Upload
digger797
View
216
Download
0
Embed Size (px)
Citation preview
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 1/42
“Moving Jack-Up Rigs, the MaerskDrilling Way – with Constant Care”
6. – 7. November 2012, Clarion Hotel Stavanger
Speaker: Towmaster Per Frederiksen
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 2/42
Maersk Drilling
Moving boundaries withinoffshore drilling
40 Years: 1972 – 2012
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 3/42
Maersk Drilling is a WorldwideOperator
NW Europe
5 Ultra Harsh Jack-ups
4 Harsh Jack-ups
Caspian Sea
1 Mid-water Semi
Korea (yard)
4 Ultra deepwater drill ships
US GoM
1 Ultra Deepwater Semi
Denmark – Copenhagen
3,300 employees (5,300 in EDC)
Egypt
1 Ultra Deepwater Semi
Egyptian Drilling Company(50/50 Joint Venture)
61 land and workover rigs
3 low spec jack-ups
2 Premium jack-ups
SE Asia2 Premium Jack-ups
Australia
1 Semi (management)
r ca
1 Ultra Deepwater Semi1 Ultra Harsh Jack-up
Venezuela
10 Drilling Barges
Singapore (yard)
3 Ultra Harsh Jack-ups
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 4/42
’ ’
Maersk Drilling Milestones
1972 1975 1976 1995 2003/2004 2007 2008
forms a joint
venture with EGPC
to establish
Egyptian Drilling
Company
established and
acquires their first
semi-sub, ZEPHYR I
first newbuilding,
MÆRSK EXPLORER,
was built; the
largest jack-up the
world had ever seen
jack-up rigs, the
sister rigs “MÆRSK
INNOVATOR” and
“MÆRSK
INSPIRER”, were
delivered
takes delivery of
MAERSK
COMPLETER, the
first rig in a
newbuilding
programme of 9
jack-ups and semi-
subs delivered from
2007 – 2010
enters the FPSO
market and changes
name to Maersk
Contractors
changes name and
splits into two
businesses; Maersk
Drilling and Maersk
FPSOs
2012 - We Invest in the Future
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 5/42
New units on order
DEEPWATER ADVANCED I, II, III & IV XL ENHANCED I, II & III
• Contract for four ultra deepwater drillships
• Option for two additional units
• Delivery in 2013 and 2014
• To be built at Samsung Heavy Industries
• Total investment approximately USD 2.6 billion
• Order for three high-spec, ultra harsh environment jack-ups
• Option for one additional unit
• Delivery in 2014 and 2015
• To be built at Keppel FELS in Singapore
• Total investment approximately USD 1.9 billion
We will grow our business by developing and expanding in the
high-end, harsh environment jack-up and ultra deepwater floater
segments
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 6/42
Maersk Drilling’s fleet26 drilling rigs, 7 new buildings and 1 unit on management contract
3 MSC CJ62-120/Hitachi
Delivered 1986 - 1993
Jack-ups
4 MSC CJ50-X100 MC
Delivered 2008 - 2009
2 MSC CJ70-150 MC
Delivered 2003 - 2004
2 Baker Pacific Class 375
Delivered 2007 - 2008
1 BMC 350
Delivered 1984
10 x Barges
Delivered 1981-1998
One of the Youngest and MostAdvanced Rig Fleets
Semisubmersible Other
1 DSS 20-CAS-M
Delivered 2003
3 DWSS-21
Delivered 2009 - 2010
3 MSC CJ70-X150MD
Delivery 2013 - 2014
OtherNew buildings
4 Samsung 96K drillships
Delivery 2013/2014
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 7/42
Maersk Drilling Rigs – 2012Jack-up rigs
MÆRSK ENDURER
MÆRSK GIANT
MAERSK GUARDIAN
MÆRSK GALLANT
MÆRSK INNOVATOR
MÆRSK INSPIRER
1977
1986
1986
1993
2003
2004
MAERSK RESILIENT
MAERSK RESOLUTE
MAERSK RESOLVE
MAERSK REACHER
2 Newbuilding CJ70
2008
2008
2009
2009
2011
Constantly
Moving
Boundaries for
Technological
MAERSK COMPLETERMAERSK CONVINCER 20072008
1 Newbuilding CJ70 2012
Semi-submersibles Cantilevered Barges
MAERSK EXPLORER
MÆRSK DEVELOPER
MAERSK DISCOVERER
MÆRSK DELIVERER
NAN HAI 6 (MANAGEMENT)
2003
2009
2009
2010
MAERSK RIG 61
MAERSK RIG 62
MAERSK PATHFINDER
MAERSK PIONEER
1994
1995
1998
1998
Deve opments
Drill Ships
4 Newbuilding K96 2011
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 8/42
Quality Management
• SIRIUS is the main tool for integrating sustainability in our business practices
• SIRIUS is compliant with ISO 9001 and OHSAS 18001 and maintains ISO 14001, ISPS
and ISM certification where applicable
• We continously monitor, evaluate and improve the SIRIUS application and its content
...is essentially about securing that we deliver what our customers want
