Lecture 5 - Delta UnivDr. A.Helba CIV 416 E 12 Arrangement of Radial Steel A sr 2- calculate and...

Preview:

Citation preview

  • Nov-15

    Dr. A.Helba CIV 416 E 1

    A Guide to Designing Reinforced Concrete Water Tanks

    Helba AlaaDr.

    Analysis of Circular R.C. slabs (Roofs – Floors)

    Design of simply supported circular roof slabs

    Arrangement of st. rft. in circular s.s. slab

    Illustrative Example

    Lecture 5

  • Nov-15

    Dr. A.Helba CIV 416 E 2

    R R s.s. slab

    Fixed slab

  • Nov-15

    Dr. A.Helba CIV 416 E 3

    Moments and St. Rft. in Circular R.C Plates

    Ast

    Asr

    Asmax

    Steel required:

    As max , Asr radial steel and Ast tangential

    x

    Y

    r

    t

    Moments:

    M max

    Mr radial moment Mt tangential

    R = radius

    R

    Analysis of circular Simply Supported Slab

    • in a circular plate Radial Moments

    (Mr) and Tangential Moments (Mt) could be calculated from the following equations:

    Mr max = M+ve

    max

    B.Mr .D

    at center:

    2

    (3 )16

    wR

    Mredge=0

  • Nov-15

    Dr. A.Helba CIV 416 E 4

    Analysis of circular Simply Supported Slab

    • Tangential Moments (Mt)

    Mt max = M+ve

    max

    B.Mt.D

    at center: 2

    (3 )16

    wR

    At edge: Mt edge

    2

    (2 2 )16

    wR

    Moments at any point in S. S. circular Slab

    22

    22

    [(3 )(1 )]16

    [(3 ) (1 3 ) ]16

    = Poisson's ratio

    r and =

    R

    r

    t

    wRM

    wRM

    ( = 0 at center , = 1 at edge)

  • Nov-15

    Dr. A.Helba CIV 416 E 5

    • For concrete assume n = 0.2 then :

    2

    2

    2

    2

    (1

    (1 )5 2

    )5

    t

    r

    and

    wRM

    wRM

    + ve tension downside

    - ve tension upperside

    Table XII

    coeffs. for Moment in Circular Slab / No Center

    Support / Uniform Load / Fixed Edge

    0.0

    R

    0.1

    R

    0.2

    R

    0.3

    R

    0.4

    R

    0.5

    R

    0.6

    R

    0.7

    R

    0.8

    R

    0.9

    R

    1.0

    R

    Fixed

    Fixed

  • Nov-15

    Dr. A.Helba CIV 416 E 6

    Asr radial steel to resist Mr

    PLAN SEC. ELEV.

    Asr

    Ast r R

    Asr Ast

    Mr Mr

    Ast tangential steel to resist Mt

  • Nov-15

    Dr. A.Helba CIV 416 E 7

    Calculation and arrangement of Asr in circular S.S. slab

    The radial steel is distributed on the perimeter which varies along the slab radius , the radial steel should be calculated by its total amount.

    Calculate the radius (r) at which Asr (total) is maximum

    by putting

    0r totaldM

    dr

    (r) for Maximum Asr (total)

    (

    22 22

    2 3

    2(1 )(2 )

    5 5

    2

    5

    r total

    wR wR rM r r r

    R

    wR r r

    ( 2 22

    3 05

    10.577

    3 3

    r totaldM w R rdr

    Rr

  • Nov-15

    Dr. A.Helba CIV 416 E 8

    Maximum Mr total For simply supported circular slab the

    total radial steel (the maximum area) is only calculated at = 1/√3 = 0.58

    2 22

    2 3 3

    1

    3

    2(1 )(2 ) ( )(2 )

    5 5 3

    4 4

    15 16.515 3

    r total

    rat

    R

    wR wRM r r

    rwR wR wD

    Example: Design of Roof Slab

    Data: Dtank(inner)=7.5 m , H=5 m, fcu=25 N/mm2 ,mild steel

    Loads on roof slab:

    Assume troof = D / 50 = 7500 / 50 = 150 mm

    own wt. of slab = 0.15 X 25 = 3.75 kN/m2

    covering = 1 kN/m2 (may be ass. 0.75 to 1 kN/m2)

