Environmental Monitoring Report Semestral Report July 2016 ARM: Sustainable Urban Development Investment Program Tranche 1 Prepared by the Yerevan Municipality for the Asian Development Bank.

Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

Environmental Monitoring Report Semestral Report July 2016

ARM: Sustainable Urban Development Investment

Program – Tranche 1

Prepared by the Yerevan Municipality for the Asian Development Bank.

Page 2: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

Environmental Monitoring Report

Bi-annual Report

January-June 2016

ARM: Sustainable Urban Development Investment

Program, Tranche 1

Project Number: 42417-023

Loan Number: L2752-ARM

Prepared: July 2016

Prepared by the Yerevan Municipality

Yerevan Project Implementation Unit

Page 4: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

2

2

ABBREVIATIONS

ADB Asian Development Bank

AP affected people

DESC detailed engineering and construction supervision consultant

EARF environmental assessment and review framework

EIA environmental impact assessment

EMP environmental management plan

EMR environmental Monitoring Report

ES environmental specialist

GRM grievance redress mechanism

IEE initial environmental examination

MNP Ministry of Nature Protection

NPE nature protection expertise

PIU project implementation unit

PPMS project performance monitoring system

REA rapid environmental assessment

RA Republic of Armenia

RE resident engineer

SEMP site-specific environmental management plan

SNCO state non-commercial organization

SPS (2009) Safeguards Policy Statement (2009)

SUDIP Sustainable Urban Development Investment Program

YM Yerevan Municipality

Page 5: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

3

3

Contents

I. Introduction .................................................................................................................................. 4

A. Project Description .................................................................................................................... 4

B. Project Progress ....................................................................................................................... 4

Construction Implementation Progress for New Shirak street-Artashat highway, Tender 2 .............. 4

C. Institutional Arrangements of the Project .................................................................................. 5

II. Environmental Management ........................................................................................................ 6

A. Environmental Safeguards Program ......................................................................................... 6

B. ADB mission ............................................................................................................................. 6

C. Grievance Redress Mechanism and Public Consultation .......................................................... 7

D. Meetings and Communication................................................................................................. 10

E. Awareness Raising and Environmental Training ..................................................................... 10

III. Environmental Monitoring ........................................................................................................... 11

A. Environmental Monitoring Program ......................................................................................... 11

B. Environmental Monitoring Program ......................................................................................... 11

a. Environmental Monitoring for Tender 2 ...................................................................................... 11

C. Non-compliance Notices ......................................................................................................... 13

D. Corrective Action Plans........................................................................................................... 13

IV. Findings and Recommendations ................................................................................................ 14

V. Future program .......................................................................................................................... 15

VI. Annexes ..................................................................................................................................... 16

A. Annex 1: List of training participants for Tender 2 ...................................................................... 16

B. Annex 2: List of EHS training participants held on 21, 22 June 2016 .......................................... 20

C. Annex 3: Corrective action plan for Tender 2 ............................................................................. 21

D. Annex 4: Status of the previous weekly environmental site monitoring reports for Tender 2 ....... 27

E. Annex. 5: Suggested Post-Construction Environmental Audit Checklist for Tender 1 ................. 30

F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 2 ......................... 33

G. Annex 7: Example of weekly environmental monitoring checklist .............................................. 34

Page 6: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

4

4

I. Introduction

1. This bi-annual environmental monitoring report covers the time period of January-June 2016. The

report was prepared by PIU ES.

A. Project Description

2. The Government of Armenia received a loan on 19 May 2011 from the ADB to finance the SUDIP,

Tranche 1. The main objective of the Project is to build a new highway to expressway standards that

links the existing Shirak Street and Arshakunyats Avenue to the Artashat highway.

3. The Project comprises the following main components:

(i) the construction of a new 6-lane divided road;

(ii) the construction of a round-about at Shirak street; and

(iii) the construction of road links.

Figure 1: Map showing the Tranche 1 location

B. Project Progress

Construction Implementation Progress for New Shirak street-Artashat highway, Tender 2

4. The construction of the Tender 2, Tranche 1 is currently in the implementation stage. The following

works are in progress:

Page 7: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

5

5

-at Artashat highway: asphalt pavement and some miscellaneous works are remaining to complete

railway overpass and also highway, as well as one footbridge is under construction;

at New-Shirak street: the construction works in the area of intersection started during reporting

period; retaining walls and overpass construction is underway.

Figure 2: Map showing Tender 2 for the New Shirak street-Artashat highway location

Figure 3: Tender 2 for the New Shirak street-Artashat highway pictures

C. Institutional Arrangements of the Project

5. The major tasks of the PIU ES are to carry out the overall environmental management ensuring full

compliance of the Project implementation with Armenian legislation and ADB SPS (2009). The ES

serves as a liaison between the safeguard team of DESC, YM, the executing agency, MNP of the RA

and Ministry of Culture of the RA, project affected people, ADB and develops and maintains direct

relationships with government authorities, with the help of DESC ES organizes and conducts public

consultations, etc. PIU ES Ruzanna Voskanyan manages all construction site activities related to the

environmental issues and PIU land acquisition and resettlement specialist Sirak Gyulbudaghyan

manages all resettlement and social aspects issues.

Page 8: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

6

6

6. DESC- Egis International Company environmental management team is responsible for the

preparation of environmental assessment of Tranche 1 documents and is responsible for

environmental supervision of construction works of New Shirak street – Artashat highway Tender 2.

Edita Vardgesyan is supervision ES of construction works of New Shirak street – Artashat highway

Tender 2. Hasmik Aleksayan supervision social specialist is responsible for all aspects of the social

issues.

7. The Tender 2 “Vahagn & Samvel” LTD Contractor’s ES David Harutyunyan is responsible for

preparation and implementation of the SEMPs in accordance with EIA/EMP, monitoring of the

construction activities. Contractor’s ES reports to DESC ES after which the DESC ES reports to PIU

ES. Sona Poghosyan, social specialist and Nona Davtyan, assistant to social specialist are

responsible for all aspects of the social issues during the construction.

II. Environmental Management

A. Environmental Safeguards Program

8. The implementation of the environmental safeguards program started in January 2013 and was in

progress during the reporting period.

9. Based on ADB comment PIU together with the consultants is revising the IEE for Hayrenik

overpass. The revised IEE will be submitted to ADB in the beginning of the next reporting period.

10. In the beginning of the reporting period PIU submitted to ADB national consultant for review the

Post-Construction Environmental Audit Checklist for Arshakunyats Street Section km 0+000 -km

1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of

Audit Checklist for Tender 1 is attached in Annex 5 of the present report.

11. Weekly environmental monitoring checklist, SEMP, monthly reports, and other registers for

Tender 2 were prepared in close collaboration with PIU ES, DESC international and local ESs.

