111
06/27/22 Author: Prof. Dr.Tomas Ganiron Jr 1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change Plan 5-5 Risk Plan 5-6 Contracting

11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Embed Size (px)

Citation preview

Page 1: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 1

CHAPTER FIVE 5-PLANNING PROCESS

5-1 Quality plan5-2 Communication Plan5-3 Implementation Plan5-4 Change Plan 5-5 Risk Plan5-6 Contracting

Page 2: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 2

Quality

Meskimen’s LawWhen they want it bad,

they get it bad.

Page 3: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

4-1 Quality

Quality means many things to many peopleQuality ISO 8402: “the totality of features and

characteristics of a product or service that bear on its ability to satisfy started or implied needs”.

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 3

Page 4: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 4

Definitions: Quality

Fitness for use

Features they want

Customer value

Conformance to specifications.

Problems they don’t want.

Zero defects.

+

+

+

Page 5: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 5

Quality vs. Grade

• Grade — a category or rank given to entities having the same functional use but different requirements for quality:

– Ford Escort vs. BMW 635i

Page 6: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 6

Cost of Quality

• Cost of conformance:– Prevention costs– Appraisal (inspection) costs

• Cost of non-conformance:– Internal failure costs — fixes prior to delivery– External failure costs — fixes after delivery

Page 7: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

4-1 Quality plan

This plan details :• Quality assurance

– Establish organisational procedures and standards for quality.

• Quality planning– Select applicable procedures and standards for

a particular project and modify these as required.

• Quality control– Ensure that procedures and standards are

followed by the software development team.• Quality management should be separate from

project management to ensure independence.

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 7

Page 8: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Process-based quality

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 8

Define processDevelopproduct

Assess productquality

Standardiseprocess

Improveprocess

QualityOK

No Yes

Page 9: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 9

Quality assurance and standards

Standards are the key to effective quality management.

They may be international, national, organizational or project standards.

Product standards are specifications and criteria for the characteristics of products

Process standards are criteria for the way the products are made

Page 10: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 10

An Introduction toSix Sigma

Page 11: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 11

What Is Six Sigma? • Degree of variation;• Level of performance in terms of defects;• Statistical measurement of process capability;• Benchmark for comparison;• Process improvement methodology;• It is a Goal;• Strategy for change;• A commitment to customers to achieve an

acceptable level of performance

Page 12: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 12

Sigma Level

Defects Per Million Opportunities

Rate of Improvement

1 690,000

2 308,000 2 times

3 66,800 5 times

4 6,210 11 times

5 230 27 times

6 3.4 68 times

Page 13: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 14

ControlControlDefineDefine MeasureMeasure AnalyzeAnalyze ImproveImprove

Establish standards to maintain process;

Design the controls, implement and monitor.

Evaluate financial impact of the project

Identify, evaluate and select projects for improvement

Set goalsForm

teams.

Collect data on size of the selected problem,

identify key customer requirements,

Determine key product and process characteristic.

Analyze data, establish and confirm the “ vital few “ determinants of the performance.

Validate hypothesis

Improvement strategy

Develop ideas to remove root causes

Design and carry out experiments,

Optimize the process.

Final solutions

Six Sigma Project Phases

Page 14: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

4-2 Communications plan

The objectives of the Communication Plan are:

Help manage expectations regarding the project. Ensure methods used for communication will be most

effective. Assure appropriate levels of communication with internal and

external project stakeholders. Provide relevant, accurate, consistent information at all

times. Generate and sustain enthusiasm and support for the project

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 15

Page 15: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 16

COMMUNICATIONS PLAN OUTLINE MODEL Name of Project:Date: ____________

1. Intended audience(s)?

2. What is the main message we wish to communicate? What are secondary messages, and messages for

different audiences?

3. Time frame?

4. What relevant research, data (surveys, focus group results, similar projects elsewhere, etc.) are or will soon become available?