•We have a process for revision of the management system, which enables internal andexternal stakeholders to provide feedback, either via the SIRIUS revision form,
management reviews, customer surveys, or stakeholder meetings
• The feedback is integrated into one Sustainability plan (HSSE, CSR and Quality), which
guide our efforts in delivering what our customers want
We have a systematic audit framework in place to secure
that we, as well as stakeholders, comply with our values
and sustainability policies
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 9/42
Constant Care”intet tab skal os ramme, som ved rettidig omhu kunne afværges”
”My old saying ’No loss should hit us
which can be avoided with constantcare’ this must be a watchwordthroughout the entire organisation”
A. P. Møller in a letter to Mærsk Mc-Kinney Møller, December 2nd 1946
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 10/42
Rig Moves
Wet TowDry Tow (Heavy-lift)
Our units are moved by dedicated and specially trained
Towmasters who are in overall charge of the rig move.
This ensures safe and efficient rig moves.
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 11/42
Extracts from NWEA Guidelines• 3. Tow Masters
• Actively participated in the execution of at least five rig move
operations on a similar MOU type or a suitable combination of rig
moves and simulator training. (This should be documented.)
• Extensive knowledge of all relevant Rules and Regulations.
Now: ”GOMO”
• NWEA Guidelines For The Safe Management of Offshore Supply and
Rig Moving Operations.
• Extensive knowledge of the Rig move plan.
• English language capabilities Participated in the execution of, at least
three rig move operations onboard an anchor handling vessel, or
previous experience as AHTS Master or relevant marine experience.
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 12/42
Replacing NWEA. Presently (2012) sent out by IMCA for comments
GOMO: GUIDELINES for OFFSHORE MARINE OPERATIONS
7.4.3.6 Tow Master(s)
Tow masters must be able to demonstrate sufficient expertise in relevant MOU
move operations and appropriate levels of actual experience.
In this context the tow master should have participated in MOU movingoperations in the following operations in the following capacities:
In relation to semi-submersible units acted as a stand-alone Barge
Supervisor on such units for a minimum of three (3) rig moves under
supervision, or in a position of responsibility as a rig move observer
for a minimum of five (5) rig moves.
In relation to self-elevating units….. same as above!
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 13/42
GOMO: GUIDELINES for OFFSHORE MARINE OPERATIONS
Replacing NWEA. Presently (2012) sent out by IMCA for comments
7.4.3.6 Tow Master(s)
In addition, the tow master should:Hold valid STCW Class 1(Deck) or equivalent qualification.
Hold valid GMDSS Certificates.
Have full understanding of the proposed operation, including
.
Recommended Competencies and training for tow masters include:
AH Simulator Course
Towmaster Simulator Course
Geotechnical / Soil Evaluation Course (for self-elevating units.
Offshore Meteorology Course.Knowledge of DP Operations.
Knowledge of relevant rules and regulations.
Ability to communicate effectively in English and / or local working
language.
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 14/42
# Qualifications / Courses Period Place
1 Rig Move Simulator 5 days MT, Svendborg
2 Soil Evaluation / Special 2 days DGI, Lyngby
3 Offshore Meteorology 1 day DMI, CPH
4 Anchor Handling Simulatorincl. DP Familiarization
5 days MT, Svendborg
5 ARPA 3½ days Denmark
6 GMDSS 10 days Denmark
Training Programme for Maersk Drilling Towmasters
2 as c ay enmar
8 First Aid & Medic Care 5 days Denmark
9 Management Seminar 5 days Denmark
10 BOSIET 5 days WW
11 Liberia / Panama Licences - -
12 DK / UK / N Medicals - -
13 Towmaster Assistant,approx. 20 rig moves
12 – 18 mdr All rig types, MD
14 Office, familiarization 3 weeks Office, Lyngby
15 Towmaster Manual , Sirius 2 days Incl. in 14, above
16 Anchor Handler, onboard 2-4 weeks North Sea
Recruiting from OIM, Barge Engineer
and/or AHTS Captain, Chief Officer.
