SEMESTRAL PROJECT REPORTFor the First (1st) Semester of the Year 2017
Period : January 2017 to June 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 1
1 Executive Summary
1.1 Current Implementation Situation
1.1.1 Civil Works
Implementation of the WINRIP Project is scheduled to be implemented into three (3)Annual Work Programs (AWP's). The implementation starts with the preparation oftender documents (detailed design drawings including associated bidding documents),tendering stage (procurement of works) and the actual civil works constructionimplementation.
The original implementation schedules of the three (3) Annual Work Programs (AWPs)are scheduled in three (3) phases, namely ; AWP-1 to start in mid-2011 and to becompleted on the last quarter of 2014, AWP-2 is expected to begin in mid 2012 withtarget date of completion by mid-2016 and AWP-3 is expected to start during the earlypart of 2013 and to be completed during the middle part of 2017.
However, due to some unavoidable circumstances the original implementationschedules did not materialized.
Based on the present status of the program implementation progress, a revisedimplementation schedule, the Project Implementation Timeline (as shown onAppendix 1) is to be implemented in order to accommodate the originally delayedschedule into the remaining time frame of the WINRIP Program until the expiry date ofthe loan agreement by the end of December 2017. Shown on Appendix 2 is the currentconstruction status of the implementation relative to the Project ImplementationTimeline. Table 1 shows the present status.
Table 1 - Implementation Status as of End of the 1st Semester on June 30, 2017
Notes : Package No.9 (Rantau Tijang – Kota Agung), Package No.18 (Mukomuko – Bts. Sumbar) arecancelled from the program and Package No.10 (Sp. Empat – Sp. Air Balam) propose to becancelled.
PackPackage Name
Contract Under Under Defect LiabilityPeriodNo. Sign Construct
1 Krui - Biha √ Completed √2 Padang Sawah - Sp.Empat √ Completed √3 Manggopoh - Padang Sawah √ Completed √4 Ipuh - Bantal √ Completed √5 Sp. Rampa - Poriaha √ √6 Ps. Pedati - Kerkap √ Completed √7 Indrapura - Tapan √ √8 Bts.Pariaman - Manggopoh √ √
11 Bantal - Mukomuko √ Completed √12 Kambang - Indrapura √ √13 Sp. Rukis - Tj.Kemuning √ √14 Painan - Kambang √ √15 Sibolga - Bts.Tap Sel √ √16 Seblat - Ipuh √ √17 Sp.Gn.Kemala - Pg.Tampak √ √19 Lais - Bintunan √ Completed √20 Lubuk Alung - Sicincin √ √21 Lubuk Alung - Kuraijati √ √
T O T A L : 18 11 7
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 2
During the 2nd semester of this year 2016, four (4) contract packages were issuedNotice To Proceed (NTPs) to commence the works, contract agreements for one (1)sub-projects has been signed.
1.1.2 Consultancy Services
TA Consultant PlannedMobilization
ContractSigned
ActualMobilization
CTC Jul 2012 5 Nov 2012 12 Nov 2012
DSC Jul 2012 11 Jun 2013 19 Jun 2013
Capacity Building for DisasterRisks Reduction
Cancelled
Development of SlopeStabilization, Design andManagement
June 2017
Capacity Building forEnvironmental Management Cancelled
Capacity Building forRoad Safety Cancelled
1.2 Current Status of Loan
At the end of this semester on June 30, 2017 some 47.64% or USD 119.09 million of theavailable loan had been disbursed, which is 5.64% over the revised forecastedexpenditures of 42.00% (USD 105.00 million) at the end of the semester.
Total disbursements during this Semester amounted to USD 13.51 million coveringthe payments for "Statement of Work Accomplished' (MC) to civil worksContractors of the on-going construction packages and advance payments toContractors of newly started contract packages. Details of the Disbursements andExpenditures Status are presented in Appendix 1.
A more detailed and updated status of the loan are fully described and presented ineighteenth (18th) Semester Financial Report covering the 1st Semester (January - June)of the Year 2017 which is under preparation and will be submitted separately.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 3
1.3 Current Problems and Action Required
Program Activity Responsibility
AWP-14 Nos. Completed and provisionally handed over. Under defects
liability period for seven hundred and thirty (730) days.Contractor, DSC andPPK
AWP-2 & AWP-3
11Nos.seven (7) packages out of the eleven (11) packagesunder construction are way behind schedule with hugepercentages of negative progress slippages.Contractors of the problematic packages shall resolveimmediately the current problems. PPK and DSC shallclosely monitor the activities of the Contractor.
3 Nos. Completed and provisionally handed over. Under defectsliability period for seven hundred and thirty (730) days.
2 Nos. Cancelled.1 No. Proposal to be Cancelled.
Contractor , DSC
and PPK
Contractor, DSC and PPK
Capacity Building forDisaster Risks Reduction
Cancelled
Technical Assistance forDevelopment of SlopeStabilization, Design andManagement
Still in selection process. POKJA, Sub-Directorate ofGeotechnical and SlopeManagement, Directorate ofRoad Construction, DGH,MPWH
Capacity Building forEnvironmentalManagement
Cancelled
Capacity Building forRoad Safety Cancelled -
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 4
2 General
2.1 Reporting Requirements
Semestral Project Report: This Report have been prepared as stipulated and inaccordance with Schedule II (Project Monitoring Reporting and Evaluation) of the LoanAgreement and the Report shall not be made publicly available without clearanceand/or approval by DGH and the World Bank.
Quarterly Progress Reports: These have been prepared for each quarter since the 1st
quarter of the Year 2014 with the latest Report, submitted on the last week of Jan2017, as required and stipulated in CTC’s Consultancy contract. Prior to the productionof this report, Monthly Progress Reports have been prepared and have dealt with allaspects of the works. This report attempts to bring the situation up to date by coveringoverall progress up to the end of the semester.Financial Monitoring Reports: These have been prepared for each quarter since thebeginning of 2013 with the first Report, issued in May 2013, covering the periodJanuary — March 2013. Since that date quarterly reports have been prepared andsubmitted regularly.
Report Period Covered Date IssuedFinancial Monitoring Report No. 1 January 2013 – March 2013 May 15, 2013Financial Monitoring Report No. 2 April 2013 – June 2013 August 15, 2013Financial Monitoring Report No. 3 July 2013 – September 2013 November 15, 2013Financial Monitoring Report No. 4 October 2013 – December 2013 February 15, 2014Financial Monitoring Report No. 5 January 2014 – March 2014 May 15, 2014Financial Monitoring Report No. 6 April 2014 – June 2014 August 15, 2014Financial Monitoring Report No. 7 July 2014 – September 2014 November 15, 2014Financial Monitoring Report No. 8 October 2014 – December 2014 April 7, 2015Financial Monitoring Report No. 9 January 2015 – March 2015 August 31, 2015Financial Monitoring Report No. 10 April 2015 – June 2015 October 2, 2015Financial Monitoring Report No. 11 July 2015 – September 2015 December 16, 2015Financial Monitoring Report No. 12 October 2015 – December 2015 February 10, 2016Financial Monitoring Report No. 13 January 2016 – March 2016 June 8, 2016Financial Monitoring Report No. 14 April 2016 – June 2016 August 25, 2016Financial Monitoring Report No. 15 July 2016 – September 2016 December 2, 2016Financial Monitoring Report No. 16 October 2016 – December 2016 March 20, 2017Financial Monitoring Report No. 17 January 2017 – March 2017 June 14, 2017Financial Monitoring Report No. 18 April 2013 – June 2013 Under Preparation
CTC Monthly Progress Reports: These report have been prepared covering each fullmonth since January 2013. Subsequent reports have been submitted on a regularmonthly basis.Environmental Studies and Activity Reports: These report have been continuouslyupdated and submitted to PMU for submission to World Bank for Bank's issuance of NoObjection Letter (NOL). Appendix S-1 shows the summary of submitted of Reportscovering each contract package since inception of the Project.Social Impact Studies and Activity Reports: These report which mainly dealt with theimplementation of "Land Acquisition Resettlement Action Plan" (LARAP) have beencontinuously submitted to PMU for submission to World Bank for Bank's issuance ofNo Objection Letter (NOL). Appendix S-2 indicates the updated summary of all
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 5
#REF! 1,25
0,00
10,00
20,00
30,00
40,00
50,00
60,00
70,00
80,00
90,00
100,00
Month
% Co
mplet
e
Actual Expenditure USD119.09 mil (47.64%)
WINRIP ACTUAL PROGRESS UP TO JUNE 2017 AND FORECAST UP TO JUNE 2018
ACTUAL June 2017
Original Forecast
Forecast Expenditure Rev USD 105.00 mil(42.00%)
Forecast June 2017
Deviation = + 5.64 %
submitted Reports.Anti-Corruption Action Plan (ACAP) : Community Development Activity Reports:These Reports have been prepared and continuously submitted to the Client.Appendix S-3 shows the summary of submitted Reports from the very first (1st)submittal up to latest report before the Semester ended.Community Representative Observers (CRO) and Third Party Monitoring (TPM)Reports: These Reports were consolidated and reviewed by CTC as prepared andsubmitted by the appointed CRO's and TPMs of the respective contract package.Their reports were based on their actual observations and monitoring during pre-bid meetings, site visit and bid openings of every contract package under procurement.Appendix S-4 shows the updated summary of all reports which were forwarded to PMU.
2.2 Loan Status
The agreed allocation of loan funds from the original loan agreement together with the %disbursed to the end of the Semester date (June 30, 2016) is presented in Table 2.
Table 2
Category DescriptionLoan Restructuring
Amount US$
Total Disbursementfor the 1st Semester of
2017
PreviousDisbursement
Total Disbursed byWB to End June 30,
2017 in US$% Disbursed
1 Part 1 Betterment and CapacityExpansion of National Roads.
220,400,000.00 13,509,633.35 98,794,523.12 112.304.156,47 50.95
2 Part 2
Implementation Support
17,000,000.00 0 6,790,105.83 6,790,105.83 39.94
3Part 3
Road Sector InstitutionalDevelopment
0 0 0 0 0
4Part 4
Contingency for Disaster RiskResponse
0 0 0 0 0
Unallocated 12,600,000.00 0 0 0 0
Original LoanAmount
250,000,000.00 13,509,633.35 105,584,628.95 119.094.262,30 47.64
2.3 Financial Management
S-Curve for Financial Progress
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 6
A report at the end of the semester (June 30, 2011) is presented in Appendix 4, whileAppendix 5 is the Disbursement Plan estimated until December 2017, the expiry date ofthe Loan Agreement.
2.4 Project Cost MonitoringA detailed summary of the project cost monitoring in tabular format is presented asAppendix 6 at the end of this report.
2.5 World Bank Implementation Review Mission and Site Visit
During this 1st Semester, there was a World Bank supervision for implementation reviewtook place on Jul 17, 2017 with the kick off and wrap up meeting respectively.
The Technical and Financial Audit Consultant (TFAC) mission took place on 25, April 2017until 24, March 2017 with site visit inspection on Packages No.14, 20 and 20 respectively.
Introducing TFAC was held on January 2017 for Packages No.8, 12, 14, 16, 20 and 21 inPadang by World Bank.
An "Agreed Key Action Plans" for progress compliance monitoring of the status of theworks on monthly interval is shown in Table 3.
Table 3 “Agreed Key Action and Plans”
No. Action By WhomUpdate Status
July 17, 2017New Deadline
1.
Send to the World Bank (WB) the contractmodification request for package 03 (for additionalstone masonry) – World Bank will only approve it ifTFAC findings for packages 2 and 3 are followedup/contractor complies with his defect liability.
PMU and CTC.
After the follow-up bythe contractor of theTFAC findings of packages2 and 3
2. Send to the WB the request for contractmodification and time extension for package 05. PMU and CTC.
July 18, 2017
3. Send IPPKH license to work in the 1.59 km wherethe road crosses the protected forest for package 5. PMU and CTC.
September 11, 2017
4.Inform the WB about the possibility use ABPNmoney to construct the additional drainage underpackage 06 to avoid that water enters into a housingarea.
PMU, CTC andDSC.
This is included in 2018ABPN budget.
5. Send to the WB a reevaluation of the proposedsolution, including a unit rate analysis for theconcrete pavement construction for package 15.
WBEnd of July 2017
6.Send to the WB report with the results of theinvestigation conducted by the Inspectorate Generalregarding the problem of the undue invoice underpackage 14 and the follow up by Bina Marga.
PPK, PMU andCTC
End of July 2017
7.Inform the WB about what they plan to do withpackage 12 (PT LMA and PT. CTA), which is currentlyfor consideration with the Director (third showcause meeting failed).
PMU and CTC.Next review meeting
8.
Send WB the DSC report with analysis that showsthat the solution is adequate given the deteriorationof the pavement (cracking one year after overlay forbiking event- possible problems underneath) inpackage 20.
DSC, PMU andCTC.
End of July 2017
9. Inform the WB about the progress in package 21 (3rd
Show Cause Meeting succeeded). PMU and CTC.Next review meeting
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 7
No. Action By WhomUpdate Status
July 17, 2017New Deadline
10. Inform WB about the need for a contractmodification in Package 7 to include additional twoadditional sections.
PMU and CTC.Next review meeting
11. Package 8 may need a variation order for a secondlane for part of the section (contract ends inDecember 2017).
PMU and CTC.No deadline yet provided
12. Inform the WB about the reasons for differentaccumulated asphalt paving accounting by thecontractor/Engineer and CTC.
Next review meeting
13. Start contract for the slope stabilization, design, andmanagement assignment (11 months).
July 7, 2017
14. Send to the WB the 2nd DSC contract modificationfor price escalation. PMU and CTC.
No date provided
15. Send to the WB the information on how theinundated spots on the road of package 7 will befixed.
PMU and CTC.End of July 2017
16.
Re-send to the WB the revised environmentalmanagement and monitoring plan (RKPPL) forpackage 16, including additional info on part of thesection as well as the environmental documentationused to obtain the quarry licenses.
PMU and CTC.As soon as possible
17.Send to the WB the environmental managementand monitoring plan of RKPPLs and UKL-UPLimplementation quarterly and every semesterrespectively for all packages.
PMU and CTC.Quarterly and eachsemester
18.
Report to the WB on the implementation of theaction plan on how to avoid spills in base camps andimprove base camp management in all packageswith problems (including photos of progress in thefield)
PMU and CTC.Implementation ongoing
End of July 2017 or ifpossible earlier
19. Carry out the last HIV/AIDS workshop for package16. PMU/CTC/ DSC. Packages 16: May
2017
20. Provide WB with a list of the package with basecamp management issues (oil spills, inadequatedrainage).
PMU/CTCDone email to WB on 2May 2017
21. Training on base camp management for contactors,DSC, PPK. WB
Done on 11, 18 & 22 May2017
22. Send letters to the contractors informing them thatthey are violating the rules by not adhering tocertain base camp management practices.
DGH/PMU/CTC
Done (the list of lettersemailed to WB on 6 June2017)
23.Inform the WB on the role BLH and theenvironmental department of Bina Marga can playto improve base camp management performancesince this is against the local laws.
SubditLKJ/PMU/CTC
Mid-August 2017
24. Update the Winrip website with all environmentaldocuments including RKPPLs, RKPPL and othermonitoring reports, etc.
PMU and CTC.End of July 2017
25. Submit to the WB LARAPs monitoring reports forpackages 07, 08, 12, 13, 14, 15, 17, 20, and 21. PMU and CTC. Reporting ongoing
End of August 2017
26. For package 05, send to the WB the LARAPimplementation report for the remedial action. PMU and CTC.
DelayedSeptember 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 8
No. Action By WhomUpdate Status
July 17, 2017New Deadline
27. For package 05, send to the WB the additionalLARAP for additional affected assets. PMU and CTC.
Delayed Mid of August 2017
28.Submit to the WB the 2016 financial audit report. PMU and CTC.
End of Dec 2017
29. Submit to the WB the quarterly IFR for the periodApril to June 2017. PMU.
August 15, 2017
30. Send to the WB the TFAC response for the first visitof packages 20, 21, 14.
PMU/DSC/CTC.
Package 14: Underprocess
Package 20: Informal(June 5, 2017)Package 21: Informal(June 15, 2017)
Package 14: Mid ofAugust 2017
Package 20: End ofJuly 2017
31.Send to the WB the follow up to TFAC findings forpackages 3 (never received a feedback - concretedrainage broken, asphalt start waving, …) and 2(asphalt already broken).
Mid-August 2017.
32.Send to the WB the TFAC response:1. For the first visit of packages 05, 08, 13, 15 and 172. For the second visit of package 06packages 05, 06,08, 13, 15, and 17.
PMU/DSC/CTC.
Package 05: Done(April 4, 2017)
Package 06: Done(March 21, 2017)
Package 08: Done(March 31, 2017)
Package 13: Done(March 21, 2017)
Package 15: Done(March 31, 2017)
Package 17: Done(March 21, 2017)
33.
Send to the WB the TFAC response:1. For the first visit of package 12
2. For the second visit of packages 05, 08, 15, 07,13 and 17
PMU/DSC/CTC.
Package 05, August 9,2017
Package 08, August 10,2017
Package 15, August 9,2017
Package 07, August 11,2017
Package 13, August 18,2017
Package 17, August 14,2017
Package 12, August 11,2017
34. Next supervision mission document progress interms of cancelled component C. WB August 2017
35. Submit regularly to the WB the quarterly progressreports. PMU.
This activity must becarried out everycalendar quarter.
36.Update the newsletter quarterly, including the list ofcontracts, implementation progress, project relatedworkshops, and number, typology and status ofcomplaints.
PMU.
This activity must becarried out everycalendar quarter.
37. Send the quarterly newsletter to the civil societyforum in each project province in hard copy orthrough an electronic mailing system.
PMU.
This activity must becarried out everycalendar quarter.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 9
2.6 Project Steering Committee Meeting
No Steering Committee meeting during this 1st half of the Year 2016.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 10
3 Project Management and Implementation
3.1 Procurement Status
(A) Civil Works
Civil Works are now being implemented in Annual Work Programs (AWP) which havebeen numbered AWP-1, AWP-2, and AWP-3.
All Contract Agreements for the four (4) AWP-1 contract packages were signed by theend of 2013 with actual work commencement on January 2014.
Under the two (2) implementation programs, AWP-2 and AWP-3, fourteen (14) packageswere already procured, while the other one (1) remaining package is proposal to becancelled.
Table 4 Shows the actual pre-construction and procurement status under theimplementation schedules AWP-2 and AWP-3
Table 4
PackageNo. Package Name Status
AWP-2
5 Sp. Rampa - PoriahaProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on June 18, 2015
6 Ps. Pedati - Kerkap Procured. Under construction since the issuance of NoticeTo Proceed (NTP) on March 11, 2015
7 Indrapura — TapanProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on December 10, 2015
8 Bts. Pariaman — ManggopohProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on March 23, 2016
10 Sp. Empat — Sp. Air Balam
Cancelled . The road is still in relatively in good condition andwidening is not needed immediately.
11 Bantal - MukomukoProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on February 23, 2015
12 Kambang — IndrapuraProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on May 23, 2016.
13 Sp. Rukis — Tj. KemuningProcured. Under construction since the issuance ofNotice To Proceed on July 22, 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 11
PackageNo. Package Name Status
AWP-3
14 Painan — KambangProcured. Under construction since the issuance of NoticeTo Proceed on August 3, 2016
15 Sibolga — Bts. TapselProcured. Under construction since the issuance of NoticeTo Proceed (NTP) on November 20, 2015
16 Seblat - IpuhProcured. Under construction since the issuance of NoticeTo Proceed on November 8, 2016.
17 Sp.Gn.Kemala — Pg. TampakProcured. Under construction since the issuance of NoticeTo Proceed (NTP)on September 4, 2015.
19 Lais — Bintunan Procured. Construction completed. Under DefectNotification period for 730 days.
20 Lubuk Alung — SicincinProcured. Under construction since the issuance of NoticeTo Proceed on September 1, 2016.
21 Lubuk Alung - KuraitajiProcured. Under construction since the issuance of NoticeTo Proceed on September 1, 2016.
Note : Packages No.9 and No.18 are cancelled from the program.
Presented in Appendix 7 is the current status of procurement management.
(B) Services
The Core Team (CTC), Design & Supervision Consultant (DSC), and the others CapacityBuilding Consultancy status are discussed in Section 3.4.
3.2 Implementation Status – Civil Works
As of end of this reporting semester June 2017, seven (6) contract packages werecompleted and currently under detects liability period for twenty four (24) monthseffective on the day the TOC’s were issued.
Eleven (11) packages are currently under construction, details of each contract packageare shown in Table 5.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 12
Table 5
ProgramContractPackage
#Contractor Name of Road Province Contract
Signed
Commencement of
Work
Original
TimeExtension/Contraction
Revised
ContractAmount
ContractTime
CompletionDate Contract Amount Contract
TimeCompletion
Date
AWP-1
1 PT. Jaya KonstruksiManggala Pratama Tbk Biha - Krui Lampung Nov 25,
2013 Jan 8, 2014 134,909,211,000 640 CD Oct 9, 2015 93 CD 149,193,782,000 733 CD Jan 20, 2016
2PT.Jaya Konstruksi ManggalaPratama Tbk
Padang Sawah –Sp. Empat includingAir Gadang
WestSumatera Dec 6, 2013 Jan 6, 2014 197,936,699,000 730 CD Jan 5, 2016 105 CD 247,572,130,000 835 CD Apr 14,
2016
3 PT. Jaya KonstruksiManggala Pratama Tbk
Manggopoh –Padang Sawah
WestSumatera Dec 6, 2013 Jan 6, 2014 143,688,963,000 730 CD Jan 5, 2016 75 CD 183,940,872,000 805 CD Mar 17,
2016
4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal Bengkulu Nov 14,
2013 Jan 13, 2014 186,936,750,000 730 CD Jan 12, 2016 90 CD 194,902,179,000 820 CD May 31,2016
AWP-2
5 PT. Nusa KonstruksiEnjiniring Tbk.
Sp. Rampa -Poriaha
NorthSumatera
March 17,2015
June 18,2015 107,321,260,310 540 CD Dec 8, 2016 254 CD 107,321,260,310 794 CD Aug 19,
2017
6 PT. Waskita Karya (Persero)Tbk. Ps. Pedati - Kerkap Bengkulu Feb 27,
2015Mar 11,
2015 86,517,470,000 450 CD Jun 2, 2016 240 CD 118,444,156,000 690 CD Jan 28, 2017
7 PT. Adhi Karya Indrapura – Tapan WestSumatera
Nov 26,2015
Dec 10,2015 129,699,900,000 630 CD Aug 30,
2017 - 129,699,900,000 630 CD Aug 30,2017
8 PT. PP/PT. Statika MitraSarana J.O
Bts. Kota Pariaman- Manggopoh
WestSumatera Jan 28, 2016 Mar 23,
2016 355,500,000,000 720 CD Mar 12,2018 - 71 CD 355,500,000,000 645 CD Dec 31,
2017
11 PT. Hutama Karya/PT. DayaMulya J.O.
Bantal –Mukomuko Bengkulu Dec 18,
2014Feb 23,
2015 228,899,717,000 720 CD Feb 11,2017 104 CD 262,611,303,000 824 CD May 26,
2017
12 PT. Lancar Jaya/PT. CahayaT.A. J.O
Kambang –Indrapura
WestSumatera Jan 28, 2016 May 23,
2016 358,650,400,000 720 CD May 12,2018 -132 CD 358,650,400,000 588 CD Dec 31,
2017
13 PT. Waskita Karya (Persero)Tbk.
Sp. Rukis – TJ.Kemuning Bengkulu Dec 18,
2014July 22,
2015 292,700,000,000 720 CD July 10,2017 107 CD 292,700,000,000 827 CD Oct 25, 2017
AWP-3
14 PT. Yasa PatriaPerkasa/Conbloc, JO Painan – Kambang West
Sumatera Jun 1, 2016 Aug 3, 2016 214,327,429,680 630CD Apr 12,2018 -114 CD 214,322,429,000 516 CD Dec 31,
2017
15 PT. PembangunanPerumahan (Persero)
Sibolga – Bts.Tapsel
NorthSumatera
July 13,2015
Nov 20,2015 260,100,000,000 810 CD Feb 6, 2018 - 37 CD 260,100,000,000 773 CD Dec 31,
2017
16 KSO PT Yasa PP-MultiStructure Ipuh - seblat Bengkulu Oct 28, 2016 Nov 8, 2016 211,374,500,000 630CD July 30,
2018 - 211,374,500,000 630 CD Jul 30, 2018
17 PT. Jaya KonstruksiManggala Pratama Tbk
Sp. Gunung Kemala– Pugung Tampak Lampung Nov 17,
2014 Sept 4, 2015 199,551,000,000 720 CD Aug 23,2017 38 CD 199,551,233,000 801 CD Nop 12,
2017
19 PT. Roda Tekindo Purajaya Bintunan - Lais Bengkulu Feb 27,2015
Mar 11,2015 33,689,452,000 300 CD Jan 4, 2016 178 CD 44,419,760.000 478 CD June 30,
2016
20 PT. Nindya Karya Lubuk Alung –Sicincin
WestSumatera Jun 1, 2016 Sept 1, 2016 113,818,300,000 540 CD Feb 22,
2018 - 53 CD 113,818,300,000 487 CD Dec 31,2017
21 PT. Multi Structure Lubuk Alung –Kuraitaji
WestSumatera Jun 1, 2016 Sept 1, 2016 126,301,900,000 540 CD Feb 22,
2018 - 53 CD 126,301,900,000 487 CD Dec 31,2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 13
Activities done during this month on the on-going construction packages were repair andrestoration of deteriorated existing pavements, roadway excavation, embankmentformation, spreading of granular pavement for roadway widening, asphalt paving, structuralworks, construction of stone masonry side ditches, stockpiling of raw material, productionof crush aggregates, other minor works, bridge construction, finalization of “FieldEngineering” surveys and mobilization of resources of the newly started contract package.
The four (4) contract packages under implementation program AWP-1 were alreadycompleted and now under defects liability period for two (2) years since the issuance ofTOCs.
Under the implementation program AWP-2 and AWP-3, there are currently twelve (12)contract packages that are on-going construction implementation. Physical progress of six(6) of the packages are lagging far behind schedule with negative slippages from -34.62% to-12.21% while progress for the other four (4) packages are still slightly on or behindschedule, two (2) packages are on ahead schedule.
Progress status of the on-going civil works contracts as of this reporting period are shown inTable 4.2.
Following are brief status of the on-going construction contract packages:
Package No. 1 : Biha – KruiThe contract package is completed on January 20, 2016 and provisionally handed over to theEmployeer and currently under “Defects Notification Period” until after two (2) yearsreckoned from the issuance of the TOC.
A more detailed previous status during the whole duration of the contract implementationof this Package is presented in ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah – Sp. Empat (Including Air Gadang Bridge)The contract package is completed on April 14, 2016 and provisionally handed over to theEmployeer and currently under “Defects Notification Period” until after two (2) yearsreckoned from the issuance of the TOC.
ANNEX P-2 Executive Summary Report present a more detailed status during the wholeduration of the contract implementation of the Contract Package.
Package No. 3 : Manggopoh – Padang SawahThe contract package is completed on March 17, 2016 and provisionally handed over to theEmployeer on March 17, 2016 and currently under “Defects Notification Period” until aftertwo (2) years reckoned from the issuance of the TOC.
A more detailed status of the project progress during the whole duration of the contractimplementation are shown in ANNEX P-3 “Executive Summary Report”.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 14
Table 6
ProgramContractPackage
#Contractor Name of Road
Target ProgressSchedule Ending
June 2017
Actual ProgressAccomplished Slippage Time Elapsed Remaining
Time Remarks
AWP-1
1 PT. Jaya Konstruksi ManggalaPratama Tbk Biha - Krui * - - - - Completed
PHO : Jan 20, 2016
2PT. Jaya Konstruksi ManggalaPratama Tbk Padang Sawah – Sp.Empat
incl.Air Gadang * - -- - -Completed
PHO : April 14, 2016
3 PT. Jaya Konstruksi ManggalaPratama Tbk Manggopoh – Padang Sawah * - - - -
CompletedPHO : Mar 17, 2016
4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal * - - - -
CompletedPHO : May 31, 2016
AWP-2
5 PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha 99.43% 63.37% -28.32% -37.05% 33CD Based on revised contract timeand schedule
6 PT. Waskita Karya Tbk Ps. Pedati – Kerkap * - - - -Completed
PHO : Jan 28, 2017
7 PT. Adhi Karya Indrapura - Tapan 80.56% 55.86% -24.69% 88.24% 74 CDBased on revised contract timeand schedule
8 PT. PP/PT. Statika Mitra J.O Bts. Kota Pariaman –Manggopoh 73.96% 74.73% 0.77% 69.60% 197 CD
Based on revised contract timeand schedule
11 PT. Hutama Karya/ PT. DMT Mukomuko - Bantal * - - - - CompletedPHO : Jan 28, 2017
12 PT. Lancarjaya/PT. Cahaya T.A.JO Kambang – Indrapura 77.90% 11.93% -65.97% 66.44% 197 CD
Based on revised contract timeand schedule
13 PT. Waskita Karya (Persero) Tbk Sp. Rukis – Tj. Kemuning 97.87% 50.29% -47.58% 96.80% 23 CDBased on original contract timeand revised schedule
AWP-3
14 PT. Yasa – PT. Conbloc (JO) Painan – Kambang 37.80% 32.89% -4.91% 61.75% 197 CD Based on revised contract timeand schedule
15 PT. Pembangunan Perumahan(Persero) Sibolga – Bts. Tapsel 84.69% 43.75% -40.95% 74.48% 197 CD
Based on revised contract timeand schedule
16 PT Yasa-Multi Structure, Jo Seblat –Ipuh 10.78% 12.11% 1.33% 35.14% 408 CD
17 PT. Jaya Konstruksi ManggalaPratama Tbk Sp. Gn Kemala – Pg. Tampak 79.35% 77.53% -1.82.% 86.13% 105 CD Based on revised contract time
and schedule
19 PT. Rodatekindo Purajaya Lais - Bintunan * - - - - CompletedPHO : June 30, 2016
20 PT. Nindya Karya Lubuk Alung – Sicincin 71.88% 57.73% -14.15% 59.47% 197 CD Based on revised contract time21 PT. Multi Structure Lubuk Alung – Kuraitaji 55.91% 39.33% -16.58% 59.47% 197 CD Based on revised contract time
* Under defects liability period for 720 calendar days
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 15
Package No. 4 : Ipuh – BantalThe contract package is completed on May 31, 2016 and provisionally handed over to theEmployeer on May 31, 2016 and currently under “Defects Notification Period” until after two(2) years reckoned from the issuance of the TOC.
ANNEX P-4 “Executive Summary Report” shows the details and status of the project.
Shown in ANNEX P-4 “Executive Summary Report” showing the details and status of the
project.
Package No. 5 : Sp. Rampa – Poriaha
The progress as of this semester is only achieved of 62.37% against the scheduled 99.43%.
The completion date is 20, July 2017, thus the contractor is under preparation of anothercontract amendment for the increase of contract value and the extension of time.
ANNEX P-5 “Executive Summary Report” shows the Contractor’s Progress Schedule.
Package No. 6 : Kerkap – Ps. Pedati
The contract package is completed on January 28, 2017 and provisionally handed over tothe Employer and currently under “Defects Notification Period” until after two (2) yearsreckoned from the issuance of TOC.
ANNEX P-6 “Executive Summary Report” shows the complete details of the contractpackage.
Package No. 7: Indrapura – TapanThis semester progress is sharply increased of 5.41% comparing the previous monthprogress, 1.59%.
Nevertheless the main reason of improved progress was due to suspended working time forcrusher plants allowed by the local people. However the completion date of the works is30, August 2017, hence the contractor is preparing of the contract amendment of contractvalue and the extension of time including additional works of 4 km which is situated in theproject road.
ANNEX P-7 “Executive Summary Report” shows the complete details of the contractpackage.
Package No. 8 : Bts. Kota Pariaman - ManggopohThe progress as of this reporting semester is achieved of 74.73% against the scheduled73.96% having a little ahead 0.77%.
Currently unsettled land acquisition, 133 paps is critical issue hampering remaining progressof the works
ANNEX P-8 “Executive Summary Report” shows the complete details of the contractpackage.
Package No. 11 : Bantal - MukomukoThe completion date is on 26, May 2017 and the inspection for the provisional hand-over is
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 16
already done and the process verbal has been issued on 19, May 2017.
For more detailed of the Contract Package, refer to ANNEX P-11 “Executove SummaryReport”.
Package No. 12 : Kambang - IndrapuraThe progress as of this semester achieved of only 11.93% against the scheduled 77.90%having much lagged behind, -65.97%.
The main reasons for delayed progress are likely same as before. The Contractor is doing hisduty without any significant improvement of site operation inspite of huge delay ofprogress.
The client is still looking for a resolution about how to handle the contractor in accordancewith the contract conditions and what to be the most realistic provisions and measures tobe taken.
Details of the Contract Package are shown in ANNEX P-12 “Executive Summary Report”.
Package No. 13 : Sp. Rukis – Tj. KemuningThe progress as of this semester, 50.29% is much lagged behind the scheduled, 97.87%.
The completion date of this works is 10, July 2017. Hence, the contractor has proposed theextension of time for unsettled land acquisition of segment No. 2, about 18 km andsegment No. 3, about 2 km as of the end of May 2017.
Details of the work progress are shown in ANNEX P-13 “Executive Summary Reports.
Package No. 14: Painan - KambangThe Progress as of this semester is achieved of 32.89% against the scheduled 37.80% havingslippage rate -4.91%.
The progress of Asphalt pavement of this month is only 1.42% which is much less than theprevious month, 8.89% because of a little working areas for Asphalt paving works.Nevertheless this month progress of preparatory work like pavement widening & shoulders,granular pavement were done in very small areas. The contractor is repeatly advised toincrease the work forces for widening teams to accommodate the progress of Asphaltpaving works.
ANNEX P-14 “Executive Summary Report” shows the complete details of the project.
Package No. 15: Sibolga – Bts. TapselThe progress as of this semester is only 43.75% against the scheduled, 84.69% havingslippage rate -40.94%.
The main reasons of delayed progress are unsettled land acquisition, 12.9 km and delay ofrelocating the utilities of electrical poles (PLN) and water pipes (PDAM).
The contractor had being advised to propose for design changes of typical sections inaccordance with site situations utilizing the existing ROW (Ave. 11m width) for the areaswhich are situated un very densely populated road.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 17
Detailed and work progresses of the contract package are shown in ANNEX P-15 “ExecutiveSummary Report”.
Package No. 16 : Seblat – IpuhThis semester progress has been achieved of 3.43% against the scheduled, 3.63% and theaccumulated progress as of this months is 12.11% against the scheduled, 10.7% havingahead progress, 1.33%.
The progress of this month was made with various works like Drainage, Earthworks,Structures, etc. But the pavement works are no progress.The contractor has to concentrate for early start of asphalt paving works which is mostmajor weight of the works reached at 53.56% from the total.
ANNEX P-16 “Executive Summary Report” shows the complete details and work progressof the project.
Package No. 17 : Sp. Gunung Kemala – Pg. TampakThe progress of this semester is achieved of 4.80% against the scheduled, 4.02% havingahead of 0.78%.
Ac wearing course was started is this month and the working areas for AC-WC is in largestretches which could be constructed for 2 or 3 month.
The contractor should start for the minor works and shoulder final layer as soon as AC-WCcompletion
ANNEX P-17 “Executive Summary Report” shows the complete details and work progressof the project.
Package No. 19 : Lais – BintunanThe contract package is completed on June 30, 2016 and provisionally handed over to theemployer and currently under “Defects Notification Period” until after two (2) yearsreckoned from the issuance of the TOC.
Complete details of the contract package are shown in ANNEX P-19 “Executive SummaryReport”.
Package No. 20 : Lubuk Alung - SicincinThe progress as of this semester is achieved of 57.73% against the scheduled, 71.88%having slippage rate, -14.15% and this month progress, 3.50% is much lagged behind thelast month 7.45% especially asphalt paving works. Moreover, Drainage works are notconstructed for 2 consecutive months.
Unsettled land acquisition, 117 paps and delaying of relocation of utilities, PDAM waterpipes and electrical poles seem to be hampering the progress of works.
ANNEX P-20 “Executive Summary Report” shows the Contractor’s schedule and workprogress.
Package No. 21 : Lubuk Alung - KuraitajiThe progress as of this semester, 39.33% is much lagged behind the scheduled, 55.91%
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 18
having slippage rate -16.58%.
The progress of drainage works are sharply dropped down to 0.89% comparing to the lastmonth, 5.43%.
Furthermore, the progress of asphalt pavement works are also so slow. The Contractor hasto maintain the work continuous financial supports from their head office to maintain theprogress in more than normal.2
ANNEX P-21 “Executive Summary Report” shows the Contractor’s schedule and workprogress.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 19
3.3 Variation Order Details
To date, amendements and/or variation orders for six (6) construction contract packageswere already processed and approved by Pejabat Pembuat Komitmen (PPK), theauthorize Office to approve financial disbursement.
The approved variations orders were due to the following reasons :
a) Change of Engineer’s Team Leader from V. Thiagarajah to Johnson Villar and fromJohnson Villar to Efren L. Baccani.
b) Change of PPK Sub Project Manager.
c) Contract amount revision due to Technical Justification of Field Engineeringresults.
d) Revision of time for completion (time extension).
e) Contract amount revision due to contract price adjustment (escalation of unitrates).
f) Change of Contractor’s authorize representative.
g) Deletion of unspent provisional sum amounting to Rp. 7.1 Billion and balancing ofquantity overruns/underruns.
h) Final Quantity.
i) Change Bank Account
In regards with additive/deductive cost variations, original cost of the six (6) constructioncontract packages increases by Rp. 156,579,234,000 while the variation orders for theother contract packages are still under evaluation by DSC and PPK which is expected thatthe results will increase the respective original contract amounts.
In anticipation of future claims for varied works by the Contractors, 6% cost increases forpackages under AWP-2 and AWP-3 to cover any Variation Orders that may arise duringthe implementation of the Works.
Presented in Table 7 are details of Variation Orders for the four (4) sub-projects underAWP-1 and nine (9) contract packages covered by AWP-2 and AWP-3
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 20
Table 7 – Details of Variation Orders
Reason For Change :A – Change of Engineer’s Team Leader from V. Thiagarajah to Johnson Villar.B – Change of PPK Sub Project Manager.C – Contract amount revision due to Technical Justification of Field Engineering results.D – Revision of time for completion (time extension).E – Contract amount revision due to contract price adjustments (escalation).F – Change of Contractor’s authorize representative.G –Deletion of unspent provisional sum amounting to Rp. 7.1 Billion and balancing of quantity overruns/underruns.H –Final quantity (overuns/underruns).I – Change Bank Account.
PackageNo.
Original ContractAmount
(Rp)
AmendNo.
Variation +/-(Rp)
Revised ContractAmount (Rp) Variance % Time Extension Reason For
Change
1 134,909,211,000
1 0 134,909,211,000 0 - A2 +19,163,804,000 154,073,015,000 +14.20 - C3 0 154,073,015,000 0 - B4 0 154,073,015,000 0 93 D5 -13,817,995,000 140,255,020,000 -8,97 - G6 0 140,255,020,000 0 - A&B7 +8,938,762,000 149,193,782,000 +6,37 - E
2 197,936,699,000
1 0 197,936,699,000 0 - A2 0 197,936,699,000 0 - F3 0 197,936,699,000 0 - B4 +28,776,518,000 226,713,217,000 +14.54 - C5 0 226,713,217,000 +14.54 105 D6 +22,635,714,000 249,348,931,000 +25.97 - E7 0 249,348,931,000 +25.97 - B8 -1,776,801,000 247,572,130,000 -0.72% - E&H
3 143,688,963,000
1 0 143,688,963,000 0 - A2 0 143,688,963,000 0 - F3 0 143,688,963,000 0 - B4 +21,468,809,000 165,157,772,000 +14.94 - C5 0 165,157,772,000 +14.94 75 D6 +18,783,100,000 183,940,872,000 +11.37 - E7 0 183,940,872,000 0 - H8 -488,187,000 183,452,685,000 0 - E&H
4 186,936,750,000
1 0 186,936,750,000 0 - A2 +9,501,334,000 196,438,084,000 +5.08 - C3 0 196,438,084,000 +5.08 - B4 0 196,438,084,000 +5.08 90 D5 -1,535,905,000 194,902,179,000 -0.79 - H
5 107,321,260,0001 0 107,321,260,000 0 - A2 0 107,321,260,000 0 +224 D
8 355,500,000,0001 0 355,500,000,000 0 -81 D2 0 355,500,000,000 0 - C
11 228,899,717,0001 0 228,899,717,000 0 - B2 +33,711,586,000 262,611,303,000 +14.73 - C
12 358,650,400,000 1 0 358,650,400,000 0 -132 C&D
13 292,700,000,000
1 0 292,700,000,000 0 - I2 0 292,700,000,000 0 - B3 0 292,700,000,000 0 - F4 0 292,700,000,000 0 - C5 0 292,700,000,000 0 - C
14 214,322,429,000 1 0 214,322,429,000 0 -114 C&D15 260,100,000,000 1 0 260,100,000,000 0 -37 C&D17 199,551,233,000 1 0 199,551,233,000 0 - C
19 33,689,452,0001 0 33,689,452,000 0 - B2 +10,730,308,000 44,419,760,000 +31.85 125 CD
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 21
3.4 Consultancy ServicesTechnical Assistance for Core Team Consultant (CTC) to Support the ProjectManagement Unit.
Lead Consultant: PT. Perentjana Djaja
CTC Contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 Nov 2012 betweenthe Ministry of Public Works , Directorate of Planning, DGH and PT. Perentjana Djaja,Yongma Engineering Co. Ltd, PT. Epadascon Permata Engineering Consultant, JV and thework commenced on 12 November 2012.
Amendment No.1 to original contract was signed on October 25, 2013.
Amendment No. 2 was officially approved, on September 3, 2014.
Amendment No. 3 has been approved on November 30, 2015.
Amendment No. 4 to the current CTC Contract was signed on March 4, 2016.
Amendment No. 5 to the current CTC contract was signed on April 10, 2017.
Presented in Table 8 is the current status of CTC contract.
Table 8Description USD IDR
Original Contract including 10% VAT 1,404,370 23,556,940,000
Amendment No.1 including 10% VAT 1,447,517 24,668,792,500
Variance Against Original Contract +3,07% +4,72%
Combine Variance Against Original Contract +4.12%
Amendment No. 2 including 10% VAT 1,509,117 24,704,544,150
Variance Against Original Contract +7,46% +4,87%
Combine Variance Against Original Contract +5.81%
Amendment No.3 including 10% VAT 1,473,917 26,328,054,500
Variance Against Original Contract +4.95% +11.76%
Combine Variance Against Original Contract +9.29%
Amendment No. 4 including 10% VAT 1,918,158 40,878,169,529
Variance Against Original Contract +36.58% +73.53%
Combine Variance Against Original Contract +60.12%
Amendment No. 5 including 10% VAT 1,595,403.33 41,545,386,446
Variance Against Original Contract 13.69% 76.36%
Combine Variance Against Original Contract 53.58%Note : Combine variance (USD+IDR) is based on 1 USD = Rp. 9,558 exchange rate used during the
time of signing the original Contract Agreement.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 22
Technical Assistance for Design & Supervision Consultant (DSC)
Lead Consultant: Renardet S.A
DSC Contract No. KU.03.01/PPK-PR/WINRIP/Bx/01/VI/2013 was signed on 11 Jun 2013between the Ministry of Public Works, Head of Regional Office for National RoadsImplementation, BBPJN III, DGH and Renardet S.A. PT Cipta Strada, PT. Daya CreasiMitrayasa, PT. Seecons and PT. Yodya Karya (Persero) Joint Venture and mobilized on 19June 2013.
Table 9 shows the current status of DSC contract.
Table 9
Description USD IDR
Original Contract plus 10% VAT 902.660 57,000,575,500
Addendum No.1 plus 10% VAT 1,147,190 60,541,139,347
Variance Against Original Contract +27.09% +6.21%Note :
1)Adendum No.1 was approved by DGH on 18 December 2016 with World Bank concurranceand issuance of No Objection Letter (NOL)
Technical Assistance for Development of Slope Stabilization, Design and Management:
The Technical Assistance for Disaster Risk Reduction was canceled based on theresults of meeting between DGH and the WB on October 12, 2015. It was decided tocancel the Technical Assistance and replaced by a “Technical Assistance forDevelopment of Slope Stabilization, Design and Management” (under Loan Category-2).
As mentioned in previous Monthly Report, eight (8) interested consultants met thedeadline for submission of “Expression of Interest”. After POKJA’s evaluation, five (6)consulting firms made the shortlist, three (4) international and two (2) localcompanies.
The revised proposed shortlisted consultants from POKJA and the revised “RequestFor Proposal (RFP) have already been submitted to World Bank for request of NoObjection Letter (NOL). The World Bank had issued No Objection Letter for RFP andShortlisted Consultant respectively on September 23, 2016 and October 27, 2016.
RFP had sent by POKJA to all shortlisted consultants on November 2, 2016. Pre-Proposal Conference was held on November 22, 2016 and all shortlisted consultantsattended the event. The submission and opening the technical proposals was held onDecember 5, 2016. Three (3) consultants submitted the proposals, one (1) consultantwas late for submitting their proposal and other one (1) consultant did not submit theproposal.
POKJA evaluated the technical proposal first, while the financial proposal keep closedin envelope and will be opened after NOL for Techanical Evaluation Report (TER)issued by the World Bank. Evaluation of technical proposal was finalized by POKJA on
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 23
December 23, 2016 with issuance the Technical Evaluation Report (TER). CTC reviewedthe TER and submitted the founding issues and recommendation related the TER toPMU WINRIP on December 29, 2016.Procurement Plan for consulting services is presented in Appendix 8.
3.5 Implementation of the Anti-Corruption Act ion Plan
Community Representative Officers (CRO)
To date, the selection of Community Representative Observers (CRO) has been 100%completed for all the nineteen (19) contract packages with the last selection process wasconducted on November 17, 2015 in Padang for Contract Packages 14, 20 and 21. Theoverall total numbers of appointed CRO’s are thirty eight (38) individuals who were mostlyprofessional lecturers from different colleges or universities nearby to the projects.
All these thirty eight (38) CROs discharged their duties as independent observers fornineteen (19) Contract Packages during the procurement activities. All of CRO activitieshave finish on September 31, 2016.
A complete list of CROs appointed with their corresponding credentials can be found inAppendix 9.
Appendix 10 shows the activities of the CROs since the inception of the Project.
Third Party Monitors (TPM)
All of Third Party Monitors (TPM) for 19 Packages of WINRIP were appointed of fifty seven(57) TPM. But package 10 (Sp. Empat – Sp. Air Balam) is removed from the list of WINRIPprograms due to bidding failure, so there are only 18 packages were been contracted.Therefore the number of TPM appointment to date become 54 have been approved.
List of appointed TPM with their respective occupations and professional affiliations areshown in Appendix 11, while Appendix 12 shows the past to present activities/progress ofthe TPM.
Complaint Handling System (CHS)
The WINRIP website has been online, and available for reporting all aspects of the Anti-Corruption Action Plan including the registering of complaints by the general public. Thewebsite can be accessed at the URL address http://www.winrip-ibrd.com.
The CHS application has been completed. The application was put in sub-domain ofWINRIP website since February 2014. To access it, click on the sub-domain URL addresshttp://chs.winrip-ibrd.com. Appendix 13 and Appendix 14 show the Work Plan on CHSSystem and Work Activities on Publication/Disclosures.
The CHS team has been monitoring public complain via SiPP and WINRIP website.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 24
During this 2nd semester of 2016 there was no complaint monitored nor received. Detailsof previous complains are shown in Appendix 13.
Status of the implementation of the anti – corruption action plan is presented in Appendix15.
3.6 Implementation of the Environmental Management Plan and LARAP
A project category is assigned to each package as either Category A, B or C depending onthe likely degree of influence on environmental issues with a brief explanation as follows:
Category A project is one which will have a significant negative impact on theenvironment and may have an influence on areas outside the actual project area. Aproject classified as such requires an Amdal (Ka-Andal,Andal, RKL & RPL) study.
Category B project is one which affects the people or the environment to some extent butwith a smaller impact than a Category A. The required environmental analysis is a UKL-UPL study only.
Category C project has minimal effect on the people or environment and anenvironmental analysis is not required. SPPL are used to handle any minor problem whichmay arise.
Details of packages that require environmental and social safeguard are given inAppendix 16 and the following Table 10 provides a summary of the work involved in the18 WINRIP packages.
All the eighteen (18)packages require environmental impact investigations and studieswhich need the approval by Environmental Agency (BLH).
Eight (8) of the eighteen (18) packages are categorized under “Category A” projectswherein Amdal/EIA studies are required and have to be approved by World Bank. Theeight (8) packages are covered only by four (4) Amdal/EIA studies as some single studycovers a combination of two (2) or three (3) sub-projects as indicated in Table 10. While18 social studies (SLARAP and LARAP) require the approval of the World Bank. All the 18environmental studies for the eighteen (18) sub-projects including a separate study (UKL-UPL) for Air Gadang Bridge on Package No.2 were approved by BLH with 4 of these studies(Amdal/EIA) were granted No Objection Letter (NOL) from the World Bank while all the 18social studies (LARAP) were already issued No Objection Letter (NOL) from the WorldBank.
Appendix 16 details the list of Environmental Safeguard, Appendix 17 describes theEnvironmental Management Plan (EMP) Compliance and Appendix 18 is the status ofmonitoring the environmental mitigation up to the end of this Semester (June 2017).
While Appendix 19 shows the brief status and progress of environmental safeguards.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 25
Presented below Table 10 in a tabulated format is the current status of the environmentaland social studies.
