Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Terraprobe Consulting Geotechnical & Environmental Engineering
Construction Materials Inspection & Testing
Terraprobe Inc. Greater Toronto Hamilton – Niagara Central Ontario Northern Ontario
11 Indell Lane 903 Barton Street, Unit 22 220 Bayview Drive, Unit 25 1012 Kelly Lake Rd., Unit 1
Brampton, Ontario L6T 3Y3 Stoney Creek, ON L8E 5P5 Barrie, Ontario L4N 4Y8 Sudbury, Ontario P3E 5P4
(905) 796-2650 Fax: 796-2250 (905) 643-7560 Fax: 643-7559 (705) 739-8355 Fax: 739-8369 (705) 670-0460 Fax: 670-0558
www.terraprobe.ca
DETAILED GEOTECHNICAL INVESTIGATION AND ENGINEERING DESIGN REPORT 12, 16 & 20 CORDOVA AVENUE
TORONTO, ONTARIO
Prepared For: Minto Cordova LP 4101 Yonge Street, Suite 600 Toronto, Ontario M2P 1N6
Attention: Mr. Frank Pagliuca
File No. 1-17-0848-01 Issued: August 8, 2018
Revised (Rev.1): November 9, 2018
© Terraprobe Inc.
Distribution of Report:
1 PDF Copy - Minto Cordova LP 1 Copy - Minto Cordova LP 1 Copy - Terraprobe Inc.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. i
TABLE OF CONTENTS
1.0 THE PROJECT ................................................................................................................................... 1
2.0 SUBSURFACE CONDITIONS ........................................................................................................... 2
2.1 STRATIGRAPHY........................................................................................................................... 2
2.1.1 PAVEMENT STRUCTURE AND EARTH FILL ......................................................................................... 3 2.1.2 NATIVE SAND ............................................................................................................................... 3 2.1.3 SANDY SILT .................................................................................................................................. 4 2.1.4 GLACIAL TILL ................................................................................................................................ 4 2.1.5 PRACTICAL REFUSAL (POSSIBLE WEATHERED BEDROCK) ................................................................. 4
2.2 GROUND WATER ........................................................................................................................ 5
3.0 GEOTECHNICAL ENGINEERING DESIGN ...................................................................................... 6
3.1 FOUNDATION DESIGN PARAMETERS ............................................................................................ 7
3.1.1 SPREAD FOOTING FOUNDATIONS .................................................................................................... 7 3.1.2 RAFT FOUNDATION ........................................................................................................................ 8
3.2 EARTHQUAKE DESIGN PARAMETERS ........................................................................................... 9
3.3 EARTH PRESSURE DESIGN PARAMETERS .................................................................................. 10
3.4 SLAB ON GRADE DESIGN PARAMETERS ..................................................................................... 11
3.5 BASEMENT DRAINAGE ............................................................................................................... 12
3.6 SITE SERVICING ....................................................................................................................... 13
3.6.1 BEDDING .................................................................................................................................... 13 3.6.2 BACKFILL ................................................................................................................................... 13 3.6.3 TRENCH PLUGS .......................................................................................................................... 14
4.0 DESIGN CONSIDERATIONS FOR CONSTRUCTABILITY ............................................................ 15
4.1 EXCAVATIONS .......................................................................................................................... 15
4.2 GROUND WATER CONTROL ....................................................................................................... 16
4.3 EARTH-RETENTION SHORING SYSTEMS ..................................................................................... 17
4.3.1 LATERAL EARTH PRESSURE DISTRIBUTION .................................................................................... 17 4.3.2 CAISSON AND SOLDIER PILE TOE EMBEDMENT .............................................................................. 18 4.3.3 LATERAL BRACING ELEMENTS ...................................................................................................... 18
4.4 SITE WORK .............................................................................................................................. 19
4.5 QUALITY CONTROL ................................................................................................................... 19
5.0 LIMITATIONS AND USE OF REPORT ........................................................................................... 20
5.1 PROCEDURES ........................................................................................................................... 20
5.2 CHANGES IN SITE AND SCOPE ................................................................................................... 21
5.3 USE OF REPORT ....................................................................................................................... 22
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. ii
FIGURES
Figure 1 – SITE LOCATION PLAN
Figure 2 – BOREHOLE LOCATION PLAN (EXISTING CONDITION)
Figure 3 – BOREHOLE LOCATION PLAN (PROPOSED CONDITION)
Figure 4 – SUBSURFACE PROFILE
APPENDICES
Appendix A – ABBREVIATIONS AND TERMINOLOGY; BOREHOLE LOGS
Appendix B – GEOTECHNICAL LABORATORY RESULTS
Appendix C – BASEMENT DRAINAGE DETAILS
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 1
1.0 THE PROJECT
Terraprobe Inc. was retained by Minto Cordova LP to conduct a subsurface investigation and provide
detailed geotechnical engineering design recommendations for the proposed redevelopment of municipal
addresses 12, 16 & 20 Cordova Avenue. The properties under consideration in this report are located
south of Dundas Street West and west of Islington Avenue, in Toronto, Ontario. A site location plan is
provided as Figure 1. Terraprobe is also providing Phase One and Two Environmental Site Assessments
(ESA) and a hydrogeological study under separate covers.
The site is currently occupied by four (4) residential buildings. The proposed redevelopment includes
demolishing the existing residential dwellings and constructing a 27-storey tower resting on a P5
underground parking structure, with a lowest finished floor elevation (FFE) at Elev. 109.2 ±m (i.e. about
16 ±m below grade). The following drawing set was provided to Terraprobe for review in preparation of
this revised (Rev.1) report:
“12-20 Cordova Ave”, Project No. 18-101, Drawing No. A1-1 to A5-1, dated November 16,
2018, by Rafael + Bigauskas Architects.
Terraprobe completed a previous subsurface investigation (Boreholes 1 to 3, and 101) for this
redevelopment in February 2018 for the purposes of preliminary geotechnical engineering design
(“Preliminary Geotechnical Investigation and Engineering Design Report – 12-20 Cordova Avenue,
Etobicoke, Ontario”, File No. 1-17-0848-01, dated March 15, 2018).
For the purposes of detailed design, the subsurface investigation involved the following:
For detailed geotechnical engineering design purposes:
o One (1) exterior borehole (Borehole 201-D) to a target depth of 23 m below grade, and
four (4) exterior boreholes (Boreholes 202 to 205) to a target depth of 20 m below grade,
or until practical refusal
For hydrogeological and environmental purposes:
o Two (2) interior boreholes (Boreholes 301 and 302) to a target depth of 3 m below grade,
or until practical refusal (the boreholes were advanced using a direct-push machine,
therefore N-Values were not measured)
o One (1) exterior 150 mm pumping well (Pump Well 1) installed at a target depth of 20 m
below grade
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 2
o Two (2) exterior boreholes (Borehole 201-S, 401-D) to a target depth of 8 and 23 m
below grade, respectively.
The locations of the boreholes are provided on the Borehole Location Plans as Figure 2 (Existing
Condition) and Figure 3 (Proposed Condition). A subsurface profile of the boreholes is provided as
Figure 4. The results of the individual boreholes are recorded on the Borehole Logs in Appendix A. A
summary of the geotechnical laboratory tests is provided in Appendix B.
Interpretation, analysis and advice with respect to the geotechnical engineering aspects of the proposed
development are provided, based on the information secured from this investigation. The anticipated
construction conditions pertaining to foundation design, seismic site classification, slab on grade design,
earth pressure design, basement drainage, excavation, shoring design, short term dewatering and other
constructability recommendations are discussed.
2.0 SUBSURFACE CONDITIONS
The borehole elevations and coordinates are provided relative to geodetic datum (NAD 83). The
horizontal coordinates are reported relative to the Universal Transverse Mercator geographic coordinate
system (UTM Zone 17T). The boreholes were surveyed for horizontal coordinates and geodetic elevations
with a Trimble R10 Receiver connected to the Global Navigation Satellite System and the Can-Net
Virtual Reference Station Network.
The subsurface soil and ground water conditions encountered in the boreholes are presented on the
attached Borehole Logs in Appendix A. The stratigraphic boundaries indicated on the geotechnical
Borehole Logs are inferred from non-continuous samples and observations of drilling resistance and
typically represent a transition from one soil type to another. These boundaries should not be interpreted
to represent exact planes of geological change. The subsurface conditions have been confirmed in a series
of widely spaced boreholes and will vary between and beyond the borehole locations. The discussion has
been simplified in terms of the major soil strata for the purposes of geotechnical design.
Asphaltic concrete material thicknesses provided in the report were obtained at individual borehole
locations, as measured through the collar of the open borehole. Thicknesses may vary between and
beyond borehole locations.
2.1 Stratigraphy
The following stratigraphy is based on the exterior borehole findings (Boreholes 1 to 3, 101, 201-D to
205, and 401-D), as well as the geotechnical laboratory testing conducted on selected representative soil
samples. Boreholes 301 and 302 were advanced using a direct-push machine and encountered practical
refusals at depths of 1.8 to 2.9 m below the basement slab (Elev. 123.0 to 121.8 m); N-values were not
measured, therefore these Borehole Logs are included for reference only. The summary below is provided
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 3
for general guidance only. Detailed depths/elevations/thicknesses are given in the following subsections.
In general, five (5) main stratigraphic units were encountered on site as follows:
1. A layer of earth fill (about 1.8 ±m thick on average), overlying
2. Native sand (about 6.6 ±m thick on average), underlain by
3. Sandy silt (about 7.2 ±m thick on average), underlain by
4. A variable glacial till (about 5 ±m thick on average), underlain by
5. Practical refusal on possible weathered bedrock at Elev. 102 to 106 ±m (from the southeast
portion of the site to the northwest portion of the site). Due to the site access, project time
constraints and limited equipment availability, rock coring was not performed at this site.
The stabilized ground water table is at about Elev. 120 ±m.
2.1.1 Pavement Structure and Earth Fill
Boreholes 1 to 3, 101, 204, and 205 encountered a pavement structure at grade consisting of 50 to
165 mm of asphaltic concrete underlain by 15 mm of aggregate (in Borehole 101 only) and a layer of
earth fill extending to depths of 1.5 to 2.3 m below grade (Elev. 122.7 to 123.9 m below grade).
Boreholes 201-S and 201-D, 202, and 203 were located adjacent to Boreholes 1, 2, and 3, respectively;
the 200-series boreholes were straight drilled to a depth of 7.6 m below grade (Elev. 117.4 to 118.8 m)
prior to sampling, and hence did not observe the earth fill. The earth fill varies in composition from sand
to silty sand, with trace amounts of clay, gravel, and deleterious materials (ash and cinders, asphalt and
brick fragments, organics, rootlets). Due to the variation and inconsistent placement of the earth fill
material, the relative density of the earth fill varies but is on average loose.