    L . L = 1 kN/m2 (inaccessible roof)

    w roof = 5.75 kN/m2

    wu = 1.5 w = 1.5 X 5.75 = 8.625 kN/m2

    assume twall (for practical purposes) = H/20 = 5/20 = 0.25 m

    radius of roof slab Rroof = 7.5/2 + 0.25 = 4 m

  • Nov-15

    Dr. A.Helba CIV 416 E 9

    Moments in Cicular Roof Slab • Maximum Moments:

    at middle of slab

    • Radial Moment Mr :

    Mr max +ve = wuR2/5 = 8.63 X 42 / 5 = 27.6 kN.m

    • Tangential Moment Mt :

    Mt max +ve = Mr max +ve = 27.6 kN.m

    mm

    bf

    R

    Md

    c

    u 88

    )1000(5.1

    25)214.0(

    106.27 6

    cumax

    min

    As max

    Asr radial steel Ast tangential st. Asmax square mesh at center in 0.25Dx0.25D

    Steel Rft. in circular roof slab

    Ast

    Asr

    As max

  • Nov-15

    Dr. A.Helba CIV 416 E 10

    Calculation of st. rft. in circular roof slab 1- calculate As mesh at center As max(at middle)=Mumax/ [bcrd(1-a/2)fy/s] = 27.6 X 106 / [ 0.9 X 110 X (1 - 0.23/2)(240/1.15)]

    = 1511.4 mm2 chosen 8 f 16 / m' as a square mesh in middle area of 2m X 2m (area of 0.5 R X 0.5 R)

    (Check As min= 0.25 % Ac = 2.5 t = 2.5 x 150 = 375 mm2)

    mesh 16 f 16 in 2m

    2- calculate and arrange the radial steel Asr - Calculate Maximum Total Radial Steel Asr tot max

    Mur total max. = 8.625 X 83 / 16.5 = 267.7 kN.m

    3

    .16.5

    r total MAX

    wDM

    62

    , . . : 23

    12

    267.7 1012607

    240 0.1421 110

    1.15 2

    rusr total

    y

    cr

    s

    cr

    M RA N B to get use b

    fd

    mm

    a a

    b

    b

    Trial 1 : chosen 112 f 12 (with bcr =1)

  • Nov-15

    Dr. A.Helba CIV 416 E 11

    Arrangement of Radial Steel Asr At circle ❷ 112 f 12 (Asr tot at r2 =

    0.58 x 4 = 2.32 m) are distributed along a perimeter = 2 r2 = 14.6m at spacing s2 = 14600/112 = 130 mm < 200 mm

    At the support (outer edge of roof

    slab) R = 4m, and perimeter = 2 R = 25.13 m.

    Spacing of 112 bars at the edge circle ❸s3 = 25130/112 = 224.4 mm > 200 mm, in this case the solution is to increase the required number of bars so as to keep sedge to 200 mm, so,

    nreq = 25130/200 = 125.7 use 126 bars spaced with: sat (r=0. 58R) =2 (0.58R)/126=

    14577/126 = 115.7 mm.

    Trial 2: chosen 126 f 12

    Arrangement of Radial Steel Asr In order to cut off half the number of radial bars (63 out of 126) try the

    following: 1- calculate the perimeter required to limit spacing of bars to 80 mm, = 126

    x 80/1000 = 10.08 m at r = 10.08/2 = 1.6 m (at circle ❹ you can use 126/2 = 63 bars at = 0.4)

    Then As 4 total available = 63 x 113 = 7119 mm2

    Check with Asr required at circle ❹ as follows: - Calculate Mr4 at r4 = 1.6 m, = 0.4 Mr4 = wR

    2(1-2)/5 = 8.63(4)2[1-(.4)2]/5 = 23.2 kN.m Mr4 total = (2 r4) x 23.2 = 233.2 kN.m Then As 4 total required This trial cannot be done as As 4 total required >> As 4 total available .. Cancel it ..

    624 233.2 10 10807

    240 0.121 1101

    1.15 22

    ru

    ycrcr

    s

    Mmm

    fd

    a bb

  • Nov-15

    Dr. A.Helba CIV 416 E 12

    Arrangement of Radial Steel Asr 2- calculate and check Asr required at mesh outer perimeter

    (at circle ❶ , r1 = R/4 = 1 m, = 0.25 and perimeter = 6.28 m):

    - calculate Mr1 at r1 = 1.0 m , = 0.25: Mr1 = wR

    2(1-2)/5 = 8.63(4)2[1-(.25)2]/5 = 25.9 kN.m Mr1 total = (2 r1) x 25.9 = 162.7 kN.m Then As 1 total required Then Asr1 total required (7540 mm2) > As cut off avilable (7119 mm2) It needs 67 f 12 at s1 = 6280/67= 94 mm > 80 mm o.K That means using 67 x 2 = 134 bars Ld = 40 f = 40 x 12 = 480 mm use extension 0.5 m for overlap.