Table 10
WorksProgram
No ofPackages
No of Investigations Approval by Remarks
BLH World Bank
AWP-1 4 9
1 - Amdal
2 – UKL-UPL
2 - SPPL
4 - Full LARAP
1 - Amdal
2 – UKL-UPL
2 - SPPL
1 - EIA
No Need
No Need
4 - Full LARAP
Coverage of SingleAmdal/EIA study arethe following Packages :
a) Packages 1 and 17
b) Package 7,12 and14
c) Package 11 and 16
d) Package 8
AWP-2 7 15
3 - Amdal
4 – UKL-UPL
1 - Simple LARAP
7 - Full LARAP
3 - Amdal
4 – UKL-UPL
3 - EIA
No Need
1 - SLARAP
7 - Full LARAP
AWP-3 7 13
1 - Amdal
5 – UKL-UPL
7 - Full LARAP
1 – Amdal;
5 – UKL-UPL
1 - EIA
No Need
8 - Full LARAP
Total 18 37 Env=18,Soc=19 18 Env= 4, Soc=19
Note: 1) UKL & UPL do not need a NOL from WB, and SPPL not necessary to submit to the WB.
2) Packages 9 and 18 to be deleted.
3) Air Gadang Bridge have separate investigation, hence, total equals 22.
Approximately, the construction implementation of the nineteen (19) civil works contractpackages affected 27,791 peoples with the removal of their improvements such ashouses, fruit trees, fences, terraces, entrance ramps and other obstruction within theroad right of way. In the end of this semester, 21,398 have been compensated or 77.1%of the overall PAPs.
Likewise, the affected total land areas that requires acquisition is approximately 510,609square meters (revision due to the package 20 and 21 not need land acquisition). To date,462,797 square meters has been acquired while the remaining right of way areas are stillunder process. Overall progress of land acquisition 90.64%.
Appendix 20 shows the status of overall land acquisition and Table 11 present thenumbers of Project Affected People (PAP) for each sub-project. Appendix 21 presents theupdate status of Social safeguards, Disclosures and Progress of LARAP implementations.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 26
Table 11
PackageNo.
Name Of Road Total PAP Compensated %Completed
Remarks
1 Krui - Biha 2,815 2,815 100.00
2 Padang Sawah – Sp. Empat 442 442 100.00 Updated
3 Manggopoh – Pd. Sawah 1,338 1,338 100.00
4 Ipuh – Bantal 257 257 100.00
5 Sp. Rampa – Poriaha 78 68 87.18
6 Pasar Pedati – Kerkap 637 637 100.00
7 Indrapura – Tapan 891 840 94.00 Updated
8 Bts. Pariaman – Manggopoh 2.339 2,206 94.00 Updated
10 Sp. Empat – Sp. Air Balam 2,915 1,725 59.18
11 Bantal – Mukomuko 243 243 100.00
12 Kambang – Indrapura 2,992 1,196 40.00 Updated
13 Sp. Rukis – Tj. Kemuning 2,917 2,471 84.71 Updated
14 Painan – Kambang 2,589 1,268 49.00 Updated
15 Sibolga – Bts. Tapsel 2,003 711 35.00 Updated
16 Seblat – Ipuh 259 259 100.00 Updated
17 Sp. Gunung Kemala – Pg. Tampak 25.21 2.507 99.44 Updated
19 Lais – Bintunan 556 556 100.00
20 Lubuk Alung – Sicincin 1.070 977 91.31 Tentative
21 Lubuk Alung – Kuraitaji 929 882 94.94 Tentative
TOTAL 27,791 21,398 77.00
Note : The numbers of PAPs on each contract packages varies from time to time during thefinalization of the supporting documents for the payments of affected improvements.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 27
4 Workshops & Training
Presented in Appendix 22 is the Summary of Workshop and Trainings since the project started upto end of this 1st semester of 2017.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 28
5 Project Development Objective Indicators
Key Performance Indicators are developed and agreed between the World Bank and GOI, and willbe monitored over the whole project period the changes in variables will be calculated annually.The set indicators are describe in the project Appraisal Document (PAD) and the Loan Agreementbetween the GOI and the World Bank.
The overall progress towards achieving the PDO of increasing the effective use of selectedsections of national roads along the Western Sumatra Corridor by reducing road user costs isconsidered moderately satisfactory. Progress in implementation has picked up, and there hasbeen an advance with respect to several project indicators. In addition, a project restructuring isbeing processed which should bring the project largely back on track.
The PMU provided an update on the achievement of the indicator targets. There has beenrelatively good progress on three of the five intermediate indicators. For one of the remainingintermediate indicators on bridge improvement, progress is expected within the next semester.The last intermediate indicator related to institutional strengthening will be cancelled in theframework of project restructuring. For the PDO indicator on AADT, CTC carried out static trafficcounts in March 2015 and confirmed that the original indicator targets are adequate. The missionrefined a few indicators definitions/baselines and updated some indicator targets to take intoaccount the project implementation delays. These changes will be reflected in the upcomingproject restructuring.
From the baseline 2010 AADT and estimated AADT for the year 2014/2015, the extrapolatedAADT for the year 2013 resulted to 11,254 vehicles per day or 8.8% above the targeted 10,347vehicles per day in 2013. Shown in Table 11 is the comparison between target and actualestimated AADT.
Table 11Year Targeted AADT EstimatedBaseline (2010) 7,837
FY1 (2013) target 10,347FY1 (2013) actual 11,254FY2 (2014) target 11,351FY2 (2014) actual 12,696FY3 (2015) target 12,453FY4 (2016) target 13,304
FY5 (2017) end target 14,214
Appendix 23 shows the update PDO Indicators during the WB review mission on August, 2016and other set of indicators still to be updated in the future.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 29
6 Legal Covenants
Status of the legal covenant under Schedule 2 (Project Execution) of the Loan Agreement are
shown in Appendix 24.
2017 Semestral Project Report 1st Semester : January-June 2017
Table Of Contents
1 Executive Summary .............................................................................................................. 1
1.1 Current Implementation Situation ............................................................................. 1
1.1.1 Civil Works............................................................................................................... 1
1.1.2 Consultancy Services .............................................................................................. 2
1.2 Current Status of Loan............................................................................................... 2
1.3 Current Problems and Action Required ...................................................................... 3
2 General................................................................................................................................ 4
2.1 Reporting Requirements ............................................................................................ 4
2.2 Loan Status ............................................................................................................... 5
2.3 Financial Management .............................................................................................. 5
2.4 Project Cost Monitoring ............................................................................................. 6
2.5 World Bank Implementation Review Mission and Site Visit ....................................... 6
2.6 Project Steering Committee Meeting ......................................................................... 9
3 Project Management and Implementation......................................................................... 10
3.1 Procurement Status ................................................................................................. 10
3.2 Implementation Status – Civil Works........................................................................ 11
3.3 Variation Order Details ........................................................................................ 19
3.4 Consultancy Services............................................................................................ 21
3.5 Implementation of the Anti-Corruption Act ion Plan ........................................... 23
3.6 Implementation of the Environmental Management Plan and LARAP........................... 24
4 Workshops & Training........................................................................................................ 27
5 Project Development Objective Indicators.......................................................................... 28
6 Legal Covenants................................................................................................................. 29
2017 Semestral Project Report 1st Semester : January-June 2017
APPENDICES
Appendix S-1 : Summary of Submitted Studies and Reports (Environmental Activity)
Appendix S-2 : Summary of Submitted Studies and Reports (Social Activity)
Appendix S-3 : Summary of Submitted Community Development Activity Reports
Appendix S-4 : Summary of Submitted Community Representative Observers (CRO) and ThirdParty Monitoring (TPM) Reports
Appendix 1 : Project Implementation Timeline
Appendix 2 : Actual Implementation Timeline
Appendix 3 : Disbursement and Expenditures Status
Appendix 4 : Report At The End of 2nd Semester (December 2016)
Appendix 5 : Disbursement Plan
Appendix 6 : Detailed Summary of the Project Cost Monitoring
Appendix 7 : Procurement Management of Civil Works
Appendix 8 : Procurement Plan for Consulting Services
Appendix 9 : List of Names of Community Representative Observers (CRO)
Appendix 10 : Anti Corruption Action Plan (ACAP)
Activity Progress of Community Representative Observers (CRO)
Appendix 11 : List of Appointed Third Party Monitors (TPM)
Appendix 12 : Progress of Third Party Monitoring (TPM) Activities
Appendix 13 : Complaints Handling Mechanism System (CHS)
Appendix 14 : Work Activities On Publication/Disclosure
Appendix 15 : Status of Anti - Corruption Action Plan
Appendix 16 : Environmental Safeguards
Appendix 17 : Environmental Management Plan (EMP) Compliance
Appendix 18 : Status of Monitoring of Environmental Mitigation
Appendix 19 : Brief Summary Status and Progress of Environmental Safeguards
Appendix 20 : Overall Land Acquisition Status as of December 2016
Appendix 21 : Status of Social Safeguards, Disclosures and Progress of LARAP Implementation
Appendix 22 : Summary of Workshops and Trainings In 2012 up to 2016
Appendix 23 : Project Development Objective Indicators
Appendix 24 : Status of Legal Covenants
2017 Semestral Project Report 1st Semester : January-June 2017
ANNEXES – Executive Summary Report (Progress “S” Curve)
Annex P-1 : Package No. 1 (Biha – Krui)
Annex P-2 : Package No. 2 (Padang Sawah – Sp. Empat)
Annex P-3 : Package No. 3 (Manggopoh – Padang Sawah)
Annex P-4 : Package No. 4 (Ipuh - Bantal)
Annex P-5 : Package No. 5 (Sp. Rampa – Poriaha)
Annex P-6 : Package No. 6 (Ps. Pedati – Kerkap)
Annex P-7 : Package No. 7 (Indrapura – Tapan)
Annex P-8 : Package No. 8 (Bts. Kota Pariaman – Manggopoh)
Annex P-11 : Package No. 11 (Bantal – Mukomuko)
Annex P-12 : Package No. 12 (Kambang – Indrapura)
Annex P-13 : Package No. 13 (Sp. Rukis – Tj. Kemuning)
Annex P-14 : Package No. 14 (Painan - Kambang)
Annex P-15 : Package No. 15 (Sibolga – Bts. Tapsel)
Annex P-16 : Package No. 16 (Seblat – Ipuh)
Annex P-17 : Package No. 17 (Sp. Gunung Kemala – Pugung Tampak)
Annex P-19 : Package No. 19 (Lais – Bintunan)
Annex P-20 : Package No. 20 (Lubuk Alung - Sicincin)
Annex P-21 : Package No. 21 (Lubuk Alung - Kuraitaji)
ANNEXES
Annex P-1 : Package No. 1
Annex P-2 : Package No. 2
Annex P-3 : Package No. 3
Annex P-4 : Package No. 4
Annex P-5 : Package No. 5
Annex P-6 : Package No. 6
Annex P-7 : Package No. 7
Annex P-8 : Package No. 8
Annex P-11: Package No.11
Annex P-12: Package No.12
Annex P-13: Package No.13
Annex P-14 : Package No.14
Annex P-15: Package No.15
Annex P-16: Package No.16
Annex P-17: Package No.17
Annex P-19 : Package No.19
Annex P-20 : Package No.20
Annex P-21 : Package No.21
05-Jul-15 Status : 17-Jun-17Contract
BALAI Amount Time ellaps Remaining
Plan (incl VAT) days days Target Highest Avg The latest
Actual IDR million % % % % % %
SIMPANG RAMPA - PORIAHA II 17-Mar-15 540 20-Jul-17 107.321 99,43 62,37 (37,05) 507 33 37,63 8,40 2,84 5,95PT. NUSA KONSTRUKSI ENJ Tbk. Medan 18-Jun-15 224 95,67% 4,33%SIBOLGA - Batas TAPSEL II 13-Jul-15 810 31-Dec-17 260.100 84,69 43,75 (40,95) 613 197 11,25 7,27 2,57 3,18 PT. PEMBANGUNAN PERUMAHAN Medan 20-Nov-15 -37 773,00 74,48% 25,52%
PADANG SAWAH-SIMPANG EMPAT III 6-Dec-13 730 19-Apr-16 226.713 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 105 14-Apr-16MANGGOPOH - PADANG SAWAH III 6-Dec-13 730 20-Mar-16 165.157 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 75 17-Mar-16BATAS KOTA PARIAMAN-MANGGOPOH III 28-Jan-16 720 31-Dec-17 355.500 73,96 74,73 0,77 452 197 3,61 9,75 5,34 5,74PT PP - STATIKA JO Padang 23-Mar-16 -71 69,60% 30,40%LUBUK ALUNG - SICINCIN III 1-Jun-16 540 31-Dec-17 113.818 71,88 57,73 (14,15) 290 197 7,04 13,41 7,22 3,50PT NINDYA KARYA Padang 1-Sep-16 -53 59,47% 40,53%KURAI TAJI - LUBUK ALUNG III 1-Jun-16 540 31-Dec-17 126.301 55,91 39,33 (16,58) 290 197 10,11 12,50 4,92 4,42PT MULTI STRUCTURE Padang 1-Sep-16 -53 59,47% 40,53%INDRAPURA-TAPAN III 26-Nov-15 630 30-Aug-17 129.700 80,56 55,86 (24,69) 556 74 22,07 7,86 3,29 5,41PT. ADHI KARYA Padang 10-Dec-15 - 88,24% 11,76%KAMBANG-INDERAPURA III 28-Jan-16 720 31-Dec-17 358.650 77,90 11,93 (65,97) 391 197 14,68 2,37 1,08 2,21PT LANCARJAYA MA-CAHAYA TA,JO Padang 23-May-16 -132 66,44% 33,56%PAINAN - KAMBANG III 1-Jun-16 630 31-Dec-17 214.327 37,80 32,89 (4,91) 319 197 11,18 9,72 3,65 3,99KSO YASA - CONBLOC Padang 3-Aug-16 -114 61,75% 38,25%
IPUH - BANTAL III 14-Nov-13 730 11-Apr-16 196.438 100 100 -PT WASKITA KARYA - PT DMT, JO Padang 13-Jan-14 90 31-May-16KERKAP - PASAR PEDATI III 27-Feb-15 450 28-Jan-17 118.444 100 100 -PT. WASKITA KARYA Tbk Padang 11-Mar-15 240 28-Jan-17BANTAL - MUKOMUKO III 18-Dec-14 720 26-May-17 262.611 100 100 -PT. HUTAMA KARYA - PT. DMT, JO Padang 23-Feb-15 104SEBLAT - IPUH III 28-Oct-16 630 30-Jul-18 211.375 10,78 12,11 1,33 222 408 6,76 3,78 2,02 3,43PT YASA - MULTI STRUCTURE, JO Padang 8-Nov-16 - 35,14% 64,86% BINTUNAN-LAIS III 27-Feb-15 300 30-Jun-16 44.418 100 100 -PT RODATEKNINDO PURAJAYA Padang 11-Mar-15 178 30-Jun-16SIMPANG RUKIS-TANJUNG KEMUNING III 18-Dec-14 720 10-Jul-17 292.700 97,87 50,29 (47,58) 697 23 49,71 10,31 2,39 1,42PT. WASKITA KARYA Padang 22-Jul-15 - 96,80% 3,20%
BIHA - KRUI V 25-Nov-13 640 10-Jan-16 154.073 100 100 -PT Jaya Konstruksi MP, Tbk Palembang 8-Jan-14 93 20-Jan-16Sp.Gn KEMALA-PUGUNG TAMPAK V 17-Nov-14 720 30-Sep-17 199.551 79,35 77,53 (1,82) 615 105 7,49 8,08 4,08 4,80PT Jaya Konstruksi MP, Tbk Palembang 4-Sep-15 38 86,13% 13,87%
CONTRACTSIGN DATE
COW
CIVIL WORKS PROGRESSWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)
Package No. & Name PROGRESS ACHIEVEMENTTime for
CompletionTOC/ PHO
Time for Completion
Actual Dev
Physical Progress (%)
SchTime
extension /contraction
20
21
04
06
19
12
17
11
07
16
14
01
13
02
03
Contractor
08
05
15
6 ESR CTC 17 Jun 2017_93BEBF
ANNEX P-1
MONTH :
Package No. Time Elapsed (Days)
Name Time Elapsed (%)
Project Manager Scheduled Progress (%) 100,00 Contractor Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 733 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 100% Contract Amount Add-1 (+ VAT) Rp. Contract Amount Add-5 (+ VAT) Rp.Price Adjustment Rp.
Comp Add.2 Accum Actual Accum AccumTotal Total Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 8,25 7,22 7,54 7,54 7,54II D r a i n a g e 34,19 23,78 25,35 25,35 25,35III Earthworks 3,95 6,56 4,65 4,65 4,65
IV Pavement Widening &Shoulders
1,47 0,94 1,02 1,02 1,02
V Granular Pavement 9,22 7,04 7,49 7,49 7,49VI Asphalt Pavement 40,14 46,76 41,07 41,07 41,07VII S t r u c t u r e s 1,09 5,36 6,41 6,41 6,41
VIII Reinstatement & MinorWorks
1,20 1,91 6,05 6,05 6,05
IX Day Work 0,14 0,12 0,09 0,09 0,09
X Routine MaintenanceWorks
0,36 0,32 0,33 0,33 0,33
TOTAL 100,00 100,00 100,0 - 100,0 100,0Note :
1. 100% completed on January 20162. Taking-Over Certificate issued on January 20, 20163. Defects Liability Periode until January 19, 2018
2016Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250,22 0,87 1,69 5,62 11,11 18,06 24,50 31,58 38,99 46,36 52,53 60,68 67,46
31,90 35,31 40,53 47,72 56,69 65,59 75,18 84,21 94,42 100,0088,43 91,76 96,08 100,00
0,10 0,58 0,79 1,59 2,93 3,71 4,79 5,98 8,60 11,28 12,62 16,08 18,71 21,04 25,88 32,67 37,50 42,27 45,05 55,51 65,00 70,08 76,56 91,02 100,00(0,12) (0,29) (0,90) (4,03) (8,18) (14,35) (19,71) (25,60) (30,39) (35,08) (39,91) (44,60) (48,75) (14,27) (14,65) (15,06) (19,18) (23,31) (30,13) (28,70) (29,43) (18,34) (15,19) (5,06) -
0,48 0,21 0,80 1,34 0,78 1,08 1,19 2,62 2,68 1,34 3,46 2,63 2,33
140.255.020.000
Actual Progress (%) Balance (%)
Div Description
The month of time for complation
Rivised Progress Schedul Add.1 (%) Original Progress Schedul (%)
Month
Rivised Progress Schedul Add.2 (%)
17-Jun-17
PHYSICAL PROGRESS MONITORING TABLE2014 Year
20-Jan-16
PHYSICAL WORK PROGRESS BY CATEGORY
134.909.211.000154.073.015.000
2015
PT JAYA KONSTRUKSI MP, Tbk
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
MAJOR PROBLEMS ACTION TO BE TAKEN
01
TIM
E June 17, 2017
BIHA - KRUI
RENARDET S.A JV
Joko Wisargo, ST, MT
AMO
UN
T
08-Jan-1425-Nov-13
DISBURSEMENT (Incl VAT)
140.255.020.000
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 01
Original
1st Revised Shc
2nd Revised Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-1
ANNEX P-2
MONTH :
Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 835 Status date Take Over Date Accumulative Rp. 100% Original Contract Amount Rp. *) Include advance payment Contract Amount + VO + Price Adj Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 10,46 3,378 3,38 3,38 3,38
II D r a i n a g e 3,53 3,244 3,24 3,24 3,24
III Earthworks 4,44 4,691 4,69 4,69 4,69
IV Pavement Widening &Shoulders
2,26 1,948 1,95 1,95 1,95
V Granular Pavement 10,49 10,944 10,94 10,94 10,94
VI Asphalt Pavement 52,09 57,028 57,03 57,03 57,03
VII S t r u c t u r e s 14,35 16,115 16,12 16,12 16,12
VIII Reinstatement & MinorWorks
1,65 2,002 2,00 2,00 2,00
IX Day Work 0,12 0,108 0,11 0,11 0,11
X Routine MaintenanceWorks
0,62 0,541 0,54 0,54 0,54
TOTAL 100,00 100,00 100,00 - 100,00 100,00
Note :
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Original Progress Schedul (%) 0,45 0,90 2,20 3,45 7,17 13,58 17,48 20,63 27,88 33,56 38,81 44,72 50,52 56,13 62,58 67,95 73,65 79,35 1st Revised Progress Schedul (%) 66,92 71,10 81,03 87,07 91,35 95,62 100,00 2nd Revised Progress Schedul (%) 92,53 95,62 96,75 97,25 98,21 100,00Actual - 0,13 1,02 2,19 4,11 5,96 9,69 13,85 22,55 25,61 31,45 33,73 40,41 44,25 49,98 55,715 58,61 58,35 63,76 71,36 77,80 83,27 92,53 93,20 92,85 95,73 96,83 100,00Balance (0,45) (0,77) (1,17) (1,26) (3,07) (7,62) (7,80) (6,78) (5,33) (7,95) (7,36) (10,99) (10,11) (11,88) (12,59) (12,23) (15,04) (8,57) (7,35) (9,67) (9,27) (8,08) (3,09) (2,41) (3,90) (1,52) (1,37)
0,89 1,17 1,91 1,86 3,72 4,17 8,69 3,07 5,84 2,28 6,68 3,84 38,29
1. 100% completed April 14, 20162. Taking-Over Certificate issued on April 14, 20163. Defects Liability Periode until April 13, 2018
197.936.699.000
Amandm04
ISMAN, ST
AMO
UN
T
RENARDET S.A JV06-Dec-1306-Jan-14
June 17, 2017PADANG SAWAH-SIMPANG EMPAT02
TIM
E
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Jun-17
The month of time for complation
DISBURSEMENT (Incl VAT)17-Jun-17
247.572.130.000
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
PHYSICAL PROGRESS MONITORING TABLE2014 2015 2016
247.572.130.000
14-Apr-16
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 02
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-2
ANNEX-P3
MONTH :
Package No. Time Elapsed (Days)
Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 There is outstanding payment of 2.4 billion rupiahs and contract Proposal of contract amendment under process Contractor Actual Overall Progress (%) 100,00 amount not yet amended Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 805 Status date Take Over Date Accumulative Rp. 98,6% Original Contract Amount Rp. *) Include advance payment Contract Amount + VO + Price Adj Rp.
Comp Revised Accum Actual Accum AccumTotal Total Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 10,21 10,21 2,39 2,39 2,39II D r a i n a g e 13,17 13,17 10,09 10,09 10,09III Earthworks 3,04 3,04 6,99 6,99 6,99
IV Pavement Widening &Shoulders
2,45 2,45 1,92 1,92 1,92
V Granular Pavement 11,27 11,27 11,25 11,25 11,25VI Asphalt Pavement 55,81 55,81 59,72 59,72 59,72VII S t r u c t u r e s 0,80 0,80 5,28 5,28 5,28
VIII Reinstatement &Minor Works
2,27 2,27 1,02 1,02 1,02
IX Day Work 0,22 0,22 0,69 0,69 0,69
X Routine MaintenanceWorks
0,76 0,76 0,65 0,65 0,65
TOTAL 100 100 100,0 - 100 100Note :
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 270,26 1,00 1,67 2,45 4,78 7,45 10,70 14,27 21,53 30,10 36,95 44,01 51,62 58,67 65,63 73,03 79,97 87,04
70,14 74,54 82,69 89,96 95,17 97,89 100,0093,78 98,11 99,31 100,00
0,24 0,48 2,07 2,43 2,87 5,45 5,70 7,01 12,43 14,45 19,30 24,38 29,11 30,11 32,97 39,72 43,28 43,98 48,56 54,37 65,63 85,01 91,15 96,30 98,38 99,13 100,00(0,02) (0,52) 0,40 (0,02) (1,91) (2,00) (5,00) (7,26) (9,10) (15,65) (17,65) (19,63) (22,51) (28,56) (32,66) (33,31) (36,69) (26,16) (25,98) (28,32) (24,33) (10,16) (6,74) 2,52 0,27 (0,18) -
0,24 1,59 0,36 0,44 2,58 0,25 1,31 5,42 2,02 4,85 5,08 4,73 1,00
Balance (%)
2016
Rivised Progress Schedul (%)
183.940.872.000
Rivised Progress Schedul (%)
Actual Progress (%)
PHYSICAL PROGRESS MONITORING TABLE Year 2014 Month The month of time for complation
2015
PHYSICAL WORK PROGRESS BY CATEGORY
Original Progress Schedul (%)
Div Description
181.414.693.470143.688.963.000
1. 100% completed on March 17, 20162. Taking-Over Certificate issued on March 17, 2016 3.Defects Liability Periode until March 16, 2018
DISBURSEMENT (Incl VAT)
17-Mar-1617-Jun-17
Opukenigara, ST
AMO
UN
T
RENARDET S.A JV06-Dec-13
PT JAYA KONSTRUKSI MP, Tbk
06-Jan-14
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Jun-17
03
TIM
E June 17, 2017MANGGOPOH - PADANG SAWAH MAJOR PROBLEMS ACTION TO BE TAKEN
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 03
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-3
ANNEX P-4
MONTH :
Package No. Time Elapsed (Days)
Name Time Elapsed (%)
Project Manager Scheduled Progress (%) 100,00 Contractor PT WASKITA KARYA - PT DAYA JO Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 820 Status date Take Over Date Accumulative Rp. 100,0% Contract Amount Rp. *) Include advance payment
Contract Amount Add-1 Rp.
Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to
% Month Month Month thisMonth
I G e n e r a l 7,59 5,99 5,99 5,99II D r a i n a g e 12,26 8,18 8,18 8,18III Earthworks 3,58 3,06 3,06 3,06
IV Pavement Widening &Shoulders
3,39 3,05 3,05 3,05
V Granular Pavement 18,07 16,82 16,82 16,82VI Asphalt Pavement 49,27 47,02 47,02 47,02VII S t r u c t u r e s 2,55 4,82 4,82 4,82
VIII Reinstatement & MinorWorks
2,95 10,88 10,88 10,88
IX Day Work 0,14 0,00 0,00 0,00
X Routine MaintenanceWorks
0,20 0,18 0,18 0,18
TOTAL 100 100,0 - 100,00 100,00Note :
1. 100% completed on March 31, 20162. Taking-Over Certificate issued on March 31, 20163. Defects Liability Periode until March 30, 2018
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Schedl Progress Original (%) 0,11 0,32 0,75 1,14 6,57 10,29 12,85 15,81 20,08 24,22 32,76 40,88 47,93 55,61 63,451st Revised Schedule (%) 28,57 37,28 48,18 56,89 64,18 73,78 84,47 91,89 98,53 2nd Revised Schedule (%) 61,23 62,14 76,26 86,77 96,29 100,0 Actual Progress (%) - 0,18 0,40 0,53 0,56 0,78 0,87 1,45 3,73 5,35 8,10 9,35 13,79 21,76 27,67 35,43 39,36 42,14 44,24 46,28 50,09 53,17 61,23 70,32 78,69 84,64 91,62 94,53 Balance (%) (0,11) (0,14) (0,35) (0,61) (6,01) (9,51) (11,98) (14,36) (16,35) (18,88) (24,66) (31,53) (34,14) (33,85) (0,91) (1,86) (8,81) (14,75) (19,95) (27,51) (34,38) (38,72) (37,30) 8,18 2,43 (2,13) (4,67) (5,47)
0,22 0,13 0,03 0,22 0,09 0,58 2,27 1,62 2,76 1,25 4,44 7,97
Fathoni Ikhsan, ST
04MAJOR PROBLEMS ACTION TO BE TAKENTI
ME June 17, 2017
IPUH - BANTAL
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
13-Jan-1414-Nov-13
2015
RENARDET S.A JV
AMO
UN
T
20162014PHYSICAL PROGRESS MONITORING TABLE
31-Mei-16
Div Description
194.902.179.000
DISBURSEMENT (Incl VAT)
186.936.750.000194.902.178.999,00
PHYSICAL WORK PROGRESS BY CATEGORY
17-Jun-17
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 04
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-4
ANNEX P-5
MONTH :
Package No. Time Elapsed (Days) 730
Name SIMPANG RAMPA - PORIAHA Time Elapsed (%) 95,55% Project Manager Scheduled Progress (%) 99,43 Contractor PT. NUSA KONSTRUKSI ENJ Tbk. Actual Overall Progress (%) 62,37 Supervision Consultant Balance (%) -37,05Contract Sign Progress This Month (%) 5,95 Commencement Date Time for Complation (Days) 764 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 57,88%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 8,09 1,18 0,01 1,20II D r a i n a g e 2,77 0,39 - 0,39III Earthworks 21,28 33,38 1,09 34,47
IV Pavement Widening &Shoulders
1,28 0,26 - 0,26
V Granular Pavement 8,04 4,19 0,03 4,23VI Asphalt Pavement 38,75 0,23 4,69 4,92VII S t r u c t u r e s 16,22 16,74 0,13 16,87
VIII Reinstatement & MinorWorks
3,48 - - -
IX Day Work 0,10 0,04 - 0,04
X Routine MaintenanceWorks
- - - -
TOTAL 100,0 56,42 5,95 62,37 -Note :
Year Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Schedl Progress Original (%) 0,22 0,99 3,89 8,90 16,87 23,69 36,44 40,23 46,08 50,69 56,28 60,45 66,93 69,02 78,66 88,79 96,82 1001st Revised schedul 41,88 41,99 53,49 63,38 76,53 82,27 97,61 99,43 100 Actual Progress (%) - 0,57 1,09 1,69 2,72 3,08 3,53 5,77 7,37 10,11 16,66 18,44 26,83 28,19 30,00 31,28 35,23 35,25 42,73 43,50 45,99 48,20 51,22 56,42 62,37 Balance (%) (0,22) (0,42) (2,80) (7,20) (14,16) (20,61) (32,91) (34,45) (38,70) (40,58) (39,63) (42,02) (40,10) (40,83) (48,66) (57,51) (61,59) (6,63) 0,74 (9,99) (17,39) (28,32) (31,06) (41,19) (37,05)Progress per month - 0,57 0,52 0,60 1,03 0,37 0,44 2,25 1,60 2,74 6,55 1,78 8,40 1,36 1,81 1,28 3,95 0,02 7,5 0,8 2,49 2,22 3,01 5,20 5,95
0,57 0,52 0,60 1,03 0,37 0,44 2,25 1,60 2,74 6,55 1,78 8,40 1,36
Div Description
PHYSICAL WORK PROGRESS BY CATEGORY
17-Jun-1762.118.800.409
20-Jul-17
Jun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
EXECUTIVE SUMMARY REPORT
RENARDET S.A JV
05
TIM
E June 17, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
AMO
UN
TSaleh Samsuri, ST • Contractor is working to fix the stone crusher whichoften damaged• Coordination with the Ministry of LHK
DISBURSEMENT (Incl VAT)18-Jun-1517-Mar-15
2015PHYSICAL PROGRESS MONITORING TABLE
107.321.260.310
2016 2017
• Delays in AC work, 3.5 km land is ready for paving.Crushed stone aggregate is not adequate yet because thecrushing plant production is not yet effective.• Renewal of License Borrow and Use for Forest Area (1.5km) is constrained by the certainty of the environmentalresearch that will be used, whether the revision UKL-UPLor DELH
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 05
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-05
ANNEX P-06
MONTH :
Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Yahya, ST Scheduled Progress (%) 100,00 Contractor PT. WASKITA KARYA Tbk Actual Overall Progress (%) 100,00 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 450 240 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 83,39%Price Adjustment Rp.
Add Accum Actual Accum AccumLast this to this Sch to this
% Month Month Month Month
I G e n e r a l 1,69 1,69 1,69 1,69II D r a i n a g e 1,61 1,61 1,61 1,61III Earthworks 8,58 8,58 8,58 8,58
IV Pavement Widening &Shoulders
2,93 2,93 2,93 2,93
V Granular Pavement 16,48 16,48 16,48 16,48VI Asphalt Pavement 60,39 60,39 60,39 60,39VII S t r u c t u r e s 5,63 5,63 5,63 5,63
VIII Reinstatement & MinorWorks
2,15 2,15 2,15 2,15
IX Day Work - - - -
X Routine MaintenanceWorks
0,54 0,54 0,54 0,54
TOTAL 100 100,0 - 100,00 100,00
Note :1. 100% completed on January 28, 20172. Taking-Over Certificate issued on January 28, 2073. Defects Liability Periode until January 28, 2019
Year 2017 Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May June July August Sep Oct Nop Dec Jan The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Schedl Progress Original (%) 0,17 0,59 1,28 3,09 4,38 8,17 14,27 25,82 38,49 49,93 62,08 75,00 85,36 95,41 100,001st Revised schedul 56,000 60,47 74,94 100,002nd Revised schedul 58,86 70,27 79,80 88,09 96,07 100,0 Actual Progress (%) 0,07 0,33 0,76 1,04 1,18 2,27 10,03 15,13 18,75 20,54 23,04 25,89 27,55 32,701 36,020 39,34 45,15 56,31 64,44 74,87 87,78 91,23 100,0 Balance (%) -0,15 -0,26 -0,53 -2,04 -3,20 -5,90 -4,24 -10,69 -19,74 -29,38 -39,04 -49,11 -57,81 -62,71 -63,98 -21,12 -29,79 -2,56 -5,83 -4,93 -0,31 -4,84 0,00
0,42 0,29 0,13 1,10 7,76 5,09 3,62 1,79 2,49 2,85 1,67 5,15
PHYSICAL PROGRESS MONITORING TABLE2015
118.444.155.000
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
2016
98.772.608.568
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS6
TIM
E June 17, 2017KERKAP - PASAR PEDATI MAJOR PROBLEMS
17-Jun-1728-Jan-17DISBURSEMENT (Incl VAT)
ACTION TO BE TAKEN
AMO
UN
T
27-Feb-1511-Mar-15
Calendar Days +
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 06
Original Sch
1st Revised Sch
2nd Revised Sch
Actual
6 ESR CTC 17 Jun 2017_93BEBF P-06
ANNEX P-07
MONTH :
Package No. Time Elapsed (Days) 555 Name Time Elapsed (%) 88,10% Sub Project Manager / PPK Scheduled Progress (%) 80,56 Contractor PT ADHI KARYA Actual Overall Progress (%) 55,86 Supervision Consultant Balance (%) -24,69Contract Sign Progress This Month (%) 5,41 Commencement Date Time for Complation (Days) 630
Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 51,8%Price Adjustment Rp.
Comp Accum Actual AccumTotal Last this to this
% % Month Month Month
I G e n e r a l 2,45 1,57 0,10 1,67 1,21II D r a i n a g e 21,84 7,27 0,04 7,31 20,10III Earthworks 5,38 4,70 0,68 5,38 7,25IV
Pavement Widening &Shoulders
1,09 0,03 - 0,03 0,68V Granular Pavement 9,22 5,41 0,84 6,26 7,52VI Asphalt Pavement 51,16 26,32 3,62 29,94 50,00VII S t r u c t u r e s 6,08 4,38 0,14 4,51 6,32VIII
Reinstatement & MinorWorks
2,48 0,47 - 0,47 0,65IX Day Work 0,09 0,12 - 0,12 0,17X
Routine MaintenanceWorks
0,20 0,19 - 0,19 0,15 TOTAL 100,0 - 50,46 5,41 55,86 94,03
Note :
Year 2015 Month Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug The month for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Original Progress Schedul (%) 0,16 0,31 0,59 0,67 1,24 1,92 3,90 5,63 8,72 16,79 24,44 32,37 43,74 50,84 62,90 72,65 80,61 87,11 94,03 98,20 100,0 Revised Progress Schedul (%) Add -1 24,44 32,37 43,74 50,84 62,90 72,65 80,61 87,11 94,03 98,20 100,0 Revised Progress Schedul (%) CCO / Add -3 55,68 64,85 72,65 80,56 90,98 100,0 Actual Progress (%) 0,15 0,31 0,59 0,82 1,18 3,62 4,75 5,63 12,87 16,70 23,49 31,35 39,03 41,27 45,61 48,054 48,87 50,46 55,86 Balance (%) (0,01) - 0,00 0,15 (0,06) 1,70 0,85 0,00 4,15 (0,09) (0,95) (1,02) (4,71) (9,57) (17,29) (7,63) (15,98) (22,19) (24,69)Progress per month 0,31 0,28 0,23 0,36 2,44 1,14 0,88 7,24 3,83 6,79 7,86 7,68 2,24 4,34 2,44 0,82 1,59 5,41
0,59 0,23 0,36 2,44 1,14 0,88 7,24 3,83 6,79 7,86 7,68 2,24 37,65
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Amandment
Accum Schto thisMonth
• Lots of disturbance from the local people and theyprovided limit of operational time for Stone Crusher12 hours
• The proposed additional work: 4 km (existingroad) has not been proposed by contractor
• Contractor has coordinated with thePolice and Head of District, as well asacceleration of operating license foradditional stone crusher• Waiting for approval regarding the useof the remaining budget from cancellationof Package #1030-Agust-17 17-Jun-17
10-Des-15
Filino Kalani, ST
AMO
UN
T
RENARDET S.A JV PT. SEECONS03-Dec-15
DISBURSEMENT (Incl VAT)
67.178.379.981
2017
June 17, 2017MAJOR PROBLEMS ACTION TO BE TAKEN
2016
7
TIM
E
INDRAPURA - TAPAN
129.699.900.000
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 07
ORIGINAL Sch
1st REVISED Sch
2nd REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-07
ANNEX P-08
MONTH :
Package No. Time Elapsed (Days) 451 Name Time Elapsed (%) 69,49% Sub Project Manager / PPK Scheduled Progress (%) 73,96 Contractor PT. PP - STATIKA CONSORTIUM Actual Overall Progress (%) 74,73 Supervision Consultant Balance (%) 0,77
Contract Sign Progress This Month (%) 5,74
Commencement Date Time for Complation (Days) 649
Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 69,3%Price Adjustment Rp.
Comp Actual Accumto to
Total this this% Month Month Month
I G e n e r a l 2,13 0,44 0,00 0,44II D r a i n a g e 19,56 6,88 1,62 8,50III Earthworks 6,43 4,55 0,16 4,72IV
Pavement Widening &Shoulders
3,43 0,23 0,48 0,71V Granular Pavement 14,77 9,76 0,24 10,00VI Asphalt Pavement 48,29 41,81 1,86 43,67VII S t r u c t u r e s 2,97 4,49 0,301 4,79VIII
Reinstatement & MinorWorks
2,16 0,68 0,741 1,42IX Day Work 0,05 - - -X
Routine MaintenanceWorks
0,20 0,15 0,337 0,49 TOTAL 100,0 68,99 5,74 74,73 -
Note :
Year Month Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Jan Feb The month for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Original Progress Schedul (%) 0,02 0,09 0,17 0,31 0,44 2,77 7,58 13,22 22,21 30,85 35,38 48,22 55,71 66,39 74,64 78,72 83,79 90,13 94,80 97,82 99,27 99,96 100,00 Revised Progress Schedul (%) 27,55 35,38 44,13 51,83 59,73 68,69 73,96 79,40 88,40 94,40 97,52 99,37 99,91 100,00 Actual Progress (%) 0,27 1,12 2,37 3,59 6,21 9,69 18,79 28,40 32,15 37,93 47,48 57,22 65,01 68,99 74,73 Balance (%) 0,18 0,96 2,06 3,15 3,44 2,12 5,57 6,19 1,30 2,55 3,35 5,39 5,28 0,31 0,77Progress per month 0,00 0,27 0,85 1,25 1,22 2,62 3,48 9,10 9,61 3,75 5,78 9,55 9,75 7,79 3,98 5,74
0,94 1,25 1,22 2,62 3,48 9,10 9,61 3,75 5,78 9,55 9,75 7,79 58,80
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS08
TIM
E June 17, 2017Bts Kota Pariaman - Manggopoh MAJOR PROBLEMS ACTION TO BE TAKEN
246.238.571.000
RENARDET S.A JV PT. SEECONS
28-Jan-16
23-Mar-16
Opukenigara, ST
AMO
UN
T
DISBURSEMENT (Incl VAT)31-Des-17 17-Jun-17
● Unsettled land acquisation 133 PAPs
2018Dec
Div DescriptionAccum
LastAccumSch to
thisMonth
PHYSICAL PROGRESS MONITORING TABLE2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
355.500.000.000
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 08
Original Sch
Revised Sch
Actual
ANNEX P-11
MONTH :
Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT. HUTAMA KARYA, Tbk JO PT. DMT Actual Overall Progress (%) 100,00 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) Contract Sign Progress This Month (%) Commencement Date
Take Over Date
Time for Complation (Days) 824 Calendar Days Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 91,3% Contract Amount Add-1 (+ VAT) Rp.Price Adjustment Rp.
Accum Actual Accum AccumLast this to this Sch to this
% Month Month Month MonthI G e n e r a l 0,85 0,87 - 0,87 0,87II D r a i n a g e 2,49 2,88 - 2,88 2,88III Earthworks 11,27 10,58 - 10,58 10,58
IV Pavement Widening &Shoulders
3,60 3,22 0,17 3,40 3,40
V Granular Pavement 14,41 14,21 - 14,21 14,21VI Asphalt Pavement 52,35 53,27 0,00 53,27 53,65VII S t r u c t u r e s 9,88 11,02 0,03 11,06 10,59
VIII Reinstatement & MinorWorks
4,87 2,90 0,56 3,46 3,55
IX Day Work - - - - -
X Routine MaintenanceWorks
0,28 0,28 - 0,28 0,28
TOTAL 100,00 99,23 0,77 100,0 100,0Note :
Year Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May June July August Sep Oct Nop Dec Jan Feb Mar Apr May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Schedl Progress Original (%) 0,39 2,18 4,68 7,70 9,91 14,17 18,72 22,96
20,01 22,98 25,39 29,15 36,74 43,85 51,45 58,80 66,39 70,16 77,18 84,00 89,39 93,63 96,19 99,45 100,0075,54 92,39 95,86 98,98 100
Actual Progress (%) 1,477 5,59 6,59 9,13 10,00 11,28 15,09 17,23 23,22 24,82 26,84 33,04 38,87 44,59 51,81 56,74 58,88 65,03 71,00 74,78 84,85 86,28 87,49 89,78 96,37 99,23 100 Balance (%) 1,08 3,42 1,92 1,43 0,09 (2,89) (3,64) (2,78) 0,23 (0,56) (2,31) (3,70) (4,98) (6,86) (6,99) (9,65) (11,28) (12,15) (13,01) (14,61) (8,78) (9,91) (11,96) (2,61) 0,52 0,25 0,00Progress per month 4,12 1,00 2,54 0,87 1,28 3,80 2,15 5,99 1,61 2,02 6,20 5,83 5,71 7,22 4,93 2,14 6,15 5,97 3,79 10,07 1,43 1,21 2,28 6,60 2,86 0,77
1,00 2,54 0,87 1,28 3,80 2,15 5,99 1,61 2,02 6,20 5,83 5,71
11
TIM
E June 17, 2017BANTAL - MUKOMUKO MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Div Description
239.716.422.774
Amend-02
17-Jun-17
23-Feb-15
DISBURSEMENT (Incl VAT)26-May-17
18-Dec-14 AMO
UN
TFathoni Ikhsan, ST
2 nd Rivised Progress Schedul (%)
2017
1 st Rivised Progress Schedul (%)
PHYSICAL PROGRESS MONITORING TABLE2015 2016
228.899.717.000262.611.303.000
PHYSICAL WORK PROGRESS BY CATEGORY
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 11
Original Sch
1st Revised Sch
2nd Revised Sch
Actual
6 ESR CTC 17 Jun 2017_93BEBF P-11
ANNEX P-12
MONTH :
Package No. Time Elapsed (Days) 390 Name Time Elapsed (%) 66,33% Sub Project Manager / PPK Filino Kalani, ST Scheduled Progress (%) 77,90 Contractor Actual Overall Progress (%) 11,93
Balance (%) (65,97) Supervision Consultant RENARDET S.A JV PT. Daya Creasi Mitrayasa Progress This Month (%) 2,21 • Being discussed with contractor JO Contract Sign Commencement Date Take Over Date Status date Time for Complation (Days) 588 Calendar Days Accumulative Rp. 12,79% Contract Amount (Incl VAT) Rp.Price Adjustment Rp.
Add. Accum Actual Accum AccumTotal Last this to this Sch to
% Month Month Month thisMonth
I G e n e r a l 3,64 0,67 (0,27) 0,40II D r a i n a g e 3,75 - 0,12 0,12III Earthworks 6,23 0,86 0,40 1,26IV
Pavement Widening &Shoulders
2,67 - - -V Granular Pavement 18,49 3,23 1,05 4,27VI Asphalt Pavement 57,59 3,79 1,26 5,05VII S t r u c t u r e s 5,49 0,75 (0,34) 0,41VIII
Reinstatement & MinorWorks
1,96 0,33 - 0,33IX Day Work 0,05 0,01 (0,01) -X
Routine MaintenanceWorks
0,13 0,08 - 0,08 TOTAL 100,00 9,72 2,21 11,93 -
Note :
May June July Augustus Sept October Nov Des January Feb March April May June July Augustus Sept October Nov Des January Feb March April May1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250,09 0,58 0,84 1,26 1,61 4,10 8,31 14,09 21,50 31,99 44,07 56,50 71,44 77,99 77,99 80,17 82,88 85,50 89,12 91,76 94,29 97,31 99,45 99,78 100,00
1,50 2,34 4,93 9,39 15,87 27,24 40,55 54,23 70,99 77,90 80,34 83,37 86,33 90,58 95,17 100,0
0,192 0,44 0,87 0,98 1,05 1,97 2,13 4,02 4,03 4,99 5,928 7,35 9,72 11,930,10 (0,14) 0,03 (0,28) (0,45) (0,37) (2,80) (5,37) (11,84) (22,25) (34,62) (46,88) (61,27) (65,97)
Progress per month 0,43 0,11 0,07 0,91 0,17 1,89 0,01 0,96 0,94 1,42 2,37 2,210,25 0,43 0,11 0,07 0,91 0,17 1,89 0,01 0,96 0,94 1,42 2,37 2,21
12
TIM
E June 17, 2017Kambang - Indrapura MAJOR PROBLEMS
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
ACTION TO BE TAKEN
AMO
UN
T
PT. LANCARJAYA MANDIRI ABADI - PT.CAHAYA TUNGGAL ABADI , JO.
