Environmental Monitoring Report Semestral Report July 2016
ARM: Sustainable Urban Development Investment
Program – Tranche 1
Prepared by the Yerevan Municipality for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environmental Monitoring Report
Bi-annual Report
January-June 2016
ARM: Sustainable Urban Development Investment
Program, Tranche 1
Project Number: 42417-023
Loan Number: L2752-ARM
Prepared: July 2016
Prepared by the Yerevan Municipality
Yerevan Project Implementation Unit
2
2
ABBREVIATIONS
ADB Asian Development Bank
AP affected people
DESC detailed engineering and construction supervision consultant
EARF environmental assessment and review framework
EIA environmental impact assessment
EMP environmental management plan
EMR environmental Monitoring Report
ES environmental specialist
GRM grievance redress mechanism
IEE initial environmental examination
MNP Ministry of Nature Protection
NPE nature protection expertise
PIU project implementation unit
PPMS project performance monitoring system
REA rapid environmental assessment
RA Republic of Armenia
RE resident engineer
SEMP site-specific environmental management plan
SNCO state non-commercial organization
SPS (2009) Safeguards Policy Statement (2009)
SUDIP Sustainable Urban Development Investment Program
YM Yerevan Municipality
3
3
Contents
I. Introduction .................................................................................................................................. 4
A. Project Description .................................................................................................................... 4
B. Project Progress ....................................................................................................................... 4
Construction Implementation Progress for New Shirak street-Artashat highway, Tender 2 .............. 4
C. Institutional Arrangements of the Project .................................................................................. 5
II. Environmental Management ........................................................................................................ 6
A. Environmental Safeguards Program ......................................................................................... 6
B. ADB mission ............................................................................................................................. 6
C. Grievance Redress Mechanism and Public Consultation .......................................................... 7
D. Meetings and Communication................................................................................................. 10
E. Awareness Raising and Environmental Training ..................................................................... 10
III. Environmental Monitoring ........................................................................................................... 11
A. Environmental Monitoring Program ......................................................................................... 11
B. Environmental Monitoring Program ......................................................................................... 11
a. Environmental Monitoring for Tender 2 ...................................................................................... 11
C. Non-compliance Notices ......................................................................................................... 13
D. Corrective Action Plans........................................................................................................... 13
IV. Findings and Recommendations ................................................................................................ 14
V. Future program .......................................................................................................................... 15
VI. Annexes ..................................................................................................................................... 16
A. Annex 1: List of training participants for Tender 2 ...................................................................... 16
B. Annex 2: List of EHS training participants held on 21, 22 June 2016 .......................................... 20
C. Annex 3: Corrective action plan for Tender 2 ............................................................................. 21
D. Annex 4: Status of the previous weekly environmental site monitoring reports for Tender 2 ....... 27
E. Annex. 5: Suggested Post-Construction Environmental Audit Checklist for Tender 1 ................. 30
F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 2 ......................... 33
G. Annex 7: Example of weekly environmental monitoring checklist .............................................. 34
4
4
I. Introduction
1. This bi-annual environmental monitoring report covers the time period of January-June 2016. The
report was prepared by PIU ES.
A. Project Description
2. The Government of Armenia received a loan on 19 May 2011 from the ADB to finance the SUDIP,
Tranche 1. The main objective of the Project is to build a new highway to expressway standards that
links the existing Shirak Street and Arshakunyats Avenue to the Artashat highway.
3. The Project comprises the following main components:
(i) the construction of a new 6-lane divided road;
(ii) the construction of a round-about at Shirak street; and
(iii) the construction of road links.
Figure 1: Map showing the Tranche 1 location
B. Project Progress
Construction Implementation Progress for New Shirak street-Artashat highway, Tender 2
4. The construction of the Tender 2, Tranche 1 is currently in the implementation stage. The following
works are in progress:
5
5
-at Artashat highway: asphalt pavement and some miscellaneous works are remaining to complete
railway overpass and also highway, as well as one footbridge is under construction;
at New-Shirak street: the construction works in the area of intersection started during reporting
period; retaining walls and overpass construction is underway.
Figure 2: Map showing Tender 2 for the New Shirak street-Artashat highway location
Figure 3: Tender 2 for the New Shirak street-Artashat highway pictures
C. Institutional Arrangements of the Project
5. The major tasks of the PIU ES are to carry out the overall environmental management ensuring full
compliance of the Project implementation with Armenian legislation and ADB SPS (2009). The ES
serves as a liaison between the safeguard team of DESC, YM, the executing agency, MNP of the RA
and Ministry of Culture of the RA, project affected people, ADB and develops and maintains direct
relationships with government authorities, with the help of DESC ES organizes and conducts public
consultations, etc. PIU ES Ruzanna Voskanyan manages all construction site activities related to the
environmental issues and PIU land acquisition and resettlement specialist Sirak Gyulbudaghyan
manages all resettlement and social aspects issues.
6
6
6. DESC- Egis International Company environmental management team is responsible for the
preparation of environmental assessment of Tranche 1 documents and is responsible for
environmental supervision of construction works of New Shirak street – Artashat highway Tender 2.
Edita Vardgesyan is supervision ES of construction works of New Shirak street – Artashat highway
Tender 2. Hasmik Aleksayan supervision social specialist is responsible for all aspects of the social
issues.
7. The Tender 2 “Vahagn & Samvel” LTD Contractor’s ES David Harutyunyan is responsible for
preparation and implementation of the SEMPs in accordance with EIA/EMP, monitoring of the
construction activities. Contractor’s ES reports to DESC ES after which the DESC ES reports to PIU
ES. Sona Poghosyan, social specialist and Nona Davtyan, assistant to social specialist are
responsible for all aspects of the social issues during the construction.
II. Environmental Management
A. Environmental Safeguards Program
8. The implementation of the environmental safeguards program started in January 2013 and was in
progress during the reporting period.
9. Based on ADB comment PIU together with the consultants is revising the IEE for Hayrenik
overpass. The revised IEE will be submitted to ADB in the beginning of the next reporting period.
10. In the beginning of the reporting period PIU submitted to ADB national consultant for review the
Post-Construction Environmental Audit Checklist for Arshakunyats Street Section km 0+000 -km
1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of
Audit Checklist for Tender 1 is attached in Annex 5 of the present report.
11. Weekly environmental monitoring checklist, SEMP, monthly reports, and other registers for
Tender 2 were prepared in close collaboration with PIU ES, DESC international and local ESs.
B. ADB mission
12. An ADB mission to check compliance of SUDIP 1 Program activities to the ADB SPS (2009
safeguard requirements took place on 22 April 2016. The mission was implemented by Armine
Yedigaryan, ADB National Environmental Consultant. Ruzanna Voskanyan, the PIU’s, Edita
Vardgesyan, the DESC’s ES and Contractor’s representatives also joined the mission. The mission
7
7
visited construction sites at Aratshat highway, Nor Shirak and Arshakunyats roundabout section, as
well as communicated with APs from the residential houses next to the RoW. The recommendations
of the mission audit on further actions were related to the vibration and dust control, as well as it was
recommended one more time present the GRM to the public.
