Project Update

NOVEMBER 2011

Page 2: Osx project update english_november 2011

OSX Shipbuilding

NOVEMBER 2011

Page 3: Osx project update english_november 2011

3

Açu Industrial Complex

A new cluster for the offshore and heavy industry

90 km² Industrial Complex (1.5 x larger than Manhattan Island)

Page 4: Osx project update english_november 2011

UCN Açu: Layout

Administrative buildings with LEED

Certification (US Green Building Council)

Dry dock and ETS

Quays

Jacket assembly area

Administrative buildings

ETA

Green Curtain

Module construction area

Platform construction area

Electricity Substation 345 kV – 13.8 kV

FPSO

Industrial unit

4

Page 5: Osx project update english_november 2011

UCN Açu: Licensing Schedule

P Oct-10 Jan-11 Jun-11 Jul-11 Feb-11

P P P P

Public Meetings

PreliminaryLicense (LP)

Issuance

InstallationLicense (LI) Issuance

Beginning of Construction

5

EIA/RIMA Filling

Page 6: Osx project update english_november 2011

UCN Açu: Shipbuilding Unit schedule

Packages Procurement Mobilization

Removal of Vegetation 2Q11 2Q11

Preparation of the Terrain 3Q11 3Q11

North Quay and Jacket’s Area 4Q11 1Q12

Dry Dock 4Q11 1Q12

South Quay and Respective Retro Area 4Q11 1Q12

Industrial Buildings 3Q11 4Q11

Utilities and Infrastructure 3Q11 3Q11

Administrative Buildings (Leed) 1Q12 1Q12

Auxiliary Buildings (Non Leed) 4Q11 1Q12

Electromechanical Assembly 1Q12 2Q12

Supervision Support 2Q11 2Q11

Construction Site 3Q11 3Q11

Breakwater 1Q11 1Q11

Dredging 3Q11 3Q11

P P

P P

P P P

P P

P P

P P

P P

6

Page 7: Osx project update english_november 2011

UCN Açu: Estimated delivery for the sections

UCN Sections (Ready) 2012 2013 2014

Area 1 for assembly of jackets 4th Quarter - -

Area 2 for assembly of jackets - 1st Quarter -

Area for initial cutting of steel plates - 1st Quarter -

Slot 1 for FPSO integration - 1st Quarter -

Slot 2 for FPSO integration - 2nd Quarter -

Slot 3 for FPSO integration - 3rd Quarter -

Slot 4 for FPSO integration - 4th Quarter -

Slot 5 and 6 for FPSO integration - - 2nd Quarter

Completion of construction of UCN - - 2nd Quarter

7

Page 8: Osx project update english_november 2011

Credit facility: 80% of CAPEX

Total tenor ranging from 18 to 20 years with a grace period of up to 3 years and interest rates that vary from US$ + 2% to US$ + 4% per year

Lending Agents: BNDES, Caixa Econômica Federal, Banco do Brasil, BNB and Banco da Amazônia

Capex Distribution by Activity:

UCN Açu: Financing (Merchant Marine Fund)

14.4%

2011 2013 2014 2012

63.6% 20.1% 1.9%

US$ MM OSX LLX

Dredging and Engineering 93 90

Break Water 135 129

Quay 262 -

Buildings 339 -

Dry Dock 133 -

Roads and Paving 146 -

Equipment and Others 487 -

Total of US$ 1.933 MM 1.714 219

8

Page 9: Osx project update english_november 2011

UCN Açu: Flora rescue

9

Page 10: Osx project update english_november 2011

UCN Açu: Wildlife rescue

10

Page 11: Osx project update english_november 2011

11

UCN Açu: Terrain after flora and wildlife rescue

Page 12: Osx project update english_november 2011

12

UCN Açu: Construction of the canal

Page 13: Osx project update english_november 2011

13

UCN Açu: Construction of the canal

Page 14: Osx project update english_november 2011

UCN Açu: Construction of the canal

14

Page 15: Osx project update english_november 2011

15

UCN Açu: Breakwater

Page 16: Osx project update english_november 2011

Current Order Book Status: OGX

* Delivery at UCN Açu (ex-installation)

Equipment Capacity Estimated CAPEX

(US$ MM) Delivery *

FPSO OSX-1 80K bopd 610 3Q11

FPSO OSX-2 100K bopd 775 2Q13

FPSO OSX-3 100K bopd 800 3Q13

FPSO OSX-4 100K bopd 850-900 2Q14

FPSO OSX-5 100K bopd 850-900 4Q14

WHP-1 30 wells 400-450 3Q13

WHP-2 30 wells 400-450 4Q13

Total 4.685-4.885

16

Page 17: Osx project update english_november 2011

FPSO OSX-1

NOVEMBER 2011

Page 18: Osx project update english_november 2011

FPSO OSX-1: Customization

12

MODIFICATION WORK

NEW INSTALLATION

Hull / Engine Room Mod.

