Upload
informa-australia
View
1.869
Download
7
Tags:
Embed Size (px)
DESCRIPTION
Nchena Mothebe, Director Transmission, from Botswana Power Corporation has presented at the Botswana Coal and Energy Conference. If you would like more information about the conference, please visit the website: http://bit.ly/13MkVsy
Citation preview
ELECTRICITY SUPPLY INDUSTRY IN
BOTSWANA, POWER SUPPLY AND DEMAND IN SOUTHERN AFRICA
Date 17th April 2013
Presented by: Nchena Z Mothebe
PRESENTATION OVERVIEW
1. BOTSWANA ELECTRICITY SUPPLY INDUSTRY OVERVIEW
2. ELECTRICITY CONSUMPTION AND DEMAND FORECAST IN BOTSWANA
3. CURRENT ELECTRICITY SUPPLY AND DEMAND SITUATION IN BOTSWANA
4. BOTSWANA POWER GENERATION PLANS
5. BOTSWANA’S SUPPLY – DEMAND BALANCE OUTLOOK
6. BOTSWANA TRANSMISSION GRID DEVELOPMENT PLAN
7. THE SOUTHERN AFRICAN REGION POWER SUPPLY OUTLOOK
BOTSWANA ESI OVERVIEW
BOTSWANA ESI OVERVIEW
BPC Generation
IPP Generation
BPC Transmission
SAPP Import / Export
BPC Customer Services & Supply
Electricity End Users
Domestic
Commercial
Government
Mining
Botswana Power Corporation (BPC) (Wholly Owned by GoB: Single Buyer Model)
Regulator Being Established
Power Sector Reforms • Electricity Supply Act (2007) Amended
– IPPs • Establishment of an Energy & Water Regulator (BEWRA)
CB
32
Legislation for private sector Generation investments Independent Power Producer (IPP) framework - 2007.
Establishment of an Energy & Water Regulator in progress
Ministry deals with regulatory issues
Single Buyer Model envisaged for the foreseeable future
Power Purchase Agreement with the National Power Utility
Transmission Use of System (TUOS) Agreement
PPA Key Issues (Project Tariff, Project Risk Allocation, Project Termination Provisions, Guarantees, Concessions, Permits / Licenses & Currency)
BOTSWANA ESI OVERVIEW
No. ITEM UNIT 2009/10 2010/11 2011/12 2012/13 (unaudited)
1 Installed Capacity (Base Load)
MW 132 132 132 132
2 Installed Capacity (Peaking)
MW
160 160 160
3 System Max. Demand MW 553 553 542 578
4 Max Demand Growth % 9.9% 0% -2% 7%
5 Energy Sales GWh 3,109 3,118 3,198 3,394
6 Sales Growth % 8% 0.3% 3% 6%
7 Internal Generation GWh 457 372 202 53
8 Total Imports GWh 2,985 3,180 3,591 2,813
9 Number of Customers No. 214,170 251,773 291,338 318,236
10 Number of Employees No. 1,841 2,188 2,047 2,047
11 Average Electricity Selling Price
t/kWh 36 48 57 59
KEY BPC (UTILITY) INFORMATION
ELECTRICITY CONSUMPTION AND DEMAND FORECAST IN BOTSWANA
Botswana’s Historic Electricity Demand Trend
1. Electricity Demand has been increasing significantly over the years. (Energy – 6% & Capacity - 8% annually in the last 5 years) 2. Botswana’s reliance on power imports increased from 51% in 2000 to 94% in 2012. 3. The continuing electricity demand growth at the backdrop of a Regional power supply deficit necessitated construction of a 600MW coal fired
power station to avert a power crisis in Botswana
6%
94%
2012
Local(GWh)
Import(GWh)
0
500
1000
1500
2000
2500
3000
3500
4000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Historic Energy Supply (GWh)
Local (GWh) Import (GWh)
Historic Electricity Market Segmentation
Domestic Market Share has grown from 19% to 28% in last 10 Years. The Commercial sector has grown from 24% to 28% in the same period. 350 out of 494 villages electrified. 28 to be electrified this year. ~70% access.
