Project Update

SEPTEMBER 2011

1

Page 2: Osx project update inglês_setembro_final

OSX Shipbuilding

SEPTEMBER 2011

2

Page 3: Osx project update inglês_setembro_final

Açu Shipyard – Industrial District

A new cluster for heavy industry

3

Page 4: Osx project update inglês_setembro_final

Açu Shipyard – Layout

Administrative buildings with LEED

Certification (US Green Building Council)

FPSO

Dry dock

and effluent

treatment

station

Quays

Electricity Substation 345 kV – 13.8 kV

Jacket assembly area

Administrative

buildings

ETA

Green Curtain

Module construction area

Platform construction area

Industrial unit

4

Page 5: Osx project update inglês_setembro_final

Shipyard– Licensing Schedule

Oct-10

Jan-11Jun-11

Jul-11

EIA/RIMA Filling

Public MeetingsPreliminary License

(LP) Issuance

Installation License (LI) Issuance

Beginning of Construction

Feb-11

12

Page 6: Osx project update inglês_setembro_final

Shipyard Financing : Merchant Marine Fund

Credit facility: 80% of CAPEX

Total tenor ranging from 18 to 20 years with a grace period of up to 3 years

and interest rates that vary from US$ + 2% to US$ + 4% per year

Lending Agents: BNDES, Caixa Econômica Federal, Banco do Brasil, BNB and

Banco da Amazônia

Capex Distribution by Activity (million):

6

OSX LLX

Dredging and Engineering US$ 93 US$ 90

Break Water US$ 135 US$ 129

Quay US$ 262 -

Buildings US$ 339 -

Dry Dock US$ 133 -

Roads and Paving US$ 146 -

Equipment and Others US$ 487 -

Total: US$ 1,914 US$ 1,695 US$ 219

Page 7: Osx project update inglês_setembro_final

UCN – Construction Timeline

PackagesReceipt of Proposals

Contracting Mobilization

Vegetation Supression March-11 2Q11Installation License

Issuance

Ground Preparation May-11 3Q11 3Q11

North Quay and WHP area June-11 3Q11 4Q11

Dry dock June-11 3Q11 4Q11

South Quay and Respective Retro Area June-11 3Q11 4Q11

Industrial Buildings April-11 3Q11 4Q11

Utilities and Infrastructure May-11 3Q11 3Q11

Administrative Buildings (LEED) July-11 1Q12 1Q12

Administrative Buildings (Non LEED) Sepetember-11 4Q11 1Q12

Electromechanical Assembly August-11 1Q12 2Q12

Supervisory Support December-10 2Q11 2Q11

Contractor houses April-11 3Q11 3Q11

15

Page 8: Osx project update inglês_setembro_final

Pictures: Dredging and Vegetation Supression

8

Page 9: Osx project update inglês_setembro_final

Order Book Status - OGX

* Delivery at the shipyard (ex-installation)

9

Equipment Capacity Estimated CAPEX (US$ MM) Delivery*

FPSO OSX-1 80K bopd 610 3Q 2011

FPSO OSX-2 100K bopd 775 2Q 2013

FPSO OSX-3 100K bopd 800 3Q 2013

FPSO OSX-4 100K bopd 850-900 2Q 2014

FPSO OSX-5 100K bopd 850-900 4Q 2014

WHP-1 30 wells 400-450 2Q 2013

WHP-2 30 wells 400-450 1Q 2013

Total 4,685-4,885

Page 10: Osx project update inglês_setembro_final

FPSO OSX-1

SEPTEMBER 2011

10

Page 11: Osx project update inglês_setembro_final

FPSO OSX-1 – Customization

MODIFICATION WORK

NEW INSTALLATION

Hull / Engine Room Mod.

Central Pipe Rack Mod.

M430 Mod.

M400 Mod.

M310 New M280 Mod. M250 New M220 Mod. W140 Mod.

F110 Mod.

N130 Mod.

N160 Mod.

M350 NewM200 New

M320 Mod. M290 Mod. M260 Mod.

