21
NamPower Electricity Supply Update A Presentation to the Chamber of Mines By Paulinus Shilamba MD: NamPower 22 May 2014

NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

  • Upload
    others

  • View
    28

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

NamPower

Electricity Supply Update

A Presentation to

the Chamber of Mines

By

Paulinus Shilamba

MD: NamPower

22 May 2014

Page 2: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Contents

Current power supply challenges

Power supply outlook

Projects (generation and transmission)

Electricity tariffs

Conclusion

Presentation to Chamber of Mines 22052014 2

Page 3: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Current power supply challenges

Regional power supply deficit

Reliance on imports (average 60%, up to 80% during dry seasons)

Regional transmission congestions (Zambia and RSA)

Aging power supply infrastructure and associated higher maintainance costs

Interruptible supply from Eskom as per the new arrangements

Challenges to accommodate IPPs without GRN guarantees

High economic growth and step loads (driven by the mining sector)

Termination of four (4) regional PPA’s within the next few months, namely:

ZESA: 150 MW – October 2014

Eskom Supplemental: 200 MW – April 2015

Aggreko: 115 MW – August 2015

Eskom Off Peak: 300 MW – April 2016

Presentation to Chamber of Mines 22052014 3

Page 4: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Power supply outlook

2014 – 2015

Electricity supply management challenges

Short-term critical supply (STCS) project implemented

Power supply situation manageable to a certain extend

2016 – 2017

Serious power supply deficits will be experienced

STCS project expanded to cover the deficit

A new 250 MW plant to be commissioned by mid 2016

2018 and beyond

New base load plant in operation

Namibia a net exporter of electricity

Presentation to Chamber of Mines 22052014 4

Page 5: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Hourly demand forecast: 2014-2036

-200

0

200

400

600

800

1000

1200

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

20

34

20

35

20

36

Peak D

em

an

d (

MW

)

Year

Non-Step Load Step Loads DSM Total Transmission Level Load

Page 6: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Electricity Supply Forecast

6

A new 250 MW plant being implemented to avoid load shedding in 2016 and 2017.

The plant to operate in peaking and stand by mode after 2018.

Presentation to Chamber of Mines 22052014

Page 7: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

NamPower Capacity Expansion Program

7

Refurbishment program New Power Stations STCS Project Transmission

• Van Eck refurbishment

• Ruacana Runner

Replacement

• The 250 MW power plant

• Kudu Gas Power Station

• Baynes Hydro Power Station

• Renewables

• IPPs

• PPA (Imports)

• Transmission Master Plan

• ZIZABONA

• Kudu Transmission

This capital investment program can only succeed with stakeholder assistance and support

Presentation to Chamber of Mines 22052014

Page 8: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

STCS Initiatives

NamPower generation plants (Van Eck, Ruacana)

Import arrangements (ZESA, Eskom, ZESCO, EDM and Aggreko)

PPA negotiations with Independent Power Producers (IPPs)

Solar IPP tender for procurement of 30MW in progress

Demand side management (N$350 million, 110 MW saving potential)

Free distribution of 1,000,000 domestic LED bulbs

Subsidised installation of 20,000 domestic solar water heaters

Demand reduction agreements and agreements with large

customers to gain access to their standby generators

Presentation to Chamber of Mines 22052014 8

Page 9: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

The 250 MW Power Plant

Emergency diesels has been one of the NamPower

options to ensure security of supply for Namibia

Latest analysis found a long term 250 MW plant

at Walvis Bay to be more viable and cost effective

in comparison with the short term option mainly

due to its additional long term benefits (post Kudu)

The project must be fast tracked and become operational by mid 2016

The plant will be developed through the Special Purpose Vehicle (SPV) in

which NamPower will have up to 30 percent equity (PPP Framework)

The tenders for the procurement of the strategic equity partner and project

developer is currently in the market

The plant to operate in base-load mode in 2016 and 2017, and in mid-merit /

peaking and standby mode in 2018 and beyond

The choice of fuel left to the market for proposal and determination

Presentation to Chamber of Mines 22052014 9

Page 10: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Kudu Gas to Power Project

• Flag ship project with significant benefits

• FID by mid 2014, FC by December 2014

and commercial operation by 2018

• Milestones achieved since September 2012

Most outstanding issues resolved

PDA signed with upstream parties

Joint Development Agreement (JDA) and PPA Term sheet signed with CEC

PPA and Tx connection negotiations with CEC and Eskom on-going

Evaluation of tenders for procurement of Coordination Bank, EPC, SEP and

O&M contractors at advanced stage and to be awarded in June 2014

Document with quantification of GRN guarantees submitted to GRN

Negotiation of GSA with Upstream parties at an advanced stage

Discussions at an advanced stage with Namdeb/Debmarine for the allocation of

site and services, and with MME for de-proclamation of the plant site

GRN allocation of N$1,6 billion for Kudu in the current budget cycle appreciated

Presentation to Chamber of Mines 22052014 10

Page 11: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Impact of Kudu on the economy

Electricity Supply: Namibia becomes a net exporter of electricity

GRN income: Approximately N$1billion in the form of royalties, taxes and dividends per year

Job Creation

Upstream: Not many during construction, but ±200 permanent jobs during operation

Downstream: ± 1500 jobs during construction and 70 permanent jobs during operation