Typical training period:
16 to 18 months – pending
previous experiences.
as er ar ner ac e y so
experience from a maritime position– including offshore experience from
a drilling rig and/or an AHTS.
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 15/42
• Maersk Drilling employ presently
12 Towmasters and 1 Towmaster Trainee
• Presently advertising for 2 Towmaster Trainees• (Link > http://www.maerskdrilling.com/Career/Vacancies/Pages/Vacancies.aspx )
• They have a total Towmaster Experience of 51 years
Maersk Drilling Towmasters
– where they have been in charge of more than 1800rig moves
• Maersk Drilling are moving Own and Management
Units with a Towmaster in charge of rig and rigmove operations. The Towmaster is taking over the
responsibilities of the OIM
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 16/42
Towmaster Per Frederiksen
Moving Jack-Up Rigs, the
“Maersk Drilling Way”- with Constant Care -
CV – few headlines:1981 – 1983: Navigation School, Denmark
-------------
2001 – 2003: Instructor, MT Svendborg.
2002: Promoted Captain in A. P. Moller.
2003 – 2004: Captain in MSS: AHTS at West Africa & North Sea.2004: Instructor at MT Svendborg.
2006: Towmaster Trainee, Maersk Drilling
2007: Promoted Towmaster, Maersk Drilling
2007 – Ongoing: Towmaster in Maersk Drilling
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 17/42
Maersk Drilling Towmasters
RESPONSIBILITIES:
• Safety of Personnel and Unit
• Environment
• Assure Sea-worthy Condition
• Equipment in Safe Condition• Equipment Operational
• Permit To Work System
• Daily Report to Shore Base and
Towmasters Department
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 18/42
Maersk Drilling Towmasters
• WORK SCOPE INCLUDES:
• “Ownership” of the coming Rig Move!• Prepare the Rig Move Papers prior to a Rig Move
• Person in Charge (OIM)
• n s a y arame ers
• Verify Weather Information
• Manning Requirements
• Maintain an Accurate Event Log
• Inspect the Attending Vessels
• Raise a Revision Request
• Complete the Rig Move Report
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 19/42
Who is this Person?Who will ensure and be responsible for:
- All Requirements
- Procedures: Safety / Operational- Rules
- Policies
- Systems
-
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 20/42
• ENVIRONMENTAL DATA
E.G.:
- 100 Year Wind & Wave Data (NORSOK)
(SNAME: 50 Year)
- 10 Year Current Data
- Expected Installation Period, Directional or
Seasonal
Site Assessments – Input Output
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 21/42
Geotechnical Analyses – Input
• INPUT: Soil Data
• Soil Data should fulfil the requirements
stated in the Towmaster Manual (SIRIUS)
• Unknown Areas and Unknown Locations
require Core Samples / Soil Data from
below each spud can
• OUTPUT: Penetration Curves
• Predicted spud can penetration into the
soil for loads increasing to a certain Level
– FINAL PRELOAD
Output
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 22/42
More Penetration Curves
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 23/42
The MD Location Evaluation
Consists of:
1. Site Assessments
General Engineering – Location Evaluation
.
3. Recommendations from
Engineering to Towmaster,
e.g. Preloading Procedure
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 24/42
Rig Move – Flow Chart
• End of Engineering’s
involvement when theLocation Evaluation isissued
• Towmaster’s Department”Takes Over”
• Scope Of Work
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 25/42
Warranty – Location Approval
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 26/42
•Input to MD Management:
• Location Approval, issued by Warranty Surveyor
• MD’S Requirements, signed by Warranty Surveyor
• Penetration Anal sis
MD CEO – Certificate of Acceptance
• Engineering Assessments• Location Evaluation, issued by MD Engineering
• Seabed Survey
• Towmaster’s Letter of Instruction• Operation Plan: Scope Of Work, Passage Plan
• Copies of Sea Charts
• Other Relevant Drawings
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 27/42
CEO – Certificate of Acceptance
Rig Move accepted by MD CEO
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 28/42
Ready to commence the Move
• ”Go Ahead” received – ALL Papers signed
• Tow Team, Towmaster(s) & Warranty Surveyor, sign on theMODU
• Inspection / Approval of the MODU
• Seaworthiness, Operational readiness, Certificates, Manning(Down!)