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Government 138.80 147.30 186.60 196.20 227.10 216.90 226.60 262.00 273.50 290.40 307.50 308.00 323.15
Domestic 280.40 333.60 370.50 419.70 489.40 539.30 584.40 681.70 745.10 768.70 829.10 873.00 878.76
Commercial 491.80 462.30 478.10 533.10 527.80 613.10 631.10 634.00 683.90 734.60 830.70 820.00 910.10
Mining 759.70 899.40 919.60 1001.10 1077.10 1046.60 1184.30 1199.00 1186.20 1123.20 1149.30 1117.00 1086.00
0.00
500.00
1000.00
1500.00
2000.00
2500.00
3000.00
3500.00
Historic Energy Consuption per Sector (GWh)
47%
24%
19%
10%
2002
34%
28%
28%
10%
2012
Botswana’s Long Term Demand Forecast
-
200
400
600
800
1,000
1,200
1,400
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Po
wer
Dem
and
(M
W)
Botswana Electricity Demand Forecast (MW) (2011 – 2031)
High Low Likely
Yr. 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Likely (MW)
571 580 644 681 711 744 773 854 877 902 924 941 959 1003 1017
Botswana’s Long Term Energy Forecast
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Ener
gy G
Wh
/ a
nn
um
Botswana Electrical Energy Forecast (GWh / Annum) 2011 -2031
High Low Likely
Yr. 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Likely (GWh)
3,229
3,420
3,804
3,982
4,129
4,294
4,428
4,909
5,009
5,134
5,241
5,319
5,391
5,656
5,720
CURRENT ELECTRICITY SUPPLY AND DEMAND SITUATION IN BOTSWANA
Meeting Demand in the Short to Medium Term
Source Capacity Remarks
Morupule A 0 MW 27 year old plant experiencing availability
challenges;
Refurbishment Plan in progress (Restore
116MW) by 2015
Tenders closed in March 2013
Emergency
Power Facilities
160 MW
(Diesel)
70MW – Rented Diesel Generation (To Dec 2013)
90MW – OCGT , Dual Fuel (CBM & Diesel)
Morupule B
528 MW
Coal Fired Plant - Commissioning in progress.
Initial Commercial Operation by end of 2012
Revised Commercial Operation by Mid 2013
Morupule A 120MW P/S Orapa 90MW OCGT 70MW Diesel Rental Morupule B 600MW
Meeting Demand (Short Term – Power Imports) Source Capacity Remarks
Eskom
(South Africa)
300MW 100MW Non Firm
(2013 – 2015)
• 200MW Non Firm
(Jan – July 2013)
EDM
(Mozambique)
Up to 50 MW Non Firm
NamPower
(Namibia)
Up to
100MW
Non Firm
CHALLENGES • Regional Power Supply Deficit which renders the Supply Non Firm. • No new Firm Contracts can be secured till Surplus Capacity for Bilateral Contracts is restored.
THE MORUPULE B PROJECT (UPDATE) Activity Unit 1 Unit 2 Unit 3 Unit 4
Construction 100% 100% 100% 98%
Commissioning 100% 100% 100% 90%
Reliability Run 100% 100% 100% 0%
Performance Tests 100% 100% 100% 0%
Unit Status 1.Unit 1: Out of service since 15th January 2013 to carry our repair works on Primary and Secondary Air Ducts which have exhibited cracks. The Unit is expected back in service by end of April 2013. 2.Unit 2: Out of service since 16th January 2013 to carry out Cleaning and repair works on FBHE Tubes. The unit is expected to be back in service sometime in May/June 2013.. 3.Unit 3: Unit is in service at a loading of 110MW (Net). Unit is also exhibiting Primary and Secondary Air Duct cracks which require attention once other units are in service. 4.Unit 4: Unit in final stage of construction after which it needs to go through Reliability Run &Performance Tests. No firm time lines are available but the Unit IS expected to be in commercial operation by end of June 2013.