2.1.2 Native Sand
Underlying the earth fill, Boreholes 1 to 3, 101, 204 and 205 encountered a native sand deposit at depths
of 1.5 to 2.3 m below grade (Elev. 122.5 to 123.4 m). The sand deposit extends to 3.0 to 12.2 m below
grade (Elev. 112.5 to 122 m). The sand contains a variable amount of gravel (ranging from trace gravel to
gravelly), and is generally brown and transitions from moist to wet with increasing depth. The Standard
Penetration Test (SPT) results (N-Values) measured in the sand ranged from 4 blows per 300 mm of
penetration to 93 blows per 225 mm of penetration, indicating a loose to very dense relative density (on
average compact above Elev. 120 ±m and dense below Elev. 120 ±m in Boreholes 1, 2 and 101, and
consistently dense to very dense in Boreholes 3 and 201-D to 205, and 401-D).
Underlying the sand deposit, Borehole 204 (advanced in the southern portion of the site) encountered an
upper glacial till at a depth of 3.0 m below grade (Elev. 122.0 m) extending to a depth of 7.6 m below
grade (Elev. 117.4 m). This upper glacial till was not observed in the remaining boreholes. The glacial till
consists of a sandy silt matrix, contains trace amounts of clay and gravel, and is brown and moist. The
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 4
SPT N-Values measured in the glacial till are greater than 50 blows per less than 300 mm of penetration,
indicating a very dense relative density.
2.1.3 Sandy Silt
Underlying the sand deposit and glacial till observed in Borehole 204, a sandy silt deposit was
encountered at depths of 6.1 to 12.2 m below grade (Elev. 112.4 to 118.5 m). Boreholes 2 and 3 were
terminated in the silt at depths of 8.2 to 9.8 m below grade (Elev. 14.8 to 116.7 m), whereas the remaining
boreholes fully penetrated the deposit at depths of 12.2 to 16.8 m below grade (Elev. 108.2 to 112.4 m).
The sandy silt contains trace clay, transitions from brown to grey with increasing depth, and is generally
wet. The SPT N-Values measured in the silt ranged from 22 blows to 100 blows per 300 mm of
penetration, indicating a compact to very dense relative density (on average very dense).
2.1.4 Glacial Till
Underlying the sand silt deposit, the boreholes encountered a variable glacial till deposit at depths of 12.2
to 16.8 m below grade (Elev. 108.2 to 112.4 m). Borehole 1 was terminated in the glacial till at a depth of
17.4 m below grade (Elev. 107.6 m). Boreholes 202 to 205 encountered practical refusal at depths of 17.4
to 19.5 m below grade (Elev. 105.4 to 107.6 m), whereas Boreholes 101, 201-D and 401-D fully
penetrated the glacial till at depths of 16.8 to 22.9 m below grade (Elev. 101.8 to 108.2 m). The glacial till
varies from cohesive to cohesionless, with a matrix ranging from clayey silt, to sandy silt, to silty sand, to
gravelly sand, to sand and gravel, contains trace to some clay, and is consistently grey and moist.
Boreholes 202, 203 and 204 observed trace to some shale fragments embedded within the glacial till with
increasing depth. Borehole 203 encountered a zone of dense sand and silt embedded in the glacial till at a
depth of 16.8 m below grade (Elev. 108.1 m) extending to a depth of 18.3 m below grade (Elev. 106.6 m).
The SPT N-Values measured in cohesive glacial till were consistently greater than 50 blows per less than
300 mm of penetration, suggesting a hard consistency, and ranged from 26 to 141 blows per 300 mm of
penetration in the cohesionless glacial till, indicating a compact to very dense relative density (on average
dense in Boreholes 202 and 203, and very dense in the remaining boreholes).
2.1.5 Practical Refusal (Possible Weathered Bedrock)
Underlying the glacial till in Boreholes 101, 201-D and 401-D, possible weathered bedrock was inferred
at a depth of 22.9 m below grade (Elev. 101.8 to 102.1 m) based on the tri-cone grinding, drilling
observations, samples recovered, and the practical refusals observed. Boreholes 202 to 204 encountered
practical tri-cone and sampler refusal at depths of 17.6 to 19.5 m below grade (Elev. 10.54 to 107.0 m);
samples of the weathered bedrock were not recovered in these boreholes. It is not clear if this refusal was
on boulders or bedrock. Due to the site access, project time constraints and limited equipment availability,
rock coring was not performed at this site.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 5
2.2 Ground Water
The boreholes were cased by hollow stem augers or advanced using mud rotary techniques and contained
drill fluid upon completion of drilling, therefore depth to cave measurements were not practical. The
boreholes were instrumented with 50 mm dia. ground water monitoring wells to facilitate long-term
ground water monitoring. Stabilized ground water level measurements were made in the monitoring wells
at least one week after the completion of drilling. The ground water measurements are shown on the
Borehole Logs and are summarized as follows.
BH No.
Depth of BH (m)
On completion
(m) Strata Screened
Water Depth / Elev. (m)
July 3, 2018
Water Depth / Elev. (m)
July 4, 2018
Water Depth / Elev. (m)
July 8, 2018
Water Depth / Elev. (m)
Aug 7, 2018
Unstabilized Water Level
1 17.4 16.9 Sandy Silt
(Elev. 108.8 to 111.8 m) 5.4 / 119.6 5.4 / 119.6 5.7 / 119.3 5.5 / 119.5
2 9.8 7.5 Sandy Silt
(Elev. 115.5 to 118.5 m) 5.3 / 119.2 5.3 / 119.2 5.4 / 119.1 5.4 / 119.1
3 8.2 6.6 Gravelly Sand
(Elev. 117.3 to 120.3 m) 3.9 / 120.9 4.0 / 120.8 4.0 / 120.8 4.3 / 120.5
101 23.3 Dry Silt and Silt Glacial Till
(Elev. 102.0 to 105.1 m) 7.5 / 117.3 7.5 / 117.3 7.8 / 117.0 7.5 / 117.2
201-S 23 Dry Sand
(Elev. 117.5 to 120.5 m) 5.4 / 119.7 Not Measured 5.5 / 119.6
201-D 7.6
Contained drill fluid upon
completion of drilling.
Monitoring well not installed.
202 17.6 Gravelly Sand Glacial Till (Elev. 107.8 to 110.8 m)
7.3 / 117.4 Not
Measured 7.9 / 116.8 7.3 / 117.3
203 19.5 Sandy Silt Glacial Till and Sand
and Silt (Elev. 106.6 to 109.6 m)
5.3 / 119.6 5.3 / 119.6 6.7 / 118.2 5.5 / 119.4
204 18.4 Sandy Silt to Silty Sand Glacial
Till (Elev. 106.9 to 109.9 m)
5.3 / 119.7 5.3 / 119.7 6.8 / 118.2 5.5 / 119.5
205 18.6 Sandy Silt and Sandy Silt
Glacial Till (Elev. 107.5 to 110.5 m)
5.4 / 120.2 5.4 / 120.25 6.1 / 119.5 5.6 / 120.0
401-S 10.7 Sandy Silt
(Elev. 114.7 to 117.8 m) Wells were not installed during this
period.
5.5 / 119.9
401-D 22.4 Glacial Till
(Elev. 103.0 to 106.0 m) 6.5 / 118.9
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 6
For design purposes, the stabilized ground water table is at about Elev. 120 ±m. In general, the excavation
to the P5 FFE at Elev. 109.2 ±m will extend below the stabilized ground water table. The native sand is
considered a high permeability material, which will permit the free flow of water below the ground water
table. The glacial tills and sand silt soils are considered low to moderate permeability materials, and will
typically preclude the free flow of water; zones of cohesionless soils (sands and gravels) embedded within
the glacial till will produce water when penetrated.
Construction dewatering at adjacent sites, existing building drains or dewatering systems, and seasonal
fluctuations may cause significant changes to the depth of the ground water table over time. Additional
information pertaining to ground water at the site is discussed in the Hydrogeological Report by
Terraprobe under a separate cover (File No. 1-17-0848-46).
3.0 GEOTECHNICAL ENGINEERING DESIGN
The following discussion and recommendations are based on the factual data obtained from this
investigation, and are intended for use of the owner and the design engineer. Contractors bidding or
providing services on this project should review the factual data and determine their own conclusions
regarding construction methods and scheduling.
This report is provided on the basis of these terms of reference and on the assumption that the design
features relevant to the geotechnical analyses will be in accordance with applicable codes, standards and
guidelines of practice. If there are any changes to the site development features or any additional
information relevant to the interpretations made of the subsurface information with respect to the
geotechnical analyses or other recommendations, then Terraprobe should be retained to review the
implications of these changes with respect to the contents of this report.
Considering that the P5 level (FFE at Elev. 109.2 ±m) will be made in the wet cohesionless soils below
the ground water table (Elev. 120 ±m), Terraprobe recommends two options for the site:
1. Conventional spread footings, with waterproofed walls designed to withstand lateral hydrostatic
pressure (i.e. an impermeable interlocking caisson wall must be installed to control ground water
during construction), and a subfloor drainage system; or
2. Raft foundation with fully waterproofed walls and base (i.e. full “bathtub” solution).
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 7
3.1 Foundation Design Parameters
The proposed redevelopment includes demolishing the existing residential dwellings and constructing a
27-storey tower resting on a P5 underground parking structure, with a lowest finished floor elevation
(FFE) at Elev. 109.2 ±m. For design purposes, the stabilized ground water table is at about Elev. 120 ±m.
Below the P5 level (about 11 ±m below the stabilized ground water table) conventional spread footing
foundations would be made on very dense native soils below the stabilized ground water table. The soils
must be dewatered to a minimum of 1.2 m below the lowest founding elevation prior to reaching down to
the ground water table, to preserve the in situ integrity of the native cohesionless soils. If the subsurface is
not dewatered prior to excavation, the cohesionless soils will become disturbed by the ingress of ground
water and the following recommendations for bearing capacity will not be valid.
3.1.1 Spread Footing Foundations
Below the P5 level (FFE at Elev. 109.2 ±m), conventional spread footing foundations made to bear on the
dewatered very dense native soils at Elev. 108 ±m can be designed using a maximum factored
geotechnical resistance at ultimate limit state (ULS) of 900 kPa. The maximum net geotechnical reaction
at serviceability limit state (SLS) is 600 kPa, for an estimated total settlement of 25 mm.
For these bearing pressures, the minimum width of isolated footings must be 2.0 m. These minimum
dimensions apply regardless of loading considerations, in conjunction with the above recommended
geotechnical resistance. The settlement at SLS will occur as load is applied, and is linear and
non-recoverable. Differential settlement is a function of spacing, loading and foundation size.
Footings stepped from one level to another must be at a slope not exceeding 7 vertical to 10 horizontal.
The design earth cover for frost protection of foundations exposed to ambient environmental temperatures
is 1.2 metres in the Greater Toronto area. Experience suggests that the temperature in “unheated”
underground parking levels two or more levels below grade with normal ventilation provisions is not as
severe as the ambient open air condition. Certainly, the earth cover required to prevent frost effects on
foundations in the lower parking levels need not be any greater than 1.2 metres, and experience in a
number of structures has shown that perimeter foundations provided with 600 mm of cover perform
adequately as do interior isolated foundations with 900 mm of cover. At locations adjacent to ventilation
shafts, it is normal practice to provide insulation to ensure that foundations are not affected by the cold air
flow.
