PROJECT UPDATE

Rio de Janeiro | March 2012 |

Page 2: Osx project update eng_ march

FPSO OSX-1 SHIPBUILDING 2

Page 3: Osx project update eng_ march

AÇU INDUSTRIAL COMPLEX

A New Cluster for the Offshore and Heavy Industry

90 km² Complexo Industrial (1,5x maior que a ilha de Manhattan)

GE

90 km² Industrial Complex (1.5 x larger than Manhattan Island)

Page 4: Osx project update eng_ march

UCN AÇU: LAYOUT

90 km² Complexo Industrial (1,5x maior que a ilha de Manhattan)

Administrative buildings with LEED

Certification (US Green Building Council)

Dry dock and ETS

Quays

Jacket assembly area

Administrative buildings

ETA

Green Curtain

Module construction area

Platform construction area

Electricity Substation 345 kV – 13.8 kV

FPSO

Industrial unit

4

Page 5: Osx project update eng_ march

UCN AÇU: LICENSING SCHEDULE

Oct-10 Jan-11 Jun-11 Jul-11 Feb-11

Public Hearings

Preliminary License Issuance

Installation License

Issuance Beginning of Construction

EIA/RIMA Filling

P P P P P

5

Page 6: Osx project update eng_ march

UCN AÇU: SHIPBUILDING UNIT SCHEDULE

PACKAGES PROCUREMENT MOBILIZATION

REMOVAL OF VEGETATION 2Q11 2Q11

PREPARATION OF THE TERRAIN 3Q11 3Q11

NORTH QUAY AND JACKET'S AREA 1Q12 1Q12

DRY DOCK 1Q12 1Q12

SOUTH QUAY AND RESPECTIVE RETRO AREA 1Q12 1Q12

INDUSTRIAL BUILDINGS 3Q11 4Q11

UTILITIES AND INFRASTRUCTURE 3Q11 3Q11

ADMNISTRATIVE BUILDINGS (LEED) 1Q12 1Q12

AUXILIARY BUILDINGS (NON-LEED) 1Q12 1Q12

ELECTROMECHANICAL ASSEMBLY 1Q12 2Q12

SUPERVISION SUPPORT 2Q11 2Q11

CONSTRUCTION SITE 3Q11 3Q11

BREAKWATER 1Q11 1Q11

DREDGING 3Q11 3Q11

P

P P

P P

P P

P P

P P

P P

P P

P

6

Page 7: Osx project update eng_ march

UCN AÇU: ESTIMATED PARTIAL DELIVERIES

UCN Sections (Ready) 2012 2013 2014

AREA 1 FOR ASSEMBLY OF JACKETS 4th QUARTER - -

AREA 2 FOR ASSEMBLY OF JACKETS - 1st QUARTER -

AREA FOR INITIAL CUTTING OF STEEL PLATES - 1st QUARTER -

SLOT 1 FOR FPSO INTEGRATION - 1st QUARTER -

SLOT 2 FOR FPSO INTEGRATION - 2nd QUARTER -

SLOT 3 FOR FPSO INTEGRATION - 3rd QUARTER -

SLOT 4 FOR FPSO INTEGRATION - 4th QUARTER -

SLOT 5 AND 6 FOR FPSO INTEGRATION - - 2nd QUARTER

COMPLETION OF CONSTRUCTION OF UCN - - 2nd QUARTER

7

Page 8: Osx project update eng_ march

UCN AÇU: FINANCING

Fundo da Marinha Mercante (Merchant Marine Fund)

Credit facility: 80% CAPEX

Total tenor ranging from 18 to 20 years with a grace period of up to 3

years and interest rates that vary between US$ + 2% to US$ + 4% per annum

Lending Agents: BNDES, Caixa Econômica Federal, Banco do Brasil, BNB

and Banco da Amazônia

8

Page 9: Osx project update eng_ march

UCN AÇU: FINANCING

2011 2012 2014 2013

63,6% 20,1% 1,9% 14,4%

Capex distribution per year/activity

TOTAL OF US$ 1,933 MM

DESCRIPTION OSX (US$) LLX (US$)

DREDGING AND ENGINEERING 93 90

BREAK WATER 135 129

QUAY 262 -

BUILDINGS 339 -

DRY DOCK 133 -

ROADS AND PAVING 146 -

EQUIPMENT, ENGINEERING AND ENVIRONMENT 487 -

OTHERS 119 -

TOTAL $1.714 $219

9

Page 10: Osx project update eng_ march

UCN AÇU:

