EGLINTON CROSSTOWN Eglinton-Mount Pleasant March 13, 2018

2

INFORMATION IS CURRENT AS OF MARCH 13, 2018 AND SUBJECT TO CHANGE

3

Agenda

• Eglinton Station Update • Mount Pleasant Station Update

4

Eglinton Station Update

5

Eglinton Station Update

Recently Completed • First three weekends of TTC subway closure works at Berwick Avenue

Ongoing • Shoring on and west of Yonge Street, north and south side of Eglinton • THESL 2B – Hillsdale (partially complete), Yonge (ongoing)

Upcoming • Traffic shift for shoring on the north side of Eglinton Avenue, east of Yonge Street (20-40

Eglinton East) – March 13th • Water site service connections proposed overnight on Eglinton east of Yonge –

tentatively March 15th for 2-3 nights (20-50 Eglinton East affected by water shut off) • Toronto Hydro relocation 2A

– Eglinton Avenue East, Dunfield Avenue, Holly Avenue

• Weekend subway closures for TTC upgrades – May 19/20 is the next weekend closure; another public meeting will be arranged for April

• Shoring on the north side of Eglinton Avenue, west of Yonge Street

6

Next Phase of Shoring – March 13th

Presenter
Presentation Notes
These relocations will take place in order to allow for construction and excavation of the future station.

7

THESL Relocation 2A – March/April

Presenter
Presentation Notes
These relocations will take place in order to allow for construction and excavation of the future station.

8

Next Phase of Shoring – April/May

Presenter
Presentation Notes
These relocations will take place in order to allow for construction and excavation of the future station.

9

Mount Pleasant Station Update

10

Mount Pleasant Station Construction Update

ACTIVITY LOCATION APPROXIMATE DURATION

WINTER/SPRING 2018

Support of Excavation (Piling) North side of Eglinton Ave E Ongoing through March 2018

Storm Sewer Installation – Stage 1 Taunton Road and Eglinton Ave E Week of March 12 for three (3) weeks

Pedestrian Rerouting SW sidewalk at Mt. Pleasant Rd and Eglinton Ave E (Brownlow Ave site) As early as March 19, 2018

Storm Sewer Installation – Stage 2 Brownlow Ave and Eglinton Ave E Week of March 26 for two (2) weeks

Traffic Change See map Early April 2018

Traffic Change See map Early May 2018

11

Current Construction Staging

Until April 2018

12

Pedestrian Rerouting

Beginning as early as March 19, 2018

STORM SEWER SITE

STORM SEWER SITE

13

Upcoming Construction Staging

Beginning early April for approximately four (4) weeks

14

Future Construction Staging

Early May 2018

What to Expect: Storm Sewer Installation

• In December 2017, crews began installation of a new storm sewer system along the south side

of Eglinton Ave E, between Taunton Rd and Brownlow Ave

• Work will resume on March 12, 2018

• Crews will use a hand-mining method whereby the sewer pipe will be hydraulically pushed

through the soil from the shaft while soil is simultaneously removed

• The work will be completed in three stages:

• Part 1 – Mining and pipe installation Taunton Rd to Mt Pleasant Rd (three weeks)

• Part 2 – Mining and pipe installation Brownlow Ave to Mt Pleasant Rd (two weeks)

• Part 3 – Connection work (two weeks)

What to Expect

• 24/5 operation, Monday through Friday

• Noise from construction equipment, 25K generator, pumps and fans

• Pedestrian rerouting around Brownlow Ave/Eglinton Ave E work zone

• Truck traffic entering/exiting work zones

16

Mount Pleasant Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

17

Mount Pleasant Station Main Entrance

*60% rendering

18

Mount Pleasant Station Secondary Entrance

*60% rendering

19

Mount Pleasant Station Plan View

STATION BOX

Recommended