Click here to load reader
Upload
salehsbeih
View
79
Download
2
Embed Size (px)
Citation preview
Project Control and level of "Effort of Engagement"
By: Mohammad S. Abu Sbeih, CPIM * on Apr 20th
, 2013
We should always remember that the project is a “business case” that has been justified
enough to be realized. This business case is presented in the form of value (business
outcomes) and disaggregated backward into “realization phases” which is project lifecycle.
During project life cycle, many level of control should be in place to ensure that the project is
still within its justified business case and predetermined constraints tolerances.
As it is well known; control is implemented by monitoring the actual status / performance
versus the baseline to predict and capture variances in order to take corrective action and get
things back to their original baselines or re-adjust the tolerances themselves. Control is not
performed at one level, as we have strategic planning (corporate /program/project board
level), tactical planning (PMO/project manager level) and operational planning (project
manager/team level); the project should be tracked, reviewed, and corrected at all of these
levels.
Submitting progress reports by project managers to PMO is not enough to ensure proper
project control; it is just a one element of the complicated project control puzzle. To ensure
there is a good project control system in place; the following should exist:
Coherence “top-down” objectives and tolerances disaggregation line across
project levels.
Rigid “bottom-up” status and performance reporting line across project levels
during normal cases (project within tolerances).
Systemized “bottom-up” escalation line and (issues/risks/changes) rising, tracking,
and solving across project levels for exception cases (variance exceeded the agreed-
upon tolerances).
Decision points and control gates across project life cycle to check project status
and take control decisions.
Remember: “Governance System” and “Risk Management System” are a prerequisite to
achieve proper control over projects.
“Effort of Engagement”
Let us initiate and use this term to describe the amount of involvement of each project
layer “director, manager, and member” in the project control process across project life
cycle.
The above figure shows that:
1. During initiating management stage: the project board “Directors” has the highest
level of “Effort of Engagement” for defining the project and setting constraints and
polices. Then the project manager joins and leads the work until the end of the
planning management stage with the highest level of “Effort of Engagement” for
defining phases and implementation methodology, assigning resources…etc.
2. During execution management stage: the project team get involved in the project
with the highest level of “Effort of Engagement” for executing the wok and delivering
the product, while project manager level of “Effort of Engagement” decreases to the
level of monitoring and managing progress and resources.
3. During closing management stage: the level of “Effort of Engagement” of project
manager and project board starts to rise again as it is time to close requirements and
ensure proper business review and benefits realization.
The project layer “director, manager, and team member” with the highest level of
“Effort of Engagement” should lead control activities and initiate the escalation process
for exception cases. For example; during planning and execution management stages, project
directors will not get involved in project repetitive control work; instead they will just
respond to exception cases. The same situation regarding project manager and tasks
execution, he/she will still focus on the whole project phase progress leaving the control of
tasks to the team leader and responding only to escalated cases; this is what is called
“Management by Exception”.
By dividing the “Effort of Engagement” between project layers you will achieve tight
and rigid governance model which ensures proper control over the project.
Consolidating the three above charts in one figure, the result is the “PMI” figure for the
project management processes’ groups.
Project board (project directing layer) “Effort of Engagement” chart coincides
with both the initiating and closing processes’ groups chart
Project manager (project managing layer) “Effort of Engagement” chart coincides
with the initiating, planning, and closing processes’ groups chart
Project team (project delivering layer) “Effort of Engagement” chart coincides
with the execution processes’ groups chart
The following table summarizes “Effort of Engagement” for all project levels
Project Level
"Effort of Engagement"
Level of authority
Lead the effort of
control in the
following
management stage
"Manage by
Exceptions" in the
following
management stage
Project board Initiating + Closing Planning +
Execution Project tolerance
Project manger initialing + Planning
+ Closing Execution Phase tolerance
Team member Execution - Work Package
tolerance
(*) Mohammad S. Abu Sbeih is currently working for
METHOD as Lead Business Consultant. He has ten years of
excessive experience in the fields Project Management,
Business Process Management, and Organizational
Restructuring and Development in various manufacturing
and consulting firms in MENA region. Recently he has
participated with METHOD in the development and set up
of different PMOs for many industries.
You can reach him at ([email protected])
(+966 547 933 026)