C. Grievance Redress Mechanism and Public Consultation
13. For feedback, concerns and complaints from the APs, a GRM, inspired by the problem solving
function of ADB’s guidelines and policies should be maintained for the duration of the Project. The
GRM is intended to assist aggrieved persons in lodging their complaints and to describe the
mechanism designed to redress their grievances in a timely and effective manner. The parties
potentially involved are: the complainants, Contractor, DESC, PIU, EA, NGOs, and the courts. The
details of the GRM operation could be found in EIA for Tender 2 road links1.
14. A proper GRM has been established to meet environmental related concerns of affected people in
Artashat Highway-New Shirak and Shirak street and Arshakunyats avenue road sections Tender 2.
The availability of the logbook and registered complains in the Contractor’s field office was regularly
checked during the monitoring site visits.
15. During this reporting period there were complaints from the affected people such as dust and
noise, which were effectively treated according to the adopted procedure. Contractor was insistently
requested to take measures to control dust and to implement mitigation measures to reduce dust
emissions during the construction process. The corrections were suggested by the PIU/DESC ES
during the monitoring visits.
16. During the reporting period complains (table 1) regarding cracks due to demolishment works,
blocked access and damaged utilities were taken which are under review (see below table) by the
Contractor’s, Supervision Engineer’s social specialists coordinated by Sirak Gyulbudaghyan - PIU
land acquisition and resettlement Specialist.
17. During the inventory survey the buildings located in the affected zone have been examined,
videotaped and photographed, as well as appropriate acts have been developed and signed with
owners/users for each building. Also the Contractor has made additional seismological surveys for
the risky buildings with involvement of licensed seismological company/specialist. The next survey
will be conducted after the completion of the construction works to access the possible damages (if
1 EIA/EMP for Tender 2 H.2. Grievance Redress Mechanism, page 43 of 57.
8
8
any) applying the same survey methodology which was done prior to the beginning of the
construction. Any damage which is result of the construction during the Project will either be repaired
by the contractor at his own funds or the owners should be compensated again by the funds of the
Contractor and all the APs of the below table are informed.
Table 1 – Status of complaints during the reporting period
APs address Issues Date of complaints
Status Responsible person
1 Noragavit 1, houses 16, 16a, 18
Cracks due to demolishment works
21.07.2015
Completed (Emergency reinforcement plan approved by ADB, provide compensations)
Coordinated by Vardan Karapetyan- PIU Engineer Supervised by Engineer with social specialist
2 Noragavit 4, 15
Cracks due to demolishment works
21.07.2015
Completed (Answered by PIU, no further complaint during the reporting period)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
3 Arshakunyats 286/27
Cracks due to demolishment. Noise from work on Sunday
28.10.2015
Completed (Answered by PIU, no further complaint during the reporting period)
Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
4 Noragavit 4, house 30/2
Blocked access
04.03.2016 Completed (access has been provided)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
5 Noragavit 1, 1 block, house 4
Cracks due to demolishment works, sunlight issue, noise, demand to acquire the whole property
05.03.2016
Pending (Under the investigation stage; YM suggested 3 options to the AP to resolve the case. All 3 cases were rejected by the AP)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
6 Noragavit 1, 13/1 & 1 st,, 1 block
Blocked access
16.03.2016 Completed (access has been provided)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
7 Noragavit 1 house 4/1
Cracks due to demolishment. Noise from work on Sunday
17.05.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
8 Noragavit 1 house 13/1
Blocked access Humidity of the house
17.05.2016 03.06.2016
Completed (access has been provided; Investigated by Engineer and conclusion is that
Coordinated by Vardan Karapetyan- PIU Engineer and Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist Supervised by Engineer with social
9
9
humidity of the house is not from construction work and reposnce has been sent by PIU to AP, no further complaint during the reporting period)
specialist
9 Noragavit 1, 7/2 house
Cracks due to demolishment works
16.05.2016
Completed (Answered by PIU, no further complaint during the reporting period)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
10 Noragavit 1, block 1, house 4/1
Cracks due to demolishment.
27.05.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
11
Noragavit 1, block 1, 2, 11 houses and , block 2, 7 houses
Cracks due to demolishment works
18.05.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
12 Noragavit 4, block 1, house 15
Cracks due to demolishment works
21.06.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
13 Noragavit 4, block 1, house 10
Cracks due to demolishment works
10.06.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist
14 Noragavit 1/2, house 9
Cracks due to demolishment works
13.06.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist
15 Noragavit 1, house 7/2
Cracks due to demolishment works
14.06.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist
16 Noragavit 4st., block 1, house 12
Cracks due to demolishment works
21.06.2016 Pending (under the investigation stage)
Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist
17 Noragavit 1, bock 2, house 11
Cracks due to demolishment
27.06.16 Pending (under the investigation stage)
Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
18 Arshakunyats 286/21
Cracks due to demolishment.
29.06.16 Pending (under the investigation stage)
Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist
10
10
D. Meetings and Communication
18. During the reporting period environmental safeguards issues were regularly discussed during the
joint meetings with YM, PIU and DESC. Particularly the following issues were repeatedly discussed:
preparation and finalization of the IEEs for Hayrenik overpass approval process and related issues.
19. ADB site visit took place on 22 April 2016. Mrs. Armine Yedigaryan visited the Artashat Highway
PK km 0+300÷ km 1+850 and New Shirak Street PK km 0+0.100÷ km 0+0.400 construction site. She
checked the construction works on site, compliance of civil works to the EIA/EMPs and SEMP.
20. Regular meetings and discussions within PIU, DESC and the Contractor’s environmental team
during the reporting period took place via joint meetings, official correspondence and emails, phone
calls and personal contacts. Particularly the issue on the dust control measures; on safety on high fill
slopes; on the findings of additional measurements of environmental parameters; removal of
construction waste long-term left on-site, findings of training sessions, as well as the non-
conformances detected during the monitoring visits and action measures on their implementation
were discussed.
E. Awareness Raising and Environmental Training
21. The awareness raising and environmental orientation program was developed in the scope of
capacity building in the EIAs/IEEs and EMPs for Tender 2. According to the program the Contractor
was responsible to arrange orientation session about project activities and environmental awareness.
During this session, all the people working on the site should focus their efforts to protect environment
and insure the safe handling of the social issues during construction period in accordance with ADB
SPS (2009), Armenian environmental legislation, EIA and EMP. Further details about the awareness
raising and environmental orientation program could be found in final EIA and EMP Tender 22 and
Contractor’s SEMPs.