5. Why communicate? What do we want people to do as a result?

Page 16: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 17

6. Activities/publications/events associated with the plan

7. Resources required: funds; skills; equipment, supplies; staff time, temporaries, consultants

8. Who has primary responsibility? Who are the collaborators/helpers/supporters?

9. Who is responsible for internal communications around this plan, what needs to be done?

10. How will we evaluate/ /measure the success of the plan?

COMMUNICATIONS PLAN OUTLINE MODEL (cont)

Page 17: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

4-3 Implementation plan

This plan details who will be affected, how they will be affected and the plans for transitioning the change.

It ensures you have considered training and after change support, What will happen when the project winds up?

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 18

Page 18: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 19

Project plan: EHR ImplementationTask Duration Start FinishAssessment 5 days 1/8/06 1/13/06Select product selection group

0.5 days 1/9/06 1/9/06

Select project development team

0.5 days 1/9/06 1/9/06

Complete needs assessments

2 days 1/9/06 1/10/06

Develop project charter

5 days 1/9/06 1/13/06

Develop preliminary budget

3 days 1/9/06 1/11/06

Document current workflows

5 days 1/9/06 1/13/06

Implementation Project Plan Model

Page 19: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

4-4 Change Plan

Helpful tools for managing change are :

The Action and/or Issue register and The Change Control form/register.

What these two documents do is : Help you control the issues/risks/actions that people are

raising Help change will affect your project outcomes (time, cost or

scope)

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 20

Page 20: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Change Plan

Change process make sure the change is :

identified and approved.

Just because someone thinks a change would be a good idea doesn’t mean it should be added to your project.

Once you start to deliver something amazing, everyone will want to have a say. The challenge is to manage their expectations without compromising your original plan.

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 21

Page 21: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 22

Four Project Baselines

• Scope baseline = progressively detailed product description

• Stakeholder satisfaction baseline = project success criteria

• Cost baseline = budget• Schedule baseline = schedule

04/20/23

Page 22: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 23

Types of Changes

• Scope changes (modify product documentation and often project plan):

– Requirements changes– Clarifications– Site emergencies

• Work changes (modify project plan):– Resource changes– Modified approach– Corrective action

Page 23: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 24

Evaluating Change Requests

• All change requests are documented:– Emergency changes are documented after the

fact.– Non-emergencies are documented before

being considered.

• Change requests should be documented by the requestor.

04/20/23

Page 24: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 25

First Level Approvalof Change Requests

• Usually provided by the project manager or a senior team member:

– Are the expected benefits significant enough to merit further investigation?

• Implications:– Must have budget for this work!– Benefits may include cost avoidance– Organizational politics must be considered

04/20/23

Page 25: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 26

Second Level Approval of Change Requests

• Usually provided by a Change Control Board (CCB):

– Do the expected benefits outweigh any negative impacts?

• Implications:– Must have budget for this work!– Benefits may include cost avoidance– Organizational politics must be considered

04/20/23

Page 26: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 27

Change Control Board

• A formally constituted group responsible for approving or rejecting change requests.

• Powers and responsibilities should be well-defined and agreed upon in advance.

• On larger, more complex projects, there may be multiple CCBs.

04/20/23

Page 27: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 28

Change Plan Model

Page 28: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 29

Page 29: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 30

Page 30: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 31

4-5 Risk Plan

Project risk management does not deal with future decisions, but with the future of present

decisions.With apologies to

Peter Drucker

Page 31: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 32

Definition: Risk

• The possibility of suffering harm or loss. (American Heritage Dictionary)

• The potential for realizing unwanted, negative consequences from an event. (Rowe)

• More things can happen than will happen. (Dimson)

Risks are always in the future!

Page 32: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 33

Risks, Problems,and Responses

Risk

Risk Response

Problem

Problem Response

Page 33: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 34

Risk Management Processes: Identify

Prioritize

Respond

Monit

or

Identify

Page 34: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 35

Two Main Parts to a Risk Statement

• Cause• Source• Event• Condition

• Effect• Impact• Outcome• Consequence

If this happens and we do nothing …

… that this will happen

… there is a very real chance …

Page 35: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 36

A StructuredRisk Statement

Given that{cause or condition} …

there is a very real chance that {optional interim cause/effect} …

[such that {this success criteria}will be {affected in this way}.]

04/20/23

Page 36: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 37

Sample Risk Statement

Given that issues with the customer cannot be resolved in a timely fashion

there is a very real chance thatconfusion and disagreements over requirements may occur

such that our cost and schedule toleranceswill be exceeded.