M380 New

M230 New

11

Page 12: Osx project update inglês_setembro_final

FPSO OSX-1 – Project Progress

12

Page 13: Osx project update inglês_setembro_final

FPSO OSX-1 Sail Away

Milestones Achieved

Sail away ceremony

Start of journey to Brazil

Preliminary license issued for OGX

13

Milestone Date

Begining of installation of mooring system September 2011

Arrival of buoy (from Batam) September 2011

Arrival of OSX-1 1st week in October 2011

Installation of STP Buoy November 2011

Page 14: Osx project update inglês_setembro_final

FPSO OSX-1 – En Route to Brazil

Estimated Date of Arrival: 1st week in October, 2011

As of 9/26/11

14

Page 15: Osx project update inglês_setembro_final

14%

26%

28%

28%

4%

Age

20 to 30 years

30 to 40 years

40 to 50 years

50 to 60 years

Greater than or equal to 60 years

15

Total crew : 89 people

FPSO OSX-1 – Personnel Experience

49%

32%

19%

Less than 20 years

20 to 30 years

Greater than or equal to

30 years

Years of Experience

Page 16: Osx project update inglês_setembro_final

OSX-2 / WHP-1 System

SEPTEMBER 2011

16

Page 17: Osx project update inglês_setembro_final

OSX-2 / WHP-1 System

WHP-1 OSX-2

17

Page 18: Osx project update inglês_setembro_final

OSX-2 / WHP-1 System

Construction Contract

— EPCI contract signed with SBM

— Acquisition of VLCC - accomplished

Long term debt commitment

— Committed financing with 3 leading banks (ING,

Santander, Itaú) and 5 others

— Contract at final stage of negotiation with

probable signature for Oct/2011.

— Debt/Equity structure – 80/20

OSX-2 WHP-1

Construction Contract

— Signing of LOI with Techint – 1st quarter 2011

— Start of Engineering - 1st quarter 2011

— Contract signed with Techint

— LOI for Drilling Package signed with TTS

Long term debt

- Financing: BNDES and GIEK

18

Milestone Date

Arrival of hull at Keppel shipyard

(Singapore) 1st Quarter 2011

P & IDs approved for construction 2nd Quarter 2011

Docking of VLCC 3rd Quarter 2012

FPSO departure from yard 2nd Quarter 2013

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-1 2nd Quarter 2013

Page 19: Osx project update inglês_setembro_final

OSX-3 / WHP-2 System

SEPTEMBER 2011

19

Page 20: Osx project update inglês_setembro_final

OSX-3 / WHP-2 System

WHP-2 OSX-3

20

Page 21: Osx project update inglês_setembro_final

OSX-3 / WHP-2 System

Construction Contract

— Aquisition of VLCC - accomplished

— EPCI contract signed with MODEC

Long term debt commitment

— Financing: 1st half 2012

OSX-3 WHP-2

Construction Contract

— Signing of LOI with Techint - February 2011

— Start of Engineering - February 2011

— Contract signed with Techint

Long term debt

— Financing: BNDES and GIEK

21

Milestone Date

Docking of VLCC 4th Quarter 2011

P & IDs approved for construction 2nd Quarter 2012

FPSO departure from yard 3rd Quarter 2013

Milestone Date

Start of construction and assembly 4th Quarter 2011

Load Out of WHP-2 1st Quarter 2013

Page 22: Osx project update inglês_setembro_final

FPSO OSX-4

SEPTEMBER 2011

22

Page 23: Osx project update inglês_setembro_final

FPSO OSX-4

OSX-3 WHP-2Milestones Achieved

Aquisition of VLCC Suhail Star / value US$ 27 million

Signing of contract for OSXflex Project ( Chemtec & Kromav )