Prior to pouring concrete for the footings, the footing subgrade must be cleaned of deleterious materials,
softened, disturbed, or caved materials, and any standing water. As per the Ontario Building Code (2012),
the footing excavations must be inspected and approved by Terraprobe to ensure the bearing capacities
stated above are applicable. If soft soils are encountered at the proposed bearing depths during footing
excavation, sub-excavation to competent soil is required under the direction of the geotechnical engineer.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 8
Furthermore, native soils tend to weather and deteriorate on exposure to the atmosphere or to surface
water, therefore foundation bases that will remain open and exposed to the atmosphere for an extended
period of time shall be protected by applying a skim coat of lean concrete. If construction is to proceed in
freezing conditions, temporary frost protection for the footing bases and concrete must be provided.
3.1.2 Raft Foundation
If for whatever reason a drained foundation scheme is not used, then a raft slab and a fully waterproofed
structure could be considered. Should the underground levels be designed as a waterproof “tanked”
structure with no permanent dewatering, a raft foundation will be required to carry structural loads. A raft
foundation covering the whole width of the site (about 35 ±m) is considered in the discussion below on a
preliminary basis only. Pressuremeter testing could be performed at the site to improve the following
preliminary capacities.
Five (P5) Underground Levels
Considering five (P5) underground levels (Elev. 109.2 ±m), the excavation for a raft-supported structure
will remove about 250 kPa of effective stress at the raft base elevation (assumed Elev. 107.2 ±m).
Assuming that the foundation is made on dewatered, undisturbed native soils, a raft foundation bearing at
Elev. 107.2 ±m (about 2 ±m below the P5 FFE) can therefore be designed using an overall bearing
pressure of 250 kPa, resulting in no additional net change in effective stress on the foundation soils and
therefore negligible settlement. For up to 25 mm of settlement, a rigid raft foundation (about 35 ±m x
35 ±m) can be designed assuming a preliminary uniformly disturbed net geotechnical reaction at SLS of
160 kPa (i.e. a total bearing pressure at the raft base of 410 kPa). For up to 50 mm of settlement, a rigid
raft foundation (about 35 ±m x 35 ±m) can be designed using a preliminary uniformly distributed net
geotechnical reaction at SLS of 320 kPa (i.e. a total bearing pressure at the raft base of 570 kPa).
The modulus of subgrade reaction appropriate for the design of a raft supported on the undisturbed very
dense soils at Elev. 108 ±m is 11 MPa/m for 50 mm of settlement.
The maximum factored geotechnical resistance at ULS of a raft foundation at this elevation should be
limited to 2,000 kPa for preliminary purposes only.
General Raft Recommendations
It will be necessary to positively dewater the site to a minimum 1.2 m below the proposed bottom of the
raft founding elevation (i.e. to Elev. 106.8 ±m) prior to excavation to preserve the in situ integrity of the
native soils. If the subsurface is not dewatered prior to excavation, the native soils will become disturbed
by the ingress of ground water and the above recommendations for bearing capacity will not be valid.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 9
The site should not be excavated below Elev. 120 ±m without positive dewatering in place, to preserve
the native soils in their undisturbed state. A discussion on the dewatering approach is provided in
Section 4.2, using a caisson cutoff wall, and in Terraprobe’s Hydrogeological Report (File No.
1-17-0848-46)
During construction it will be necessary to consider the potential uplift pressure on the underside of a raft
foundation due to hydrostatic forces. Positive dewatering operations during construction must be
continued until such time as the factored structural dead load exceeds the potential factored uplift forces.
The raft design parameters provided here are based on assuming a conceptual uniform load imparted
across the entire base of the raft. In reality, the structural design of a raft will not produce uniform loading
at the base of the raft. Concentrated loads which locally exceed the SLS bearing pressure may not produce
a large amount of settlement, given their localized nature and reduced zone of influence. To account for
all of this, raft foundation design should be an iterative process between the structural and geotechnical
engineers. Once the preliminary structural design is complete and the induced loading at the base of the
raft is known, the resulting SLS loading and configuration must be assessed by Terraprobe and the
resulting total and differential settlements must be estimated. The settlement results are then reviewed by
the structural engineer, and the design is revised as needed.
3.2 Earthquake Design Parameters
The Ontario Building Code (2012) stipulates the methodology for earthquake design analysis, as set out
in Subsection 4.1.8.7. The determination of the type of analysis is predicated on the importance of the
structure, the spectral response acceleration and the site classification.
The parameters for determination of Site Classification for Seismic Site Response are set out in Table
4.1.8.4A of the Ontario Building Code (2012). The classification is based on the determination of the
average shear wave velocity in the top 30 metres of the site stratigraphy, where shear wave velocity (vs)
measurements have been taken. Alternatively, the classification is estimated on the basis of rational
analysis of undrained shear strength (su) or penetration resistance (N-values).
s avg
d
d
ii
n
i
sii
n
1
1
S u avg
d
d
s
ii
n
i
u ii
n
1
1
Navg
d
d
N
ii
n
i
ii
n
1
1
Shear wave velocity
Undrained shear strength
SPT N-values
Beneath the proposed foundations for this site, the site soils consist of very dense sandy silt and glacial
tills. Based on this information and a rational analysis of the SPT N-Values, It is recommended that the
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 10
site designation for seismic analysis is Class C for foundations made uniformly on very dense native soils,
as per Table 4.1.8.4.A of the Ontario Building Code (2012). Tables 4.1.8.4.B and 4.1.8.4.C. of the same
code provide the applicable acceleration and velocity-based site coefficients.
Site Class Values of Fa
Sa(0.2) ≤ 0.25 Sa(0.2) = 0.50 Sa(0.2) = 0.75 Sa(0.2) = 1.00 Sa(0.2)≥ 1.25
C 1.0 1.0 1.0 1.0 1.0
Site Class Values of Fv
Sa(1.0) ≤ 0.1 Sa(1.0) = 0.2 Sa(1.0) = 0.3 Sa(1.0) = 0.4 Sa(1.0) ≥ 0.5
C 1.0 1.0 1.0 1.0 1.0
3.3 Earth Pressure Design Parameters
The appropriate values for use in the design of structures subject to unbalanced earth pressures at this site
are tabulated as follows:
Stratum/Parameter γ φ Ka Ko Kp
Compact Granular Fill
Granular ‘B’ (OPSS 1010) 21 32 0.31 0.47 3.26
Existing Earth Fill 19 29 0.35 0.52 2.88
Native Sands and Silts 21 34 0.28 0.44 3.54
Glacial Till 21 36 0.26 0.41 3.85
where: γ = bulk unit weight of soil (kN/m3)
φ = internal angle of friction (degrees)
Ka = Rankine active earth pressure coefficient (dimensionless)
Ko = Rankine at-rest earth pressure coefficient (dimensionless)
Kp = Rankine passive earth pressure coefficient (dimensionless)
The above earth pressure parameters pertain to a horizontal grade condition behind a retaining structure.
Values of earth pressure parameters for an inclined retained grade condition will vary.
Walls subject to unbalanced earth pressures must be designed to resist a pressure that can be calculated
based on the following equation:
𝑷 = 𝑲[𝜸(𝒉 − 𝒉𝒘) + 𝜸′𝒉𝒘 + 𝒒] + 𝜸𝒘𝒉𝒘
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 11
where, P = the horizontal pressure at depth, h (m)
K = the earth pressure coefficient
hw = the depth below the groundwater level (m)
γ = the bulk unit weight of soil, (kN/m3)
γ’ = the submerged unit weight of the exterior soil, (γ - 9.8 kN/m3)
q = the complete surcharge loading (kPa)
The above equation pertains to a horizontal grade condition behind a retaining structure. Values of earth
pressure against retaining structures for an inclined retaining grade condition will vary.
Where the wall backfill can be drained effectively to eliminate hydrostatic pressures on the wall that
would otherwise act in conjunction with the earth pressure, this equation can be simplified to:
𝐏 = 𝐊[𝛄𝐡 + 𝐪]
To ensure that there is no hydrostatic pressure acting in conjunction with the earth pressure, where the
structure is built by open cut excavation methods, this equation assumes that free-draining granular
backfill such as Granular ‘B’ (OPSS 1010) is used and effective drainage is provided.
Consideration must also be given to the possible effects of frost on structures retaining earth. Pressures
induced by freezing in frost-susceptible soils exert pressures and are effectively irresistible.
The factored geotechnical resistance to sliding of earth retaining structures is developed by friction
between the base of the footing and the soil. This friction (R) depends on the normal load on the soil
contact (N) and the frictional resistance of the soil (tan φ) expressed as: R = N tan φ. This is an
unfactored resistance. The factored resistance at ULS is Rf = 0.8 N tan φ.
3.4 Slab on Grade Design Parameters
The P5 slab is set at Elev. 109.2 ±m, and will be made on dense to very dense native sandy silt and glacial
till. The native soils constitute an adequate subgrade for the support of a slab on grade for a drained
foundation scheme. The modulus of subgrade reaction appropriate for the design of a fully drained
slab-on-grade resting on the granular drainage layer resting on the native soils is 60,000 kPa/m.
Prior to the construction of the slab, it is recommended that the silt subgrade be cut neat and inspected
under the supervision of Terraprobe for obvious loose or disturbed areas as exposed, or for areas
containing excessively deleterious materials or moisture. Proof-rolling of the native subgrade is not
recommended as this will disturb the otherwise competent soil. These areas shall be recompacted in place
and retested, or else replaced with Granular B placed as engineered fill (in lifts 150 mm thick or less and
compacted to a minimum of 98 % SPMDD).
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 12
It is necessary that building floor slabs be provided with a capillary moisture barrier and drainage layer.
This is made by placing the slab on a minimum 300 mm layer of HL-8 Coarse Aggregate or 19 mm clear
stone (OPSS 1004) compacted by vibration to a dense state. Cohesionless soils below the stabilized
ground water table will be encountered at the subgrade for the slab on grade. Therefore, a suitable
non-woven geotextile filter (Terrafix 360R or equivalent approved by Terraprobe) must be installed (with
a minimum 900 mm overlap) below the HL-8 Coarse Aggregate or 19 mm clear stone; otherwise, without
proper filtering there may be entry of fines from the surrounding subgrade soils into the bedding. This
loss of ground could result in a loss of support of the slab and clogging of the subfloor drainage system.
The water level in the wet subgrade must be lowered at least 1.2 m below the lowest excavation elevation
prior to excavation for the duration of below grade construction. To preserve the integrity of the subgrade
once the subgrade elevation is reached, a skim coat of lean concrete could be applied to create a
trafficable surface.
If a waterproofed/tanked solution is chosen, then raft design parameters are provided in Section 3.1.2.
3.5 Basement Drainage
A separate Hydrogeological Report has been prepared by Terraprobe for this site
(File. No. 1-17-0848-46), which provides the approximate amount of daily temporary (construction) and
permanent ground water collection and discharge.