22. According to EIA, Annex 6 EMP for Tender 2 and SEMP the Contractor organized training for the
23 new hired staff during this reporting period on minimizing waste at source, proper handling of the
waste, workers’ safety measures during work and emergency preparedness in case of incidents, and
health risks and prevention which include information and education on sexually transmitted diseases
and HIV/AIDS. Site introduction environmental and health & safety training for the sub-contractor’s
new hired workers, engineering staff and foremen were held by Contractor on 21 May 2016 and 06
March 2016 (list of participants attached in Annex 1).
2 EIA/EMP for Tender 2 I.3. Implementation arrangement, c) Awareness raising and environmental Training, page 54 of 57; Annex 4, Table
1, para 6, page 6 of 31.
11
11
23. DESC’s national environmental Consultant is providing supervision of Contractor’s ongoing
training, timely guidance to the Contractor’s environmentally responsible staff during the reporting
period. Supervision ES regularly briefed both Contractor’s and sub-contractor’s staff while monitoring
visits.
24. Two public hearings for Hayrenik overpass under Tranche 1 held on 22 March and 29 April 2016.
Final IEE for Hayrenik overpass under Tranche 1 will be submitted to ADB in the beginning of the
next reporting period.
25. An awareness raising training session was held by Mr. Pierre Bourguignon, DESC-Egis
International Company Environmental Manager on Health & Safety (21 June 2016) and on
Environment (22 June 2016). Mr. Pierre Bourguignon explained the topics via PP Presentations:
“Health & Safety Management” and “Environmental Management”. Contractor’s and sub-contractor
key staffs including environmental, social specialists and engineers were invited (list of participants is
attached in Annex 2).
III. Environmental Monitoring
A. Environmental Monitoring Program
26. Environmental monitoring program with a view to ensure compliance with the ADB’s
environmental requirements and all applicable environmental laws, regulations and standards for
environmental protection of RA has been developed in the scope of IEEs/EIAs and EMPs for Tender
2. The EIAs and EMPs contain monitoring activities to be considered during project implementation:
management from the engineering design phase, preconstruction, construction through the operation
and maintenance periods. Details of monitoring activities and reporting are presented in approved
final EIAs and EMPs for Tender 23.
B. Environmental Monitoring Program
a. Environmental Monitoring for Tender 2
27. According to the contract the specialized monitoring company shall implement the measurements
in accordance with the approved measurement of environmental parameters: air pollution, noise,
vibration plan during the reporting period January-June 2016.
3 EIA/EMP for Tender 2, I. Environmental Management Plan, I.2 Monitoring page 52 of 57; Annex 4 Table 2, page 23 of 31; EIA/EMP for
Tender 3, I. Environmental Management Plan,I.2 Monitoring page 56 of 62; Annex 4 Table 2,page 28 of 36 and EIA/EMP for Davitashen-Ashtarak highway, I. Environmental Management Plan,I.2 Monitoring page 54 of 61; Annex 3 Table 2, page 23 of 31.
12
12
28. During the reporting period construction site monitoring visits (see Annex 7: Example of weekly
environmental monitoring checklist) and dump site monitoring visits organized jointly with PIU,
Contractor’s and DESC’s ESs, RE and other responsible representatives of the Contractor
participated in some of the monitoring visits.
29. The excavation materials are located in the dump site area of “X-Y’’ LLC basalt mining company
in Shahumyan 2, Silikyan district. Series of site visits were undertaken to the dump site “X-Y” LLC to
check compliance with EMP/ SEMP and Engineer’s requirements, as well as to check whether the
instructions given during the previous visit were done by the Contractor. The last site visit
implemented on 23 June 2016 stated that the site was used in accordance with EMP/SEMP and the
Engineer’s/PIUs instructions.
30. “Lernametalurgiayi Institute”, the company contracted by general contractor for environmental
measurements, carried out regular environmental monitoring of dust, air quality, noise and vibration
on 22.01.2016, 15.02.2016, 15.03.2016, 15.04.2016, 29.04.2016, 13.05.2016, 30.05.2016,
10.06.2016 and 22.06.2016 (see Annex 7). Selection of measurement points varied by taking into
consideration the impacted sensitive receptors within 50 m and ongoing construction works criteria. In
those cases when contractor timely notified Engineer on the measurements date, the points were
agreed jointly. Otherwise the measurement points were selected under the supervision of contractor’s
ES. In order to ensure the smooth process Engineer requested from contractor timely notification of
the date of measurements.
31. According to the provided reports of sub- contractor Lernametallurgie on 10 June the vibration
levels in measurement points 1, 2 and 3 is below from both the baseline level and the Maximum
Permissible Values. In the points 4 and 5 both maximum and average values exceed the baseline
level but are within permitted legislative standards. According to the provided reports for
measurements implemented on 22 June the vibration level in all measurement points was below from
both Maximum Permissible Level and the baseline data.
32. Based on the ADB requirement Contractor signed an additional contract with the sub- contractor
Lernametallurgie for additional measurements in one point relevant to AP's complains (see table 1,
point 5). The measurements were implemented on 17, 20, 21 and 22 June at 9:30 am and 11:00 am.
The time of measurements was determined based on the principle of operation of vibration
generating machinery. According to the provided reports vibration acceleration slightly exceeded both
Maximum Permissible and the baseline level only on 17 June at 11:00. All other measurements
showed that measurement hour for maximum and average values the vibration level was below the
baseline level and far below the Maximum Permissible standard.
13
13
33. Detailed information on the results of regular monitoring measurements is presented in the Noise
and Dust Assessment Reports available in “Vahagn & Samvel” LTD office and attached to the
Contractor’s monthly progress reports and measurements are summarized in Annex 6 of the present
report.
34. By the Site Instruction issued on 6 June 2016 Contractor was instructed to implement the Method
of Fill-Up in Middle of Grade Separated Roundabout and to provide safety measures on high slopes
and at high Retaining Walls. Contractor was instructed to remove large loose stones and dress
slopes smoothly to avoid any falling-down or rolling of material.
35. By the end of reporting period Contractor started using the second water truck on- site and
implemented more frequent watering. The site visits and measurements show that the dust control
can be considered as almost satisfactory.
C. Non-compliance Notices
36. A final warning and note by the email dated 2 June 2016 was sent by PIU directly to the
Contractor requesting implementation of proper watering on- site otherwise the civil works shall be
stopped. Also by the email sent on 6 June 2016 by PIU the Contractor was requested to use the
second water truck and implement more frequent watering of the site during the day in order to
minimize the further complaints concerning dust. The last site visit stated that the warning was
addressed and Contractor is using the second water truck on- site and implements frequent watering
of sites close to residential areas.
