IEM Daily Field Report
Prepared By: John Bruscella IEM Representative
Page 1 of 4
Signed In Signed Out Southwest Brooklyn Marine Transfer Station
1824 Shore Parkway Brooklyn, New York 11214
Date: May 17, 2016 Inspector: John Bruscella Location /
Description:
Project #: URLI1401 Site Time: 0655 to 1530 Assigned by: SPD
Day Weather General Site Conditions
Monday Thursday Clear Snow Warm Clear
Tuesday Friday Overcast Windy Hot Muddy
Wednesday Rain Cold Temperature Range: 57 ºF to 64 ºF
General Contractor: Prismatic Development Corporation (PDC) Construction Manager: URS / LiRo
G/C Name: Richard Tonnensen CM Name: Michael Balarezo / Michael Pokorny
S/C&S/C Supervisor: NA CM Phone #: 917-983-5608 / 917-983-5616
Equipment and Machinery in Use(1):
Crane(s)
Elevating Work Platforms
Forklift with extendable arm (Lull)
Pile Driver
Water Tank Truck (1) List of equipment and machinery is based on field observations and is not inclusive of every equipment and machinery that may have been present at the site.
Personnel on Site(1):
Personnel Organization Personnel Organization
Personnel PDC Michael Balarezo URS / LiRo
Erdal Gurten Greeley and Hanson Mike Pokorny URS / LiRo
Robert Amrhein Certified Safety Nabil Saadi URS / LiRo
Nelson Mendez EnTech Roberto Vazquez URS / LiRo
Anthony Controneo Total Safety Consultant Victor Bogatyrev URS / LiRo
Personnel AEL, Presco, Giaquinto, Solar Inc.,
Stonebridge, Blue Diamond, Soil Solutions, Olympic Plumbing, National Fireproofing
Tom Karas URS / LiRo
Andrew Port Louis Berger
(1) List of personnel on site is based on field observations and is not inclusive of every personnel that may have been present at the site.
Observations:
Time Stamp Details
Time On Site: 6:55 am
6:55 am Four air monitoring stations were set up at perimeter locations specified by the CM, forming a quadrangle around the anticipated work area. According to EnTech, air monitoring is occurring at the four air monitoring stations beginning at 6:30 am. The air monitoring station locations are depicted on the Sketch.
7:00 am to 3:15 pm GC installing wooden forms around columns on the deck of the main building in the central section of the site. GC installing and removing wooden forms from around shear walls in eastern section of the site.
Day / Date: Tuesday / May 17, 2016 Client: URS / LiRo H2M Project No.: URLI1401
Prepared By: John Bruscella IEM Representative
Page 2 of 4
7:20 am to 3:15 pm
Stonebridge utilizing two cranes to erect structural steel in the western and central sections of the concrete foundation slab. Stonebridge utilizing elevating work platforms to install structural steel after being erected. Stonebridge welding structural steel in the western and southern sections of the site. Stonebridge fastening metal sheets onto the roof of the main building in the central section of the site.
7:00 am to 3:15 pm Presco bending rebar on the ramp in the northern section of the site and installing rebar on the second floor deck of the main building on the central portion of the site. Lull forklift utilized to move rebar.
7:00 am to 3:00 pm Solar installing conduit on the second floor of the main building on the concrete foundation slab.
7:00 am to 3:00 pm Olympic Plumbing installing drainage plumbing in the northern portion of the concrete foundation slab.
7:00 am to 3:00 pm Giaquinto building interior cinder block walls for the main building in the northern section of the concrete foundation slab. Cement mixing and concrete block cutting in the northeastern section of the concrete foundation slab. Giaquinto utilizing a Lull forklift to move materials around the site.
7:00 am to 3:00 pm Blue Diamond installing duct work throughout the first floor of the main building on the concrete slab in the northern section of the site.
7:00 am to 12:00 pm Soil Solutions welding and driving piles in the eastern section of the site.
7:00 am to 2:00 pm GC installing foam insulation on the northern external wall of the main building.
7:30 am to 10:00 am GC applying waterproofing paint to the external masonry in the northwestern portion of the site.
8:00 am to 10:00 am Flatbed truck and trailer carrying scaffolding enters the site through the gate and Stabilized Construction Entrance on 25th Avenue. Lull forklift utilized to unload scaffolding in the eastern section of the site.
9:30 am to 10:00 am & 12:00 pm to 12:30 pm
Site work stops for a work break.
3:30 pm Site work stops for the day. EnTech removes air monitoring stations.
Time Off-Site: 3:30 pm
General Observations:
According to EnTech, particulate matter and total organic vapors were not detected at concentrations greater than the action levels. The GC was observed implementing dust suppression at the site by wetting down the ground surface with water from the water tank truck at 7:30 am and 10:50 am.
Issues discussed this date with Construction Manager: None.
Persons Contacted: N/A
Status: N/A
Notes: N/A
IEM Daily Field Report
SKETCH
Prepared By: John Bruscella IEM Representative
Page 3 of 4
Approximate Location of Air Monitoring Stations B3.
Approximate Location of Air Monitoring Stations B2.
Approximate Location of Air Monitoring Stations B1.
Approximate Location of Air Monitoring Stations B4.
Approximate location of interior cinder block wall installation
Approximate location of structural steel installation
Approximate location of pile driving
Approximate location of waterproofing
Approximate location of insulation installation
IEM Daily Field Report
PHOTOGRAPH LOG
Prepared By: John Bruscella IEM Representative
Page 4 of 4