To assist in maintaining dry basements and preventing seepage, it is recommended that exterior grades
around the building be sloped away at a 2 % gradient or more, for a distance of at least 1.2 metres. For a
drained foundation scheme, provision of nominal subfloor drainage is required in conjunction with the
perimeter drainage of the structure, to collect and remove the water that infiltrates at the building
perimeter and under the floor. Perimeter and subfloor drainage are required throughout below grade areas.
It is recommended that the subfloor drainage system consists of minimum 100 mm diameter perforated
pipes wrapped in filter fabric spaced at a maximum of 3 metres on centre. The pipes must be surrounded
by a minimum of 100 mm of 19 mm clear stone/HL-8 Coarse Aggregate, and the pipe inverts should be a
minimum 300 mm below the base of the slab. The elevator pits can be drained separately with an
independent lower pumping sump or can be designed as water proof structures which are below the
drainage level. A typical basement subdrain detail is provided in Appendix C. The subfloor drains can be
constructed in trenches as shown in the typical detail, or alternatively they can be constructed on a flat
subgrade subexcavated at least 300 mm below the base of the slab.
Prefabricated drainage composites, such as Mirafi G-Series or Terradrain 200 (Terrafix), should be
incorporated between shoring walls and the cast-in-place concrete foundation wall to make a drained
cavity. Drainage from the cavity must be collected at the base of the wall in non-perforated pipes and
conveyed directly to the sumps. The flow to the building sump from the subsurface drainage will be
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 13
governed largely by the building perimeter drainage collection during rainfall and runoff events. Typical
shored and open cut excavation drainage details are provided in Appendix C.
The drainage system is a critical structural element, since it keeps water pressure from acting on the
basement floor slab or on the foundation walls. As such, the sump that ensures the performance of this
system must have a duplexed pump arrangement for 100% pumping redundancy and these pumps must be
on emergency power. The size of the pump should be adequate to accommodate the anticipated ground
water and storm event flows. It is expected that the seepage can be controlled with typical widely
available commercial sump pumps.
If for any reason a drained structure is not preferred, the structure could be designed as a waterproofed
structure designed to withstand hydrostatic pressures and uplift.
3.6 Site Servicing
3.6.1 Bedding
In general, the existing earth fill and native sand at the site compacted to a minimum of 98% SPMDD, or
neatly cut sandy silt and glacial till soils, will provide adequate support for buried services on a
conventional well graded granular base material. Where disturbance of the trench base has occurred, such
as due to ground water seepage or construction traffic, the disturbed soils should be sub-excavated and
replaced with suitably compacted granular fill.
Granular bedding material should consist of a conventional Class ‘B’ bedding, such as Granular ‘A’,
conforming to OPSS 1010 specification. The bedding material should be compacted to a minimum of
95% SPMDD. The use of HL 8 coarse aggregate (sewer stone) or 19 mm clear stone bedding is
prohibited at this site since without proper filtering, there may be entry of fines from the surrounding soils
into the bedding. This loss of ground could result in a loss of support to the pipes and possible future
settlements.
If services are situated in the cohesionless deposits below the stabilized ground water table
(Elev. 120 ±m), the subgrade must be dewatered a minimum of 1.2 m below the lowest excavation level
and trench plugs be installed to protect the groundwater and to prevent its lowering due to the “French
Drain” effect of the granular bedding and backfill material. The use of HL 8 coarse aggregate (sewer
stone) or 19 mm clear stone (OPSS 1004) bedding is not permitted.
3.6.2 Backfill
In general, excavated soils encountered on site may be re-used as backfill, provided the moisture content
of these materials is within 2% of optimum to ensure adequate compaction, the trenches are wide enough
to accommodate large compaction equipment, and the soil is free of any deleterious material (e.g. brick
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 14
fragments, cinders). Soils wet of optimum could be put aside to dry, tilled to reduce the moisture content
so that they can be effectively compacted, or could be mixed with less wet material. Alternatively,
materials of higher moisture content could be wasted and replaced with imported material which can be
readily compacted.
The backfill should consist of clean earth fill and should be placed in lifts of 150 mm thickness or less
and compacted to a minimum of 98% SPMMD (in settlement sensitive areas) and 95% SPMDD (in
non-settlement sensitive areas) at a water content within 2% of optimum. Existing earth fill and native
sandy silts and glacial tills will be difficult to place and compact successfully in narrow trench
excavations, where large compaction equipment could not operate. For narrow trench excavations, it is
recommended that free draining granular material, such as OPSS 1010 Granular ‘B’ be used in order to
allow for adequate compaction using vibratory equipment. The placement and inspection of any earth fill
as backfill must be conducted under the full time observation of Terraprobe, the geotechnical engineer.
The sandy silts and glacial tills are not immediately free draining and will be difficult to handle and
compact if they become wet as a result of inclement weather or seepage. Hence, it can be expected that
earthworks carried out during wet periods (i.e., spring and fall) of the year may result in increased
earthwork costs. The cohesive soils and specifically the silt at this site are susceptible to frost effects. If
the building has flush entrances, care must be taken in detailing the exterior slabs/sidewalks, providing
insulation and/or drainage and/or non-frost susceptible backfill to maintain the flush threshold during
freezing weather conditions.
3.6.3 Trench Plugs
Clay plugs are usually installed in trenches to protect the groundwater and to prevent its lowering due to
the “French Drain” effect of the granular bedding and backfill material. If the invert of the trench is below
the water table and local drawdown of the groundwater level cannot be tolerated for environmental or any
other reasons, then clay plugs must be installed within the granular bedding and the granular zones of
backfill material.
Clay plugs should be placed in the trenches at 50 m intervals along the full length of the trench, where the
invert of the trench is below the water table. The plug should be 1 m thick measured along the pipe, and
should completely replace the granular bedding and sand backfill placed above the springline and the
obvert of the sewer or watermain. The clay plugs must be compacted to 95% SPMDD. Material used for
the clay plugs should contain not less than 15% particles finer than 2 microns and should have a
coefficient of permeability less than 10-6
cm/second. Only the clayey silt to sandy silt portions of the
glacial till meets these criteria; in general, the majority of the site soils do not meet these criteria.
Unshrinkable fill can also be used as a substitute for clay plugs. Before construction the contractor should
submit a representative sample of the proposed clay plug material for permeability and particle size
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 15
testing to verify compliance with the specifications. During construction, further representative samples
should be tested to determine its acceptability.
Alternatively, cut off collars can be installed around the pipe barrel to achieve the same effect. Collars
should not be placed closer than 1.0 m to a pipe joint and precautions should be taken to ensure that 95%
compaction is achieved around the collars. Watertight connections are required between the collar and the
pipe wall.
4.0 DESIGN CONSIDERATIONS FOR CONSTRUCTABILITY
4.1 Excavations
Excavations must be carried out in accordance with the Occupational Health and Safety Act, Ontario
Regulation 213/91 (as amended), Construction Projects, Part III – Excavations, Sections 222 through 242.
These regulations designate four (4) broad classifications of soils to stipulate appropriate measures for
excavation safety. For practical purposes, the earth fill and native cohesionless soils (sands and silts) are
considered Type 3 soils above the ground water table and Type 4 below, and the glacial tills are
considered Type 2 soils.
Where workers must enter excavations advanced deeper than 1.2 m, the trench walls should be suitably
sloped and/or braced in accordance with the Occupational Health and Safety Act and Regulations for
Construction Projects. The regulation stipulates maximum slopes of excavation by soil type as follows:
Soil Type Base of Slope Steepest Slope Inclination
1 within 1.2 metres of bottom of trench 1 horizontal to 1 vertical
2 within 1.2 metres of bottom of trench 1 horizontal to 1 vertical
3 from bottom of trench 1 horizontal to 1 vertical
4 from bottom of trench 3 horizontal to 1 vertical
Minimum support system requirements for steeper excavations are stipulated in the Occupational Health
and Safety Act and Regulations for Construction Projects, and include provisions for timbering, shoring
and moveable trench boxes.
The overburden soils can be removed by conventional excavation equipment. Excavations at this site may
encounter construction debris, deleterious materials and other obstructions in the earth fill and native
cobble/boulder obstructions. The size and distribution of cobbles/boulders/obstructions cannot be
predicted with boreholes, as the sampler size is insufficient to secure representative particles of this size.
The risk and responsibility for the removal and disposal of cobbles/boulders/obstructions must be
addressed in the contract documents for foundations, excavations and shoring contractors.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 16
4.2 Ground Water Control
Ground water control and considerations pertaining to ground water and drainage are discussed in
Terraprobe’s Hydrogeological Report for the site under a separate cover (File No. 1-17-0848-46).
For design purposes, the stabilized ground water table is at about Elev. 120 ±m. The excavation to the P5
level (FFE at Elev. 109.2 ±m) will extend about 11 ±m below the stabilized ground water table. The
glacial tills and sand silt soils are considered low to moderate permeability materials, which will typically
preclude the free flow of water; zones of cohesionless soils embedded within the glacial till will produce
water when penetrated.
Positive dewatering during construction is required to a minimum 1.2 m below the lowest excavation
elevation prior to excavation below the stabilized ground water table. Without prior positive dewatering,
the native subgrade below the ground water table at this site will become disturbed and will lose their
integrity to support foundations. The water level must be kept at least 1.2 m below the lowest excavation
elevation during construction. The installation of a skim coat of lean concrete (mud-slab) is recommended
to preserve the subgrade integrity, and to provide a working platform.
An impermeable interlocking caisson wall is required and will be constructed along the entire extent of
the excavation, extending into the possible weathered bedrock; the soil overburden would be cut off,
precluding ground water flow into the excavation. For this situation, Terraprobe recommends advancing a
few additional boreholes (without sampling the soil overburden) to bedrock, with rock coring, to confirm
the bedrock elevation and quality at this site; dewatering can likely be accomplished by pumping from the
sealed excavation and cut-off using sump pumps. A caisson wall would also prevent any sloughing of
weak soils and loss of ground during lagging installation. It is possible that the bedrock elevation varies
considerably across the site due to proximity to the Humber River Valley.
The relevant project information must be provided to a professional dewatering contractor who will be
responsible for the design and installation of the dewatering systems. The dewatering system must be
properly installed and screened to ensure that sediment and fine soils are not removed, which could result
in settlement of the ground or structures near the site. Once the dewatering method and shoring system are
designed, Terraprobe should be retained to evaluate the potential impacts (i.e. settlement) to nearby
structures and land caused by lowering the water table.
If for any reason a drained structure is not preferred, the structure could be designed as a waterproofed
structure designed to withstand hydrostatic pressures and uplift. For a raft waterproofed foundation
scheme, the dewatering must remain on until such time as factored dead loads exceed factored uplift
loads.
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 17
4.3 Earth-Retention Shoring Systems
The site is bounded by municipal road Cordova Avenue to the north, and existing commercial properties
and associated parking lots to the south, east and west. No excavation shall extend below the foundations
of existing adjacent structures without adequate alternative support being provided. Where excavations
cannot be sloped, they can be supported using a shoring system such as soldier piles and lagging shoring
or a continuous interlocking caisson wall shoring.
