48
SUBSEA LIFTING OPERATIONS The different phases of a subsea lift from an offshore construction vessel 02/12/09 – Vidar Kupen

1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

Embed Size (px)

DESCRIPTION

Subsea business

Citation preview

Page 1: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

SUBSEA LIFTING OPERATIONS

The different phases of a subsea lift from an offshore construction vessel 02/12/09 – Vidar Kupen

Page 2: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

2Subsea Lifting Operations 2009

Preparations for offshore lifting- Structures, installation vessel and project specific requirements

- Engineering tools

- Available equipment / tools on vessel

Lifting offshore - Different phases of subsea lift- Seafastening

- Lift-off from deck

- Slewing / overboarding

- Through the splash zone

- Landing phase

- Recovery to deck

Summary

Contents

Page 3: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

3Subsea Lifting Operations 2009

Preparations for offshore liftingInstallation vessel, structures and project specific requirements

Engineering toolsAvailable equipment / tools on vessel

Page 4: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

4Subsea Lifting Operations 2009

Installation vessel - Skandi Arctic

Main DimensionsLength overall: 156.9 m

Breadth: 27.0 m

Depth to 1st deck: 12.0 m

Draft (design): 6.5 m

Draft (scantling): 8.5 m

Cranes400 Te box boom crane NOV

58 Te knuckle boom crane

Page 5: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

5Subsea Lifting Operations 2009

Structures - ManifoldMain dimensions L x B x H, 20.3 x 15.0 x 6.1 m

Weight 175 Te

Supported on circular mudmats

Large area roof hatches

Manifold at Skandi Arctic deck

Page 6: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

6Subsea Lifting Operations 2009

Main dimensions 9 off spools.

L and Z-shaped, pipe dimension 4”, 6” and 10”

Heavy terminations: Termination heads (2.5 Te) and SPEMs (5.0 Te)

Typical termination head

Typical SPEM

Structures - Spools

Spools at load-out quay

Page 7: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

7Subsea Lifting Operations 2009

Presence of drill rigWhen overboarding and landing spools

Operations inside 500m zone, no welding allowed

Positioning systems relative to drill rig when landing

Risk of reduced visibility when cementing wells

Landing inside existing structures, ROV to observe closely to avoid clash

Project specific requirements

Page 8: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

8Subsea Lifting Operations 2009

Preparations for offshore liftingInstallation vessel, structures and project specific requirements

Engineering toolsAvailable equipment / tools on vessel

Page 9: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

9Subsea Lifting Operations 2009

Engineering toolsIAF – Incident Analysis and Feedback:Database with records of incidents in recent projects (2002 onwards).

Consulted when starting new projects, in risk assessment, HAZOP etc.

“To avoid repeating costly mistakes, and to understand the reason for these mistakes. Its objective is to improve the quality of our work “

Page 10: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

10Subsea Lifting Operations 2009

Engineering toolsAutocad useful tool for:- Deck layouts, 3D models for complicated spool layouts

- Installation sketches

- Clearance to ship side / crane

- Lift radius vs crane capacity and hook height

Clash check & verification of hook height

Spool

Deck layout

Page 11: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

11Subsea Lifting Operations 2009

Engineering tools

Deck layout

Simulation of Marine Operations, SIMO:Installation analyses:

- Splash zone (slack slings, crane capacity)

- Crane tip motion (landing criteria)

Input:

- Vessel description

- Describe installed object (weight, buoyancy, CoG, slamming, drag, added mass)

- Environmental data

SIMO – Analysed submergence levels

Page 12: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

12Subsea Lifting Operations 2009

Engineering toolsSimulation of Marine Operations, SIMO:Output:

- Sling tension (time history or statistical)

- Crane tip motion (position, velocity & acceleration)

http://www.sintef.no/Home/Marine/MARINTEK/Software-developed-at-MARINTEK/SIMO/

SIMVIS – Visualisation of SIMO analysisStatistical representation of results

Page 13: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

13Subsea Lifting Operations 2009

Engineering toolsShip Manoeuvring Simulator Centre, SMSC: Simulation of lift using crane drivers from Skandi Arctic. Tool helpful for:

- Planning deck layout, positioning of bumpers, tagging towers and check for clashes

- Simulate operations. Videos used for familiarisation meetings, HAZOPs etc.

- Training for crane drivershttp://www.smsc.no/

SMSC – Skandi Arctic lifting spools SMSC – Control room “bridge”

Page 14: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

14Subsea Lifting Operations 2009

Engineering toolsShip Manoeuvring Simulator Centre, SMSC:

Page 15: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

15Subsea Lifting Operations 2009

Preparations for offshore liftingInstallation vessel, structures and project specific requirements

Engineering toolsAvailable equipment / tools on vessel

Page 16: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

16Subsea Lifting Operations 2009

Available equipment / tools on vesselEquipment available for controlling the load:Lift-off: Endless rope taglines (riggers)

In air: Tagging towers with winches +

Crane tugger winches

Landing: Guidewire winches + Clumpweight

Tagging Towers

Crane tugger winchesGuidewire winches

Page 17: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

17Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 18: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

18Subsea Lifting Operations 2009

Toolbox talkOperational personnel gathered to discuss:Installation procedure / work plan

Lift plan & rigging specifications drawing

Deck layout

Contingency operations

Experiences from load-out

Page 19: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

19Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 20: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

20Subsea Lifting Operations 2009

Seafastening / Mudmat interface:Curved steel plate to establish contact between mudmats and seafastening beams.

To be shimmed towards mudmat.

- Confirm seafastening design is acceptable

- No welding to mudmat / manifold

Seafastening - Manifold

Page 21: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

21Subsea Lifting Operations 2009

Spools at different elevations: Bumpers integrated in supports for spool ends, SPEM and termination head.

