Upload
harry1981
View
243
Download
3
Tags:
Embed Size (px)
DESCRIPTION
Subsea business
Citation preview
SUBSEA LIFTING OPERATIONS
The different phases of a subsea lift from an offshore construction vessel 02/12/09 – Vidar Kupen
2Subsea Lifting Operations 2009
Preparations for offshore lifting- Structures, installation vessel and project specific requirements
- Engineering tools
- Available equipment / tools on vessel
Lifting offshore - Different phases of subsea lift- Seafastening
- Lift-off from deck
- Slewing / overboarding
- Through the splash zone
- Landing phase
- Recovery to deck
Summary
Contents
3Subsea Lifting Operations 2009
Preparations for offshore liftingInstallation vessel, structures and project specific requirements
Engineering toolsAvailable equipment / tools on vessel
4Subsea Lifting Operations 2009
Installation vessel - Skandi Arctic
Main DimensionsLength overall: 156.9 m
Breadth: 27.0 m
Depth to 1st deck: 12.0 m
Draft (design): 6.5 m
Draft (scantling): 8.5 m
Cranes400 Te box boom crane NOV
58 Te knuckle boom crane
5Subsea Lifting Operations 2009
Structures - ManifoldMain dimensions L x B x H, 20.3 x 15.0 x 6.1 m
Weight 175 Te
Supported on circular mudmats
Large area roof hatches
Manifold at Skandi Arctic deck
6Subsea Lifting Operations 2009
Main dimensions 9 off spools.
L and Z-shaped, pipe dimension 4”, 6” and 10”
Heavy terminations: Termination heads (2.5 Te) and SPEMs (5.0 Te)
Typical termination head
Typical SPEM
Structures - Spools
Spools at load-out quay
7Subsea Lifting Operations 2009
Presence of drill rigWhen overboarding and landing spools
Operations inside 500m zone, no welding allowed
Positioning systems relative to drill rig when landing
Risk of reduced visibility when cementing wells
Landing inside existing structures, ROV to observe closely to avoid clash
Project specific requirements
8Subsea Lifting Operations 2009
Preparations for offshore liftingInstallation vessel, structures and project specific requirements
Engineering toolsAvailable equipment / tools on vessel
9Subsea Lifting Operations 2009
Engineering toolsIAF – Incident Analysis and Feedback:Database with records of incidents in recent projects (2002 onwards).
Consulted when starting new projects, in risk assessment, HAZOP etc.
“To avoid repeating costly mistakes, and to understand the reason for these mistakes. Its objective is to improve the quality of our work “
10Subsea Lifting Operations 2009
Engineering toolsAutocad useful tool for:- Deck layouts, 3D models for complicated spool layouts
- Installation sketches
- Clearance to ship side / crane
- Lift radius vs crane capacity and hook height
Clash check & verification of hook height
Spool
Deck layout
11Subsea Lifting Operations 2009
Engineering tools
Deck layout
Simulation of Marine Operations, SIMO:Installation analyses:
- Splash zone (slack slings, crane capacity)
- Crane tip motion (landing criteria)
Input:
- Vessel description
- Describe installed object (weight, buoyancy, CoG, slamming, drag, added mass)
- Environmental data
SIMO – Analysed submergence levels
12Subsea Lifting Operations 2009
Engineering toolsSimulation of Marine Operations, SIMO:Output:
- Sling tension (time history or statistical)
- Crane tip motion (position, velocity & acceleration)
http://www.sintef.no/Home/Marine/MARINTEK/Software-developed-at-MARINTEK/SIMO/
SIMVIS – Visualisation of SIMO analysisStatistical representation of results
13Subsea Lifting Operations 2009
Engineering toolsShip Manoeuvring Simulator Centre, SMSC: Simulation of lift using crane drivers from Skandi Arctic. Tool helpful for:
- Planning deck layout, positioning of bumpers, tagging towers and check for clashes
- Simulate operations. Videos used for familiarisation meetings, HAZOPs etc.
- Training for crane drivershttp://www.smsc.no/
SMSC – Skandi Arctic lifting spools SMSC – Control room “bridge”
14Subsea Lifting Operations 2009
Engineering toolsShip Manoeuvring Simulator Centre, SMSC:
15Subsea Lifting Operations 2009
Preparations for offshore liftingInstallation vessel, structures and project specific requirements
Engineering toolsAvailable equipment / tools on vessel
16Subsea Lifting Operations 2009
Available equipment / tools on vesselEquipment available for controlling the load:Lift-off: Endless rope taglines (riggers)
In air: Tagging towers with winches +
Crane tugger winches
Landing: Guidewire winches + Clumpweight
Tagging Towers
Crane tugger winchesGuidewire winches
17Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
18Subsea Lifting Operations 2009
Toolbox talkOperational personnel gathered to discuss:Installation procedure / work plan
Lift plan & rigging specifications drawing
Deck layout
Contingency operations
Experiences from load-out
19Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
20Subsea Lifting Operations 2009
Seafastening / Mudmat interface:Curved steel plate to establish contact between mudmats and seafastening beams.
To be shimmed towards mudmat.
- Confirm seafastening design is acceptable
- No welding to mudmat / manifold
Seafastening - Manifold
21Subsea Lifting Operations 2009
Spools at different elevations: Bumpers integrated in supports for spool ends, SPEM and termination head.