B. ADB mission

12. An ADB mission to check compliance of SUDIP 1 Program activities to the ADB SPS (2009

safeguard requirements took place on 22 April 2016. The mission was implemented by Armine

Yedigaryan, ADB National Environmental Consultant. Ruzanna Voskanyan, the PIU’s, Edita

Vardgesyan, the DESC’s ES and Contractor’s representatives also joined the mission. The mission

Page 9: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

7

7

visited construction sites at Aratshat highway, Nor Shirak and Arshakunyats roundabout section, as

well as communicated with APs from the residential houses next to the RoW. The recommendations

of the mission audit on further actions were related to the vibration and dust control, as well as it was

recommended one more time present the GRM to the public.

C. Grievance Redress Mechanism and Public Consultation

13. For feedback, concerns and complaints from the APs, a GRM, inspired by the problem solving

function of ADB’s guidelines and policies should be maintained for the duration of the Project. The

GRM is intended to assist aggrieved persons in lodging their complaints and to describe the

mechanism designed to redress their grievances in a timely and effective manner. The parties

potentially involved are: the complainants, Contractor, DESC, PIU, EA, NGOs, and the courts. The

details of the GRM operation could be found in EIA for Tender 2 road links1.

14. A proper GRM has been established to meet environmental related concerns of affected people in

Artashat Highway-New Shirak and Shirak street and Arshakunyats avenue road sections Tender 2.

The availability of the logbook and registered complains in the Contractor’s field office was regularly

checked during the monitoring site visits.

15. During this reporting period there were complaints from the affected people such as dust and

noise, which were effectively treated according to the adopted procedure. Contractor was insistently

requested to take measures to control dust and to implement mitigation measures to reduce dust

emissions during the construction process. The corrections were suggested by the PIU/DESC ES

during the monitoring visits.

16. During the reporting period complains (table 1) regarding cracks due to demolishment works,

blocked access and damaged utilities were taken which are under review (see below table) by the

Contractor’s, Supervision Engineer’s social specialists coordinated by Sirak Gyulbudaghyan - PIU

land acquisition and resettlement Specialist.

17. During the inventory survey the buildings located in the affected zone have been examined,

videotaped and photographed, as well as appropriate acts have been developed and signed with

owners/users for each building. Also the Contractor has made additional seismological surveys for

the risky buildings with involvement of licensed seismological company/specialist. The next survey

will be conducted after the completion of the construction works to access the possible damages (if

1 EIA/EMP for Tender 2 H.2. Grievance Redress Mechanism, page 43 of 57.

Page 10: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

8

8

any) applying the same survey methodology which was done prior to the beginning of the

construction. Any damage which is result of the construction during the Project will either be repaired

by the contractor at his own funds or the owners should be compensated again by the funds of the

Contractor and all the APs of the below table are informed.

Table 1 – Status of complaints during the reporting period

APs address Issues Date of complaints

Status Responsible person

1 Noragavit 1, houses 16, 16a, 18

Cracks due to demolishment works

21.07.2015

Completed (Emergency reinforcement plan approved by ADB, provide compensations)

Coordinated by Vardan Karapetyan- PIU Engineer Supervised by Engineer with social specialist

2 Noragavit 4, 15

Cracks due to demolishment works

21.07.2015

Completed (Answered by PIU, no further complaint during the reporting period)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

3 Arshakunyats 286/27

Cracks due to demolishment. Noise from work on Sunday

28.10.2015

Completed (Answered by PIU, no further complaint during the reporting period)

Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

4 Noragavit 4, house 30/2

Blocked access

04.03.2016 Completed (access has been provided)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

5 Noragavit 1, 1 block, house 4

Cracks due to demolishment works, sunlight issue, noise, demand to acquire the whole property

05.03.2016

Pending (Under the investigation stage; YM suggested 3 options to the AP to resolve the case. All 3 cases were rejected by the AP)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

6 Noragavit 1, 13/1 & 1 st,, 1 block

Blocked access

16.03.2016 Completed (access has been provided)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

7 Noragavit 1 house 4/1

Cracks due to demolishment. Noise from work on Sunday

17.05.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

8 Noragavit 1 house 13/1

Blocked access Humidity of the house

17.05.2016 03.06.2016

Completed (access has been provided; Investigated by Engineer and conclusion is that

Coordinated by Vardan Karapetyan- PIU Engineer and Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist Supervised by Engineer with social

Page 11: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

9

9

humidity of the house is not from construction work and reposnce has been sent by PIU to AP, no further complaint during the reporting period)

specialist

9 Noragavit 1, 7/2 house

Cracks due to demolishment works

16.05.2016

Completed (Answered by PIU, no further complaint during the reporting period)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

10 Noragavit 1, block 1, house 4/1

Cracks due to demolishment.

27.05.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

11

Noragavit 1, block 1, 2, 11 houses and , block 2, 7 houses

Cracks due to demolishment works

18.05.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

12 Noragavit 4, block 1, house 15

Cracks due to demolishment works

21.06.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

13 Noragavit 4, block 1, house 10

Cracks due to demolishment works

10.06.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist

14 Noragavit 1/2, house 9

Cracks due to demolishment works

13.06.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist

15 Noragavit 1, house 7/2

Cracks due to demolishment works

14.06.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist

16 Noragavit 4st., block 1, house 12

Cracks due to demolishment works

21.06.2016 Pending (under the investigation stage)

Coordinated by Sirak Gyulbudaghyan – PIU land acquisition and resettlement Specialist

17 Noragavit 1, bock 2, house 11

Cracks due to demolishment

27.06.16 Pending (under the investigation stage)

Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

18 Arshakunyats 286/21

Cracks due to demolishment.

29.06.16 Pending (under the investigation stage)

Supervision Engineer social specialist with coordination of Sirak Gyulbudaghyan - PIU land acquisition and resettlement Specialist

Page 12: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

10

10

D. Meetings and Communication

18. During the reporting period environmental safeguards issues were regularly discussed during the

joint meetings with YM, PIU and DESC. Particularly the following issues were repeatedly discussed:

preparation and finalization of the IEEs for Hayrenik overpass approval process and related issues.

19. ADB site visit took place on 22 April 2016. Mrs. Armine Yedigaryan visited the Artashat Highway

PK km 0+300÷ km 1+850 and New Shirak Street PK km 0+0.100÷ km 0+0.400 construction site. She

checked the construction works on site, compliance of civil works to the EIA/EMPs and SEMP.

20. Regular meetings and discussions within PIU, DESC and the Contractor’s environmental team

during the reporting period took place via joint meetings, official correspondence and emails, phone

calls and personal contacts. Particularly the issue on the dust control measures; on safety on high fill

slopes; on the findings of additional measurements of environmental parameters; removal of

construction waste long-term left on-site, findings of training sessions, as well as the non-

conformances detected during the monitoring visits and action measures on their implementation

were discussed.

E. Awareness Raising and Environmental Training

21. The awareness raising and environmental orientation program was developed in the scope of

capacity building in the EIAs/IEEs and EMPs for Tender 2. According to the program the Contractor

was responsible to arrange orientation session about project activities and environmental awareness.