• MODU is signed over from the Person in Charge (OIM) to theTowmaster ≈ Overall Responsible
• Weather Forecasts (2 Independent) available
• Suitable Weather Window(s) indentified
• Departure / Transit / Arrival
• When installed – the MODU is signed back to the Person in
charge (OIM)
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 29/42
Approval & Briefing of Vessels
• Vessels are normally provided by the Client
• All Vessels shall be fit for the proposed and intended
Operation
• All Vessels must be in compliance with the standards
stipulated in the Location Approval, SOW, Operation
anua an y t e atten ng arranty urveyor
• Towing/AH Equipment, Manning, Bunkers
- Language Barriers & Culture Diversities!
• All Certificates must be valid
• General Aim: All general Operations shall be in
agreements with the NWEA ”GOMO” GUIDELINES
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 30/42
Inspection of Attending Vessels
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 31/42
Bollard Pull Required
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 32/42
Arrival & Installation of a Jack-Up
• Pin rig in Stand-off loc, approx 50 – 100 m from final pos
• Run anchors / utilization of DP Classed AHTV
• Re-connect tugs
• 1. Winch rig to final assisted by tugs and or –• 2. Walk rig to final assisted by tugs
• Pin rig in final (Tolerances: +/- 0.5m & +/- 1°0 or less!)
• na pos on approve y e en
• Commence elevating hull = Commence preloading
• Disconnect tugs
• Recover anchors
• Preload: Site specific. Shallow / Deep penetrations
• Punch Through / Rapid Penetrations
• Hold / Dump preload water
• Elevate hull to final air gap
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 33/42
Punch Through!!!
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 34/42
Punch Through!!!
The Noble David Tinsley experienced “Punch Through"while conducting Preloading Operations on May 8 2009
All three Legs have penetrated the Sea Floor off the Coastof Qatar, causing severe damage to the Jack-Up and legs
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 35/42
Punch Through!!!
Vantage Drilling Rig, Sapphire Driller experiences a Bow Leg Run
/ Punch Through in the early morning hours on 30 Oct 2009
”It appears a Zero Air Gap Preload was being conducted, which
most likely minimized Potential Structure Failure”
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 36/42
MAERSK VICTORY”Punch Through” 1997 – Adelaide, Australia
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 37/42
Risk of Rapid Penetrations!
•Rig at positive draft to Zero air gap• (Positive draft requires higher preload to achieve the required Seabed Reaction)
• Preload as close as possible to sea level
- Gain buoyancy in case of rapid penetrations
- Pending actual weather, sea state and tide
• re oa one eg a a me
- To reduce the overall weight of the rig andthen minimise potential structural damage
• Closely monitor the Penetration versus Seabed Reaction
as weight is added
• To catch the first indication of which Penetration Curvethe spud can is following: Lower or Upper Bound or ?
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 38/42
Preloading – Moving Boundaries!
“Punch Through?”“Punch Through?”
”Controlled Rapid Penetration”
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 39/42
Departure – Freeing Legs
• Leg and Spud Can are stuck in the soil due to
vacuum underneath the Spud Can combined
with soil on top of the Spud Can.
• Jetting below the Spud Can will break down the
vacuum and start filling up the gap generated
by the leg creeping upwards.
• The hull buoyancy will overcome the weight of
soil on top of the Spud Can.
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 40/42
Spud Can, seen from below
Size, one of three: 200 m²
Tip & Jetting Nozzles
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 41/42
Freeing Legs: ”Pull” & Jet!
Stuck on the Port Leg!
8/13/2019 11 - Final PFR 28 Oct KTF Stavanger Nov 2012
http://slidepdf.com/reader/full/11-final-pfr-28-oct-ktf-stavanger-nov-2012 42/42
Thank You! STILL TIME FOR QUESTIONS !!!