Flexible supports for spool piping
Cargo strops
Seafastening - Spools
22Subsea Lifting Operations 2009
Spreader frame resting 4.0m above deck level: Bumpers integrated in supports.
Guiding spreader frame into position offshore.
Cargo strops for easy release and to re-establish seafastening
Seafastening - Spreader Frame
23Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
24Subsea Lifting Operations 2009
Lift rigging, spool to spreader frameSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.
Pre-rigged slings on spools and spreader frame
ROV shackles for subsea release. ROV hooks not used due to potential of release during installation.
25Subsea Lifting Operations 2009
Lift rigging, spreader frame to tuggersSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.
ROV hooks for subsea release and connection during recovery
Crane tuggers
Tagging towers
26Subsea Lifting Operations 2009
Lift rigging, spreader frame to crane hookSafe connection from deck level: Spreader frame resting in supports, no personnel under suspended loads.
Lift slings inside spreader frame, hook lowered to deck level
27Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
28Subsea Lifting Operations 2009
Lift-off from deckManifold: Crane tuggers – not to be used
Tagging tower winches – not installed
Control rotation of structure using endless rope taglines
Position crane hook above manifold lift-off location, recorded during mobilisation
Contingency – increase crane radius during overboarding to avoid clash with vessel in
case manifold start spinning.
29Subsea Lifting Operations 2009
Lift-off from deckSpreader frame:Crane tugger bridle tensioned to control spreader frame
Lift against bumpers
Control spreader frame using crane tuggers and tagging towers
Position spreader frame above spool lift-off location, recorded during mobilisation
30Subsea Lifting Operations 2009
Lift-off from deckSpool: Crane tugger bridle and tagging towers to control spreader frame
Endless rope taglines at spool ends (termination head and SPEM)
Limit movements to avoid clashing with supports & structures on deck
31Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
32Subsea Lifting Operations 2009
Slewing / Overboarding
Clash check & verification of hook heightDeck layout
Manifold Installation, 175 Te No crane tuggers
No tagging towers
Taglines to control lift-off
Ballasting system prepared
Where? NOT above other subsea infrastructure
33Subsea Lifting Operations 2009
Slewing / OverboardingSpool Installations58 Te spreader frame + approx 20 Te spool
2 off crane tuggers
3 off tagging towers
Taglines to control lift-off
34Subsea Lifting Operations 2009
Slewing / Overboarding
35Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
36Subsea Lifting Operations 2009
Splash zoneSlack slings or challenging crane capacity?Large crane radius and hydrodynamic loads -> Crane capacity
Buoyancy, drag, added mass & slamming -> Slack slings
Entrapped air, collapse of structural members
37Subsea Lifting Operations 2009
Splash zoneDisconnect winch wiresLeave structure at -15m to allow water to flood structural members
Crane tugger wires and tagging towers are disconnected at -40m using ROV hooks.
38Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
39Subsea Lifting Operations 2009
Landing - SpoolsPrepare landing area Open hatches for access
Install guideposts
Install guiding arrangement Establish guidewires
Apply correct tension in guidewires
Landing Land spool in supports
Continue lowering spreader frame
Release rigging
40Subsea Lifting Operations 2009
Landing - ManifoldEstablish guiding arrangement Seabed indicators
Clumpweight to keep stable heading
Transponders and Gyro verify position heading
Digiquartz and Bullseye to verify after landing
41Subsea Lifting Operations 2009
Different phases of offshore liftToolbox talkSeafastening
Lift riggingLift-off from deck
Slewing / OverboardingSplash zone
LandingRecovery
42Subsea Lifting Operations 2009
RecoveryIn general recovery of installation aids Slings with excessive movements (all secured, shackles?)
Clumpweight, ROV basket, guideposts (loose items)
Spreader bar or spreader frame (control)
Contingency: Recovery of installed structure / spool
Deck layout & preparations
Crane capacity for recovery
Seafastening of recovered structure
43Subsea Lifting Operations 2009
Recovery – Spreader FrameMeans to control spreader frame:ROV connect crane tugger winches and tagging tower winches at -15m depth.
Increase crane radius and tension up crane tugger bridle as spreader frame comes to surface
Ensure slow water exit, the spreader frame will be emptied for water.
44Subsea Lifting Operations 2009
Landing in supports / disconnection of lift rigging Spreader frame resting against bumpers
Land spreader frame in supports
Seafasten spreader frame using cargo strops
Disconnect spool lift rigging
Recovery – Spreader Frame
45Subsea Lifting Operations 2009
RecoveryDeck layout and preparationsDepending on the structure to be recovered and equipment available, prepare:
Bumpers
Grillage
Winch philosophy – avoid entanglement
Ballasting operations
Know all load details, footprint, weight, submerged weight, enclosed fluids
Assume loose items, stones / sand, entrapped water
46Subsea Lifting Operations 2009
Summary
47Subsea Lifting Operations 2009
SummaryImportant aspects when planning and executing offshore lifts: Deck layout, slewing path
Winches for controlling loads in air
Crane capacity curves, also for recovery (alarm settings)
Communication with offshore personnel
Learn from mobilisation (crane settings, ballasting requirements, load handling)
HSE – Plan to avoid working at height and under suspended loads
Plan for contingencies!
48Subsea Lifting Operations 2009