During this session, all the people working on the site should focus their efforts to protect environment

and insure the safe handling of the social issues during construction period in accordance with ADB

SPS (2009), Armenian environmental legislation, EIA and EMP. Further details about the awareness

raising and environmental orientation program could be found in final EIA and EMP Tender 22 and

Contractor’s SEMPs.

22. According to EIA, Annex 6 EMP for Tender 2 and SEMP the Contractor organized training for the

23 new hired staff during this reporting period on minimizing waste at source, proper handling of the

waste, workers’ safety measures during work and emergency preparedness in case of incidents, and

health risks and prevention which include information and education on sexually transmitted diseases

and HIV/AIDS. Site introduction environmental and health & safety training for the sub-contractor’s

new hired workers, engineering staff and foremen were held by Contractor on 21 May 2016 and 06

March 2016 (list of participants attached in Annex 1).

2 EIA/EMP for Tender 2 I.3. Implementation arrangement, c) Awareness raising and environmental Training, page 54 of 57; Annex 4, Table

1, para 6, page 6 of 31.

Page 13: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

11

11

23. DESC’s national environmental Consultant is providing supervision of Contractor’s ongoing

training, timely guidance to the Contractor’s environmentally responsible staff during the reporting

period. Supervision ES regularly briefed both Contractor’s and sub-contractor’s staff while monitoring

visits.

24. Two public hearings for Hayrenik overpass under Tranche 1 held on 22 March and 29 April 2016.

Final IEE for Hayrenik overpass under Tranche 1 will be submitted to ADB in the beginning of the

next reporting period.

25. An awareness raising training session was held by Mr. Pierre Bourguignon, DESC-Egis

International Company Environmental Manager on Health & Safety (21 June 2016) and on

Environment (22 June 2016). Mr. Pierre Bourguignon explained the topics via PP Presentations:

“Health & Safety Management” and “Environmental Management”. Contractor’s and sub-contractor

key staffs including environmental, social specialists and engineers were invited (list of participants is

attached in Annex 2).

III. Environmental Monitoring

A. Environmental Monitoring Program

26. Environmental monitoring program with a view to ensure compliance with the ADB’s

environmental requirements and all applicable environmental laws, regulations and standards for

environmental protection of RA has been developed in the scope of IEEs/EIAs and EMPs for Tender

2. The EIAs and EMPs contain monitoring activities to be considered during project implementation:

management from the engineering design phase, preconstruction, construction through the operation

and maintenance periods. Details of monitoring activities and reporting are presented in approved

final EIAs and EMPs for Tender 23.

B. Environmental Monitoring Program

a. Environmental Monitoring for Tender 2

27. According to the contract the specialized monitoring company shall implement the measurements

in accordance with the approved measurement of environmental parameters: air pollution, noise,

vibration plan during the reporting period January-June 2016.

3 EIA/EMP for Tender 2, I. Environmental Management Plan, I.2 Monitoring page 52 of 57; Annex 4 Table 2, page 23 of 31; EIA/EMP for

Tender 3, I. Environmental Management Plan,I.2 Monitoring page 56 of 62; Annex 4 Table 2,page 28 of 36 and EIA/EMP for Davitashen-Ashtarak highway, I. Environmental Management Plan,I.2 Monitoring page 54 of 61; Annex 3 Table 2, page 23 of 31.

Page 14: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

12

12

28. During the reporting period construction site monitoring visits (see Annex 7: Example of weekly

environmental monitoring checklist) and dump site monitoring visits organized jointly with PIU,

Contractor’s and DESC’s ESs, RE and other responsible representatives of the Contractor

participated in some of the monitoring visits.

29. The excavation materials are located in the dump site area of “X-Y’’ LLC basalt mining company

in Shahumyan 2, Silikyan district. Series of site visits were undertaken to the dump site “X-Y” LLC to

check compliance with EMP/ SEMP and Engineer’s requirements, as well as to check whether the

instructions given during the previous visit were done by the Contractor. The last site visit

implemented on 23 June 2016 stated that the site was used in accordance with EMP/SEMP and the

Engineer’s/PIUs instructions.

30. “Lernametalurgiayi Institute”, the company contracted by general contractor for environmental

measurements, carried out regular environmental monitoring of dust, air quality, noise and vibration

on 22.01.2016, 15.02.2016, 15.03.2016, 15.04.2016, 29.04.2016, 13.05.2016, 30.05.2016,

10.06.2016 and 22.06.2016 (see Annex 7). Selection of measurement points varied by taking into

consideration the impacted sensitive receptors within 50 m and ongoing construction works criteria. In

those cases when contractor timely notified Engineer on the measurements date, the points were

agreed jointly. Otherwise the measurement points were selected under the supervision of contractor’s

ES. In order to ensure the smooth process Engineer requested from contractor timely notification of

the date of measurements.

31. According to the provided reports of sub- contractor Lernametallurgie on 10 June the vibration

levels in measurement points 1, 2 and 3 is below from both the baseline level and the Maximum

Permissible Values. In the points 4 and 5 both maximum and average values exceed the baseline

level but are within permitted legislative standards. According to the provided reports for

measurements implemented on 22 June the vibration level in all measurement points was below from

both Maximum Permissible Level and the baseline data.

32. Based on the ADB requirement Contractor signed an additional contract with the sub- contractor

Lernametallurgie for additional measurements in one point relevant to AP's complains (see table 1,

point 5). The measurements were implemented on 17, 20, 21 and 22 June at 9:30 am and 11:00 am.

The time of measurements was determined based on the principle of operation of vibration

generating machinery. According to the provided reports vibration acceleration slightly exceeded both

Maximum Permissible and the baseline level only on 17 June at 11:00. All other measurements

showed that measurement hour for maximum and average values the vibration level was below the

baseline level and far below the Maximum Permissible standard.

Page 15: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

13

13

33. Detailed information on the results of regular monitoring measurements is presented in the Noise

and Dust Assessment Reports available in “Vahagn & Samvel” LTD office and attached to the

Contractor’s monthly progress reports and measurements are summarized in Annex 6 of the present

report.

34. By the Site Instruction issued on 6 June 2016 Contractor was instructed to implement the Method

of Fill-Up in Middle of Grade Separated Roundabout and to provide safety measures on high slopes

and at high Retaining Walls. Contractor was instructed to remove large loose stones and dress

slopes smoothly to avoid any falling-down or rolling of material.

35. By the end of reporting period Contractor started using the second water truck on- site and

implemented more frequent watering. The site visits and measurements show that the dust control

can be considered as almost satisfactory.

C. Non-compliance Notices

36. A final warning and note by the email dated 2 June 2016 was sent by PIU directly to the

Contractor requesting implementation of proper watering on- site otherwise the civil works shall be

stopped. Also by the email sent on 6 June 2016 by PIU the Contractor was requested to use the

second water truck and implement more frequent watering of the site during the day in order to

minimize the further complaints concerning dust. The last site visit stated that the warning was

addressed and Contractor is using the second water truck on- site and implements frequent watering

of sites close to residential areas.