28-Jan-1623-May-16 DISBURSEMENT (Incl VAT)31-Dec-17 17-Jun-17
45.875.490.000358.650.400.000
• Unsettled land acquisation 1.820 PAPs• SCM-3 and test case FAILED
Month
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
PHYSICAL PROGRESS MONITORING TABLE
Year 2016 2017 2018
The month of time for complation Original Progress Schedul (%) 1st Rivised Progress Schedul (%)
Actual Progress (%) Balance (%)
2nd Rivised Progress Schedul (%)
• GS and key personnel are required• Being pursued the best solution by the employer
• Poor management in the project operational
• Lack of financial support from the Head Office of LeadContractor
• Absence of contractor's GS• Shortage of contractor's engineer
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 12
ORIGINAL
1st REVISED Sch
2nd REVISED Sch
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\6 ESR CTC 17 Jun 2017_93BEBF P-12
ANNEX P-13
MONTH :
Package No. Time Elapsed (Days) 696
Name SIMPANG RUKIS-TANJUNG KEMUNING Time Elapsed (%) 96,67% Project Manager Paides Tabril, ST,MT Scheduled Progress (%) 97,87 Contractor PT. WASKITA KARYA Actual Overall Progress (%) 50,29 Supervision Consultant Balance (%) -47,58Contract Sign Progress This Month (%) 1,42 Commencement Date Time for Complation (Days) 720 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 40,44%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,38 0,41 - 0,41II D r a i n a g e 1,87 1,06 0,05 1,11III Earthworks 16,52 5,49 0,01 5,51
IV Pavement Widening &Shoulders
4,11 0,65 0,08 0,72
V Granular Pavement 8,43 8,57 0,08 8,64VI Asphalt Pavement 64,33 30,65 1,00 31,65VII S t r u c t u r e s 2,05 1,28 0,20 1,49
VIII Reinstatement & MinorWorks
2,14 0,70 0,00 0,70
IX Day Work - - - -
X Routine MaintenanceWorks
0,18 0,059 - 0,059
TOTAL 100,0 48,87 1,42 50,29 -Note :
Year Month Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Schedl Progress Original (%) 0,02 0,21 1,65 4,18 6,69 9,61 14,62 20,36 26,94 33,58 41,24 47,87 50,63 58,32 63,60 68,28 72,97 77,66 82,62 86,79 91,19 95,75 99,36 99,74 100,001st Revised Schedule (%) 0,20 0,90 2,20 4,00 5,80 7,50 9,50 11,50 13,30 15,40 16,13 20,18 24,00 27,82 32,00 36,44 41,47 46,63 54,87 63,48 72,34 81,13 90,08 97,87 100,00 Actual Progress (%) - 0,36 0,88 2,19 3,39 13,71 13,84 14,37 14,62 16,02 17,34 18,25 18,55 19,06 19,25 20,53 22,77 32,63 41,11 42,71 44,34 47,26 48,87 50,29 Balance (%) (0,02) 0,14 (0,77) (1,98) (3,30) 4,10 (0,78) (5,99) (12,32) (17,56) (23,90) (29,63) (32,08) (39,26) (44,34) (47,75) (50,20) (45,03) (41,51) (20,77) (28,01) (33,87) (41,21) (47,58)Progress per month - 0,36 0,52 1,32 1,20 10,3 0,14 0,53 0,24 1,40 1,32 0,91 0,30 0,51 0,19 1,27 2,24 9,86 8,48 1,60 1,63 2,92 1,61 1,42
0,36 0,52 1,32 1,20 10,31 0,14 0,53 0,24 1,40 1,32 0,91 0,30 0,51
13
TIM
E June 17, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
AMO
UN
T
RENARDET S.A JV18-Dec-1422-Jul-15
• Unsettled Land acquisition 446 PAPs• Poor management at the operational contractor(no GS for about 1.5 months)• Amendment to the extension of time has not beenproposed
• The budget is already allocated in DIPA 2017, PPK attemptto complete land acquisition on April 2017
• The new GS has already started since March 8, 2017• Will be submitted by the contractor on April 2017
DISBURSEMENT (Incl VAT)10-Jul-17 17-Jun-17
292.700.000.000 118.373.002.251
PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 13
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-13
ANNEX P-14
MONTH :
Package No. Time Elapsed (Days) 318 Name Time Elapsed (%) 63,86% Sub Project Manager / PPK Rahmat Donal, ST, MT Scheduled Progress (%) 37,80 Contractor 'PT YASA - CONBLOC, JV Actual Overall Progress (%) 32,89 Supervision Consultant RENARDET S.A JV Balance (%) (4,91) Contract Sign Progress This Month (%) 3,99 Commencement Date Time for Complation (Days) 498 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 38,04%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to
% Month Month Month thisMonth
I G e n e r a l 0,38 0,70 - 0,70 0,87II D r a i n a g e 1,87 0,92 0,19 1,11 4,29III Earthworks 16,52 3,54 1,94 5,48 5,63
IV Pavement Widening &Shoulders
4,11 - - - 0,54
V Granular Pavement 8,43 5,52 0,44 5,96 10,25VI Asphalt Pavement 64,33 16,85 1,42 18,27 13,39VII S t r u c t u r e s 2,05 0,83 - 0,83 2,27
VIII Reinstatement & MinorWorks
2,14 0,34 - 0,34 0,34
IX Day Work - 0,01 - 0,01 0,01
X Routine MaintenanceWorks
0,18 0,20 0,00 0,20 0,20
TOTAL 100,00 28,90 3,99 32,89 37,80
Note :
Augustus Sept October Nov Des January Feb March April May June July Augustus Sept October Nov Des January Feb March April1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 210,17 0,34 0,51 0,94 2,02 4,47 7,12 10,30 14,85 21,63 29,98 38,68 47,74 54,09 63,68 71,43 79,18 86,11 92,51 97,49 100,00,17 0,56 0,72 1,78 5,87 10,05 15,36 20,60 28,07 32,72 37,80 45,12 53,79 66,71 80,65 92,59 100,00,18 0,47 2,65 3,83 3,94 5,96 9,27 15,63 19,18 28,90 32,890,00 (0,09) 1,92 2,05 (1,92) (4,09) (6,09) (4,96) (8,89) (3,82) (4,91)
Progress per month 0,18 0,29 2,18 1,19 0,11 2,02 3,31 6,37 3,54 9,72 3,990,29 2,18 1,19 0,11 2,02 3,31 6,37 3,54 9,72 3,99 (32,89) - -
14
TIM
E June 17, 2017 Painan - Kambang MAJOR PROBLEMS
1-Jun-163-Aug-16
13-Dec-17214.322.429.680
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
ACTION TO BE TAKEN
AMO
UN
T
DISBURSEMENT (Incl VAT)17-Jun-17
81.524.457.452
Unsettled land acquisition: 1.519 PAPSProduction of stone crusher is smaller than the capacity ofAMP
Acceleration of LARAP implementation, thebudget is already available in DIPA 2017Additional of 1 Crushing Plant with capacity of 150tons per day is being set up
Actual Progress (%) Balance (%)
201820172016 Year
Month
Revise Progress Schedul (%)
The month of time for complation Original Progress Schedul (%)
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 14
ORIGINAL Sch
1st REVISED Sch
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\6 ESR CTC 17 Jun 2017_93BEBF P-14
ANNEX P-15
MONTH :
Package No. Time Elapsed (Days) 575 Name Time Elapsed (%) 74,4% Project Manager Scheduled Progress (%) 84,69 Contractor PT. PEMBANGUNAN PERUMAHAN Actual Overall Progress (%) 43,75 Supervision Consultant Balance (%) -40,9Contract Sign Progress This Month (%) 3,18 Commencement Date Time for Complation (Days) 773 Take Over Date Status date Contract Amount (Incl VAT) Accumulative Rp. 28%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 2,30 1,15 - 1,15II D r a i n a g e 5,13 0,37 0,00 0,37III Earthworks 6,34 3,82 0,36 4,17
IV Pavement Widening &Shoulders
2,16 0,70 0,00 0,70
V Granular Pavement 24,41 8,24 0,81 9,04VI Asphalt Pavement 40,48 22,38 1,90 24,28VII S t r u c t u r e s 16,75 3,16 0,12 3,27
VIII Reinstatement & MinorWorks
2,39 0,75 - 0,75
IX Day Work 0,04 0,01 - 0,01
X Routine MaintenanceWorks
- - - -
TOTAL 100,0 40,57 3,18 43,75 -Note :
Year
Month Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Schedl Progress Original (%) 0,11 0,45 1,04 3,18 5,57 8,98 13,46 19,96 23,3 29,8 36,3 42,3 48,17 53,91 58,4 64,3 69,6 75,51 81,15 87,1 90,01 93,9 97,3 98,7 99,7 100,0 100,0 100,01st Revised Sch 7,4 11,8 14,1 18,5 23,8 30,1 37,5 44,4 49,9 57,0 63,5 70,2 77,5 84,7 88,2 93,1 97,6 99,4 100,0 Actual Progress (%) 0,15 0,46 0,92 1,42 1,69 2,34 4,72 5,59 5,96 8,94 8,99 12,04 13,25 20,5 27,0 27,9 29,4 34,7 40,6 43,7 Balance (%) 0,03 0,02 (0,12) (1,76) (3,88) (6,64) (2,7) (6,2) (8,2) (9,5) (14,8) (18,0) (24,2) (23,9) (23,0) (29,2) (34,1) (35,5) (36,9) (40,9)Progress per month 0,3 0,5 0,5 0,5 0,3 0,6 2,4 0,9 0,4 3,0 0,0 3,1 1,2 7,3 6,5 0,9 1,6 5,2 5,9 3,2
0,32 0,46 0,50 0,27 0,65 2,38 0,87 0,37 2,99 0,04 3,05 1,21 7,27
EXECUTIVE SUMMARY REPORT
PROGRESS STATUS15
TIM
E
Jun-17
PROJECT DATA SUMMARY OF WORK PROGRESSJune 17, 2017
MAJOR PROBLEMS ACTION TO BE TAKENSIBOLGA - BTS. TAPSEL
20182015 2016 2017
DISBURSEMENT (Incl VAT)
AMO
UN
TSaleh Samsuri, ST
PHYSICAL WORK PROGRESS BY CATEGORY
31-Des-17 17-Jun-1773.391.372.452
A Joint Venture of Renardet, S.A.13-Jul-1520-Nop-15
260.100.000.000
PHYSICAL PROGRESS MONITORING TABLE
Div Description
• Unsettled land acquisitionz: 12.9 Km• Residents in the area of Pinangsori - Pinangbaru (4 Km length) isnot willing to do remeasurement of land acquisition• Delay in relocating the utilities of electrical poles PLN and PDAMpipe (water)● Unse led land acquisa on 1.291 PAPs
• Acceleration of LARAP implementation• After field engineering, the Contractor proposes to utilize thewidth of existing road (Min. Width 11 m)• Coordination with PLN. The contract helps provide a ruptured pipeand it was proposed to make ducting for crossing PDAM pipe every1 km.
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 15
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-15
ANNEX P-16
MONTH :
Package No. 16 Time Elapsed (Days) 221
Name Seblat - Ipuh Time Elapsed (%) 35,1%
Project Manager Fathoni Ikhsan, ST Scheduled Progress (%) 7,15 Contractor KSO PT Yasa - Multi Structure Actual Overall Progress (%) 8,68 Supervision Consultant A Joint Venture of Renardet, S.A. Balance (%) 1,53Contract Sign Progress This Month (%) 3,78 Commencement Date Time for Complation (Days) 630 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 11,46%Price Adjustment Rp.
Comp Add.2 Accum Actual Accum AccumTotal Total Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 1,40 1,51 0,82 0,02 0,84 0,92II D r a i n a g e 13,85 13,71 1,22 2,29 3,51 4,05III Earthworks 6,57 5,95 1,48 0,52 2,00 2,56
IV Pavement Widening &Shoulders
2,32 2,30 0,08 - 0,08 -
V Granular Pavement 10,85 10,97 4,01 - 4,01 0,44VI Asphalt Pavement 51,52 53,56 0,00 - 0,00 -VII S t r u c t u r e s 8,41 8,46 0,97 0,46 1,43 2,71
VIII Reinstatement & MinorWorks
4,79 3,25 - 0,13 0,13 -
IX Day Work 0,05 0,05 0,02 0,00 0,02 0,02
X Routine MaintenanceWorks
0,24 0,24 0,09 0,00 0,09 0,09
TOTAL 100,00 100,00 8,68 3,43 12,11 10,78Note :
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 210,07 0,26 0,57 4,03 8,73 12,40 17,12 21,87 25,29 30,86 36,98 43,59 52,25 58,94 63,06 69,89 75,30 80,70 86,70 92,22 100,0
1st REVISED Schedul (%) 0,16 0,26 0,57 1,02 2,10 4,32 7,15 10,78 16,24 20,83 25,94 30,14 37,57 46,70 53,77 62,47 70,59 80,97 90,76 97,97 100,00,18 0,260 0,407 1,04 2,17 4,90 8,68 12,110,11 - (0,16) (2,99) 0,07 0,58 1,53 1,33
Progress per month 0,18 0,08 0,15 0,63 1,13 2,73 3,78 3,430,08 0,15 0,63 1,13 2,73 3,78 3,43 (12,11) - - - - -
24.224.417.000
Year
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
DISBURSEMENT (Incl VAT)31-Jul-18 17-Jun-17
211.374.500.000
ACTION TO BE TAKEN
AMO
UN
TTI
ME June 17, 2017
2018
MAJOR PROBLEMS
• Under process of field engineering • After field engineering, the Contractor willevaluate the entire quantity and propose thechange to PHO date
PHYSICAL WORK PROGRESS BY CATEGORY
Balance (%)
28-Oct-1608-Nop-16
2016 2017 Month The month of time for complation Original Progress Schedul (%)
Actual Progress (%)
Div Description
PHYSICAL PROGRESS MONITORING TABLE
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 16
ORIGINAL Sch
1st REVISED Sch
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\6 ESR CTC 17 Jun 2017_93BEBF P-16
ANNEX P-17
MONTH :
Package No. Time Elapsed (Days) 652
Name PUGUNG TAMPAK-Sp.Gn KEMALA Time Elapsed (%) 90,56% Project Manager Scheduled Progress (%) 79,35 Contractor PT. JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 77,53 Supervision Consultant Balance (%) -1,82Contract Sign Progress This Month (%) 4,80 Commencement Date Time for Complation (Days) 720 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 61,95%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 8,05 1,676 - 1,676 1,678II D r a i n a g e 12,92 7,94 0,588 8,53 11,11III Earthworks 16,93 17,36 0,069 17,43 19,54
IV Pavement Widening &Shoulders
7,36 5,37 0,400 5,77 6,80
V Granular Pavement 4,09 2,24 0,205 2,45 3,11VI Asphalt Pavement 42,82 34,22 3,307 37,53 30,55VII S t r u c t u r e s 1,98 3,39 0,224 3,61 5,31
VIII Reinstatement & MinorWorks
5,30 0,138 - 0,138 0,77
IX Day Work 0,23 0,07 - 0,07 0,17
X Routine MaintenanceWorks
0,34 0,32 0,010 0,33 0,31
TOTAL 100,0 72,73 4,80 77,53 79,35
Note :
Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Agt Sep The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Schedl Progress Original (%) 0,18 0,70 1,18 1,51 2,39 3,80 6,10 10,09 14,15 18,21 21,04 26,32 33,01 39,79 46,73 54,12 61,80 69,15 75,00 80,05 85,25 90,26 95,19 100,0 100,0 1st Revised Progress Schedul (%) 50,59 55,87 62,09 68,69 75,33 79,35 85,57 91,8 100,0 Actual Progress (%) 0,921 1,13 1,42 3,05 3,45 4,11 6,16 9,54 13,81 16,99 17,41 20,33 28,34 33,32 38,86 41,34 49,01 53,30 61,37 66,06 72,73 77,53 Balance (%) 0,74 0,43 0,23 1,54 1,06 0,30 0,06 (0,55) (0,34) (1,23) (3,63) (5,99) (4,68) (6,47) (7,87) (12,78) (12,80) (2,57) (0,72) (2,63) (2,60) (1,82)Progress per month 0,92 0,21 0,29 1,63 0,40 0,66 2,05 3,38 4,28 3,18 0,42 2,92 8,00 4,99 5,54 2,48 7,66 4,29 8,08 4,69 6,67 4,80
0,21 0,29 1,63 0,40 0,66 2,05 3,38 4,28 3,18 0,42 2,92 8,00 4,99
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
17
TIM
E June 17, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN• Acceleration of LARAP implementation
RENARDET S.A JV17-Nov-1404-Sep-15
DISBURSEMENT (Incl VAT)
AMO
UN
TJoko Wisargo, ST, MT
23-Agust-17 17-Jun-17199.551.233.000 123.631.200.533,33
• Unsettled land acquisition: 98 PAPS
PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 17
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-17
ANNEX P-19
MONTH :
Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Yahya, ST Scheduled Progress (%) 100,0 Contractor Actual Overall Progress (%) 100,0 Supervision Consultant Balance (%) Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 300 Calendar Days Final Time for Complation (Days) 477 Calendar Days Status date Take Over Date Accumulative Rp. 100% Contract Amount (Incl VAT) Rp. Contract Amount Add-1 (+ VAT) Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,43 0,32 0,32 0,32II D r a i n a g e 3,15 2,73 2,73 2,73III Earthworks 11,96 11,31 11,31 11,31
IV Pavement Widening &Shoulders
5,30 4,02 4,02 4,02
V Granular Pavement 10,69 8,82 8,82 8,82VI Asphalt Pavement 59,66 64,4 64,4 64,41VII S t r u c t u r e s 2,00 4,02 4,02 4,02
VIII Reinstatement & MinorWorks
6,79 4,35 4,35 4,35
IX Day Work
X Routine MaintenanceWorks
0,03 0,02 0,02 0,02
TOTAL 100,00 100,00 - 100 100,00Note :
1. 100% completed on 30 Jun 20162. Taking-Over Certificate issued on 30 Jun 20163. Defects Liability Periode until 29 Jun 2018
Year Month March April May June July Aug Sept Oct Nov Des Jan Feb March April May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Schedl Progress Original (%) 0,12 1,40 8,96 18,40 21,37 23,62 37,37 58,19 87,25 100,00
43,60 52,20 67,79 79,68 98,93 100,00 Actual Progress (%) 0,15 1,30 6,28 14,54 16,21 22,41 28,90 49,74 57,15 57,48 52,77 77,34 80,78 97,14 100,00 Balance (%) 0,03 -0,10 -2,68 -3,86 -5,16 -1,21 -8,47 -8,45 -30,10 13,88 0,57 9,55 1,10 -1,79 0,00
4,98 8,26 1,67 6,20 6,49 20,84 7,42 0,32 (4,71) 24,57 3,44 16,36
19
TIM
E June 17, 2017 BINTUNAN-LAIS MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
44.419.760.000
Rivised Progress Schedul Add.1 (%)
2016PHYSICAL PROGRESS MONITORING TABLE
Div
2015
Description
PHYSICAL WORK PROGRESS BY CATEGORY
17-Jun-1744.419.760.829
27-Feb-1511-Mar-15
RENARDET S.A JV
30-Jun-16
DISBURSEMENT (Incl VAT)
AMO
UN
T
PT RODATEKNINDO PURAJAYA
33.689.452.000
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 19
ORIGINAL
REVISED SCH
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-19
ANNEX P-20
MONTH :
Package No. Time Elapsed (Days) 289 Name Time Elapsed (%) 59,47% Project Manager Andi Mulya Rusli, ST, MT Scheduled Progress (%) 71,88 Contractor 'PT Nindya Karya (Persero) Actual Overall Progress (%) 57,73 Supervision Consultant RENARDET S.A JV PT.Yodya (Persero) Balance (%) -14,15 Contract Sign Progress This Month (%) 3,50 Commencement Date Time for Complation (Days) 486 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 45,33%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,90 0,72 (0,17) 0,54II D r a i n a g e 32,44 26,71 - 26,71III Earthworks 6,64 2,77 0,44 3,21
IV Pavement Widening &Shoulders
3,78 - - -
V Granular Pavement 9,52 4,06 0,64 4,70VI Asphalt Pavement 42,49 17,95 3,24 21,19VII S t r u c t u r e s 1,83 1,10 0,14 1,24
VIII Reinstatement & MinorWorks
1,93 - - -
IX Day Work 0,04 - - -
X Routine MaintenanceWorks
0,43 0,92 (0,78) 0,13
TOTAL 100,00 54,23 3,50 57,73 -Note :
Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Schedl Progress Original (%) 0,30 0,57 3,95 12,38 19,58 30,48 45,58 57,67 68,57 71,76 77,66 84,15 89,19 95,47 98,66 100,00 1st Revised Progress Schedul (%) 0,23 0,52 4,41 10,83 18,56 30,61 42,24 55,64 67,61 71,88 76,86 82,61 88,27 94,64 97,91 100,00 Actual Progress (%) 0,39 0,63 3,77 13,60 16,95 23,14 33,37 46,78 54,23 57,73 Balance (%) 0,09 0,06 (0,18) 1,22 (2,63) (7,34) (12,21) (8,86) (13,39) (14,15)Progress per month 0,39 0,24 3,14 9,83 3,35 6,19 10,23 13,41 7,45 3,50
3,14 9,83 3,35 6,19 10,23 13,41 7,45 3,50 (57,73) - - -
20
TIM
E June 17, 2017LubuK Alun - Sicincin MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
2016 2017
113.818.300.00031-Dec-17
• Unsettled land acquisition: 117 PAPs• Obstruction on relocation of PDAM pipe & powerpoles (PLN)AM
OU
NT
1-Jun-161-Sep-16
DISBURSEMENT (Incl VAT)
• Acceleration of LARAP implementation• PPK to coordinate with PDAM & PLN
Div Description
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
17-Jun-1751.588.664.567
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 20
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-20
ANNEX P-21
MONTH :
Package No. Time Elapsed (Days) 289 Name Time Elapsed (%) 59,47% Project Manager Opukenigara, ST Scheduled Progress (%) 55,91 Contractor 'PT Multi Structur Actual Overall Progress (%) 39,33 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) (16,58) Contract Sign Progress This Month (%) 4,42 Commencement Date Time for Complation (Days) 486 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 36,76%Price Adjustment Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 3,34 3,30 - 3,30II D r a i n a g e 36,79 8,87 0,89 9,76III Earthworks 6,17 2,28 0,44 2,72
IV Pavement Widening &Shoulders
2,29 - - -
V Granular Pavement 7,72 3,01 0,45 3,46VI Asphalt Pavement 37,82 13,1 1,67 14,8VII S t r u c t u r e s 3,29 3,71 0,97 4,68
VIII Reinstatement & MinorWorks
2,24 0,56 - 0,56
IX Day Work 0,04 - - -
X Routine MaintenanceWorks
0,30 0,07 - 0,07
TOTAL 100,00 34,91 4,42 39,3 -Note :
Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Schedl Progress Original (%) 0,56 2,40 4,37 12,27 21,33 28,48 37,16 43,98 50,80 55,91 62,73 71,26 76,82 82,58 94,28 100,0 1st Revised Progress Schedul (%) 2,05 3,03 9,86 20,07 28,23 35,21 42,76 50,07 55,91 61,52 69,07 75,59 81,76 91,81 100,0 Actual Progress (%) 0,78 1,94 2,20 3,25 13,38 15,66 21,25 22,41 34,91 39,33 Balance (%) 0,22 (0,11) (0,83) (6,61) (6,69) (12,57) (13,96) (20,35) (15,16) (16,58)Progress per month 0,78 1,16 0,26 1,05 10,13 2,28 5,59 1,16 12,50 4,42
0,26 1,05 10,13 2,28 5,59 1,16 12,50 4,42 (39,33) - - -
21
TIM
E June 17, 2017LubuK Alun - Kuraitaji MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTJun-17
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
2016 2017
31-Dec-17126.301.900.000
• Drainage work progress is too slow. Only 3 teamsare available while it required 9 teams. The totalpercentage of drainage work is 37% Compared to38% pavement work• Lack of financial support from the Contractor’sHead Office▪ Unsettled land acquisation 90 PAPs
AMO
UN
T
1-Jun-161-Sep-16
DISBURSEMENT (Incl VAT)
• Contractors working team gradual increase of 3teams into 9 teams
• SCM held on March 13, 2017 in Directorate ofRoad Preservation to ask firmness contractormanagement in allocating fund for projectimplementation.
Div Description
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
17-Jun-1746.424.898.000
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 21
ORIGINAL Sch
1st REVISED Sch
ACTUAL
6 ESR CTC 17 Jun 2017_93BEBF P-21
Appendix S-1 As of JUNE 2017
1 2 3 5 6 7 8 9
1 Krui - Bha Lampung 1 SPPL November 2010 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013 /NOL
2 AMDAL Environmental Feasibility : 12 Oct 2012
Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013/NOL
3 Monitoring of Integration
AMDAL into Design - 1X 15 August 2014 NN NN
4 AMDAL Implementation Report
(PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015 ;
29 April 2015 ; 19 Oct2015
11 Mei 2015 ; 14 Des2015
5 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL
6 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17Feb 2016
31 July 2015 ; 24 Nov2015 ; Informal to WB 4
& 17 Feb 2016
13 August 2015:14 Dec 15 ; 19 Feb
2016
7 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
2 Padang Sawah - Sp Empat Sumatera Barat 1 SPPL Nov. 2013 1X - 20 Jan 2014 14 April 2014/NOL
Jembatan Air Gadang Sumatera Barat 2 UKL & UPL Recommendation: Nov 2013 1X - 09 June 2014 08 Auguts 2014/NOL
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015 ; 28 Jun 2016
29 April 2015 ; 19 Oct2015 : 21 Juli 2016
11 Mei 2015 ; 14 Des2015 ; 22 Juli 2016
4 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL
5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17Feb 2016 ; 28 Jun 2016
31 July 2015 ; 24 Nov2015 ; Informal to WB 4& 17 Feb 2016 ; 21 Juli
2016
13 August 2015:14 Dec 15 ; 19 Feb2016 ; 22 Juli 2016
6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
3 Manggopoh - Padang Sawah Sumatera Barat 1 SPPL 30 Dec 2013 1X - 20 Jan 2014 14 April 2014
2 SPPL Implementation Report
(PIU to BLH) - each 6month
17 April 2015 29 April 2015 11 Mei 2015
3 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL
4 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17Feb 2016
31 July 2015 ; 24 Nov2015 ; Informal to WB 4
& 17 Feb 2016
13 August 2015:14 Dec 15 ; 19 Feb
2016
5 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
4 Ipuh - Bantal Bengkulu 1 SPPL (Initial study) 20 Dec 2013 1X April 2013 - -
2 UKL & UPL Environmental permits : 6 Des 2014 1X - 06 Feb 2015
(Environment permits) 23 Feb 2015
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015 ; 28 Juni 2016
29 April 2015 ; 19 Oct2015 : 21 Juli 2016
11 Mei 2015 ; 14 Des2015 ; 22 Juli 2016
4 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL
5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17Feb 2016 ; 28 Jun 2016
31 July 2015 ; 24 Nov2015 ; Informal to WB 4& 17 Feb 2016 ; 21 Juli
2016
13 August 2015:14 Dec 15 ; 19 Feb2016 ; 22 Juli 2016
4
Correspondence of Environmental Safeguard and Reporting on CTC WINRIP
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province Sent to WBCTC Letters to PMUDurations
Environmental Activity, CTC WINRIP
WB NOL/LettersEnvironmental Safeguard
1 2 3 5 6 7 8 94
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/LettersEnvironmental Safeguard
6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
5 Sp. Rampa - Poriaha Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 11 Nov 2014 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
28 Jun 2016 21 Juli 2016 22 Juli 2016
4 RKPPL - 1X 26 April 2016 13 May 2016 30 Juni 2016
6 RKPPL Implementation Report Quarter 4 Feb 2016 ; 17 Feb
2016 ; 28 Jun 2016;11Nov 2016; 2 Jun 2017
Informal to WB 4 & 17Feb 2016 : 21 Juli 2016;28 Nov 2016 ; 15 Mar2017 (informal) ; 9 Jun
19 Feb 2016 ; 22 Juli2016; 19 Des 2016; UP
6 HIV - AIDS Campaign Report - 1X 29 February 2016 15 March 2016 NN
6 Ps. Pedati - Kerkap Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - Quarter 28 Jun 2016 21 Juli 2016 ; 20 Nov
2016 (informal) 22 Juli 2016
4 RKPPL - one time 4 Nov 2015 24-Nov-15 14 Des 2016 (NOL)
5 RKPPL Implementation Report Quarter 13 Nov 2015 ; 4 Feb
2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016
24 Nov 2015; Informalto WB 4 & 17 Feb 2016;
21 Juli 2016; 28 Nov2016 ; 15 Mar 2017
(informal)
14 Des 2016 (NOL) ; 19Feb 2016 ; 22 Juli
2016; 19 Des 2016
6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN
7 Indrapura - Tapan Sumatera Barat 1 AMDAL Environmental feasibility : 05 Feb 2014 ;
environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
1 March 2017 13 April 2017 17 April 2017
4 RKPPL - 1X 27 Feb 2017 20 March 2017 5 April 2017
5 RKPPL Implementation Report Quarter 15 Mar 2017
(informal) ; 2 Jun 2017 15 Mar 2017 (informal)
; 9 Jun 2017 5 April 2017 ; UP
6 HIV - AIDS Campaign Report - 1X 29 Sept 2016 13 October 2016 NN
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014
2 Monitoring of Integration
AMDAL into Design - 1X 6 Oct 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
29 Sept 2016 13 October 2016 NY
4 RKPPL - 1X 02 November 2016 14 November 2016 23 November 2016
5 RKPPL Implementation Report Quarter 15 Mar 2017
(informal) ; 2 Jun 2017
15 Mar 2017 (informal); 9 Jun 2017 UP
6 HIV - AIDS Campaign Report - 1X 11 November 2016 ; 6April 2017
28 November 2016; 13April 2017
NN
9 Bentungan- Tais (N.013.018 ; 43,42km)
Bengkulu
1 2 3 5 6 7 8 94
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/LettersEnvironmental Safeguard
10 Sp. Empat - Air Balam Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014
11 Bantal - Mukomuko Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 10 Dec 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
28 Jun 2016 ; 29 April 2016 (informal)
; 21 Juli 2016 ; 5 Des2016 informal
22 Juli 2016
4 RKPPL - 1X 10 Des 2015 23-Dec-15 8 Jan 2016/NOL
5 RKPPL Implementation Report Quarter
13 Nov 2015 ; 4 Feb2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016;15 Mar 2017 (informal)
; 2 Jun 2017
24 Nov 2015; Informalto WB 4 & 17 Feb 2016;
21 Juli 2016; 28 Nov2016 ; 15 Mar 2017
(informal) ; 9 Jun 2017
14 Des 2016 (NOL) ; 19Feb 2016 ; 12 Juli
2016; 19 Des 2016 ; UP
6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
12 Kambang - Indrapura Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
1 March 2017 13 April 2017 17 April 2017
4 RKPPL - 1X 27 Feb 2017 ; 8 May
2017 (Rev RKPPL) 20 March 2017 ; 29 May
2017 (Rev RKPPL) 5 April 2017 ; UP
5 RKPPL Implementation Report Quarter 15 Mar 2017
(informal) ; 2 Jun 2017 15 Mar 2017 (informal)
; 9 Jun 2017 5 April 2017 ; UP
6 HIV - AIDS Campaign Report - 1X 29 Sept 2016 13 October 2016 NN
13 Sp. Rukis - Tj. Kemuning Bengkulu 1 UKL & UPL Recommendation : 31 Jan 2012 (Link of SpRukis Mana-Bts Kab Kaur & 4 Feb 2012 (Bts
Kaur - Tj Kemuning) 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
UKL&UPL into Design - 1X 6 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
28 Jun 2016 21 Juli 2016 22 Juli 2016
4 RKPPL - 1X 4 Nov 2015 24-Nov-15 14 Dec 2015/NOL
5 RKPPL Implementation Report Quarter
4 Feb 2016 ; 17 Feb2016 ; 28 Jun 2016 : 11
Nov 2016; 15 Maret2017 ; 2 Jun 2017
Informal to WB 4 & 17Feb 2016 : 21 Juli 2016;
28 Nov 201615; Mar2017 (informal) ; 9 Jun
2017
19 Feb 2016 ; 22 Juli2016; 19 Des 2016 ; UP
6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN
14 Painan - Kambang Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
1 March 2017 13 April 2017 17 April 2017
4 RKPPL - 1X 10 Feb 2017 28 Feb 2017 17 March 2017
5 RKPPL Implementation Report Quarter 15 Mar 2017
(informal) ; 2 Jun 2017 15 Mar 2017 (informal)
; 9 Jun 2017 17 March 2017 ; UP
1 2 3 5 6 7 8 94
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/LettersEnvironmental Safeguard
6 HIV - AIDS Campaign Report - 1X 21 Des 2016 28 Des 2016 NN
15 Sibolga - Bts. Tapsel Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 11 Nov 2014 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
28 Jun 2016 21 Juli 2016 22 Juli 2016
4 RKPPL - 1X 02 November 2016 14 November 2016 23 November 2016
5 RKPPL Implementation Report Quarter28 Juni 2016 : 11 Nov
2016; 15 Mar 2016(informal) ; 2 Jun 2017
21 Juli 2016; 28 Nov2016; 15 Mar 2017
(informal) ; 9 Jun 2017
22 Juli 2016; 19 Des2016 ; UP
6 HIV - AIDS Campaign Report - 1X 29 February 2016 15 March 2016 NN
16 Sebelat-Ipuh Inc.Air Lalang & AirGunung Bridges
Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 10 Dec 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NN
4 RKPPL - 1X 2 June 2017 9 June 2017 UP
5 RKPPL Implementation Report Quarter 2 Jun 2017 9 Jun 2017 UP
6 HIV - AIDS Campaign Report - 1X 13 June 2017 UP NN
17 Sp. Gunung Kemala-Pg. Tampak,Inc Way Tauu Bridge
Lampung 1 AMDAL Environmental Feasibility : 12 Oct 2012
Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
AMDAL into Design - 1X 11 Nov 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
28 Jun 2016 21 Juli 2016 ; 28 Sept
2016 ; 20 Nov 2016 22 Juli 2016
4 RKPPL - 1X 26 April 2016 13 May 2016 30 Juni 2016
5 RKPPL Implementation Report Quarter28 Juni 2016 : 11 Nov
2016;15 Mar 2017(informal) ; 2 Jun 2017
21 Juli 2016; 28 Nov2016 ;15 Mar 2017
(informal) ; 9 Jun 2017
22 Juli 2016; 19 Des2016 ; UP
6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN
18 Seblat - Ketahun (N.013.005 :Panjang 42,07km)
Bengkulu
19 Lais- Bintunan Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 6 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 3month
28 Jun 2016 21 Juli 2016 ; 20 Nov
2016 (informal) 22 Juli 2016
4 RKPPL - 1X 4 Nov 2015 24-Nov-15 14 Dec 2015/NOL
5 RKPPL Implementation Report Quarter 13 Nov 2015 ; 4 Feb
2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016
24 Nov 2015; Informalto WB 4 & 17 Feb 2016:
21 Juli 2016; 28 Nov2016
14 Des 2016 (NOL) ; 19Feb 2016 ; 22 Juli
2016; 19 Des 2016
6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN
20 Lubuk Alung - Sincin Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
1 2 3 5 6 7 8 94
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/LettersEnvironmental Safeguard
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
2 June 2017 9 June 2017 UP
4 RKPPL - 1X 10 Feb 2017 28 Feb 2017 17 March 2017
RKPPL Implementation Report Quarter 15 Mar 2017 (informal) 15 Mar 2017 (informal) 17 March 2017
5 HIV - AIDS Campaign Report - 1X 6 April 2017 13 April 2017 NN
21 Lubuk Alung - Kuraitaji Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
2 June 2017 9 June 2017 UP
4 RKPPL - 1X 27 Feb 2017 ; 8 May
2017 (Rev RKPPL) 20 March 2017 ; 29 May
2017 (Rev RKPPL) 5 April 2017 ; UP
5 RKPPL Implementation Report Quarter 15 Mar 2017 (informal) 15 Mar 2017 (informal) 5 April 2017
6 HIV - AIDS Campaign Report - 1X 6 April 2017 13 April 2017 NN
Keterangan :
incl. 1 Document Studi Amdal
incl. 1 Document Studi Amdal
NYS: Not Yet Started incl. 1 Document Studi Amdal
NY : Not Yet
NN : Not Need
UP : Under Process
Appendix S-2 As of Juni 2017
NOL Not Yet NOL
1 Krui - Biha 1 Studi LARAP (2,815 WTP) 19 Desember 2012 4 Januari 20131 Monitoring LARAP 2 April 2013 10 April 2013 18 April 20131 Monitoring LARAP Rev 18 Juni 2013 21 Juni 2013 26 Juni 20132 Monitoring LARAP 2 Oktober 2015 16 Oktober 2015 20 Oktober 2015
2 Pd. Sawah - Sp. Empat 1 Studi LARAP (414 WTP) 12 Desember 2012 13 Desember 20121 Monitoring LARAP 2 April 2013 10 April 2013 18 April 20132 Monitoring LARAP Rev 5 Juli 2013 15 Juli 2013 19 Juli 20133 Monitoring LARAP 28 Januari 2015 06 Februari 2015 12 Februari 2015
2a Pd. Sawah - Sp. Empat Studi LARAP Tambahan (52 WTP) 10 Juli 2014 10 Juli 2014 21 Juli 2014
3 Manggopoh - Pd. Sawah 1 Studi LARAP (1,338 WTP) 12 Desember 2012 13 Desember 20121 Monitoring LARAP 2 April 2013 5 April 2013 18 April 2013
Monitoring LARAP Rev 18 Juni 2013 21 Juni 2013 26 Juni 20132 Monitoring LARAP - 25 Februari 2014 5 Maret 20143 Monitoring LARAP 10 Juni 2014 19 Juni 2014 23 Juni 20144 Monitoring LARAP 28 Januari 2015 06 Februari 2015 12 Februari 20155 Monitoring LARAP 26 Februari 2015 06 Maret 2015 17 Maret 20156 Monitoring LARAP 2 Oktober 2015 16 Oktober 2015 20 Oktober 2015
4 Ipuh - Bantal 1 Studi LARAP (257 WTP) 23 November 2012 10 Desember 20121 Monitoring LARAP (157 WTP) 23 Desember 2013 24 Desember 2013 6 Januari 2014
Total WTP 261 2 Monitoring LARAP (70 WTP) - 25 Februari 2014 5 Maret 20143 Monitoring LARAP (34 WTP) 23 Januari 2015 06 Februari 2015 12 Februari 2015
5 Sp. Rampa - Poriaha 1 Studi LARAP (71 WTP) 30 Agustus 2013 10 September 2013 16 September 20132 Studi LARAP (Action Plan Signed) 29 Oktober 2013 6 November 2013 12 November 20131 Additional LARAP 23 Desember 2015 08 Januari 20161 Monitoring LARAP ( 68 WTP) 16 November 2016
Additional LARAP 20 Februari 2017 20 Maret 2017
6 Ps. Pedati - Kerkap 1 Studi LARAP (637 WTP) 29 Oktober 2013 13 November 2013 20 November 20132 Studi LARAP rev 30 Desember 2013 9 Januari 2014 16 Januari 20143 Studi LARAP (Action Plan Signed) 25 Februari 2014 21 Mei 2014 30 Mei 20141 Monitoring LARAP (546 WTP) 5 Maret 2015 16 Maret 2015 23 Maret 2015
Total WTP 637 1a Kelengkapan Monitoring LARAP (dok Appraisal) 13 Mei 2015 29 Mei 2015 -2 Monitoring LARAP ( 91 WTP) 25 November 2015 27 November 2015 05 Januari 2016
7 Indarapura - Tapan 1 Studi LARAP (861 WTP) 3 September 2014 24 September 2014 14 Oktober 20142 Studi LARAP (Action Plan Signed) 16 Februari 2015 06 Maret 2015 17 Maret 20151 Monitoring LARAP (276 WTP) 29 Februari 2016 10 Februari 2016 16 Maret 20162 Monitoring LARAP (207 WTP) 20 Juli 2016 21 Juli 2016 15 Agustus 2016
Total WTP 653 3 Monitoring LARAP (89 WTP) 10 November 2016 11 November 20164 Monitoring LARAP (61 WTP) 6 Januari 2017 16-Jan-17 26 Januari 20175 Monitoring LARAP (20 WTP) 31 Mei 2017 5 Juni 2017 22 Juni 2017
8 Bts Kota Pariaman - Manggopoh 1 Studi LARAP (2,339 WTP) 23 Juli 2014 7 Agustus 2014 12 Agustus 2014
Summary of Studies and ReportsSocial Impact Activity, CTC WINRIP
Number ofPackage
Name of LinkNo ofdoc
Document CTC Letter to PMU Sent to WB (DPJJ-WB)Response from World Bank
NOL Not Yet NOL
Number ofPackage
Name of LinkNo ofdoc
Document CTC Letter to PMU Sent to WB (DPJJ-WB)Response from World Bank
2 Studi LARAP (Action Plan Signed), informal sending 18 September 2015 -1 Monitoring LARAP (840 WTP) 25 Januari 2016 14 Januari 2016 8 Maret 2016
Total WTP 2206 2 Monitoring LARAP (926 WTP) - 09 Mei 20163 Monitoring LARAP (440 WTP) 19 Desember 2016 9 Januari 2017
9 Rantau Tijang - Kota Agung
10 SP. Empat - Air Balam Studi LARAP (2,915 WTP) 23 Juli 2014 7 Agustus 2014 12 Agustus 20141 Monitoring LARAP (1.421 WTP) 25 Januari 2016 14 Januari 2016 8 Maret 2016
11 Bantal - Muko Muko 1 Studi LARAP (243 WTP) 29 Oktober 2013 13 November 2013 20 November 20132 Studi LARAP rev 30 Desember 2013 9 Januari 2014 16 Januari 20143 Studi LARAP (Action Plan Signed) 25 Februari 2014 21 Mei 2014 30 Mei 20141 Monitoring LARAP (81 WTP) 19 November 2014 2 Desember 2014 2 Desember 20142 Monitoring LARAP (58 WTP) 23 Januari 2015 06 Februari 2015 12 Februari 2015
2a Kelengkapan Monitoring LARAP (Strip Map) 13 Mei 2015 29 Mei 2015 -Total WTP 243 3 Monitoring LARAP (15 WTP) 25 November 2015 27 November 2015 05 Januari 2016
4 Monitoring LARAP ( 89 WTP) 21 Oktober 2016 26 Oktober 2016 28 Oktober 2016
12 Kambang - Indrapura 1 Studi LARAP (2,992 WTP) 3 September 2014 24 September 2014 14 Oktober 20142 Studi LARAP (Action Plan Signed) 16 Februari 2015 06 Maret 2015 17 Maret 20151 Monitoring LARAP (216 WTP) 26 Mei 2016 7 Juni 2016
Total WTP 629 2 Monitoring LARAP (60 WTP) 2 November 2016 11 November 2016 11 November 20163 Monitoring LARAP (88 WTP) 23 Januari 2017 9 Februari 2017 13 Februari 20174 Monitoring LARAP (265 WTP) 31 Mei 2017 5 Juni 2017 22 Juni 2017
13 Sp. Rukis - Tj Kemuning 1 Studi LARAP (2,917 WTP) 29 Oktober 2013 13 November 2013 20 November 20132 Studi LARAP rev 30 Desember 2013 9 Januari 2014 16 Januari 20143 Studi LARAP (Action Plan Signed) 25 Februari 2014 21 Mei 2014 30 Mei 20141 Monitoring LARAP (149 WTP) 06 Juli 2015 31 Juli 2015 18 Agustus 20152 Monitoring LARAP (40 WTP) 22 September 2015 12 Oktober 2015 13 Oktober 20153 Monitoring LARAP (193 WTP) 25 Januari 2016 14 Januari 2016 8 Maret 20164 Monitoring LARAP (188 WTP) 20 September 2016 6 Oktober 2016 12 Oktober 2016
Total WTP 2179 5 Monitoring LARAP (333 WTP) 8 November 2016 18 November 20166 Monitoring LARAP (1.090 WTP) 20 Februari 2017 20 Maret 20177 Monitoring LARAP (186 WTP) 17 Mei 2017 19 Mei 2017 23 Mei 2017
14 Painam - Kambang 1 Studi LARAP (2,648 WTP) 28 November 2014 18 Desember 2014 18 Desember 20142 Studi LARAP (Action Plan Signed) 16 Februari 2015 06 Maret 2015 17 Maret 20151 Monitoring LARAP (126 WTP) 20 Juli 2016 20 Juli 2016 01 Agustus 2016
Total WTP 467 2 Monitoring LARAP (62 WTP) 3 November 2016 11 November 2016 11 November 2016total yg sdh dibayar 1.129 3 Monitoring LARAP (220 WTP) 20 Februari 2017 20 Maret 2017
4 Monitoring LARAP (59 WTP) 14 Juni 2017 19 Juni 2017
15 Sibolga - Bts. Tapsel 1 Studi LARAP (2,003 WTP) 22 Oktober 2013 28 Oktober 20132 Studi LARAP rev (Action Plan Signed) 15 Januari 2014 30 Januari 2014 9 Februari 20141 Monitoring LARAP (43 WTP) 16 October 2015 16 November 2015 16 November 20152 Monitoring LARAP (72 WTP) 25 Januari 2016 14 Januari 2016 8 Maret 20163 Monitoring LARAP (237 WTP) 29 Februari 2016 10 Februari 2016 15 Maret 2016
NOL Not Yet NOL
Number ofPackage
Name of LinkNo ofdoc
Document CTC Letter to PMU Sent to WB (DPJJ-WB)Response from World Bank
4 Monitoring LARAP (55 WTP) 18 April 2016 13 April 2016 19 May 2016Total WTP 702 5 Monitoring LARAP (34 WTP) 13 Juni 2016 8 Agustus 2016 18 Agustus 2016
6 Monitoring LARAP (127 WTP) 4 Januari 2017 16 Januari 2017 26 Januari 20177 Monitoring LARAP (134 WTP) 14 Juni 2017 19 Juni 2017
16 Sebelat - Ipuh 1 Studi LARAP (259 WTP) 29 Oktober 2013 13 November 2013 20 November 20132 Studi LARAP rev 30 Desember 2013 9 Januari 2014 16 Januari 20143 Studi LARAP (Action Plan Signed) 25 Februari 2014 21 Mei 2014 30 Mei 20141 Monitoring LARAP (139 WTP) 23 Januari 2015 06 Februari 2015 12 Februari 2015
1a Kelengkapan Monitoring LARAP (Strip Map) 13 Mei 2015 29 Mei 2015 -2 Monitoring LARAP (102 WTP) 16 Oktober 2015 27 November 2015 05 Januari 2016
Total WTP 274 Update LARAP Monitoring Report 11 Mei 2016 7 Juni 20163 Monitoring LARAP ( 33 WTP) 24 Oktober 2016 10 November 2016 11 November 2016
17 Sp. Gunung Kemala - Pg. Tampak 1 Studi LARAP (2,620 WTP) 5 September 2013 10 September 2013 16 September 20132 Studi LARAP rev (Action Plan Signed) 29 Oktober 2013 6 November 2013 12 November 20131 Monitoring LARAP (154 WTP) 21 September 2015 12 Oktober 2015 13 Oktober 20152 Monitoring LARAP (735 WTP) 25 November 2015 27 November 2015 05 Januari 2016
Total WTP 2507 3 Monitoring LARAP (1,156 WTP) 8 November 2016 9 November 2016 (Informal) 18 November 20164 Monitoring LARAP (462 WTP) 30 Maret 2017 18 April 2017
18 Muko-Muko - Bts Sumbar
19 Lais - Bintunan 1 Studi LARAP (538 WTP) 29 Oktober 2013 13 November 2013 20 November 20132 Studi LARAP rev 30 Desember 2013 9 Januari 2014 16 Januari 20143 Studi LARAP (Action Plan Signed) 25 Februari 2014 21 Mei 2014 30 Mei 20141 Monitoring LARAP (266 WTP) 5 Maret 2015 16 Maret 2015 23 Maret 2015
1a Kelengkapan Monitoring LARAP (dok Appraisal) 13 Mei 2015 29 Mei 2015 -Total WTP 538 2 Monitoring LARAP (208 WTP) 25 November 2015 27 November 2015 05 Januari 2016
3 Monitoring LARAP (64 WTP) 9 November 2016 13 Desember 2016
20 Lubuk Alung - Sicincin 1 Studi LARAP (1,070 WTP) 28 November 2014 18 Desember 2014 18 Desember 20141 Monitoring LARAP (670 WTP) 8 September 2016 19 September 2016 26 September 2016
Total WTP 950 2 Monitoring LARAP (280 WTP) 13 Februari 2017 18 April 2017
21 Lubuk Alung - Kuraitaji 1 Studi LARAP (869 WTP) 28 November 2014 18 Desember 2014 18 Desember 2014
1 Monitoring LARAP (515 WTP)01 Agustus 2016 01 Agustus 2016
01 Agustus 2016 (Nonformal)
Total WTP 751 2 Monitoring LARAP (236 WTP) 19 Desember 2016 24 Januari 2017
Page 1 of 3
Community Development Activity Reports
As of End of June, 2017
CTC WINRIPAppendix S-3
No. Number ofReport Activity Date of Activity CTC Transmittal Letter
No.Date of Submission
Report
1 14-06/01 Workshop of Bid Documment Evaluation February 28 – March 1,2013
14_06/YKB/O/069 October 8, 2013
2 14-06/02 Socialization for CRO Selection AWP 1 April 9, 2013 (Padang)April 11, 2013 (Palembang)
14_06/YKB/O/069 October 8, 2013
3 14-06/03 Workshop of World Bank ProcurementGuidelines for WINRIP April 24 – 25, 2013 14_06/YKB/O/069 October 8, 2013
4 14-06/04 CRO Selection and Training, Package No. 01and 04 May 23, 2013 14_06/YKB/O/069 October 8, 2013
5 14-06/05 CRO Selection and Training, Package No. 02and 03 May 27, 2013 14_06/YKB/O/069 October 8, 2013
6 14-06/06 CRO Mentoring for Site Visit, Package No. 02and 03 June 10 – 11, 2013 14_06/YKB/O/069 October 8, 2013
7 14-06/07 CRO Mentoring for Site Visit, Package No. 04 June 12 – 13, 2013 14_06/YKB/O/069 October 8, 2013
8 14-06/08 CRO Mentoring for Bid Submission and BidOpening, Package No. 02 and 03 July 18, 2013 14_06/YKB/O/069 October 8, 2013
9 14-06/09 Socialization for TPM Selection, Package No.01 February 14, 2014 14_06/CTA/O/220 October 1, 2014
10 14-06/10 Socialization for TPM Selection, Package No.02 and 03 February 18, 2014 14_06/CTA/O/220 October 1, 2014
11 14-06/11 Socialization for TPM Selection, Package No.04 March 3, 2014 14_06/CTA/O/220 October 1, 2014
12 14-06/12 TPM Selection, Package No. 01 March 5, 2014 14_06/CTA/O/220 October 1, 201413 14-06/13 TPM Selection, Package No. 02 and 03 March 7, 2014 14_06/CTA/O/220 October 1, 201414 14-06/14 TPM Selection, Package No. 04 March 10, 2014 14_06/CTA/O/220 October 1, 201415 14-06/15 TPM Training, Package No. 01 June 5 -6, 2014 14_06/CTA/O/266 December 17, 2014
Page 2 of 3
No. Number ofReport Activity Date of Activity CTC Transmittal Letter
No.Date of Submission
Report16 14-06/16 TPM Training, Package No. 02 and 03 June 17 – 18, 2014 14_06/CTA/O/266 December 17, 201417 14-06/17 TPM Training, Package No. 04 July 7 – 8, 2014 14_06/CTA/O/266 December 17, 201418 14-06/18 CRO Selection and Training, Package No. 17 July 17, 2014 14_06/CTA/O/231 November 3, 2014
19 14-06/19 CRO Selection and Training, Package No. 05 August 20, 2014 14_06/CTA/O/231 November 3, 2014
20 14-06/20 CRO Selection and Training, Package No. 11and 13 September 1, 2014 14_06/CTA/O/231 November 3, 2014
21 14-06/21 CRO Selection and Training, Package No. 06and 19 November 27, 2014 14_06/CTA/O/266 December 17, 2014
22 14-06/21.A TPM Selection for Package No. 17 December 4, 2015 14_06/CTA/O/415 November 11, 201523 14-06/22 CRO Selection and Training, Package No. 15 December 16, 2014 14_06/CTA/O/285 January 21, 201524 14-06/23 TPM Selection for Package No. 11 and 13 December 22, 2014 14_06/CTA/O/314 April 7, 201525 14-06/24 TPM Socialization for Package No. 05 and 15 January 28, 2015 14_06/CTA/O/314 April 7, 201526 14-06/25 TPM Training, Package No. 11 and 13 March 11 – 13, 2015 14_06/CTA/O/325 May 18, 2015
27 14-06/14A Complaint Handling Unit Report per May2014 Per May 2014 14_06/CTA/O/327 May 18, 2015
28 14-06/26 Complaint Handling Unit Report per May2015 Per May 2015 14_06/CTA/O/327 May 18, 2015
29 14-06/26.A TPM Selection for Package No. 05 and 15 April 9, 2015 14_06/CTA/O/415 November 11, 201530 14-06/27 TPM Selection for Package No. 06 and 19 May 5, 2015 14_06/CTA/O/343 June 22, 2015
31 14-06/28 CRO Selection and Training No. 07, 08, 10,and 12 June 12, 2015 14_06/CTA/O/343 June 22, 2015
32 14-06/29 TPM Training, Package No. 06 and 19 June 4 – 5, 2015 14_06/CTA/O/351 July 8, 201533 14-06/30 TPM Monitoring Report Package No. 01 August 19 – 20, 2015 14_04/CTA/O/367 August 26, 201534 14-06/31 TPM Training, Package No. 05 and 15 October 9, 2015 14_06/CTA/O/408 October 27, 201535 14-06/32 TPM Training, Package No. 17 October 22, 2015 14_06/CTA/O/411 October 29, 201536 14-06/33 CRO Selection and Training Package No. 16 November 4, 2015 14_06/CTA/450 January 21, 2016
37 14-06/34 CRO Selection and Training Package No. 14,20,21 November 17, 2015 14_06/CTA/O/429 December 7, 2015
38 14-06/35 Selection of Third Party Monitoring (TPM)Package No. 07 and 12 December 22, 2015 14_06/CTA/O/445 January 11, 2016
39 14-06/36 Selection of Third Party Monitoring (TPM)Package No. 16 December 29, 2015 14_06/CTA/O/445 January 11, 2016
Page 3 of 3
Notes:
Reports are made by Community Development Team, CTC WINRIP, submitted to PMU WINRIP.