04/20/23

Page 37: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 38

Review Project Success Criteria

• Start risk identification by reviewing your project success criteria:

– Product success– Project management success

• Document what could interfere:– Consider causes of problems from past projects– Use risk taxonomies (see next slide)

• Brainstorm what else could go wrong.

Page 38: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 39

Risk Taxonomy

• Definition — domain specific classification or categorization of risks.

• Objective — help to ensure that the most common risk causes have been identified.

04/20/23

Page 39: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 40

Specific classification or Categorization of risks. (A Simple Taxonomy)

• Environment — war, famine, flood, and pestilence; terrorism, pollution

• Economy — currency rate changes, market conditions, competition

• Government — changes in laws and regulations

• Company actions — change in strategic direction, internal politics

Page 40: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 41

… continued• Stakeholder actions — changes in

requirements, conflicts• Other projects — reliance on their staff or

their deliverables• Planning errors — WBS omissions, estimating

errors• Assumptions and constraints — things that

can go wrong

Page 41: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 42

Types of Impacts

• Impacts may affect the project, the business, or another project.

• Typical impacts include:– Cost overruns– Schedule delays– Shortfalls in scope or quality– Stakeholder dissatisfaction– Multiple impacts

04/20/23

Page 42: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 43

Summary of Key Points

• Risks are always in the future.• You can never eliminate all risk.• Focus your attention on the most severe

risks.

Page 43: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 44

4-6Negotiations

Learning Objectives• Upon completion, you should be able to:

– List the six foundations of negotiations– Identify five negotiating styles and four

categories of negotiations– Differentiate interests and positions– Prepare for a negotiation– Recognize and respond to a competitive

negotiation style04/20/23

Page 44: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 45

Please allow me to introduce myself …

04/20/23

Page 45: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 46

We’d like to know a little bit about you for our files …

04/20/23

Page 46: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 47

Proposed Norms

• Start (and end) on time• Ask questions• Electronics on silent• Short frequent breaks• Have fun!

04/20/23

Page 47: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 48

Core Concepts

The road to success is always under construction.Lily Tomlin

04/20/23

Page 48: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 49

Module Overview

• Definitions• Types of negotiations• Should you negotiate?• Six Foundations• Four Stages

04/20/23

Page 49: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 50

Dictionary Definition

“To confer with another or others in order to come to terms or reach an agreement;

to arrange or settle by discussionand mutual agreement.”

04/20/23

Page 50: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 51

A Practitioner’s View

“Think of negotiation as a cooperative enterprise: common interests must be

sought.In a good negotiation,

everybody wins something.”

Gerard Nierenberg

04/20/23

Page 51: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 52

Definition: Successful Negotiation

• Both sides think the other was fair.• Both sides feel the other side cared about their

needs.• Both sides believe the other side will fulfill the

agreement.• Both sides are reasonably satisfied with the

agreement.• Both sides would negotiate together again.

04/20/23

Page 52: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 53

Type III:Transactions

Type II:Relationship

Type IV:Tacit Coordination

Concern for ResultsHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

Type I:Balanced Concerns

Type III:Transactions

Type II:Relationship

Type IV:Tacit Coordination

Negotiating Situations

04/20/23

Page 53: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 54

… continued

• We will focus on Type I, Balanced Concerns, since that is the situation for most project negotiations.

• Each type of situation assumes that both sides have the same view — we will deal with what happens when the sides have different views later in the program.

04/20/23

Page 54: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 55

Should You Negotiate?

Not … if you are already in agreement.Not … if only one outcome is acceptable.Not … if time is of the essence and a decision

must be made.Not … if potential gains are not worth the

effort to prepare.

04/20/23

Page 55: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 56

NegotiationsIn a typical negotiation, the customer attempts to increase the performance specifications while reducing the schedule and the budgeted cost.