Flexible supports for spool piping

Cargo strops

Seafastening - Spools

Page 22: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

22Subsea Lifting Operations 2009

Spreader frame resting 4.0m above deck level: Bumpers integrated in supports.

Guiding spreader frame into position offshore.

Cargo strops for easy release and to re-establish seafastening

Seafastening - Spreader Frame

Page 23: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

23Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 24: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

24Subsea Lifting Operations 2009

Lift rigging, spool to spreader frameSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.

Pre-rigged slings on spools and spreader frame

ROV shackles for subsea release. ROV hooks not used due to potential of release during installation.

Page 25: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

25Subsea Lifting Operations 2009

Lift rigging, spreader frame to tuggersSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.

ROV hooks for subsea release and connection during recovery

Crane tuggers

Tagging towers

Page 26: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

26Subsea Lifting Operations 2009

Lift rigging, spreader frame to crane hookSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.

Lift slings inside spreader frame, hook lowered to deck level

Page 27: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

27Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 28: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

28Subsea Lifting Operations 2009

Lift-off from deckManifold: Crane tuggers – not to be used

Tagging tower winches – not installed

Control rotation of structure using endless rope taglines

Position crane hook above manifold lift-off location, recorded during mobilisation

Contingency – increase crane radius during overboarding to avoid clash with vessel in

case manifold start spinning.

Page 29: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

29Subsea Lifting Operations 2009

Lift-off from deckSpreader frame:Crane tugger bridle tensioned to control spreader frame

Lift against bumpers

Control spreader frame using crane tuggers and tagging towers

Position spreader frame above spool lift-off location, recorded during mobilisation

Page 30: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

30Subsea Lifting Operations 2009

Lift-off from deckSpool: Crane tugger bridle and tagging towers to control spreader frame

Endless rope taglines at spool ends (termination head and SPEM)

Limit movements to avoid clashing with supports & structures on deck

Page 31: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

31Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 32: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

32Subsea Lifting Operations 2009

Slewing / Overboarding

Clash check & verification of hook heightDeck layout

Manifold Installation, 175 Te No crane tuggers

No tagging towers

Taglines to control lift-off

Ballasting system prepared

Where? NOT above other subsea infrastructure

Page 33: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

33Subsea Lifting Operations 2009

Slewing / OverboardingSpool Installations58 Te spreader frame + approx 20 Te spool

2 off crane tuggers

3 off tagging towers

Taglines to control lift-off

Page 34: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

34Subsea Lifting Operations 2009

Slewing / Overboarding

Page 35: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

35Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 36: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

36Subsea Lifting Operations 2009

Splash zoneSlack slings or challenging crane capacity?Large crane radius and hydrodynamic loads -> Crane capacity

Buoyancy, drag, added mass & slamming -> Slack slings

Entrapped air, collapse of structural members

Page 37: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

37Subsea Lifting Operations 2009

Splash zoneDisconnect winch wiresLeave structure at -15m to allow water to flood structural members

Crane tugger wires and tagging towers are disconnected at -40m using ROV hooks.

Page 38: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

38Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 39: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

39Subsea Lifting Operations 2009

Landing - SpoolsPrepare landing area Open hatches for access

Install guideposts

Install guiding arrangement Establish guidewires

Apply correct tension in guidewires

Landing Land spool in supports

Continue lowering spreader frame

Release rigging

Page 40: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

40Subsea Lifting Operations 2009

Landing - ManifoldEstablish guiding arrangement Seabed indicators

Clumpweight to keep stable heading

Transponders and Gyro verify position heading

Digiquartz and Bullseye to verify after landing

Page 41: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

41Subsea Lifting Operations 2009

Different phases of offshore liftToolbox talkSeafastening

Lift riggingLift-off from deck

Slewing / OverboardingSplash zone

LandingRecovery

Page 42: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

42Subsea Lifting Operations 2009

RecoveryIn general recovery of installation aids Slings with excessive movements (all secured, shackles?)

Clumpweight, ROV basket, guideposts (loose items)

Spreader bar or spreader frame (control)

Contingency: Recovery of installed structure / spool

Deck layout & preparations

Crane capacity for recovery

Seafastening of recovered structure

Page 43: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

43Subsea Lifting Operations 2009

Recovery – Spreader FrameMeans to control spreader frame:ROV connect crane tugger winches and tagging tower winches at -15m depth.

Increase crane radius and tension up crane tugger bridle as spreader frame comes to surface

Ensure slow water exit, the spreader frame will be emptied for water.

Page 44: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

44Subsea Lifting Operations 2009

Landing in supports / disconnection of lift rigging Spreader frame resting against bumpers

Land spreader frame in supports

Seafasten spreader frame using cargo strops

Disconnect spool lift rigging

Recovery – Spreader Frame

Page 45: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

45Subsea Lifting Operations 2009

RecoveryDeck layout and preparationsDepending on the structure to be recovered and equipment available, prepare:

Bumpers

Grillage

Winch philosophy – avoid entanglement

Ballasting operations

Know all load details, footprint, weight, submerged weight, enclosed fluids

Assume loose items, stones / sand, entrapped water

Page 46: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

46Subsea Lifting Operations 2009

Summary

Page 47: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

47Subsea Lifting Operations 2009

SummaryImportant aspects when planning and executing offshore lifts: Deck layout, slewing path

Winches for controlling loads in air

Crane capacity curves, also for recovery (alarm settings)

Communication with offshore personnel

Learn from mobilisation (crane settings, ballasting requirements, load handling)

HSE – Plan to avoid working at height and under suspended loads

Plan for contingencies!

Page 48: 1 - The Different Phases of a Subsea Lift From an Offshore Construction Vessel - KTF 2009

48Subsea Lifting Operations 2009