EVOLUTION OF THE WORKS

Page 11: Osx project update eng_ march

UCN AÇU: BREAKWATER

11

The towing operation to Porto do Açu is expected

to take place during the first half of 2012

Aerial view of the 6 concrete “boxes” in Porto do

Forno, Arraial do Cabo

11

Page 12: Osx project update eng_ march

UCN AÇU: AERIAL VIEW

12

Page 13: Osx project update eng_ march

UCN AÇU: CONSTRUCTION OF THE CANAL

13 13

Page 14: Osx project update eng_ march

14

UCN AÇU: CONSTRUCTION OF THE CANAL

125 m

1370 m

Beginning of construction of the breakers to protect the approach canal to the

Açu Shipbuilding Unit

Distance escavated

14

Page 15: Osx project update eng_ march

UCN AÇU: EARTHWORKS & BUILDINGS

15

Administrative Building (LEED) Plots to be used by contractors

Water Treatment Plant Plots to be used by contractors

15

Page 16: Osx project update eng_ march

UCN AÇU: EARTHWORKS & BUILDINGS

16

1. Medical Centre 2. Administrative Building (LEED)

3. Canteen

Concrete factory 1

3

2

16

Page 17: Osx project update eng_ march

UCN AÇU: BUILDINGS

17

Canteen

Effluent Treatment Plant

17

Page 18: Osx project update eng_ march

UCN AÇU: BUILDINGS

18

Administrative Building (LEED)

Page 19: Osx project update eng_ march

FPSO OSX-1 LEASING

& SERVICES

Page 20: Osx project update eng_ march

CURRENT ORDER BOOK STATUS: OGX

* delivery at the shipyard (ex installation) 20

EQUIPMENT CAPACITYESTIMATED CAPEX

(US$ MM)DELIVERY*

FPSO OSX-1 80K bopd 610 3Q 2011

FPSO OSX-2 100K bopd 775 2Q 2013

FPSO OSX-3 100K bopd 800 3Q 2013

FPSO OSX-4 100K bopd 850-900 2Q 2014

FPSO OSX-5 100K bopd 850-900 4Q 2014

WHP-1 30 wells 400-450 3Q 2013

WHP-2 30 wells 400-450 4Q 2013

PLSV (SAPURA) NA 263 4Q 2014

Total 4,948-5,148

Page 21: Osx project update eng_ march

FPSO OSX-1:

DESTINATION WAIMEA

Page 22: Osx project update eng_ march

FIRST OIL FOR OGX: 18H 39M 50S

22 22

31ST January 2012

Page 23: Osx project update eng_ march

FPSO OSX-1: CUSTOMIZATION

23

Page 24: Osx project update eng_ march

Age

FPSO OSX-1: CREW

Total of 89 crew members

Years of Experience

14%

26%

28%

28%

4%

20 to 30 years

30 to 40 years

40 to 50 years

50 to 60 years

Greater than or equal

to 60 years

49%

32%

19%

Less than 20 years

20 to 30 years

Greater than or equal

to 30 years

24

Page 25: Osx project update eng_ march

OGX PRODUCTION MODEL

WHP FPSO

Page 26: Osx project update eng_ march

OSX-2 / WHP-1 SYSTEM

OSX-2

Construction Contract

■ EPCI contract signed with SBM

■ Acquisition of VLCC – accomplished

Long term debt commitment

■ Facility agreement entered into lead by ING, Itaú-BBA and Santander: US$ 850 million (12 years, LIBOR +4,41% p.a.)

■ Other financial institutions participating in the syndicate : HSBC, Citibank, ABN Amro Bank, Banco do Brasil, NIBC and DnB Nor

■ Debt/Equity structure : 80/20

WHP-1

Construction Contract

■ Signing of LOI with Techint – 1Q11

■ Start of Engineering – 1Q11

■ Contract signed with Techint

■ LOI for Drilling Package signed with TTS

Milestone Date

Arrival of hull at Keppel shipyard

(Singapore) 3rd Quarter 2011

P&IDs approved for construction 2nd Quarter 2011

FPSO departure from yard 2nd Quarter 2013

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-1 3rd Quarter 2013

26

Page 27: Osx project update eng_ march

OSX-3

Construction Contract

■ Acquisition of VLCC - accomplished

■ EPCI contract signed with MODEC

Long term debt commitment

■ Financing: 1st half 2012

WHP-2

Construction Contract

■ Signing of LOI with Techint – 1Q11

■ Start of Engineering – 1Q11

■ Contract signed with Techint

OSX-3 / WHP-2 SYSTEM

Milestone Date

Arrival of hull at conversion shipyard 4th Quarter 2011

P&IDs approved for construction 1st Quarter 2012

FPSO departure from yard 3rd Quarter 2013

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-2 4th Quarter 2013

27

Page 28: Osx project update eng_ march

FPSO OSX-4

Page 29: Osx project update eng_ march

MILESTONES ACHIEVED AND NEXT STEPS

VLCC sister hulls acquired by OSX in Nov. 2010:

US$ 27 million each

FPSO OSXFLEX concept contracted with CKE

Consortium (Chemtech, Kromav and Exactum)