A common negotiation problem is deciding how to deal with the customer ‘s request to lower the price

If it is a competitive solicitation, the customer often will play off one prospective contractor against another to try to maximize his benefit

04/20/23

Page 56: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 57

Negotiations

Several things can help :

1-A good plan, well explained2-A clear understanding of your risk-response planning ( have you any padding? Any contingency budget?3-Management guidance , or clearance, on how much you can give up

04/20/23

Page 57: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 58

Negotiations

Several things can help :

4- A complete WBS with activity schedule and cost estimate can help to explain and defend to the prospective customer

5- A reputation for having met prior commitments

04/20/23

Page 58: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 59

Summary ofKey Points

• Negotiation is part art and part science.• Six Foundations define the concepts you

must master.• Four Stages define the process of

negotiating.

04/20/23

Page 59: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 60

Foundation 1:Your Negotiating Style

Nothing is quite as astonishing as common sense and plain dealing.Ralph Waldo Emerson

04/20/23

Page 60: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 61

Five Negotiating Styles

Concern for ResultsHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

N2. Collaborate

N1. Defeat

N3. Accommodate

N4. Withdraw

N5. Compromise

04/20/23

Page 61: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 62

Negotiating Style 5:Compromise

• Find an acceptable agreement:– Meet halfway.– Split the difference.– Look for trade-offs.

• Behavior in thoughtexperiment?

04/20/23

Page 62: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 63

Negotiating Style 3:Accommodate

• Accommodate the other party’s needs:– Good relationships produce good deals.– Maintain harmony.– Make concessions for the sake of the

relationship.

• Behavior in thoughtexperiment?

04/20/23

Page 63: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 64

Negotiating Style 1:Defeat

• Defeat the other party at any cost:– Drive a hard bargain.– Total victory is the goal.– There can be only one winner.

• Behavior in thoughtexperiment?

04/20/23

Page 64: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 65

Negotiating Style 4:Withdraw

• Withdraw and remove oneself:– Keep a low profile.– Results are beyond my influence.– Indifferent; resigned.

• Behavior in thoughtexperiment?

04/20/23

Page 65: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 66

Negotiating Style 2:Collaborate

• Work to build a win-win outcome:– Form a partnership.– Push for mutual gain.– Focus on problem-solving.

• Behavior in thoughtexperiment?

04/20/23

Page 66: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 67

What Style Do the Professionals Prefer?

• Of all lawyers:– 65% are consistently collaborative (N2)– 24% are consistently competitive (N1)

• Of those viewed as most effective:– 75% were consistently collaborative– 12% were consistently competitive

Study by Professor Gerald R. Williams

04/20/23

Page 67: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 68

… continued

• Irritators (i.e., insults, attacks):– Average negotiator = 10.8 per hour– Best negotiators = 2.3 per hour

• Emotion-laden comments:– Average negotiator = 6.3%– Best negotiators = 1.9%

04/20/23

Page 68: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 69

Personal Attributes ofthe Best Negotiators

• Listening skills• Willingness to prepare• Subject matter knowledge• Verbal communication ability• Analytic ability

04/20/23

Page 69: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 70

Summary ofKey Points

• Most people have a dominant or preferred style.

• Collaborative and cooperative behaviors are most successful.

04/20/23

Page 70: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 71

Module Overview

• Interests and positions• Discovering interests• Different kinds of interests

04/20/23

Page 71: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 72

Interests vs. Positions

• An interest is a need — it involves emotions and feelings.

Positions are (mostly) measurable and quantifiable.

• Interests are not negotiable — although they may change or new ones may be uncovered.

A position is one way to satisfy an interest.

04/20/23

Page 72: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 73

… continued

• Interests are the criteria we use to assess potential agreements — there are usually many positions that will satisfy our interests.

Positions are what we eventually agree to … but only when they satisfy our interests.

04/20/23

Page 73: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 74

Be Sure to Consider Personal Interests

• Ego, pride, and self-esteem• A need to win or be in control• Acceptance by others• Approval from others• Job pressures

04/20/23

Page 74: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 75

Summary ofKey Points

• Interests must be satisfied to reach agreement.

• Interests must be known to be satisfied.

04/20/23

Page 75: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 76

Sources of Authorityin Negotiations

• Position-based:– Corporate hierarchy– Documented policies and procedures

• Person-based:– Charisma– Knowledge– Connections

04/20/23

Page 76: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 77

Leverage

What Does Leverage Mean? the mechanical advantage gained by being in a position to use a lever.