    621 162.7 10 7540

    240 0.121 1101

    1.15 22

    ru

    ycrcr

    s

    Mmm

    fd

    a bb

    Finally: chosen 134 f 12

    Arrangement of Radial Steel Asr Finally: Then Asr total required = 134 f 12 to be arranged as follows: 67 f 12 with length L1 and another 67 f 12

    with length L2 : L1 = R – r1 – cover + v

    al part + 2 hook = 4 – 1 - .030 + (0.15 -2 x .03) + 2 X 6f = 3.204 m L1 = 3.25 m L2 = R – r1 – cover + ld + 2 hook = 4 – 1 - .030 + 0.5 + 2 x 6 x 0.012 = 3.614 m

    L2 = 3.75 m

  • Nov-15

    Dr. A.Helba CIV 416 E 13

    3- calculate and arrange the tangential steel Ast - Calculate Maximum tangential Steel Ast max/m’ (at r = R/4 , r = 0.25)

    Mtu1 = wuR2(1-1

    2/2)/5

    =8.625 X 42 (1 – 0.252/2)/ 5 = 26.74 kN.m 6

    11

    27.7 10

    240 0.121 1101

    1.15 22

    tust

    ycrcr

    s

    MA

    fd

    a bb

    chosen 7 f 16 / m’ = 1377 mm

    2 (bcr = 0.9)

    And use 6 f 16 / m’ at Mt = 1206 x 0.9 x (240/1.15) x 0.95 x110 = 23.67 kN.m (corresponding to 2 = 2(1-5M/wR2) = 0.29 , = 0.535) at r5 = .535 x 4 = 2.14 m and so on .) starting from r = 2.2 m .

    150 mm

    PLAN Roof Slab rft.

    3.75 m

    3.75 m

    0.25 m

    0.25 m

  • Nov-15

    Dr. A.Helba CIV 416 E 14

    SEC. ELEV.

    Roof Slab rft.

    5.0 m

    0.15 m

    square mesh 16 f 16 in 2m

    C.L.

    Alternative choice and Arrangement of Radial Steel Asr

    (Note: if f 16 mm is chosen bcr = 0.9 and As = 13954 mm2 )

    At circle ❷ 70 f 16 (Asr tot at r2 = 0.58 x 4 = 2.32 m) are distributed along a

    perimeter = 2 r2 = 14.6m at spacing s2 = 14600/70 = 209 mm > 200 mm then the number of f 16 mm bars should be increased from 70 to 14600/200 = 73 bars to keep spacing of bars =< 200 mm)

    Check At the support (outer edge of roof slab) R = 4m, and perimeter =

    2R = 25.13 m. Spacing of 73 bars at the edge sedge = 25130/73 = 344 mm >> 200 mm, in

    this case the solution is to use 73 f 12 amid the other number of bars so as to get sedge = 25130/146 = 172 mm < 200 mm, so, these additional 73 f 12 are ended at s = 200mm at r = r2 = 2.32 m

    L = R – r2 = 4 – 2.32 = 1.68 m use L = 1.75

    Trial 1 : chosen 70 f 16 (with bcr = 0.9)

    Trial 2 : chosen 73 f 16 & add 73 f 12

  • Nov-15

    Dr. A.Helba CIV 416 E 15

    Finally: Then Asr total required = 73 f 16 with length L1 and 73 f 12 with length L2 : L1 = R – r1 – cover + ld + 2 hook = 4 – 1 - .030 + 0.5 + 2 X 6f = 3.614 m L1 = 3.75 m L2 = R – r2 – cover + v

    al part + 2 hook = 4 – 2.32 - .030 + (0.15 -2 x .03) + 2 x 6 x 0.012

    = 1.884 m

    L2 = 2 m r2 = 2.3 m

    Alternative choice and Arrangement of Radial Steel Asr

    150 mm

    PLAN

    Roof Slab rft.