No. Number ofReport Activity Date of Activity CTC Transmittal Letter
No.Date of Submission
Report
40 14-06/37 Selection of Third Party Monitoring (TPM)Package No. 08 and 10 January 14, 2016 14_06/CTA/O/456 January 29, 2016
41 14-06/38 Socialization of Third Party Monitoring(TPM) Package No. 14, 20, and 21 April 27, 2016 14_06/CTA/O/516 June 14, 2016
42 14-06/39 Selection of Third Party Monitoring (TPM)Package No. 20 and 21 May 26, 2016 14_06/CTA/O/516 June 14, 2016
43 14-06/40 Preparatory Training of Third PartyMonitoring (TPM) Packages No. 07 and 08 June 9, 2016 14_06/CTA/O/527 June 24, 2016
44 14-06/41 TPM Training Package 12 & 14 September 27, 2016 14-06/JJS/O/584 October 20, 201645 14-06/42 TPM Training Package 20 & 21 October 13, 2016 14-06/JJS/O/584 October 20, 2016
Page 1 of 4
CRO Reports
Community Development, CTC WINRIP
As of End of June, 2017Appendix S-4
No. Activity Date of Activity Composed By CTC Transmittal LetterNo.
Date of SubmissionReport
1 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 17 July 18, 2014 Y. Martono Hadi 14_06/CTA/O/242 November 18, 2014
2 Monitoring of Bid Opening, Package No. 17 August 15, 2014 Y. Martono Hadi 14_06/CTA/O/242 November 18, 2014
3 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 05 August 21, 2014 Medis Sejahtera 14_06/CTA/O/227 October 8, 2014
4 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 11 September 8, 2014 Hesti Aulia Sari, ST 14_06/CTA/O/227 October 8, 2014
5 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 13 September 8, 2014 Hot Maria, ST 14_06/CTA/O/227 October 8, 2014
6 Monitoring of Bid Opening, Package No.05 September 22, 2014 Medis Sejahtera, ST., MT 14_06/CTA/O/227 October 8, 20147 Monitoring of Bid Opening, Package No.11 October 3, 2014 Hesti Aulia Sari, ST 14_06/CTA/O/270 January 7, 20158 Monitoring of Bid Opening, Package No.13 October 3, 2014 Hot Maria, ST 14_06/CTA/O/270 January 7, 2015
9 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 19 December 5, 2014 Hesti Aulia Sari, ST 14_06/CTA/O/285 January 21, 2015
10 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 06 December 5, 2014 Hot Maria, ST 14_06/CTA/O/292 February 3, 2015
11 Monitoring of Bid Opening, Package No.06 December 29, 2014 Hot Maria, ST 14_06/CTA/O/312 March 25, 201512 Monitoring of Bid Opening, Package No.19 December 29, 2014 Hesti Aulia Sari, ST 14_06/CTA/O/312 March 25, 2015
13 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 15 January 26, 2015 Ir. M. Koster Silaen, MT 14_06/CTA/O/346 July 3, 2015
14 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 07 June 15 – 16, 2015 Ir. Riswandi, M.Si 14_06/CTA/O/351 July 8, 2015
15 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 12
June 15 – 16, 2015 Syaiful Amri, SST., MT 14_06/CTA/O/352 July 14, 2015
16Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 08 June 15 – 16, 2015 Ir. M. Nursyaifi Yulius, MT 14_06/CTA/O/359 August 6, 2015
Page 2 of 4
Notes:
Reports are composed by Community Representative Observer (CRO, submitted to PMU WINRIP through Community Development CTC WINRIP.
No. Activity Date of Activity Composed By CTC Transmittal LetterNo.
Date of SubmissionReport
17 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 10 June 15 – 16, 2015 Ir. Drs. Heldi, MT.,Ph.D 14_06/CTA/O/359 August 6, 2015
18 Monitoring of Bid Opening, Package No.15 February 23, 2015 Ir. M. Koster Silaen, MT 14_06/CTA/O/365 August 26, 2015
19 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 16 November 5, 2015 Besperi, ST., MT 14_06/CTA/O/419 November 25, 2015
20 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 20 November 18, 2015 Ir. Riswandi, M. Si 14_06/CTA/O/442 January 6, 2016
21 Monitoring of Bid Opening, Package No.07 August 13, 2015 Ir. Riswandi, M.Si 14_06/CTA/O/448 January 19, 201622 Monitoring of Bid Opening, Package No.12 August 13, 2015 Syaiful Amri, SST.,MT 14_06/CTA/O/448 January 19, 2016
23 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 14 November 18, 2015 Ir. Alzahri, MT 14_06/CTA/O/454 January 25, 2016
24 Monitoring of Pre-Bid Meeting and Site Visit, PackageNo. 21 November 18, 2015 Jafril Tanjung, DR., Eng 14_06/CTA/O/456 January 29, 2016
25 Monitoring of Bid Opening, Package No.08 August 13, 2015 Ir. M. Nursyaifi Yulius, MT 14_06/CTA/O/465 February 17, 201626 Monitoring of Bid Opening, Package No.14 January 5, 2016 Ir. Alzahri, MT 14_06/CTA/O/500 May 10, 201627 Monitoring of Bid Opening, Package No.20 January 5, 2016 Ir. Riswandi, M.Si 14_06/CTA/O/500 May 10, 201628 Monitoring of Bid Opening, Package No.21 January 5, 2016 Jafril Tanjung, DR., Eng 14_06/CTA/O/506 May 31, 2016
Page 3 of 4
TPM Reports
Community Development, CTC WINRIPAs of End of June, 2016
No. Activity Date of Activity Composed By CTC Transmittal LetterNo.
Date of SubmissionReport
1 Monitoring Report Phase I Package No. 04 August 2015 TPM Package No. 04(Universitas Bengkulu) 14_06/CTA/O/409 October 27, 2015
2 Monitoring Report Phase I Package No. 03 June 2015 TPM Package No. 03(Universitas Bung Hatta) 14_06/CTA/O/415 November 11, 2015
3 Monitoring Report Phase I Package No. 01 April – August 2015 TPM Package No. 01(Universitas Bandar Lampung) 14_06/CTA/O/420 November 26, 2015
4 Monitoring Report Phase I Package No. 02 September 2015 TPM Package No. 02(Politeknik Negeri Padang) 14_06/CTA/O/437 December 21, 2015
5 Monitoring Report Phase II Package No. 03 October 2015 TPM Package No. 03(Universitas Bung Hatta) 14_06/CTA/O/487 April 15, 2016
6 Monitoring Report Phase II Package No. 04 December 2015 TPM Package No. 04(Universitas Bengkulu) 14_06/CTA/O/518 June 16, 2016
7 Monitoring Report Phase I Package No. 11 October - November 2015 TPM Package No. 11(Universitas Bengkulu) 14_06/CTA/O/518 June 16, 2016
8 Monitoring Report Phase I Package No. 06 November 2015 TPM Package No. 06(Universitas Bengkulu) 14_06/CTA/O/518 June 16, 2016
9 Monitoring Report Phase III Package No. 04 March – April 2016 TPM Package No. 04(Universitas Bengkulu) 14_06/CTA/O/526 June 23, 2016
10 Monitoring Report Phase II Package No.01 August 2015 TPM Package No. 01(Universitas Bandar Lampung) 14_06/CTA/O/569 September 19, 2016
11 Monitoring Report Phase II Package No.11 March 2016 TPM Package No.11(Universitas Bengkulu) 14_06/CTA/O/569 September 19, 2016
12 Monitoring Report Phase III Package No.01 December 15 – Jan 2016 TPM Package No. 01(Universitas Bandar Lampung) 14_06/CTA/O/569 September 19, 2016
13 Monitoring Report Phase III Package No.03 February – March 2016 TPM Package No. 02(Universitas Bung Hatta) 14_06/CTA/O/569 September 19, 2016
14 Monitoring Report Phase II Package No.06 April – May 2016 TPM Package No. 06(Universitas Bengkulu) 14_06/CTA/O/661 March 13, 2017
15 Monitoring Report Phase III Package No.06 Dec - January 2017 TPM Package No. 06(Universitas Bengkulu) 14_06/CTA/O/661 March 13, 2017
Page 4 of 4
Notes:
Reports are composed by Third Party Monitoring (TPM) Team, submitted to PMU WINRIP through Community Development CTC WINRIP.
16 Monitoring Report Phase III Package No.11 September 2016 TPM Package No. 11(Universitas Bengkulu) 14_06/CTA/O/661 March 13, 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 1Project Implementation Timeline
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 Krui - Biha 25,00 21 mth
2 Padang Sawah - Sp.Empat 40,90 24 mth
3 Manggopoh - Padang Sawah 32,00 24 mth
4 Ipuh - Bantal 42,40 24 mth
5 SIMPANG RAMPA - PORIAHA 11,10 18 mth
11 BANTAL - MUKOMUKO 50,10 24 mth
13 SP RUKIS - TJ KEMUNING 56,30 24 mth
17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth
6 PS. PEDATI - KERKAP 25,00 15 mth
19 LAIS - BINTUNAN 11,60 10 mth
15 SIBOLGA - BATAS TAPSEL 36,00 27 mth
7 INDRAPURA - TAPAN 19,50 21 mth
8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth
10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth
12 KAMBANG - INDRAPURA 55,20 24 mth
14 PAINAN – KAMBANG 31,50 21 mth
16 SEBLAT – IPUH 34,50 21 mth
20 LUBUK ALUNG – SICINCIN 14,60 18 mth
21 LUBUK ALUNG – KURAITAJI 16,80 18 mth
9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARD
Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study
Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
CONSTRUCTION
CONSTRUCTION
Rev-DED RS
DED
COWPROC
COW CONSTRUCTION
OE & BD
DED Rev-DED RS OE & BD
OE & BD
DED OE & BD
COW
CONSTRUCTION
SBD & OE + BD
SBD & OE + BD
PQ PROC
PROC
CONSTRUCTION
DED RSA & REVISED DED
CONSTRUCTION
PQ
RS
Proc
COW
SBD
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
DED RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
OE
BD
DED
SBD & OE + BD
Rev-DED RS
DED Rev-DED RS
OE & BD
DED RSA & REVISED DED OE & BD
CONSTRUCTION
PROC COW
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS PQ
CONSTRUCTION
Review DED & RS PQ PROC COW
Review DED & RS PQ
COW CONSTRUCTION
PROC
Pack# PACKAGE NAME
2012 2013 2014 2015 2016 2017 2018
PROC COW
PROC COW
PROC COW
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
COW
PROC COW
PROC COW
PROC
CONSTRUCTION
CONSTRUCTION
PROC COW
December 31, 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Actual Implementation Timeline of WINRIP
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Core Team Consultant (CTC) 40 mth IMPLEMENTATION Time extension for sevices
Design & Supervision Cslt (DSC) 42 mth IMPLEMENTATION Time extension for sevices
TA for Dev.of Slope Stabilization, Design & M anagement IMPLEMENTATION
1 Krui - Biha 25,00 21 mth 8 Jan'14
2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan'14
3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan'14
4 Ipuh - Bantal 42,40 24 mth 10 Jan'14
5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun'15 20 Jul'17
11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb'15 26 May'17
13 SP RUKIS - TJ KEMUNING 56,30 24 mth 10 Jul'17
17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep'15 23 Agt'17
6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar'15 28 Jan'17
19 LAIS - BINTUNAN 11,60 10 mth 11 Mar'15 CONSTRUCTION 300+125+53 days 30 Jun '16
15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov'15
7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec'15 30 Agt'17
8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth PROC 23 Mar'16
10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth
12 KAMBANG - INDRAPURA 55,20 24 mth
14 PAINAN – KAMBANG 31,50 21 mth PROC 13 Aug'16
16 SEBLAT – IPUH 34,50 21 mth 08 Nov'16 30 Jul'18
20 LUBUK ALUNG – SICINCIN 14,60 18 mth 1 Sep'16
21 LUBUK ALUNG – KURAITAJI 16,80 18 mth 1 Sep'16
Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARD
1st Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study
2nd Revised target : 586,10 km Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
Review DED & RS PQ
Review DED & RS PQ
PQ
Review DED & RS
Review DED & RS
PROC
CONSTRUCTION 720 days
CONSTRUCTION 720 days22-Jul-15
PQ PROC
ICB
ICB
ICB
ICB
ICB
#########CONSTRUCTION 640 + 93 days
14-Apr-16
PROC
17-Mar-16
CONSTRUCTION 540 + 224 days
CONSTRUCTION 730 + 105 days
CONSTRUCTION 730 + 75 days
CONSTRUCTION 730 + 90 days 31-Mei-16
Pack# PACKAGE NAME
2012 2013 2014 2015 2016 2017 2018
PQ
RS
Proc
COW
SBD
DED
OE
BD
DED
NCB
NCB
DED
NCB
NCB
NCB
Review DED & RS
Review DED & RS SBD & OE + BD
RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
SBD & OE + BD
DED RSA & REVISED DED OE & BD
DEDICB RSA & REVISED DED OE & BD
Review DED & RS
SBD & OE + BD
6-Nov-12
19-Jun-13
PROC
PROC
DED
Rev-DED RS
ICB
ICB
NCB
NCB
DED
PROC
CONSTRUCTION 720 daysICB
ICB
ICB
ICB
PROC
CONSTRUCTION 810 - 37 days
DED
CONSTRUCTION 630 days
23-Mei-16 CONSTRUCTION 720 - 132 days
31-Des-17
31-Des-17
PROC
PROC
to be canceled
CONSTRUCTION 720 - 71 days
Rev-DED RS
Rev-DED RS
Rev-DED RS
31-Des-17
PROCUREMENT
31-Des-17
31-Des-17
CONSTRUCTION 450+90 days
CONSTRUCTION 540 - 53 days
CONSTRUCTION 540 - 53 days
CONSTRUCTION 630 - 114 days
CONSTRUCTION
31-Des-17
31-Des-17
31-Des-17
31-Des-17
Appendix 2
Appendix No.3 in USDDetail of Loan Expenditures RemainingCategory Allocation Disbursement Current Cumulative Loan
Quarter to date Allocation1 2 3 4 5 6 7 8 = 3 - 6 9 = 8 *0,7
1 Civil Works under part 1 of the project 220,400,000.00 98,794,523.12 4,404,391.98 98,794,523.12 150,053,037.90 121,605,476.88
01. Krui - Biha 11,757,337.74 0.00 7,391,833.64 4,365,504.10 3,055,852.8702. Padang Sawah - Sp.Empat/Inc Air Gadang Brgd 17,250,183.32 0.00 13,162,825.29 4,087,358.03 2,861,150.6203. Manggopoh - Padang Sawah 12,522,493.13 0.00 9,649,862.15 2,872,630.98 2,010,841.6904. Ipuh - Bantal 16,291,537.76 0.00 10,415,731.61 5,875,806.15 4,113,064.3117. Sp.Gng Kemala - Pugung Tampak 16,335,263.93 792,668.97 4,910,969.88 11,424,294.05 7,997,005.8405. Simpang Rampa - Poriaha 8,579,261.55 0.00 2,609,575.90 5,969,685.65 4,178,779.9611. Bantal - Mukomuko 18,765,198.80 765,238.42 11,721,961.80 7,043,237.00 4,930,265.9013. Sp Rukis - Tj Kemuning 23,454,051.00 1,160,260.33 6,204,924.87 17,249,126.13 12,074,388.2906. Ps. Pedati - Kerkap 6,641,396.33 0.00 5,216,123.16 1,425,273.17 997,691.2219. Lais - Bintunan 2,586,125.12 0.00 2,326,279.16 259,845.96 181,892.1815. Sibolga - Batas Tapsel 19,954,872.00 0.00 3,976,286.88 15,978,585.12 11,185,009.5808. Bts.Kota Pariaman - Manggopoh 25,627,995.00 1,236,807.37 8,210,106.3510. Simpang Empat - Sp.Air Balam07. Indrapura - Tapan 9,350,065.79 0.00 2,717,738.67 6,632,327.12 4,642,628.9812. Kambang - Indrapura 25,855,107.34 0.00 2,439,361.48 23,415,745.86 16,391,022.1014. Painan - Kambang 16,286,741.38 0.00 3,899,196.65 12,387,544.73 8,671,281.3116. Seblat - Ipuh, Inc Air Lalang/Guntung Brgd 16,909,960.00 0.00 996,825.62 15,913,134.38 11,139,194.0720. Lubuk Alung - Sicincin 8,578,485.27 0.00 1,478,969.35 7,099,515.92 4,969,661.1421. Lubuk Alung - Kuraitaji 9,519,374.20 449,416.89 1,465,950.66 8,053,423.54 5,637,396.4818. Mukomuko - Batas Sumbar **09. Rantau Tijang - Kota Agung **
2Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 2 of the project
17,000,000.00 6,790,105.83 70,776.05 5,859,934.18 11,140,065.82 10,209,894.17
3Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 3 of the project
0.00 0.00 0.00 0.00 0.00 0.00
4Goods, Non Consulting Services, ConsultingServices and Incremental Operating Cost underpart 4 of the project
0.00 0.00 0.00 0.00 0.00 0.00
5 Unallocated 12,600,000.00 0.00 0.00 0.00 0.00 12,600,000.00
250,000,000.00 105,584,628.95 4,475,168.03 104,654,457.30 161,193,103.71 144,415,371.05
Note : Ending Balance for Special Account Eof June 2017 USD 99,943.74 , include any corrections at Special Account for audit finding BPK FY 2014 amounting in USD 11,765.00
Western Indonesia National Roads Improvement ProjectDisbursement and Expenditures StatusFor the Quarter ending June 30, 2017
IBRD Loan No. 8043 - ID
LoanCat
Remaining Amount ofContract
Expenditures not yetreplenish
Form 1 - E
Appendix No.4Western Indonesia National Roads Improvement ProjectProject Report Format - 2Report for the quarter ended on 30-06-2017
Particulars ( Amount in US $ )
Bank Fund disbursed till date I 119,094,262.30Total Project Uses till date II 150,958,748.05World Bank Share @ 70% for CW III 112,304,156.47World Bank Share @ 100% for TA IV 6,206,522.78World Bank Share @ 100% for IOC V 240,932.58Ending Balance Special Account VI 99,943.74Funds Undisbursed to date VII 130,905,737.70
Forecast for Project payments for the next 6 months VIII 59,839,238.67World Bank Share @ 70% for CW IX 41,887,467.07World Bank Share @ 100% for TA X 2,274,235.85World Bank Share @ 100% for IOC XI 31,890.82Fund Undisbursed for next 6 month 86,712,143.95Net Funds required from the Bank 44,193,593.75
Forecast for DIPA from GOI for the 6 months XII 15,645,644.93
Mar-14
Appendix No.5 in million
2012Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
1. Krui – Biha - 22,000.00 - 24,905.00 16,750.58 65,479.22 65,455.65 16,012.00 15,972.28 8,503.00 6,257.13 104,435.65 149,193.782. Padang Sawah – Simpang Empat includingthe Air Gadang Bridge
- 14,517.46 - 53,002.13 46,918.57 119,959.10 97,372.66 38,549.03 37,187.67 0.00 0.00 173,300.49 247,572.13
3. Manggopoh – Padang Sawah - 15,243.50 - 33,324.86 30,188.81 90,403.40 73,227.64 30,206.32 28,422.50 1,715.66 0.00 128,758.61 183,940.874. Ipuh - Bantal - 21,449.19 - 29,725.59 25,002.15 64,270.93 64,270.92 50,733.42 50,733.42 8,250.40 0.00 136,431.53 194,902.185. Sp Rampa - Poriaha - 12,203.12 - 11,915.99 11,435.68 63,207.10 7,512.48 27,545.00 27,431.69 23,431.00 7,731.86 75,124.88 107,321.266. Ps. Pedati - Kerkap - 7,444.50 - 10,937.19 - 18,378.05 18,168.63 51,645.05 50,972.20 18,744.74 0.00 82,910.91 118,444.167. Indrapura - Tapan - 8,597.35 - 3,600.65 - 16,467.32 13,618.48 45,394.97 22,579.82 54,591.62 10,833.33 90,789.93 129,699.908.Bts Kota Pariaman - Manggopoh - 17,043.79 - 11,819.91 - 67,297.72 - 106,790.09 92,024.66 156,825.35 80,342.34 248,850.00 355,500.0010. Simpang Empat – Sp. Air Balam - 21,971.02 - 11,782.39 - 91,466.02 - 107,440.35 0.00 0.00 0.00 0.00 0.0011. Bantal - Mukomuko - 9,881.00 - 13,721.11 - 65,716.23 53,170.33 97,385.34 92,669.57 47,288.91 22,022.80 183,827.91 262,611.3012. Kambang - Indrapura - 11,525.46 - 9,124.16 - 83,424.41 - 59,370.06 32,112.84 25,105.00 0.00 251,055.28 358,650.4013. Sp Rukis – Tj Kemuning - 15,117.96 - 18,184.41 - 56,569.59 38,980.32 52,474.94 28,498.05 44,605.16 23,328.88 204,890.00 292,700.0014. Painan - Kambang - - - - - 1,999.08 - 51,566.64 51,373.96 97,977.59 5,693.16 150,029.20 214,327.4315. Sibolga – Bts TapSel - - 15,154.73 - 41,831.13 18,207.00 70,000.00 34,818.46 38,385.00 8,445.66 182,070.00 260,100.0016. Seblat - Ipuh including Air Lalang and AirGuntung bridge
- 6,000.00 - - - 20,457.96 - 13,538.65 13,316.59 32,850.95 3,640.50 147,962.15 211,374.50
17. Sp. Gng Kemala – Pugung Tampakincluding Way Taau bridge
- 4,351.98 - 13,815.26 - 14,762.82 8,604.09 70,000.00 38,246.00 50,886.72 32,845.76 139,685.86 199,551.23
19. Lais- Bintunan - - - 6,000.00 - 13,478.65 13,478.65 17,615.19 17,615.19 1,866.00 31,093.83 44,419.76Lubuk Alung - Sicincin - - - - - 916.56 - 19,652.36 19,420.73 60,252.09 16,907.72 79,672.81 113,818.30Lubuk Alung - Kuraitaji - - - - - 7,477.53 - 18,428.59 13,261.70 75,149.63 19,235.73 88,411.33 126,301.90Biha-Bengkunat - - - - - - - - - - 0.00 0.00Sorkam-Sibolga - - - - - - - - - - 0.00 0.00TOTAL: Betterment and Capacity Expansionof National Roads
0.00 187,346.32 0.00 267,013.39 130,295.80 903,562.82 472,066.84 944,348.00 666,657.32 746,428.83 237,284.87 2,499,300.37 3,570,429.10
Core Team Consultant 6,399.75 7,187.72 5,500.00 5,455.13 9,102.76 15,698.80 9,000.00 6,334.94 14,963.38 2,626.50 35,095.90 35,095.90Design and Supervision Consultant 9,600.00 8,834.40 2,500.00 2,410.18 15,746.09 10,605.31 13,000.00 7,956.30 13,000.00 9,180.00 59,877.82 59,877.82IOC 1,039.75 709.92 490.73 526.04 800.00 819.42 631.47 336.45 738.80 372.27TOTAL: Implementation Support 0.00 17,039.51 16,022.11 8,490.73 7,865.31 25,648.85 27,123.53 22,631.47 14,627.69 28,702.18 12,178.77 94,973.72 94,973.72
Slope Protection 240.00 - 1,500.00 - 1,500.00 - 2,000.00 2,000.00 9,487.50 9,487.50Mitigation and Road Safety Unit 0.00 0.00 0.00 0.00 0.00TOTAL: Road Sector InstitutionalDevelopment
0.00 240.00 0.00 1,500.00 0.00 1,500.00 0.00 2,000.00 2,000.00 0.00 9,487.50 9,487.50
TOTAL per year 0.00 221,665.33 32,044.23 285,494.86 146,026.42 930,711.67 499,190.37 968,979.47 681,285.01 777,131.01 249,463.64 2,603,761.59 3,674,890.32
Note : Rp. 13,900 per USDWB Portion in
Million USD192.87
Implementation Support
Road Sector Institutional Development
CONTRACT2015 2016 2017
DISBURSEMENT PLANTOTAL contract
amount or estimate
Betterment and Capacity Expansion of National Roads
20142013WB Portion
Appendix No. 6Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1. CIVIL WORKS
1 CIVIL WORKS ICB Krui - Biha PT. JAYA KONSTRUKSI INDONESIA IDR 149,193,782,000.00 27-Dec-13 3,102,911,853.00 146,090,870,147.0001-26/04-WINRIP-WP1/CE/A/8043/11-13 MANGGALA PRATAMA 2-Jan-14 9,443,644,770.00 136,647,225,377.00
Tanggal 14 November 2013 20-Jun-14 385,839,106.00 136,261,386,271.003-Jul-14 1,174,292,924.00 135,087,093,347.00
30-Sep-14 527,162,987.00 134,559,930,360.0029-Oct-14 1,604,409,090.00 132,955,521,270.0018-Nov-14 425,049,074.00 132,530,472,196.0016-Dec-14 1,293,627,617.00 131,236,844,579.004-Dec-14 1,062,799,456.00 130,174,045,123.0016-Dec-14 3,234,607,041.00 126,939,438,082.0026-Mar-15 760,025,552.00 126,179,412,530.007-Apr-15 2,313,121,244.00 123,866,291,286.00
30-Mar-15 2,500,939,071.00 121,365,352,215.007-Apr-15 7,611,553,695.00 113,753,798,520.005-Jun-15 1,658,385,311.00 112,095,413,209.0025-Jun-15 5,047,259,643.00 107,048,153,566.009-Jul-15 3,395,857,119.00 103,652,296,447.0015-Jul-15 10,335,217,319.00 93,317,079,128.0028-Jul-15 1,111,274,527.00 92,205,804,601.0024-Jul-15 3,382,139,867.00 88,823,664,734.0024-Aug-15 769,214,079.00 88,054,450,655.008-Sep-15 2,341,086,329.00 85,713,364,326.0015-Sep-15 2,723,498,444.00 82,989,865,882.0028-Sep-15 8,288,908,308.00 74,700,957,574.0013-Nov-15 2,034,310,771.00 72,666,646,803.0016-Nov-15 6,191,380,606.00 66,475,266,197.002-Dec-15 1,329,067,062.00 65,146,199,135.0015-Dec-15 4,044,986,712.00 61,101,212,423.0014-Dec-15 1,515,000,000.00 59,586,212,423.0022-Dec-15 15,900,000,000.00 43,686,212,423.0029-Dec-15 5,122,768,175.00 38,563,444,248.0029-Mar-16 4,301,903,142.00 34,261,541,106.0026-May-16 2,221,619,283.00 32,039,921,823.0022-Jun-16 6,761,449,993.00 25,278,471,830.0026-May-16 1,612,932,730.00 23,665,539,100.0022-Jun-16 4,908,925,700.00 18,756,613,400.000-Jan-00 2,055,915,260.00 16,700,698,140.00
17-May-17 6,257,133,400.00 10,443,564,740.00
138,750,217,260.00 10,443,564,740.002 CIVIL WORKS ICB Padang Sawah - Sp.Empat PT. JAYA KONSTRUKSI INDONESIA IDR 247,572,130,000.00 30-Dec-13 4,552,544,077.00 243,019,585,923.00
Including Air Gadang Bridge MANGGALA PRATAMA 2-Jan-14 13,855,568,930.00 229,164,016,993.0039-06/02-WINRIP-WP1/CE/A/8043-ID/12-13 23-Jun-14 577,715,230.00 228,586,301,763.00
Tanggal 06 December 2013 14-Jul-14 1,225,456,548.00 227,360,845,215.0010-Sep-14 662,017,142.00 226,698,828,073.0030-Sep-14 2,521,001,709.00 224,177,826,364.004-Nov-14 2,141,055,147.00 222,036,771,217.004-Dec-14 6,536,641,989.00 215,500,129,228.002-Dec-14 4,797,630,309.00 210,702,498,919.0016-Dec-14 14,601,483,549.00 196,101,015,370.0013-Mar-15 3,036,091,659.00 193,064,923,711.007-Apr-15 9,240,278,960.00 183,824,644,751.0017-Jun-15 3,634,751,210.00 180,189,893,541.0026-May-15 11,062,286,290.00 169,127,607,251.0018-Jun-15 3,423,796,910.00 165,703,810,341.0026-Jun-15 10,420,251,466.00 155,283,558,875.001-Jul-15 4,184,037,410.00 151,099,521,465.0024-Jul-15 12,734,026,900.00 138,365,494,565.00
Western Indonesia National Roads Improvement ProjectContract Expenditure Report Goods and Works)
for the quarter ended June 30, 2017IBRD Loan 8043 - ID
Remaining amount Of Contr. Note
590770D001/01-WINRIP/17
415066J002/01-WINRIP/17
425690J003/01-WINRIP/17
433621J004/01-WINRIP/17
436754J005/01-WINRIP/17150171302000620006/01-WINRIP/17150171302000657007/01-WINRIP/17150171302001652008/01-WINRIP/17150171302002396009/11-WINRIP/17150171302002624010/01-WINRIP/17150171302003134011/01-WINRIP/17150171302003619012/01-WINRIP/17150171302004876013/01-WINRIP/17150171302005381014/01-WINRIP/17150171302005945015/01-WINRIP/17150171302006280
015-A/01-WINRIP/17160171302002021016/01-WINRIP/17160171302002020017/01-WINRIP/17
0018/01-WINRIP/17
040668I002/02-WINRIP/06
079428I003/02-WINRIP/06
092390I004/02-WINRIP/06
611285K005/02-WINRIP/06
617797K006/02-WINRIP/06150101302000227007/02-WINRIP/06150101302000553008/02-WINRIP/06150101302000291009/02-WINRIP/06150101302001366010/02-WINRIP/06
Form 3 - C
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Remaining amount Of Contr. Note
4-Sep-15 2,500,030,310.00 135,865,464,255.0016-Sep-15 7,608,787,900.00 128,256,676,355.0015-Oct-15 4,148,810,610.00 124,107,865,745.0030-Oct-15 12,626,814,900.00 111,481,050,845.0012-Nov-15 2,687,415,450.00 108,793,635,395.0020-Nov-15 8,179,090,500.00 100,614,544,895.007-Dec-15 8,378,943,700.00 92,235,601,195.0015-Dec-15 25,501,133,000.00 66,734,468,195.007-Mar-16 681,051,160.00 66,053,417,035.0014-Mar-16 2,072,764,400.00 63,980,652,635.006-Apr-16 1,572,309,670.00 62,408,342,965.0021-Apr-16 4,785,290,300.00 57,623,052,665.006-Apr-16 1,942,482,710.00 55,680,569,955.0021-Apr-16 5,911,903,900.00 49,768,666,055.0012-May-16 1,195,703,760.00 48,572,962,295.0027-May-16 3,639,098,400.00 44,933,863,895.0016-Jun-16 1,362,934,160.00 43,570,929,735.0029-Jun-16 4,154,313,564.00 39,416,616,171.0022-Jun-16 2,607,201,996.00 36,809,414,175.0029-Jun-16 7,934,962,595.00 28,874,451,580.0029-Nov-16 2,855,067,280.00 26,019,384,300.005-Dec-16 8,689,335,200.00 17,330,049,100.00
230,242,080,900.00 17,330,049,100.003 CIVIL WORKS ICB Manggopoh - Padang Sawah PT. JAYA KONSTRUKSI INDONESIA IDR 183,940,872,000.00 30-Dec-13 3,304,846,149.00 180,636,025,851.00
40-06/03-WINRIP-WP1/CE/A/8043-ID/12-13 MANGGALA PRATAMA 2-Jan-14 10,058,227,410.00 170,577,798,441.00Tanggal 06 December 2013 12-Jun-14 874,188,600.00 169,703,609,841.00
30-Jun-14 1,854,339,454.00 167,849,270,387.0010-Sep-14 452,231,941.00 167,397,038,446.0016-Oct-14 2,142,280,848.00 165,254,757,598.004-Nov-14 1,056,538,775.00 164,198,218,823.003-Dec-14 3,242,758,578.00 160,955,460,245.002-Dec-14 2,598,814,340.00 158,356,645,905.0010-Dec-14 7,909,434,949.00 150,447,210,956.0024-Mar-15 2,035,856,558.00 148,411,354,398.007-Apr-15 6,196,085,177.00 142,215,269,221.005-May-15 3,747,867,347.00 138,467,401,874.0026-May-15 11,406,552,794.00 127,060,849,080.0018-Jun-15 2,327,836,290.00 124,733,012,790.0026-Jun-15 7,084,719,142.00 117,648,293,648.0031-Jul-15 2,547,451,480.00 115,100,842,168.0027-Jul-15 7,753,113,200.00 107,347,728,968.008-Sep-15 2,368,489,630.00 104,979,239,338.0016-Sep-15 7,208,446,700.00 97,770,792,638.0013-Oct-15 3,814,452,020.00 93,956,340,618.0016-Oct-15 11,609,201,800.00 82,347,138,818.0013-Nov-15 2,138,953,770.00 80,208,185,048.0020-Nov-15 6,509,859,300.00 73,698,325,748.0014-Dec-15 5,079,605,660.00 68,618,720,088.0015-Dec-15 15,459,669,400.00 53,159,050,688.0010-Mar-16 982,207,180.00 52,176,843,508.0014-Mar-16 2,989,326,200.00 49,187,517,308.005-Apr-16 1,329,094,560.00 47,858,422,748.0021-Apr-16 4,045,070,400.00 43,813,352,348.0027-Apr-16 1,697,026,940.00 42,116,325,408.009-May-16 5,164,864,600.00 36,951,460,808.0029-Nov-16 2,366,264,610.00 34,585,196,198.005-Dec-16 7,201,674,900.00 27,383,521,298.0014-Dec-16 1,060,606,502.00 26,322,914,796.0014-Dec-16 3,241,038,828.00 23,081,875,968.0020-Dec-16 1,899,314,378.00 21,182,561,590.0014-Dec-16 5,780,522,020.00 15,402,039,570.00
168,538,832,430.00 15,402,039,570.004 CIVIL WORKS ICB Ipuh - Bantal PT. WASKITA KARYA - DAYA INDONESIA IDR 194,902,179,000.00 16-Dec-13 4,299,545,250.00 190,602,633,750.00
01-26/04-WINRIP-WP1/CE/A/8043/11-13 MULIA TURANGGA JO 23-May-14 13,085,572,500.00 177,517,061,250.00Tanggal 14 November 2013 SARI, Jo 18-Dec-14 3,574,973,901.00 173,942,087,349.00
17-Dec-14 8,341,605,771.00 165,600,481,578.00
150101302001771011/02-WINRIP/06150101302002244012/02-WINRIP/06150101302002653013/02-WINRIP/06150101302003211014/02-WINRIP/06160101302000241015/02-WINRIP/06160101302000541016/02-WINRIP/06160101302000542017/02-WINRIP/06160101302000663018/02-WINRIP/06160101302001295019/02-WINRIP/06160101302001363020/02-WINRIP/06
160,101,302,003,373021/02-WINRIP/06
040667I003/03-WINRIP/06
079428I004/03-WINRIP/06
092449I005/03-WINRIP/06
611286K006/03-WINRIP/06
617798K007/03-WINRIP/06150101302000275008/03-WINRIP/06150101302000536009/03-WINRIP/06150101302000921010/03-WINRIP/06150101302001367011/03-WINRIP/06150101302001811012/03-WINRIP/06150101302002228013/03-WINRIP/06150101302002681014/03-WINRIP/06150101302003186015/03-WINRIP/06160101302000268016/03-WINRIP/06160101302000540017/03-WINRIP/06160101302000743018/03-WINRIP/06
160101302003372.00019/03-WINRIP/06
160101302003842.00020/03-WINRIP/06
160101302004034.00021/03-WINRIP/06
254931Y004/04-WINRIP/26141401303000328005/04-WINRIP/26
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Remaining amount Of Contr. Note
18-Mar-15 3,116,950,024.00 162,483,531,554.007-Apr-15 7,272,883,390.00 155,210,648,164.0022-Apr-15 4,856,427,624.00 150,354,220,540.004-May-15 11,331,664,457.00 139,022,556,083.0019-Jun-15 5,419,957,509.00 133,602,598,574.001-Jul-15 12,646,567,523.00 120,956,031,051.0030-Jul-15 2,507,276,647.00 118,448,754,404.007-Aug-15 5,850,312,175.00 112,598,442,229.0011-Nov-15 571,150,974.00 112,027,291,255.0020-Nov-15 9,939,288,848.00 102,088,002,407.0016-Dec-15 3,811,666,448.00 98,276,335,959.0018-Dec-15 17,230,209,100.00 81,046,126,859.003-Jun-16 7,744,867,686.00 73,301,259,173.009-May-16 23,571,336,436.00 49,729,922,737.007-Dec-16 6,683,310,047.00 43,046,612,690.0020-Dec-16 20,340,508,835.00 22,706,103,855.007-Dec-16 2,241,375,059.00 20,464,728,796.0020-Dec-16 6,821,576,265.00 13,643,152,531.00
181,259,026,469.00 13,643,152,531.005 CIVIL WORKS ICB Pugung Tampak-Simpang PT. JAYA KONSTRUKSI INDONESIA IDR 199,551,233,000.00 12-Dec-14 4,589,678,359.00 194,961,554,641.00
Gunung Kemala MANGGALA PRATAMA 16-Dec-14 6,846,000,000.00 188,115,554,641.00 07-17/17-WINRIP-AWP2/CE/8043-ID/11-14 9-Mar-15 7,122,586,310.00 180,992,968,331.00
Tanggal 17 November 2014 0-Jan-00 486,778,919.00 180,506,189,412.0018-Dec-15 1,481,501,057.00 179,024,688,355.0028-Dec-15 736,408,597.00 178,288,279,758.0029-Mar-16 2,241,243,558.00 176,047,036,200.0027-Apr-16 436,054,136.00 175,610,982,064.008-Apr-16 1,327,121,284.00 174,283,860,780.0014-Jun-16 2,343,162,994.00 171,940,697,786.0020-Jun-16 7,131,365,636.00 164,809,332,150.0028-Jun-16 1,898,632,009.00 162,910,700,141.0013-Jul-16 5,778,445,245.00 157,132,254,896.008-Aug-16 972,495,225.00 156,159,759,671.0019-Aug-16 2,959,768,075.00 153,199,991,596.0022-Sep-16 1,142,112,785.00 152,057,878,811.0028-Sep-16 3,475,995,434.00 148,581,883,377.0028-Oct-16 1,961,954,693.00 146,619,928,684.007-Nov-16 5,971,166,454.00 140,648,762,230.002-Dec-16 1,801,951,832.00 138,846,810,398.0014-Dec-16 5,484,201,227.00 133,362,609,171.008-Dec-16 1,273,769,543.00 132,088,839,628.0020-Dec-16 3,876,689,913.00 128,212,149,715.0015-Dec-16 1,733,878,870.00 126,478,270,845.0010-Feb-17 5,277,022,648.00 121,201,248,197.0016-Mar-17 1,729,539,150.00 119,471,709,047.0014-Mar-17 5,263,814,804.00 114,207,894,243.0028-Apr-17 2,120,835,556.00 112,087,058,687.002-May-17 6,454,716,910.00 105,632,341,777.008-Jun-17 1,722,914,763.00 103,909,427,014.005-Jun-17 5,243,653,626.00 98,665,773,388.0019-Jun-17 3,485,008,692.00 95,180,764,696.0016-Jun-17 10,606,548,192.00 84,574,216,504.00
114,977,016,496.00 84,574,216,504.006 CIVIL WORKS ICB Bantal - Muko muko PT. HUTAMA KARYA - DAYA INDONESIA IDR 262,611,303,000.00 3-Feb-15 5,264,693,491.00 257,346,609,509.00
07-26/11-WINRIP-WP2/CE/A/8043/12-14 MULIA TURANGGA Jo 17-Feb-15 16,022,980,190.00 241,323,629,319.00Tanggal 18 December 2014 30-Apr-15 3,485,711,256.00 237,837,918,063.00
19-May-15 8,133,326,264.00 229,704,591,799.003-Jul-15 1,189,179,908.00 228,515,411,891.0015-Jul-15 2,774,753,120.00 225,740,658,771.003-Sep-15 1,203,976,691.00 224,536,682,080.0016-Sep-15 2,809,278,947.00 221,727,403,133.0030-Oct-15 376,793,584.00 221,350,609,549.0012-Nov-15 3,869,659,266.00 217,480,950,283.002-Dec-15 3,152,046,193.00 214,328,904,090.0015-Dec-15 11,292,672,085.00 203,036,232,005.0016-Dec-15 2,716,519,950.00 200,319,712,055.00
151401303000013006/04-WINRIP/26151401303000069007/04-WINRIP/26151401303000111008/04-WINRIP/26151401303000151009/04-WINRIP/26151401303000452010/04-WINRIP/26151401303000591011/04-WINRIP/26161401303000201012/04-WINRIP/26161401303000466013/04-WINRIP/26161401303000467014/04-WINRIP/26
438732J001/17-WINRIP/17001A/17-WINRIP/17150171302006023.00002/17-WINRIP/17150171302006263003/17-WINRIP/17160171302001476004/17-WINRIP/17160171302002410005/17-WINRIP/17160171302002679006/17-WINRIP/17160171302003345007/17-WINRIP/17160171302004309008/17-WINRIP/17160171302005108009/17-WINRIP/17160171302006060010/17-WINRIP/17160171302006461011/17-WINRIP/17160171302006621012/17-WINRIP/17170171302000764013/17-WINRIP/17170171302001396014/17-WINRIP/17170171302002191015/17-WINRIP/17170171302000764016/17-WINRIP/17
151401303000002001/11-WINRIP/26151401303000073002/11-WINRIP/26151401303000130003/11-WINRIP/26151401303000226004/11-WINRIP/26151401303000421005/11-WINRIP/26151401303000561006/11-WINRIP/26151401303000592
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Remaining amount Of Contr. Note
18-Dec-15 8,267,669,415.00 192,052,042,640.003-Jun-16 8,345,519,808.00 183,706,522,832.0028-Apr-16 25,399,408,111.00 158,307,114,721.003-Jun-16 3,192,299,603.00 155,114,815,118.003-Jun-16 9,715,694,444.00 145,399,120,674.0024-Jun-16 1,898,870,946.00 143,500,249,728.0013-Jul-16 5,779,172,445.00 137,721,077,283.0012-Oct-16 4,038,309,643.00 133,682,767,640.0021-Nov-16 12,290,507,609.00 121,392,260,031.0016-Nov-16 8,130,799,683.00 113,261,460,348.0023-Nov-16 24,745,912,071.00 88,515,548,277.007-Dec-16 4,842,774,317.00 83,672,773,960.0013-Dec-16 14,738,878,354.00 68,933,895,606.009-Mar-17 3,350,629,214.00 65,583,266,392.0014-Mar-17 10,197,567,168.00 55,385,699,224.000-Jan-00 3,885,434,370.00 51,500,264,854.0013-Apr-17 11,825,235,037.00 39,675,029,817.00
222,936,273,183.00 39,675,029,817.007 CIVIL WORKS ICB Sp. Rukis - Tanjung Kemuning PT. WASKITA KARYA INDONESIA IDR 292,700,000,000.00 13-Mar-15 6,732,100,000.00 285,967,900,000.00
01-26/13-WINRIP-WP2/CE/A/8043/12-14 24-Mar-15 20,489,000,000.00 265,478,900,000.00Tanggal 18 December 2014 19-Nov-15 1,407,008,900.00 264,071,891,100.00
3-Dec-15 4,282,201,000.00 259,789,690,100.008-Dec-15 4,668,711,350.00 255,120,978,750.0018-Dec-15 14,209,121,500.00 240,911,857,250.0028-Dec-15 2,622,152,950.00 238,289,704,300.0013-Jan-16 7,980,465,500.00 230,309,238,800.0019-Oct-16 3,334,611,093.00 226,974,627,707.0018-Oct-16 10,148,816,370.00 216,825,811,337.0014-Dec-16 3,406,880,187.00 213,418,931,150.0016-Dec-16 10,368,765,785.00 203,050,165,365.0028-Dec-16 5,054,326,038.00 197,995,839,327.0030-Jan-17 15,382,731,420.00 182,613,107,907.0018-Jun-17 2,610,876,683.00 180,002,231,224.008-May-17 7,946,146,425.00 172,056,084,799.00
120,643,915,201.00 172,056,084,799.008 CIVIL WORKS NCB Lais - Bintuan PT INDONESIA IDR 44,419,760,000.00 20-Mar-15 1,162,286,094.00 43,257,473,906.00
05-26/19-WINRIP-WP2/CE/A/8043/02-15 RODATEKNINDO 13-Apr-15 3,537,392,460.00 39,720,081,446.00Tanggal 27 February 2015 PURAJAYA 20-Oct-15 1,389,046,533.00 38,331,034,913.00
12-Nov-15 4,227,532,927.00 34,103,501,986.0015-Dec-15 1,434,270,673.00 32,669,231,313.0015-Dec-15 4,365,171,613.00 28,304,059,700.0015-Dec-15 443,094,343.00 27,860,965,357.0019-Dec-15 1,348,548,000.00 26,512,417,357.003-Jun-16 3,076,823,460.00 23,435,593,897.009-May-16 9,364,245,316.00 14,071,348,581.0015-Jun-16 1,524,859,292.00 12,546,489,289.0024-Jun-16 4,640,876,104.00 7,905,613,185.007-Dec-16 675,337,370.00 7,230,275,815.001-Dec-16 2,055,374,604.00 5,174,901,211.007-Dec-16 510,827,240.00 4,664,073,971.001-Dec-16 1,554,691,600.00 3,109,382,371.00
41,310,377,629.00 3,109,382,371.009 CIVIL WORKS NCB Ps.Pedati - Kerkap PT. WASKITA KARYA INDONESIA IDR 118,444,156,000.00 9-Apr-15 2,984,852,715.00 115,459,303,285.00
04-26/06-WINRIP-WP2/CE/A/8043/02-15 22-Apr-15 9,084,334,350.00 106,374,968,935.00Tanggal 27 February 2015 18-Nov-15 1,596,911,311.00 104,778,057,624.00
3-Dec-15 4,860,164,860.00 99,917,892,764.0016-Dec-15 1,387,928,758.00 98,529,964,006.0018-Dec-15 4,224,131,002.00 94,305,833,004.003-Jun-16 1,135,953,659.00 93,169,879,345.009-May-16 3,457,250,264.00 89,712,629,081.0030-Jun-16 3,760,614,927.00 85,952,014,154.0013-Jul-16 11,445,349,777.00 74,506,664,377.0019-Aug-16 2,168,738,201.00 72,337,926,176.007-Sep-16 6,600,507,567.00 65,737,418,609.0014-Sep-16 2,221,614,316.00 63,515,804,293.00
007/11-WINRIP/26161401303000202008/11-WINRIP/26161401303000203009/11-WINRIP/26161401303000237010/11-WINRIP/26161401303000390011/11-WINRIP/26161401303000432012/11-WINRIP/26161401303000465013/11-WINRIP/26171401303000011014/11-WINRIP/26
0.00015/11-WINRIP/26
150161301001510001/13-WINRIP/26150161301013494002/13-WINRIP/26150161301015079003/13-WINRIP/2615016130105955
004/13-WINRIP/26160161301013068005/13-WINRIP/26160161301017725006/13-WINRIP/26160161301018036007/13-WINRIP/26170161301019396008/13-WINRIP/26
151401301000031001/19-WINRIP/26151401301000625002/19-WINRIP/26151401301000820003/19-WINRIP/26151401301000819004/19-WINRIP/26161401303000324005/19-WINRIP/26161401303000340006/19-WINRIP/26161401303000683007/19-WINRIP/26161401303000684008/19-WINRIP/26
151401301000070001/06-WINRIP/26151401301000681002/06-WINRIP/26151401301000820003/06-WINRIP/26161401303000325004/06-WINRIP/26161401303000400005/06-WINRIP/26161401301000489006/06-WINRIP/26161401301000549
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Remaining amount Of Contr. Note
20-Sep-16 6,761,434,874.00 56,754,369,419.0024-Nov-16 4,119,862,968.00 52,634,506,451.001-Dec-16 12,538,713,378.00 40,095,793,073.0013-Dec-16 3,341,223,118.00 36,754,569,955.0020-Dec-16 10,168,939,924.00 26,585,630,031.00
91,858,525,969.00 26,585,630,031.0010 CIVIL WORKS ICB Simpang Rampa - Poriaha PT. NUSA KONSTRUKSI INDONESIA IDR 107,321,260,310.00 30-Jul-15 2,468,388,987.00 104,852,871,323.00
01-09/05-WINRIP-WP2/CE/A/8043/05-15 ENJINIRING Tbk 5-Oct-15 7,512,488,222.00 97,340,383,101.00Tanggal 00 May 2015 28-Dec-15 4,595,650,107.00 92,744,732,994.00
1-Jul-16 2,342,128,075.00 90,402,604,919.0029-Sep-16 17,851,399,464.00 72,551,205,455.000-Jan-00 3,147,809,112.00 69,403,396,343.00
20-Dec-16 9,580,288,601.00 59,823,107,742.0016-Jun-17 2,540,469,158.00 57,282,638,584.0019-Jun-17 7,731,862,654.00 49,550,775,930.00
57,770,484,380.00 49,550,775,930.0011 CIVIL WORKS ICB Sibolga - Batas Tapsel PT. PEMBANGUNAN INDONESIA IDR 260,100,000,000.00 20-Nov-15 5,982,300,000.00 254,117,700,000.00
02-03/15-WINRIP-WP2/CE/A/8043/07-15 PERUMAHAN 16-Nov-15 18,207,000,000.00 235,910,700,000.00Tanggal 13 July 2015 13-Apr-16 720,897,373.00 235,189,802,627.00
24-Jun-16 1,775,322,914.00 233,414,479,713.0012-Oct-16 7,597,192,178.00 225,817,287,535.005-Dec-16 904,460,579.00 224,912,826,956.0012-Dec-16 2,752,706,110.00 222,160,120,846.0022-Dec-16 8,039,671,896.00 214,120,448,950.0012-Dec-16 24,468,566,640.00 189,651,882,310.0019-May-17 2,775,002,463.00 186,876,879,847.0022-May-17 8,445,659,670.00 178,431,220,177.00
81,668,779,823.00 178,431,220,177.0012 CIVIL WORKS NCB Indrapura - Tapan PT. ADHI KARYA INDONESIA IDR 129,699,900,000.00 15-Dec-15 4,474,646,550.00 125,225,253,450.00
01-06/07-WINRIP-AWP II/CE/A/8043/12-15 28-Dec-15 13,618,489,500.00 111,606,763,950.00Tanggal 03 Desember 2015 21-Jun-16 834,958,320.00 110,771,805,630.00
24-Jun-16 2,568,568,800.00 108,203,236,830.0025-Oct-16 2,031,522,840.00 106,171,713,990.0026-Oct-16 6,182,895,600.00 99,988,818,390.0014-Dec-16 4,543,603,540.00 95,445,214,850.0014-Dec-16 13,828,358,600.00 81,616,856,250.0013-Jun-17 10,833,327,680.00 70,783,528,570.00
58,916,371,430.00 70,783,528,570.0013 CIVIL WORKS ICB Bts.Kota Pariaman - Manggopoh PP - STATIKA CONSORTIUM INDONESIA IDR 355,500,000,000.00 17-Mar-16 24,885,000,000.00 330,615,000,000.00
06-06/08-WINRIP-WP2/CE/A/8043-ID/01-16 5-Apr-16 8,176,500,000.00 322,438,500,000.00Tanggal 28 January 2016 28-Jun-16 809,863,810.00 321,628,636,190.00
13-Jul-16 2,464,802,900.00 319,163,833,290.0024-Aug-16 1,841,477,290.00 317,322,356,000.007-Sep-16 5,604,496,100.00 311,717,859,900.0015-Sep-16 1,924,915,770.00 309,792,944,130.0027-Sep-16 5,858,439,300.00 303,934,504,830.0024-Oct-16 2,888,959,850.00 301,045,544,980.0031-Oct-16 8,792,486,500.00 292,253,058,480.0022-Nov-16 6,915,459,680.00 285,337,598,800.005-Dec-16 21,047,051,200.00 264,290,547,600.009-Dec-16 7,679,496,220.00 256,611,051,380.0014-Dec-16 23,372,379,800.00 233,238,671,580.009-Mar-17 5,402,003,560.00 227,836,668,020.0016-Mar-17 16,440,880,400.00 211,395,787,620.0012-Apr-17 7,796,130,140.00 203,599,657,480.0013-Apr-17 23,727,352,600.00 179,872,304,880.0010-May-17 4,161,307,660.00 175,710,997,220.0010-May-17 12,664,849,400.00 163,046,147,820.0016-Jun-17 9,038,757,350.00 154,007,390,470.0022-Jun-17 27,509,261,500.00 126,498,128,970.00
229,001,871,030.00 126,498,128,970.0014 CIVIL WORKS ICB Kambang - Indrapura INDONESIA IDR 358,650,400,000.00 16-Jun-16 8,248,959,200.00 350,401,440,800.00
02-06/12-WINRIP-WP2/CE/A/8043-ID/01-16 28-Apr-16 25,105,528,000.00 325,295,912,800.00
007/06-WINRIP/26161401303000669008/06-WINRIP/26161401303000696009/06-WINRIP/26
150041303004697001-A/05-WINRIP/03150041303011347160041303005002002/05-WINRIP/03
0.00003/05-WINRIP/03170041303004264004/05-WINRIP/03
150041302005417001/15-WINRIP/03160041302001277160041302002826002/15-WINRIP/03160041302006156003/15-WINRIP/03160041302006662004/15-WINRIP/03170041302002177005/15-WINRIP/03
150101302003482001/07-WINRIP/06160101302001327002/07-WINRIP/06160101302002849003/07-WINRIP/06160101302003843004/07-WINRIP/06005/07-WINRIP/06
001/08-WINRIP/06160101302000511160101302001419002/08-WINRIP/06160101302002125003/08-WINRIP/06160101302002338004/08-WINRIP/06160101302002844005/08-WINRIP/06160101302003297006/08-WINRIP/06160101302003764007/08-WINRIP/06170101302000387008/08-WINRIP/06170101302000800009/08-WINRIP/06170101302001172010/08-WINRIP/06170101302001174011/08-WINRIP/06
PT LANCARJAYA MANDIRIABADI - PT CAHAYA TUNGGAL
ABADI Jo
160101304005270001/12-WINRIP/06
Disbursement Contract Procurement Contract Supplier/ Nationality Contract Contract Amount Payment realization Code Cat. Category Description Method /ii Number /iii Contractor Currency Value Invoiced No. SP2D/WA Date of SP2D Amount(Rp) Amount (US$) (Rp.) (US$) Comp.