37. All further non- conformances detected during the monitoring visits have been treated according
to the adopted procedure: Contractor is being requested via the Engineer’s monitoring report to
correct the non- conformances within the deadline set for correction otherwise the non- compliance
notice shall be issued. Correction was checked during the next site visit.
D. Corrective Action Plans
38. During the reporting period construction site monitoring visits were held by DESC once a week
and by PIU ES on 21.01.2016, 16.02.2016, 16.02.2016, 19.02.2016, 12.03.2016, 22.04.2016,
26.05.2016 and 23.06.2016 in Artashat-New Shirak highway Tender 2 (See Annex 4: Status of the
previous weekly environmental site monitoring reports). Dump site monitoring visits were organized
by PIU and DESC’s national and international ESs on 23.06.2016.
39. Corrective action plans were developed to address each non-conformance found during
monitoring (see Annex 3: Corrective action plan for Tender 2).
14
14
IV. Findings and Recommendations
40. The monitoring visits implemented by PIU/ Engineer during the reporting period concluded in the
following findings. The recommendations are done also taking into consideration the findings of ADB
mission held on 22 April 2016.
- Dust: Dust level is too high close to sensitive receptors and should be reduced to comply with
legislative standards. Contractor was strongly recommended to operated more water trucks and
implement more frequent watering of the sites (now partly corrected);
- Vibration: Although Contractor always reported on the vibration level within the legislative standards
he was requested to follow ADB recommendations and implement additional measurements,
- Awareness of APs on the GRM is poor. Contractor was recommended once again to present the
GRM presented to the public and attached the contact information around the construction site (now
corrected).
- Bridges: Safety of Sub- contractor Kamurdjshin working on height is not assured. The necessary
PPE particularly the belts or harnesses are missing. Safety of workers next to welding works is not
ensured. Workers are doing the electrical cutting without proper PPE. Smoking workers are detected
very close to the explosive balloons. Sub- contractor is doing improper lifting of materials and is using
unsafe electrical panels and unsafe plugs. Protective guardrails on the bridges and safe staircases
are missing. Sub- contractor was recommended to correct the situation immediately.
- Arshakunyats Roundabout and Nor Shirak: Contractor's workers on the wall structures poor. Safe
accesses to work site are not ensured. More trainings on safety for management staff both Contractor
and sub-contractor is needed since safety of the site is very poor. Contractor was recommended to
correct the situation immediately (now corrected);.
-waste and dismantled utilities are being repeatedly detected on-site (partly corrected);
- workers are provided with and are using the uniform, applicable safety/protection equipment for site
conditions (mostly corrected);
- health check of newly hired workers is needed (corrected);
- bins for garbage collection are installed but Contractor is requested to move the bins and install next
to on-going construction works (corrected);
- cleaning and proper organization of contractor’s camp area is needed (partly corrected); all the open
holes alongside the asphalt covered section of Artashat highway should be safely covered (at least
temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is
needed (partly corrected);
- mud spread preventive measures were needed (not corrected).
Status of the action from environmental monitoring (January-June 2016) see in Annex 3.
15
15
V. Future program
N Action Time frame Responsible
1 Submit IEE for Hayrenik overpass August-September 2016 PIU, DESC 2 Public consultations August-September 2016 PIU, DESC 3 Regular monitoring visits of
construction works according to the EMP for Tender 2
Once a month/once a week PIU/DESC
4 excavated material dump site inspection visit for Tender 2
Once a month PIU, DESC
5 Review of the environmental monitoring data on dust, noise, vibration and NO/NO2/SO2 for Tender 2
Every month /twice a month PIU/DESC
6 Review and approval of the construction updated SEMPs for Tender 2
Upon the need PIU, DESC
7 Contractors new staff safeguard training for Tender 2
Upon the need DESC, Contractor
8 Regular awareness training for newly recruited staff for Tender 2
Upon the need DESC, Contractor
9 Review and addressing the GRM for Tender 2
End of every month/ every week
PIU/DESC
10 Other routine issues Upon the need PIU, DESC, Contractor
11 Reporting on environmental safeguards
Monthly, Quarterly Bi-annual
PIU, DESC, Contractor
16
16
VI. Annexes A. Annex 1: List of training participants for Tender 2
17
17
18
18
19
19
20
20
B. Annex 2: List of EHS training participants held on 21, 22 June 2016
21
21
C. Annex 3: Corrective action plan for Tender 2 Corrective action plan for Tender 2 the construction period from January to June 2016:
N Deadline for request
Corrective action request Date of
corrective action
Corrective
action status
1
15.01.2016 Warning signs and fencing were missing in many sections. 15.01.2016 Mostly corrected
2
15.01.2016 21.01.2016 27.01.2016
The same waste and dismantled utilities are being repeatedly detected on- site and they are still on-site. Contractor is requested to remove the rest of waste
-
Not corrected
3
15.01.2016 21.01.2016 27.01.2016
Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions
- Not corrected
4
15.01.2016 21.01.2016 27.01.2016
Bins for garbage collection are not installed in Arshakunyats Roundabout section. 24.12.2015 Not corrected
5
15.01.2016 21.01.2016 27.01.2016
More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.
24.12.2015 Not corrected
6
15.01.2016 21.01.2016 27.01.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is needed.
- Not corrected
22
22
7
15.01.2016 21.01.2016 27.01.2016
Work safety of workers is not ensured. Necessary PPE is missing. - Not corrected
8
15.01.2016 21.01.2016 27.01.2016
Any safe access to the work site (bridges, staircases) is not ensured. The staircases are installed not properly and are not usable. Monitoring inspection is not possible.
- Not corrected
9
15.01.2016 21.01.2016 27.01.2016
Mud spread preventive measures were needed. - Not corrected
10
15.01.2016 21.01.2016 27.01.2016
Waste asphalt is disposed of in non- approved sites - Not corrected
N Deadline for
request
Corrective action request Date of
corrective action
Corrective
action status
1 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Warning signs and fencing were missing in many sections.
25.02.2016 Corrected
2 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Workers are provided with uniforms and are using uniform, applicable safety/protection equipment for site conditions
25.02.2016 Mostly corrected
3 1.02.2016 8.02.2016 15.02.2016
Winter time organization of the workers’ mealtime is not acceptable.
16.02.2016 Mostly corrected
4 1.02.2016 8.02.2016 15.02.2016
First aid kit is available on-site and is not accessible to all workers.
16.02.2016 Corrected
5 1.02.2016 8.02.2016 15.02.2016
Fire extinguisher was missing 16.02.2016 Corrected
6 1.02.2016 8.02.2016 15.02.2016
More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.
16.02.2016 Corrected partly
7 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Work site is not cleaned from the garbage 25.02.2016 Corrected partly
8 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Bins for garbage collection are not installed in Arshakunyats Roundabout section.
25.02.2016 Corrected partly
9 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Any safe access to the work site (bridges, staircases) is not ensured. The staircases are installed not properly and are not usable.