Start of tanks inspection and thickness measurement of the hull

23

Milestone Date

Specifications for hull conversion 1st Quarter 2012

End of hull conversion 4th Quarter 2012

Arrival of hull at UCN slot 1 1st Quarter 2013

Delivery by shipyard 2nd Quarter 2014

Page 24: Osx project update inglês_setembro_final

FPSO OSX-5

SEPTEMBER 2011

24

Page 25: Osx project update inglês_setembro_final

FPSO OSX-5

OSX-3 WHP-2Milestones Achieved

Aquisition of VLCC – Gemini Star / value US$ 27 million

Signing of OSXflex Project

Start of tanks inspection and thickness measurement of the hull

25

Milestone Date

Specifications for hull repair 2nd Quarter 2012

End of hull conversion 2nd Quarter 2013

Arrival of hull at UCN slot 2 3rd Quarter 2013

Delivery by shipyard 4th Quarter 2014

Page 26: Osx project update inglês_setembro_final

UCN – Occupation of slots by FPSOs

Slot Delivery Vessel Arrival Delivery by the UCN

Slot 1: 1Q13 OSX-4: 2Q13 OSX-4: 2Q14

Slot 2: 2Q13 OSX-5: 3Q13 OSX-5: 4Q14

Slot 3: 2Q13 OSX-6: 3Q13 OSX-6: 4Q14

Slot 4: 3Q13 OSX-7: 4Q13 OSX-7: 4Q14

Slot 5: 4Q13 OSX-8: 4Q13 OSX-8: 1Q15

Slot 6: 1Q14 OSX-9: 2Q14 OSX-9: 3Q15

Slot 1

Slot 2

Slot 4

Slot 3

Slot 5

Slot 6

*

*

*

*

* Subject to new orders from OGX

17

Page 27: Osx project update inglês_setembro_final

Project Accelerators

27

Page 28: Osx project update inglês_setembro_final

Maximize competitiveness through standardization of production units

Reach 70% of standardization of units (plant and deck)

Signature of long-term contracts with suppliers

KEY SYSTEMS

Water injection

Cargo handling

Energy generation

Gas compression

Offloading System

Supervisory System

Anchoring and Turret System

OTHER SYSTEMS

Water harvesting

Compressed air

Fire Fighting System

Tubing and Accessories

Load pump

Ballast pumps

Sept. 2011 Feb. 2012

Project Accelerators: Standardization of Equipment

28

Page 29: Osx project update inglês_setembro_final

Advantages

Modules can be removed without damaging the project

Capable of treating a range of oil specifications

Potential gain: 5 months in the engineering phase

Status

Contract signed with Chemtech-Kromav-Exactum

First OSXflex units: OSX-4 and OSX-5.

MIN

API RGO LDA

MAX MIN MAX MIN MAX

Project Accelerators: OSX Flex Engineering

29

Page 30: Osx project update inglês_setembro_final

ITN – Naval Technology Institute

30

Page 31: Osx project update inglês_setembro_final

ITN : Phase I - Objectives

Qualification of up to 3,100 personnel in 23 functions by the end of 2012

Utilization of facilities and instructors from SENAI

Scholarships provide financial assistance, food and transportation

Estimated budget: R$ 12.7 million

SENAI Campos SENAI MacaéSENAI São João da Barra

31

Page 32: Osx project update inglês_setembro_final

ITN : Phase I - Recruiting

• Courses in final stage of planning

• Recruiting and selection taking place during 4th quarter of 2011

• Beginning of classes scheduled for 1st quarter 2012

• Initial programs: welders, mechanics, electricians, among others

32

CityAprox.

distanceWork force

Population

São João da Barra 20 KM 6,000 33,000

Campos 40 KM 92,000 460,000

Radius Up to 50 KM 98,000 493,000

Quissamã 75 KM 3,000 20,000

São Francisco 95 KM 3,000 41,000

São Fidelis 100 KM 5,000 37,000

Macaé 130 KM 113,000 206,000

Radius 2 Up to 150 KM 222,000 797,000

Page 33: Osx project update inglês_setembro_final

Next Milestones

30

Page 34: Osx project update inglês_setembro_final

Next Milestones

Arrival of OSX-1 and first oil

Conclusion of OSX-2 financing

Beginning of construction : WHP-1 and WHP-2

Financing of OSX-3, WHP-1 and WHP-2

New orders from OGX

Orders from third parties

31

Page 35: Osx project update inglês_setembro_final

Investor Relations Contacts

[email protected]

+55 21 2555 6914

Page 36: Osx project update inglês_setembro_final