Should soldier pile and lagging shoring be constructed, the wet cohesionless soils encountered below the
stabilized ground water table (Elev. 120 ׅ±m) could potentially slough into the excavation during the
installation of lagging boards, and may need to be dewatered prior to excavation for lagging installation.
The dewatering system must be filtered such that fines are not removed with the ground water resulting in
loss of ground.
The shoring system would best be supported by pre-stressed soil anchors extending beneath the adjacent
lands and municipal roads. Pre-stressed anchors are installed and stressed in advance of excavation and
this limits movement of the shoring system as much as is practically possible. The use of anchors on
adjacent properties requires the consent of the adjacent land owners, expressed in encroachment
agreements. The City Transportation and Works Department negotiates “permits” for the encroachment in
City lands, which are generally allowed.
4.3.1 Lateral Earth Pressure Distribution
If the shoring is supported with a single level of earth anchor or bracing, a triangular earth pressure
distribution similar to that used for the basement wall design is appropriate. Where multiple supports are
used to support the excavation, research has shown that a distributed pressure diagram more realistically
approximates the earth pressure on a shoring system of this type, when restrained by pre-tensioned
anchors. For the native cohesionless soils, the multi-level supported shoring can be designed based on a
rectangular earth pressure distribution with a maximum pressure defined by:
𝑷 = 𝟎. 𝟔𝟓 𝑲[𝜸𝑯 + 𝒒]
where, P = the horizontal pressure at depth, H (kPa)
K = the earth pressure coefficient (see Section 3.3)
H = the total depth of the excavation (m)
γ = the bulk unit weight of soil, (kN/m3)
q = the complete surcharge loading (kPa)
For ground water pressure distribution along the shoring wall in conjunction with the above soil
pressures, the stabilized ground water table should be taken at Elev. 120 ±m. The ground water pressure
distribution is only applicable where an impermeable boundary condition is created along the perimeter of
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 18
the excavation, as is the case with a continuous interlocking caisson wall. Conventional soldier pile and
lagging do not experience the water pressures, as water is allowed to drain freely through the wall.
4.3.2 Caisson and Soldier Pile Toe Embedment
Caisson and solider pile toes will be made in the very dense native soils below the P5 level. The
horizontal resistance of the caisson and solider pile toes will be developed by embedment below the base
of the excavation, where resistance is developed from passive earth pressure.
The native cohesionless soils at this site are sufficiently permeable and wet such that augered borings
made into these soils will be unstable. It is necessary to advance temporarily cased holes to the glacial till
to prevent excess caving during the soldier pile and all augered hole installations. Drill holes for piles,
caissons, and/or fillers, utilizing temporary liners, mud drilling techniques, and/or other methods as
deemed necessary by the contractor may be required to prevent issues such as: groundwater inflow or loss
of soil into the drill holes, and disturbance to placed concrete.
4.3.3 Lateral Bracing Elements
If anchor support is necessary and determined to be feasible, the shoring system should be supported by
pre-stressed soil anchors extending beneath the adjacent lands. Pre-stressed anchors are installed and
stressed in advance of excavation and this limits movement of the shoring system as much as is
practically possible. The use of anchors on adjacent properties requires the consent of the adjacent land
owners, expressed in encroachment agreements.
Conventional earth anchors could be made with a continuous hollow stem augers or alternatively
post-grouted wash bored anchors can be made. The design adhesion for earth anchors is controlled as
much by the installation technique as the soil and therefore a proto-type anchor must be made in each
anchor level executed to demonstrate the anchor capacity and validate the design assumptions. A
proto-type anchor must be made to demonstrate the anchor capacity (performance tested). All production
anchors must be proof-tested to 133% of the design load, to validate the design assumptions.
The subsurface soils are sufficiently cohesionless, permeable and/or wet that augered holes could
experience caving. It will be necessary to advance temporarily cased holes to maintain sidewall support
and to prevent the ingress of water during soldier pile (and caisson wall fillers, if applicable) installation,
use slurry, etc. or other means or methods deemed necessary by the contractor.
Conventional earth anchors made in the dense to very dense native soils may be designed using a working
adhesion of 60 kPa. It is expected that post-grouted anchors can be made such that an anchor will safely
carry about 80 kN/m of adhered anchor length (at a nominal diameter of 150 mm).
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 19
The very dense native soils at the P5 level (Elev. 109.2 ±m) are suitable for the placement of raker
foundations. Raker footings established on the native soils at an inclination of 45 degrees can be designed
for a maximum factored geotechnical resistance at ULS of 450 kPa.
4.4 Site Work
The earth fill and native soils at this site will become disturbed and may lose their integrity to support
when subjected to traffic, particularly when wet. It can be expected that a subgrade made in the native
soils will be disturbed unless dewatered to a minimum of 1.2 m below the lowest excavation elevation,
and an adequate granular working surface is provided to protect the integrity of the subgrade soils from
construction traffic, especially during periods of wet weather. Subgrade preparation works cannot be
adequately accomplished during wet weather and the project must be scheduled accordingly. The
disturbance caused by the traffic can result in the removal of disturbed soil and use of granular fill
material for site restoration or underfloor fill that is not intrinsic to the project requirements.
The most severe loading conditions on the subgrade may occur during construction. Consequently,
special provisions such as end dumping and forward spreading of earth and aggregate fills, restricted
construction lanes, and half-loads during placement of the granular base and other work may be required,
especially if construction is carried out during unfavourable weather.
If construction proceeds during freezing weather conditions, adequate temporary frost protection for the
founding subgrade and concrete must be provided. The native soils at this site are susceptible to frost
damage. Consideration must be given to frost effects, such as heave or softening, on exposed soil surfaces
in the context of this particular project development. Depending on the weather at the time of construction
it could be necessary to install a skim coat of lean concrete (mud-slab) to preserve the subgrade integrity,
and to provide a trafficable surface.
4.5 Quality Control
Prior to the start of excavation, it is advisable to complete visual pre-construction condition surveys of
adjacent lands and buildings. These surveys document the baseline condition at the start of construction
for the adjudication of any damage claims related to the works. Even a well-executed shoring system
designed with appropriate parameters cannot preclude all movements, and depending on the existing
condition of the adjacent structure, small changes in stress or soil volume can cause displacements or
cracking. The City of Toronto will require, as a condition of the excavation permit, that the shoring
performance be monitored as excavation proceeds. Terraprobe provides shoring monitoring services.
The proposed structure may be founded on conventional spread footings, deep foundations or a raft
foundation. The foundation installations must be reviewed in the field by Terraprobe, the geotechnical
engineer, as they are constructed. The on-site review of the condition of the foundation subgrade as the
foundations are constructed is an integral part of the geotechnical design function and is required by
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 20
Section 4.2.2.2 of the Ontario Building Code (2012). If Terraprobe is not retained to carry out foundation
evaluations during construction, then Terraprobe accepts no responsibility for the performance or non-
performance of the foundations, even if they are ostensibly constructed in accordance with the conceptual
design advice contained in this report.
The long term performance of the slab on grade is highly dependent upon the subgrade support
conditions. Stringent construction control procedures should be maintained to ensure that uniform
subgrade moisture and density conditions are achieved as much as practically possible. The design advice
in this report is based on an assessment of the subgrade support capabilities as indicated by the boreholes.
These conditions may vary across the site depending on the final design grades and therefore, the
preparation of the subgrade and the compaction of all fill should be monitored by Terraprobe at the time
of construction to confirm material quality, thickness, and to ensure adequate compaction.
The requirements for fill placement on this project have been stipulated relative to Standard Proctor
Maximum Dry Density (SPMDD). In situ determinations of density during fill placement on site are
required to demonstrate that the specified placement density is achieved. Terraprobe is a CNSC certified
operator of appropriate nuclear density gauges for this work and can provide sampling and testing
services for the project as necessary, with our qualified technical staff.
Concrete will be specified in accordance with the requirements of CAN3 - CSA A23.1. Terraprobe
maintains a CSA certified concrete laboratory and can provide concrete sampling and testing services for
the project as necessary.
Terraprobe staff can also provide quality control services for Building Envelope, Roofing and Structural
Steel, as necessary, for the Structural and Architectural quality control requirements of the project.
Terraprobe is certified by the Canadian Welding Bureau under W178.1-1996.
5.0 LIMITATIONS AND USE OF REPORT
5.1 Procedures
This investigation has been carried out using investigation techniques and engineering analysis methods
consistent with those ordinarily exercised by Terraprobe and other engineering practitioners, working
under similar conditions and subject to the time, financial and physical constraints applicable to this
project. The discussions and recommendations that have been presented are based on the factual data
obtained from this investigation.
The drilling work was carried out by a drilling contractor and was observed and recorded by Terraprobe
on a full time basis. The exterior boreholes were made by a continuous flight power auger machine using
hollow stem augers and mud rotary techniques. The Terraprobe technician logged the boreholes and
examined the samples as they were obtained. The samples obtained were sealed in clean, air-tight
Minto Cordova LP Revised (Rev.1): November 9, 2018 12, 16 & 20 Cordova Avenue, Toronto, Ontario File No. 1-17-0848-01
Terraprobe Page No. 21
containers and transferred to the Terraprobe laboratory, where they were reviewed for consistency of
description by a geotechnical engineer. Ground water monitoring wells were installed in both boreholes to
measure long-term ground water levels.
The samples of the strata penetrated were obtained using the Split-Barrel Method technique
(ASTM D1586). The samples were taken at intervals. The conventional interval sampling procedure used
for this investigation does not recover continuous samples of soil at any borehole location. There is
consequently some interpolation of the borehole layering between samples and indications of changes in
stratigraphy as shown on the borehole logs are approximate.
It must be recognized that there are special risks whenever engineering or related disciplines are applied
to identify subsurface conditions. A comprehensive sampling and testing programme implemented in
accordance with the most stringent level of care may fail to detect certain conditions. Terraprobe has
assumed for the purposes of providing design parameters and advice, that the conditions that exist
between sampling points are similar to those found at the sample locations.
It may not be possible to drill a sufficient number of boreholes, or sample and report them in a way that
would provide all the subsurface information and geotechnical advice to completely identify all aspects of
the site and works that could affect construction costs, techniques, equipment and scheduling. Contractors
bidding on or undertaking work on the project must be directed to draw their own conclusions as to how
the subsurface conditions may affect them, based on their own investigations and their own
interpretations of the factual investigation results, and their approach to the construction works, cognizant
of the risks implicit in the subsurface investigation activities.
5.2 Changes in Site and Scope
It must be recognized that the passage of time, natural occurrences, and direct or indirect human
intervention at or near the site have the potential to alter subsurface conditions. In particular, caution
should be exercised in the consideration of contractual responsibilities as they relate to control of seepage,
disturbance of soils, and frost protection.
The design parameters provided and the engineering advice offered in this report are based on the factual
data obtained from this investigation made at the site by Terraprobe and are intended for use by the owner
and its retained design consultants in the design phase of the project. If there are changes to the project
scope and development features, the interpretations made of the subsurface information, the geotechnical
design parameters, advice and comments relating to constructability issues and quality control may not be
relevant or complete for the project. Terraprobe should be retained to review the implications of such
changes with respect to the contents of this report.