Supply – Demand Balance Outlook 2013
Jan Feb Mar Apri May Jun Jul Aug Sep Oct Nov Dec
Orapa 90MW 90 90 90 90 90 90 90 90 90 90 90 90
APR Rental Plant 70 70 70 70 70 70 70 70 70 70 70 70
Eskom (Imports) 300 300 300 300 300 300 300 100 100 100 100 100
Morupule B 132 0 132 132 264 264 264 264 264 396 396 396
Morupule A 0 0 0 0 0 0 0 0 0 0 0 0
Peak Demand 500 520 530 530 550 580 580 570 560 550 540 500
0
100
200
300
400
500
600
700
800
Cap
acit
y (M
W)
Monthly Capacity (MW) 2013
Total Supply 592 460 592 592 724 724 724 524 524 656 656 656
Peak Demand 500 520 530 530 550 580 580 570 560 550 540 500
Capacity Balance 92 -60 62 62 174 144 144 -46 -36 106 116 156
Assumptions:
•Units available at Morupule B: 1 in Q1; 2 in Q2 and Q3; and 3 in Q4
•300 MW Imports from Eskom available
Jan Feb Mar Apri May Jun Jul Aug Sep Oct Nov Dec
Orapa 90MW 90 90 90 90 90 90 90 90 90 90 90 90
APR Rental Plant 70 70 70 70 70 70 70 70 70 70 70 70
Eskom (Imports) 100 100 100 100 100 100 100 100 100 100 100 100
Morupule B 132 132 132 132 264 264 264 264 264 396 396 396
Morupule A 0 0 0 0 0 0 0 0 0 0 0 0
Peak Demand 500 520 530 530 550 580 580 570 560 550 540 500
0
100
200
300
400
500
600
700
Ca
pac
ity
(MW
)
Monthly Capacity Balance 2013
Total Supply 392 392 392 392 524 524 524 524 524 656 656 656
Peak Demand 500 520 530 530 550 580 580 570 560 550 540 500
Capacity Balance -108 -128 -138 -138 -26 -56 -56 -46 -36 106 116 156
Supply – Demand Balance Outlook - 2013
Assumptions:
•Units available at Morupule B: 1 in Q1; 2 in Q2 and Q3; and 3 in Q4
•200 MW Imports from Eskom NOT available
BOTSWANA POWER GENERATION PLANS
Generation Projects Plan Capacity
(MW) Timing Remarks
132 2015 Refurbishment plan in progress Tenders closed in March 2013
600
2013
Commissioning in progress.
300
2016/17
Feasibility study done – Morupule B Phase 2 Units 5 & 6 Published in government gazette on 12th April 2013. Tenders (IPP) expected by April/May 2013. Procurement of Financial, Technical and Legal Advisors in progress.
300
2016/17
Tenders (IPP) expected by April/May 2013. Procurement of Financial, Technical and Legal Advisors in progress.
90
TBA
Conversion to 24hr operation on CBM. Timing of Commercial Availability of CBM in sufficient quality and quantity to operate a gas fired power station remains unknown.
Sources
Morupule A
IPP Brown Field
IPP Green Field
Coal Bed Methane
Morupule B
RENEWABLE ENERGY PROJECTS Capacity
(MW) Timing Remarks
100
2017/18
Bankable Feasibility completed in March 2013 100MW CSTP; Central Tower with 4hrs TES at Jwaneng
75MW
TBA
REFIT Tariff study completed in 2011 Capacity:5kW to 5MW (Solar, Biomass, Biogas) Awaiting Cabinet Approval
1.3MW 2012 PV Pilot Project on-grid in operation since August 2012 (Japanese Grant Funding)
Located at Phakalane, Gaborone
Sources
Solar Thermal
Draft Energy Policy requires that 15% and 25% of the Electricity
Demand be met from Renewable Energy Resources by 2016 and 2030 respectively.
• Central Receiver with Molten Salt as the heat transfer and storage medium.
• 100 MWe with 4hrs Thermal Energy Storage
• The plant will be dry cooled or hybrid cooled designed to optimise water usage.
• All auxiliary power will be sourced from the National grid
• Life of plant will be a minimum of 25 years.
• Located at Jwaneng
• COD: 2017/18
• Project Structure: IPP or PPP?