37. All further non- conformances detected during the monitoring visits have been treated according

to the adopted procedure: Contractor is being requested via the Engineer’s monitoring report to

correct the non- conformances within the deadline set for correction otherwise the non- compliance

notice shall be issued. Correction was checked during the next site visit.

D. Corrective Action Plans

38. During the reporting period construction site monitoring visits were held by DESC once a week

and by PIU ES on 21.01.2016, 16.02.2016, 16.02.2016, 19.02.2016, 12.03.2016, 22.04.2016,

26.05.2016 and 23.06.2016 in Artashat-New Shirak highway Tender 2 (See Annex 4: Status of the

previous weekly environmental site monitoring reports). Dump site monitoring visits were organized

by PIU and DESC’s national and international ESs on 23.06.2016.

39. Corrective action plans were developed to address each non-conformance found during

monitoring (see Annex 3: Corrective action plan for Tender 2).

Page 16: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

14

14

IV. Findings and Recommendations

40. The monitoring visits implemented by PIU/ Engineer during the reporting period concluded in the

following findings. The recommendations are done also taking into consideration the findings of ADB

mission held on 22 April 2016.

- Dust: Dust level is too high close to sensitive receptors and should be reduced to comply with

legislative standards. Contractor was strongly recommended to operated more water trucks and

implement more frequent watering of the sites (now partly corrected);

- Vibration: Although Contractor always reported on the vibration level within the legislative standards

he was requested to follow ADB recommendations and implement additional measurements,

- Awareness of APs on the GRM is poor. Contractor was recommended once again to present the

GRM presented to the public and attached the contact information around the construction site (now

corrected).

- Bridges: Safety of Sub- contractor Kamurdjshin working on height is not assured. The necessary

PPE particularly the belts or harnesses are missing. Safety of workers next to welding works is not

ensured. Workers are doing the electrical cutting without proper PPE. Smoking workers are detected

very close to the explosive balloons. Sub- contractor is doing improper lifting of materials and is using

unsafe electrical panels and unsafe plugs. Protective guardrails on the bridges and safe staircases

are missing. Sub- contractor was recommended to correct the situation immediately.

- Arshakunyats Roundabout and Nor Shirak: Contractor's workers on the wall structures poor. Safe

accesses to work site are not ensured. More trainings on safety for management staff both Contractor

and sub-contractor is needed since safety of the site is very poor. Contractor was recommended to

correct the situation immediately (now corrected);.

-waste and dismantled utilities are being repeatedly detected on-site (partly corrected);

- workers are provided with and are using the uniform, applicable safety/protection equipment for site

conditions (mostly corrected);

- health check of newly hired workers is needed (corrected);

- bins for garbage collection are installed but Contractor is requested to move the bins and install next

to on-going construction works (corrected);

- cleaning and proper organization of contractor’s camp area is needed (partly corrected); all the open

holes alongside the asphalt covered section of Artashat highway should be safely covered (at least

temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is

needed (partly corrected);

- mud spread preventive measures were needed (not corrected).

Status of the action from environmental monitoring (January-June 2016) see in Annex 3.

Page 17: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

15

15

V. Future program

N Action Time frame Responsible

1 Submit IEE for Hayrenik overpass August-September 2016 PIU, DESC 2 Public consultations August-September 2016 PIU, DESC 3 Regular monitoring visits of

construction works according to the EMP for Tender 2

Once a month/once a week PIU/DESC

4 excavated material dump site inspection visit for Tender 2

Once a month PIU, DESC

5 Review of the environmental monitoring data on dust, noise, vibration and NO/NO2/SO2 for Tender 2

Every month /twice a month PIU/DESC

6 Review and approval of the construction updated SEMPs for Tender 2

Upon the need PIU, DESC

7 Contractors new staff safeguard training for Tender 2

Upon the need DESC, Contractor

8 Regular awareness training for newly recruited staff for Tender 2

Upon the need DESC, Contractor

9 Review and addressing the GRM for Tender 2

End of every month/ every week

PIU/DESC

10 Other routine issues Upon the need PIU, DESC, Contractor

11 Reporting on environmental safeguards

Monthly, Quarterly Bi-annual

PIU, DESC, Contractor

Page 18: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

16

16

VI. Annexes A. Annex 1: List of training participants for Tender 2

Page 19: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

17

17

Page 20: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

18

18

Page 21: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

19

19

Page 22: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

20

20

B. Annex 2: List of EHS training participants held on 21, 22 June 2016

Page 23: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

21

21

C. Annex 3: Corrective action plan for Tender 2 Corrective action plan for Tender 2 the construction period from January to June 2016:

N Deadline for request

Corrective action request Date of

corrective action

Corrective

action status

1

15.01.2016 Warning signs and fencing were missing in many sections. 15.01.2016 Mostly corrected

2

15.01.2016 21.01.2016 27.01.2016

The same waste and dismantled utilities are being repeatedly detected on- site and they are still on-site. Contractor is requested to remove the rest of waste

-

Not corrected

3

15.01.2016 21.01.2016 27.01.2016

Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions

- Not corrected

4

15.01.2016 21.01.2016 27.01.2016

Bins for garbage collection are not installed in Arshakunyats Roundabout section. 24.12.2015 Not corrected

5

15.01.2016 21.01.2016 27.01.2016

More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.

24.12.2015 Not corrected

6

15.01.2016 21.01.2016 27.01.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is needed.

- Not corrected

Page 24: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

22

22

7

15.01.2016 21.01.2016 27.01.2016

Work safety of workers is not ensured. Necessary PPE is missing. - Not corrected

8

15.01.2016 21.01.2016 27.01.2016

Any safe access to the work site (bridges, staircases) is not ensured. The staircases are installed not properly and are not usable. Monitoring inspection is not possible.

- Not corrected

9

15.01.2016 21.01.2016 27.01.2016

Mud spread preventive measures were needed. - Not corrected

10

15.01.2016 21.01.2016 27.01.2016

Waste asphalt is disposed of in non- approved sites - Not corrected

N Deadline for

request

Corrective action request Date of

corrective action

Corrective

action status

1 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Warning signs and fencing were missing in many sections.

25.02.2016 Corrected

2 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Workers are provided with uniforms and are using uniform, applicable safety/protection equipment for site conditions

25.02.2016 Mostly corrected

3 1.02.2016 8.02.2016 15.02.2016

Winter time organization of the workers’ mealtime is not acceptable.

16.02.2016 Mostly corrected

4 1.02.2016 8.02.2016 15.02.2016

First aid kit is available on-site and is not accessible to all workers.

16.02.2016 Corrected

5 1.02.2016 8.02.2016 15.02.2016

Fire extinguisher was missing 16.02.2016 Corrected

6 1.02.2016 8.02.2016 15.02.2016

More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.

16.02.2016 Corrected partly

7 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Work site is not cleaned from the garbage 25.02.2016 Corrected partly

8 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Bins for garbage collection are not installed in Arshakunyats Roundabout section.

25.02.2016 Corrected partly

9 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Any safe access to the work site (bridges, staircases) is not ensured. The staircases are installed not properly and are not usable.