No Description to date1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Remaining amount Of Contr. Note
Tanggal 28 January 2016 28-Oct-16 833,097,260.00 324,462,815,540.0026-Oct-16 2,535,513,400.00 321,927,302,140.0014-Dec-16 1,469,306,240.00 320,457,995,900.0020-Dec-16 4,471,801,600.00 315,986,194,300.00
42,664,205,700.00 1,958,531,661,480.0015 CIVIL WORKS NCB Painan - Kambang KSO YASA - CONBLOC INDONESIA IDR 214,327,429,680.00 25-Nov-16 7,394,296,324.00 206,933,133,356.00
03-06/14-WINRIP-AWP-III/CE/A/8043-ID/06-16 13-Jul-16 22,504,380,116.00 184,428,753,240.0029-Nov-16 783,927,400.00 183,644,825,840.00
Tanggal 01 Juni 2016 23-Nov-16 2,385,866,000.00 181,258,959,840.0014-Dec-16 8,701,791,940.00 172,557,167,900.0014-Dec-16 26,483,714,600.00 146,073,453,300.0013-Jun-17 5,693,159,500.00 140,380,293,800.00
73,947,135,880.00 140,380,293,800.0016 CIVIL WORKS NCB Lubuk Alung - Sicincin PT NINDYA KARYA (Persero) INDONESIA IDR 113,818,300,000.00 28-Sep-16 3,926,731,350.00 109,891,568,650.00
14-06/20-WINRIP-AWP-III/CE/A/8043-ID/06-16 13-Jul-16 11,950,921,500.00 97,940,647,150.00Tanggal 01 Juni 2016 9-Dec-16 2,454,464,270.00 95,486,182,880.00
14-Dec-16 7,469,804,300.00 88,016,378,580.0019-Apr-17 2,392,052,900.00 85,624,325,680.0020-Apr-17 7,280,161,000.00 78,344,164,680.0014-Jun-17 3,163,340,650.00 75,180,824,030.0016-Jun-17 9,627,558,500.00 65,553,265,530.00
48,265,034,470.00 65,553,265,530.0017 CIVIL WORKS NCB Lubuk Alung - Kuraitaji PT MULTI STRUCTURE INDONESIA IDR 126,301,900,000.00 19-Sep-16 4,357,415,550.00 121,944,484,450.00
15-06/21-WINRIP-AWP-III/CE/A/8043-ID/06-16 13-Jul-16 13,261,699,500.00 108,682,784,950.00Tanggal 01 Juni 2016 17-Feb-17 799,298,990.00 107,883,485,960.00
17-Feb-17 2,432,649,100.00 105,450,836,860.0019-Mar-17 1,161,811,190.00 104,289,025,670.0016-Mar-17 3,535,947,100.00 100,753,078,570.0016-May-17 975,449,320.00 99,777,629,250.0022-May-17 2,968,758,800.00 96,808,870,450.0016-Jun-17 3,383,751,490.00 93,425,118,960.0019-Jun-17 10,298,374,100.00 83,126,744,860.00
43,175,155,140.00 83,126,744,860.0018 CIVIL WORKS NCB Seblat - Ipuh incl.Air Lalang PT. YASA PATRIA PERKASA INDONESIA IDR 211,374,500,000.00 13-Dec-16 4,375,452,150.00 206,999,047,850.00
& Air Guntung Bridge MULTI STRUCTURE 20-Dec-16 13,316,593,500.00 193,682,454,350.0005-26/16-WINRIP-WP3/CE/A/8043/10-16 0-Jan-00 1,196,163,760.00 192,486,290,590.00
Tanggal 28 October 2016 19-Apr-17 3,640,498,400.00 188,845,792,190.00
22,528,707,810.00 188,845,792,190.00
NOTES:
VAT for Loan portion is not collected/i: This Report provides procurement information for the project from inception to the latest reporting date./ii: Each method in Procurement Guidelines should be shown separately
ICB : International Competitive BiddingNCB : National Competitive BiddingNS : National ShopingDC : Direct Contracting
PT LANCARJAYA MANDIRIABADI - PT CAHAYA TUNGGAL
ABADI Jo 160101304013439002/12-WINRIP/06160101304017808003/12-WINRIP/06
160101304015571001/14-WINRIP/06160101304015860002/14-WINRIP/06160101304017854003/14-WINRIP/06004/14-WINRIP/06
160101303004531001/20-WINRIP/06160101303006545002/20-WINRIP/06170101303001520003/20-WINRIP/06170101303002922004/20-WINRIP/06
160101303004336001/21-WINRIP/06170101304000753002/21-WINRIP/06170101304001566003/21-WINRIP/06170101304004793004/21-WINRIP/06170101304006642005/21-WINRIP/06
T O T A L CIVIL WORKS 3,359,054,604,990.00 1,968,454,011,200.00 3,244,520,560,970.00
161401301000697001/16-WINRIP/26
0.00002/16-WINRIP/26
Appendix 8
Procurement Plan of Implementation SupportWestern Indonesia National Roads Improvement Project (WINRIP)Executing Agency: Directorate General of Highways , Ministry of Public Works and Housing.
Ref.No. Contract Description Project Cost (US$) Procurement
Method
Review byBank
(Prior/Post)Schedule
Preparationof Draft
REOI
EOIadvertised in
MPWWebsite
Dateline ofEOI
Submission
SubmissionRFP to WB WB NOL to RFP
Opening ofFinancialProposal
FinalEvaluation
Report
ContractSign
Service Startdate Consultant Remarks
Allocated Original Addendum Actual Submission WB NOL Submission WB NOL Submission Submission WB NOL Original Addendum
2 Implementation Support
Schedule 14-Nov-10 05-Dec-10 23-Jan-11 12-Feb-11 12-Mar-11 02-Apr-11 23-Apr-12 04-Jun-12 22-Jul-12 05-Aug-12 12-Aug-12 15-Sep-12 29-Sep-12 22-Oct-12 12-Nov-12
Actual 26-Nov-10 7-Jun-11 7-Jul-11 30-Jan-12 7-Mar-12 9-Dec-11 6-Mar-12 20-Mar-14 30-Apr-12 14-Jun-12 29-Jun-12 27-Aug-12 3-Sep-12 21-Sep-12 12-Oct-12 5-Nov-12 16-Nov-12
Schedule 11-Dec-11 08-Jan-12 27-Feb-12 26-Mar-12 07-May-12 28-May-12 08-Oct-12 22-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 26-Nov-12 01-Apr-13 18-Apr-13 02-May-13
Actual 26-Nov-10 7-Jun-11 7-Jul-11 4/2/2012 10-Aug-12 20-Jan-12 23-May-12 31-Aug-14 23-Oct-12 20-Dec-12 21-Feb-13 5-Mar-13 13-Mar-13 25-Mar-13 19-Apr-13 11-Jun-13 25-Jun-13
Schedule 15-Dec-15 22-Dec-15 19-Jan-16 29-Jan-16 12-Feb-16 05-Feb-16 19-Feb-16 26-Feb-16 08-Apr-16 06-May-16 20-May-16 03-Jun-16 17-Jun-16 15-Jul-16 29-Jul-16 12-Aug-16 26-Aug-16 12
Revised 24-Jun-16 15-Jul-15 04-Aug-16 01-Aug-16 08-Aug-16 18-Aug-16 26-Aug-16 29-Aug-16 28-Sep-16 21-Oct-16 04-Nov-16 21-Nov-16 25-Nov-16 05-Dec-16 16-Dec-16 13-Jan-17 23-Jan-17 11
2nd Revised 02-Nov-16 05-Dec-16 09-Jan-17 23-Jan-17 18-Apr-17 28-Apr-17 10-May-17 17-May-17 14-Jun-17 19-Jun-17 11
Actual 24-Jun-16 15-Jul-15 4-Aug-16 18-Aug-16 23-Sep-16 2-Sep-16 27-Oct-16 2-Nov-16 5-Dec-16 12-Jan-17 7-Apr-17 20-Apr-17 15-May-17 19-May-17 15-Jun-17
Updated June 30, 2017
PT. Egis InternationalIndonesia, PT.
Disiplan Consult, PT.Widya Graha Asana.
61.83
55
1,000,000USD 155,300.
+ IDR6,577,000,000
.
QCBS Prior
Period (Month)
40
42
Loanreallocation
Date ofReceipt ofProposals
Prior
Evaluation and Short List Technical EvaluationReport Negotiation & Draft Contract
Prior
Theissuance
RFP to theshortlisted
firms
QCBS
QCBS
PT. Perentjana Djaja,Yongma Eng. Co. Ltdand PT. Epadascon
Permata EngineeringConsultant
Renardet S.A., PT.Cipta Strada, PT. DayaCreasi Mitrayasa, PT.Seecons, PT. Yodya
Karya (Persero)
Technical Assistance for Development of SlopeStabilization, Design and Management, Western
Indonesia Roadsc
Contract(US$)
(excl. VAT)
USD1,743,780 +
IDR37,161,972,29
9
USD1,042,900 +
IDR55,037,399,40
6
aCore Team Consultant (Project Management,Technical Assistant, Enviromental & Social Aspectand Road safety Audit)
5,000,000
USD1,276,700 +
IDR21,415,400,00
0
bDesign and Supervision Consultant (Design AWP-2 & 3 and Construction Supervision of Civil WorksProject)
10,000,000
USD 820,600+
IDR51,818,705,00
0
T O T A L
C:\Users\tedy\AppData\Local\Temp\Appendix 8 Draft Proc Plan WINRIP Consultants June 2017_D3C20A
No.
Pac
kage
Nam
e of
Pack
age
Sele
ctio
n Da
te
Trai
ning
Dat
e
Loca
tion
Telp. Email
Date
of P
re-B
idM
eetin
g an
d Si
teVi
sit
Date
of B
idO
peni
ng
No
Obj
ectio
nLe
tter
from
Wor
ldBa
nk
Anno
unce
men
tof
Bid
Win
ner
Pre-
Bid
Mee
ting
Bid
Ope
ning
1 Ir. Lukman MuizziJl. Poltek Grya Mitra A-5 RT07/RW 02, Bukit Lama,Palembang
08127118508 [email protected] of MuhammadiyahPalembang University
2 Ir. Wahidin Perum Politeknik NegeriSriwijaya
08127853585 [email protected] of Politeknik NegeriSriwijaya
1 Ir. Masril Syukur, M.ScJl. Handayani I No. 11, Steba,Padang
081267170435 [email protected]
Head Admission ofProcurement ConstructionCommittee of AndalasUniversity
2 Darwizal Daoed, MTKomplek Pelangi Indah BlokC4/4, Kuranji, Padang
08126603921 [email protected]
Lecturer of AndalasUniversity
1Ir. Jafril Tanjung, MT.,DR.,Eng
Jl. Banuaran Gg. Mesjid RayaNo. 47, Padang
08126623930 [email protected]
Lecturer of AndalasUniversity
2 Prof. Dr. Ir. Zaidir,MS Komp. Cendana Perak KopiBlok A-9, Padang
08126622012 [email protected] of ProcurementServices Unit of AndalasUniversity
1 Sartika Nisumanti, ST.,MTJl. Anggrek Raya No. 629,Palembang
081377924368 [email protected] of Indo GlobalMandiri University
2 Ir. Zainuddin Muchtar,MTJl. Putri Kembang Dadar No.110, B. Sibuntang,Palembang
08179766579 [email protected]
Lecturer of Politeknik NegeriSriwijaya
1Ir. Yohanes Martono Hadi,MT
Jl. Bungur No. 3/4 Blok TC 1,Way Halim Permai, TanjungKarang, Bandar Lampung
0816414590 [email protected]
Lecturer of LampungUniversity
2 Ofik Taufik Purwadi, ST.,MTJl. Z.A. Pagar Alam No. 26,Bandar Lampung
081279647013 [email protected] of LampungUniversity
1Medis Sejahtera Surbakti,ST., MT
Jl. Perpustakaan No. 1,University of NorthSumatera.
081396565879 [email protected]
Lecturer of University ofNorth Sumatera
2 Josep Admika Ginting, STJl. Industri No. 75, TanjungMorawa.
0811638886 [email protected]
Trainer of EngineeringLearning and Training CenterMedan
Package
Sept 18,2013
Sept 18,2013
Sept 18,2013
Sept 18,2013
July18,
2014
Aug21,
2014NCB
Oct 14,2014
Feb. 02,2015 ˅
Des16,
2013
Sept22,
2014
Oct 16,2014
Aug 20,2014
BBPJN I Office, Jl.Sakti Lubis No. 1,
Medan6
NorthSumatera
05Sp. Rampa -Poriaha
Aug 20,2014
5 Lampung 17
Sp. GunungKemala -PugungTampak
July 17,2014
Aug15,
2014
June25,
2014
July 17,2014
Satker PJN II Office, Jl.Wolter MongonsidiNo. 220 B, Bandar
Lampung
03Manggopoh -Pd. Sawah
May 27,2013
May 27,2013
BBPJN II Office, Jl. JatiNo. 109 Padang
2West
Sumatera02
Pd. Sawah -Simp. Empat
May 27,2013
May 27,2013
May 23,2013
BBPJN III Office, Jl. H.M. Noerdin PandjiNo. 78 Palembang
4 Bengkulu 04 Ipuh - BantalMay 23,
2013
WestSumatera
3
Nov 26,2013
Nov 26,2013
Oct 28,2013
BBPJN II Office, Jl. JatiNo. 109 Padang
May20,
2013
July18,
2013
May 23,2013
May20,
2013
July18,2013
May17,2013
July18,2013
June10,
2013
June10,
2013
June10,
2013
June10,
2013
CRO's Address
CRO's Contact
CRO's Occupation
CRO Selection and Training
Appendix 9.A List of Names of Community Representative Observers (CROs)
May17,
2013
BBPJN III Office, Jl. H.M. Noerdin PandjiNo. 78 Palembang
July18,
20131 Lampung 01 Krui - Biha
Date
of I
nvita
tion
to B
id
No Province
May23,
2013
CRO's Involvement in BiddingProcess
Name of Selected CRO
Nov 12,2013
Reports Related toCRO's Activity
˅
˅
˅
˅
˅
˅
˅
˅
˅
˅
˅
No.
Pac
kage
Nam
e of
Pack
age
Sele
ctio
n Da
te
Trai
ning
Dat
e
Loca
tion
Telp. Email
Date
of P
re-B
idM
eetin
g an
d Si
teVi
sit
Date
of B
idO
peni
ng
No
Obj
ectio
nLe
tter
from
Wor
ldBa
nk
Anno
unce
men
tof
Bid
Win
ner
Pre-
Bid
Mee
ting
Bid
Ope
ning
Package
CRO's Address
CRO's Contact
CRO's Occupation
CRO Selection and Training
Date
of I
nvita
tion
to B
id
No Province
CRO's Involvement in BiddingProcess
Name of Selected CRO
Reports Related toCRO's Activity
1 Hesti Aulia Sari, ST Jl. Mahakam Raya No. 27 Rt.9 Rw. 3, Kota Bengkulu.
085266724618 [email protected]
Assisstant of Lecturer ofBengkulu University
2 Rendesti Nofy Yelizar, STJl. R.A. Kartini Rt. 7 No. 01,Bengkulu Utara.
081373447043 [email protected]
Assisstant of Lecturer ofBengkulu University
1 Hot Maria AngelinaJl. Beo No. 60 Rt. 05 Rw. 02,Perumnas Lingkar Barat,Bengkulu.
085788095319 [email protected]
Assisstant of Lecturer ofBengkulu University
2 Muhammad Fauzi, ST., MT
Jl. Unib Permai Blok 1 No. 50, Pematang Gubernur,Muara Bangkahulu,Bengkulu.
081367690429 [email protected]
Lecturer of BengkuluUniversity
1 Muhammad Fauzi, ST., MT
Jl. Unib Permai Blok 1 No. 50, Pematang Gubernur,Muara Bangkahulu,Bengkulu.
081367690429 [email protected]
Lecturer of BengkuluUniversity
2 Hot Maria Angelina, STJl. Beo No. 60 Rt. 05 Rw. 02,Perumnas Lingkar Barat,Bengkulu.
085788095319 [email protected]
Assisstant of Lecturer ofBengkulu University
1 Hesti Aulia Sari, ST Jl. Mahakam Raya No. 27 Rt.9 Rw. 3, Kota Bengkulu. 085266724618
Assisstant of Lecturer ofBengkulu University
2 Agung Febrianto, STDwi Tunggal RT 02/RW 003,Curup Utara - Bengkulu.
085366851999 [email protected]
Assisstant of Lecturer ofBengkulu University
1Ernie Shinta Y. Sitanggang,ST., MT
Jl. Eka Surya PerumahanTaman Monaco Blok E No.17, Medan Johor.
081264881193 [email protected]
Lecturer of Politeknik NegeriMedan
2 Ir. M. Koster Silaen, MTJl. Pintu Air IV No. 296/41Komplek Politeknik NegeriMedan.
081376506226 [email protected]
Lecturer of Politeknik NegeriMedan
1 Ir. Riswandi, M.SiJl. Lubuk Bayu No. 1 KurauPagang Nanggalo, Padang.
08126713602 [email protected]
Lecturer of Politeknik NegeriPadang
2 Apwiddhal, ST.,MTJl. Garuda No. 1 Air TawarTimur, Padang. 081374698872 [email protected]
Lecturer of Politeknik NegeriPadang
Jun. 12,2015 ˅
BBPJN I Office, Jl.Sakti Lubis No. 1,
Medan
Jan 9,2015
Feb23,
2015
Feb 12,2015 ˅
NCBFeb 12,
2015
Sept 8,2014
Sept 8,2014
May. 7,2015
Dec29,
2014
Nov 18,2014
Oct 3,2014
Dec29,
2014
12West
Sumatera
NCB
Jan 26,2015
11North
SUmatera15
Sibolga - BatasTapsel
Dec 16,2014
Dec 16,2014
Dec 5,2014
10 Bengkulu 19 Lais - BintunanNov 27,
2014Nov 27,
2014
Satker PJN IBengkulu, Jl. Ir.
Rustandi SugiantoKm. 12+225, Pulau
Baai, Bengkulu
Nov24,
2014
9 Bengkulu 06Pasar Pedati -Kerkap
Nov 27,2014
Nov 27,2014
Satker PJN IBengkulu, Jl. Ir.
Rustandi SugiantoKm. 12+225, Pulau
Baai, Bengkulu
Nov24,
2014
Dec 5,2014
8 Bengkulu 13Sp. Rukis -TanjungKemuning
Sept 1,2014
Sept 1,2014
Satker PJN IBengkulu, Jl. Ir.
Rustandi SugiantoKm. 12+225, Pulau
Baai, Bengkulu
Nov 13,2014
Nov 14,2014 ˅
Nov 28,2014 ˅
Aug22,
2014
Oct 3,2014
Aug22,
2014
Satker PJN IBengkulu, Jl. Ir.
Rustandi SugiantoKm. 12+225, Pulau
Baai, Bengkulu
Sept 1,2014
Sept 1,2014
7 Bengkulu 11Bantal -Mukomuko ˅
˅
˅
˅
˅
˅
Nov 13,2015 ˅ ˅Jun 12,
2015Jun 12,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
Jun 1,2015
Jun 15,2015
Aug13,
201507
Indrapura -Tapan
Oct 12,2015
No.
Pac
kage
Nam
e of
Pack
age
Sele
ctio
n Da
te
Trai
ning
Dat
e
Loca
tion
Telp. Email
Date
of P
re-B
idM
eetin
g an
d Si
teVi
sit
Date
of B
idO
peni
ng
No
Obj
ectio
nLe
tter
from
Wor
ldBa
nk
Anno
unce
men
tof
Bid
Win
ner
Pre-
Bid
Mee
ting
Bid
Ope
ning
Package
CRO's Address
CRO's Contact
CRO's Occupation
CRO Selection and Training
Date
of I
nvita
tion
to B
id
No Province
CRO's Involvement in BiddingProcess
Name of Selected CRO
Reports Related toCRO's Activity
1 M. Nursyaifi Yulius, MT(Mgt)
Jl. Gadih Rantih Ujung No.20B, Padang.
08126608128 [email protected] of Bung HattaUniversity
2 Ir. Alzahri, MT Komp. Polamas Blok W5,Padang.
082388122008 [email protected] of Bung HattaUniversity
1 Ir. Drs. Heldi, M.SiJl. Bandes Parak SigarangNo. I 3,Kuranji, Padang.
081363428468 [email protected]
Lecturer of Bung HattaUniversity
2 Ir. Afrizal Naumar, MT Jl. Ulak Karang, Padang. 081363418758Lecturer of Bung HattaUniversity
1 Syaiful Amri, SST.,MT Jl. Andalas Gg. Sarga IndahNo. 43, Padang.
081363435968 [email protected]
Lecturer of Politeknik NegeriPadang
2 B. Army, ST.,MT Taman Bamaran Indah BlokP No. 3. Padang
085274352715 [email protected] of Politeknik NegeriPadang
1 Besperi, ST., MTJl. WR. Supratman, KandangLimun - Bengkulu.
Lecturer of BengkuluUniversity
2 Anggi Nidya Sari, ST., MTJl. Halmahera RT 2 RW 3 No.5, Bengkulu.
082180708080 [email protected] of BengkuluUniversity
1M. Nursyaifi Yulius, MT(Mgt)
Jl. Gadih Rantih Ujung No.20B, Padang.
08126608128 [email protected] of Bung HattaUniversity
2 Ir. Alzahri, MTKomp. Polamas Blok W5,Padang. 082388122008 [email protected]
Lecturer of Bung HattaUniversity
1 Ir. Riswandi, M.Si Jl. Lubuk Bayu No. 1 KurauPagang Nanggalo, Padang.
08126713602 [email protected]
Lecturer of Politeknik NegeriPadang
2 Syaiful Amri, SST.,MTJl. Andalas Gg. Sarga IndahNo. 43, Padang.
081363435968 [email protected]
Lecturer of Politeknik NegeriPadang
1Ir. Jafril Tanjung, MT.,DR.,Eng
Jl. Banuaran Gg. Mesjid RayaNo. 47, Padang
08126623930 [email protected]
Lecturer of AndalasUniversity
2 T. Ophiyandri, PhD Jl. Belibis Blok C No. 17, AirTawar - Padang.
0811665723 [email protected]
Lecturer of AndalasUniversity
Apr 4.2016
May 3.2016 ˅
16
17
18
19
Bengkulu
WestSumatera
20Lubuk Alung -Sicincin
Nov. 17,2015
21Lubuk Alung -Kuraitaji
Nov. 17,2015
14Painan -Kambang
Nov. 17,2015
Sept.26,
2016˅
˅
Nov18,
2015
Jan 5,2016
Mar 23,2016
May 3.2016 ˅ ˅
Nov. 17,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
Nov 2,2015
Nov18,
2015
Jan 5,2016
Nov. 17,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
Nov 2,2015
Nov18,
2015
Jan 5,2016
Mar 23,2016
May 3.2016 ˅ ˅
Nov. 17,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
Nov 2,2015
˅16 Seblat - IpuhNov. 4,2015
Nov. 4,2015
Satker PJN IBengkulu, Jl. Ir.
Rustandi SugiantoKm. 12+225, Pulau
Baai, Bengkulu
Oct22,
2015
Nov 5,2015
Nov19,
2015
Augt 31,2016
13
14
15
WestSumatera
Jun 12,2015
08Bts. Pariaman -Manggopoh
Jun 12,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
May28,
2015
Jun 15,2015
Aug13,
2015
Dec 9,2015
Jan 5,2016 ˅ ˅
Und
er P
roce
ss
˅
Faile
d Bi
ddin
g, d
elet
edfr
om th
e pr
ogra
m
Jun 12,2015
Jun 12,2015
BBPJN II Office, Jl. JatiNo. 109 Padang
12Kambang -Indrapura
May28,
2015
Jun 15,2015
Aug13,
2015
Nov 26,2015
Dec 29,2015 ˅ ˅
Jun 12,2015
Jun 12,2015
10Sp. Empat - Sp.Air Balam
BBPJN II Office, Jl. JatiNo. 109 Padang
May28,
2015
Jun 15,2015
Aug13,
2015
Feb 22,2016
No ProvinceNo. of
packageName of Package Name of Appointed CRO Occupation of Appointed CRO
1. Ir. Lukman Muizzi Lecturer of Muhammadiyah Palembang University
2. Ir. Wahidin Lecturer of Politeknik Negeri Sriwijaya
1. Ir. Masril Syukur, M.Sc Head Admission of Procurement Construction Committee of Andalas University
2. Darwizal Daoed, MT.,DR.,Eng Lecturer of Andalas University
1. Ir. Jafril Tanjung,MT.,DR.Eng Lecturer of Andalas University
2. Prof. Dr. Zaidir, MS Head of Procurement Services Unit of Andalas University
1. Sartika Nisumanti, ST.,MT Lecturer of Indo Global Mandiri University
2. Ir. Zainuddin Muchtar, MT Lecturer of Politeknik Negeri Sriwijaya
1. Ir. Yohanes Martono Hadi, MT Lecturer of Lampung University
2. Ofik Taufik Purwadi, ST.,MT Lecturer of Lampung University
1. Medis Sejahtera Surbakti, ST., MT Lecturer of University of North Sumatera
2. Josep Admika Ginting, ST Trainer
1. Hesti Aulia Sari, ST Assisstant of Lecturer of Bengkulu University
2. Rendesti Nofy Yelizar, ST Assisstant of Lecturer of Bengkulu University
1. Hot Maria Angelina, ST Assisstant of Lecturer of Bengkulu University
2. Muhammad Fauzi, ST., MT Lecturer of Bengkulu University
1. Muhammad Fauzi, ST., MT Lecturer of Bengkulu University
2. Hot Maria Angelina, ST Assisstant of Lecturer of Bengkulu University
1. Hesti Aulia Sari, ST Assisstant of Lecturer of Bengkulu University
2. Agung Febrianto, ST Assisstant of Lecturer of Bengkulu University
1. Ernie Shinta Y. Sitanggang, ST., MT Lecturer of Politeknik Negeri Medan
2. Ir. M. Koster Silaen, MT Lecturer of Politeknik Negeri Medan11 North Sumatera 15
Sibolga - BatasTapsel
9 06Pasar Pedati -
Kerkap
10 19 Lais - Bintunan
Bengkulu
8 13Sp. Rukis - Tanjung
Kemuning
7 11 Bantal - Mukomuko
Bengkulu
5 Lampung 17Sp. Gunung Kemala -
Pugung Tampak
6 North Sumatera 05 Sp. Rampa - Poriaha
Appendix 9.B List of Appointed CRO and their Occupation
2 02Pd. Sawah - Simp.
Empat
1 Lampung 01 Krui - Biha
West Sumatera
4 Bengkulu 04 Ipuh - Bantal
3 03Manggopoh - Pd.
Sawah
No ProvinceNo. of
packageName of Package Name of Appointed CRO Occupation of Appointed CRO
1. Ir. Riswandi, M.Si Leturer of Politeknik Negeri Padang
2. Apwiddhal, ST.,MT Leturer of Politeknik Negeri Padang
1. M. Nursyaifi Yulius, MT (Mgt) Lecturer of Bung Hatta University
2. Ir. Alzahri, MT Lecturer of Bung Hatta University
1. Ir. Drs. Heldi, M.Si Lecturer of Bung Hatta University
2. Ir. Afrizal Naumar, MT Lecturer of Bung Hatta University
1. Syaiful Amri, SST.,MT Leturer of Politeknik Negeri Padang
2. B. Army, ST.,MT Leturer of Politeknik Negeri Padang
1. Besperi, ST., MT Lecturer of Bengkulu University
2. Anggi Nidya Sari, ST., MT Lecturer of Bengkulu University
1. M. Nursyaifi Yulius, MT (Mgt) Lecturer of Bung Hatta University
Ir. Alzahri, MT Lecturer of Bung Hatta University
2. Ir. Riswandi, M.Si Leturer of Politeknik Negeri Padang
1. Syaiful Amri, SST.,MT Leturer of Politeknik Negeri Padang
1. Ir. Jafril Tanjung, MT.,DR.Eng Lecturer of Andalas University of Padang
2. T. Ophiyandri, PhD Lecturer of Andalas University of Padang
18 20Lubuk Alung -
Sicincin
19 21Lubuk Alung -
Kuraitaji
West Sumatera
16 Bengkulu 16 Seblat - Ipuh
17 14 Painan - Kambang
12 07 Indrapura - Tapan
13 08Bts. Pariaman -
ManggopohWest Sumatera
14Sp. Empat - Sp. Air
Balam10
15 12Kambang -Indrapura
No Province No. ofPackage
Name of Package SelectionDate
TrainingDate
Location Remarks
5 Lampung 17SP. Gunung
Kemala - PugungTampak
July 17, 2014July 17,
2014Satker PJN II Office, Jl. Wolter Mongonsidi No. 220 B,
Bandar LampungAttended by 2 candidates from Lampung University, 1 candidate be the Primary CRO and another bethe Secondary CRO. CRO Training was held directly after the selection process.
6 NorthSumatera 05
Sp. Rampa -Poriaha Aug 20, 2014
Aug 20,2014 BBPJN I Office, Jl. Sakti Lubis No. 1, Medan
Attended by 2 candidates, one from University of North Sumatera and another from EngineeringLearning and Training Center (ELTC). The Primary CRO is the one from University of North Sumatera,and the Secondary CRO is the one from ELTC. CRO Training was held directly after the selection process.
7 11 Bantal -Mukomuko
Sept 1, 2014 Sept 1,2014
Attended by 4 candidates from Bengkulu University. For Package number 11, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after the selectionprocess.
8 13Sp. Rukis -Tanjung
KemuningSept 1, 2014 Sept 1,
2014
Attended by 4 candidates from Bengkulu University. For Package number 13, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after the selectionprocess.
9 06Pasar Pedati -
Kerkap
Attended by 4 candidates from Bengkulu University. For Package number 06, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after the selectionprocess.
10 19 Lais - BintunanAttended by 4 candidates from Bengkulu University. For Package number 19, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after the selectionprocess.
Nov 27,2014
Satker PJN I Bengkulu, Jl. Ir. Rustandi Sugianto Km.12+225, Pulau Baai, Bengkulu
Bengkulu
Bengkulu Nov 27, 2014
Satker PJN I Bengkulu, Jl. Ir. Rustandi Sugianto Km.12+225, Pulau Baai, Bengkulu
Appendix 9.C CRO Selection and Training Process
BBPJN III Office, Jl. H. M. Noerdin Pandji No. 78Palembang
BBPJN II Office, Jl. Jati No. 109 Padang
May 23, 2013
May 27, 2013
3West
Sumatera 03Manggopoh - Pd.
Sawah
Ipuh - BantalBBPJN III Office, Jl. H. M. Noerdin Pandji No. 78
Palembang
Attended by 6 candidates, 2 candidates from Politeknik Negeri Sriwijaya, 1 candidate fromMuhammadiyah Palembang University, 2 candidates from Indo Global Mandiri Palembang University,and 1 candidate from Palembang University. For Package number 01, a Primary CRO selected fromMuhammadiyah Palembang University and a Secondary CRO selected from Politeknik Negeri Sriwijaya.CRO Training was held directly after the selection process.
Attended by 4 candidates from Andalas University. For Package number 02, a Primary CRO and aSecondary CRO selected from Andalas University. CRO Training was held directly after the selectionprocess.
Attended by 4 candidates from Andalas University. For Package number 03, a Primary CRO and aSecondary CRO selected from Andalas University. CRO Training was held directly after the selectionprocess.
Attended by 6 candidates, 2 candidates from Politeknik Negeri Sriwijaya, 1 candidate fromMuhammadiyah Palembang University, 2 candidates from Indo Global Mandiri Palembang University,and 1 candidate from Palembang University. For Package number 04, a Primary CRO selected from IndoGlobal Mandiri University and a Secondary CRO selected from Politeknik Negeri Sriwijaya. CRO Trainingwas held directly after the selection process.
May 23, 2013
May 23,2013
May 27,2013
May 23,2013
Krui - Biha
Pd. Sawah - Simp.Empat
4 Bengkulu 04
1 Lampung 01
2West
Sumatera 02
No Province No. ofPackage
Name of Package SelectionDate
TrainingDate
Location Remarks
11North
Sumatera 15Sibolga - Batas
Tapsel Dec 16, 2014Dec 16,
2014 BBPJN I Office, Jl. Sakti Lubis No. 1, MedanAttended by 2 candidates from State Polytecnic of Medan, 1 candidate be the Primary CRO and anotherbe the Secondary CRO. CRO Training was held directly after the selection process.
12 07 Indrapura - Tapan Jun 12, 2015Jun 12,2015
Attended by 4 candidates from State Polytecnic of Padang and 4 candidates from Bung HattaUniversity. For Package 07, a Primary CRO and a Secondary CRO selected from State Polytecnic ofPadang. CRO Training was held directly after the selection process.
13 08Bts. Pariaman -
Manggopoh Jun 12, 2015Jun 12,2015
Attended by 4 candidates from State Polytecnic of Padang and 4 candidates from Bung HattaUniversity. For Package 08, a Primary CRO and a Secondary CRO selected from Bung Hatta University.CRO Training was held directly after the selection process.
14 10Sp. Empat - Sp.
Air Balam Jun 12, 2015Jun 12,2015
Attended by 4 candidates from State Polytecnic of Padang and 4 candidates from Bung HattaUniversity. For Package 10, a Primary CRO and a Secondary CRO selected from Bung Hatta University.CRO Training was held directly after the selection process.
15 12Kambang -Indrapura Jun 12, 2015
Jun 12,2015
Attended by 4 candidates from State Polytecnic of Padang and 4 candidates from Bung HattaUniversity. For Package 12, a Primary CRO and a Secondary CRO selected from State Polytecnic ofPadang. CRO Training was held directly after the selection process.
16 Bengkulu 16 Seblat - IpuhNov. 04,
2015Nov. 04,
2015Satker PJN I Bengkulu, Jl. Ir. Rustandi Sugianto Km.
12+225, Pulau Baai, Bengkulu
Attended by 2 candidates from Bengkulu University. For Package number 16, a Primary CRO and aSecondary CRO selected from Bengkulu University. CRO Training was held directly after the selectionprocess.
17 14 Painan -Kambang
Nov. 17,2015
Nov. 17,2015
Attended by 6 candidates: 2 from State Polytecnic of Padang, 2 from Bung Hatta University, and 2 fromAndalas University. For Package 14, a Primary CRO and a Secondary CRO selected from Bung HattaUniversity. CRO Training was held directly after the selection process.
18 20Lubuk Alung -
SicincinNov. 17,
2015Nov. 17,
2015
Attended by 6 candidates: 2 from State Polytecnic of Padang, 2 from Bung Hatta University, and 2 fromAndalas University. For Package 20, a Primary CRO and a Secondary CRO selected from State Polytecnicof Padang. CRO Training was held directly after the selection process.
19 21Lubuk Alung -
KuraitajiNov. 17,
2015Nov. 17,
2015
Attended by 6 candidates: 2 from State Polytecnic of Padang, 2 from Bung Hatta University, and 2 fromAndalas University. For Package 21, a Primary CRO and a Secondary CRO selected from Andalas StateUniversity of Padang. CRO Training was held directly after the selection process.
WestSumatera
BBPJN II Office, Jl. Jati No. 109 Padang
BBPJN II Office, Jl. Jati No. 109 PadangWestSumatera
Appendix 9.D
Date of Pre-Bid Meeting
Date of BidOpening
Announcement Dateof Bid Winner
1 Lampung 01 Krui - Biha May 17, 2013 June 10, 2013 July 18, 2013 Nov 12, 20131. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 13, 2013.2. Attending Bid Opening on July 18, 2013.
2 West Sumatera 02Pd. Sawah -Simp. Empat
May 20, 2013 June 10, 2013 July 18, 2013 Nov 26, 20131. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 11, 2013.2. Attending Bid Opening on July 18, 2013.
3 West Sumatera 03Manggopoh -
Pd. SawahMay 20, 2013 June 10, 2013 July 18, 2013 Nov 26, 2013
1. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 11, 2013.2. Attending Bid Opening on July 18, 2013.
4 Bengkulu 04 Ipuh - Bantal May 17, 2013 June 10, 2013 July 18, 2013 Oct 28, 20131. Attending Pre-Bid Meeting on June 10, 2013, and Site Visit on June 13, 2013.2. Attending Bid Opening on July 18, 2013.
5 Lampung 17SP. Gunung
Kemala -Pugung Tampak
June 25, 2014 July 18, 2014 Aug 15, 2014 Oct 16, 20141. Attending Pre-Bid Meeting on July 18, 2014, and Site Visit on July 19, 2014.2. Attending Bid Opening on August 15, 2014.
6 North Sumatera 05Sp. Rampa -
PoriahaDes 16, 2013 Aug 21, 2014 Sept 22, 2014 Feb. 02, 2015
1. Attending Pre-Bid Meeting on August 21, 2014, and Site Visit on August 22, 2014.2. Attending Bid Opening on Sepetmber 22, 2014.
7 Bengkulu 11Bantal -
MukomukoNov 14, 2014
1. Attending Pre-Bid Meeting on September 8, 2014, and Site Visit on September 9, 2014.2. Attending Bid Opening on October 3, 2014.
8 Bengkulu 13Sp. Rukis -Tanjung
KemuningNov 28, 2014
1. Attending Pre-Bid Meeting on September 8, 2014, and Site Visit on September 9, 2014.2. Attending Bid Opening on October 3, 2014.
9 Bengkulu 06Pasar Pedati -
Kerkap
10 Bengkulu 19 Lais - Bintunan
11 North Sumatera 15Sibolga - Batas
TapselDec 23, 2014 Jan 26, 2015 Feb 03, 2015 Jun. 12, 2015
1. Attending Pre-Bid Meeting and Site Visit on January 26, 2015.2. Attending Bid-Opening on February 23, 2015.
Dec 29, 2014Nov 24, 2014 Dec 5, 2014 Feb 12, 2015
No ProvinceNo. of
PackageName ofPackage
Date ofInvitation to
Bid
CRO's Involvement in the Bidding Process
Oct 3, 2014
1. Attending Pre-Bid Meeting and Site Visit on December 5, 2014.2. Attending Bid Opening on December 29, 2014.
Sept 8, 2014Aug 22, 2014
Reports of CRO Activity
Date of Pre-Bid Meeting
Date of BidOpening
Announcement Dateof Bid Winner
No ProvinceNo. of
PackageName ofPackage
Date ofInvitation to
Bid
CRO's Involvement in the Bidding ProcessReports of CRO Activity
12 07 Indrapura -Tapan
Jun 1, 2015 Jun 15, 2015 Aug 13, 2015 Nov. 13, 20151. Attending Pre-Bid Meeting and Site Visit on June 15, 2015.2. Attending Bid Opening on Augustus 13, 2015,
13 08Bts. Pariaman -
ManggopohMay 28, 2015 Jun 15, 2015 Aug 13, 2015 Jan. 5, 2016
1. Attending Pre-Bid Meeting and Site Visit on June 15, 2015.2. Attending Bid Opening on Augustus 13, 2015.
14 10 Sp. Empat - Sp.Air Balam
May 28, 2015 Jun 15, 2015 Aug 13, 2015 Under Process1. Attending Pre-Bid Meeting and Site Visit on June 15, 2015.2. Attending Bid Opening on Augustus 13, 2015.
15 12 Kambang -Indrapura
May 28, 2015 Jun 15, 2015 Aug 13, 2015 Dec. 29, 20151. Attending Pre-Bid Meeting and Site Visit on June 15, 2015.2. Attending Bid Opening on Augustus 13, 2015.
16 Bengkulu 16 Seblat - Ipuh Oct 22, 2015 Nov 5, 2015 Nov 19, 2015 Under Process1. Attending Pre-Bid Meeting and Site Visit on November 5, 2015.2. Attending Bid Opening on November 19, 2015.
17 14Painan -
KambangNov 2, 2015 Nov 18, 2015 Jan 5, 2016 May 3, 2016
1. Attending Pre-Bid Meeting and Site Visit on November 18, 2015.2. Attending Bid Opening on January 5, 2015.
18 20Lubuk Alung -
SicincinNov 2, 2015 Nov 18, 2015 Jan 5, 2016 May 3, 2016
1. Attending Pre-Bid Meeting and Site Visit on November 18, 2015.2. Attending Bid Opening on January 5, 2015.
19 21Lubuk Alung -
KuraitajiNov 2, 2015 Nov 18, 2015 Jan 5, 2016 May 3, 2016
1. Attending Pre-Bid Meeting and Site Visit on November 18, 2015.2. Attending Bid Opening on January 5, 2015.
West Sumatera
West Sumatera
APPENDIX 10
Anti Corruption Action Plan (ACAP)
Activity Progress of Community Representative Observers(CRO)
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 10 ACAP Activity ProgressActivities Progress of Community Representative Observers (CROs)
January 2013 – June 2017 and the Works Plan
No Subject of Activities Date of Finish/completed
1. Orientation and studied of WINRIP documents and Development of Works Plan January 2013
2 Prepared of Workshop of Procurement Document Evaluation. February 2013
3. Conducted Workshop of Procurement Document Evaluation for POKJA, Satker/PPK, BalaiBBPJN and PMU.
Febr. 28, 2013 –March 01, 2013
4. Provided of Term of Reference (TOR) of the CRO's Selection and Guidelines for CRO’sSelection
March 1, 2013
5. Provided the Materials (Slide Presentation/Power-point) of General Explanations aboutWINRIP and the CRO’s selection and
March 8, 2013
6. Provided Training Materials for CROs. March 8, 2013
7. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
March 11, 2013
8 Preparation of Socialization on CROs selection in BBPJN II Padang for package 02 PadangSawah – Simpang Empat and package 03 Manggopoh - Padang Sawah, and Socialization onCROs selection in BBPJN III Palembang for package 01 Krui – Biha and package 04 Ipuh –Bantal.
March 31, 2013
9. Socialization on CROs selection in BBPJN II Padang for package 02 Padang Sawah – SimpangEmpat and package 03 Manggopoh - Padang Sawah
April 9, 2013
10 Socialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.
April 11, 2013
11. Sent the Invitation letter from Head of BBPJN III to Rector of Universities /Head of Colleges inPalembang, about selection of the CROs for package 01. Krui – Biha (Prov. Lampung) andpackage 04. Ipuh – Bantal (Prov. Bengkulu).
May 17, 2013
12. Sent the Invitation letter from Head of BBPJN II to Rector of Universities /Head of Colleges inPadang, about selection of the CROs for package 02. Padang Sawah – Simpang Empat andpackage 03. Manggopoh - Padang Sawah (Prov. Sumatera Barat).
May 20, 2013
13. Selection of CROs for Packages Krui – Biha Province Lampung and Ipuh – Bantal ProvinceBengkulu, and training for selected CROs in BBPJN III Palembang
May 23, 2013
14. Selection of WPM/CROs for Packages Manggopoh – Padang Sawah and Padang Sawah –Simpang Empat, and training for selected CROs in BBPJN II Padang
May 27, 2013
15. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
May 28, 2013
16. Guiding the Balai Besar Pelaksanaan Jalan Nasional (Balai) II Padang to compose theApplication Letter for Approval of selected CROs for Package 03. Manggopoh – PadangSawah, package 02. Padang Sawah – Simpang Empat, and Balai III Palembang for Package 01.Krui – Biha Province Lampung and Package 04. Ipuh – Bantal Province Bengkulu.
May 29, 2013
17. Compiling summary of the results of Selection the Community Representative Observers(CROs)/ Wakil Pengamat dari Masyarakat (WPM) and the Training activities for selectedCROs for four Packages AWP-1
June 1 - 9, 2013
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
18. Assist PMU to prepare the Approval letter of selected CROs for four AWP-1 Packages, andprepare of the Decree on Establishment the CROs of AWP-1 WINRIP from Director ofPlanning DGH, as the Chairman of PMU.
June 1 - 9, 2013
19. Monitor and observation the Pre-Bid Meeting and Site Visit activities of Procurement Processthat held by the Procurement Committee, in BBPJN II and III, on 10 June 2013 by CROs inimplementing their tasks on the
June 10 - 16,2013
20. Evaluate of the CROs observation on Pre-Bid Meeting and Site Visit activities Jun.17 - 23, 2013
21. Examine the report of CROs on the monitoring and observation of Pre-Bid Meeting and SiteVisit at the packages of Annual Works Program - 1 (AWP-1) WINRIP.