Central Pipe Rack Mod.

M430 Mod.

M400 Mod.

M310 New M280 Mod. M250 New M220 Mod. W140 Mod.

F110 Mod.

N130 Mod.

N160 Mod.

M350 New M200 New

M320 Mod. M290 Mod. M260 Mod.

M380 New

M230 New

Page 19: Osx project update english_november 2011

FPSO OSX-1: Project Progress

13

Page 20: Osx project update english_november 2011

FPSO OSX-1: Destination Waimea

Milestone Date

Beginning of instalation of mooring system September 2011

Arrival of buoy (from Batam) September 2011

Arrival of OSX-1 in Rio de Janeiro, Brazil 6th October 2011

Installation of STP Buoy November 2011

First Oil OGX December 2011

14

Page 21: Osx project update english_november 2011

14%

26%

28%

28%

4%

Age

20 to 30 years

30 to 40 years

40 to 50 years

50 to 60 years

Greater than or equal to 60 years

FPSO OSX-1: Total Crew: 89 people

15

49%

32%

19%

Less than 20 years

20 to 30 years

Greater than or equal to

30 years

Years of Experience

Page 22: Osx project update english_november 2011

OSX-2 / WHP-1 System

NOVEMBER 2011

Page 23: Osx project update english_november 2011

OSX-2 / WHP-1 System

WHP-1 OSX-2

17

Page 24: Osx project update english_november 2011

Construction Contract

EPCI contract signed with SBM

Acquisition of VLCC – accomplished

Long term debt commitment

Facility agreement entered into lead by ING,

Itaú-BBA and Santander: US$ 850 million

Other financial institutions participating in the

syndicate : HSBC, Citibank, ABN Amro Bank,

Banco do Brasil, NIBC and DnB Nor.

Debt/Equity structure – 80/20

12 years, LIBOR +4,41% p.a.

OSX-2 / WHP-1 System

Construction Contract

Signing of LOI with Techint – 1Q11

Start of Engineering – 1Q11

Contract signed with Techint

LOI for Drilling Package signed with TTS

WHP-1 OSX-2

18

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-1 3rd Quarter 2013

Milestone Date

Arrival of hull at Keppel shipyard

(Singapore) 3rd Quarter 2011

P&IDs approved for construction 2nd Quarter 2011

FPSO departure from yard 2nd Quarter 2013

Page 25: Osx project update english_november 2011

OSX-3 / WHP-2 System

NOVEMBER 2011

Page 26: Osx project update english_november 2011

OSX-3 / WHP-2 System

WHP-2 OSX-3

20

Page 27: Osx project update english_november 2011

Construction Contract

Aquisition of VLCC - accomplished

EPCI contract signed with MODEC

Long term debt commitment

Financing: 1st half 2012

OSX-3 / WHP-2 System

Construction Contract

Signing of LOI with Techint – 1Q11

Start of Engineering – 1Q11

Contract signed with Techint

WHP-2 OSX-3

21

Milestone Date

Arrival of hull at conversion shipyard 4th Quarter 2011

P&IDs approved for construction 1st Quarter 2012

FPSO departure from yard 3rd Quarter 2013

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-2 4th Quarter 2013

Page 28: Osx project update english_november 2011

FPSO OSX-4

NOVEMBER 2011

Page 29: Osx project update english_november 2011

OSX-3 WHP-2

VLCC sister hulls acquired by OSX in Nov. 2010 : US$ 27 million each

FPSO OSXFLEX concept contracted with CKE Consortium (Chemtech, Kromav and Exactum)

Close-up Survey of the hulls performed by ShipScan and monitored by Bureau Veritas

Preparation Stage: engineering project for conversion of the hulls

Integration UCN Açu : 2Q2013 marking the start-up of UCN Açu’s activities

Delivery at UCN Açu in 2Q2014

FPSO OSX-4: Milestones achieved and next steps

Milestone Date

Specifications for hull conversion 1Q12

End of hull conversion 4Q12

Arrival of hull at UCN slot 1 2Q13

Delivery by shipyard 2Q14

23

Page 30: Osx project update english_november 2011

FPSO OSX-5

NOVEMBER 2011

Page 31: Osx project update english_november 2011

OSX-3 WHP-2

VLCC sister hulls acquired by OSX in Nov. 2010 : US$ 27 million each

FPSO OSXFLEX concept contracted with CKE Consortium (Chemtech, Kromav and Exactum)

Close-up Survey of the hulls performed by ShipScan and monitored by Bureau Veritas