16.02.2016 Corrected partly
10 1.02.2016 8.02.2016 15.02.2016
Construction sites are not watered 16.02.2016 Corrected partly
11 15.01.2016 21.01.2016 27.01.2016
The same waste and dismantled utilities are being repeatedly detected on-site. Contractor is requested to remove the rest of waste.
- Not corrected
12 1.02.2016 8.02.2016 15.02.2016
Access of strangers on- site is not restricted. Safety of AP is not ensured
- Not corrected
23
23
25.02.2016
13 15.02.2016 25.02.2016
Person in charge on emergency management is not appointed and is not present on-site.
- Not corrected
14 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Copy of ERP and emergency contact list is missing in Arshakunyats section
- Not corrected
15 1.02.2016 8.02.2016 15.02.2016 25.02.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is needed.
- Not corrected
16 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Work safety of workers is not ensured. Necessary PPE is missing.
- Not corrected
17 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Mud spread preventive measures were needed.
- Not corrected
18 1.02.2016 8.02.2016 15.02.2016 25.02.2016
Waste asphalt is disposed of in non- approved sites
- Not corrected
N Deadline for
request
Corrective action request Date of
corrective action
Corrective
action status
1 4.03.2016 12.03.2016 17.03.2016
Person in charge on emergency management is appointed and is present on-site
17.03.2016 Corrected Mr. Hovik Movsisyan is appointed
2 4.03.2016 12.03.2016 17.03.2016
Amounts of bins for garbage collection are increased
17.03.2016 Partly corrected
3 4.03.2016 12.03.2016 17.03.2016
Work site is not cleaned from the garbage 17.03.2016 Corrected partly
4 4.03.2016 12.03.2016 17.03.2016
Trucks are operating using covers 17.03.2016 Corrected
5 4.03.2016 12.03.2016 17.03.2016
The same waste and dismantled utilities are being repeatedly detected on- site. Contractor is requested to remove the rest of waste
17.03.2016 Partly corrected
6 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Contractor is violating the SEMP doing the disposal of the excavated earth material within the non- approved area.
24.03.2016 Corrected
24
24
7 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Dust control is implemented Construction sites are watered
24.03.2016 Corrected partly
8 4.03.2016 12.03.2016 17.03.2016
Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions
17.03.2016 Mostly corrected
9 4.03.2016 12.03.2016 17.03.2016
More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.
17.03.2016 Corrected partly
10 4.03.2016 12.03.2016 17.03.2016
Work safety of workers is not ensured. Necessary PPE is missing.
17.03.2016 Corrected partly
11 17.03.2016 24.03.2016
Non- approved disposal of the asphalt waste is detected
- Not corrected
12 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Contractor is responsible to organize removal: by the owner of the utilities or using own resources.
- Not corrected
13 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Access of strangers on- site is not restricted. Safety of AP is not ensured
- Not corrected
14 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Copy of ERP and emergency contact list is missing in Arshakunyats section
- Not corrected
15 4.03.2016 12.03.2016 17.03.2016 24.03.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.
- Not corrected
16 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Sanitary-hygienic conditions for workers are poor and need improvement.
- Not corrected
N Deadline for
request
Corrective action request Date of
corrective action
Corrective action
status
1 6.04.2016 Gravel layer to all accesses of the roads needed to prevent spread of mud
6.04.2016 Corrected
2 26.04.2016 Warning signs and exclusion barriers erected around work site areas and regularly re-installed
26.04.2016 Corrected
3 6.04.2016 Dust control is implemented Construction sites watered
6.04.2016 Corrected partly
4 6.04.2016 The attached ERP posters need to be properly re-installed
6.04.2016 Corrected partly
5 6.04.2016 20.04.2016
Work site is not cleaned from the garbage 26.04.2016 Corrected partly
6 6.04.2016 13.04.2016 20.04.2016
Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions
6.04.2016 13.04.2016 20.04.2016
Corrected partly
7 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Additional trainings on safety 26.04.2016 Corrected partly
25
25
8 6.04.2016 13.04.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.
13.04.2016
Corrected partly
9 6.04.2016 13.04.2016
The same waste was repeatedly detected on- site. Contractor is requested to remove the rest of waste
13.04.2016 Corrected partly
10 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Contractor is violating the SEMP doing the disposal of the excavated earth material within the non- approved area.
- Not corrected
11 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Workers are using safety/protection equipment for site conditions
- Not corrected
12 17.03.2016 24.03.2016
Non- approved disposal of the asphalt waste is detected
- Not corrected
13 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Contractor is responsible to organize removal: by the owner of the utilities or using own resources.
- Not corrected
14 4.03.2016 12.03.2016 17.03.2016 24.03.2016
Access of strangers on- site is not restricted. Safety of AP is not ensured
- Not corrected
15 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Amounts of bins for garbage collection are not sufficient
- Not corrected
16 6.04.2016 13.04.2016 20.04.2016 26.04.2016
Sanitary-hygienic conditions for workers are poor and need improvement.
- Not corrected
N Deadline for
request
Corrective action request Date of
corrective action
Corrective action
status
1 25.05.2016 Traces of leaked cement were present on public roads at Arshakunyats section
25.05.2016 Corrected
2 10.05.2016 People were poorly aware on the GRM. Contractor was requested to attach posters informing on GRM.
10.05.2016 Corrected
3 10.05.2016 More trainings for workers were needed on ERP at time of starting employment
10.05.2016 Corrected
4 10.05.2016 Missing ERP posters at Arshakunyats and Nor Shirak section need to be re-installed
10.05.2016 Corrected
5 10.05.2016 19.05.2016 25.05.2016
Fencing and prohibiting posters to restrict the access of unauthorized people on- site were missing.
25.05.2016 Corrected partly
6 10.05.2016 19.05.2016 25.05.2016
Excavated waste should be removed from work site
25.05.2016 Corrected partly
26
26
7 10.05.2016 19.05.2016
Contractor is responsible to organize removal: by the owner of the utilities or using own resources.
19.05.2016
Corrected partly
8 10.05.2016 19.05.2016
Temporarily dumped earth material from the camp's area and from Artashat
highway should be removed to approved dump sites
19.05.2016 Corrected partly
9 19.05.2016 25.05.2016
Gravel layer to all accesses to the roads needed to prevent spread of mud
25.05.2016 Corrected partly
10 1.05.2016 Dust control is implemented Construction sites watered
1.05.2016 Corrected partly
11 10.05.2016 19.05.2016
Work site is not cleaned from the garbage 19.05.2016
Corrected partly
12 10.05.2016 19.05.2016
Workers are provided with and are using the uniform, applicable safety/protection equipment for site conditions
19.05.2016 Corrected partly
7 10.05.2016 19.05.2016 25.05.2016
Additional trainings on safety - Not corrected
8 10.05.2016 19.05.2016 25.05.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.