16.02.2016 Corrected partly

10 1.02.2016 8.02.2016 15.02.2016

Construction sites are not watered 16.02.2016 Corrected partly

11 15.01.2016 21.01.2016 27.01.2016

The same waste and dismantled utilities are being repeatedly detected on-site. Contractor is requested to remove the rest of waste.

- Not corrected

12 1.02.2016 8.02.2016 15.02.2016

Access of strangers on- site is not restricted. Safety of AP is not ensured

- Not corrected

Page 25: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

23

23

25.02.2016

13 15.02.2016 25.02.2016

Person in charge on emergency management is not appointed and is not present on-site.

- Not corrected

14 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Copy of ERP and emergency contact list is missing in Arshakunyats section

- Not corrected

15 1.02.2016 8.02.2016 15.02.2016 25.02.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers. Also night time illumination is needed.

- Not corrected

16 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Work safety of workers is not ensured. Necessary PPE is missing.

- Not corrected

17 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Mud spread preventive measures were needed.

- Not corrected

18 1.02.2016 8.02.2016 15.02.2016 25.02.2016

Waste asphalt is disposed of in non- approved sites

- Not corrected

N Deadline for

request

Corrective action request Date of

corrective action

Corrective

action status

1 4.03.2016 12.03.2016 17.03.2016

Person in charge on emergency management is appointed and is present on-site

17.03.2016 Corrected Mr. Hovik Movsisyan is appointed

2 4.03.2016 12.03.2016 17.03.2016

Amounts of bins for garbage collection are increased

17.03.2016 Partly corrected

3 4.03.2016 12.03.2016 17.03.2016

Work site is not cleaned from the garbage 17.03.2016 Corrected partly

4 4.03.2016 12.03.2016 17.03.2016

Trucks are operating using covers 17.03.2016 Corrected

5 4.03.2016 12.03.2016 17.03.2016

The same waste and dismantled utilities are being repeatedly detected on- site. Contractor is requested to remove the rest of waste

17.03.2016 Partly corrected

6 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Contractor is violating the SEMP doing the disposal of the excavated earth material within the non- approved area.

24.03.2016 Corrected

Page 26: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

24

24

7 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Dust control is implemented Construction sites are watered

24.03.2016 Corrected partly

8 4.03.2016 12.03.2016 17.03.2016

Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions

17.03.2016 Mostly corrected

9 4.03.2016 12.03.2016 17.03.2016

More training on safety for management staff both Contractor and sub- contractor is needed since safety of the site is very poor.

17.03.2016 Corrected partly

10 4.03.2016 12.03.2016 17.03.2016

Work safety of workers is not ensured. Necessary PPE is missing.

17.03.2016 Corrected partly

11 17.03.2016 24.03.2016

Non- approved disposal of the asphalt waste is detected

- Not corrected

12 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Contractor is responsible to organize removal: by the owner of the utilities or using own resources.

- Not corrected

13 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Access of strangers on- site is not restricted. Safety of AP is not ensured

- Not corrected

14 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Copy of ERP and emergency contact list is missing in Arshakunyats section

- Not corrected

15 4.03.2016 12.03.2016 17.03.2016 24.03.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.

- Not corrected

16 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Sanitary-hygienic conditions for workers are poor and need improvement.

- Not corrected

N Deadline for

request

Corrective action request Date of

corrective action

Corrective action

status

1 6.04.2016 Gravel layer to all accesses of the roads needed to prevent spread of mud

6.04.2016 Corrected

2 26.04.2016 Warning signs and exclusion barriers erected around work site areas and regularly re-installed

26.04.2016 Corrected

3 6.04.2016 Dust control is implemented Construction sites watered

6.04.2016 Corrected partly

4 6.04.2016 The attached ERP posters need to be properly re-installed

6.04.2016 Corrected partly

5 6.04.2016 20.04.2016

Work site is not cleaned from the garbage 26.04.2016 Corrected partly

6 6.04.2016 13.04.2016 20.04.2016

Workers are provided with uniform and are using uniform, applicable safety/protection equipment for site conditions

6.04.2016 13.04.2016 20.04.2016

Corrected partly

7 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Additional trainings on safety 26.04.2016 Corrected partly

Page 27: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

25

25

8 6.04.2016 13.04.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.

13.04.2016

Corrected partly

9 6.04.2016 13.04.2016

The same waste was repeatedly detected on- site. Contractor is requested to remove the rest of waste

13.04.2016 Corrected partly

10 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Contractor is violating the SEMP doing the disposal of the excavated earth material within the non- approved area.

- Not corrected

11 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Workers are using safety/protection equipment for site conditions

- Not corrected

12 17.03.2016 24.03.2016

Non- approved disposal of the asphalt waste is detected

- Not corrected

13 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Contractor is responsible to organize removal: by the owner of the utilities or using own resources.

- Not corrected

14 4.03.2016 12.03.2016 17.03.2016 24.03.2016

Access of strangers on- site is not restricted. Safety of AP is not ensured

- Not corrected

15 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Amounts of bins for garbage collection are not sufficient

- Not corrected

16 6.04.2016 13.04.2016 20.04.2016 26.04.2016

Sanitary-hygienic conditions for workers are poor and need improvement.

- Not corrected

N Deadline for

request

Corrective action request Date of

corrective action

Corrective action

status

1 25.05.2016 Traces of leaked cement were present on public roads at Arshakunyats section

25.05.2016 Corrected

2 10.05.2016 People were poorly aware on the GRM. Contractor was requested to attach posters informing on GRM.

10.05.2016 Corrected

3 10.05.2016 More trainings for workers were needed on ERP at time of starting employment

10.05.2016 Corrected

4 10.05.2016 Missing ERP posters at Arshakunyats and Nor Shirak section need to be re-installed

10.05.2016 Corrected

5 10.05.2016 19.05.2016 25.05.2016

Fencing and prohibiting posters to restrict the access of unauthorized people on- site were missing.

25.05.2016 Corrected partly

6 10.05.2016 19.05.2016 25.05.2016

Excavated waste should be removed from work site

25.05.2016 Corrected partly

Page 28: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

26

26

7 10.05.2016 19.05.2016

Contractor is responsible to organize removal: by the owner of the utilities or using own resources.

19.05.2016

Corrected partly

8 10.05.2016 19.05.2016

Temporarily dumped earth material from the camp's area and from Artashat

highway should be removed to approved dump sites

19.05.2016 Corrected partly

9 19.05.2016 25.05.2016

Gravel layer to all accesses to the roads needed to prevent spread of mud

25.05.2016 Corrected partly

10 1.05.2016 Dust control is implemented Construction sites watered

1.05.2016 Corrected partly

11 10.05.2016 19.05.2016

Work site is not cleaned from the garbage 19.05.2016

Corrected partly

12 10.05.2016 19.05.2016

Workers are provided with and are using the uniform, applicable safety/protection equipment for site conditions

19.05.2016 Corrected partly

7 10.05.2016 19.05.2016 25.05.2016

Additional trainings on safety - Not corrected

8 10.05.2016 19.05.2016 25.05.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.