Preparation Stage: engineering project for conversion of the hulls

Integration UCN Açu : 3Q2013 marking the start-up of UCN Açu’s activities

Delivery at UCN Açu in 4Q2014

Milestone Date

Specifications for hull repair 2Q12

End of hull conversion 2Q13

Arrival of hull at UCN slot 2 3Q13

Delivery by shipyard 4Q14

25

FPSO OSX-5:Milestones achieved and next steps

Page 32: Osx project update english_november 2011

UCN – Occupation of slots by FPSOs

Slot Delivery Vessel Arrival Delivery by the UCN

Slot 1: 1Q13 OSX-4: 2Q13 OSX-4: 2Q14

Slot 2: 2Q13 OSX-5: 3Q13 OSX-5: 4Q14

Slot 3: 3Q13 OSX-6: 3Q13 OSX-6: 4Q14

Slot 4: 4Q13 OSX-7: 4Q13 OSX-7: 4Q14

Slot 5: 2Q14 OSX-8: 2Q14 OSX-8: 2Q15

Slot 6: 2Q14 OSX-9: 2Q14 OSX-9: 3Q15

Slot 1

Slot 2

Slot 4

Slot 3

Slot 5

Slot 6

*

*

*

*

* Subject to new orders from OGX

26

Page 33: Osx project update english_november 2011

Project Accelerators

Page 34: Osx project update english_november 2011

Project Accelerators

Page 35: Osx project update english_november 2011

Maximize competitiveness through standardization of production units

Reach 70% of standardization of units (plant and deck)

Signature of long-term contracts with suppliers

Project Accelerators: Standardization of Equipment

KEY SYSTEMS

Water injection

Cargo handling

Energy generation

Gas compression

Offloading System

Supervisory System

Anchoring and Turret System

OTHER SYSTEMS

Water harvesting

Compressed air

Fire Fighting System

Tubing and Accessories

Load pump

Ballast pumps

SEP / 11 FEB / 11

29

Page 36: Osx project update english_november 2011

Advantages

Modules can be removed without damaging the project

Capable of treating a range of oil specifications

Potential gain: 5 months in the engineering phase

Status

Contract signed with Chemtech-Kromav-Exactum

First OSXflex units: OSX-4 and OSX-5.

30

Project Accelerators: OSX Flex Engineering

MIN

API RGO LDA

MAX

MIN

MAX

MIN MAX

Page 37: Osx project update english_november 2011

ITN – Naval Technology Institute

Page 38: Osx project update english_november 2011

Fase 2 – Conhecimento, Tecnologia e Inovação

32

ITN : Objectives

Qualification of up to 3,100 personnel in 23 functions by the

end of 2012

Use of SENAI’s facilities and faculty in the city of Campos, as

well as mobile units in São João da Barra. Macaé in the future

Scholarships providing financial assistance, food and

transportation

Estimated budget: R$ 12.7 million

SENAI Campos SENAI Macaé SENAI São João da Barra

Page 39: Osx project update english_november 2011

Curriculum planning

Adapting the necessary facilities

Classes scheduled to commence in January 2012

Organization and production of teaching material

ITN : Phase I – Qualification and Training

City Aprox. Distance Work Force Population

São João da Barra

20 Km 6.000 33.000

Campos 40 Km 92.000 460.000

Radius Up to 50 Km 98.000 493.000

Quissamã 75 Km 3.000 20.000

São Francisco 95 Km 3.000 41.000

São Fidelis 100 Km 5.000 37.000

Macaé 130 Km 113.000 206.000

Radius 2 Up to 150 Km 222.000 797.000

33

Page 40: Osx project update english_november 2011

Fase 2 – Conhecimento, Tecnologia e Inovação

34

ITN : Phase II – Training at UCN Açu

40 specialists from Hyundai based in Brazil for 5 years

50 employees from UCN Açu to be trained at Hyundai’s shipyard in

Ulsan, South Korea (4 groups from August 2012 through April

2014)

Construction of ITN at UCN Açu, with an area of approximately

1.800 m2

Facilities for workshops, labs, classrooms, auditorium and library

Implementation of systems for simulation of operations and

offshore units

Page 41: Osx project update english_november 2011

Fase 2 – Conhecimento, Tecnologia e Inovação

35

ITN – Phase III Supply Chain Strengthening

ITN: Phase IV Technological Innovation

Identification of suppliers that have the potential to develop new materials,

equipment, and innovative work methodologies, focused on OSX’s potential

demand

Establish partnerships with Brazilian and international academic institutions,

focused on the development and assimilation of new technologies

Page 42: Osx project update english_november 2011

Next Milestones

Page 43: Osx project update english_november 2011

First Oil OGX – December 2011

Beginning of construction: WHP-1 and WHP-2

Financing: OSX-3, WHP-1 and WHP-2

Contract shipyard to convert the OSX4 and OSX5 hull’s

Shipyard financing contract (Merchant Marine Fund)

New orders from OGX

Orders from third parties

37

Next Milestones

Page 44: Osx project update english_november 2011