Modify the template of monitoring the report of the CROs, to be more focused and moresystematically
June 24 - 30,2013
22. Monitor /Observe of Bids Submission and Bids Opening for four packages AWP-1 byCommunity Representative Observers (CROs) for Package 01, 02, 03, and 04
July 18, 2013
23. Monitoring and examined of the CRO’s Report on the monitoring and observation of BidSubmission and Bid Opening activities for four packages of Annual Works Program - 1 (AWP-1) WINRIP, which have been carried out on July 18, 2013
August, 2013
24 Preparation on the Socialization of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha and package Sibolga – BatasTapanuli Selatan
October 2013
25 Monitored /Observed of Procurement progress on Commencement of Bid Winners for fourpackages AWP-1 (Package 01, 02, 03, and 04) and informed to related CommunityRepresentative Observers (CROs).
November 2013
26 Carried out the dissemination of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha. in Balai (BBPJN) I Medanand in Project Management (Satker) Office.
November 19 –20, 2013
27 Carried out the CROs selection for package 17: Simpang Gunung Kemala – Pugung Tampak inLampung..
July 17, 2014
28 Carried out the CROs selection for package 05: Simpang Rampa – Poriaha in North Sumateraprovince.
August 20, 2014
29 Carried out the CROs selection for package 11: Bantal – Mukomuko, and package 13:Simpang Rukis – Tanjung Kemuning in Bengkulu province.
Sept. 1, 2014
30 Ms. Hesti Aulia Sari, ST, CRO for Package 11: Bantal - Mukomuko, meet the invitation of theProcurement Committee (Pokja of Procurement Unit/Unit Layanan Pengadaan BBPJN III,PIU/Satker PJN Region I Bengkulu Province).
Oct. 03, 2014
31 Ms. Hot Maria Angelina, ST, CRO for Package 13: Simpang Rukis - Tanjung Kemuning wasattended Bid-Opening meeting meet the invitation by the Procurement Committee (Pokja ofProcurement Unit/Unit Layanan Pengadaan BBPJN III, PIU/Satker PJN Region II BengkuluProvince).
Oct. 03, 2014
32 Carried out the CROs selection for package 06: pasar Pedati –Kerkap and package 19: Lais -Bintunan in Bengkulu province.
Nov. 27, 2014
33 The elected CROs (Ms. Hot Maria Angelina, ST and Ms. Hesti Aulia Sari, ST) attanded Pre-BidMeeting and site visit for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais –Bintunan), Bengkulu Province
Dec. 05, 2014
34 The Community Development team CTC WINRIP has carried out the selection of CROs forPackage 15: Sibolga – Batas Tapanuli Selatan. The Elected CRO is Ernie Shinta Y. Sitanggang,ST, MT, and Ir. M. Koster Silaen, MT as the substitute CRO (both from Politeknik NegeriMedan / State Polytechnic of Medan)
Dec. 16, 2014,
35 The elected CROs for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan)Bengkulu Province was attanded the Bid-Opening Meeting.
Dec. 29, 2014
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
36 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Pre-Bid Meeting.
Jan. 26, 2015
37 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Bid Opening Meeting
Feb. 23, 2015
38 The Community Development team CTC WINRIP has carried out the selection of CROs forfour packages WINRIP in West Sumatera province, as follow; The appointed CRO for Package 07: Indrapura – Tapan, is Ir. Riswandi, M.Si, and
Apwiddhal, ST, MT as the substitute CRO, both from State Polytechnic of Padang(Politeknik Negeri Padang).
The appointed CRO for Package 08: Batas Pariaman – Manggopoh, is M. Nursyaifi Yulius,MT (Mgt), and Ir. Alzahri, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
The appointed CRO for Package 10: Simpang Empat – Simpang Air Balam, is Ir. Drs. Heldi,M.Si, and Ir. Afrizal Naumar, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
The appointed CRO for Package 12: Kambang – Indrapura, is Syaiful Amri, SST, MT, and B.Army, ST, MT as the substitute CRO, both from State Polytechnic of Padang (PoliteknikNegeri Padang)
June 12, 2015
39 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were attended the Pre-BidMeeting and Site Visit as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion II of West Sumatera ProvinceThe appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were attended the Pre-Bid Meeting and Site Visit as invited by theProcurement Committee (Pokja) of PIU/Satker PJN Region I of West Sumatera Province.
June. 15-16, 2015
40 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were sent the ObservationReport on Pre-Bid Meeting and Site Visit.
July. 02, 2015
41 The appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were sent the Observation Report on Pre-Bid Meeting and Site Visit.
July. 10, 2015
42 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), and the CRO for Package 12:Kambang – Indrapura (Syaiful Amri, SST, MT) were attended the Bid Opening Meeting.
August 13, 2015
43 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), and the CRO for Package 10: Simpang Empat – Simpang Air Balam (Ir. Drs. Heldi, M.Si)were attended the Bid Opening Meeting.
August 13, 2015
44 Selection of CROs for packages 16 (Sebelat – Ipuh) in Bengkulu province, as follow; The appointed CRO for Package 16 is Mr. Besperi, ST, MT, and and Ms. Anggi Nidya Sari,
ST., MT as the substitute CRO. Both of them were from Bengkulu University.
Nov,.4-5, 2015
45 Selection of CROs for packages 14, 20, and 21 in West Sumatera province, as follow; The Elected CRO for Package 14 (Painan - Kambang) were Mr. M. Nursyaifi Yulius, MT
(Mgt), and Mr. Ir. Alzahri, MT, as the substitute CRO, both of them were from Bung HattaUniversity.
The Elected CRO for Package 20 (Lubuk Alung - Sicincin), were Mr. Ir. Riswandi, M.Si andMr. Syaiful Amri, SST., MT, as the substitute CRO, both of them were from StatePolitechnic of Padang (Politeknik Negeri Padang).
The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji) were Mr. Jafril Tanjung, DR. Engand Mr. Ophiyandri, Ph.D as the substitute CRO, both of them were from AndalasUniversity
Nov,.16-17, 2015
46 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of Bengkulu Province.
Nov. 05, 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
47 The substitute CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended thePre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region II of West Province.
Nov. 18, 2015
48 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
49 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
50 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Bid Opening Meeting, invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of Bengkulu Province.
Nov. 19, 2015
51 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Pre-Bid Meeting and Site Visit
Nov. 25, 2015
52 The CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended the Bid OpeningMeeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJN Region II ofWest Province.
Jan. 05, 2016
53 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Bid Opening Meeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion I of West Sumatera Province.
Jan. 05, 2016
54 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Bid Opening Meeting as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Jan. 05, 2016
55 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Pre-Bid Meeting and Site Visit.
Jan. 06, 2016
56 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), was sent the ObservationReport on Bid Opening and Bid Winner Announcement.
Jan. 19, 2016
57 The CRO for Package 12: Kambang – Indrapura (Syaiful Amri, SST, MT) was sent theObservation Report on Bid Opening and Bid Winner Announcement.
Jan. 19, 2016
58 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT) was sent the observationreport on Pre-Bid Meeting and Site Visit.
Jan. 25, 2016
59 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Pre-Bid Meeting and Site Visit.
Jan. 29, 2016
60 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), was sent the Observation Report on Bid Opening and Bid Winner Announcement.
Feb. 17, 2016
61 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT), was sent the ObservationReport on Bid Opening and Bid Winner Announcement
May 10, 2016
62 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Bid Opening and Bid Winner Announcement
May 10, 2016
63 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Bid Opening and Bid Winner Announcement
May 31, 2016
64 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Bid Opening Meeting and the Announcement of Bid-Winner forPackage 16 (Seblat – Ipuh) in Bengkulu Province
September 2016
I II III I II III IV V VI I II III Final
1 Dr. Ir. Hery RiyantoJl. Duku D2 No. 9, Kel.Beringin Raya, Kemiling-B. Lampung
08127218266 [email protected] of BandarLampung University
V V V V V - - - -
2 Ir. Sugito, MTJl. Sukardihamdani,Palapa 5A No. 29A,Bandar Lampung
08218143644 [email protected] of BandarLampung University
V V V V V - - - -
3 Ir. Juniardi, MTJl. U. Surapati Gg.Mataram No. 1, BandarLampung
085225168058 [email protected] Dep. of CivilEngineering of BandarLampung University
V V V V V - - - -
1 Syaiful Amri,SST., MTJl. Andalas Gg. SargaIndah No. 43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
V V V V V - - - -
2 Ir. Syaifullah Ali,MTKomp. Pelangi IndahB5/5 Korong Gadang,Kuranji
08126601952 [email protected] of PoliteknikNegeri Padang
V V V V V - - - -
3 Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1Kurao, Pagang Nanggalo,Padang
08126713602 [email protected] of PoliteknikNegeri Padang
V V V V V - - - -
1 Ir.M. Nursyaifi Yulius,MTJl. Gadih Rantih UjungNo. 20 B, Padang
08126608128 [email protected] of Bung HattaUniversity
V V V V V - - - -
2 Alzahri, ST.,MTKomp. Polamas Blok W5,Alai Parak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
V V V V V - - - -
3 Ir. Heldi, M.ScParak Jigarang No. 1/3RT 03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
V V V V V - - - -
1 Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No.50, Pematang Gubernur -Bengkulu
08137690429 [email protected] of BengkuluUniversity
V V V V V - - - -
2 Hardiansyah, ST.,MTRT01/RW 004 SumurDewa-Slebar, Bengkulu
081368008820 [email protected] of BengkuluUniversity
V V V V V - - - -
3 Agung Febrianto,STRT 02/RW 003, DwiTunggal - Curup Utara,Bengkulu
085366851999 [email protected] staff ofBengkulu University
V V V V V - - - -
1 Ir. Y. Martono Hadi, MTJl. Bungur No. 3 WayHalim, Bandar Lampung.
0816414590 [email protected] of LampungUniversity
V
2 Ofik Taufik Purwadi, ST., MTJl. Swadaya 7 No. 56Gunung Terang, BandarLampung.
081279647013 [email protected] of LampungUniversity
V
3 Tas'an Junaidi, ST., MTJl. Padat Karya RT 06/RW01 Rajabasa Raya, B.Lampung.
081369109125 [email protected] of LampungUniversity
V
1 Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No.50, Pematang Gubernur -Bengkulu
08137690429 [email protected] of BengkuluUniversity
V V V - - - - - -
2 Hesti Aulia Sari, STJl. P. Natadiraja No. 20Kel. Gedang, GadingCempaka - Bengkulu
085266724618 [email protected] staff ofBengkulu University
V V V - - - - - -
3 Hot Maria Angelina, STJl. Beo No. 60 PerumnasLingkar Barat, KotaBengkulu.
085788095319 [email protected] staff ofBengkulu University
V V V - - - - - -
1 Hardiansyah, ST., MTJl. Hibrida 15 No. 43,Sidomulyo, GadingCempaka - Bengkulu.
081368008820 [email protected] of BengkuluUniversity
V
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
4 Bengkulu 04 Ipuh - BantalMarch
10, 2014
5 Lampung 17Sp. Gunung
Kemala - PugungTampak
Dec 04,2014
July 7-8,2014
7 Bengkulu 13Sp. Rukis - Tj.
KemuningDec 22,
2014March 11-12, 2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
6 Bengkulu 11Bantal -
MukomukoDec 22,
2014
V - - -
V V V -
V -V V
Satker PJN I Office, Jl.Khatib Sulaiman No.
9, Padang
TPM's Occupation
TPM Involvement
3West
Sumatera03
Manggopoh - Pd.Sawah
March 7,2014
June 18-19, 2014
No ProvinceNo. Package
Sele
ctio
nDa
te
Trai
ning
Dat
e
Name of Selected TPMSite Visit Coordination Meeting
LocationTPM's Address
Telp. Email
Appendix 11.A List of Names of Third Party Monitoring (TPM)
Package Observed TPM Selection and Training TPM Contact
June 18-19, 2014
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang
1 Lampung 01 Krui - BihaMarch 5,
2014June 5-6,
2014
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
2West
Sumatera02
Pd. Sawah -Simp. Empat
March 7,2014
Reports Related toTPM's Activity
V V V -
On
Proc
ess
Oct. 22,2015
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
On
Proc
ess
March 11-12, 2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
VVV
I II III I II III IV V VI I II III Final
TPM's Occupation
TPM Involvement
No ProvinceNo. Package
Sele
ctio
nDa
te
Trai
ning
Dat
e
Name of Selected TPMSite Visit Coordination Meeting
LocationTPM's Address
Telp. Email
Package Observed TPM Selection and Training TPM ContactReports Related to
TPM's Activity
2 Agung Febrianto, STJl. Asrama I Gang SetiaBudi No. 5, Curup -Bengkulu.
085366851999 [email protected] staff ofBengkulu University
V
3 Nanda Pratama, STJl. Hibrida 2 RT 06 RT 07Kelurahan Sidomulyo,Bengkulu.
085266724617 [email protected]
Lecturer staff ofBengkulu University
V
1 Sahrul Harahap, STJl. Bakti Kopri Gg. Asri,Padangsidempuan.
081376919899 [email protected] of GrahaNusantara University
V
2Asroi Benny Noor Harahah,ST., MT
Jl. Bakti Abdi I No. 5,Padangsidempuan.
081260244024 [email protected] of GrahaNusantara University
V
3 M. Yusuf Parlagutan Lubis, STJl. Thamrin No. 1,Padangsidempuan.
08139661661 [email protected] of GrahaNusantara University
V
1 Ahmad Rafii, STJl. Imam Bonjol Gg.Surya, Pdg.sidempuan.
081370511188 [email protected] of GrahaNusantara University
V
2 Roy Efendi Subarja, STJl. Dwikora II,Padangsidempuan.
08126320644 [email protected] of GrahaNusantara University
V
3 Masitoh Hasibuan, STJl. Sisingamangaraja Gg.Magabe, Pdg. sidempuanSelatan.
082369328301 [email protected] of GrahaNusantara University
V
1 Dr. Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No.50, Pematang Gubernur -Bengkulu
08137690429 [email protected] of BengkuluUniversity
V V V - - - - - -
2 Hesti Aulia Sari, STJl. P. Natadiraja No. 20Kel. Gedang, GadingCempaka - Bengkulu
085266724618 [email protected] staff ofBengkulu University
V V V - - - - - -
3 Anggi Nidya Sari, ST., M.EngJl. Halmahera RT 02 RW03 No. 5, Bengkulu.
082180708080 [email protected] of BengkuluUniversity
V V V - - - - - -
1 Dr. Khairul Amri, ST., MTJl. Hibrida 15 Gg. Mandiri5 No. 25, Bengkulu.
081367719694 [email protected] of EngineeringFaculty, BengkuluUniversity
V - - - - - - - -
2 Nanda Pratama, STJl. Hibrida 2 RT 06 RT 07Kelurahan Sidomulyo,Bengkulu.
085266724617 [email protected]
Lecturer staff ofBengkulu University
V - - - - - - - -
3 Desti Eka Putri, STJl. WR. Supratman,Kandang Limun, KotaBengkulu.
081919493764 [email protected] staff ofBengkulu University
V - - - - - - - -
1 Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1Kurao, Pagang Nanggalo,Padang
08126713602 [email protected] of PoliteknikNegeri Padang
V
2 Syaiful Amri,SST., MTJl. Andalas Gg. SargaIndah No. 43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
V
3 Apwiddhal, ST,.MTJl. Gapura No. 1 AirTawar Timur, Padang
81374698872 [email protected] of PoliteknikNegeri Padang
V
1 Syaiful Amri,SST., MTJl. Andalas Gg. SargaIndah No. 43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
V
12West
Sumatera07
Indrapura -Tapan
Dec. 22,2015
Jun. 9,2016
Satker PJN II, Jl. S.Parman No. 129A,
Padang
On
Proc
ess
13West
Sumatera12
Kambang -Indrapura
Dec. 22,2015
Will besheduled
later
Satker PJN II, Jl. S.Parman No. 129A,
Padang
On
Proc
ess
-11 Bengkulu 19 Lais - BintunanMay 5,2015
June 4 -5,2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
- -
On
Proc
ess
10 Bengkulu 06Ps. Pedati -
KerkapMay 5,2015
June 4 -5,2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
V V V
Apr 9,2015
Oct. 9,2015
Graha NusantaraUniversity, Jl. Dr.
Sutomo,Padangsidempuan
8North
Sumatera05
9North
Sumatera15
Sibolga - Bts.Tapsel
Sp. Rampa -Poriaha
Apr 9,2015
Oct. 9,2015
Graha NusantaraUniversity, Jl. Dr.
Sutomo,Padangsidempuan
7 Bengkulu 13Sp. Rukis - Tj.
KemuningDec 22,
2014March 11-12, 2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu O
n Pr
oces
sO
n Pr
oces
s
I II III I II III IV V VI I II III Final
TPM's Occupation
TPM Involvement
No ProvinceNo. Package
Sele
ctio
nDa
te
Trai
ning
Dat
e
Name of Selected TPMSite Visit Coordination Meeting
LocationTPM's Address
Telp. Email
Package Observed TPM Selection and Training TPM ContactReports Related to
TPM's Activity
2 Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1Kurao, Pagang Nanggalo,Padang
08126713602 [email protected] of PoliteknikNegeri Padang
V
3 B. Army, ST,. MTTaman Bamaran IndahBlok P No. 3 Padang
085274352715 [email protected] of PoliteknikNegeri Padang
V
1 Dr. Muhammad Fauzi, ST.,MTJl. Unib Permai Blok I No.50, Pematang Gubernur -Bengkulu
08137690429 [email protected] of BengkuluUniversity
2 Deri Saputra, STPerumnas BentiringIndah, MuaraBangkahulu - Bengkulu
08992212213 [email protected]. Lecturer of BengkuluUniversity
3 M. Ridwan Sami, STJl. Batang Hari 6 No. 26,Bengkulu
082281767448 [email protected]. Lecturer of BengkuluUniversity
1 Ir.M. Nursyaifi Yulius,MTJl. Gadih Rantih UjungNo. 20 B, Padang
08126608128 [email protected] of Bung HattaUniversity
V
2 Alzahri, ST.,MTKomp. Polamas Blok W5,Alai Parak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
V
3 Yendri Nursami, S. TiJl. Tepi Banjir Kanal No. 9A, Sawahan Timur -Padang
085217374888 [email protected] of Bung HattaUniversity
V
1 Ir. Drs. Heldi, M.SiParak Jigarang No. 1/3RT 03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
- - -
2 Ir. Afrizal Naumar, MTJl. Raya Kurao No. 1Padang
081363418758 [email protected] of Bung HattaUniversity
- - -
3 Yul Cherlina Z., ST., MTJl. Anshar No. 29 A, RT02/RW 05, Dadok -Tunggul Hitam, Padang
081363424638 [email protected] of Bung HattaUniversity
- - -
1 Dr. Ir. Wardi, M.SiWisma Utama Blok D4No. 4, Lubuk Begalung -Kota Padang.
081374332825 [email protected] of Bung HattaUniversity
V
2 Ir. Drs. Heldi, M.Si., Ph.DParak Jigarang No. 1/3RT 03/05 Kuanji, Padang.
081363428468 [email protected] of Bung HattaUniversity
V
3 Asril Yazid, STKomp. Griya Lestari BlokD8, Batung Taba LubegPadang.
08126733441 [email protected] of Bung HattaUniversity
V
1 Dr. Ir. Bambang Istijono, MEJl. Tenggiri No. 171 C,Ulak Karang Selatan,Padang.
0811664421 [email protected] of AndalasUniversity
V
2 Benny Hidayat, ST., MT.,Ph.DKomplek Kampus LimauManis, Padang.
081249814406 [email protected] of AndalasUniversity
V
3Taufika Ophiyandri,ST.,M.Sc.,Ph.D
Jl. Belibis Blok C No. 17,Air Tawar - Padang.
0811665723 [email protected] of AndalasUniversity
V
1 Ir. M. Nursyaifi Yulius,M(Mgt)Satker PJN II, Jl. S.Parman No. 129A,
Padang
Jl. Gadih Rantih UjungNo. 20 B, Padang
08126608128 [email protected] of Bung HattaUniversity
V
2 Alzahri, ST.,MTBPJN III Padang, Jl.Jati No.109 Padang
Komp. Polamas Blok W5,Alai Parak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
V
18West
Sumatera21
Lubuk Alung -Kuraitaji
May. 26,2016
Will besheduled
later
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang
On
Proc
ess
17West
Sumatera20
Lubuk Alung -Sicincin
May. 26,2016
Will besheduled
later
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang
On
Proc
ess
13West
Sumatera12
Kambang -Indrapura
Dec. 22,2015
Will besheduled
later
Satker PJN II, Jl. S.Parman No. 129A,
Padang
On
Proc
ess
14 Bengkulu 16 Seblat - IpuhDec. 29,
2015
Will besheduled
later
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
16West
Sumatera10
Sp. Empat - Sp.Air Balam
Jan. 14,2016
Will besheduled
later
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang- - -
15West
Sumatera08
Bts. Pariaman -Manggopoh
Jan. 14,2016
Jun. 9,2016
Satker PJN I, Jl.Khatib Sulaiman No.
9, Padang
On
Proc
ess
-19West
Sumatera14
Painan -Kambang
Augt. 12,2016
Sept. 27,2016
On
Proc
ess
I II III I II III IV V VI I II III Final
TPM's Occupation
TPM Involvement
No ProvinceNo. Package
Sele
ctio
nDa
te
Trai
ning
Dat
e
Name of Selected TPMSite Visit Coordination Meeting
LocationTPM's Address
Telp. Email
Package Observed TPM Selection and Training TPM ContactReports Related to
TPM's Activity
3 Ir. Drs. Heldi, M.Sc, PhDParak Jigarang No. 1/3RT 03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
V
-19West
Sumatera14
Painan -Kambang
Augt. 12,2016
Sept. 27,2016
On
Proc
ess
No ProvinceNo.
PackagePackage Name of Selected TPM Occupation
1. Dr. Ir. Hery Riyanto Lecturer of Bandar Lampung University
2. Ir. Sugito, MT Lecturer of Bandar Lampung University
3. Ir. Juniardi, MT Head Department of Civil Engineering of Bandar Lampung University
1. Syaiful Amri,SST., MT Lecturer of Politeknik Negeri Padang
2. Ir. Syaifullah Ali,MT Lecturer of Politeknik Negeri Padang
3. Ir. Riswandi, M.SI Lecturer of Politeknik Negeri Padang
1. Ir.M. Nursyaifi Yulius,MT Lecturer of Bung Hatta University
2. Alzahri, ST.,MT Lecturer of Bung Hatta University
3. Ir. Heldi, M.Sc Lecturer of Bung Hatta University
1. Muhammad Fauzi,ST.,MT Lecturer of Bengkulu University
2. Hardiansyah, ST.,MT Lecturer of Bengkulu University
3. Agung Febrianto,ST Lecturer staff of Bengkulu University
1. Ir. Y. Martono Hadi, MT Lecturer of Lampung University
2. Ofik Taufik Purwadi, ST., MT Lecturer of Lampung University
3. Tas'an Junaidi, ST., MT Lecturer of Lampung University
1. Muhammad Fauzi,ST.,MT Lecturer of Bengkulu University
2. Hesti Aulia Sari, ST Lecturer staff of Bengkulu University
3. Hot Maria Angelina, ST Lecturer staff of Bengkulu University
1. Hardiansyah, ST., MT Lecturer of Bengkulu University
2. Agung Febrianto, ST Lecturer staff of Bengkulu University
3. Nanda Pratama, ST Lecturer staff of Bengkulu University
1. Sahrul Harahap, ST Lecturer of Graha Nusantara University
2. Asroi Benny Noor Harahah, ST., MT Lecturer of Graha Nusantara University
3. M. Yusuf Parlagutan Lubis, ST Lecturer of Graha Nusantara University
1. Ahmad Rafii, ST Lecturer of Graha Nusantara University2. Roy Efendi Subarja, ST Lecturer of Graha Nusantara University
8 North Sumatera 05 Sp. Rampa - Poriaha
9 North Sumatera 15 Sibolga - Bts. Tapsel
6 Bengkulu 11 Bantal - Mukomuko
7 Bengkulu 13Sp. Rukis - Tj.
Kemuning
1 Lampung 01 Krui - Biha
Manggopoh - Pd.Sawah
4 Bengkulu 04 Ipuh - Bantal
Appendix 11.B List of TPM's Occupation
5 Lampung 17Sp. Gunung Kemala -
Pugung Tampak
2 West Sumatera 02Pd. Sawah - Simp.
Empat
3 West Sumatera 03
No ProvinceNo.
PackagePackage Name of Selected TPM Occupation
3. Masitoh Hasibuan, ST Lecturer of Graha Nusantara University1. Dr. Muhammad Fauzi,ST.,MT Lecturer of Bengkulu University2. Hesti Aulia Sari, ST Lecturer staff of Bengkulu University3. Anggi Nidya Sari, ST., M.Eng Lecturer of Bengkulu University1. Dr. Khairul Amri, ST., MT Dean of Engineering Faculty, Bengkulu University2. Nanda Pratama, ST Lecturer staff of Bengkulu University3. Desti Eka Putri, ST Lecturer staff of Bengkulu University1. Ir. Riswandi, M.SI Lecturer of Politeknik Negeri Padang2. Syaiful Amri,SST., MT Lecturer of Politeknik Negeri Padang3. Apwiddhal, ST,.MT Lecturer of Politeknik Negeri Padang1. Syaiful Amri,SST., MT Lecturer of Politeknik Negeri Padang2. Ir. Riswandi, M.SI Lecturer of Politeknik Negeri Padang3. B. Army, ST,. MT Lecturer of Politeknik Negeri Padang1. Dr. Muhammad Fauzi, ST.,MT Lecturer of Bengkulu University2. Deri Saputra, ST Ass. Lecturer of Bengkulu University3. M. Ridwan Sami, ST Ass. Lecturer of Bengkulu University1. Ir.M. Nursyaifi Yulius,MT Lecturer of Bung Hatta University2. Alzahri, ST.,MT Lecturer of Bung Hatta University3. Yendri Nursami, S. Ti Lecturer of Bung Hatta University1. Ir. Drs. Heldi, M.Si Lecturer of Bung Hatta University2. Ir. Afrizal Naumar, MT Lecturer of Bung Hatta University3. Yul Cherlina Z., ST., MT Lecturer of Bung Hatta University1. Dr. Ir. Wardi, M.Si Lecturer of Bung Hatta University2. Ir. Drs. Heldi, M.Si.,Ph.D Lecturer of Bung Hatta University3. Asril Yazid, ST Lecturer of Bung Hatta University1. Dr. Ir. Bambang Istijono, ME Lecturer of Andalas University2. Benny Hidayat, ST., MT.,Ph.D Lecturer of Andalas University3. Taufika Ophiyandri, ST.,M.Sc.,Ph.D Lecturer of Andalas University1. Ir. M. Nursyaifi Yulius,M (Mgt) Lecturer of Bung Hatta University2. Alzahri, ST.,MT Lecturer of Bung Hatta University3. Ir. Drs. Heldi, M.Sc, PhD Lecturer of Bung Hatta University
17 West Sumatera 20Lubuk Alung -
Sicincin
18 West Sumatera 21Lubuk Alung -
Kuraitaji
15 West Sumatera 08Bts. Pariaman -
Manggopoh
16 West Sumatera 10Sp. Empat - Sp. Air
Balam
14 Bengkulu 16 Seblat - Ipuh
12 West Sumatera 07 Indrapura - Tapan
13 West Sumatera 12Kambang -Indrapura
10 Bengkulu 06 Ps. Pedati - Kerkap
11 Bengkulu 19 Lais - Bintunan
9 North Sumatera 15 Sibolga - Bts. Tapsel
19 West Sumatera 14 Painan - Kambang
Date Location Training Date Location
1 Lampung 01 Krui - BihaMarch 5,
2014
Satker PJN II Office, Jl. W. R.Mongonsidi No. 220 B, BandarLampung
June 5-6, 2014Satker PJN II Office, Jl. W. R. Mongonsidi No. 220B, Bandar Lampung
Elected TPM team was from University of BandarLampung.
2West
Sumatera02 Pd. Sawah - Simp. Empat Elected TPM team was from Politeknik Negeri Padang.
3West
Sumatera03 Manggopoh - Pd. Sawah
Elected TPM team was from University of Bung HattaPadang.
4 Bengkulu 04 Ipuh - BantalMarch 10,
2014
Satker PJN I Office, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai-Bengkulu
July 7-8, 2014Satker PJN I Office, Jl. Ir. Rustandi Sugianto Km12+225, Pulau Baai-Bengkulu
Elected TPM team was from Bengkulu University.
5 Lampung 17Sp. Gunung Kemala -
Pugung TampakDec 04, 2014
Satker PJN II Office, Jl. W. R.Mongonsidi No. 220 B, BandarLampung
Oct. 22, 2015Satker PJN II Office, Jl. W. R. Mongonsidi No. 220B, Bandar Lampung
Elected TPM team was from Lampung University
6 Bengkulu 11 Bantal - Mukomuko Elected TPM team was from Bengkulu University
7 Bengkulu 13 Sp. Rukis - Tj. Kemuning Elected TPM team was from Bengkulu University
8North
Sumatera05 Sp. Rampa - Poriaha Elected TPM team was from Graha Nusantara University
9North
Sumatera15 Sibolga - Bts. Tapsel Elected TPM team was from Graha Nusantara University
10 Bengkulu 06 Ps. Pedati - Kerkap Elected TPM team was from Bengkulu University
11 Bengkulu 19 Lais - Bintunan Elected TPM team was from Bengkulu University
12West
Sumatera07 Indrapura - Tapan Jun. 9, 2016 BBPJN II Office, Jl. Jati No. 109 Padang Elected TPM team was from Politeknik Negeri Padang.
13West
Sumatera12 Kambang - Indrapura Sept. 27, 2016 BBPJN III Office, Jl. Jati No. 109 Padang Elected TPM team was from Politeknik Negeri Padang.
14 Bengkulu 16 Seblat - Ipuh Dec. 29, 2015Satker PJN I Office, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai-Bengkulu
Will be sheduledlater
Will be decided later Elected TPM team was from Bengkulu University
15West
Sumatera08
Bts. Pariaman -Manggopoh
Jan. 14, 2016 Jun. 9, 2016 BBPJN II Office, Jl. Jati No. 109 Padang Elected TPM team was from Bung Hatta University
16West
Sumatera10 Sp. Empat - Sp. Air Balam Jan. 14, 2016 - - Elected TPM team was from Bung Hatta University
17West
Sumatera20 Lubuk Alung - Sicincin
May. 26,2016
Oct. 13, 2016 BPJN III Office, Jl. Jati No. 109 Padang Elected TPM team was from Bung Hatta UniversitySatker PJN I Office, Jl. Khatib SulaimanNo. 9 Padang
Satker P2JN Bangkulu Province, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai - Bengkulu
Dec 22, 2014
Dec. 22, 2015Satker PJN II, Jl. S. Parman No. 129A,Padang
Apr 9, 2015Graha Nusantara University, Jl. Dr.Sutomo, Padangsidempuan
Oct. 9, 2015PPK 12 Sibolga CS; PIA Hotel Pandan Beach,Tapanuli Tengah
May 5, 2015Satker PJN I Office, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai-Bengkulu
June 4 - 5, 2015Satker PJN I Office, Jl. Ir. Rustandi Sugianto Km12+225, Pulau Baai-Bengkulu
Satker PJN I Office, Jl. Khatib SulaimanNo. 9 Padang
TPM TrainingRemarks
Appendix 11.C List of Selection and Training of TPM
PackageNo ProvinceNo.
Package
TPM Selection
June 18-19, 2014 BBPJN II Office, Jl. Jati No. 109 PadangSatker PJN I Office, Jl. Khatib SulaimanNo. 9 Padang
March 7,2014
Satker PJN I Office, Jl. Ir. RustandiSugianto Km 12+225, Pulau Baai-Bengkulu
March 11 -12,2015
Date Location Training Date Location
TPM TrainingRemarksPackageNo Province
No.Package
TPM Selection
18West
Sumatera21 Lubuk Alung - Kuraitaji
May. 26,2016
Oct. 13, 2016 BPJN III Office, Jl. Jati No. 109 Padang Elected TPM team was from Andalas University
19West
Sumatera14 Painan - Kambang Agt. 12, 2016
Satker PJN II, Jl. S. Parman No. 129A,Padang
Sept. 27, 2016 BBPJN III Office, Jl. Jati No. 109 Padang Elected TPM team was from Bung Hatta University
Satker PJN I Office, Jl. Khatib SulaimanNo. 9 Padang
I II III I II III IV V VI VII VIII I II III Final
1. Dr. Ir. Hery Riyanto V V V V V
2. Ir. Sugito, MT V V V V V
3. Ir. Juniardi, MT V V V V V
1. Syaiful Amri,SST., MT V V V V V
2. Ir. Syaifullah Ali,MT V V V V V
3. Ir. Riswandi, M.SI V V V V V
1. Ir. M. Nursyaifi Yulius,MT V V V V V
2. Alzahri, ST.,MT V V V V V
3. Ir. Heldi, M.Sc V V V V V
1. Muhammad Fauzi,ST.,MT V V V V V
2. Hardiansyah, ST.,MT V V V V V
3. Agung Febrianto,ST V V V V V
1. Ir. Y. Martono Hadi, MT V
2. Ofik Taufik Purwadi, ST., MT V
3. Tas'an Junaidi, ST., MT V
1. Muhammad Fauzi,ST.,MT V V V
2. Hesti Aulia Sari, ST V V V
3. Hot Maria Angelina, ST V V V
1. Hardiansyah, ST., MT V
2. Agung Febrianto, ST V
3. Nanda Pratama, ST V
1. Sahrul Harahap, ST V
2. Asroi Benny Noor Harahah, ST., MT V
3. M. Yusuf Parlagutan Lubis, ST V
1. Ahmad Rafii, ST V
2. Roy Efendi Subarja, ST V
3. Masitoh Hasibuan, ST V
1. Dr. Muhammad Fauzi,ST.,MT V V V
2. Hesti Aulia Sari, ST V V V
3. Anggi Nidya Sari, ST., M.Eng V V V
1. Dr. Khairul Amri, ST., MT V
2. Nanda Pratama, ST V
3. Desti Eka Putri, ST V
1. Ir. Riswandi, M.Si V
2. Syaiful Amri,SST., MT V
On
Proc
ess
12West
Sumatera07
Indrapura -Tapan
V V
11 Bengkulu 19 Lais - Bintunan X X X
10 Bengkulu 06Ps. Pedati -
KerkapV
9North
Sumatera15
Sibolga - Bts.Tapsel
On
Proc
ess
8North
Sumatera05
Sp. Rampa -Poriaha
On
Proc
ess
11Bantal -
Mukomuko
7 Bengkulu 13Sp. Rukis - Tj.
Kemuning
V V
V V
V V V
X X X
4 Bengkulu 04 Ipuh - Bantal
3West
Sumatera03
Manggopoh -Pd. Sawah
V
Appendix 11.D Status of TPM Activities and Reporting
2West
Sumatera02
Pd. Sawah -Simp. Empat
Site Visit
1 Lampung 01 Krui - Biha
TPM Involvement Reports of TPM ActivityName of Selected TPMNo Province
V V V
No.Package
Package Coordination Meeting
5 Lampung 17
Sp. GunungKemala -PugungTampak U
nder
Pro
cess
V
On
Proc
ess
6 Bengkulu
I II III I II III IV V VI VII VIII I II III Final
Site Visit
1 Lampung 01 Krui - Biha
TPM Involvement Reports of TPM ActivityName of Selected TPMNo Province
V V V
No.Package
Package Coordination Meeting
3. Apwiddhal, ST,.MT V
1. Syaiful Amri,SST., MT V
2. Ir. Riswandi, M.Si V
3. B. Army, ST,. MT V
1. Dr. Muhammad Fauzi,ST.,MT
2. Deri Saputra, ST
3. M. Ridwan Sami, ST
14 Bengkulu 16 Seblat - Ipuh
On
Proc
ess
13West
Sumatera12
Kambang -Indrapura
On
Proc
ess
12West
Sumatera07
Indrapura -Tapan
I II III I II III IV V VI VII VIII I II III Final
Site Visit
1 Lampung 01 Krui - Biha
TPM Involvement Reports of TPM ActivityName of Selected TPMNo Province
V V V
No.Package
Package Coordination Meeting
1. Ir.M. Nursyaifi Yulius,MT V
2. Alzahri, ST.,MT V
3. Yendri Nursami, S. Ti V
1. Ir. Drs. Heldi, M.Si
2. Ir. Afrizal Naumar, MT
3. Yul Cherlina Z., ST., MT
1. Dr. Ir. Wardi, M.Si V
2. Ir. Drs. Heldi, M.Si.,Ph.D V
3. Asril Yazid, ST V
1. Dr. Ir. Bambang Istijono, ME V
2. Benny Hidayat, ST., MT.,Ph.D V
3. Taufika Ophiyandri, ST.,M.Sc.,Ph.D V
1. Ir. M. Nursyaifi Yulius, M(Mgt) V
2. Alzahri, ST.,MT V
3. Ir. Drs. Heldi, M.Sc, PhD V
17West
Sumatera20
Lubuk Alung -Sicincin
On
Proc
ess
18West
Sumatera21
Lubuk Alung -Kuraitaji
On
Proc
ess
15West
Sumatera08
Bts. Pariaman -Manggopoh
On
Proc
ess
16West
Sumatera10
Sp. Empat -Sp. Air Balam
19West
Sumatera14
Painan -Kambang
On
Proc
ess
1 Dr. Ir. Hery RiyantoJl. Duku D2 No. 9, Kel. BeringinRaya, Kemiling-B. Lampung
08127218266 [email protected] of BandarLampung University
2 Ir. Sugito, MTJl. Sukardihamdani, Palapa 5ANo. 29A, Bandar Lampung
08218143644 [email protected] of BandarLampung University
3 Ir. Juniardi, MTJl. U. Surapati Gg. MataramNo. 1, Bandar Lampung
085225168058 [email protected] Dep. of CivilEngineering of BandarLampung University
1 Syaiful Amri,SST., MTJl. Andalas Gg. Sarga Indah No.43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
2 Ir. Syaifullah Ali,MTKomp. Pelangi Indah B5/5Korong Gadang, Kuranji
08126601952 [email protected] of PoliteknikNegeri Padang
3 Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1 Kurao,Pagang Nanggalo, Padang
08126713602 [email protected] of PoliteknikNegeri Padang
1 Ir.M. Nursyaifi Yulius,MTJl. Gadih Rantih Ujung No. 20B, Padang
08126608128 [email protected] of Bung HattaUniversity
2 Alzahri, ST.,MTKomp. Polamas Blok W5, AlaiParak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
3 Ir. Heldi, M.ScParak Jigarang No. 1/3 RT03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
1 Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No. 50,Pematang Gubernur - Bengkulu
08137690429 [email protected] of BengkuluUniversity
2 Hardiansyah, ST.,MTRT01/RW 004 Sumur Dewa-Slebar, Bengkulu
081368008820 [email protected] of BengkuluUniversity
3 Agung Febrianto,STRT 02/RW 003, Dwi Tunggal -Curup Utara, Bengkulu
085366851999 [email protected] staff of BengkuluUniversity
1 Ir. Y. Martono Hadi, MTJl. Bungur No. 3 Way Halim,Bandar Lampung.
0816414590 [email protected] of LampungUniversity
2 Ofik Taufik Purwadi, ST., MTJl. Swadaya 7 No. 56 GunungTerang, Bandar Lampung.
081279647013 [email protected] of LampungUniversity
Appendix 11.E List of Data of Third Party Monitoring (TPM)
Oct. 22,2015
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
5 Lampung 17Sp. Gunung
Kemala - PugungTampak
Dec 04,2014
4 Bengkulu 04 Ipuh - BantalMarch 10,
2014July 7-8,
2014
No. Package SelectionDate
Training Date Location
June 18-19, 2014
Satker PJN I Office, Jl.Khatib Sulaiman No.
9, Padang
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang
3West
Sumatera03
Manggopoh - Pd.Sawah
March 7,2014
2West
Sumatera02
Pd. Sawah - Simp.Empat
March 7,2014
June 18-19, 2014
Telp. EmailNo Province
Package Observed
Name of Selected TPMTPM Selection and Training
TPM's AddressTPM Contact
TPM's Occupation
1 Lampung 01 Krui - BihaMarch 5,
2014June 5-6,
2014
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
No. Package SelectionDate
Training Date Location Telp. EmailNo Province
Package Observed
Name of Selected TPMTPM Selection and Training
TPM's AddressTPM Contact
TPM's Occupation
3 Tas'an Junaidi, ST., MTJl. Padat Karya RT 06/RW 01Rajabasa Raya, B. Lampung.
081369109125 [email protected] of LampungUniversity
1 Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No. 50,Pematang Gubernur - Bengkulu
08137690429 [email protected] of BengkuluUniversity
2 Hesti Aulia Sari, STJl. P. Natadiraja No. 20 Kel.Gedang, Gading Cempaka -Bengkulu
085266724618 [email protected] staff of BengkuluUniversity
3 Hot Maria Angelina, STJl. Beo No. 60 PerumnasLingkar Barat, Kota Bengkulu.
085788095319 [email protected] staff of BengkuluUniversity
1 Hardiansyah, ST., MTJl. Hibrida 15 No. 43,Sidomulyo, Gading Cempaka -Bengkulu.
081368008820 [email protected] of BengkuluUniversity
2 Agung Febrianto, STJl. Asrama I Gang Setia BudiNo. 5, Curup - Bengkulu.
085366851999 [email protected] staff of BengkuluUniversity
3 Nanda Pratama, STJl. Hibrida 2 RT 06 RT 07Kelurahan Sidomulyo,Bengkulu.
085266724617 [email protected] staff of BengkuluUniversity
1 Sahrul Harahap, STJl. Bakti Kopri Gg. Asri,Padangsidempuan.
081376919899 [email protected] of GrahaNusantara University
2 Asroi Benny Noor Harahah, ST., MTJl. Bakti Abdi I No. 5,Padangsidempuan.
081260244024 [email protected] of GrahaNusantara University
3 M. Yusuf Parlagutan Lubis, STJl. Thamrin No. 1,Padangsidempuan.
08139661661 [email protected] of GrahaNusantara University
1 Ahmad Rafii, STJl. Imam Bonjol Gg. Surya,Pdg.sidempuan.
081370511188 [email protected] of GrahaNusantara University
2 Roy Efendi Subarja, STJl. Dwikora II,Padangsidempuan.
08126320644 [email protected] of GrahaNusantara University
3 Masitoh Hasibuan, STJl. Sisingamangaraja Gg.Magabe, Pdg. sidempuanSelatan.
082369328301 [email protected] of GrahaNusantara University
1 Dr. Muhammad Fauzi,ST.,MTJl. Unib Permai Blok I No. 50,Pematang Gubernur - Bengkulu
08137690429 [email protected] of BengkuluUniversity
2 Hesti Aulia Sari, STJl. P. Natadiraja No. 20 Kel.Gedang, Gading Cempaka -Bengkulu
085266724618 [email protected] staff of BengkuluUniversity
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
10 Bengkulu 06 Ps. Pedati - KerkapMay 5,2015
June 4 -5,2015
Oct. 9,2015
Graha NusantaraUniversity, Jl. Dr.
Sutomo,Padangsidempuan
Graha NusantaraUniversity, Jl. Dr.
Sutomo,Padangsidempuan
9North
Sumatera15
Sibolga - Bts.Tapsel
Apr 9,2015
8North
Sumatera05
Sp. Rampa -Poriaha
Apr 9,2015
Oct. 9,2015
March 11-12, 2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
7 Bengkulu 13Sp. Rukis - Tj.
KemuningDec 22,
2014
6 Bengkulu 11Bantal -
MukomukoDec 22,
2014March 11-12, 2015
Oct. 22,2015
Satker PJN II Office,Jl. W. R. Mongonsidi
No. 220 B, BandarLampung
5 Lampung 17Sp. Gunung
Kemala - PugungTampak
Dec 04,2014
No. Package SelectionDate
Training Date Location Telp. EmailNo Province
Package Observed
Name of Selected TPMTPM Selection and Training
TPM's AddressTPM Contact
TPM's Occupation
3 Anggi Nidya Sari, ST., M.EngJl. Halmahera RT 02 RW 03 No.5, Bengkulu.
082180708080 [email protected] of BengkuluUniversity
1 Dr. Khairul Amri, ST., MTJl. Hibrida 15 Gg. Mandiri 5 No.25, Bengkulu.
081367719694 [email protected] of EngineeringFaculty, BengkuluUniversity
2 Nanda Pratama, STJl. Hibrida 2 RT 06 RT 07Kelurahan Sidomulyo,Bengkulu.
085266724617 [email protected] staff of BengkuluUniversity
3 Desti Eka Putri, STJl. WR. Supratman, KandangLimun, Kota Bengkulu.
081919493764 [email protected] staff of BengkuluUniversity
1 Ir. Riswandi, M.SIJl. Lubuk Bayu No. 1 Kurao,Pagang Nanggalo, Padang
08126713602 [email protected] of PoliteknikNegeri Padang
2 Syaiful Amri,SST., MTJl. Andalas Gg. Sarga Indah No.43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
3 Apwiddhal, ST,.MTJl. Gapura No. 1 Air TawarTimur, Padang
81374698872 [email protected] of PoliteknikNegeri Padang
1 Syaiful Amri,SST., MTSatker PJN II, Jl. S.Parman No. 129A,
Padang
Jl. Andalas Gg. Sarga Indah No.43, Padang
081363435968 [email protected] of PoliteknikNegeri Padang
2 Ir. Riswandi, M.SIBPJN II Padang Jl. Jati
109 PadangJl. Lubuk Bayu No. 1 Kurao,Pagang Nanggalo, Padang
08126713602 [email protected] of PoliteknikNegeri Padang
3 B. Army, ST,. MTTaman Bamaran Indah Blok PNo. 3 Padang
085274352715 [email protected] of PoliteknikNegeri Padang
1 Dr. Muhammad Fauzi, ST.,MTJl. Unib Permai Blok I No. 50,Pematang Gubernur - Bengkulu
08137690429 [email protected] of BengkuluUniversity
2 Deri Saputra, STPerumnas Bentiring Indah,Muara Bangkahulu - Bengkulu
08992212213 [email protected]. Lecturer of BengkuluUniversity
3 M. Ridwan Sami, STJl. Batang Hari 6 No. 26,Bengkulu
082281767448 [email protected]. Lecturer of BengkuluUniversity
1 Ir.M. Nursyaifi Yulius,MTJl. Gadih Rantih Ujung No. 20B, Padang
08126608128 [email protected] of Bung HattaUniversity
2 Alzahri, ST.,MTKomp. Polamas Blok W5, AlaiParak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
Jun. 9,2016
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
15West
Sumatera08
Bts. Pariaman -Manggopoh
Jan. 14,2016
14 Bengkulu 16 Seblat - IpuhDec. 29,
2015
Will besheduled
later
Sept. 27,2016
Satker PJN II, Jl. S.Parman No. 129A,
Padang
13West
Sumatera12
Kambang -Indrapura
Dec. 22,2015
12West
Sumatera07 Indrapura - Tapan
Dec. 22,2015
Jun. 9,2016
June 4 -5,2015
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
Satker PJN I Office, Jl.Ir. Rustandi Sugianto
Km 12+225, PulauBaai-Bengkulu
11 Bengkulu 19 Lais - BintunanMay 5,2015
10 Bengkulu 06 Ps. Pedati - KerkapMay 5,2015
June 4 -5,2015
No. Package SelectionDate
Training Date Location Telp. EmailNo Province
Package Observed
Name of Selected TPMTPM Selection and Training
TPM's AddressTPM Contact
TPM's Occupation
3 Yendri Nursami, S. TiJl. Tepi Banjir Kanal No. 9 A,Sawahan Timur - Padang
085217374888 [email protected] of Bung HattaUniversity
1 Ir. Drs. Heldi, M.SiParak Jigarang No. 1/3 RT03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
2 Ir. Afrizal Naumar, MT Jl. Raya Kurao No. 1 Padang 081363418758 [email protected] of Bung HattaUniversity
3 Yul Cherlina Z., ST., MTJl. Anshar No. 29 A, RT 02/RW05, Dadok - Tunggul Hitam,Kota Padang
081363424638 [email protected] of Bung HattaUniversity
1 Dr. Ir. Wardi, M.SiWisma Utama Blok D4 No. 4,Lubuk Begalung - Kota Padang.
081374332825 [email protected] of Bung HattaUniversity
2 Ir. Drs. Heldi, M.Si., Ph.DParak Jigarang No. 1/3 RT03/05 Kuanji, Padang.
081363428468 [email protected] of Bung HattaUniversity
3 Asril Yazid, STKomp. Griya Lestari Blok D8,Batung Taba Lubeg Padang.
08126733441 [email protected] of Bung HattaUniversity
1 Dr. Ir. Bambang Istijono, MEJl. Tenggiri No. 171 C, UlakKarang Selatan, Padang.
0811664421 [email protected] of AndalasUniversity
2 Benny Hidayat, ST., MT.,Ph.DKomplek Kampus Limau Manis,Padang.
081249814406 [email protected] of AndalasUniversity
3Taufika Ophiyandra, ST., M.Sc.,Ph.D
Jl. Belibis Blok C No. 17, AirTawar - Padang.