- Not corrected
11 10.05.2016 19.05.2016 25.05.2016
Safety on bridges and wall structures is poor
- Not corrected
15 10.05.2016 19.05.2016 25.05.2016
The bins for garbage collection at Nor Shirak and Artashat sections are missing
- Not corrected
16 10.05.2016 19.05.2016 25.05.2016
Sanitary-hygienic conditions for workers are poor and need improvement.
- Not corrected
N Deadline for
request
Corrective action request Date of
corrective action
Corrective action
status
1 3.06.2016 16.06.2016 23.06.2016
Dust control is implemented Construction sites watered
30.06.2016
Corrected
2 16.06.2016 Workers are provided with and are using the uniform
16.06.2016 Corrected
3 16.06.2016 23.06.2016
Workers are provided with and are using applicable safety/protection equipment for site conditions
30.06.2016 Corrected partly
27
27
4 16.06.2016 23.06.2016
Temporarily dumped earth material from the camp's area and from Artashat
highway should be removed to approved dump sites
23.06.2016 Corrected partly
Contractor started
removal
5 16.06.2016 23.06.2016
Contractor is responsible to organize removal: by the owner of the utilities or using own resources.
23.06.2016 Corrected partly
6 16.06.2016 30.06.2016
Contractor was requested to remove the asphalt waste to the designated dump site
23.06.2016 Corrected partly
7 16.06.2016 30.06.2016
Contractor was requested to remove all the construction waste to the designated dump site
23.06.2016 Corrected partly
8 16.06.2016 23.06.2016
Sanitary-hygienic conditions for workers are poor and need improvement.
30.06.2016 Corrected partly
9 16.06.2016 23.06.2016
Safety on bridges and wall structures is poor
23.06.2016 Corrected partly
10 16.06.2016 23.06.2016
Additional trainings on safety 23.06.2016 Corrected partly
11 16.06.2016 23.06.2016
Contractor was requested to re-cover all accesses to the roads by the gravel layer to prevent spread of mud
- Not corrected
12 16.06.2016 23.06.2016
The bins for garbage collection at Nor Shirak and Artashat sections are missing
- Not corrected
13 16.06.2016 23.06.2016
Fencing and prohibiting posters to restrict the access of unauthorized people on- site were missing.
- Not corrected
14 16.06.2016 23.06.2016
Work site is not cleaned from the garbage - Not corrected
15 16.06.2016 23.06.2016
Contractor is requested correct some unsafe practices detected on- site
- Not corrected
16 5.06.2016 16.06.2016 23.06.2016
All the open holes alongside the asphalt
covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.
- Not corrected
D. Annex 4: Status of the previous weekly environmental site monitoring reports for Tender 2
During the reporting period regular weekly and monthly monitoring visits against the schedule of
compliance areas of civil works to the requirements set in EIA and EMP have been implemented by
PIU and Engineer’s ESs and the monitoring sheets completed. Improvement of the detected non-
28
28
conformances was checked during the next site visit. The summary of compliance/ non- conformance
is presented in the Matrix below:
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 15 January
14 7 11 0/1 7
Week 2 21 January
14 6 12 0/0 8
Week 3 27 January
10 4 17 0/0 8
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 5 February
12 2 18 3/1 15
Week 2 11 February
11 5 17 0/2 13
Week 3 16 February
13 8 12 2/7 10
Week 4 25 February
14 7 11 1/4 11
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 4 March
13 6 14 0/4 10
Week 2 12 March
15 7 12 1/4 9
Week 3 17 March
18 8 8 3/5 8
Week 4 24 March
18 6 9 0/4 8
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 6 April
18 12 4 2/7 4
Week 2 13 April
18 10 5 0/4 4
Week 3 22 April
18 10 5 2/1 6
Week 4 26 April
18 9 7 1/2 4
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 16 9 8 2/1 8
29
29
4 May
Week 2 13 May
18 10 3 3/7 5
Week 3 28 May
19 11 4 0/4 4
Week 4 25 May
20 9 5 1/4 5
Monitoring visit Fully compliant Partly compliant
Non- conformity
Non- conformities corrected (F/P)
Non- conformities not corrected
Week 1 3 June
20 12 2 1/4 3
Week 2 9 June
20 14 0 0/3 3
Week 3 16 June
21 13 0 1/1 3
Week 4 23 June
19 13 0 0/4 6
E. Annex. 5: Suggested Post-Construction Environmental Audit Checklist for Tender 1 Site: Arshakunyats Street Section km 0+000 -km 1+280, Tender 1, Tranche 1
Time: 01.01.2015-26.01.2016 No. Activity Impacts Measure/s suggested as per Check Measures Implemented
1 Project site
vegetation
rehabilitati
on
(re-
vegetation)
Change of land cover,
erosion resulting from
the construction
activities
Plantation and vegetation
measures (trees, grass etc.)
checked Indicated measures have been carried out at Arshakunyats Street Section km 0+000 -km 1+280
on November-December 2014. Totally 153 trees and 30 shrubs were planted. The remaining
amount (435 trees and 165 shrubs) shall be planted during the upcoming favorable season
within Tender 2.
The health state and growth of trees and shrubs is being regularly checked during the liability
period.
Proper landscaping with
drainage
2
Top soil
manageme
nt
Erosion of soil
Storing and managing
removed topsoil for re-use
for landscaping activities
checked During construction period the topsoil was removed and stored only within the Military
aviation institute area in accordance with SEMP and after the completion of civil works was re-
used for the landscaping of the same Military aviation institute area. The topsoil was not used
for landscaping of the area alongside the RoW.
No topsoil was removed and/or stored during the post- construction period. 3 Oil
manageme
nt
Equipment and
machinery repairing
Avoid oil spill to open soil.
Repair works to be taken on
concrete cover area.
checked There were no oils or other spillages during the post construction time.
During the project implementation, Oil management issues had been carried out in compliance
measure prescribed by EIA/ EMP and respective SEMPs.
31
31
4 Waste
manageme
nt
Waste accumulation,
air and soil pollution
Collect and disposal all wastes
including construction debris at
designated location;
checked During construction period all the construction waste was temporarily disposed of within the
area indicated in the SEMP, then removed to and disposed at the approved dump site.
No waste was generated during the post- construction period
Dumping sites restored and
submitted officially to local
communities
checked The dump site used for the Tender 1 is also being used by the same Contractor for the Tender
2. The restoration of the dump site area will be implemented by the end of Tender 2 Project:
L2752-ICB/CW-T2 5 Noise and
vibration,
air
manageme
nt
Excessive noise and
vibration due
to new road
Noise has been monitored on
a periodic basis and in
response to any complaints.
checked Noise and vibration levels were measured during 2015 on regular basis (three times ) and were
in compliance with RA legislative standards and bellow the baseline level.
