HUDSON SCHOOL DISTRICTHUDSON, WISCONSINBRAY PROJECT NO. 3210
Wednesday | September 2, 2015
POTENTIAL SOLUTIONS COMPARISON
AUDITORIUM
#1 - New 9-12 High School
- 6-8 at Current Middle School- 6-8 at Current High School
9th-12th Grades
1,800 / 2,000
New 9-12 High School To Be Determined 6th-8th Grades
600 / 675 No Work Existing Site 6th-8th Grades
600 / 675 Upgrades & Renovations Existing Site New Auditorium Included at New High School / Existing to
Remain at HHS
#2 - New 10-12 High School
- 6-7 at Current Middle School- 8-9 at Current High School
10th-12th Grades
1,350 / 1,500
New 10-12 High School
Current HMS/Hudson Prairire + Potential Additional Adjacent
Property
6th-7th Grades
800 / 900 No Work Existing Site 8th-9th Grades
850 / 950 Upgrades & Renovations Existing Site New Auditorium Included at New High School / Existing to
Remain at HHS
#2a - New 10-12 High School
- 6-7 at Current Middle School- 8-9 at Current High School
10th-12th Grades
1,350 / 1,500
New 10-12 High School To Be Determined 6th-7th Grades
800 / 900 No Work Existing Site 8th-9th Grades
850 / 950 Upgrades & Renovations Existing Site New Auditorium Included at New High School / Existing to
Remain at HHS
#3 - New 10-12 High School
- 6-9 at Current Middle School- 6-9 at Current High School
10th-12th Grades
1,350 / 1,500
New 10-12 High School To Be Determined 6th-9th Grades
825 / 925 No Work Existing Site 6th-9th Grades
825 / 925 Upgrades & Renovations Existing Site New Auditorium Included at New High School / Existing to
Remain at HHS
#4 - New 11-12 High School
- 6-7 at Current Middle School- 8-10 at Current High School
11th-12th Grades
900 / 1,000
New 11-12 High School To Be Determined 6th-7th Grades
800 / 900 No Work Existing Site 8th-10th Grades
1,300 / 1,450
Upgrades & Renovations Existing Site Upgrades to Existing
#5 - New 6-7 Middle School
- 8-9 at Current Middle School- 10-12 at Current High School
6th-7th Grades
800 / 900 New 6-7 Middle School District-Owned Land on County Highway
UU
8th-9th Grades
850 / 950 No Work Existing Site10th-12th Grades
1,350 / 1,500
Upgrades & Renovations Existing Site Upgrades to Existing
#6 - New 6-8 Middle School
- 6-8 at Current Middle School- 9-12 at Current High School
6th-8th Grades
600 / 675 New 6-8 Middle School District-Owned Land on County Highway
UU
6th-8th Grades
600 / 675 No Work Existing Site 9th-12th Grades
1,800 / 2,000
Additions, Upgrades & Renovations + Synthetic Turf
Phy Ed & Practice Field Existing Site Upgrades to Existing
#7 - New 8-9 Middle School
- 6-7 at Current Middle School- 10-12 at Current High School
8th-9th Grades
850 / 950 New 8-9 Middle School District-Owned Land on County Highway
UU
6th-7th Grades
800 / 900 No Work Existing Site10th-12th Grades
1,350 / 1,500
Upgrades & Renovations Existing Site Upgrades to Existing
New
Ele
m
Opt
ion
s
#8
- New Elementary School to Replace Hudson Prairie
- 6-8 at Current Middle School expands into Hudson Prairie Space
- 9-12 at Current High School
Kinder. -5th Grades
588 New Elementary School to
House Relocated Hudson Prairie Elementary Students
District-Owned Land on County Highway
UU
6th-8th Grades
1,200 / 1,350
Minor Renovation of Hudson Prairie to Support Middle School
Students / Curriculum Existing Site
9th-12th Grades
1,800 / 2,000
Additions, Upgrades & Renovations + Synthetic Turf
Phy Ed & Practice Field Existing Site Upgrades to Existing
#9 - No New Schools
- 6-8 at Current Middle School- 9-12 at Current High School
6th-8th Grades
1,200 / 1,350
Additions & Renovations Existing Site 9th-12th Grades
1,800 / 2,000
Additions, Upgrades & Renovations + Synthetic Turf
Phy Ed & Practice Field Existing Site Upgrades to Existing
#10
- Close Hudson Prairie Elementary- Reconfigure All Elem Attendance Areas- 6-8 at Current Middle School expands
into Hudson Prairie Space - 9-12 at Current High School
6th-8th Grades
1,200 / 1,350
Minor Renovation of Hudson Prairie to Support Middle School
Students / Curriculum Existing Site
9th-12th Grades
1,800 / 2,000
Additions, Upgrades & Renovations + Synthetic Turf
Phy Ed & Practice Field Existing Site Upgrades to Existing
#11
- 6th Grade Relocated to Elem Schools- Reconfigure All Attendance Areas
- 7-8 at Current Middle School- 9-12 at Current High School
7th-8th Grades
800 / 900 No Work Existing Site 9th-12th Grades
1,800 / 2,000
Additions, Upgrades & Renovations + Synthetic Turf
Phy Ed & Practice Field Existing Site Upgrades to Existing
S:\1- Current Projects\3210 - Hudson School District\4 Schematic Design\HudsonSD_OptionSummary_09-02-15_DRAFT.xls
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
New Stadium for Football, Soccer & Track, New Tennis Courts, and New Baseball and Softball
Fields at New High School Site
Complete Reconfiguration of All Attendance Areas and Additions to Existing Elementary Schools
Kinder. - 6th Grades
New
Mid
dle
Sch
ool O
ptio
ns
No
New
Bu
ildin
g/Si
te O
ptio
ns
HUDSON MIDDLE SCHOOL
Site / Location
Site / Location
Option Summary
Kinder. - 5th Grades
Grade Config.
Option Grouping & Number
No New Schools / Sites
New Stadium for Football, Soccer & Track, New Tennis Courts, and New Baseball and Softball
Fields at New High School Site
New Stadium for Football, Soccer & Track, New Tennis Courts, and New Baseball and Softball
Fields at New High School Site
New Stadium for Football, Soccer & Track, New Tennis Courts, and New Baseball and Softball
Fields at New High School Site
OUTDOOR ATHLETIC & REC. FIELDSNEW SCHOOL / OTHER
New Stadium for Football, Soccer & Track, New Tennis Courts, and New Baseball and Softball
Fields at New High School Site
New
Hig
h S
choo
l Opt
ion
s
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Grade Config.
Capacity Classrooms /
CorePotential Scope / Solution
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Potential Scope / SolutionSite /
Location
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Existing Stadium Upgrades = Synthetic Turf, Track, Bleachers & Support Building. Baseball &
Softball = Lights & Toilet Rooms. Existing HS Site = New Tennis Courts
Capacity Classrooms /
Core
Capacity Classrooms /
CorePotential Scope / Solution
Close Hudson Prairie and Complete Reconfiguration of All Elementary Attendance Areas and 6 Classroom
Addition to River Crest
Potential Scope / Solution / Location Grade Config.
Potential Scope / Solution
HUDSON HIGH SCHOOL
DRAFT
Recommended