0811665723 [email protected] of AndalasUniversity
1 Ir. M. Nursyaifi Yulius,M (Mgt)Satker PJN II, Jl. S.Parman No. 129A,
Padang
Jl. Gadih Rantih Ujung No. 20B, Padang
08126608128 [email protected] of Bung HattaUniversity
2 Alzahri, ST.,MTBPJN II Padang Jl. Jati
109 PadangKomp. Polamas Blok W5, AlaiParak Kopi, Padang
08126721639 [email protected] of Bung HattaUniversity
3 Ir. Drs. Heldi, M.Sc, PhDParak Jigarang No. 1/3 RT03/05 Kuanji, Padang
081363428468 [email protected] of Bung HattaUniversity
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang18
WestSumatera
21Lubuk Alung -
KuraitajiMay. 26,
2016
Will besheduled
later
Will besheduled
later
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang
17West
Sumatera20
Lubuk Alung -Sicincin
May. 26,2016
16West
Sumatera10
Sp. Empat - Sp. AirBalam
Jan. 14,2016
Will besheduled
later
Jun. 9,2016
Satker PJN I, Jl. KhatibSulaiman No. 9,
Padang15
WestSumatera
08Bts. Pariaman -
ManggopohJan. 14,
2016
19West
Sumatera14 Painan - Kambang
Augt 12,2016
Sept. 27,2016
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 12The Progress of Third Party Monitoring (TPM) Activities
January 2013 – June 2017 and Works Plan for Next Steps
No Subject of Activities Target Completed
1. Preparation the initial draft of ToR of selection the TPM Dec, 2013 Dec, 2013
2. Providing the TPM selection guidelines. Dec, 2013 Dec, 2013
3. Providing the Training Materials for the TPM Dec, 2013 Dec, 2013
4. Preparing the official letter from the Director of Planning as Chairman ofPMU to Head of BBPJN II & III, about the Selection of TPM. Jan, 2014 Jan. 24, 2014
5. Preparing the official letter from the Director of Planning as Chairman ofPMU to Universities, about the Selection of TPM. Jan., 2014 Jan 29, 2014
6. Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Satker/PPK, about the Selection of TPM Jan, 2014 Jan 13, 2014
7.Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Universities and Satker/PPK, about the Socialization ofTPM Selection for Package 01, 02, & 03
Feb. 2014 Feb. 07, 2014Feb. 13, 2014
8. Socialization of the TPM selection for package 01: Krui - Biha. Feb. 2014 Febr. 14, 2014
9. Socialization of the TPM selection for package 02: Padang Sawah –Simpang Empat and package 03: Manggopoh – Simpang Empat Feb. 2014 Febr. 18, 2014
10.Preparing the official letter from the Director of Planning as Chairman ofPMU to University of Bengkulu, about the Selection of TPM for package04: Ipuh - Bantal.
Jan, 2014 Febr. 19, 2014
11. Help the PMU on formulating the TPM Evaluation Team March 2014 Febr. 25, 2014
12. Implementation of selection of the TPM for four AWP-1 packages by TPMEvaluation Team March 2014 March 10, 2014
13. Delivery of the Preparatory Training for elected TPM for package 01: Krui– Biha in Lampung June 2014 June 5 - 6, 2014
14Delivery of the Preparatory Training for elected TPM for package 02:Padang Sawah – Simpang Empat, and package 03: Mangopoh – PadangSawah in West Sumatera
June 2014 June 17-18, 2014
15 Delivery of the Preparatory Training for elected TPM for package 04: Ipuh– Bantal in Bengkulu July 2014 July 7 – 8, 2014
16 Approval process of elected TPM July 2014 July 7 – 8, 2014
17 Assist PMU to prepare the Decree on Establishment the TPM of AWP-1WINRIP from Director of Planning DGH, as the Chairman of PMU.
August 2014 Sept. 1, 2014
18
Sending the Coordination Letter from Director of Planning, DirectorateGeneral of Highways to the Head of BBPJN Region I Medan, aboutSelection of the Third Party Monitoring (TPM) for package 05 (SimpangRampa – Poriaha, and package 15 (Sibolga – Tapanuli Selatan border) inNorth Sumatera.
October 2014 Oct, 07, 2014
19
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Lampung (UNILA) for package 17 (SimpangGunung Kemala – Pugung Tampak) in Lampung Province.
October 2014 Oct, 03, 2014
20
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Sumatera Utara (USU) for package 05(Simpang Rampa – Poriaha) in North Sumatera Province
October 2014 Oct, 03, 2014
21
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Bengkulu (UNIB) for package 11 (Bantal –Mukomuko) and package 13 (Simpang Rukis - Tanjung Kemuning) inBengkulu Province.
October 2014 Oct, 20, 2014
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Target Completed
22Selection of the Third Party Monitoring (TPM) for packages 17 (SimpangGunung Kemala – Pugung Tampak) Lampung Province November 2014 Dec. 4, 2014
23 Selection of the Third Party Monitoring (TPM) for packages 11, and 13,Bengkulu Province
December 2014 Dec. 22, 2014
24 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Graha Nusantara Padang-sidempuan
January 2015 Jan, 28, 2015
25 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Sumatera Utara Medan
January 2015 Jan, 30, 2015
26
The Employment Agreement or Memorandum of Understanding betweenTPM (packages 01, 02, 03, and 04) with the CTC WINRIP (PT. PlannersDjaja) has been signed. November 2014 Feb. 26, 2015
27Delivery of the Preparatory Training for elected TPM for package 11:Bantal – Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, inBengkulu
January 2015 March 11-12,2015
28 Selection of the Third Party Monitoring (TPM) for packages 05, and 15,Northern Sumatera Province March 2015 April 9, 2015
29 Selection of the Third Party Monitoring (TPM) for packages 06, and 19, inBengkulu Province May 2015 May 5, 2015
30Delivery of the Preparatory Training for elected TPM for package 06:Pasar Pedati – Kerkap and package 19: Lais – Bintunan, in BengkuluProvince
June 2015 June 4-5, 2015
31 The TPM of package 01 (Krui - Biha) has been doing site observations (fieldvisit) for the first phase July 2015
32 TPM package 02 (Padang Sawah - Simpang Empat) and package 03(Mangopoh - Padang Sawah), had conducted a field visit for first phase July 2015
33 The TPM of package 01 (Krui - Biha) has been done site observations (fieldvisit) for the second phase
3rd week ofAugust 2015
34 The TPM of package 04 (Ipuh - Bantal) has been done site observations(field visit) for the first phase
4th of August2015
35 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 01 Krui - Biha Agt. 19 -21, 2015
36 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 Ipuh - Bantal Agt. 27 -28, 2015
37The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat)package 03 (Manggopoh Padang Sawah)
Sept. 10 - 11,2015
38The TPM of Package 02 (Padang Sawah – Simpang Empat) an package 03(Manggopoh Padang Sawah) had been done site observations (field visit)for the first phase
Sept, 2015
39Delivery of the Preparatory Training for appointed TPM for package 05:Sp. Rampa – Poriaha and package 15: Sibolga – Batas Tapsel in NorthSumatera Province
October 9, 2015
40 Delivery of the Preparatory Training for appointed TPM for package 17:Sp. Gunung Kemala – Pugung Tampak in Lampung Province Oct. 22, 2015
41 TPM package 04 Ipuh – Bantal has submitted their Field Visit MonitoringReport to PMU WINRIP Oct. 27, 2015
42 TPM package 03 Maggopoh – Padang Sawah has submitted their FieldVisit Monitoring Report to PMU WINRIP Nov. 11, 2015
43 TPM package 01 Krui – Biha has submitted their Field Visit MonitoringReport to PMU WINRIP Nov. 26, 2015
44The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 11 (Bantal – Mukomuko) package 13(Simpang Rukis – Tanjung Kemuning) in Bengkulu Province
Dec. 03-04, 2015
45 Selection of the Third Party Monitoring (TPM) for packages 07 and 12 in Dec. 22, 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Target Completed
West Sumatera Province
46 Selection of the Third Party Monitoring (TPM) for package 16 in BengkuluProvince Dec. 29, 2015
47 Selection of the Third Party Monitoring (TPM) for packages 08 and 10 inWest Sumatera Province Jan. 14, 2016
48The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 (Ipuh – Bantal) and package 11 (Bantal– Mukomuko) in Bengkulu Province
Apr. 6-8, 2016
49The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat) andpackage 03 (Manggopoh – Padang Sawah) in West Sumatra Province
Apr. 20-22, 2016
50The Community Development Team of CTC WINRIP has carry out ofSocialization of the TPM for package 14, 20, 21 to Andalas University ofpadang in BBPJN II Padang.
Apr. 27, 2016
51Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan) inBengkulu Province.
May 18–20, 2016
52Community Development team has carry out of TPM selection for package20 (Lubuk Alung - Sicincin) and package 21 (Lubuk Alung – Kuraitaji) inWest Sumatera Province
May 26, 2016
53Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 07and package 08 in West SumateraProvince
June 9, 2016
54Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) and package 15 (Sibolga – BatasTapsel) in North Sumatera Province.
June 20–22, 2016
55 Community Development team has monitored the TPM activity onpackage 17 (Simpang Gn. Kemala – Pugung Tampak) in Lampung Province. July 27–29, 2016
56 Community Development team has carry out of TPM selection for package14 (Painan – Kambang) in West Sumatera Province Agt. 11–13, 2016
57 Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) in Bengkulu. Agt. 24–26, 2016
58Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 12 and package 14 in West SumateraProvince
Sept. 27, 2016
59Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 20 and package 21 in West SumateraProvince
Oct. 13, 2016
60Community Development team has monitored the TPM activity onpackage 07 (Indrapura – Tapan) and package 12 (Kambang – Indrapura) inWest Sumatera Province.
Nov. 16–19, 2016
61 Community Development team has monitored the TPM activity onpackages 13 (Simpang Rukis – Tanjung Kemuning) in Bengkulu Proince. Nov. 28–30, 2016
62 Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) in Nort Sumatera Province. Dec. 15 - 17, 2016
63 Community Development team has monitored the TPM activity onpackage 08 (Bt. Kota Pariaman – Manggopoh) in West Sumatera Province. Dec. 22 - 24, 2016
64 Community Development team has monitored the TPM activity onpackage 06 (Ps. Pedati – Kerkap) in Bengkulu Province. Dec. 29 - 31, 2016
65
Community Development team was facilitation TPM for package 04 (Ipuh- Bantal) and package 11 (Bntal – Mukomuko) of Bengkulu Province,meeting with Management of PT. Perentjana Djaja, on topic ofreimbursement of TPM monitoring cost.
Jan. 16, 2017
66Community Development team has monitored the TPM activity onpackage 20 (Lubuk Alung – Sicincin) and package 21 (Lubuk Alung –Kuraitaji) in West Sumatera Province.
March 2 - 4, 2017
67 Community Development team has monitored the TPM activity on March 15 - 17, 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities Target Completed
package 14 (Painan – Kambang) in West Sumatera Province.
68 Community Development team has monitored the TPM activity onpackage 17 (Simp. Gng Kemala – Pugung Tampak) in Lampung Province.
March 22 - 24, 2017
69 Community Development team has monitored the TPM activity onpackage 12 (Kambang – Indrapura) in West Sumatera Province.
April 10 - 12, 2017
70 Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 16 in Bengkulu Province
April 27, 2017
71 Develop Report of Preparatory Training for TPM of package 16 (Sebelat -Ipuh) in Bengkulu
May 2, 2017
72 Develop Evaluation Report on Implementation of Third Party Monitoring(TPM) from the project beginning up to May 2017
May 4-8, 2017
73Prepare draft Special Report of the Implementation of Anti-CorruptionAction Plan (ACAP) as a part of draft CTC WINRIP Final Report or ProjectCompleting Report
Begin on May 9,2017
74Prepare the response to Supreme Audit Board / Badan PemeriksaKeuangan (BPK) Republic of Indonesia findings on funding the Third PartyMonitoring from Provisional Sums.
May 29-30, 2017
75Community Development team has monitored the TPM activity onpackage 15 (Sibolga – Batas Tapsel) and package 05 (Simpang Rampa –Poriaha) in North Sumatera Province.
June 13 - 17, 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 13Works Plan on Complaints Handling Mechanism System (CHS) Activities.
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Review of Minister Decree of Public Works No. 323/2005 concerning the procedures ofHandling input from communities on the environment of the Ministry of Public Works April 18, 2013
2 Preparation of Complaints Register and the complaints address (developing of web site ofWINRIP) and provided ACAP to inputting data in the web site.
Completed on themiddle of Feb. 2014.
3 Preparation of Complaint Handling Procedure (already available on the websiteapplication http://www.winrip-ibrd.com) April 2014
4The completion of the Initial investigation of a complaint Procedure, and the procedurefor the investigation of Complaints, as well as the conclusion of investigation (alreadyavailable on the website application http://www.winrip-ibrd.com)
April 2014
5 Monitored and noted the public complaints via SiPP website and WINRIP website, butuntil December 2014 have no complaint about the WINRIP programs December 2014
6
Clarification of Community complaint for package 02 & 03 by Jejak Media Group (JMG) byMr. Buyung on gravel aggregate materials, routine maintenance, and watering work site(dust pollution). It has been followed up by PPK 09 and PPK 10 to hold a clarificationmeeting, followed by the elements PPK, Supervision Consultant (DSC), and Jejak MediaGroup (JMG).
March 23, 2015
7
Clarification of information of work implementation on package 04: Ipuh - Bantal wasunfavorable, by TPM member (Mr. Hardiansyah, ST, MT). The information obtained fromthe local mass media. The problem is that the people around the location of the packageIpuh - Bantal especially road users complained about the excavation of road widening isleft open for an extended period of time without equipped with signs and safety fence,felt very dangerous, especially when driving at night, and according to the informationsome of the riders had been an accident which the vehicle plunged into the hole dug.This information has been followed up by PPK 01 Bengkulu together with the SupervisionConsultant (DSC Field Team) to instruct the Contractor to install traffic signs and safetyfences in places that endanger of road user
March 26, 2015
8
On May 11, 2015, Mr. Dr. M. Fauzi, ST, MT,, the main observer of the Third PartyMonitoring for Package 11 (Bantal - Mukomuko) Bengkulu Province, conveyinginformation from local newspaper clippings (Koran Rakyat Bengkulu) containing news thata 1.5-year-old toddler fell and nearly drowned in the excavation of the road wideningPackage 11 (Bantal - Mukomuko) which flooded about 80 cm deep. That is because theexcavation is situated in the location residential and not immediately undertaken, andwere not given the signs and safety fence.The complaint was submitted to the PMU and forwarded to the related PIU / PPK to beclarified.Until the end of May there has been no follow-up report to the complaint from the PIU /PPK 01 linked.
May 11, 2015
9
The CHS team has been received the copy of complaints letter from Tender Participantson package 08 to the Procurement Committee. Disclaimer of submitted by the tenderparticipants of package 08 (Batas Kot Pariaman – Manggopoh) PT. Adhi Karya (Persero)Tbk – PT. Yasa Patria Perkasa, JO by letter No: ADHI-YASA/12/I/2016 dated January 12,2016, to the Procurement Committee concerning to the results of Bid Evaluation Report(BER) section III, clause 4, point 4.2 (b): Specific Construction Experience in Key Activitiesspecifically on the experience of aggregate base production.
Jan. 15, 2016
10
CHS team has been received the other similar complaint to the Procurement Committeewas submitted by the same tender participant of package 12: Painan – Kambang (PT. AdhiKarya (Persero) Tbk – PT. Yasa Patria Perkasa, JO) by letter No: ADHI-YASA/11/I/2016dated January 4, 2016. The content of complaint was the similar subject i.e. the results ofBid Evaluation Report (BER) section III, clause 4, point 4.2 (b): Specific ConstructionExperience in Key Activities specifically on the experience of aggregate base production
Jan. 15, 2016
11CHS team has been received the complaints from Riki Susanato (Konsorsium Nasional LSMProvinsi Bengkulu) dated February 02, 2016. Riki Susanato and Edy Novriansyah had sent aletter No: 06/Khusus/XII/2015 dated December 11, 2015 on a request for public
Feb. 02, 2016
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
information related to the documents of WINRIP project in Bengkulu province. But thisrequest was unable to fulfill by Satker PJN Wil. I of Bengkulu Province, especially inrelation to Contract Document / Letter of Agreement between the ProjectImplementation Unit of WINRIP for Bengkulu Province with the Contractors.By not granting of the request of the documents, then Riki Susanto delivered thecomplaint through the Complaint Handling System (CHS) of WINRIP website (www.winrip-ibrd.com). The complaint was submitted to the PMU WINRIP and the relevantstakeholders to immediately follow-up.
12
On January 20, 2016, there was a World Bank letter No. 281 on reviewing Bid EvaluationReport (BER) for Package 16: Seblat – Ipuh in Bengkulu Province. World Bank has and havecomments on the Bina Marga proposed rejection of the five lower priced bidders.As a follow up of these comments, on February 10, 2016 has been held DiscussionMeeting to respond to the letter. Meeting followed by elements from the WB, PMU, PokjaPJN Reg. 1 of Bengkulu Province. Clarification should be explained in the revision of BERand sent to World Bank.
January 20, 2016February 10, 2016
13
The Complaint from Civil Society of villages in around the project STA 28+900 (DesaPondok Kandang, Desa Pondok Suguh, dan Desa Karya Mulya) was submitted through aletter of district head (Surat Camat) of Pondok Suguh, No. 620.52/56/K.05/IV/2016 datedApril 11, 2016, sent to the Supervision Consultants (Field Team DSC of Package 04) on therequest of one extra culvert / box culvert again, because the existing culvert in small sizeand its surface less downward, which is predicted when it rains the water could not floweasily or drained from the settlement and the Villages will be flooded
April 11, 2016
14
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject of performance audit of PT, JAYA KONTRUKSI MP.Tbkthat was Addendum until April 19, 2016 but the work is still ongoing until April 23 2016,how it could happen, we ask for explanation
May 11, 2016,
15
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject evaluation of stone masonry works on bridgeapproach of Air Gadang Bridge in package 02 (Padang Sawah – Simpang Empat) WestSumatera Province. The stone masonry works by contractor PT. JAYA KONTRUKSI MP.Tbkis bed quality, did not match to the specification
May 14, 2016
16
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] and to Menteri PUPERA by e-mail minister of Public Works and onsubject of the National Road in Pasaman Barat - West Sumatra province, many of themwere which seriously damaged.
May 17, 2016
17Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject that Air Gadang Bridge until May 31, 2016 is not yet befinished.
May 31, 2016
18
The Community Development Officer and Information Management Specialist wasmeeting with World Bank (Mr. Andri Wibisono) on topic of completeness the WINRIPwebsite included Complaint Handling System (CHS). The main subject is the completenessof the website application program, the completeness data sources, and the applicableand accessible of this website, so everyone can access or find the data that they needs.
August 2, 2016
19
On January 30, 2017 Complaint Unit has received one complaint from someone namedBuyung Fajri from Non-Government Organization “JEJAK Community”. It is complained ofis that, the contract value is not listed on the information board and workers of heavyequipment Operators are not using personal safety (K3) i.e helmet
January 30, 2017
20Complaint Unit has received one complaint from Buyung Fajri from Non-GovernmentOrganization “JEJAK Community” thru email dated February 15, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji
February 15, 2017
21On February 16, 2017, Complaint Unit has received one complaint from Buyung Fajri (Non-Government Organization “JEJAK Community”) thru email, regarding the maintenance ofWINRIP Packages No.03 Manggopoh – Padang Sawah
February 16, 2017
22Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 5, 14, and 21, 2017, regardingthe condition of retaining wall on approach road of Air Gadang Bridge in Packages No. 02
March 5, 14, and21, 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
Padang Sawah – Simpang Empat. This package has been PHO on April 14, 2016 is nowentered the maintenance period.
23Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 21, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji
March 21, 2017
24
On April 6, 2017 was complaint from Berita Harian Sumbar http://sumbar.auditpos.com(Non-Government Organization), thru email to the World Bank’s Highway Engineer Mr.Agus Sjamsudin ([email protected]) regarding the implementation of Package20 Lubuk Alung – Sicincin on concrete reinforcement of drainage structure was not inaccordance with the specification, and the bad quality of mortar for retaining wall
April 6, 2017ClarifiedApril 13, 2017
25
Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on April 7, 2017 and April 23, 2017,regarding the implementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji. TheContractor PT. MULTI STRUCTURE ignores the road user's safety.
April 7, 2017April 23, 2017
26Prepare the Response of the complaints from Mr. Buyung Fajri (Non-GovernmentOrganization “JEJAK”) of April 23, 2017 regarding the implementation of WINRIP PackagesNo.21 Lubuk Alung – Kuraitaji
May 2, 2017
Other Activity
1 The establishment of the settlement Commission Handling the Complaint under theInspectorate General of the Ministry of Public Works (Executing Agency) if it necessary
Will establish if there is acase that needs specialhandling
2Preparation of the device for Executing Agency such as: Procedures announcement ofpenalties, procedures for the annual Survey, Procedure Annual Independent Review, theprocess of Auctions
Done by ProcurementSpecialist and theContract ExaminerCommittee
3 The development of a code of conduct and actions for Implementing Institutions/Implementing Agency (Bidders, Suppliers, contractors and Consultants)
Done by PMU of DGH
4 Support the PMU in the Management and Monitoring of the implementation policy inhandling public complaints
Have been carried outthroughout projectimplementation period
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 14
Works Activities on Publication / Disclosure Activities
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Conducted Workshop of Procurement Document Evaluation for POKJA,Satker/PPK, Balai BBPJN and PMU
February 28, 2013– March 01, 2013
2 Conducted Workshop of World Bank Guidelines of Procurement for WINRIP tothe POKJA, Satker/PPK, Balai BBPJN and PMU
April 24 – 25, 2013
3 Review training materials on Project Management Manual (PMM), especiallyCHAPTER XI of the anti-Corruption Action Plan (ACAP)
First updating April 29, 2013
4 The second Review of training materials on Project Management Manual(PMM), Chapter I - XII
Second updating onDecember 18, 2013
5 The third Review of training materials on Project Management Manual (PMM),Chapter I - XII
third updating onApril, 2014
6. Preparing Method Transparency to the Public, and Improvement the proceduresto the Public Disclosure through information media (website).
Establishment of InformationSystem (MIS) was finish on
March 2014
7. The updating of Project Management Manual (PMM), Chapter 3, 9, 11, and 13,has been held in Bogor June 2014
8 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 01,02, and 03 June 2014
9 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 04 July 2014
10 The implementation of Dissemination/training of the PMM to Stakeholders forPackages 01, 02, 03, and 04
September 10 - 11 2014
11Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 01, 02, 03, 04, 17, 11,13, 05, 06, 19, and 15 into the WINRIP’s website.
From Augt 2013 – April, 2015
12Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 01, 02, 03, 04, 17, 11, and 13 into theWINRIP’s website.
From Augt 2013 – April, 2015
13Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into theWINRIP’s website.
From Augt 2013 – April, 2015
14Inputting / upload / update of data/documents/reports of Environmentalactivities for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
15Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
16Inputting / upload / update of Progress Report/ Actual Status (fisichal worksand financial) of each package that has been contracted (packages 01, 02, 03,and 04) into the WINRIP’s website.
From Augt 2013 – April, 2015
17 Inputting / upload of Monthly Progress Report (MPR December 2012 – December2014) into the WINRIP’s website.
Every Month
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
18 Inputting / upload of Quarterly Progress Report (QPR December 2012 –December 2014) into the WINRIP’s website.
Every Three Months
19 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 01, 02, 03, and 04.
26 – 27 November 2014
20 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter October –
December 2015
21 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 05, 11, 13, and 17.
Feb. 11 - 12, 2015
22 Report of Technical and Financial Audit Consultants (TFAC) for Packages 02 and03 has been received from TFAC Team
Feb. 27, 2015
23
Delivery of the Preparatory Training for elected TPM for package 11: Bantal –Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, in Bengkulu. Thistraining followed the elements of TPM, Satker/PPK, Contractors, SupervisionConsultants, and Balai BBPJN III Palembang.This training is intended to provide an explanation of the scope of duties of TPMand provide information to all elements involved in the implementation of theproject that the community be involved in monitoring the implementation ofthe project which is represented by the TPM, in accordance with the LoanAgreement.
March 11 – 12, 2015
24 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter January –
March 2015
25Delivery of PMM Socialization to Stakeholders (Balai BBPJN III, PIU/PPK,contractors and Supervision Consultants ‘DSC’) for four Packages (06, 11, 13,and 19) in Bengkulu Province
May 6 – 7, 2015
26
Delivery of the Preparatory Training for elected TPM and Work Plan for manageand monitor the Environment / Rencana Kerja Pengelolaan dan PemantauanLingkungan (RKPPL) for package 06: Ps. Pedati – Kerkap and package 19: Lais –Bintunan, in Bengkulu. This training followed the elements of TPM, Satker/PPK,Contractors, Supervision Consultants, and Balai BBPJN III Palembang.
June 4 – 5, 2015
27 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter April –
June 2015
28 The Mid-Term Report of the first semester 2015 has been written by the early ofJuly 2015
July, 2015
29 Delivery of PMM Training for Stakeholders (PPK, contractors and SupervisionConsultants ‘DSC’) for Packages 17, 05, and 15
November 23 – 24, 2015
30Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 07, 08, 10, 12, 14, 16,20 and 21 into the WINRIP’s website.
From May – Dec, 2015
31Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 05, 06, 07, 12, 15, 19 and 16 into theWINRIP’s website.
December, 2015
32Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From June – Dec, 2015
33 Inputting / upload / update of data/documents/reports of Environmentalactivities for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’s website.
From May – Dec, 2015
34Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From May – Dec, 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
35Inputting / upload / update of Progress Report/ Actual Status (physically works,financial and audits) of each package that has been contracted (packages 05, 06,07, 11, 13, 15, 17 and 19) into the WINRIP’s website.
From May – Dec, 2015
36Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 14, 20 and 21 into theWINRIP’s website.
January, 2016
37Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 14, 20, and 21 into the WINRIP’swebsite.
December, 2015
38 Updated the Project Management Manual (PMM) Chapter III : Planning andProgramming
January, 2016
39 Review and Updated of the Project Management Manual (PMM) Chapter IX :Performance Monitoring and Evaluation,
March, 2016
40 Review and Updated of the Project Management Manual (PMM) Chapter XI:Anti-Corruption Action Plan (ACAP)
April, 2016
41Review and Updated of Power-point presentation of the Project ManagementManual (PMM) Chapter IX : Performance Monitoring and Evaluation, Chapter XI:Anti-Corruption Action Plan (ACAP)
June, 2016
42
The Information Management Specialist and Community Development Officerimmediately follow up the results of the meeting with World Bank to becompleted and perfected. The results of that meeting be used as an ingredientof Kick-off and Wrap-up Meeting, which would then be inserted in the Final AdieMemoire of August 11, 2016
August 11, 2016
43
Delivery of PMM Socialization to Stakeholders (Balai BPJN III, PIU/Satker Region Iand II of West Sumatera, PPK 06 (pack. 20), PPK 10 (Pack. 08 & 21), PPK 14(Pack. 14), PPK 15 (Pack. 07), contractors and Supervision Consultants ‘DSC’) forfour Packages (07, 08, 14, 20, and 21) in West Sumatera Province
Augt. 29 –31, 2016
44 Delivery of TPM Preparatory Training for packages 12 and 14 in Padang, WestSumatera
Sept. 26 – 28, 2016
45The CTC (Community Development Team) has been carried out preparatorytraining for Third Party Monitoring (TPM) of packages 20 and 21 in Padang, WestSumatera.
October 13, 2016
46 Review and identify the changing of Project Management Manual (PMM)Modules from Revision-1 version to Revision-2. Oct. 18 - 24, 2016
47Prepare draft of Agreement Letter of Director of Roads Net WorkingDevelopment on establishment of Working Group /Task Force for updating andimprovement of the PMM.
Oct. 25 - 27, 2016
48 Prepare draft proposal of Price Adjustment /Escalation Workshop for theWINRIP Oct. 28 – Nov. 14, 2016
49 During January 2017 all CTC Professional were prepare the updating the ProjectManagement Manual (PMM) January 2017
50During February 2017 all CTC Professional were updated the ProjectManagement Manual (PMM) for revision 2. The Community DevelopmentOfficer was updated Chapters III, IX, XI, and XIII.3.
February 2017
51Prepare the response to Supreme Audit Board / Badan Pemeriksa Keuangan(BPK) Republic of Indonesia findings on funding the Third Party Monitoring fromProvisional Sums, and meeting with BPK
May 29-30, 2017
Activities Plan for Next Step
1 Delivering the other training programs of WINRIP shall inline of projectimplementation progress.
Depend on projectimplementation progress
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
2 Public Expose on ACAP to the civil society forum in each project location (eachpackage)
Before the construction worksstarted
3 Monitoring of the implementation of disclosure and transparency of informationto each package during contraction period.
Plan for three time monitoringto field for each package during
contraction period
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 15Status of Anti-Corruption Action Plan
Edition: June, 2017
RISKAREA NoACTIONS STATUS (as of June, 2017)
Enha
nced
Dis
clos
ure
and
Tran
spar
ency
1 MPW will provide the Contact information forcomplaints related to WINRIP in the PIP, PMM, MPWwebsite and in bidding documents.
Complaint Handling System has been established, written in PMM(Chapter 11.4), and published on DGH websitehttp://binamarga.pu.go.id linked to WINRIP website(http://www.winrip-ibrd.com) Contact information is provided in Bidding Documents Chapter 2:
Instruction to Bidders (Instruksi Kepada Peserta Lelang - IKP 34).
2 Work programs and Procurement Plan published onthe official website of MPW and made available to thepublic.
Work Programs and Procurement Plan available in the MPW website(http://eproc.pu.go.id) and (http://www.winrip-ibrd.com) Open http://www.winrip-ibrd.com, click Pengadaan there are
available data on Procurement Plan, Procurement Information, andList of Contract awarded.
3 Procurement Plan updated annually. Done. Officially sent to World Bank.4 Quarterly newsletter published on the official website
of MPW, including information concerning the list ofcontracts, implementation progress, project-relatedworkshops and the number, typology and status ofcomplaints.
Quarterly newsletter is updated every three months (quarterly) foryear 2015 has developed 3 newsletters (the first Newsletter is ofJanuary – March 2015),. The previous quarterly Newsletters werepublished on WINRIP website (http://www.winrip-ibrd.com) linked toDGH website (http://binamarga.pu.go.id), and the most recent is ofApril – June 2017 under prepared and waiting for signing by PMUOfficer. Quarterly Newsletter is attached with: Summary Physical Works
Implementation Progress, List Implementation of Training /Workshop, and the List of packages that have been contracted.Such information has been inputted or uploaded on the websiteWINRIP (http://www.winrip-ibrd.com) linked to the website of D.G.of Highways http://binamarga.pu.go.id.
5 Quarterly newsletter sent by MPW to the civil societyforum in each project province in hard copy orthrough an electric mailing system.
Quarterly newsletter published on the website WINRIP developed inthe form of tables and descriptions of activities (see point 4 above). The Quarterly Newsletter period of January -March 2017 has been
sent to the civil society forum in April 2017: i.e. Indonesian RoadDevelopment Association / Himpunan Pengembangan JalanIndonesia (HPJI) and Indonesian Transportation Society /Masyarakat Transportasi Indonesia (MTI) in central level and to theprovincial level where the WINRIP project are developed, by e-mail.
6 Bidding documents, short-list of consultants andrequests for proposals (this provision does not includeactual bids and proposals) issued in accordance withthe procurement provisions of the loan agreementavailable to any member of public promptly uponrequest, subject to payment of a reasonable fee forproducing bidding documents and request forproposals. Documents available until a year aftercompletion of the contract entered into for the goods,works or services in question.
The Bidding Documents such as: Standard Bidding Document, BidInvitations, Instruction to Bidders, General Specifications, DetailedEngineering Design/Drawing, General Condition of Contracts,Special Condition, Bill of Quantity, Owner Estimate, etc, areavailable on MPW website (http://eproc.pu.go.id) and some ofthem were uploaded in WINRIP website (http://www.winrip-ibrd.com), and continuously added for which are available data. Contract Packages #01, 02, 03, 04, 05, 06, 07, 08, 11, 13, 12, 14, 15,
16, 17, 19, 20, and 21 have been awarded. Packages # 01, 02, 03, 04, 19, and 06, has been Taking Over (PHO). Packages # 05, 07, 08, 11, 12, 13, 14, 15, 16, 17, 20 and 21 were
under construction Package 10, is expressed not as a priority on the WINRIP by the
Ministry of Public Works and Housing, so it is considered to becanceled from WINRIP program. Packages # 09 and 18 has been deleted from project list, because
the available funds are insufficient
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
RISKAREA NoACTIONS STATUS (as of June, 2017)
7 Information as follows published in UNDB on-line, andon MPW website within two weeks of contract award(after Bank’s no objection): (a) name of each bidderwho submitted a bid; (b) bid prices as read out at thebid opening; (c) name and evaluated prices of eachbid; (d) name of bidders whose bids were rejected andthe reasons for rejection; and (e) name of the winningbidders and the prices, as well as the duration andsummary scope of the contract awarded.
ICB Contract Award Notice for Packages #01, 02, 03, 04, 05, 08, 11,12, 13, 15, and 17 were published. Package #10 is deleted from WINRIP
8 List of all contracts awarded in the three monthspreceding the date of the request by any person orcompany request available, including the name of thecontractor/ supplier/ consultant, the contract amount,the number of bidders/proposals, the procurementmethod and the purpose of the contract.
The information is available, but there has been no request by anyperson or company. The Data of Physical progress of packages that are under
constructions had been completed with any changes of the contactlike: review design, CCO, technical justification, memorandum,amendment, addendum, etc.
9 Final audit reports (financial or otherwise, includingqualified audit reports) and all formal responses of thegovernment in relation to such reports publiclyavailable. The audit reports and all formal responseswill be published on the MPW official website withinone month after the report is accepted as final.
MPW has sent report as a response to the Bank regarding thefindings of the audit report. The Final Audit for 2012, 2013 and 2014 have been
completed, and uploaded to website (http://www.winrip-ibrd.com) linked to http://binamarga.pu.go.id The Final Audit for 2016 had been held by BPK, and the
audit results are being responding and follow up byDGH and the related parties.
10 Financial, technical and physical progress of theproject monitored by an IT system (integrated SiPP) aspublicly accessible project monitoring system.
Those reports are available on WINRIP website (http://fmis.winrip-ibrd.com) linked to Bina Marga website(http://binamarga.pu.go.id/bm/sipp.html). The financial, technical and physical progress was already uploaded
in the website. It’s has been completed with information of nameof contractors, number of contract, date of contract, contractPrice, duration of contract, etc. The tutorial guidance has been developed and already been sent
by MIS specialist. The financial progress report is updated every three months as the
IFR quarterly report.The technical and physical progress is updated every month as theMonthly Progress Report, and every three months as the QuarterlyProgress Report
Enha
nced
Civi
l Soc
iety
Ove
rsig
ht
11 Representatives of civil society groups invited toattend the public bid openings and other keyprocurement steps. Community RepresentativeObservers (CROs) invited from local universities orother selected independent institutions. Attendancelist for the procurement/selection process signed.
CROs for 19 packages (#01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12, 13,14, 15, 16, 17, 19, 20, 21) have been selected, and have attended therequired meeting (Pre-Bid Meeting and Bid Opening Meeting).Attendances list are available.
12 Guidelines on appropriate procedures for the aboveprovided in the PMM.
The Appropriate procedures are written in PMM Chapter 11.2,and in the TOR of CROs Selection.
13 Third Party Monitoring (TPM) mechanism established.This mechanism includes regular sharing ofinformation with the media.
TPM for all 19 Packages #01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12,13, 15, 16, 17, 19, 20, 21, and 14# had been selected.
TPM Letter of Agreement for all 19 Packages #01, 02, 03, 04, 05,06, 07, 08, 11, 12, 13, 14, 15, 16, 17, 19, 20, and 21 had beensigned.
The Agreement of TPM operational funding between TPM and CTC(PT. Perentjana Djaja) has been signed for 15 packges # 01, 02, 03,04, 05, 06, 08, 11, 13, 14, 15, 17, 18, 19, 20, and 21# For Packages 07, 12, and 16 is under process
Packages 09 and 18 were deleted from WINRIP program, andpackage 10 was failed of Bidding.
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
RISKAREA NoACTIONS STATUS (as of June, 2017)
14 Annual Accountability Meetings held. First meetingheld at the province level before procurement ofcontractors or service providers.
The Annual Accountability Meetings were held through the followingactivities: Coordination meeting at the Regional level (Balai- BBPJN) and in
each province Public Expose of LARAP to the community around the project area Socialization of projects during selection of CROs and TPM at local
universities near project sites and in the same province. (Detaildates of Socialization meeting and training of the CROs and TPMcan be found in the Monthly or Quarterly Report of WINRIP in theWINRIP’s website)
Public expose and dissemination of information to inhabitantsaround the project is delivered through Project Information Board.
PMM workshop has been carried out in: Padang on September 12, 2014 for four AWP-1 packages # 01,
02, 03, and 04. Bengkulu on May 6 – 7, 2015, delivery of PMM Socialization to
Stakeholders (Balai BBPJN III, PPK, contractors and SupervisionConsultants) for four Packages # 06, 11, 13, and 19.
Bogor on November 24 – 25, 2015, delivery of PMMSocialization to Stakeholders (BBPJN I, BBPJN III, PPK 08, PPK12, contractors and Supervision Consultants) for threePackages (05, 15, 17).
The PMM Socialization has been held in Padang on August 29 –30, 2016 for project stakeholders of six packages in WestSumatera Province # 07, 08, 12, 14, 20, and 21.
Target group of this socialization as follows: BBPJN II, PIU/Satker PJN Region I and II of West Sumatera Province, PPKswho are handling the projects (PPK 06, PPK 10, PPK 14, and PPK15), Design and Supervision Consultant (DSC), Field SupervisionConsultants, and Contractors.
PMM Revision 2 is under process for signed by Director General ofHighway.
Enha
nced
Com
plai
nts H
andl
ing
Mec
hani
sm
15 Enhanced complaints handling mechanism, whichincludes maintaining project complaint log and filingto monitor status of follow-up of each complaint,established by the MPW.
A Complaint Handling System has been established, written in PMM(Chapter 11.4), and published on WINRIP website (http://chs.winrip-ibrd.com).
16 Complaints received acknowledged to thecomplainant by the Project Implementation Unit (PIU)within seven (7) days of receipt with a copy to PMU,DGH and then World Bank. Bid-related complaintsreceived during bid evaluation period responded afterthe contract award. All complaints handlingcomponent included in the MPW website, andupdated on a monthly basis.
Up to present as recorded 10 complaints have been followed up. Complaint procedures and handling mechanism are written in
PMM (Chapter 11.4) and uploaded to website (http://chs.winrip-ibrd.com)
Complaints are handled by the Secretariat of Complaint HandlingUnit (CHU) under PMU WINRIP, and CHU will update thecomplaint status.
Dispute resolution of complaints will be handled by differentinstitutions (PPK, Satker, Inspectorate General, KomisiPenyelesaian Pengaduan), depending on the type of complaints(i.e. general matters, technical matters, or specific matters).
17 Information concerning the alternative conduits forcomplaints (telephone hotline, dedicated emailaddress and PO Box) widely disseminated.
The information of Complaint procedures has been disseminatedto the different institutions related to project implementation(PPK, Satker, Contractors, Engineer/ Supervision Consultants)during PMM workshop and to the CROs & TPM duringintroductory training.
PPK will put the information of complaint procedures and otherproject information to the public through Project InformationBoard.
18 Strict procedures to ensure anonymity of informants. The procedures ensure anonymity of informants
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
RISKAREA NoACTIONS STATUS (as of June, 2017)
19 Recording and appropriate referral of all incomingcomplaints undertaken by MPW with each casegenerating an automatic, standard format report tothe Bank.
It has been established in the WINRIP website (http://chs.winrip-ibrd.com)
Miti
gatin
g Co
llusi
on, F
orge
ry a
nd F
raud
Ris
ks
20 “Semi E-Tendering” on the MPW official publicwebsite used by MPW for both works and consultantservices. Key information (see list) published on theofficial website (www.pu.go.id): (a) invitation for bids;(b) download of bidding documents; (c) bidclarifications; (d) minutes of bid opening; (e)information of contract award.
Semi e-procurement was applied before November 2014 and full e-procurement was applied afterward.
21 All specifications defined in the bidding documents,and all clarifications sought through writtencorrespondence and replies sent to all bidders.
Done.
22 Key indicators of submitted bids analyzed by MPW,through CTC. Short technical report for each group ofbidding (the bidding packages simultaneously invited)prepared and shared with the Bank.
Applicable only to AWP-1 (Packages #01, 02, 03, and 04).
23 Contracts awarded within original bid validity period. The last information from the Procurement Specialist, there are six(6) contracts awarded within original bid validity period (Package #04, 06, 11, 13, 17, and 19).
Twelve (12) contracts awarded after original bid validity period(Packages # 01, 02, 03, 05, 07, 08, 12, 14, 15, 16, 20, and 21).
One package is deleted from WINRIP program (# 10).24 Guidelines for preparation of specifications/ selection
criteria in the bidding documents and request forproposals prepared to ensure compliance with theBank Guidelines.
Done
25 FIDIC arrangements used by MPW with theindependent supervision consultant havingresponsibility as the “Engineer” in the works contracts.
Done
26 Criteria for nominating procurement committeesestablished by MPW. Each Project ImplementationUnit includes a specified procurement officer andfinancial management officer.
Done
27 Procedures to maintain proper project andprocurement filing established by MPW, includingfiling of advertisements, bidding documents/requestfor proposals, clarifications/addenda to biddingdocument/request for proposals, minutes of bidopening, evaluation reports, contract award and finalcontract documents, and also for regular review ofaccounting reports, including all supportingdocuments (i.e. travel report, receipts, etc.).
Done
28 Regular interim audits conducted by third parties,which include review of procurement process andresults.
Done.
Sanc
tions
and
Rem
edie
s
29 Remedial actions and sanctions for cases of fraud andcorruption that are reported and for which evidence isfound established by MPW.
No cases of fraud and corruption have been encountered so far. Ifsuch case happened MPW will use remedial actions and sanctionsbased on GOI and Bank regulations.
30 Information regarding fraud, corruption, collusionand/or coercive practice cases (resulting in thetermination of the contract and possibly otherpenalties), where lessons are learned and funds areretrieved, widely disseminated.
It will be done if there are such cases.
31 Disbursement to any given contract/locationsuspended or stopped completely if cases ofcorruption not dealt with effectively.
It will be done if there are such cases.
Length Width
(Km) (m) Result ProjectCategory Comments Environmental Agency World Bank
AWP - 1
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung 36.8 6 CapacityExpansion
AMDAL (some doc withpackage No.1) A*)
sensitive areas/resident, landacquisition, steepsopes,slopes,sopt soil and riversand beach, abrasion
YES(Recommended 2012)
AMDAL YES NOLWB issued on 20November 2013
YES (Complete)
5 Sp. Rampa - Poriaha Sumatera Utara 9.7 6 CapacityExpansion
Under preparation DELH byconsultant B*)
slope stability, water quality, Runoff, bridges acces, continuedtraffic access & quarry problem.Need IPPKH for 1.59 Km atSta.12+525 to 13+950 (section 1)& Sta.15+025 to Sta.15+150)section 2.
YES(Recommended 2011) Not Required YES (Complete)
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 CapacityExpansion UKL&UPL B*)
one link,sensitive/steepsopes,slopes,sopt soil and rivers,squater on the street, resident,productive land
YES(Recommended 2011) Not Required YES (Complete)
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 CapacityExpansion UKL&UPL B*) resident, comersil areas, market
(pasar tumpah) geometric etcYES
(Recommended 2011) Not Required YES (Completed)
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 46.8 7 CapacityExpansion AMDAL A*)
Comersil areas, market, publicfacilities, Air pollution, trafficcongestion, market on street, soptsoil and rivers
YES(Recommended 2013)
AMDAL YES NOLWB issued 14
April 2014YES (Completed)
7 Indrapura - Tapan Sumatera Barat 19.5 7 CapacityExpansion AMDAL A*)
Sensitive forest areas, socialissues, slope stability, waterquality, waste management, airpollution, squater on ROW etc
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014YES (Complete)
12 Kambang - Indrapura Sumatera Barat 55.2 7 CapacityExpansion AMDAL A*)
Resident, productive land,Catcment areas,rivers, slopestability, squater on the street,land acquisition.
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014YES (Complete)
14 Painan -Kambang Sumatera Barat 31.5 7 CapacityExpansion AMDAL A*)
Sensitive forest areas, socialissues, slope stability, waterquality, waste managemnt,continued traffic access & quarryproblem
YES(Recommended 2014)
AMDAL YES NOLWB issued 8
Aug 2014YES (Complete)
Seblat - Ipuh including 34.5 6 CapacityExpansion AMDAL A*) YES (Complete)
Air Lalang & Air Guntung Bridge 64 m 6 Twin bridges
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 CapacityExpansion UKL&UPL B*)
sensitive areas/resident, landacquisition, steepsopes,slopes,sopt soil and rivers
YES(Recommended 2011) Not Required YES (Complete)
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 CapacityExpansion UKL&UPL B*) one link,sensitive/steep
sopes,slopes,sopt soil and riversYES
(Recommended 2011) Not Required YES (Complete)
APPENDIX N. 16
Intergration of EnvironmentalMitigation Into The DesignType
Environmental and Social Screening Report ApprovalNo. Package Loan Package Name PROVINSI
AMDAL YES NOLWB issued 8
Aug 2014
ENVIRONMENTAL SAFEGUARDS FOR WINRIP
As of 30 June 2017
sensitive areas/steepsopes,slopes,sopt soil and riversand beach, abrasion
YES(Recommended 2014)16 Bengkulu
APPENDIX No.17
No. Package Loan Package Name PROVINSI Contractor Road SafetyMeasurement
Awareness &Readiness to EMP
DocumentsAvailability Camp Cleanliness Labour
CampDisposal of Waste
(Sludges)Handling of
BitumenPollution Control
MeasuresVehicle
ManagementDisposal ofWastewater
Total ScoreObtained Rangking (%) Level Remarks
AWP - 1
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung PT.JACON 2 1 6 1 2 1 2 1 2 1 19 2
5 Sp. Rampa - Poriaha Sumatera Utara PT.NKE 2 2 6 2 2 2 2 2 2 2 24 3
13 Sp Rukis - Tj Kemuning Bengkulu Waskita Karya PT. 2 1 6 1 1 1 2 1 2 1 18 2
15 Sibolga - Bts Tap Sel Sumatera Utara PT.PP 1 1 6 1 1 1 2 1 2 1 17 2
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat PT.PP - PT.Statika 3 3 6 3 2 2 2 3 2 2 28 3
7 Indrapura - Tapan Sumatera Barat PT.Adhi Karya 1 1 6 2 2 1 2 2 2 1 21 2
12 Kambang - Indrapura Sumatera Barat PT. LMA 1 1 5 1 1 1 1 1 1 1 13 1
14 Painan -Kambang Sumatera Barat PT.YASA-Conbloc 2 1 6 1 2 1 2 1 2 1 18 2
Seblat - Ipuh including 2 2 6 1 2 1 2 1 2 1 19 2
Air Lalang & Air Guntung Bridge
20 Lubuk Alung - Sicincin Sumatera Barat 2 2 6 1 2 1 2 1 2 1 20 3
21 Lubuk Alung -Kurataji Sumatera Barat PT.Multi Structure 1 1 6 1 2 1 2 1 2 1 18 2
EMP Compliance on WINRIP (Jan to 30 June, 2017)
Contractor Performance on EMP
16 Bengkulu
Civil Work
APPENDIX No.18
Status as of 30 June 2017
Length Width
(Km) (m)
AWP - 1AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg.Tampak Lampung 36.8 6 X X NA - - - - - - - - -
The DSC conducted monitoring on environmental management by the contractor for April & May 2017 and not available for June 2017, The DSC report no inform about the oil & dieselfuel polution at base camp & how the contractor to manage the impact. No photograph for environmental management was conducted by the contractor in DSC environmental monitoringreport.
5 Sp. Rampa - Poriaha Sumatera Utara 9.7 6 X X X - - - - - - - - - The DSC conducted monitoring on environmental management by the contractor for April to June 2017. The DSC not inform about part of road segmen, along 1.59 Km in protected forest,Based on CTC monitoring, the blasting activity at 4 point on going, the contractor was prepare the storage for material blasting, land acquisition problem at started project.
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 X X NA - - - - - - - - - The DSC has been submit to CTC monitoring report on environmental management by the contractor for April and May 2017 while monitoring report for June 2017 not available. The DSC report not informfor the oil & diesel fuel polution at base camp & land acquisition progress on Kab.Kaur also utilities problem in Kab Kaur.
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 X X NA - - - - - - - - -The DSC has been submit the monitoring report on environmental management by the contractor for April to May 2017 & not available for June 2017, but the report not inform concerning existing roaddamage at Kel.Hajoran,Sibabangun, Pinangsori & Lumut and how the contractor being manage that impact. & no inform for the oil & diesel fuel polution at base camp utility & facility along project corridorsuch electricity (PLN), PDAM, community water network and land acquisition & road damage.
8 Bts. Kota Pariaman -Manggopoh Sumatera Barat 46.8 7 X X NA - - - - - - - - - The CTC not yet received the environmental monitoring report from DSC on April to May 2017 & not available for June 2017, The DSC environmental monitoring report not inform about the utilities
& facilities also land acquisition causing impact to civil work. No photograph for environmental management was conducted by the contractor in DSC environmental monitoring report.
7 Indrapura - Tapan Sumatera Barat 19.5 7 X X NAThe CTC has been received the environmental monitoring report from DSC on April to May 2017 & not available for June 2017, The DSC environmental monitoring report not inform about theutilities & facilities also land acquisition causing impact to civil work. and flooding issues at Sta.08+525 and cow tract at Sta.10 to Sta.15. No photograph for environmental management wasconducted by the contractor in DSC environmental monitoring report.
12 Kambang - Indrapura Sumatera Barat 55.2 7 NA NA NA The CTC not yet received the environmental monitoring report from DSC on April to January 2017,
14 Painan -Kambang Sumatera Barat 31.5 7 X X NA - - - - - - - - - The CTC not yet received the environmental monitoring report from DSC for April to May 2017 & not available for June 2017, The DSC environmental monitoring report not inform about the utilities& facilities & oil & disel fuel polution at base camp.No photograph for environmental management was conducted by the contractor in DSC environmental monitoring report.
Seblat - Ipuh including 34.5 6
Air Lalang & Air Guntung Bridge 64 m 6
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 X X NA - - - - - - - - - The CTC not yet received the environmental monitoring report from DSC for April to May 2017 & not available for June 2017,The DSC environmental monitoring report not inform about the dieselfuel polution at base camp & side ditch issues at site construction.