No complaints were lodged by APs during the post construction period.
6 Air
manageme
nt
Air quality
deterioration due
to new road
Air quality has been
monitored associated with
vehicle emissions on a
periodic basis and in
response to any complaints
checked Air quality parameters were also measured on the periodic basis (in accordance with EIA/EMP)
and measurement showed some improvement for all parameters compared with pre-
construction situation.
No complaints were lodged by APs during the post construction period.
7
Traffic
manageme
nt
Hazards and
safety issues
related to traffic
Public access and access to
the housing, shops, business
and public activities
checked All the accesses are ensured according to the design.
Road safety is ensured, proper signage is implemented
Appropriate signage is installed
32
32
8 Road
reinstatem
ent
Road damages causing
pollution, traffic
disturbance and
accidents
Streets with installed network
reinstated to pre-construction
or better conditions,
checked All the existing network was replaced and new network installed according to the design.
Trees replanted as needed All the trees are planted in accordance with landscaping design.
Access road reinstated to pre-
construction or better
conditions
All the access roads are re-instated up to pre-construction period.
9 Borrow
sites and
quarries
Land slide, soil
erosion, change in
riverbed and
landscape, accidents
Borrow sites and quarries
restored
checked .
Contractor purchased the material only from the existing quarries on contractual basis. The
contractor obtained act of acceptance to the satisfaction of the owner (in accordance with
EIA/EMP). 10 Existing
Infrastructu
re facilities
Damage or
disturbance to existing
services (supply of
electricity, water, gas,
telecom etc.)
Reinstatement to pre-
construction conditions or
proper relocation, to be
certified by the service
companies
checked Existing infrastructures had been reinstated up to pre-construction conditions and/or properly
relocated. Oral satisfaction of service companies is achieved and no complaints were received.
11 Camp site
facilities
Residual pollution and
disturbance to the
localities
All temporary/field plants
(asphalt, concrete, crushing,
etc.) have been dismantled and
removed.
checked There were no temporary plants used for the Tender 1 Project. The camp site was used only for
machinery parking purpose.
Existing camp site is foreseen for for Tender 2 widening of Artashat Highway PK km 0+300÷km
1+850 and New Shirak Street PK km 0+0.100÷km0+0.400 by the permission of YM.
33
33
Permanently operating plants
(asphalt, concrete, crushing,
etc.) have been properly
handled and
closed/surrendered.
N/A
There were no permanent plants used for the Tender 1 Project.
All temporary facilities
removed and cleaned up
The mobile house is being dismantled and removed. All the machinery is being removed. Area
is cleaned up ready for the Tender 2. 12 GRM Unresolved complaints
from Affected People
All grievances have been solved
and AP's satisfied
checked All the grievances lodged in the GRM are solved Total of seven complaints for Arshakunyats
avenue were recorded in the log book and addressed accordingly by Contractor. The
complaints were on the cracks in old houses due to construction vibration. All APs were
compensated by the Contractor and satisfied.
F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 2
34
34
G. Annex 7: Example of weekly environmental monitoring checklist MITIGATION COMPLIANCE & INSPECTION MONITORING Report N 64
Project: SUDIP – Tranche 1, Tender 2, “Construction of Road Links of the Yerevan Western Ring Road”.
Implementing Agency: DESC__________________
Scope of Inspection: Artashat Highway (PK km 0+300÷km 1+850), New Shirak Street (PK km 0+0.100÷km0+0.400 km) and Grade Separated Roundabout
Between Shirak Street and Arshakunyats Avenue
Contractor: Vahagn and Samvel LLC/ su o tra tor Ka urdjshi
Attendees : Name & Position:
Mrs. Ruzanna Voskanyan, PIU EO; Mr. Pierre Bourguignon, DESC IES
Mrs, Edita Vardgesyan, DESC ES
Date: 23.06.2016
Weather Condition: sunny
Monitoring visit was carried out with the presence of:
Mr. David Harutyunyan, Contractor's HSE
WORK SITE: General
Environmental management: environmental team, health& safety, emergency, trainings, grievance redress mechanism
Construction Activity Mitigation Measure (as per
EMP/SEMP)
Mitigation
Implemented
Yes/No/NA
Mitigation Effective*
1 to 5
Corrective Action
Request (CAR)
including deadline for
effective CA.
Resolution Status of
previous CAR
(resolved/outstanding
actions required)
Environmental team
All activities 1. Person in charge on environmental
management is appointed and is present
on-site
Y 1
Health& safety
35
35
All activities 2. Warning signs and exclusion barriers
erected around work site areas
N 3Some re-installation of
tape fencing in the
sections indicated in the
report N 63 are still
required
Correct before 30
June 2016
Non- conformance
repeated
All activities 3. Access of strangers and outsiders is
excluded
N 3People are still
crossing the
construction site very
close to open pits and
operating machinery.
At the section
demonstrated on
picture the fencing and
prohibiting posters
were missing.
At Artashat section
some holes still remain
open.
Correct before 30
June 2016
Non- conformance
repeated
All activities 4. Workers are provided with and are using
the uniform, applicable safety/protection
equipment for site conditions
N 4The uniform is mostly
OK but for the PPE see
comments below.
Correct before
immediately
All activities 5. Worker’s health checks implemented Y 1
Ensure availability of
the documents for the
inspection.
All activities 6. Sanitary-hygienic conditions for workers
are provided: drinking and washing
water supply, mealtime utilities, toilets,
rest time, etc.
N 3
Sanitary-hygienic
conditions for workers
are poor and need
improvement. Workers
are having mealtime
open air in very non-
Correct before 30
June 2016
Non- conformance
repeated
36
36
sanitary conditions.
The workers were self-
providing water.
Taking into account the
summer season the
Contractor should
organize the supply of
drinking water to
working staff.
All activities 7. First aid kit is available on-site and is
accessible to all workers.
Y 1
All activities 8. Fire extinguisher available Y 1
Emergency Response Plan
All activities 9. Person in charge on emergency
management is appointed and is present
on-site
Y 1
All activities 10. Copy of ERP and emergency contact list
are available, updated and posted in a
visible place at all work sites
Y 1
All activities 11. Accident report maintained N/A -
All activities 12. Damage of utilities and/or other
structures managed
N/A -
Trainings and orientation courses
All activities 13. Workers briefed on CEMP/ SEMP at
time of starting employment
Y 1
37
37
All activities 14. Workers briefed on ERP at time of
starting employment
Y 1
All activities 15. Job-specific environmental and safety
training for workers provided
N 3
Safety on the bridge was
poor.
Additional trainings of
working staff on safety is
needed.
Contractor should
provide full report on the
trainings with photos
especially for workers on
height and V&S staff
working on construction
of walls.
