02 Enhanced Prot

Embed Size (px)

Citation preview

  • 7/27/2019 02 Enhanced Prot

    1/16

    EnhancedTransmission Line

    Protection usingPMUs

    Faraz Z. Khan,

    Raghavendra. G, R. Nagaraja and H.P. Khincha

  • 7/27/2019 02 Enhanced Prot

    2/16

    Contents

    Introduction

    Proposed scheme

    Basic architectureCase Studies

    Conclusion

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    3/16

    Introduction

    Transmission line protection is majorly dependent on Distance

    relay operation

    Existing Distance relay operation is affected by various factors

    such as :

    Presence of Infeed

    Presence of FACTS devices

    Load encroachment

    Fault resistance

    Power swing

    Parallel line operation

    Mutual coupling effect

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    4/16

    Proposed Scheme

    Proposed scheme is concentrated to control zone 2 and zone 3

    operation of relay as zone 1 operation is generally instantaneous.

    The scheme utilizes PMU data, double ended fault location

    algorithm and communication infrastructure for its operation.

    It does not modifies the existing zone settings thus in case of

    communication failure, the conventional scheme will be intact.

    Phasor information has to be transmitted to the PDC only upon

    detection of fault in zone 1 of slave locations.

    Zone 3 setting is restricted to secondary line end for simplicity.

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    5/16

    Basic Architecture

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    6/16

    Flowchart

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    7/16

    Flowchart (contd)

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    8/16

    Case Study - Infeed operation

    Power Research and Development Consultants Pvt. Ltd.

    Zone 2 reach of the Master relay is set to cover 50% impedance of

    the line between buses 2-4 (i.e. 10 km from Bus 2)

    A three phase to ground fault is simulated at 8 km on line 2-3 from

    slave 1 location

    Slave 1 relay detected fault in Zone 1

    Computed fault distance = 7.98 km

  • 7/27/2019 02 Enhanced Prot

    9/16

    Case Study - Infeed operation

    Power Research and Development Consultants Pvt. Ltd.

    Apparent impedance seen by

    Master relay

    Apparent impedance seen bySlave1 relay

  • 7/27/2019 02 Enhanced Prot

    10/16

    Sequence of operation

    1 Zone 1 of Slave 1 triggered

    2 The voltage and current phasors at slave 1 and slave 2 are

    communicated to PDC by the respective PMUs

    3

    The fault location is estimated by PDC (i.e. 7.8 km) anddecision is taken for master relay to trigger

    4 The decision is communicated to the PMU at master

    location

    5 The signal received by PMU at master location is

    transferred to the master relay for triggering zone 2 operation

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    11/16

    Case Study - SVC operation

    Power Research and Development Consultants Pvt. Ltd.

    Zone 2 reach of the Master relay is set to cover 50% of the line

    between buses 2-3 (i.e. 55 km from Bus 2)

    Zone 3 covers the entire length of the line between buses 2-3

    A three phase to ground fault is simulated on line 2-3 at 90 km from

    slave 1 location and 20 km from slave 2 location

    Slave 2 relay detected fault in Zone 1

    Computed fault distance = 90.31 km

  • 7/27/2019 02 Enhanced Prot

    12/16

    Case Study - SVC operation

    Power Research and Development Consultants Pvt. Ltd.

    Apparent impedance seen by

    Master relay

    Apparent impedance seen bySlave2 relay

    Proposed scheme triggers the Master relay zone 3

  • 7/27/2019 02 Enhanced Prot

    13/16

    Case StudyLoad encroachment

    Power Research and Development Consultants Pvt. Ltd.

    Apparent impedance seen by

    Master relay

    Apparent impedance seen bySlave1 relay

    Proposed scheme blocks the Master relay Zone 3

  • 7/27/2019 02 Enhanced Prot

    14/16

    Conclusion

    Power Research and Development Consultants Pvt. Ltd.

    Proposed scheme is simple and utilizes basic PMU

    architecture

    It can effectively solve existing issues faced by distance

    relaying

    It retains the existing setting of the relays thus in case of

    communication failure, the conventional scheme will be

    intact.

    Proposed scheme also performs well for double circuitlines, mutual coupling effect and in presence of fault

    resistance

  • 7/27/2019 02 Enhanced Prot

    15/16

    ReferencesqAlstom T&D, Network Protection and Automation Guide, 1st edition, Alstom Grid, July 2002.

    q S. H. Horowitz, A. G. Phadke and J. S. Thorpe, Adaptive Transmission System Relaying, IEEE Trans.

    on Power Delivery, Vol. 3, No. 4, October 1988.

    q Tarlochan Singh Sidhu, Rajiv K. Varma, Pradeep Kumar Gangadharan, Fadhel Abbas Albasri and German

    Rosas Ortiz Performance of Distance Relays on Shunt-FACTs Compensated Transmission Lines, IEEE

    Trans. on Power Delivery, Vol. 20, No. 3, July, 2005.

    q Fadhel A. Albasri, Tarlochan Singh Sidhu and Rajiv K. Varma, Performance Comparison of Distance

    Protection Schemes for Shunt-FACTs Compensated Transmission Lines, IEEE Trans. on Power Delivery,

    Vol. 22, No. 4, October, 2007.q Report of the Enquiry Committee on Grid Disturbance in Northern Region on 30th July, 2012 and in

    Northern, Eastern and North-Eastern Region on 31st July, 2012.

    qNERC, August 14, 2003 Blackout: NERC Actions to Prevent and Mitigate the Impacts of Future

    Cascading Blackouts, February 10, 2004, North American Electric Reliability Council, Princeton, New

    Jersey.

    q S. H. Horowitz and A. G. Phadke, Third Zone Revisited, IEEE Trans. on Power Delivery, January 2006.

    q Seong-Il Lim, Chen-Ching Liu, Seung-Jae Lee, Myeon-Song Choi and Seong-Jeong Rim,Blocking of

    Zone 3 Relays to Prevent Cascaded Events, IEEE Trans. on Power Systems, Vol. 23, No. 2, May, 2008.

    qAmr El-Hadidy and Christian Rehtanz, Blocking of Distance Relay Zone 3 Under Load Encroachment

    Conditions: A New Approach Using Phasor Measurements Technique, Proceedings of the 14th International

    Middle East Power System Conference (MEPCON), Cairo University, Egypt, December 19-21, 2010.

    q MiPowerTM User Manual, www.prdcinfotech.com.

    Power Research and Development Consultants Pvt. Ltd.

  • 7/27/2019 02 Enhanced Prot

    16/16

    Thank You

    Power Research and Development Consultants Pvt. Ltd.