Other Direct and Indirect Project Impact

Housing, roads and other infrastructure expansion and upgrade at Oranjemund

Increased utilization of the Luderitz harbour

Impact on Secondary Industry:

Catering

Trade

Transportation/logistic services

Cleaning services

Financial services, etc

11 Presentation to Chamber of Mines 22052014

Page 12: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Baynes

• 600 MW Hydro power project on the Kunene River

• 300 MW for Namibia

• Joint Venture project between the governments of

Angola and Namibia

• Techno-economic & EIA studies completed and

approved by the PJTC

• Project found to be viable by the PJTC

• Submission soon to be made to the two

governments of Angola and Namibia with

recommendations for final approval

• Project cost: U$1,3 billion (include compensation but excludes supporting

infrastructure such as transmission, roads, rails, runways and housing)

Presentation to Chamber of Mines 22052014 12

Page 13: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Key Transmission Projects

Zizabona

Linking Zimbabwe, Zambia, Botswana and Namibia

Joint Venture project by the four utility companies

SPV registered in Namibia (NP a hosting utility)

Shareholders, Wheeling and Power Supply

Agreements to be concluded in due course

Project cost U$250 million

Expected operational date early 2018

Transmission master plan

High demand growth especially in Northern Namibia

Upgrading of transmission backbone to 400kV

Estimated initial investment cost of approximately

N$ 7,3 billion

Presentation to Chamber of Mines 22052014 13

Page 14: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

14

2014/2015

2015/2016

2016/2017

2017/2018

2018/2019

2022/2023

> 2023

SVC

Rundu Cuito 132kV

2015/2016

West Coast strengthening

2014/2015

Omatando strengthening

Ph 1: 2013/2014

Ph 2: 2015/2016

Auas Gerus 400kV

[2016/2017 2019/2020]

Gerus Otjikoto 400kV

(Operate at 220kV)

2014/2015

Omatando Otjikoto 400kV

2023

Baynes Integration

> 2023

Kudu Transmission

2017/2018

2nd Auas Kokerboom 400kV

2018/2019

Caprivi Link Bipole

Auas Omburu Gerus 400kV

, >2019

Kokerboom Upington 400kV

2022/2023

Page 15: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Electricity tariffs

Electricity pricing in Namibia is the responsibility of the ECB and is set in

accordance with GRN Policy which states that tariffs should be:

Cost reflective

Reflect the long-run marginal cost of supply

Based on sound economic principles

Only through these principles will NamPower be able to be sustainable, keep

lights on through out and ensure that:

The national economy is protected against un-served energy

The new power projects are implemented and commissioned on time

The ESI remain sustainable

NB: Having electricity at cost reflective tariffs is far cheaper and better for

the economy than blackouts or no electricity at all (darkness)

Presentation to Chamber of Mines 22052014 15

Page 16: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Presentation to Chamber of Mines 22052014 16

NamPower energy supply cost (nominal N$)

Page 17: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Main Cost drivers

Investment in new generation and transmission infrastructure (N$18 billion)

Reinvestment in aging infrastructure (equipment replacement)

High cost of import contracts

Devaluation of local currency against US dollar

Higher returns by the private sector (IPPs)

Introduction of renewable energy generation (initially)

Increased use of coal & diesel (fuel costs increases higher than inflation)

Interruptible supply from Eskom

Supplier of last resort

Presentation to Chamber of Mines 22052014 17

Page 18: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Presentation to Chamber of Mines

22052014

18

Page 19: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Presentation to Chamber of Mines 22052014 19

Cumulative shortfall: N$ 2.3 billion

Cost reflective shortfall for 2014/15

addressed through GRN fuel

subsidy of N$170 million

It is not clear if GRN will continue with the principle of tariff subsidy to enable electricity price

adjustments to follow the lower path over the next 4 years or not.

Page 20: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

Conclusion

• Namibia will continue to experience power supply deficits, and keeping the lights on will

remain challenging until the commissioning of Kudu in 2018

• In 2014 and 2015 the power supply situation will to a certain extend be manageable.

However, serious power supply deficits will be experienced in 2016 and 2017. This

deficit will be addressed through the STCS program (including the 250 MW plant)

• During the next 4 to 5 years NamPower will invest N$18 billion in new power supply

projects. During the same period we shall also rely on more costly import contracts to

ensure security of supply. Electricity tariffs will therefore continue to raise at a high rate

per annum after which they will stabilize with the introduction of Kudu in 2018

• NamPower has so far been successful in keeping the lights on thanks to the support

and cooperation from its stakeholders. We assure the mining community that with this

continued support NamPower will be able to continue to deliver on its national mandate

of powering the nation and beyond

• As usual we therefore request all our customers, especially the mining community, to

continue saving at least ten (10) percent on their energy use, particularly during peak

periods, i.e from 07h00 to 10h00 and from18h00 to 21h00

Presentation to Chamber of Mines 22052014 20

Page 21: NamPower Electricity Supply Update€¦ · Linking Zimbabwe, Zambia, Botswana and Namibia Joint Venture project by the four utility companies SPV registered in Namibia (NP a hosting

End

Thank you

21 Presentation to Chamber of Mines 22052014