Implement before 30
June 2016.
Work site cleanliness
All activities 16. The work site kept clean from debris,
garbage, etc.
N 3
Clean before 30 June
2016
38
38
All activities 17. Bins for garbage collection are installed N 3
Missing at some
Contractor's sites at
Artashat HW and Nor
Shirak sections
Correct before 30
June 2016
Non- conformance
repeated
Public communication and grievance redress mechanism: environmental issues
All activities 18. Meeting with community members on
construction activities, environmental
impacts and mitigation measures held
Y 1
All activities 19. Register of complaints maintained,
Complains observed during the last visit
addressed
Y
1
All activities 20. People are notified on inconveniences:
water, electricity breaks, etc.
N/A
Environmental parameters: Dust control
Earth works, material
delivery, removal of
existing pavement, asphalt
pavement
21. Trucks are operating using covers N/A -
22. Construction sites watered N 3 Two water tracks are
operating on site and
the traces of water in
were visible
Partly corrected
39
39
23. Equipment and haul vehicles are fitted
with effective emission control
equipment
Y 1
Noise control
Operation of machinery
while earth works,
material delivery, removal
of existing pavement,
asphalt pavement
24. Construction noise levels are acceptable
at closest sensitive receptor
Y 1 Visually the noise level was
not excessive. More exact
information shall be
obtained as soon as the
report on environmental
monitoring for May shall be
submitted.
25. Equipment fitted with effective silencers Y
1
26. managed by restricting operating hours Y 1
27. managed by portable noise barrier panels N/A
Vibration control
Operation of machinery
while removal of existing
pavement, asphalt
pavement
28. managed by reducing time exposed to
vibration,
N/A
29. managed by portable vibration barrier
panels
N/A
Earth works 30. Erosion control: excavated slopes
stabilised
Y 1
All activities using liquid
materials
31. Spillages are managed properly Y 1
Earth works 32. Sediment laden runoff is prevented Y 1
40
40
Earth works, material
delivery, removal of
existing pavement, asphalt
pavement
33. Drains are kept open and are not blocked
by sediment
Y 1
All activities using
machinery
34. Tires of trucks are cleaned before
entering city roads
N 3
The previously covered
gravel layer needs to be
refreshed and the
missing parts need to be
covered.
Clean the road and
correct before 30 June
2016
Non- conformance
repeated
Earth works 35. Excavated waste is either hauled from
work site or is retained temporary on-
N 3Some amount of waste
from Arshakunyats
Remove the rest of
waste and utilities
Corrected partly
41
41
site in spoil dumps section was removed
but significant amount
of same waste especially
at Artashat HW and
under Artashat bridge is
still on- site.
before 30 June 2016
All activities 36. Proper maintenance of re-planted trees
and shrubs, and median lawn
N/A
Construction waste management
removal of existing
asphalt pavement
37. Waste asphalt is disposed of in approved
sites Y 2An asphalt waste was
dumped in non-
permitted area
Contractor is
requested remove the
remains before 30
June 2016
Corrected partly
Earth works, demolition
of structures, dismantling
of utilities
38. Non-hazardous waste (excavation
material, rocks, concrete and metallic
parts, etc.) is managed in accordance
with SEMP
Y 3
Contractor is responsible
to agree with owner and
organise the removal of
the remains of utilities to
the determined locations.
Remove the remains
before 30 June 2016.
Corrected partly
42
42
Removal of existing
pavement,
39. Hazardous waste is managed in
accordance with SEMP
Y 2
see 37
Use of chemicals, fuel,
lubricants, etc. while all
activities
40. Leakages and liquid waste is managed in
accordance with WMP
N/A -
Contractor’s facilities and equipment Contractor’s camp
establishment
41. Site Management Plan for the camp
available
Y 1 Corrected partly
Contractor’s facilities 42. Contractor’s facilities are established according to SEMP
Y 2Contractor is requested
to remove the remains of
temporarily dumped
earth material from the
camp's area and from
Artashat HW or obtain
the YM's permission.
Correct before 30
June 2016.
* Mitigation Effectiveness Rating Criteria
1. Very Good 19
2. Good 3
3. Fair 10
4. Poor 1
43
43
5. Very Poor 0
Attachments
(Eg. Photos, Remarks, laboratory reports etc)
Remarks:
1. Safety of Sub- contractor Kamurdjshin working on height is not ensured. The necessary PPE is missing
2. Worker assisting to the welder is not wearing PPE and is unprotected.
3. Workers are doing the electrical cutting without proper PPE. One of workers is smoking very close to the explosive balloons.
44
44
4.Sub- contractor is doing improper lifting of materials.
4. Sub- contractor is using unsafe electrical panels and unsafe plugs.
45
45
5. Sub- contractor should remove the used and empty balloons from the bridge
6.Contractor's workers on the wall structures poor. Safe accesses to work site are not ensured.
3. Protective guardrails on the bridges and staircases are missing. The tape fencing is not sufficient. Contractor is requested to do metal fencing.
46
46
Good practices detected on-site
1. Almost all workers both Contractor's and Sub- contractors' were provided and wearing the proper uniform.
2. The workers were immediately provided with protective belts following the DESC IES's instructions.
Before After the DESC instructions
3. Contractor started doing tape fencing on the bridges following the DESC NES instructions.
47
47
4. Sub- contractor and Contractor care for unrestricted water courses and proper drainage.
This form, or an adaptation of it, should be used during routine (preferably weekly) site inspections by the PIU environmental specialist/unit or
representative (Supervision Consultant) to monitor implementation of the EMP for a construction project.
Routine site inspections should cover all current/relevant construction activities being implemented on the project site at the time of inspection. Ideally,
the Co tra tor’s e viro e tal a ager/fo al poi t should a o pa y the PIU e viro e tal spe ialist or represe tative duri g routine inspections. Once
completed, the form should be sent to the Contractor for his information and action including any photographs. A copy of the completed form is retained in
the data management system of the PIU for reference during subsequent site inspections and for referral during preparation of monitoring reports.
Column 1 Construction Activity – All current/relevant construction activities taking place on the project site for which mitigation measures are required
under the EMP/SEMP, are listed.
48
48
Column 2 Mitigation Measure – Specific mitigation measures required under the EMP/SEMP for the corresponding construction activity are listed.
Column 4 Corrective Action Request – Where the inspection identifies non-compliance or ineffective implementation of a mitigation measure, specific
corrective actions are identified, discussed and agreed with the Contractor including a deadline for effective corrective action.
Column 5 Resolution Status of Previous CARs – Each subsequent site inspection involves review of the resolution status of previous CARs. This is useful in
assessing the responsiveness of the Contractor to environmental non compliances and where necessary provides the basis for determining when a
contractual non-compliance penalty may need to be invoked (eg persistent noncompliance / no response to CAR).
Recommended