    3.75 m

    3.75 m

    0.25 m

    0.25 m

    Alternative choice and Arrangement of Radial Steel Asr

  • Nov-15

    Dr. A.Helba CIV 416 E 16

    Plan (Sec. under floor level) An elevated Tank (Floor rests directly on 4 Columns)

    D t 0.71 D

    Case 1 n = number of Columns = 4 or 6 or 8

    D H

    (+…. m) Hw

    SEC. PLAN

    SEC. ELEV.

    Case 1

    V (Tank Capacity) = (πD2/4)x Hw

  • Nov-15

    Dr. A.Helba CIV 416 E 17

    Loads on Wall and Floor of an elevated Tank

    (Floor rests directly on columns)

    Sec. Elev.

    D

    H

    t

    Water Pressure

    Dead Load (D.L.)

    Final B.M.D. on Walls and Floor

    1- An elevated Tank rests directly on Columns

    MFinal at connection >> MF wall Calculate MFinal at connection by

    Moment Distribution

    MFinal

    Floor structural system

  • Nov-15

    Dr. A.Helba CIV 416 E 18

    Options of wall thickness

    Uniform t Tapered t1/t2 Haunch t1/t2 2Haunches in wall &

    floor

    Case 1

    Sec. ELEV. An elevated Tank (Floor rests directly on Columns)

    t1 = twall at top

    t2 = twall at base

    t

    t t2

    t1

    tfloor tfloor

    Plan (Sec. under floor level) An elevated Tank (Floor rests on Beams on Columns)

    t 0.71 D D

    0.15 D Main Beam

    Paneled Beams

    Main Beam

    Case 2

    Wall act as a Deep Beam between columns

  • Nov-15

    Dr. A.Helba CIV 416 E 19

    Final B.M.D. on Walls and Floor

    2-An elevated Tank rests on Beams on Columns

    C.L

    MFwall

    M1

    M2

    MFinal at connection = MF wall

    Floor is divided to slabs with Mx & My

    Wall acts as D

    ee

    p B

    eam

    Floor structural system

    M1 & M2 From 3-mom. Eq.

    Plan (Sec. under floor level) An elevated Tank rests on Circular Beam on Columns

    D t 0.71 Db

    Case 3

    Db

    Db diameter of C.L. of Circular beam

    b=bbeam

  • Nov-15

    Dr. A.Helba CIV 416 E 20

    Plan (Sec. under floor level) An elevated Tank rests on Circular Shaft

    D t

    Case 4

    Dsh

    Dsh diameter of C.L. of Circular shaft

    tsh=thickness of shaft wall

    Final B.M.D. on Wall and

    Floor

    3- Elevated Tank rests on Circular Beam on Columns

    C.L

    MFwall

    Mr1

    Mr2 = Mt2 MFinal at connection = MF wall

    Mr1 = MF wall + M due to P wall + M due to floor cant. part

    Floor is circular slab with Mr & Mt (Use superposition)

    Floor structural system

    4- Elevated Tank rests on Circular Shaft

  • Nov-15

    Dr. A.Helba CIV 416 E 21

    Final B.M.D. on Wall and Floor

    An elevated Tank Floor rests directly on Columns

    Study of Case 1

    Tension and Shear in Wall and Floor

  • Nov-15

    Dr. A.Helba CIV 416 E 22

    Tension and Shear in Wall and Floor

    Final Results of B.M & N.F

    Mr

    Mt

    1

    2

    3 4

    Tring acts horizontally in Wall

  • Nov-15

    Dr. A.Helba CIV 416 E 23

    Distribution of Mr & Mt in Floor slab (Values from table XII)

    -0.15

    -0.1

    -0.05

    0

    0.05

    0.1

    0 0.2 0.4 0.6 0.8 1

    Mr

    Mt

    Ring Tension in wall for Different Base Conditions

  • Nov-15

    Dr. A.Helba CIV 416 E 24

    Sections 1 & 4 Tension due to B.M is on Air-Side (design as Cracked sec.)

    Open Tank 1

    4

    2 3

    Sections 2 & 3 Tension due to B.M is on Water-Side (design as uncracked sec.)

    1

    4

    2

    3

    An elevated Tank (Floor rests directly on Columns)

    B . M . D

    Case 1

    General Procedure for Design( 7 steps)

    • Assign the overall Dimensions for tank (D & H)

    • Consider the Connection (distribute DM– get Mf)

    • Define sections for design & design values (M,Q,N)

    • Calculate t for different sections

    & Choose proper thicknesses.

    • Calculate As required for different sections.

    • Arrange steel at sections and connections.

    • Draw steel arrangements in plan and elevation

Recommended