- Not corrected

11 10.05.2016 19.05.2016 25.05.2016

Safety on bridges and wall structures is poor

- Not corrected

15 10.05.2016 19.05.2016 25.05.2016

The bins for garbage collection at Nor Shirak and Artashat sections are missing

- Not corrected

16 10.05.2016 19.05.2016 25.05.2016

Sanitary-hygienic conditions for workers are poor and need improvement.

- Not corrected

N Deadline for

request

Corrective action request Date of

corrective action

Corrective action

status

1 3.06.2016 16.06.2016 23.06.2016

Dust control is implemented Construction sites watered

30.06.2016

Corrected

2 16.06.2016 Workers are provided with and are using the uniform

16.06.2016 Corrected

3 16.06.2016 23.06.2016

Workers are provided with and are using applicable safety/protection equipment for site conditions

30.06.2016 Corrected partly

Page 29: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

27

27

4 16.06.2016 23.06.2016

Temporarily dumped earth material from the camp's area and from Artashat

highway should be removed to approved dump sites

23.06.2016 Corrected partly

Contractor started

removal

5 16.06.2016 23.06.2016

Contractor is responsible to organize removal: by the owner of the utilities or using own resources.

23.06.2016 Corrected partly

6 16.06.2016 30.06.2016

Contractor was requested to remove the asphalt waste to the designated dump site

23.06.2016 Corrected partly

7 16.06.2016 30.06.2016

Contractor was requested to remove all the construction waste to the designated dump site

23.06.2016 Corrected partly

8 16.06.2016 23.06.2016

Sanitary-hygienic conditions for workers are poor and need improvement.

30.06.2016 Corrected partly

9 16.06.2016 23.06.2016

Safety on bridges and wall structures is poor

23.06.2016 Corrected partly

10 16.06.2016 23.06.2016

Additional trainings on safety 23.06.2016 Corrected partly

11 16.06.2016 23.06.2016

Contractor was requested to re-cover all accesses to the roads by the gravel layer to prevent spread of mud

- Not corrected

12 16.06.2016 23.06.2016

The bins for garbage collection at Nor Shirak and Artashat sections are missing

- Not corrected

13 16.06.2016 23.06.2016

Fencing and prohibiting posters to restrict the access of unauthorized people on- site were missing.

- Not corrected

14 16.06.2016 23.06.2016

Work site is not cleaned from the garbage - Not corrected

15 16.06.2016 23.06.2016

Contractor is requested correct some unsafe practices detected on- site

- Not corrected

16 5.06.2016 16.06.2016 23.06.2016

All the open holes alongside the asphalt

covered section of Artashat highway should be safely covered (at least temporarily) and/or fenced to ensure safety off APs and workers.

- Not corrected

D. Annex 4: Status of the previous weekly environmental site monitoring reports for Tender 2

During the reporting period regular weekly and monthly monitoring visits against the schedule of

compliance areas of civil works to the requirements set in EIA and EMP have been implemented by

PIU and Engineer’s ESs and the monitoring sheets completed. Improvement of the detected non-

Page 30: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

28

28

conformances was checked during the next site visit. The summary of compliance/ non- conformance

is presented in the Matrix below:

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 15 January

14 7 11 0/1 7

Week 2 21 January

14 6 12 0/0 8

Week 3 27 January

10 4 17 0/0 8

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 5 February

12 2 18 3/1 15

Week 2 11 February

11 5 17 0/2 13

Week 3 16 February

13 8 12 2/7 10

Week 4 25 February

14 7 11 1/4 11

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 4 March

13 6 14 0/4 10

Week 2 12 March

15 7 12 1/4 9

Week 3 17 March

18 8 8 3/5 8

Week 4 24 March

18 6 9 0/4 8

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 6 April

18 12 4 2/7 4

Week 2 13 April

18 10 5 0/4 4

Week 3 22 April

18 10 5 2/1 6

Week 4 26 April

18 9 7 1/2 4

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 16 9 8 2/1 8

Page 31: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

29

29

4 May

Week 2 13 May

18 10 3 3/7 5

Week 3 28 May

19 11 4 0/4 4

Week 4 25 May

20 9 5 1/4 5

Monitoring visit Fully compliant Partly compliant

Non- conformity

Non- conformities corrected (F/P)

Non- conformities not corrected

Week 1 3 June

20 12 2 1/4 3

Week 2 9 June

20 14 0 0/3 3

Week 3 16 June

21 13 0 1/1 3

Week 4 23 June

19 13 0 0/4 6

Page 32: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

E. Annex. 5: Suggested Post-Construction Environmental Audit Checklist for Tender 1 Site: Arshakunyats Street Section km 0+000 -km 1+280, Tender 1, Tranche 1

Time: 01.01.2015-26.01.2016 No. Activity Impacts Measure/s suggested as per Check Measures Implemented

1 Project site

vegetation

rehabilitati

on

(re-

vegetation)

Change of land cover,

erosion resulting from

the construction

activities

Plantation and vegetation

measures (trees, grass etc.)

checked Indicated measures have been carried out at Arshakunyats Street Section km 0+000 -km 1+280

on November-December 2014. Totally 153 trees and 30 shrubs were planted. The remaining

amount (435 trees and 165 shrubs) shall be planted during the upcoming favorable season

within Tender 2.

The health state and growth of trees and shrubs is being regularly checked during the liability

period.

Proper landscaping with

drainage

2

Top soil

manageme

nt

Erosion of soil

Storing and managing

removed topsoil for re-use

for landscaping activities

checked During construction period the topsoil was removed and stored only within the Military

aviation institute area in accordance with SEMP and after the completion of civil works was re-

used for the landscaping of the same Military aviation institute area. The topsoil was not used

for landscaping of the area alongside the RoW.

No topsoil was removed and/or stored during the post- construction period. 3 Oil

manageme

nt

Equipment and

machinery repairing

Avoid oil spill to open soil.

Repair works to be taken on

concrete cover area.

checked There were no oils or other spillages during the post construction time.

During the project implementation, Oil management issues had been carried out in compliance

measure prescribed by EIA/ EMP and respective SEMPs.

Page 33: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

31

31

4 Waste

manageme

nt

Waste accumulation,

air and soil pollution

Collect and disposal all wastes

including construction debris at

designated location;

checked During construction period all the construction waste was temporarily disposed of within the

area indicated in the SEMP, then removed to and disposed at the approved dump site.

No waste was generated during the post- construction period

Dumping sites restored and

submitted officially to local

communities

checked The dump site used for the Tender 1 is also being used by the same Contractor for the Tender

2. The restoration of the dump site area will be implemented by the end of Tender 2 Project:

L2752-ICB/CW-T2 5 Noise and

vibration,

air

manageme

nt

Excessive noise and

vibration due

to new road

Noise has been monitored on

a periodic basis and in

response to any complaints.

checked Noise and vibration levels were measured during 2015 on regular basis (three times ) and were

in compliance with RA legislative standards and bellow the baseline level.