04/20/23

Page 77: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 78

Understanding Leverage

• Leverage and power are not the same — power is objective, leverage is situational.

• Leverage changes over time — the side that most needs the deal now lacks leverage.

• Leverage is based on perception — the facts may not be relevant!

04/20/23

Page 78: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 79

Three Types of Leverage

• Positive — I have something you want.• Negative — I can cause you pain.• Normative — I can show you to be violating

the consistency principle.

04/20/23

Page 79: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 80

Sources of Leverage

• Time — project deadlines, fiscal year end• Competition — supply and demand• Marketability — name recognition• Opportunity — future business• Investment — emotional, financial• Environment — location, temperature, etc.

04/20/23

Page 80: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 81

… continued

• Information — public reports, body language, spoken comments

• Importance — strategic fit, financial impact• Pressure — from your boss• Composure — staying in control of yourself• Precedent — what happened last time?• Policy — law, ethics, procedures

04/20/23

Page 81: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 82

Threats

• Threats are usually made when I think I have leverage, but …

• When I make a threat, all of the outcomes mean trouble:

– You back down and resent it.– You don’t back down, I carry out my threat, our

relationship suffers.– You don’t back down, I don’t carry out my

threat, I lose credibility.

04/20/23

Page 82: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 83

Responding to Threats

• Control the urge to retaliate.• Acknowledge that a threat has been made by

explaining how the threat made you feel.• Restate the threat as a question.

04/20/23

Page 83: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 84

Type III:Transactions

Type IV:Tacit Coordination

Type II:Relationship

Concern for ResultsHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

Type I:Balanced Concerns

Negotiating Situations

04/20/23

Page 84: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 85

Concern for SubstanceHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

Collaborate

Defeat

Accommodate

Withdraw

Compromise

Negotiating Styles

04/20/23

Page 85: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 86

Concern for SubstanceHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

Collaborate

Defeat

Accommodate

Withdraw

Compromise

Styles and Situations,Matching Views

Balanced Concerns

Transactions

Relationship

Tacit Coordination

Y C Y C

Y CY C

04/20/23

Page 86: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 87

Match Your Styleto the Situation

• Type IV — Tacit Coordination– Example: getting seated on an airplane– Best strategies: withdraw, accommodate,

compromise

• Type III — Transactions– Example: purchase of a new car– Best strategies: defeat, collaborate,

compromise

04/20/23

Page 87: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 88

… continued

• Type II — Relationships– Example: marriage, repeat client– Best strategies: accommodate, collaborate,

compromise

• Type I — Balanced Concerns– Example: business merger, project staffing– Best strategies: collaborate, compromise

04/20/23

Page 88: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 89

Concern for SubstanceHighLow

Con

cern

for

Rela

tion

ship

Hig

hLo

w

Collaborate

Defeat

Accommodate

Withdraw

Compromise

Styles and Situations,Unmatched Views

Balanced Concerns

Transactions

Relationship

Tacit Coordination

Y

C

Y C

Y

C

04/20/23

Page 89: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 90

Developing Options

• Options are positions that will satisfy someone’s interests.

• More options mean a greater chance of finding a position that will satisfy everyone’s interests.

• Your counterpart’s view of the options may differ from yours.

04/20/23

Page 90: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 91

Preparation Is Key

• Document your analysis — interests, emotions, options, opening positions, giveaways.

• Anticipate their reactions — particularly to your opening positions.

04/20/23

Page 91: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 92

Summary ofKey Points

• Different circumstances require different strategies.

• Tools can be helpful, but the thinking is still up to you.

• Preparation is key.

04/20/23

Page 92: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 93

Summary ofKey Points

• Probe first, then disclose.• Behave purposefully.• Don’t lose sight of your interests.

04/20/23

Page 93: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 94

4-7 Contracting for Project Managers

04/20/23

Page 94: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 95

Project Management Processes

Scope definition, cost estimating, scheduling,

risk management, team building, procurement,

change control, stakeholder management, etc.