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 X X NA - - - - - - - - - The CTC has been received the environmental monitoring report from DSC on April to May 2017 & not available for June 2017.The DSC environmental monitoring report not inform about the dieselfuel polution at base camp & side ditch issues at site construction.
STATUS OF MONITORING OF ENVIRONMENTAL MITIGATION ON WINRIP YEAR 2017
Note : X = Available
PAKET WINRIP, IBRD LOAN NO. 8043-ID STATUS DAN JADWAL PELAKSANAAN
No. Package Loan Package Name PROVINSI Oct Nov RemarksJan DecFeb Mar Apr
-The CTC has been received the environmental monitoring report from DSC on April to May 2017 & not available for June 2017, The DSC environmental monitoring report not inform about thediesel fuel polution at base camp also road sign at construction site was conducted by the contractor. No photograph for environmental management was conducted by the contractor in DSCenvironmental monitoring report.
Jun Jul Aug Sep
-- - - - -- -
May
16 Bengkulu X X NA
Appendix 18 Evaluasi kinerja DSC in Env Mon Quarter April To June 2017ok1_D60DC9
Status 31 July 2017
Length Width Remedial Action
(Km) (m) DocRequirement Environmental Screening Status Status Civil work Status Remarks Status Remarks Status Remarks Status Remarks
5 Sp. Rampa - Poriaha 11.1 6 UKL/UPL
Protected forest, slopestability, water quality, Runoff, bridges acces,continued traffic access &quarry problem
Complete Balai I2011
Complete,NOL WB on 30June 2016
Construction OK The report submitto PMU 11 Nov 14 OK
Submit to PMU &WB period 2)
Jan 2017OK
Complete (28 Jan 2016)the HIV-report submit toPMU on 28 Feb 2016 &WB 15 March 2016
OK
Submit to PMU, periodJuly - Sep 2016 on Nov28, 2016, period Oct -Dec 2016 (informallyWB) on 15 March 2017.Period Jan to March2017 WB on 9 June2017
ENVIRONMENTAL : a) Quarry, AMP & Stone Crusher permits from Bupati wascomplete (extend licensing until Dec 2017/the quarry permits was availablebefore new law issued). b) Part of link, along 1.59 Km in protected forest, basedon PP No.27 year 2012 the contractor can't work at link of 1.59 Km in protectedforest. The BBPJN II under preparation for administration & technicalrequirement for IPPKH & there is 7 houses & utilitas (electric poles) will beaffected at Start project ± (Sta.0 + 000 - Sta. 1+ 000). in Sp. Rampa village.c)The contractor has been immediatelly stop the road works at Sta. 12+525 -Sta.13+950 & Sta.15+025-Sta.15+150 as the WB request. CTC finding the AMPthat no oil, diesel and asphalt spills found at base camp, rain drainage & fuelstorage available at base camp & the peoples surrounding base camp notdisturbed by base camp activities.
7 Indrapura - Tapan 19.5 7 AMDAL
Sensitive areas, socialissues, slope stability,water quality, wastemanagement, airpollution,squater on ROWetc
CompleteEnvironmentalpermits Feb 2014,NOL 8 Aug 2014
Complete, hasbeen submit toPMU 27 Feb2017 & WB onMarch 17
Construction OKThe report submitto PMU on 2 Dec
2015OK Submit to PMU &
WB on Feb 2017 OK
Complete (6 Sep 2016)the HIV-report submit toPMU on 29 Sep 2016 &WB (informally, 30 Sep2016)
OK
Period Oct to Dec2016, Informal submit toWB on 15 March 2017.Period Jan to March2017 submit to WB on 9June 2017
ENVIRONMENTAL; a) The project under construction, b) The AMP & stonecrusher & Quarry permits complete, Inadequate traffic sign on constructionsite,c) Flooding on 3 (three poin arround Sta.08+500), drainage issues, d) cowsign is needed Sta.15 - Sta.20, d) is needed embankment for some houses wasaffected by project end project (pasar Tapan). The contractor has been providethe box culvert at Sta.8 + 500 & u ditch at Km PDG 197 BLS 46 to handleflooding at site and surrounding. Misi WB finding that drums containingchemicals with no labels were stored in an open area, on the ground and nosecondary containment & poor housekeeping & the contractor not yet done forimprovement.
8 Bts. Kota Pariaman -Manggopoh 46.8 7 AMDAL
Comersil areas, market,public facilities, Airpollution, traffic congestion,market on street, soft soiland rivers
CompleteEnvironmentalpermits Juli 2013,NOL 14 April 2014
Complete, hasbeen submit toPMU 2 Nov2016/WB
Construction OKThe report submitto PMU on 6 Oct
2015OK
Submit to PMU28 Sep 2016 &
WB 13 Oct 2016OK
Complete (4 Oct 2016)the HIV-report will besubmit to PMU & WB 13Oct 2016.
OK
Submit to PMU, periodJuly - Sep 2016 on 14Nov 2016, period Oct -Dec 2016 submit to WBon 15 March 2017. Janto March 2017, submitto WB on 9 June 2017
ENVIRONMENTAL; a) The project under construction, based on CTC site fieldfinding that the base camp enough clean because power from PLN for operateAMP & base camp, the civil work has been base AC along 7 Km & excavationshoulder on some segment. The quarry & base camp permits (Governor)available. Two houses on ROW has been moved & the utilities under moving.Fuel drainage on soil without concrete cement & mixed with rain drainage.
12 Kambang - Indrapura 55.2 6 AMDAL
Resident, productive land,Catcment areas,rivers,slope stability, squater onthe street, land acquisition.
CompleteEnvironmentalpermits Feb 2014,NOL 8 Aug 2014
Complete, hasbeen submit toPMU 27 Feb2017 onprocess submitto WB
Construction OK The report submitto PMU on 2 Dec 15 OK Submit to PMU &
WB on Feb 2017 OK
Complete (6 Sep 2016)the HIV-report submit toPMU on 29 Sep 2016 &WB (informally, 30 Sep2016)
OK
Oct to Dec 2016Informal submit to WBon 15 March 17,PeriodJan to March 2017,submit to WB on 9 June2017
ENVIRONMENTAL; a) The project under construction, b) Air pollution issuesdisturbing the community surrounding project & the contractor no carried outwater sprayeng on site, c) Roads existing damage, d) civil work only in 1 poinSta.48, d) No traffic signs along the link project, d) only some workers who usehelmets, vests and boots, e) Misi WB finding: oil & diesel fuel pollusi at basecamp, poor house keeping, air pollution (asphalt smoke to office),Hydrocarbonlayers were observed in the dust collector effluent pit and contaminated soil wasclearly observed nearby the pit, likely due to the overflow and no properdrainage. Water from the pit went to the soil ditch and ultimately to the soil pitprior to discharge to the environment. Water contaminated with hydrocarbonwas also seen in the soil pit., the contractor partially done for base campimprovement.
13 Sp. Rukis - Tj.Kemuning 56.3 7 UKL/UPL
one link,sensitive/ steepslopes,soft soil and rivers,squater on the street,resident, productive land.
Complete P2JN2011
Complete NOLWB 14 Dec2015
Construction OK The report submitto PMU on 6 Oct 15 OK
Submit to WBinformal 29 April2016 (period 2),
21 July 2016
OK
Complete (14 Jan 2016)the HIV-report submit toPMU on 12 Feb 2016 &WB 15 March 2016
OK
Period Oct-Dec 2016submit to WB on 15March 2017.Period Janto March 2017 submit toWB on 9 June 2017
ENVIRONMENTAL : a) Asphalt along 25 Km in Kab.Manna, then in Kab. Kaurunder construction on Sta.43 - Sta.56 is widening & side ditch work, while fromSta.26 to Sta.43 not yet started civil work because land acquisition issues. MisiWB finding: Leaking valve was observed in the fuel storage tank area anddrainage from storage tank was mixed with rainwater drainage & Ex-asphaltdrums were observed near the front gate, laid down on the ground and spots ofasphalt spill were noticeable also Drums containing chemicals were stored inopen area on the ground without concrete/secondary containment and withoutproper sign, the contractor partially done for base camp improvement.
14 Painan - Kambang 31.5 7 AMDAL
Sensitive areas, socialissues, slope stability,water quality, wastemanagemnt, continuedtraffic access
CompleteEnvironmentalpermits Feb 2014,NOL 8 Aug 2014
Complete, hasbeen submit toWB on 28 Feb2017
Construction OKThe report submitto PMU on 2 Dec
2015OK Submit to PMU &
WB on Feb 2017 OKComplete (6 Sep 2016)the HIV-report submit toPMU on 19 Sep 2016
OK
Period Oct to Dec 2016,Informal submit to WBon 15 March 2017.Period Jan to March2017, submit to WB on9 June 2017
ENVIRONMENTAL; a) The project under construction, b) Air pollution issues,c)Inadequate traffic signs, d) only some workers who use helmets, vests andboots, e) in most segments of the road adjacent to the sea needs to be fittedguadrail, f) oil & diesel fuel pollution at base camp. Quarry permits complete byGovernor & environmental permits for AMP. Stone crusher complete. Drumswithout labels were laid down near the diesel tank and placed directly on theground/without secondary containment; poor housekeeping, the contractor notyet done for the base camp improvement.
15 Sibolga - Bts.Tap Sel 36 7 UKL/UPL
resident, commersil areas,land acquisition/socialissues, Facility & utilitiesproblem, etc.
Complete Balai I2011
Complete, hasbeen submit toPMU/WB
Construction OK The report submitto PMU 11 Nov 14 OK Submit(period 2)
Jan 2017 OK
Complete (27 Jan 2016)the HIV-report submit toPMU on 28 Feb 2016 &WB 15 March 2016
OK
Period Oct to Dec2016, Informal submit toWB on 15 March 2017.Period Jan to March2017, submit to WB on9 June 2017
Environmental: a) Land acquisition problems, PAPs not agreed to release theirproperties, some squater not yet move, b) water pipes belonging was cross theroad pavement, shoulder widening and mortal, c) The Contractor has beenimplement the Health & road sapety aspect on project. d)There are puddles inbasecamp, the contractor should improve the layout stockpile storage onbasecamp, e). Misi WB finding: Although equipment and diesel storage tankwere located on the concrete floor, no drainage and secondary containmentwere observed. Consequently, puddles were visible in several areas. Drumwithout label and secondary containment was put on the ground Asphalt leftoverwere observed around the facility perimeter (outside the fence) also poor hoesekeeping. the contractor partially done for base camp improvement.
Pack.
No.Loan Package Name
Environmental Safeguard RKPPLMonitoring of Amdal/UKL-UPL/SPPL Integration in to
the Design
Monitoring of(Amdal/UKL-UPL/SPPL
implementation) to BLH,WB&PPK)
Monitoring of HIV-AIDs Campaignactivity
Monitoring of RKPPLimplementation
(Quarterly report)
APPENDIX 19 :'ENVIRONMENTAL STATUS & PROGRESS FOR WINRIP, IBRD LOAN NO.8043-ID
Length Width Remedial Action
(Km) (m) DocRequirement Environmental Screening Status Status Civil work Status Remarks Status Remarks Status Remarks Status Remarks
Pack.
No.Loan Package Name
Environmental Safeguard RKPPLMonitoring of Amdal/UKL-UPL/SPPL Integration in to
the Design
Monitoring of(Amdal/UKL-UPL/SPPL
implementation) to BLH,WB&PPK)
Monitoring of HIV-AIDs Campaignactivity
Monitoring of RKPPLimplementation
(Quarterly report)
Seblat - Ipuh including 34.5 6
Air Lalang & Air Guntung Bridge64 m 6
36.8 6
30 m 6
20 Lubuk Alung - Sicincin 14.6 7 UKL/UPLsensitive areas/resident,land acquisition, steepslopes,soft soil and rivers
Complete TLKJ2011
Complete,was submit toWB on 28 Feb2017.
Construction OKThe report submit to
PMU on 29 Oct2015
OK
Submit to PMUon 31 May 2017
& to WB on 9June 2017
OK
Complete (7 March 2017)Target the HIV-report willsubmit to PMU early ofApril 2017
OK
Period Oct to Dec2016, Informal submit toWB on 15 March 2017.Period Jan to March2017, submit to WB on9 June 2017
ENVIRONMENTAL; a) The project under construction. b) The permits for Quarrycomplete from Governor & AMP/Stone crusher under process in BLHKab.Pariaman. C) Utilities issues on commercial & residents areas, d) occurpuddle on pasar Lubuk Alung because inadequate drainage system & side ditchproblems on some segmen. Empty drums without label and hydrocarbon spillcould be observed in several working areas. the contractor not yet done for basecamp improvement.
21 Lubuk Alung - Kurajati 16.8 7 UKL/UPL one link,sensitive/steepslopes,soft soil and rivers
Complete TLKJ2011
Complete,was submit toWB on 28 Feb2017
Construction OK The report submit toPMU on 31 July 15 OK
Submit to PMUon 31 May 2017
& to WB on 9June 2017
OK
Complete (7 March 2017)Target the HIV-report willsubmit to PMU early ofApril 2017
OK
Period Oct to Dec2016, Informal submit toWB on 15 March 2017.Period Jan to March2017, submit to WB on9 June 2017
ENVIRONMENTAL; a) The project under construction. b) The permits forQuarry complete from Governor & AMP/Stone crusher buy to suplier LKMP. &permisions for AMP & Stone Crusher LMKP complete. . c) Railway & irigationchanel issues on Started project, d) Utilities issues on commercial & residentsareas, e) occur puddle on resident area because inadequate drainage system, f)only some workers who use helmets, vests and boots, g) there side ditchproblem on some segmen. The AMP & stone crusher from LMKP, the contractorby asphalt from the suplier/LMKP
Note:P Process
NA Not AvailableNY Not Yet
Done 15 May 2017
17 Sp.Gunung Kemala -Pg.Tampak AMDAL
CompleteEnvironmentalpermits 21 Nov2012, NOL WB 20Nov 2014
Complete,NOL WB onApril 2016
Construction OK The report submitto PMU 10 Dec 14
Complete (10 Nov2015)the HIV-report hasbeen submit to PMU on 8Jan 16 & WB 13 Jan 2016
sensitive areas/resident,land acquisition, steepslopes,soft soil and riversand beach abrasion
16 AMDALsensitive areas/steepslopes, soft soil and riversand beach abrasion
Construction
OK
Submit to WB(Period 1) 21
July 2016 (period2), 20 Nov 2016
OK
P OKOK The report submitto PMU 11 Dec 14
CompleteEnvironmentalpermits April 2014,NOL 8 Aug 2014
Complete,was submit toWB on 9 June2017.
ENVIRONMENTAL : a) The project on going construction, b) The license ofQuarry, AMP,Crusher complete from Governor, The crusher & AMP has beenoperate, the civil work on going widening until 9 Km, land acquisition finish butsome utilities need to moving. Oil & Diesel spilles & poor house keeping on basecamp.the contractor partially done for base camp improvement.
Underpreparation OK
Period Jan to March2017 submit to PMU on31 May 2017, submit toWB on 9 June 2017
ENVIRONMENTAL: a).the PAPs were unpacking building, excavation and soilembankment activities ongoing, electricity pole/tiang listrik under moving byPLN, shoulder widening ongoing, errosion in basecamp site, Oil & grease inBase camp not yet fulfill manage, part of link was soil errosion, inadequatetraffic sign around construction site, Quarry & The AMP & Stone Crusher permitswas complete, d) the quarry owner has been manage the quarry as UKL&UPLrecommendation. Drums without labels were laid down in working areas, somewere placed directly on the ground/without secondary containment; poorhousekeeping & Oil Spill on the ground. the contractor partially done for basecamp improvement.
OK
Period Oct to Dec2016, Informal submit toWB on 15 March 2017.Period Jan to March2017, submit to WB on9 June 2017
(Km) (m) (m2) Rp/m2 (m2) Rp/m2 (m2) Rp/m2 (m) Rp/m (m2) Rp/m2 (m2) Rp/m2 (m2) Rp/m2 Rod Rp/rod
AWP - 1
1 Krui - Bha Lampung 25 7 Widening 2,815 2011 28,763 882 0 2,445 0 0 0 653 12/15 2,815 28,763 50,000 882 500,000 0 2,445 80,000 0 0 0 653 50,000
Pdg Sawah - Sp Empat 40.9 7 Widening 422 2011 Not LA 2,110 0 342 0 0 0 873 2012 431 Not LA 2,110 0 342 100,000 0 0 0 873 50,000
Including Air Gadang Bridge 100 m 7 New 11 2011 2,402 410 0 0 0 0 0 72 12/15 11 2,048 50,000 410 700,000 0 0 0 0 0 74 60,000
3 Manggopoh - Pdg Sawah West
Sumatera32 7 Widening 1,338 2011 Not LA 668 0 15 0 1,421 661 5,324 2012 1,338 Not LA 668 700,000 0 0 0 1,421 120,000 661 200,000 5324 60,000
4 Ipuh - Bantal Bengkulu 42.4 7 Widening 257 2011 Not LA 307 673 504 9 2,632 7 (tomb) 82 13/14 257 Not LA 307 250,000 673 400,000 504 85,000 9 75,000 2,632 100,000 7 tomb 1,8 M 82 50,000
AWP - 2 dan AWP - 3
17 Sp.Gunung Kemala - Pg. Tampak Lampung 36.8 6 Widening 2,521 2013 219,367 2,269 83,462 0 0 0 34,601 4,930 15/16 2,507 218,149 375,000 1,747 500,000 64,266 250,000 412 110,000 486 75,000 2,214 100,000 34,601 100,000 4,930 69,700
5 Sp. Rampa - Poriaha North
Sumatera9.7 6 Widening 78 2016 271 7,689 2016 68 7,000
11 Bantal - Mukomuko Bengkulu 50.1 6 Widening 243 2013 Not LA 410 413 249 17 2,937 35 2 15/16 243 Not LA 278 500,000 228 400,000 97 300,000 54 275,000 1536 100,000 0 35 400,000
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 Widening 2,917 2013 103,217 2,196 0 1,575 0 0 0 363 15/16 2,471 87,435 250,000 1,585 400,000 1,396 350,000 8,954 315,000 207 325,000 2,203 100,000 668 2242 425000
6 Ps Pedati - Kerkap Bengkulu 20.9 7 Widening 637 2013 3,625 0 2,925 4,169 4,399 0 0 2015 637 3,613 221,000 684 203,300 1827 239,850 2,479 696,200 4291 157,000 165 451,000 138 135,000
19 Lais- Bintunan Bengkulu 10.8 7 Widening 538 2013 9,504 0 652 3,276 0 1,381 379 2014 538 6,113 110,500 34 650,000 897 425,000 2,269 310,000 134 115,000 124 300,000 257 125,000
15 Sibolga - Bts Tap Sel North
Sumatera36 7 Widening 2,003 2013 45,831 3,399 992 1,563 0 0 0 385 15/16 712 16,291 160,000 41 400,000 576 200,000 301 350,000 8 250,000 186 80,000
8 Bts. Kota Pariaman - Manggopoh West
Sumatera46.8 7 Widening 2,339 2014 Not LA 8,352 0 3,673 8,771 7,863 15/16 2,206 Not LA 97 850,000 160 400,000 826 100,000 843 85,000 520 120,000 404 450,000 7,395 150,000
10 Sp Empat - Sp Air Balam West
Sumatera61.7 7 Widening 2,915 2014 Not LA 11,523 0 2,613 0 11,538 4,369 2015 1,725 1,565 850,000 1,656 400,000 703 100,000 9 275,000 190 120,000 3,446 150,000
7 Indrapura - Tapan West
Sumatera19.5 7 Widening 891 2014 Not LA 746 2,191 2,130 636 2,109 115 1,172 15/16 840 263 285,000 1,117 378,000 988 150,000 438 225,000 210 122,000 245 150,000
12 Kambang - Indrapura West
Sumatera55.2 7 Widening 2,992 2014 Not LA 2,057 0 32,741 0 17,144 3,225 15/16 1,196 612 295,000 965 410,000 1718 175,000 60 390,000 829 125,000 56 210,000
14 Painan -Kambang West
Sumatera31.5 7 Widening 2,589 2014 Not LA 10,474 0 21,735 0 20,988 0 1,044 15/16 1,268 340 800,000 276 450,000 140 210,000 48 405,000 56 135,000 458 215,000
Seblat - Ipuh including 34.5 6 Widening 254 2013 0 658 98 232 0 0 0 33 15/16 254 275 480,000 491 198,000 134 396,000 968 209,000 459 330,000
Air Lalang & Air Guntung Bridge 64 m 6 New 5 10,280 5 10,280 0
20 Lubuk Alung - Sicincin West
Sumatera14.6 7 Widening 1,070 2014 Not LA 528 0 294 0 0
2600 m(canal)
15/16 977 997 900,000 1,380 450,000 2,614 150,000 661 285,000 1,395 130,000 4,711 150,000
21 Lubuk Alung -Kurataji West
Sumatera16.8 7 Widening 929 2014 Not LA 361 0 284 0 0
433 m(canal)
0 15/16 882 460 950,000 1,053 465,000 468 160,000 80 283,000 1,398 135,000 222 110,000 2,493 155,000
18 Mukomuko - Bts. Sumbar (replacedto Sibolga - Sorkam)
Bengkulu 25.8 6 Widening NA
9 Rantau Tijang - Kota Agung (replacedto Biha - Bengkunat)
Lampung 42 7 Widening NA
As June 30, 2017
OthersHousehol
dYear Land (m2) House (m2)
Terrace(m2)
Fence(m)
Founda-tion (m) Pavement (m2) Others Trees
16 Bengkulu
PackageNumber
Package Province
2 West
Sumatera
Trees
Appendix No. 20A. Western Indonesia National Roads Improvement Projet Summary of Land Acquisition for WINRIP Packages Based on LARAP
Compensation
Household
Land House BuildingType
Length Width
Year
Terrace Fence Foundation Pavement
Land Acquistion Plan
AWP - 11 Krui - Bha Lampung 28,763 28,763 0 100.0
Padang Sawah - Sp Empat 13,352 0 13,352 0 Including Air Gadang Bridge 2,048 2,048 0 100.0
3 Manggopoh - Padang Sawah Sumatera Barat Not LA4 Ipuh- Bantal Bengkulu Not LA
AWP - 2 and AWP - 317 Sp.Gunung Kemala - Pg. Tampak Lampung 219,367 218,149 1,218 99.445 Sp. Rampa - Poriaha Sumatera Utara 94,700 86,700 8,000 91.55
11 Bantal - Mukomuko Bengkulu Not LA13 Sp Rukis - Tj Kemuning Bengkulu 103,217 87,435 15,782 84.76 Ps Pedati - Kerkap Bengkulu 3,625 3,625 0 100.0
19 Lais- Bintunan Bengkulu 9,505 9,505 0 100.015 Sibolga - Bts Tap Sel Sumatera Utara 25,752 16,291 9,461 63.38 Bts. Kota Pariaman - Manggopoh Sumatera Barat Not LA
10 Sp Empat - Sp Air Balam Sumatera Barat Not LA7 Indrapura - Tapan Sumatera Barat Not LA
12 Kambang - Indrapura Sumatera Barat Not LA14 Painan -Kambang Sumatera Barat Not LA
Seblat - Ipuh including Not LA Air Lalang & Air Guntung Bridge 10,280 10,280 0 100.0
20 Lubuk Alung - Sicincin Sumatera Barat Not LA21 Lubuk Alung -Kurataji Sumatera Barat Not LA
18 Mukomuko - Bts. Sumbar (DELETE) Bengkulu DELETE
9 Rantau Tijang - Kota Agung (DELETE) Lampung DELETE
16 Bengkulu
Total Area tobe Acquired
(m2)
TotalAcquired
(m2)
PackageNumber
Package Province
Appendix No 20. Western Indonesia National Roads Improvement Projet Overall Land Acquisition Status as June 30, 2017
Total Area to beAcquired through
LA Act (underprocess)
Progress(%)
2 Sumatera Barat
2017 Semestral (Mid-Term) Project Report 1st Semester : Jan-Jun 2017
1
Appendix 21.SOCIAL SAFEGUARSD, STATUS OF DISCLOSURE, AND PROGRESS OF LARAP IMPLEMENTATION
Jun 30, 2017
No Package Document PAP and Affected Land &Assets WB Approval Disclosure of
Document
Budget2015
(million)Pending Issue
Progress of LARAP ImplementationRemarks
Validation(inventory)
Public/Socializ
HireAppraisal
AppraisalResult Negotiation Payment Collecting
1 Krui - Bha LARAP Total PAP 2,815. AffectedLand: 28,763.12 M2; Assetaffected: building 882.13M2; Fence 2,445.41 M;Plant: 653 rod; paddy field25 plots; Social & PublicFacilities
Jan 04, 2013 Complete Certification process of thePAP being resolved byProject
complete complete complete complete complete complete NY
2 Padang Sawah -Sp Empat
LARAP Total PAP 454 . AffectedLand: . Affected Asset:building 149 unit = 2,110M2; Fence 2 unit = 341.8 M;Kiosks BBM: 25 unit; Plant:873 rod; Mosque: 2 unit
Jan 13, 2013 Complete complete Complete complete complete complete complete complete NY
2a Including AirGadang Bridge
Total PAP 12. AffectedLand: 2,110 M2; affectedasset: building 6 unit = 410M2; Plant 72 rod.
3 Manggopoh -Padang Sawah
LARAP Total PAP 1,338 .NoAffected Land . Affectedasset: building 115 unit =668.33 M2; Culvert 661.05m; concrete & foundations1,421.60 M3; Soilembankment 5,564.21 M3;Plant 5.324 rod
Jan 04, 2013 Complete Complete complete complete complete complete complete complete complete
4 Ipuh- Bantal LARAP Total PAP are change from217 PAP becomes 257 PAP.257 PAP has receivedcompensation from The LG.Asset affected: buildinghouse = 307.05 M2; terace =672.84 M2; Fence = 503.85M; foundation = 8.9 m;pavement = 2,632.01 M2;Plant 82 rod, tomb = 7 unit
Dec 10, 2012 Complete Complete complete complete complete complete complete complete complete
5 Sp. Rampa -Poriaha
AdditionalLARAP
78 PAP with affected asset:State land: 4.47 Ha,building: 271 m2, 7689trees.
NY NY 2.7Billion
Remedial action is underpayment process
Revision LARAP underchecked by Satker PJN II
complete complete complete complete complete NY NY
6 Ps Pedati - Kerkap LARAP Total PAP = 637. Affectedland = 3,625 M2. Terrace =2,925 M2; Fence = 4.169 M,floor = 4,399 m2.
Nov 20, 2013 Complete Complete Certification of the 136 PAPs
not yet
complete complete complete complete complete complete complete Certification ofthe 136 PAPswill be resolvedby Project on FY2017
2017 Semestral (Mid-Term) Project Report 1st Semester : Jan-Jun 2017
2
No Package Document PAP and Affected Land &Assets WB Approval Disclosure of
Document
Budget2015
(million)Pending Issue
Progress of LARAP ImplementationRemarks
Validation(inventory)
Public/Socializ
HireAppraisal
AppraisalResult Negotiation Payment Collecting
7 Indrapura - Tapan LARAP Total PAP 891. Partillyaffected building (housesand kiosks) = 4,013 M2 :Affected fence = 19,206 m;Partially affected otherbuilding (terrace, deckerand floors) = 9,401 M2 andtrees = 3,290.FY 2017: 0.5 Billion
Oct 14, 2014 complete APBN2016/2017
The remaining 38 from total891 PAP is under paymentprocess
complete complete complete complete complete Paymentfor 753
from total891 PAPalready
paid
238 PAPis underprocess
Compensationpayment for theremaining of 38APs will becompleted onFY 2017
8 Bts. KotaPariaman -Manggopoh
LARAP Total PAP 2.339. Partillyaffected building ( housesan kiosks) = 8,352 M2 :Affected fence = 3,673 m;Partially affected otherbuilding (terrace, deckerand floors) = 8,771 M2 andtrees = 7,863.FY 2017: 1.5 Billion
Aug 12, 2014 Complete APBDProvSumbar2015 andAPBN2015/16/17
The remaining 133 PAP is underpayment process
complete complete complete complete complete Paymentfor 2.206from total2.339 PAP
alreadypaid
NY Compensationpayment for theremaining of133 APs will becompleted onFY 2017
9 Rantau Tijang -Kota Agung
LARAP LARAP not yet available (BALAInot yet compose LARAPDocument)
Replace withBengkunat Bihain LampungProvince
10 Sp Empat - Sp AirBalam
LARAP Total PAP 2.915. Partillyaffected building ( housesan kiosks) = 11,523 M2 :Affected fence = 2,613 m :Partially affected otherbuilding (terrace, deckerand floors) = 11,538 M2 andtrees = 4,369.APBN for 8, 10, 20, 21: 70Billion
Aug 12, 2014 Complete APBDProvSumbar2015 andAPBN2015/16
The remaining 1.190 PAP isunder payment process
complete complete complete complete complete 1.725 PAPalreadybe paid
NY Compensationpayment for theremaining of1.190 APs willbe completedon FY 2017
11 Bantal -Mukomuko
LARAP Total PAP 262 . No affectedland. House building =261.7 M2; kiosks = 147.7m2, terrace = 412.9 m2,Fence = 249 M; Plant 36rod; foundation = 17.2 m2;retaining wall = 35.1 m;pavement = 2,937 m2;
Nov 20, 2013 Complete APBN2015
Complete complete complete complete complete complete Complete Complete
12 Kambang -Indrapura
LARAP Total PAP 2,889. Partillyaffected building ( housesan kiosks) = 2,057 M2 :Affected fence = 32,741 m;Partially affected otherbuilding (terrace, deckerand floors) = 17,144 M2 andtrees = 3,225.APBN for 7, 12, 14: 31 Bill
Oct 14, 2014 Complete APBN2016/2017
The remaining 1.648 PAP isunder payment process
complete complete complete complete complete 1.196 PAPalreadybe paid
427 PAPis underprocess
Compensationpayment for theremaining 1.648PAPs will bepaid on FY2017:16 Billion
2017 Semestral (Mid-Term) Project Report 1st Semester : Jan-Jun 2017
3
No Package Document PAP and Affected Land &Assets WB Approval Disclosure of
Document
Budget2015
(million)Pending Issue
Progress of LARAP ImplementationRemarks
Validation(inventory)
Public/Socializ
HireAppraisal
AppraisalResult Negotiation Payment Collecting
13 Sp Rukis - TjKemuning
LARAP Total PAP: 2.917. Affectedland = 88,852 M2. Asetaffected: building 111 unit =2,196 M2 ; Fence 127 unit =1,575 M ; Plant 363 rod ;electricity pole 25 unit
Nov 20, 2013 Complete APBN2015/16/17
The remaining 384 PAP isunder payment process
complete complete complete complete complete 2,533PAPs
alreadypaid
354 PAPalready
collected
Compensationpayment for theremaining 384PAPs will bepaid on FY 2017
14 Painan -Kambang(1 doc Amdal)
LARAP Total PAP 2.589. Partillyaffected building ( housesan kiosks) = 10,474 M2 :Affected fence 21,735m :Partially affected otherbuilding (terrace, deckerand floors) = 20,988 M2 andtrees = 10,442.APBN for 7, 12, 14: 31 Bill
Dec 19, 2014 Complete APBN2016/2017
The remaining 324 PAP is underpayment process
complete complete Complete complete process 1.268 PAPalreadybe paid
881 PAPalready
collected
Compensationpayment for theremaining 1.343PAPs will bepaid on FY2017:4.5 Billion
15 Sibolga - Bts TapSel
LARAP Total PAP 2.003 . Landaffected 1,531 plot =45,831M2. Aset affected :building 340 unit = 3,399M2 ; Fence 12 unit = 1,563M ; Plant 385 rod, Terrace= 991,607 M2
Feb 05, 2014 Complete APBN2015/16/17
The remaining 1,117 PAP isunder payment process
complete complete complete complete complete 886 PAPsalready
paid
184 PAPis underprocess
Compensationpayment for theremaining 1,117PAPs will bepaid on FY2017: 9.29Billion
16 Seblat - Ipuh SimpleLARAP
Total PAP 259 . Affectedland = 4,124 M2. Asetaffected : building 40 unit =533 M2 ; Fence 34 unit =384 M ; Plant 51 rod ;electricity pole 5 unitBudget: 4.47 Billion
Nov 20, 2013 Complete APBN2015
Complete complete complete complete complete complete complete complete complete
Air Lalang & AirGuntung Bridge
UpdatedLARAP
June 7, 2016 Complete APBN2016
Complete complete complete complete complete complete complete complete complete
17 Sp.Gunung Kemala- Pg. Tampak
LARAP Total PAP 2,620 . Landaffected = 194,278 M2.Aset affected : building 440unit = 4,557 M2 ; Plant4,267 rod ; paddy field48,602 clumps.
Sep 16, 2013 Complete APBN2015/2016/2017
The remaining 99 PAP is underpayment processCertification of the 1850 PAPsbeing resolved by Project
complete complete complete complete complete 2,521PAPs
alreadypaid
Compensationpayment for theremaining 99PAPs will bepaid on FY 2017
18 Mukomuko - Bts.Sumbar
LARAP LARAP will provided BBPJN III Replace withSibolga –Sorkam in NorthSumateraProvince
19 Lais- Bintunan LARAP Total PAP 538. Landaffected = 10,733 M2. Asetaffected : floor = 1,381 M2
; Terrace: 652 M2, Fence =3,276 M ; Tomb = 18 units,Plant 379 rod ; utilities 14unit
Nov 20, 2013 Complete APBN2015
Complete complete complete complete complete complete complete complete
2017 Semestral (Mid-Term) Project Report 1st Semester : Jan-Jun 2017
4
No Package Document PAP and Affected Land &Assets WB Approval Disclosure of
Document
Budget2015
(million)Pending Issue
Progress of LARAP ImplementationRemarks
Validation(inventory)
Public/Socializ
HireAppraisal
AppraisalResult Negotiation Payment Collecting
20 Lubuk Alung -Sicincin
LARAP Total PAP: 1,070, Affectedland: 46,579 m2, PT KAIAffected land: 682 m2,Partilly affected building(houses and kiosks) =528m2 Affected fence =294m Irrigation channal:2.600m.APBN for 8, 10, 20, 21: 70Billion
Dec 19, 2014 Complete APBN2016/2017
The remaining 63 PAP is underpayment process
complete complete complete complete complete 1007 PAPalreadypaid
57 PAP isunder
process
Compensationpayment for the
remaining 63PAPs will bepaid on FY
2017: 2 Billion
21 Lubuk Alung -Kuraitaji
LARAP Total PAP: 929, Affectedland: 40,612 m2, Partillyaffected building (housesand kiosks) = 360.9m2
Affected fence = 284mIrrigation channal: 433m.APBN for 8, 10, 20, 21: 70Billion
Dec 19, 2014 Complete APBN2016/2017
The remaining 29 PAP is underpayment process
complete complete complete complete complete 900 PAPalready
paid
49 PAP isunder
process
Compensationpayment for the
remaining 29PAPs will bepaid on FY
2017: 1.5 Billion
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 1
Appendix 22
LIST OF WORKSHOP/TRAINING IMPLEMENTATIONNo Workshop/Training Target Implementation Date
1 Procurement Training All Pokja related to WINRIP 1 – 2 November 2012
2Workshop of BidDocuments Evaluation
Balai II & III Pokja in 4 provinces related to
WINRIP
27 February – 1 March2013
3Project ManagementManual (PMM) UpdateMeeting
All stakeholders related toWINRIP 18 – 19 March 2014
4 World BankProcurement Guideline
PMU WINRIP Balai, Pokja, Satker, PPK in 4
provinces related to WINRIP23 – 24 April 2013
5 Training of RKPPL andTPM
Satker, PPK, Contractor,DSC,and TPM of Package No. 01(Krui – Biha)
5 – 6 June 2014
6Socialization of ProjectManagement Manual(PMM)
Balai, Satker, PPK, Contractor,and DSC related to Package No.01, 02, 03, and 04
12 – 14 June 2014
7 Training of RKPPL andTPM
Balai, Satker, PPK, Contractor,DSC and TPM related toPackage No. 02 (Pd. Sawah –Sp. Empat)
Balai, Satker, PPK, Contractor,DSC and TPM related toPackage No. 03 (Manggopoh –Pd. Sawah)
18 – 19 June 2015
8 Training of RKPPL andTPM
Balai, Satker, PPK, Contractor,DSC and TPM related toPackage No. 04 (Ipuh – Bantal)
7 – 8 July 2015
9Socialization of ProjectManagement Manual(PMM)
Balai, Satker, PPK, Contractor,and DSC related to Package No.01, 02, 03, and 04
10 – 11 September 2014
10 Training of InterimFinancial Report (IFR)
Financial staff of Satker ofPackage No. 01, 02, 03, and 04
26 – 27 November 2014
11 Training of InterimFinancial Report (IFR)
Financial staff of Satker ofPackage No. 05, 11, 13, 17 11 – 12 Februari 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 2
No Workshop/Training Target Implementation Date
12 Training of RKPPL andTPM
Balai, Satker, PPK, Contractor,DSC and TPM related toPackage No. 11 and 13
11 – 12 March 2015
13Socialization of ProjectManagement Manual(PMM)
Balai, Satker, PPK, Contractor,and DSC related to Package No.06, 11, 13, and 19
6 – 7 May 2015
14 Training of RKPPL andTPM
Balai, Satker, PPK, Contractor,DSC and TPM related toPackage No. 06 and 19
Balai, Satker, PPK, Contractor,and DSC related to Package No.17
4 – 5 June 2015
15 Training of InterimFinancial Report (IFR)
Financial staff of Satker ofPackage No. 06, 19, and 17
5 – 6 August 2015
16 Training of RKPPL Balai, Satker, PPK, Contractor,
and DSC related to Package No.05 and 15
7 – 8 October 2015
17 Training of TPM Balai, Satker, PPK, Contractor,
DSC and TPM related toPackage No. 05 and 15
9 October 2015
18 Training of TPM Balai, Satker, PPK, Contractor,
DSC and TPM related toPackage No. 17
22 October 2015
19 Socialization of HIV -Aids
Contractor and all workers inPackage No. 01 and 17,Lampung Province
10 November 2015
20 Socialization of HIV -Aids
Contractor and all workers inPackage No. 02 and 03, WestSumatera Province
17 November 2015
21Socialization of ProjectManagement Manual(PMM)
Balai, Satker, PPK, Contractor,and DSC related to Package No.05, 15, and 17
23 – 24 November 2015
22 Socialization of HIV -AIDS
Contractor and all workers inPackage No. 04, BengkuluProvince
4 December 2015
23 Socialization of HIV -AIDS
Contractor and all workers inPackage No. 11, BengkuluProvince
5 December 2015
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 3
No Workshop/Training Target Implementation Date
24 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 06, BengkuluProvince
12 January 2016
25 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 19, BengkuluProvince
13 January 2016
26 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 13, BengkuluProvince
14 January 2016
27 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 15, NorthSumatera Province
27 January 2016
28 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 05, NorthSumatera Province
28 January 2016
29 Training of InterimFinancial Report (IFR)
Financial staff of Satker/PPK ofPackage No. 07, 08, 10, and 12 April 12 – 13, 2016
30 Training of RKPPL
Balai, Satker, PPK, Contractor,and DSC (Field SupervisionTeam) related to Package No.07, 08, and 12
May 26 – 27, 2016
31 Training of TPM Balai, Satker, PPK, Contractor,
DSC and TPM related toPackage No. 07 and 08
9 June 2016
32 Training of InterimFinancial Report (IFR)
Financial staff of Satker fromPJN I and Satker PJN II andfinancial staf of PPK PackageNo. 05,15,14,20 and 21
July 20 -21, 2016
33Socialization of ProjectManagement Manual(PMM)
Balai, Satker, PPK, Contractor,and DSC related to Package No.07,12,08,14,20 and 21
29 – 30 Agustus 2016
34 Training of TPM Balai, Satker, PPK, Contractor,
DSC and TPM related toPackage No. 12 and 14
27 September 2016
35 Socialization of HIV –AIDS
Contractor and all workers inPackage No. 14, NorthSumatera Province
4 October, 2016
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 4
No Workshop/Training Target Implementation Date
36 Training of TPM Balai, Satker, PPK, Contractor,
DSC and TPM related toPackage No. 20 and 21
13 October 2016
37 Training of RKPPL
Balai, Satker, PPK, Contractor,and DSC (Field SupervisionTeam) related to Package No.14, 20 and 21
26 - 27 October, 2016
38 Workshop PraConstrustion
Package 07,12,14,20,21,16 and08 from Bengkulu Province
Kick Off Meeting “TechnicalAudit Package 07”
21 November, 2016
39 Training of RKPPL Balai,Satker,PPK,Contractor
and DSC (Field SupervisionTeam related to Package 16
18 – 19 January, 2017
40 Workshop PMM Stake holder of DirektorateGeneral Bina Marga 1 – 2 February, 2017
41 Socialization of HIV -AIDS
Contractor and all workers inPackage No. 8, North SumateraProvince
7 March 2017
42 Contractor and all workers in
Package No.20 and Package 21,North Sumatera Province
8 March 2017
43 Contractor and all workers inPackage No.16 Prov Bengkulu
15 – 16 May 2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Appendix 23
Project Development Objective Indicators
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Increase of AADT onproject road sections(all vehicle types)
Number Value 8,241 10,880 11,936 4,140 13,094 12,696 13,990 13,613 14,947
Date 31-Dec-2010
31-Dec-14
March2015
31-Dec-16 31-Dec-2017
Comments 2010 baselineis the simpleaverage of theAADT of the19 WINRIPsections (page41 of PAD)
Resultsfrom IRMS
Results fromstatic trafficcounts on 6links in 4provinces
Results fromIRMS (from 17packages)
2017 target calculated using the growthforecasts for four vehicle types on page 39 ofthe PAD, weighing them by the typical trafficcomposition from the 2010 Master Plan forArterial Road Network in Sumatra Island(motorcycles 54.9%, cars 24.6%, buses 2.7%and trucks 17.8%)
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for atypical car reduced byat least 5% on projectroads (base yearoperating cost:US$0.19/veh-km)
Percentage Value 0.00 n.a. 3.00 n.a. n.a. 5.00
Date 31-Dec-2010
31-Dec-14
10-Nov-15 9-Aug-1631-Dec-2017
CommentsTarget notassessedbecauseno workscompleted
Target notassessedbecause noworkscompleted
Vehicleoperating costswill beassessed atproject end
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for a
Percentage Value 0.00 n.a. 5.00 n.a. n.a. 8.00
Date 31-Dec- 31-Dec- 10-Nov-15 9-Aug-16 31-Dec-2017
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
typical bus reducedby at least 8% onproject roads (baseyear operating cost:US$0.35/veh-km)
2010 14
Comments Target notassessedbecauseno workscompleted
Target notassessedbecause noworkscompleted
Vehicleoperating costswill beassessed atproject end
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for atypical heavy truckreduced by 10% onproject roads (baseyear operating cost:US$0.65 veh-km)
Percentage Value 0.00 n.a. 7.00 n.a. n.a. 10.00
Date 31-Dec-2010
31-Dec-14
10-Nov-15 9-Aug-1631-Dec-2017
Comments Target notassessedbecauseno workscompleted
Target notassessedbecause noworkscompleted
Vehicleoperating costswill beassessed atproject end
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time for lightvehicles reduced by atleast 20% on projectroads (base yearspeed: 51 km/h)
Percentage Value 0.00 0.00 -15.29 5.00 3.7 18.20 20.00
Date 31-Dec-2010
31-Dec-13
31-Dec-14
10-Nov-15 31-Jan-1731-Dec-2017
Comments For 4ongoingworksonly
For 9ongoingworks only
Results fromsite survey(from 17packages)
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time for largebuses reduced by atleast 20% on projectroads (base year
Percentage Value 0.00 0.00 -19.57 5.00 -2.17 13.81 20.00
Date 31-Dec-2010
31-Dec-13
31-Dec-14
10-Nov-15 31-Jan-1731-Dec-2017
Comments Noavailable
For 4ongoing
For 9ongoing
Results fromsite survey
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
speed: 46 km/h) worksonly
works only (from 17packages)
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time for heavytrucks reduced by atleast 20% on projectroads (base yearspeed: 40 km/h)
Percentage Value 0.00 0.00 -17.50 5.00 -6.53 11.76 20.00
Date 31-Dec-2010
31-Dec-13
31-Dec-14
10-Nov-15 31-Jan-1731-Dec-2017
Comments For 4ongoingworksonly
For 9ongoingworks only
Results fromsite survey(from 17packages)
Intermediate Results Indicators
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Satisfactorycompletion of slopeprotection designs
Number
Value 0.00 0.00 0 3.00
Date 15-Dec-2015
15-Dec-2015
31-Jan-1731-Dec-2017
CommentsStudy incontractingphase
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Number of km ofimproved nationalroads in the projectregion as planned/Roads rehabilitated,Rural
Kilometers
Value 0.00 0.00 0 5 5.38 80 134.54 380 322 640.00
Date 31-Dec-2010
31-Dec-13
Dec-14 10-Nov-15 31-Jan-1731-Dec-2017
Comments Rev.Target
Rev.Target
Rev.Target
Rev. Target
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project
Indicator Name CoreUnit of
MeasureBaseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Number of meters ofimproved bridges
Meters
Value 0.00 0.00 0.00 0.00 0.00 48.00 0.00 96.00 100 160.00
Date 31-Dec-2010
31-Dec-13
0 10-Nov-15 31-Jan-1731-Dec-2017
Comments Rehabilitated,rural
Rev.Target
Rev.Target
Rev.Target
Rev. Target
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Satisfactorycompletion oftechnical audits for allroad projects ofcomponent 1
Percentage
Value 0.00 0.00 0.00 0.00 0.00 20.00 16.00 60.00 63.16 100.00
Date 31-Dec-2010
31-Dec-13
0 31-Jan-1731-Dec-2017
Comments Rev.Target
0 out of19
Rev.Target
3 out of 19Rev.Target
12 out 19;TFAC visit
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1(2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Satisfactorycompletion of roadsafety audits carriedout by CTC or TLKJ forall road projects ofcomponent 1
Percentage
Value 0.00 0.00 0 40 80 90 100 100 100 100.00
Date 31-Dec-2010
31-Dec-13
Dec-14 31-Jan-1731-Dec-2017
Comments 16 out of19
Rev.Target
19 out of 19Rev.Target
18 out of 18 forDetail Eng.Design
2017 Semestral Project Report 1st Semester : January-June 2017
Western Indonesia National Roads Improvement Project 1
Appendix 24Status of Legal Covenant
Loan AgreementReference Description of Covenants Due Status
Schedule 2,Section I.A.1.
The Borrower shall maintain until completion of the Project the existing SteeringCommittee, chaired by the Deputy for Infrastructure of Bappenas and consisting
of representatives of concerned ministries to guide the development of roadinfrastructure, traffic and transport
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.2.
The Borrower, through DGH, shall maintain until completion of the Project, thePMU with staffing and terms of reference satisfactory to the Borrower and the
Bank
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.3.
The Borrower, through DGH, shall ensure that Balai I shall be theImplementation Unit for Sub-Projects in North Sumatra Province, Balai II shallbe the Implementation Unit for Sub-Projects in West Sumatra Province, andBalai III shall be the Implementation Unit for Sub-Projects in Bengkulu and
Lampung Provinces
During the wholeduration of the
project Ongoing
Schedule 2,Section I.A.4.
The Borrower, through MPW, shall ensure that a Project Manager is appointedin each of the three Balais responsible for the overall management of the Sub-
Projects in each Province (Satker)
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.5.
The Borrower, through DGH, shall appoint that a Sub-Project Manager for eachSub-Project, to be responsible for the day-to-day implementation of each Sub-
Project (PPK)
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.6.
The Borrower, through DGH, shall ensure that the Sub-Project TechnicalSupervisor in the three Balais shall supervise overall technical quality of the
Sub-Projects (Head of Implementation)
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.7.
The Borrower, through DGH, shall ensure that the DOP and the ManagementUnit shall at all times during Project implementation be supported by a duly
qualified Core Team Consultants
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.8.
The Borrower, through DGH, shall ensure that the Project management Unitand each Project Implementation Unit shall at all times during Project
implementation be supported by a duly qualified Design and SupervisionConsultants
During the wholeduration of the
projectOngoing
Schedule 2,Section I.A.9. and
Schedule 2,Section I.B.3.
The Borrower, through DGH, shall ensure that and the Project ManagementUnit engage the services of capacity building under Part 3 of the Project in
accordance with terms of reference and a capacity building development planOngoing
Schedule 2,Section I.B.1.(a) –
(e)
The Borrower shall implement the Project in accordance with the ProjectManagement Manual and the Project Implementation Plan
During the wholeduration of the
projectOngoing
Schedule 2,Section I.B.2.b.(i)
DGH shall prepare and discuss with the Bank the detailed designs,procurement and construction schedule, supervision arrangements and final
cost estimates for WP2
No later than 90days after contract
signature withDSC
Delayed
Schedule 2,Section I.B.2.b.(ii)
DGH shall prepare and discuss with the Bank the detailed designs,procurement and construction schedule, supervision arrangements and final
cost estimates for WP3
No later than 180days after contract
signature withDSC
Delayed
Schedule 2,Section IV.B,(b).
For category 4 of the project, no withdrawal shall be made until: (i) the Borrowerhas declared a disaster, emergency or catastrophic event and (ii) the Bank and
the Borrower have entered into a written arrangementNot yet due
Schedule 2,Section I.B,5.
The Borrower shall at all times during Project implementation and thereafterensure that the annual budgets include sufficient funds for maintenance of the
road funded by the Project
During the wholeduration of the
projectNot yet due
Schedule 2,Section I.B,6.
The Borrower shall prepare a mid-term report, review it with the Bank and makethe report publically available After MTR Ongoing
Schedule 2,Section I.D
Each subproject and linked subproject shall be carried out in accordance withthe provisions of ESMF and LARAP. The Borrower shall report the status of
compliance as part of Project Reports
During the wholeduration of the
projectOngoing
Section 4.01 Bid documents of WP-1, PMM, PIP and PMU satisfactory to the Bank 14-Mar-2012 Complied