Close-up Survey of the hulls performed by ShipScan

and monitored by Bureau Veritas

Preparation Stage: engineering project for

conversion of the hulls

Integration UCN Açu : 2Q2013 marking the start-up

of UCN Açu’s activities

Delivery at UCN Açu in 2Q2014

Milestone Date

Specifications for hull

conversion1st Q2012

End of hull conversion 4th Q2012

Arrival of hull at UCN slot 1 2nd Q2013

Delivery by the shipyard 2nd Q2014

29

Page 30: Osx project update eng_ march

FPSO OSX-5

Page 31: Osx project update eng_ march

VLCC sister hulls acquired by OSX in Nov. 2010:

US$ 27 million each

FPSO OSXFLEX concept contracted with CKE

Consortium (Chemtech, Kromav and Exactum)

Close-up Survey of the hulls performed by ShipScan

and monitored by Bureau Veritas

Preparation Stage: engineering project for

conversion of the hulls

Integration UCN Açu : 3Q2013 marking the start-up

of UCN Açu’s activities

Delivery at UCN Açu in 4Q2014

Milestones Date

Specifications for hull repair 2nd Q2012

End of hull conversion 2nd Q2013

Arrival of hull at UCN slot 2 3rd Q2013

Delivery by the shipyard 4th Q2014

MILESTONES ACHIEVED AND NEXT STEPS

31

Page 32: Osx project update eng_ march

PROJECT

ACCELERATORS

Page 33: Osx project update eng_ march

PROJECT ACCELERATORS

Standardization of Equipment

Maximize competitiveness through standardization of production units

Reach 70% of standardization of units (plant and deck)

Signature of long-term contracts with suppliers

Water injection

Cargo handling

Energy generation

Gas compression

Offloading System

Supervisory System

Anchoring and Turret System

Water harvesting

Compressed air

Fire Fighting System

Standardized water treatment

Load pump

Ballast pumps

Key Systems Sept/11 Other Systems Feb/12

33

Page 34: Osx project update eng_ march

PROJECT ACCELERATORS

OSX Flex Engineering

Equipments/Modules may not be installed, not damaging the project

Processing plant with capacity to treat a range of oil specifications

Potential gain: 5 months in the engineering phase

Advantages

Contract signed with Chemtech-Kromav-Exactum

First OSXflex units: OSX-4 and OSX-5

Status

MIN

API RGO LDA

MAX

MIN

MAX

MIN MAX

34

Page 35: Osx project update eng_ march

ITN:

INSTITUTE

OF NAVAL

TECHNOLOGY

PARTNERSHIP BRAZIL / KOREA

Page 36: Osx project update eng_ march

ITN- INSTITUTE OF NAVAL TECHNOLOGY

Qualification of up to 3,100 personnel in 23

functions by the end of 2012

Use of SENAI’s facilities and faculty in the city of

Campos, as well as mobile units in São João da

Barra. Macaé in the future

Scholarships providing financial assistance, food and

transportation

Estimated budget: R$ 12.7 million

SENAI Campos

SENAI Macaé

SENAI São João da Barra

Objectives

36

Page 37: Osx project update eng_ march

Curriculum planning

Adapting the necessary facilities

Classes scheduled to commence in 1st quarter 2012

Organization and production of teaching material

Phase I: Qualification and Training

ITN- INSTITUTE OF NAVAL TECHNOLOGY

CityApprox.

distanceWork force Population

São João da Barra 20 Km 6.000 33.000

Campos 40 Km 92. 000 460.000

Radius Up to 50 Km 98.000 493.000

Quissamã 75 Km 3000 20.000

São Francisco 95 Km 3.000 41.000

São Fidelis 100 Km 5.000 37.000

Macaé 130 Km 113.000 206.000

Radius 2 Up to 150 Km 222.000 797.000

37

Page 38: Osx project update eng_ march

40 specialists from Hyundai based in Brazil for 5 years

50 employees from UCN Açu to be trained at Hyundai’s shipyard in Ulsan, South Korea

(4 groups from August 2012 through April 2014)

Construction of ITN at UCN Açu, with an area of approximately 1.800 m2

Facilities for workshops, labs, classrooms, auditorium and library

Implementation of systems for simulation of operations and offshore units

Phase II: Training at UCN Açu

ITN- INSTITUTE OF NAVAL TECHNOLOGY

38

Page 39: Osx project update eng_ march

Phase III- Supply Chain Strengthening

Identification of suppliers that have the potential to develop new materials, equipment and

innovative work methodologies, focused on OSX’s potential demand

Phase IV- Technological Innovation

Establish partnerships with Brazilian and international academic institutions, focused on the

development and assimilation of new technologies

ITN- INSTITUTE OF NAVAL TECHNOLOGY

39

Page 40: Osx project update eng_ march

NEXT MILESTONES

Beginning of construction: WHP-1 and WHP-2

Financing: OSX-3, WHP-1 and WHP-2

Contract shipyard to convert the OSX4 and OSX5 hull’s

Shipyard financing contract (Merchant Marine Fund)

New orders from OGX

Orders from third parties

40

Page 41: Osx project update eng_ march

41