Projects, Procurement, and Contracts

Procurement Processes

Planning Acquisition Contract Management                                    

Procurement Processes

Contract

Contract

04/20/23

Page 95: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

Author: Prof. Dr.Tomas Ganiron Jr 96

Thesaurus (2):Buyer and Seller

• Different names:– Buyer = customer, sponsor, owner– Seller = vendor, supplier, contractor, provider

• Different perspectives:– For the buyer, the seller’s work is usually a

deliverable or subproject– For the seller, the contract is often a complete

project

04/20/23

Page 96: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 97

4-7 Contracting for Project Managers

Page 97: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 98

ContractsContracts Definition of Contracts

An agreement entered into by two parties or more with the intention of creating a legal obligation, which may have elements in writing.

Development of Contract Law◦ Common law once required all contracts to be

in writing, with a seal affixed.◦ Later, some payment was required before a

contract could be enforced.◦ Mutual promises became enforceable in the

1600’s.◦ By the 1900’s, courts began to consider the

fairness of contracts before enforcing them.

Page 98: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 99

Contracts

• Legally binding obligations may be called:– Agreements– Contracts– Memoranda of understanding (MOU)– Purchase orders– Others?

Page 99: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 100

Projects, Procurement, and Contracts

Project Management Processes

Scope definition, cost estimating, scheduling,

risk management, team building, procurement,

change control, stakeholder management, etc.

Procurement Processes

Planning Acquisition Contract Management                                    

Procurement Processes

Contract

Contract

Page 100: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 101

Buyer and Seller

• Different names:– Buyer = customer, sponsor, owner– Seller = vendor, supplier, contractor, provider

• Different perspectives:– For the buyer, the seller’s work is usually a

deliverable or subproject– For the seller, the contract is often a complete

project

Page 101: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 102

Underlying Philosophy• The buyer and the seller:

– Both want to be successful– Both want the other to be successful– Both see value in the relationship

• The cost of prevention is always less than the cost of the cure:

– Contracts do not solve problems– Contracts help prevent problems

Page 102: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 103

The Buyer/Seller Relationship

+

– +

+

+

–Differing Interests

Contract

Page 103: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 104

Valid Contract: A contract is one which is in full force and enforceable by court of

action

VALID CONTRACT MUST:

A. Be between competent parties.B. Accomplish a lawful purpose.C. Include an offer and acceptance of

that offer.D. Involve an exchange of value.

Page 104: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 105

A. Competent parties:– Legal age– With appropriate authority– Mentally competent

B. Lawful purpose:– Does not violate applicable laws– Compatible with public policy

Page 105: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 106

C. Offer and Acceptance

• Anything said or done that shows a willingness to exchange value.

• Offers and acceptances may be:– Written– Spoken (with limitations)– Demonstrated through action

Page 106: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 107

Example of Offer and Acceptance

• Offer — Projects wishes to engage PM Partners for project management consulting and training.

• Acceptance — PM Partners wishes to provide consulting and training to Projects and its clients.

Page 107: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 108

D. Exchange of Value

• Both parties must receive something: – Financial or non-financial– Directly or indirectly

• Also called “consideration”

Page 108: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 109

Example of Exchange of Value

• Buyer receives:– Financial value — product or service– Non-financial value — lower risk

• Seller receives:– Financial value — payment– Non-financial value — experience

Page 109: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 110

Is It a Contract?Why or Why Not?

1. Promise to assassinate a political leader?2. Signed by chief engineer?3. Verbal instructions in emergency?4. Employment agreement for $1 per year.5. Verbal promise to build a new plant?6. Written note saying “I owe you $100.”

Page 110: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 111

Penalties and Liquidated Damages

Contracts often provide that in case of a breach of the contract, the party aggrieved may collect from the other party a certain amount as liquidated damages, or simply damages. The courts will give effect to the intention of the parties provided the amount stated is, as a matter of fact, liquidated damages and not a penalty.

Page 111: 11/14/2015Author: Prof. Dr.Tomas Ganiron Jr1 CHAPTER FIVE 5-PLANNING PROCESS 5-1 Quality plan 5-2 Communication Plan 5-3 Implementation Plan 5-4 Change

04/20/23 Author: Prof. Dr.Tomas Ganiron Jr 112