MS Project 2010 Training
- Vinit Kumar Singh
Welcome and Introduction
Welcome, we have assembled to learn to use MS Project 2010 from effort estimations to planning.
Templates
Templates would provide examples for almost all kind of plans, so its good to go through those first.
Import & Export
You can import tasks from Excel and Word.You can also simply copy the list and
paste in MPP.You need to map the fields between excel
and MPP to import the tasks.You can similarly export to pdf, excel etc.
Defining project information
Date would automatically start from today for Project plan, which can be changed as needed.
You can change things using proect>project information tool.
Start date should only be provided, let MPP decide the end date.
Defining project calendar
Either new calendar can be made or existing can be changed using Project>Change Working time.
Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab
Tasks, Inactive tasks & Summary tasks
Manually and auto scheduled taskWith manual task, we can put any text
instead of durationTasks can be organized using Summary
tasks.We can also have recurring tasks, if need
be.A non-budgeted task can be made
inactive
Milestone
Milestone represents a work accomplished like customer acceptance etc., milestone do not have any duration.
Summary tasks
Either new calendar can be made or existing can be changed using Project>Change Working time.
Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tab
WBS Codes, Show\Hide summary
Each task can be associated with a WBS (work breakdown structure) code.
We can define our own WBS codes.Highest WBS code should be added as
project code in the SEPITS for tracking.Summary tasks can be shown and hidden
from Gant chart tools>Format>Summary tasks checkbox
Link tasks
Tasks can be linked to have dependency between them
Resources
All resources can be seen at View>Resource sheet
Resources work availability should be set in maximum unit column e.g. 70% of leads.
Also cost of resources can be put here.Resources could be work, cost or material.Resources normally gets added automatically
but its not a good way. If you want new resources not to be added to the resource pool automatically, open, file>options>advanced and deselect add new resources and tasks check box
Duration, work and units
Duration = Work \ units E.g. if resource works for 50% units then task of 40 hrs is calculated
to 80 hrs by MPP Thus, 80 hours = 40 hours \ 50%
Work = Duration X Units E.g. If we enter task duration for 5 days at 40% resource usage, MPP
would give output of 16 hours Thus, 2 days = 5 days X 40%
Units = work \ duration E.g. MPP calculates units if work is provided 40 hrs and duration
160hrs. Thus, 0.25 = 40 hours \ 160 hours
Resource over-allocations
If hours assigned are higher than the maximum available time for a resource, over-allocation occurs.
Resource over-allocations can be analyzed using resource usage and resource sheet.
In resource usage view, all over allocated resources can be filtered.
It can be fixed using task inspector, team planner etc.
Resource assignments modifications
Whenever resource assignments are changed, MPP will trigger to select one of the three options. We need to click the correct option, as per our requirement there.
Team planner
Using team planner, one can assign tasks to users using drag and drop.
This can also be used to fix over-allocations of resources.
Timeline
Timeline can be viewed at View>timeline.We can add milestones on timeline and
then copy that on email for providing visual treat to client.
Master & Sub projects
One can create multiple project plans and then to analyze across the projects, one can create master plan and then add all projects plan as sub projects to that.
Leveling resources
Resources can be leveled, however it can dangerously change the whole if whole project leveling is requested. Leveling delays and splits tasks to remove over-allocations.
For that leveling should be done small portion of plan.
Baselined, scheduled and actual
Plan can be baselined from Project>Set baseline. There could be 11 baselines for a plan.
Scheduled is current plan, that may be same or changed per the progress going on.
Also actual can be used for inputting actual values, and then when required variance reports can be generated.
Project Status & Reports
Project > Project information >statisticsView > tables > variance etcProject > reports > overview > summaryUsing other text based and visual reports
More information
http://office.microsoft.com/en-us/project-help/
http://www.microsoft.com/project/en/us/default.aspx
http://www.profsr.com/msproject/msproj01.htm
http://blogs.msdn.com/b/project/
Thank You!