASH & XFEL
24Outline� Requirements of the different accelerators for the undulator vacuum chambers� PETRAIII on the example of PU1
� Development of the PU1 vacuum chamber� 3D-model � Realisation� NEG coating not discussed in this presentation
� FLASH on the example of FLASH2� Development of the FLASH2 undulator vacuum chambers� 3D-model� Realisation
� European-XFEL� Development of the European-XFEL undulator vacuum chambers� 3D-model� Special requirements on surface roughness & oxide layer
� Support system for the undulator chambers� Detail of the alignment system
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
Undulator chambers for PETRAIII, FLASH & XFEL
25
Requirements of the different accelerators for the undulator chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
PETRAIII FLASH1/FLASH2 XFEL
Pressure requirements Average pressure ˂1�10��
mbarNEG coating required
Average pressure ˂2�10��
mbarAverage pressure ˂2�10��
mbar
Beam dynamic requirements Surface roughness & oxide layer„normal“
Surface roughness & oxide layer„high“
Surface roughness & oxide layer„very high“
Magnetic gap Tunable magnetic gap, minimal 9.5-12.5 mm
Fixed magnetic gap of 12 mm (FLASH1)Tunable magnetic gap, minimal 9.0 mm (FLASH2)
Tunable magnetic gap, minimal 10.0 mm
ApertureMinimal wall thickness
Horizontal: 56-57 mmVertical: 7-10.5 mmMin. wall thickness 0.75 +0.025 – 1.0 +0.1 mm
Horizontal: 9.5-15.0 mmVertical: 7.7-9.5 mmMin. wall thickness 0.45±0.02 – 1.0 mm
Horizontal: 15 mmVertical: 8.8 mmMin. wall thickness 0.4 + 0.025 mm
Tolerance of alignment Horizontal:±0.5mmVertical : ±0.1mmAngel: 0.1mm to the magnet pole area
Horizontal:±0.2 mmVertical : ±0.1 mmAngel: 0.05 mm to the magnet pole area
Horizontal:±0.1 mmVertical : ±0.1 mmAngel: 0.05 mm to the magnet pole area
Particle free (ISO5) Not required Required Not required
Undulator chambers for PETRAIII, FLASH & XFEL
26PETRAIII undulator vacuum chambers on the example of PU1
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Simulated chamber deformation caused by the pressure difference (C. Martens , DESY, ZM1)
� Final design for the extrusded aluminum profile by MIFA Experience Precision
� Result after several design studies with manufacturers
� Wall thickness 0.7 mm� Deformation 80 µm/side
� Development for PU1
�horizontal width: 57 mm tolerance 0/+0.1
�vertical high: 10.5 mm tolerance: 0/+ 0.15
� chamber height: 12.0 mm tolerance 0/+0.05
Undulator chambers for PETRAIII, FLASH & XFEL
27PETRAIII undulator vacuum chambers on the example of PU1
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Aluminium welding � Aluminium DN100CF flange, DLC coated
� Vacuum chamber: � PU1 length 5400 mm � NEG coating
� Aircoils
� 3-D Model
Undulator chambers for PETRAIII, FLASH & XFEL
28PETRAIII undulator vacuum chambers on the example of PU1
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Realisation PU1
Undulator chambers for PETRAIII, FLASH & XFEL
29FLASH2 undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Wall thickness 0.5 mm � deformation 1µm/side
� Development for FLASH2
� Result after several design studies with manufacturers
� Final design for the extrusded aluminum profile by MIFA Experience Precision
� Simulated chamber deformation caused by the pressure difference (C. Martens , DESY, ZM1)
�vertical high: 7.7 mm tolerance +/- 0.05mm
�horizontal width: 10.0 mm tolerance +/-0.1
� chamber height: 8.6 mm tolerance +/-0.02
Undulator chambers for PETRAIII, FLASH & XFEL
30FLASH2 undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
�Friction welding flanges transition SS/Al
�Vacuum chamber: FLASH2 length 2618mm
�Aluminium laser welding
�Holes for correction coils
�Holes for cherenkov fibers
�Aluminium laser welding
� 3-D Model
Undulator chambers for PETRAIII, FLASH & XFEL
31FLASH2 undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Realisation
Undulator chambers for PETRAIII, FLASH & XFEL
32European-XFEL undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Wall thickness 0.4 mm
� Deformation is < 50 µm
� Development for European-XFEL
� Simulated chamber deformation caused by the pressure difference (C. Martens , DESY, ZM1)
� Result after several design studies with manufacturers
� Final design for the extrusded aluminum profile by MIFA Experience Precision
�horizontal width: 15 mm tolerance: 0/+0.1
�vertical high: 8.8 mm tolerance: -0.05/-0.15
� chamber height: 9.6 mm tolerance +0.02/+0.05
Undulator chambers for PETRAIII, FLASH & XFEL
33European-XFEL undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
Friction welded flanges, transition SS/Al
Water cooling
Cross section of the 5.4 m long undulator chamber
10 pockets for online dosimetry
Picture taken from talk:Beschleunigerbetriebsseminar Grömitz, 18.–21.3.2012 Lars Fröhlich, Elettra–Sincrotrone Trieste
Two wire correctors (inner channels)
� 3-D Model�Vacuum chamber: European-XFEL length 5.4mm
Undulator chambers for PETRAIII, FLASH & XFEL
34European-XFEL undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Roughness & Oxide layer� AFM treatment on a 5 m long test chamber
� Measurement preparation and equipment
Mitutoyo (Surftest SJ-210)
Sketch of sample preparation
Sample for series of measurements
Undulator chambers for PETRAIII, FLASH & XFEL
35European-XFEL undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Roughness & Oxide layer� Result of the AFM treatment on a 5 m long test chamber (Polishing only in one direction!)
� Results point out that it is essential to polish in both directions!
�Target line :80 nm Ra
�Entrance of the chamber
�Center of the chamber
�Exit of the chamber
Undulator chambers for PETRAIII, FLASH & XFEL
36European-XFEL undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Roughness & Oxide layer� Oxide layer research with TEM on AFM polished aluminium samples
after different times at air.� → result shows no growth of the oxide layer after the passivation
�Sample 26 one day at air
�Sample 21 one week at air
�Sample 22 two weeks at air
3-5 nm oxide layer on all samples
Undulator chambers for PETRAIII, FLASH & XFEL
37Support system for the undulator vacuum chambers
OLAV IV April 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
� Detail of the alignment system� Proof of principle of this alignment concept wasdone at sFlash, FLASH2 and PETRAIII where theundulator gap could be closed to design value:
sFlash 9 mm, FLASH2 9 mm & PETRAIII 12.5 mm
�Horizontal adjustment
�Vertical adjustment�Angular
adjustment
�Undulator vacuum chamber
�PETRAIII
�sFLASH & FLASH2
Undulator chambers for PETRAIII, FLASH & XFEL
�End of Part 2
38
OLAV IV Apil 01-04, 2014 NSRRC, Hsinchu, Taiwan Undulator chambers for PETRAIII FLASH & XFEL Torsten Wohlenberg MVS DESY, Hamburg
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 39
Summary and Outlook
> PETRA III achieved full beam current of 100 mA in all modes:
� 40, 60, 480, 960 Bunches
> Extension project is ongoing
> Continued work on availability needed
> Undulator chambers for various accelerator applications have been built
� Universal, flexible and precise support system being implemented
> Requirements are demanding and need vigorous control
� Geometry and Alignment
� Surface roughness
� Oxide layer
L. Lilje | Accelerator vacuum systems at DESY | 1.4.2014 | Page 40
Thanks for your attention!