FIGURES
TERRAPROBE INC.
SITE
SITE
FIGURE :Terraprobe11 Indell Lane, Brampton, Ontario, L6T 3Y3
Tel: (905) 796-2650 Fax: (905) 796-2250
Title:
File. No.:
SITE LOCATION PLAN
1-17-0848-01
1
REFERENCE
Microsoft Streets and Trips
T:\1-P
ro
ject Files\2017\1-17-0848 - 12, 16, 20,
24 C
ord
ova A
ven
ue, C
ity o
f To
ro
nto
\01-G
EO
In
vestig
atio
n\A
. D
wg
s, Lo
gs\A
uto
CA
D\1-17-0848-01 Fig
1 &
2.d
wg
, K
am
al
BH1
BH2
BH3
BH101
BH201D
BH 201S
BH202
BH205
BH203
BH204
PW1
BH301
BH302
401-S
401-D
FIGURE :Terraprobe11 Indell Lane, Brampton, Ontario, L6T 3Y3
Tel: (905) 796-2650 Fax: (905) 796-2250
Title:
File. No.:
BOREHOLE LOCATION PLAN
1-17-0848-01
(Proposed Condition)
3
REFERENCE
Project Name: 12-20 Cordova Ave
Project No.: 18-101,
Dwg No.: A1-1
Date: Nov. 16, 2018
By: Rafael+Bigauskas Architects
Approximate Borehole Location
Approximate Interior Borehole Location
Approximate Pump Well Location (Exterior)
LEGEND
Approximate Site Boundary
CORDOVA
AVENUE
Project North
T
r
u
e
N
o
r
t
h
T:\1-P
ro
ject Files\2017\1-17-0848 - 12, 16, 20,
24 C
ord
ova A
ven
ue, C
ity o
f To
ro
nto
\01-G
EO
In
vestig
atio
n\A
. D
wg
s, Lo
gs\A
uto
CA
D\1-17-0848-01 Fig
1 &
2 (2018-05-31).d
wg
, K
am
al
102
104
106
108
110
112
114
116
118
120
122
124
126
128
102
104
106
108
110
112
114
116
118
120
122
124
126
128
BH
1
BH
2
BH
3
BH
101
BH
201-
S-D
BH
202
BH
203
BH
204
BH
205
BH
301
BH
302BH
401-
S-D
Ele
vatio
n (m
)
EQUALLY SPACED Along SEC LINE BaselineLITHOLOGY GRAPHIC LEGEND
Asphalt
Fill
Sand
GravellySand
Sandy Silt
Sandy SiltTill
Aggregate
Sand andSilt Till
Bedrock
Blank
GravellySand Till
Clayey SiltTill
Sand andSilt
Silty SandTill
Concrete
Silty Sand
Sand andGravel
INTERPRETIVE LEGENDWL on completion of drilling
Stabilized WL, most recent
SITE MAP
Alignment: SEC LINEFrom E:618688, N:4833884, to E:618724, N:4833812
Rep
ort:
!SE
CT
ION
- T
AB
LOID
- E
LEV
File No.:11 Indell Lane, Brampton Ontario L6T 3Y3
(905) 796-26501-17-0848-01
Title:SUBSURFACE PROFILE
SEC LINE, EQUAL SPACING
COHESIVE SOILS(clayey silt to clay, incl.tills)
GRAVELS (gravel togravelly sand)
SILT TO SAND (not till)
0 -
34 -
62
- 4
0 -
8 -
82 -
10
50 m
m d
ia. m
onito
ring
wel
l
'N'
1 -
33 -
61
- 5
50 m
m d
ia. m
onito
ring
wel
l
'N'
24 -
60
- 11
- 5
50 m
m d
ia. m
onito
ring
wel
l
'N''N'
6 -
33 -
46
- 15
PL=
11%
LL=
16%
37 -
38
- 19
- 6
'N'
25 -
47
- 24
- 4
50 m
m d
ia. m
onito
ring
wel
l
'N'
3 -
34 -
49
- 14
PL=
11%
LL=
16%
0 -
55 -
43
- 2
50 m
m d
ia. m
onito
ring
wel
l
'N'
23 -
37
- 31
- 9
50 m
m d
ia. m
onito
ring
wel
l
'N'
50 m
m d
ia. m
onito
ring
wel
l
'N'
50 -
31
- 13
- 6
'N'
COHESIONLESS TILLSFILL
1
2
3
101
201-S-D
202
203
205
301 302
401-S-D
17
4
19
16
24
35
52
43
29
34
38
35
35
31
32
7
10
9
4
31
22
35
55
9
16
33
79
48
93 /225mm
50 /25mm
100
4
4
10
10
31
12
26
35
41
17
22
49
50 /125mm
50 /100mm
50 /100mm
50 /125mm
84 /250mm
96 /250mm
50 /125mm
50 /150mm
86
95 /275mm
71
62
100 /225mm
42
141
100 /150mm
100 /150mm
100 /150mm
23
47
72
46
28
50 /125mm
100 /150mm
100 /125mm
100 /100mm
50 /25mm
50 /125mm
73
36
38
37
26
35
50 /75mm
73 /275mm
4
22
27
39
50 /75mm
91 /275mm
50 /150mm
100 /275mm
97
73
56
67
100 /125mm
81
100 /100mm
7
14
24
72 /275mm
42
81 /275mm
63
73
88
71
48
38
49
43
100 /150mm
13
9
36
56
35
84
63
61
70
94 /250mm
50
43
44
47
50 /75mm
50 /125mm
50 /125mm
50 /25mm
APPENDICES
TERRAPROBE INC.
APPENDIX A
TERRAPROBE INC.
Terraprobe ABBREVIATIONS AND TERMINOLOGY
SAMPLING METHODS AS auger sample CORE cored sample DP direct push FV field vane GS grab sample SS split spoon ST shelby tube WS wash sample
PENETRATION RESISTANCE Standard Penetration Test (SPT) resistance ('N' values) is defined as the number of blows by a hammer weighing 63.6 kg (140 lb.) falling freely for a distance of 0.76 m (30 in.) required to advance a standard 50 mm (2 in.) diameter split spoon sampler for a distance of 0.3 m (12 in.). Dynamic Cone Test (DCT) resistance is defined as the number of blows by a hammer weighing 63.6 kg (140 lb.) falling freely for a distance of 0.76 m (30 in.) required to advance a conical steel point of 50 mm (2 in.) diameter and with 60° sides on 'A' size drill rods for a distance of 0.3 m (12 in.)."
COHESIONLESS SOILS
Compactness ‘N’ value
very loose < 4 loose 4 – 10 compact 10 – 30 dense 30 – 50 very dense > 50
COHESIVE SOILS
Consistency ‘N’ value Undrained Shear Strength (kPa)
very soft < 2 < 12 soft 2 – 4 12 – 25 firm 4 – 8 25 – 50 stiff 8 – 15 50 – 100 very stiff 15 – 30 100 – 200 hard > 30 > 200
COMPOSITION Term (e.g) % by weight
trace silt < 10 some silt 10 – 20 silty 20 – 35 sand and silt > 35
TESTS AND SYMBOLS
MH mechanical sieve and hydrometer analysis
w, wc water content
wL, LL liquid limit
wP, PL plastic limit
IP, PI plasticity index
k coefficient of permeability
γ soil unit weight, bulk
Gs specific gravity
φ’ internal friction angle
c’ effective cohesion
cu undrained shear strength
Unstabilized water level
1st water level measurement
2nd water level measurement
Most recent water level measurement
Undrained shear strength from field vane (with sensitivity)
Cc compression index
cv coefficient of consolidation
mv coefficient of compressibility
e void ratio
FIELD MOISTURE DESCRIPTIONS Damp refers to a soil sample that does not exhibit any observable pore water from field/hand inspection.
Moist refers to a soil sample that exhibits evidence of existing pore water (e.g. sample feels cool, cohesive soil is at plastic limit) but does not have visible pore water
Wet refers to a soil sample that has visible pore water
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Feb 26, 2018 6.1 119.0Feb 27, 2018 6.1 118.9Mar 2, 2018 6.0 119.0Mar 6, 2018 6.0 119.0Mar 23, 2018 6.3 118.7Apr 2, 2018 5.9 119.1Apr 26, 2018 5.6 119.4May 5, 2018 5.5 119.5May 14, 2018 5.5 119.5May 30, 2018 12.0 113.0Jun 14, 2018 5.8 119.2Jul 3, 2018 5.4 119.6Jul 4, 2018 5.4 119.6Jul 8, 2018 5.7 119.3Aug 7, 2018 5.5 119.5
50mm ASPHALT
FILL, silty sand, some clay, trace gravel,trace ash and cinders, trace brickfragments, trace rootlets, trace organics,compact, dark brown, moist
SAND, some stone fragments,compact, brown, moist
GRAVELLY SAND, trace silt, compact,brown, moist
SAND, some silt, dense to very dense,brown, moist
...at 6.1 m, wet
SANDY SILT, trace clay, dense, brown,moist to wet
...at 9.1 m, compact
...at 13.7 m, trace sand
SANDY SILT, some clay, trace gravel,dense, grey, moist(GLACIAL TILL)
END OF BOREHOLE
Unstabilized water level measured at16.9 m below ground surface uponcompletion of drilling.
50 mm dia. monitoring well installed.
1A1B
2
3
4A4B
5
6
7
8
9
10
11
12
13
14
PID: <5PID: <5
PID: <5
PID: <5
PID: <5PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
SS2 Analysis:PAH
SS3 Analysis:M&I
0 34 62 4
0 8 82 10
123.51.5
122.32.7
120.44.6
117.47.6
109.215.8
107.617.4
17
4
19
16
24
35
52
43
29
34
38
35
35
31
Uns
tabi
lized
Wat
er L
evel
125.0
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618696, N: 4833874 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
DZ
NN
JC
Drilling Method : Hollow stem augersRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : February 22, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 1fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Feb 26, 2018 6.0 118.5Feb 27, 2018 6.0 118.5Mar 2, 2018 5.9 118.6Mar 6, 2018 5.9 118.6Mar 23, 2018 5.8 118.7Apr 2, 2018 5.8 118.7Apr 26, 2018 5.0 119.5May 5, 2018 5.2 119.3May 14, 2018 5.2 119.3May 30, 2018 7.1 117.4Jun 14, 2018 5.4 119.1Jul 3, 2018 5.3 119.2Jul 4, 2018 5.3 119.2Jul 8, 2018 5.4 119.1Aug 7, 2018 5.4 119.1
50mm ASPHALT
FILL, silty sand, trace clay, trace gravel,trace ash and cinders, trace brickfragments, trace organics, dense, brown,moist...at 0.8 m, loose
SAND, some silt, compact to loose,brown, moist
GRAVELLY SAND, trace silt, dense,brown, moist
SANDY SILT, trace clay, compact todense, brown, wet
...at 7.6 m, grey
...at 9.1 m, very dense
END OF BOREHOLE
Unstabilized water level measured at7.5 m below ground surface uponcompletion of drilling.