CSTP PLANT - JWANENG
Gemasola - Spain
BOTSWANA’S SUPPLY – DEMAND BALANCE OUTLOOK
Botswana’s Supply – Demand Balance Outlook
2012 2013 2014 2015 2016 2017 2018 2019 2020
Orapa 90MW 90 90 90 90 90 90 90 90 90
APR Rental Plant 70 70 0 0 0 0 0 0 0
Eskom (Imports) 350 100 100 100 0 0 0 0 0
IPP Green Field 0 0 0 0 132 264 264 264 264
Morupule B (5 & 6) 0 0 0 0 132 264 264 264 264
Morupule B 0 264 528 528 528 528 528 528 528
Morupule A 0 0 60 60 120 120 120 120 120
Peak Demand 580 644 681 711 744 773 854 877 902
0
200
400
600
800
1000
1200
1400
Cap
acit
y (M
W)
Capacity Balance (2013 - 2020)
Total Supply 510 524 778 778 1002 1266 1266 1266 1266
Peak Demand 580 644 681 711 744 773 854 877 902
Capacity Balance -70 -120 97 67 258 493 412 389 364
An export market will be required by 2016 if all projects are realised in order deal with surplus capacity
Demand Side Management Initiatives No Strategy Capacity
(MW) Remarks
1 Compact Fluorescent Lamps (CFL – Project)
30 820 000 CFLs Installed with positive impact on Peak Demand Reduction (Done)
2 Load Shifting (Water Heating Control)
30 Smart Metering Project in progress. Commercial Operation by May 2013. (Work In Progress)
TOTAL DSM CAPACITY 60MW Virtual Peaking Power Plant
Other DSM Measures: Tariff Restructuring (Time of Use; MVA Charges )
Incentives for Energy Conservation & Energy Efficiency)
BOTSWANA TRANSMISSION GRID DEVELOPMENT PLAN
Transmission Grid Constrains
GABORONE
Francistown
Maun
Selebi-Phikwe
S O U T H
A F R I C A
Z I M B A B W E
N A M I B I A
Matimba P/S
Delta
Thamaga
2x2
15
km4
7km
51km
Tsabong
52km
Morupule A
220kV
400kV
132kV
Phokoje
AK 6
Orapa
Isang
Tati30km
Morupule B
Katima
Lobatse
Kasane
Bulawayo
Spitzkop
Jwaneng
66kV
Sowa
Mowana
Pandamatenga
HwangeVictoria
ZAMBIA
Gantsi
25km
Kanye
HVDC Westcor
Livingston
Proposed Existing
Molepolole
DML
Heuningvlei
Omaere
Orapa – 90MWHana
Shakawe
BK11
3
Main Challenges to be addressed
1. Lack of Grid Access in the Northwest Region
2. Demand Growth Outstripping
Grid Capacity in the South
3. Inadequate Transmission
capacity to support new generation investments (IPPs and Public Sector)
Impact of Challenges 1. Suppression of Economic
development (mining) 2. Suppression of Coal Beneficiation 3. Unreliable Power Supply in the
South
System Peak Demand (26 June 2012)
GABORONE
Francistown
Maun
Selebi-Phikwe
S O U T HA F R I C A
Z I M B A B W E
N A M I B I A
Matimba P/S
Delta
Thamaga
2x215km
47km
51km
Tsabong
52km
Morupule A
220kV
400kV
132kV
Phokoje
Orapa
Isang
Tati30km
Morupule B
Katima
Lobatse
Kasane
Bulawayo
Spitzkop
Jwaneng
66kV
Sowa
Mowana
HwangeVictoria
ZAMBIA
Gantsi
Kanye
HVDC W estcor
Livingston
Existing
Molepolole
Heuningvlei
Omaere
Orapa – 90MW
Shakawe
301MW
49MW
14MW
7MW
42MW
54MW
78MW
3MW
1MW
Total System Load 578MW (593MW) Morupule A - 29MW Morupule B - 130MW Imports - 365 MW Emergency – 54MW
Transmission Grid Expansion Plan
GABORONE
Francistown
Maun
Selebi-Phikwe
S O U T H
A F R I C A
Z I M B A B W E
N A M I B I A
Matimba P/S
Delta
Thamaga
2x2
15
km
47
km
51km
Tsabong
52km
Morupule A
220kV
400kV
132kV
Phokoje
AK 6
Orapa
Isang
Tati30km
Morupule B
Katima
Lobatse
Kasane
Bulawayo
Spitzkop
Jwaneng
66kV
Sowa
Mowana
Pandamatenga
HwangeVictoria
ZAMBIA
Gantsi
25km
Kanye
HVDC Westcor
Livingston
Proposed Existing
Molepolole
DML
Heuningvlei
Omaere
Orapa – 90MWHana
Shakawe
BK11
3
ZIZABONA
SOUTHERN SYSTEM
NORTH WEST
Gaborone East
S O U T H
A F R I C A
Gaborone Central
Innovation Hub
Phakalane
220kV Line
132kV Line
Tlokweng
Free Zone
ISANG
Government Enclave
Gaborone South