No complaints were lodged by APs during the post construction period.

6 Air

manageme

nt

Air quality

deterioration due

to new road

Air quality has been

monitored associated with

vehicle emissions on a

periodic basis and in

response to any complaints

checked Air quality parameters were also measured on the periodic basis (in accordance with EIA/EMP)

and measurement showed some improvement for all parameters compared with pre-

construction situation.

No complaints were lodged by APs during the post construction period.

7

Traffic

manageme

nt

Hazards and

safety issues

related to traffic

Public access and access to

the housing, shops, business

and public activities

checked All the accesses are ensured according to the design.

Road safety is ensured, proper signage is implemented

Appropriate signage is installed

Page 34: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

32

32

8 Road

reinstatem

ent

Road damages causing

pollution, traffic

disturbance and

accidents

Streets with installed network

reinstated to pre-construction

or better conditions,

checked All the existing network was replaced and new network installed according to the design.

Trees replanted as needed All the trees are planted in accordance with landscaping design.

Access road reinstated to pre-

construction or better

conditions

All the access roads are re-instated up to pre-construction period.

9 Borrow

sites and

quarries

Land slide, soil

erosion, change in

riverbed and

landscape, accidents

Borrow sites and quarries

restored

checked .

Contractor purchased the material only from the existing quarries on contractual basis. The

contractor obtained act of acceptance to the satisfaction of the owner (in accordance with

EIA/EMP). 10 Existing

Infrastructu

re facilities

Damage or

disturbance to existing

services (supply of

electricity, water, gas,

telecom etc.)

Reinstatement to pre-

construction conditions or

proper relocation, to be

certified by the service

companies

checked Existing infrastructures had been reinstated up to pre-construction conditions and/or properly

relocated. Oral satisfaction of service companies is achieved and no complaints were received.

11 Camp site

facilities

Residual pollution and

disturbance to the

localities

All temporary/field plants

(asphalt, concrete, crushing,

etc.) have been dismantled and

removed.

checked There were no temporary plants used for the Tender 1 Project. The camp site was used only for

machinery parking purpose.

Existing camp site is foreseen for for Tender 2 widening of Artashat Highway PK km 0+300÷km

1+850 and New Shirak Street PK km 0+0.100÷km0+0.400 by the permission of YM.

Page 35: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

33

33

Permanently operating plants

(asphalt, concrete, crushing,

etc.) have been properly

handled and

closed/surrendered.

N/A

There were no permanent plants used for the Tender 1 Project.

All temporary facilities

removed and cleaned up

The mobile house is being dismantled and removed. All the machinery is being removed. Area

is cleaned up ready for the Tender 2. 12 GRM Unresolved complaints

from Affected People

All grievances have been solved

and AP's satisfied

checked All the grievances lodged in the GRM are solved Total of seven complaints for Arshakunyats

avenue were recorded in the log book and addressed accordingly by Contractor. The

complaints were on the cracks in old houses due to construction vibration. All APs were

compensated by the Contractor and satisfied.

F. Annex 6: The results of air quality, noise and vibration monitoring for Tender 2

Page 36: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

34

34

G. Annex 7: Example of weekly environmental monitoring checklist MITIGATION COMPLIANCE & INSPECTION MONITORING Report N 64

Project: SUDIP – Tranche 1, Tender 2, “Construction of Road Links of the Yerevan Western Ring Road”.

Implementing Agency: DESC__________________

Scope of Inspection: Artashat Highway (PK km 0+300÷km 1+850), New Shirak Street (PK km 0+0.100÷km0+0.400 km) and Grade Separated Roundabout

Between Shirak Street and Arshakunyats Avenue

Contractor: Vahagn and Samvel LLC/ su o tra tor Ka urdjshi

Attendees : Name & Position:

Mrs. Ruzanna Voskanyan, PIU EO; Mr. Pierre Bourguignon, DESC IES

Mrs, Edita Vardgesyan, DESC ES

Date: 23.06.2016

Weather Condition: sunny

Monitoring visit was carried out with the presence of:

Mr. David Harutyunyan, Contractor's HSE

WORK SITE: General

Environmental management: environmental team, health& safety, emergency, trainings, grievance redress mechanism

Construction Activity Mitigation Measure (as per

EMP/SEMP)

Mitigation

Implemented

Yes/No/NA

Mitigation Effective*

1 to 5

Corrective Action

Request (CAR)

including deadline for

effective CA.

Resolution Status of

previous CAR

(resolved/outstanding

actions required)

Environmental team

All activities 1. Person in charge on environmental

management is appointed and is present

on-site

Y 1

Health& safety

Page 37: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

35

35

All activities 2. Warning signs and exclusion barriers

erected around work site areas

N 3Some re-installation of

tape fencing in the

sections indicated in the

report N 63 are still

required

Correct before 30

June 2016

Non- conformance

repeated

All activities 3. Access of strangers and outsiders is

excluded

N 3People are still

crossing the

construction site very

close to open pits and

operating machinery.

At the section

demonstrated on

picture the fencing and

prohibiting posters

were missing.

At Artashat section

some holes still remain

open.

Correct before 30

June 2016

Non- conformance

repeated

All activities 4. Workers are provided with and are using

the uniform, applicable safety/protection

equipment for site conditions

N 4The uniform is mostly

OK but for the PPE see

comments below.

Correct before

immediately

All activities 5. Worker’s health checks implemented Y 1

Ensure availability of

the documents for the

inspection.

All activities 6. Sanitary-hygienic conditions for workers

are provided: drinking and washing

water supply, mealtime utilities, toilets,

rest time, etc.

N 3

Sanitary-hygienic

conditions for workers

are poor and need

improvement. Workers

are having mealtime

open air in very non-

Correct before 30

June 2016

Non- conformance

repeated

Page 38: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

36

36

sanitary conditions.

The workers were self-

providing water.

Taking into account the

summer season the

Contractor should

organize the supply of

drinking water to

working staff.

All activities 7. First aid kit is available on-site and is

accessible to all workers.

Y 1

All activities 8. Fire extinguisher available Y 1

Emergency Response Plan

All activities 9. Person in charge on emergency

management is appointed and is present

on-site

Y 1

All activities 10. Copy of ERP and emergency contact list

are available, updated and posted in a

visible place at all work sites

Y 1

All activities 11. Accident report maintained N/A -

All activities 12. Damage of utilities and/or other

structures managed

N/A -

Trainings and orientation courses

All activities 13. Workers briefed on CEMP/ SEMP at

time of starting employment

Y 1

Page 39: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

37

37

All activities 14. Workers briefed on ERP at time of

starting employment

Y 1

All activities 15. Job-specific environmental and safety

training for workers provided

N 3

Safety on the bridge was

poor.

Additional trainings of

working staff on safety is

needed.

Contractor should

provide full report on the

trainings with photos

especially for workers on

height and V&S staff

working on construction

of walls.

Implement before 30

June 2016.

Work site cleanliness

All activities 16. The work site kept clean from debris,

garbage, etc.