50 mm dia. monitoring well installed.
1
2
3
4
5
6
7
8
9
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
SS1 Analysis:PAH
SS2 Analysis:M&I, VOC, PHC
SS3 Analysis:M&I
SS4 Analysis:PAH
1 33 61 5
SS8 Analysis:VOC, PHC
123.01.5
119.94.6
118.46.1
114.79.8
32
7
10
9
4
31
22
35
55
Uns
tabi
lized
Wat
er L
evel
124.5
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
121
120
119
118
117
116
115
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618724, N: 4833857 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
DZ
NN
JC
Drilling Method : Hollow stem augersRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : February 23, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 2fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Feb 26, 2018 4.7 120.1Feb 27, 2018 4.7 120.1Mar 2, 2018 4.6 120.2Mar 6, 2018 4.5 120.3Mar 23, 2018 4.4 120.4Apr 2, 2018 4.4 120.4Apr 26, 2018 3.8 121.0May 5, 2018 3.4 121.4May 14, 2018 3.4 121.4May 30, 2018 7.6 117.2Jun 14, 2018 3.8 121.0Jul 3, 2018 3.9 120.9Jul 4, 2018 4.0 120.8Jul 8, 2018 4.0 120.8Aug 7, 2018 4.3 120.5
130mm ASPHALT
FILL, silty sand, trace clay, trace gravel,trace brick fragments, trace organics,trace rootlets, loose to compact, darkbrown, moist
GRAVELLY SAND, trace silt, dense tovery dense, brown, moist
...at 4.6 m, some gravel, some silt, traceclay, wet
SANDY SILT, very dense, brown, wet
END OF BOREHOLE
Unstabilized water level measured at6.6 m below ground surface uponcompletion of drilling.
50 mm dia. monitoring well installed.
1
2
3
4
5
6
7
8
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
SS2 Analysis:M&I, PAH, VOC,PHC
SS5 Analysis:M&I, PAH
24 60 11 5
SS8 Analysis:VOC, PHC
123.31.5
117.27.6
116.68.2
9
16
33
79
48
93 /225mm
50 /25mm
100
Uns
tabi
lized
Wat
er L
evel
124.8
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
121
120
119
118
117
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618697, N: 4833830 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
DZ
NN
JC
Drilling Method : Hollow stem augersRig type : Truck-mounted
Project No. : 1-17-0848-01
Date started : February 22, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 3fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SSRUN
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Mar 27, 2018 7.7 117.0Apr 2, 2018 7.8 116.9Apr 26, 2018 7.4 117.3May 5, 2018 7.4 117.3May 14, 2018 7.4 117.3May 30, 2018 21.2 103.5Jun 14, 2018 8.3 116.4Jul 3, 2018 7.5 117.3Jul 4, 2018 7.5 117.3Jul 8, 2018 7.8 117.0Aug 7, 2018 7.5 117.2
15mm ASPHALT165mm AGGREGATE
FILL, silty sand, trace gravel, trace clay,trace rootlets, trace asphalt fragments,trace brick fragments, trace organics,loose, dark brown, moist
SAND, some silt, trace gravel, compactto dense, brown, moist
...at 4.6 m, wet below
...at 6.1 m, sandy silt layers
...at 7.6 m, grey
SANDY SILT, trace clay, compact, grey,moist
SANDY SILT, trace clay, trace gravel,dense to very dense, grey, moist(GLACIAL TILL)
SAND AND SILT, trace clay, tracegravel, very dense, grey, moist(GLACIAL TILL)
...at 21.3 m, contains trace shalefragments
POSSIBLE BEDROCK, weathered,grey, shale
END OF BOREHOLE
Borehole was dry upon completion ofdrilling.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
191
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: 10
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5...at 23.3m, corebarrel jammed
TCR = 100%SCR = 0%RQD = 0%
123.21.5
112.512.2
111.013.7
107.217.5
101.822.9
101.423.3
4
4
10
10
31
12
26
35
41
17
22
49
50 /125mm
50 /100mm
50 /100mm
50 /125mm
84 /250mm
96 /250mm
50 /125mm
Uns
tabi
lized
Wat
er L
evel
124.7
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
106
105
104
103
102
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618708, N: 4833861 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
JK
NN
JC
Drilling Method : Hollow stem augersRig type : Truck-mounted
Project No. : 1-17-0848-01
Date started : March 24, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 101fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
50mm ASPHALTIC CONCRETE
Refer to Borehole 1 for Stratigraphy.
SAND, some silt, very dense, brown,wet
SANDY SILT, trace clay, very dense,grey, wet
SANDY SILT, some clay, trace gravel,dense, grey, moist(GLACIAL TILL)
SAND AND GRAVEL, some silt, traceclay, very dense, grey, wet(GLACIAL TILL)
POSSIBLE BEDROCK, weatheredshale, grey
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
1
2
3
4
5
6
7
8
9
10
11
W1 WATER LEVELSDate Water Depth (m) Elevation (m)
Apr 26, 2018 5.8 119.2May 5, 2018 5.6 119.4May 14, 2018 5.6 119.4May 30, 2018 16.7 108.3Jun 14, 2018 5.4 119.6Jul 3, 2018 5.4 119.6Jul 4, 2018Aug 7, 2018 5.5 119.5
W2 WATER LEVELSDate Water Depth (m) Elevation (m)
Jul 4, 2018 5.9 119.1Jul 8, 2018 7.4 117.6Aug 7, 2018 7.1 117.9
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
...at 0.0m, straightdrilled to 7.6m
...at 7.6m, switchedto mud rotary
6 33 46 15
37 38 19 6
SS8 Analysis:VOC
...at 19.8m, triconegrinding to 21.3m
...at 22.7m, triconerefusal
117.47.6
115.99.1
108.216.8
106.718.3
102.1102.023.0
50 /150mm
86
95 /275mm
71
62
100 /225mm
42
141
100 /150mm
100 /150mm
100 /150mm
Uns
tabi
lized
Wat
er L
evel
125.0
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
106
105
104
103
102
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618695, N: 4833875 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : April 24, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 201-S-Dfi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Apr 26, 2018 2.1 122.5May 5, 2018 5.5 119.1May 14, 2018 5.5 119.1May 30, 2018 16.7 107.9Jun 14, 2018 7.9 116.7Jul 3, 2018 7.3 117.4Jul 8, 2018 7.9 116.8Aug 7, 2018 7.3 117.3
Straight drill to 20'
SAND, some silt, compact, brown, wet
SANDY SILT, trace clay, dense to verydense, grey, wet
SANDY SILT, some clay, trace gravel,compact, grey, moist(GLACIAL TILL)
GRAVELLY SAND, silty, trace clay, verydense, grey, moist(GLACIAL TILL)
CLAYEY SILT, some shale fragments,trace sand, trace gravel, hard, grey,moist(GLACIAL TILL)
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
50 mm dia. monitoring well installed.
1
2
3
4
5
6
7
8A8B9
PID: 0
PID: 0
PID: 0
PID: 0
PID: <5
PID: 0
PID: 0
PID: 0
PID: 0
...at 0.0m, straightdrilled to 6.1m
...at 6.1m, switchedto mud rotary
25 47 24 4
...at 17.2m, samplerbouncing triconerefusal
118.56.1
117.07.6
112.412.2
110.913.7
107.816.8
107.017.6
23
47
72
46
28
50 /125mm
100 /150mm
100 /125mm100 /
100mm
Uns
tabi
lized
Wat
er L
evel
124.6
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618723, N: 4833855 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : April 25, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 202fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Apr 26, 2018 3.6 121.3May 5, 2018 5.5 119.4May 14, 2018 5.5 119.4May 30, 2018 18.3 106.6Jun 14, 2018 6.0 118.9Jul 3, 2018 5.3 119.6Jul 4, 2018 5.3 119.6Jul 8, 2018 6.7 118.2Aug 7, 2018 5.5 119.4
Straight drill to 20'
GRAVELLY SAND, silty, trace clay, verydense, grey, moist
SANDY SILT, trace clay, very dense,grey, wet
SANDY SILT, some clay, trace gravel,dense to compact, grey, moist(GLACIAL TILL)
SAND AND SILT, trace clay, dense,grey, wet
CLAYEY SILT, some shale fragments,trace sand, trace gravel, hard, grey,moist(GLACIAL TILL)
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
50 mm dia. monitoring well installed.
1
2
3
4
5
6
7
8
9
10
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
straight drilled to6.1m
...at 6.1m, switchedto mud rotary
SS2 Analysis:M&I, PAH
SS3 Analysis:PHC
3 34 49 14
SS7 Analysis:VOC
0 55 43 2
...at 18.9m, triconerefusal
118.86.1
117.37.6
111.213.7
108.116.8
106.618.3
105.419.5
50 /25mm
50 /125mm
73
36
38
37
26
35
50 /75mm73 /
275mm
Uns
tabi
lized
Wat
er L
evel
124.9
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
106
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618698, N: 4833833 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : April 19, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 203fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Apr 26, 2018 4.7 120.3May 5, 2018 4.5 120.5May 14, 2018 4.5 120.5May 30, 2018 18.0 107.1Jun 14, 2018 6.2 118.8Jul 3, 2018 5.3 119.7Jul 4, 2018 5.3 119.7Jul 8, 2018 6.8 118.2Aug 7, 2018 5.5 119.5
50mm ASPHALT
FILL, sand, some silt, trace gravel, traceorganics, trace rootlets, trace plasticfragments, loose to compact, dark brownto brown, moist
SAND, some silt, dense, brown, moist
SANDY SILT, trace clay, trace gravel,very dense, brown, moist(GLACIAL TILL)
...at 4.6 m, gravelly
SANDY SILT, trace clay, very dense,grey, wet
...at 9.1 m, sand layer, wet
SANDY SILT, some clay, trace gravel,very dense, grey, moist(GLACIAL TILL)
SILTY SAND, some gravel, some shalefragments, trace clay, very dense, grey,moist(GLACIAL TILL)
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
50 mm dia. monitoring well installed.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
PID: 0
PID: 0
PID: 0
PID: <5
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
...at 0.8m, augergrinding to 1.4m
SS2 Analysis:M&I, PAH
SS3 Analysis:VOC, PHC
SS4 Analysis:M&I, PAH
...at 6.1m, switchedto mud rotary
SS8 Analysis:PHC
SS12 Analysis:VOC
...at 15.4m, samplerbouncing
23 37 31 9
...at 18.3m, loss fluidcirculation
122.72.3
122.03.0
117.47.6
109.815.2
108.216.8
106.618.4
4
22
27
39
50 /75mm
91 /275mm
50 /150mm
100 /275mm
97
73
56
67
100 /125mm
81
100 /100mm
Uns
tabi
lized
Wat
er L
evel
125.0
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618679, N: 4833832 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : April 23, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 204fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
Apr 26, 2018 5.5 120.1May 5, 2018 5.3 120.3May 14, 2018 5.3 120.3May 30, 2018 18.0 107.6Jun 14, 2018 5.3 120.3Jul 3, 2018 5.4 120.2Jul 4, 2018 5.4 120.2Jul 8, 2018 6.1 119.5Aug 7, 2018 5.6 120.0
50mm ASPHALTIC CONCRETE
FILL, sand, some silt, trace gravel, traceorganics, trace asphalt fragments, looseto compact, dark brown to brown, moist
SAND, some silt, trace gravel, verydense to dense, brown, moist
...at 6.1 m, wet
SANDY SILT, trace clay, very dense todense, grey, wet
SANDY SILT, some clay, trace gravel,dense, grey, moist(GLACIAL TILL)
...at 18.2 m, gravelly, very dense
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
50 mm dia. monitoring well installed.