Spitzkop
Airport Road
Rakola
KEY
SOUTHERN SYSTEM REINFORCEMENT & EXPANSION PLAN
Thamaga
Segoditshane
Proposed Existing
Molepolole
Mogoditshane
Dwaalboom Ramotswa
Mochudi
Broadhurst
Woodhall
Kgale View
Substation
Mmakgodumo
Kanye
Lobatse
Substation
Jwaneng
From Morupule
400kV Line
ZIZABONA PROJECT
To Maun
PROJECT TIMING BENEFIT
North West Grid Extension (400/220/132kV)
2013 - 2017 New Customers (Mining)
ZIZABONA 2013 - 2016 Regional Access
Rakola 220/132kV S/S & Lines 2013 - 2015 Secure and Power Supply Quality
Ramotswa 132/11kV S/S & lines 2014 - 2015 Secure and Power Supply Quality
Mochudi 132/33kV S/S & lines 2014 - 2015 Secure and Power Supply Quality
Tlokweng 132/11kV S/S & lines 2014 - 2015 Secure and Power Supply Quality
Govt. Enclave 132/11kV S/S and cables
2017 -2018 Secure and Power Supply Quality
BOTSWANA TRANSMISSION PROJECTS FOR FINANCING
THE SOUTHERN AFRICAN REGION POWER SUPPLY OUTLOOK
Dem Rep of Congo Congo Gabon
Luanda
Windhoek
Lusaka
Harare
Lilongwe
Nairobi
Dar es Salaam
Gaborone Pretoria
Johannesburg
Cape Town
Maputo Mbabane
Kinshasa Brazzaville
Angola
Tanzania
Kenya
Mozambique
South Africa
Swaziland
Lesotho
Namibia
Zambia
Botswana
Zimbabwe
Malawi
Rwanda
Burundi
H
H
H
H
H
H
H
H
H
H H
H
H
H H
H
P
H
H
T
T
T
T
T
T T T
T T T T T T
T
T
H H
H
T H
P
N
H H
H
P
T
Hydro station
Pumped storage scheme Thermal Station
Existing
Planned
1. 12 Member Countries
9 Operating 3 Non Operating 2. IPPs & ITC
Membership 3. Bilateral Contracts & Day Ahead Market 4. IGMOU, IUMOU &
ABOM
THE SAPP INTERCONNECTION
Non - Operating Members
Operating Members
KEY Total Declared 48,762MW Peak Demand 50,636MW Deficit 1874MW
SAPP – REGIONAL SUPPLY SITUATION
No. Country Utility
Installed
Capacity
[MW] As at
Jan 2013
Available
Capacity
[MW]
Jan 2013
Suppressed
Demand &
Forecast
Demand
Capacity
Shortfall
including
reserves,
MW
Calculated
Reserve
Margin, %
1 Angola ENE 1,793 1,480 1341
2 Botswana BPC 352 292 604
3 DRC SNEL 2,442 1,170 1398
4 Lesotho LEC 72 72 138
5 Malawi ESCOM 287 287 412
6 Mozambique EDM /HCB 2308 2,279 636
7 Namibia NamPower 393 360 635
8 South Africa Eskom 44,170 41,074 42416
9 Swaziland SEC 70 70 255
10 Tanzania TANESCO 1380 1,143 1444
11 Zambia ZESCO / CEC/LHPC 1,870 1,845 2287
12 Zimbabwe ZESA 2,045 1,600 2267
57,182 51,672 53,833 (7,742) -4.2%
53,722 48,762 50,636 (7,111) -3.8%
TOTAL SAPP
Total Interconnected SAPP
DEMAND AND SUPPLY SITUATION
COMMITTED GENERATION PROJECTS (NEW &
REHAB)
No Country
2013 2014 2015 2016 TOTAL
1 Angola 0 645 550 2415 3,610
2 Botswana 600 - 132 300 1032
3 DRC 55 - 580 - 635
4 Lesotho - 25 300 - 325
5 Malawi 64 - - - 64
6 Mozambique - 150 300 300 750
7 Namibia 60 - - - 60
8 RSA 923 3,105 2,543 1,322 7,893
9 Swaziland - - - - -
10 Tanzania 60 160 500 1,110 1,830
11 Zambia 230 315 600 164 1,309
12 Zimbabwe - 300 690 900 1,890
1,992 4,700 6,063 6,511 19,398 TOTAL
NEW GENERATION CAPACITY, MW
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
2012 2013 2014 2015 2016 2017 2018
MW
Planned Capacity vs Forecast , MWAll SAPP Members
Forecast Capacity Planned
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
2012 2013 2014 2015 2016 2017 2018
MW
Planned Capacity vs Forecast , MWSAPP Operating Members Only
Forecast Capacity Planned
2016
Critical
For
Capacity
2017
Critical
For
Energy
SAPP PLANNED & REQUIRED CAPACITY
SAPP NEW GENERATION TECHNOLOGIES
(2013 -2018)
52.7%
27.3%
0.5%
17.0% 2.5%
MW Installed Capacity by Technology
Coal Hydro Solar Gas Wind
Introduction of Renewable Energy
(3% from renewable energy in 5 year period)