N 3

Clean before 30 June

2016

Page 40: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

38

38

All activities 17. Bins for garbage collection are installed N 3

Missing at some

Contractor's sites at

Artashat HW and Nor

Shirak sections

Correct before 30

June 2016

Non- conformance

repeated

Public communication and grievance redress mechanism: environmental issues

All activities 18. Meeting with community members on

construction activities, environmental

impacts and mitigation measures held

Y 1

All activities 19. Register of complaints maintained,

Complains observed during the last visit

addressed

Y

1

All activities 20. People are notified on inconveniences:

water, electricity breaks, etc.

N/A

Environmental parameters: Dust control

Earth works, material

delivery, removal of

existing pavement, asphalt

pavement

21. Trucks are operating using covers N/A -

22. Construction sites watered N 3 Two water tracks are

operating on site and

the traces of water in

were visible

Partly corrected

Page 41: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

39

39

23. Equipment and haul vehicles are fitted

with effective emission control

equipment

Y 1

Noise control

Operation of machinery

while earth works,

material delivery, removal

of existing pavement,

asphalt pavement

24. Construction noise levels are acceptable

at closest sensitive receptor

Y 1 Visually the noise level was

not excessive. More exact

information shall be

obtained as soon as the

report on environmental

monitoring for May shall be

submitted.

25. Equipment fitted with effective silencers Y

1

26. managed by restricting operating hours Y 1

27. managed by portable noise barrier panels N/A

Vibration control

Operation of machinery

while removal of existing

pavement, asphalt

pavement

28. managed by reducing time exposed to

vibration,

N/A

29. managed by portable vibration barrier

panels

N/A

Earth works 30. Erosion control: excavated slopes

stabilised

Y 1

All activities using liquid

materials

31. Spillages are managed properly Y 1

Earth works 32. Sediment laden runoff is prevented Y 1

Page 42: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

40

40

Earth works, material

delivery, removal of

existing pavement, asphalt

pavement

33. Drains are kept open and are not blocked

by sediment

Y 1

All activities using

machinery

34. Tires of trucks are cleaned before

entering city roads

N 3

The previously covered

gravel layer needs to be

refreshed and the

missing parts need to be

covered.

Clean the road and

correct before 30 June

2016

Non- conformance

repeated

Earth works 35. Excavated waste is either hauled from

work site or is retained temporary on-

N 3Some amount of waste

from Arshakunyats

Remove the rest of

waste and utilities

Corrected partly

Page 43: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

41

41

site in spoil dumps section was removed

but significant amount

of same waste especially

at Artashat HW and

under Artashat bridge is

still on- site.

before 30 June 2016

All activities 36. Proper maintenance of re-planted trees

and shrubs, and median lawn

N/A

Construction waste management

removal of existing

asphalt pavement

37. Waste asphalt is disposed of in approved

sites Y 2An asphalt waste was

dumped in non-

permitted area

Contractor is

requested remove the

remains before 30

June 2016

Corrected partly

Earth works, demolition

of structures, dismantling

of utilities

38. Non-hazardous waste (excavation

material, rocks, concrete and metallic

parts, etc.) is managed in accordance

with SEMP

Y 3

Contractor is responsible

to agree with owner and

organise the removal of

the remains of utilities to

the determined locations.

Remove the remains

before 30 June 2016.

Corrected partly

Page 44: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

42

42

Removal of existing

pavement,

39. Hazardous waste is managed in

accordance with SEMP

Y 2

see 37

Use of chemicals, fuel,

lubricants, etc. while all

activities

40. Leakages and liquid waste is managed in

accordance with WMP

N/A -

Contractor’s facilities and equipment Contractor’s camp

establishment

41. Site Management Plan for the camp

available

Y 1 Corrected partly

Contractor’s facilities 42. Contractor’s facilities are established according to SEMP

Y 2Contractor is requested

to remove the remains of

temporarily dumped

earth material from the

camp's area and from

Artashat HW or obtain

the YM's permission.

Correct before 30

June 2016.

* Mitigation Effectiveness Rating Criteria

1. Very Good 19

2. Good 3

3. Fair 10

4. Poor 1

Page 45: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

43

43

5. Very Poor 0

Attachments

(Eg. Photos, Remarks, laboratory reports etc)

Remarks:

1. Safety of Sub- contractor Kamurdjshin working on height is not ensured. The necessary PPE is missing

2. Worker assisting to the welder is not wearing PPE and is unprotected.

3. Workers are doing the electrical cutting without proper PPE. One of workers is smoking very close to the explosive balloons.

Page 46: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

44

44

4.Sub- contractor is doing improper lifting of materials.

4. Sub- contractor is using unsafe electrical panels and unsafe plugs.

Page 47: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

45

45

5. Sub- contractor should remove the used and empty balloons from the bridge

6.Contractor's workers on the wall structures poor. Safe accesses to work site are not ensured.

3. Protective guardrails on the bridges and staircases are missing. The tape fencing is not sufficient. Contractor is requested to do metal fencing.

Page 48: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

46

46

Good practices detected on-site

1. Almost all workers both Contractor's and Sub- contractors' were provided and wearing the proper uniform.

2. The workers were immediately provided with protective belts following the DESC IES's instructions.

Before After the DESC instructions

3. Contractor started doing tape fencing on the bridges following the DESC NES instructions.

Page 49: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

47

47

4. Sub- contractor and Contractor care for unrestricted water courses and proper drainage.

This form, or an adaptation of it, should be used during routine (preferably weekly) site inspections by the PIU environmental specialist/unit or

representative (Supervision Consultant) to monitor implementation of the EMP for a construction project.

Routine site inspections should cover all current/relevant construction activities being implemented on the project site at the time of inspection. Ideally,

the Co tra tor’s e viro e tal a ager/fo al poi t should a o pa y the PIU e viro e tal spe ialist or represe tative duri g routine inspections. Once

completed, the form should be sent to the Contractor for his information and action including any photographs. A copy of the completed form is retained in

the data management system of the PIU for reference during subsequent site inspections and for referral during preparation of monitoring reports.

Column 1 Construction Activity – All current/relevant construction activities taking place on the project site for which mitigation measures are required

under the EMP/SEMP, are listed.

Page 50: Environmental Monitoring Report...1+280, Tender 1, Tranche 1 for the time period of 01.01.2015 to 26.01.2016. The final version of Audit Checklist for Tender 1 is attached in Annex

48

48

Column 2 Mitigation Measure – Specific mitigation measures required under the EMP/SEMP for the corresponding construction activity are listed.

Column 4 Corrective Action Request – Where the inspection identifies non-compliance or ineffective implementation of a mitigation measure, specific

corrective actions are identified, discussed and agreed with the Contractor including a deadline for effective corrective action.

Column 5 Resolution Status of Previous CARs – Each subsequent site inspection involves review of the resolution status of previous CARs. This is useful in

assessing the responsiveness of the Contractor to environmental non compliances and where necessary provides the basis for determining when a

contractual non-compliance penalty may need to be invoked (eg persistent noncompliance / no response to CAR).