1
2
3
4
5A5B
6
7
8
9
10
11
12
13
14
15
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
PID: 0
SS2 Analysis:M&I
SS3 Analysis:PAH, VOC, PHC
SS4 Analysis:M&I
5B Analysis:PAH
SS7 Analysis:PHC
SS14 Analysis:VOC
...at 18.2m, triconerefusal
123.32.3
118.07.6
108.816.8
107.018.6
7
14
24
72 /275mm
42
81 /275mm
63
73
88
71
48
38
49
43
100 /150mm
Uns
tabi
lized
Wat
er L
evel
125.6
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618677, N: 4833856 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : Track-mounted
Project No. : 1-17-0848-01
Date started : April 23, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 205fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
DP
DP
DP
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
May 30, 2018 2.0 122.8Jun 14, 2018 dry n/aJul 3, 2018 dry n/a
60mm CONCRETE
SILTY SAND, some gravel, compact,brown, damp
END OF BOREHOLE
Borehole was dry and open uponcompletion of drilling.
1
2
3
PID: 0
PID: 5
PID: 0
DP1 Analysis:VOC, PHC
DP3 Analysis:M&I, PAH, VOC,PHC
123.01.8
Uns
tabi
lized
Wat
er L
evel
124.8
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
Pocket Penetrometer Field Vane
SOIL PROFILE
TOP OF SLAB
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618705, N: 4833857 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Continuous samplingRig type : Pionjar, track-mounted
Project No. : 1-17-0848-01
Date started : May 14, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 301fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
DP
DP
DP
DP
WATER LEVEL READINGSDate Water Depth (m) Elevation (m)
May 30, 2018 2.5 122.2Jun 14, 2018 dry n/aJul 3, 2018 dry n/a
60mm CONCRETE
SILTY SAND, some gravel, compact,brown, damp
END OF BOREHOLE
Borehole was dry and open uponcompletion of drilling.
1
2
3A3B
4
PID: 0
PID: 0
PID: 0PID: 0
PID: 0
DP1 Analysis:VOC, PHC
DP4 Analysis:M&I, PAH, VOC,PHC121.8
2.9
Uns
tabi
lized
Wat
er L
evel
124.7
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
124
123
122
Pocket Penetrometer Field Vane
SOIL PROFILE
TOP OF SLAB
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618713, N: 4833841 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
TW
NN
JC
Drilling Method : Continuous samplingRig type : Pionjar, track-mounted
Project No. : 1-17-0848-01
Date started : May 14, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 302fi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
50mm ASPHALT
FILL, silty sand, some clay, trace gravel,trace brick fragments, trace cinders,loose to compact, dark brown, moist
SAND, trace to some silt, trace gravel,dense to very dense, brown, moist
...at 6.1 m, wet
SANDY SILT, trace clay, dense to verydense, grey, moist to wet
...at 12.2 m, wet below
SANDY SILT, some clay, trace gravel,dense, grey, moist(GLACIAL TILL)
SAND AND GRAVEL, silty, trace clay,trace shale fragments, very dense, grey,wet(GLACIAL TILL)...at 19.8 m, sandy gravel, some silt,trace clay
SAND, some silt, trace gravel, verydense, grey, wet
POSSIBLE BEDROCK
END OF BOREHOLE
Borehole contained drill water uponcompletion of drilling. Unstabilized waterlevel and cave not measured.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18W1 WATER LEVELS
Date Water Depth (m) Elevation (m)Aug 7, 2018 5.5 119.9
W2 WATER LEVELSDate Water Depth (m) Elevation (m)
Aug 7, 2018 6.5 118.9
PID: <5
PID: 15
PID: 10
PID: <5
PID: 5
PID: <5
PID: 10
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
PID: <5
SS1 Analysis:M&I, PAH
SS2 Analysis:VOC, PHC
...at 3.0m, switchedto mud rotary
SS5 Analysis:M&I, PAH, VOC,PHC
SS7 Analysis:VOC, PHC
...at 18.3m, tri-conegrinding
50 31 13 6...at 19.8m, tri-conegrinding to 21.3m
...at 22.4m, tri-conerefusal
123.91.5
117.87.6
110.215.2
107.118.3
104.121.3
103.0103.022.4
13
9
36
56
35
84
63
61
70
94 /250mm
50
43
44
47
50 /75mm
50 /125mm
50 /125mm
50 /25mm
Uns
tabi
lized
Wat
er L
evel
125.4
GRAIN SIZEDISTRIBUTION (%)
(MIT)
Gra
phic
Log
Typ
e
Description Unconfined
Num
ber
Ele
vatio
n S
cale
(m)
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
106
105
104
103
Pocket Penetrometer Field Vane
SOIL PROFILE
GROUND SURFACE
SAMPLES
Dynamic ConeMoisture / Plasticity
10 20 30
PL LLMC
PlasticLimit
NaturalWater Content
LiquidLimit
Hea
dspa
ceV
apou
r(p
pm)
Lab Dataand
Comments
Dep
th S
cale
(m
)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Lab Vane
Undrained Shear Strength (kPa)
40 80 120 160
ElevDepth
(m)
Inst
rum
ent
Det
ails
SP
T 'N
' Val
ue
SAGR SI CL
Position : E: 618686, N: 4833856 (UTM 17T) Elevation Datum : Geodetic
Originated by :
Compiled by :
Checked by :
MC
NN
JC
Drilling Method : Hollow stem augers / mud rotaryRig type : CME 75, truck-mounted
Project No. : 1-17-0848-01
Date started : July 4, 2018
Sheet No. : 1 of 1
Client : Minto Communities Inc.
Project : 12-20 Cordova Avenue
Location : Etobicoke, Ontario
LOG OF BOREHOLE 401-S-Dfi
le:
1-17
-084
8-01
bh
logs
.gpj
Penetration Test Values(Blows / 0.3m)
10 20 30 40
APPENDIX B
TERRAPROBE INC.
0
10
20
30
40
50
60
70
80
90
100
0.00010.0010.010.1110100
Percent R
etained (%
)
Grain Size (mm)
0
10
20
30
40
50
60
70
80
90
100
Gravel (%)Depth (m) Elev. (m)
MIT SYSTEM
Sand (%) Silt (%) Clay (%)SampleHole ID
Per
cent
Pas
sing
(%
)
(Fines, %)
SS10
SS12
SS7
11.0
14.0
6.4
113.0
110.0
118.2
0
0
1
34
8
33
62
82
61
4
10
5
1
1
2
MIT
SY
ST
EM SAND
CLAYSILT
2µm60µm2mm
COBBLESGRAVEL
COARSE MEDIUM FINE COARSE MEDIUM FINE
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
GRAIN SIZE DISTRIBUTION
SILT
0
10
20
30
40
50
60
70
80
90
100
0.00010.0010.010.1110100
Percent R
etained (%
)
Grain Size (mm)
0
10
20
30
40
50
60
70
80
90
100
Gravel (%)Depth (m) Elev. (m)
MIT SYSTEM
Sand (%) Silt (%) Clay (%)SampleHole ID
Per
cent
Pas
sing
(%
)
(Fines, %)
SS6 4.8 120.1 24 60 11 53
MIT
SY
ST
EM SAND
CLAYSILT
2µm60µm2mm
COBBLESGRAVEL
COARSE MEDIUM FINE COARSE MEDIUM FINE
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
GRAIN SIZE DISTRIBUTION
GRAVELLY SAND
0
10
20
30
40
50
60
70
80
90
100
0.00010.0010.010.1110100
Percent R
etained (%
)
Grain Size (mm)
0
10
20
30
40
50
60
70
80
90
100
Gravel (%)Depth (m) Elev. (m)
MIT SYSTEM
Sand (%) Silt (%) Clay (%)SampleHole ID
Per
cent
Pas
sing
(%
)
(Fines, %)
SS7
SS7
17.1
15.5
107.9
109.4
6
3
33
34
46
49
15
14
201D
203
MIT
SY
ST
EM SAND
CLAYSILT
2µm60µm2mm
COBBLESGRAVEL
COARSE MEDIUM FINE COARSE MEDIUM FINE
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
GRAIN SIZE DISTRIBUTION
UPPER GLACIAL TILLSANDY SILT GLACIAL TILL
0
10
20
30
40
50
60
70
80
90
100
0.00010.0010.010.1110100
Percent R
etained (%
)
Grain Size (mm)
0
10
20
30
40
50
60
70
80
90
100
Gravel (%)Depth (m) Elev. (m)
MIT SYSTEM
Sand (%) Silt (%) Clay (%)SampleHole ID
Per
cent
Pas
sing
(%
)
(Fines, %)
SS8 17.1 107.8 0 55 43 2203
MIT
SY
ST
EM SAND
CLAYSILT
2µm60µm2mm
COBBLESGRAVEL
COARSE MEDIUM FINE COARSE MEDIUM FINE
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
GRAIN SIZE DISTRIBUTION
SAND AND SILT
0
10
20
30
40
50
60
70
80
90
100
0.00010.0010.010.1110100
Percent R
etained (%
)
Grain Size (mm)
0
10
20
30
40
50
60
70
80
90
100
Gravel (%)Depth (m) Elev. (m)
MIT SYSTEM
Sand (%) Silt (%) Clay (%)SampleHole ID
Per
cent
Pas
sing
(%
)
(Fines, %)
SS8
SS6
SS14
SS16
18.5
13.9
17.1
19.9
106.5
110.7
107.9
105.5
37
25
23
50
38
47
37
31
19
24
31
13
6
4
9
6
201D
202
204
401D
MIT
SY
ST
EM SAND
CLAYSILT
2µm60µm2mm
COBBLESGRAVEL
COARSE MEDIUM FINE COARSE MEDIUM FINE
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
GRAIN SIZE DISTRIBUTION
LOWER GLACIAL TILL
0
10
20
30
40
50
60
0 10 20 30 40 50 60 70 80 90 100
MHor
OH
A - Line
Depth (m) Elev. (m)SampleBorehole
Pla
stic
ity In
dex
(PI,
%)
CL
CL
CH
Very High Extremely HighHighLow
Upper Plasticity Range
ML
CL - ML
Liquid Limit (LL, %)
SS7
SS7
17.1
15.5
107.9
109.4
11
11
MLorOL
201D
203
LL (%) PI (%)
5
5
PL (%)
16
16
Title:
1-17-0848-01File No.:11 Indell Lane, Brampton Ontario L6T 3Y3(905) 796-2650
ATTERBERG LIMITS CHART
APPENDIX C
TERRAPROBE INC.