Planta Procesadora de Cafe RED

Preview:

DESCRIPTION

Red de proyecto de una planta ara procesamiento d ecafe

Citation preview

FS FS FS

Elaboración del Plan de Riesgos

Start: Mon 03/11/14ID: 5

Finish: Fri 05/12/14Dur: 25 days

Res:

Elaboración del Plan de Compras

Start: Mon 20/10/14ID: 4

Finish: Fri 31/10/14Dur: 10 days

Res:

Elaboración del Plan de Cronograma

Start: Fri 03/10/14 ID: 3

Finish: Fri 17/10/14Dur: 11 days

Res:

Gerencia de Proyecto

Start: Fri 03/10/14 ID: 2

Finish: Thu 03/09/15Dur: 240 days

Comp: 0%

Inicio

Milestone Date: Fri 03/10/14

ID: 1

Planta Procesadora de Café

Start: Fri 03/10/14 ID: 0

Finish: Thu 03/09/15Dur: 240 days

Comp: 0%

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Elaboracion de Plan de Comunicacciones

Start: Mon 08/12/14ID: 6

Finish: Fri 26/12/14Dur: 15 days

Res:

Page 8

FS

FS

FS

FS

FS

FS

FF

Contratacion Firma de Ingenieria

Milestone Date: Mon 26/01/15

ID: 10

Diseño de Área de Procesamiento

Start: Mon 26/01/15ID: 12

Finish: Mon 23/03/15Dur: 41 days

Res:

Diseño de Patios de Cargue y Descargue

Start: Mon 26/01/15ID: 11

Finish: Mon 23/03/15Dur: 41 days

Res:

Diseño de Obra Civil

Start: Mon 26/01/15ID: 9

Finish: Mon 23/03/15Dur: 41 days

Comp: 0%

Seguimiento y Control

Start: Mon 29/12/14ID: 8

Finish: Thu 03/09/15Dur: 179 days

Res:

Entrega de Plan de Proyecto

Milestone Date: Fri 26/12/14

ID: 7

Page 9

Page 10

Page 11

FS

FS+14d

Estudio de Costos de Proveedor

Start: Fri 16/01/15 ID: 28

Finish: Thu 02/04/15Dur: 55 days

Res:

Estudio de Ubicación y Transporte a Fabrica

Start: Fri 16/01/15 ID: 27

Finish: Wed 18/03/15Dur: 44 days

Res:

Estudio de Proveedores

Start: Fri 16/01/15 ID: 26

Finish: Thu 02/04/15Dur: 55 days

Comp: 0%

Page 12

FS+2d

SS+7dFS+21d

Diseño de Procesos

Start: Tue 27/01/15ID: 32

Finish: Mon 23/02/15Dur: 20 days

Res:

Page 13

FS

Page 14

Page 15

FSEntrega de Planos

Milestone Date: Mon 23/03/15

ID: 13

Page 16

FS

FS

Consecución de Licencias de Construcción

Start: Tue 24/03/15ID: 14

Finish: Mon 25/05/15Dur: 45 days

Comp: 0%

Tramite de Licencias de Construccion

Start: Tue 24/03/15ID: 15

Finish: Mon 25/05/15Dur: 45 days

Res:

Page 17

Page 18

Page 19

Nomogramas

Start: Thu 05/02/15ID: 38

Finish: Thu 12/02/15Dur: 6 days

Res:

Planes de Manejo Ambiental

Start: Thu 05/02/15ID: 37

Finish: Thu 05/03/15Dur: 21 days

Res:

Plan de Gestión Ambiental

Start: Thu 05/02/15ID: 36

Finish: Thu 03/09/15Dur: 151 days

Comp: 0%

Page 20

Análisis de Perfiles Administrativos

Start: Tue 24/02/15ID: 35

Finish: Tue 31/03/15Dur: 26 days

Res:

Análisis de Perfiles de Planta

Start: Tue 24/02/15ID: 34

Finish: Tue 31/03/15Dur: 26 days

Res:

Estudio de Perfiles

Start: Tue 24/02/15ID: 33

Finish: Tue 31/03/15Dur: 26 days

Comp: 0%

Page 21

Page 22

Page 23

FS

FS

FS

Obra Civil

Start: Tue 26/05/15ID: 17

Finish: Fri 28/08/15Dur: 69 days

Comp: 0%

Entrega de Licencias

Milestone Date: Mon 25/05/15

ID: 16

Elaboracion de Obra Civil

Start: Tue 26/05/15ID: 18

Finish: Fri 28/08/15Dur: 69 days

Res:

Page 24

Page 25

Estudio de Clientes

Start: Fri 03/04/15 ID: 29

Finish: Mon 11/05/15Dur: 27 days

Comp: 0%

Estudio de Ubicación y Transporte al Cliente

Start: Fri 03/04/15 ID: 30

Finish: Fri 01/05/15Dur: 21 days

Res:

Page 26

Estudio de Precios de venta

Start: Tue 07/04/15ID: 31

Finish: Mon 11/05/15Dur: 25 days

Res:

Page 27

Page 28

Page 29

Page 30

FS

Entrega de Obra civil

Milestone Date: Fri 28/08/15

ID: 19

Montaje de Maquinas

Start: Fri 28/08/15 ID: 20

Finish: Thu 03/09/15Dur: 4 days

Comp: 0%

Page 31

Recibo de Maquinas

Milestone Date: Fri 28/08/15

ID: 21

Montaje de Trilladora

Start: Mon 31/08/15ID: 22

Finish: Wed 02/09/15Dur: 3 days

Res:

Montaje de Molino

Start: Mon 31/08/15ID: 23

Finish: Wed 02/09/15Dur: 3 days

Res:

Montaje de Horno

Start: Mon 31/08/15ID: 24

Finish: Thu 03/09/15Dur: 4 days

Res:

Montaje de Empacadora

Start: Mon 31/08/15ID: 25

Finish: Thu 03/09/15Dur: 4 days

Res:

Page 32

Page 33

FS Fin

Milestone Date: Thu 03/09/15

ID: 39

Page 34

Page 35

Critical

Noncritical

Critical Milestone

Milestone

Critical Summary

Summary

Critical Inserted

Inserted

Critical Marked

Marked

Critical External

External

Project Summary

Highlighted Critical

Highlighted Noncritical

Page 36

Project: Planta Procesadora de CaDate: Fri 03/10/14

Recommended