View
213
Download
0
Category
Preview:
Citation preview
Cx Sequence of Events
ICE Activities OAC Activities
Cx RFP
Response to RFP Owner issues Cx contract
Initialization Letter to Architect
Cx Sequence of Events
ICE Activities OAC Activities Issue "SD" documents
Review "SD" & issue comments
Response to Cx comments
Cx Sequence of Events
ICE Activities OAC Activities Issue “DD" documents including Cx comments
Review “DD" & issue comments
Response to Cx comments
Issue Preliminary Cx Plan
Cx Sequence of Events
ICE Activities OAC Activities Issue “CD" documents including Cx comments
Review “CD" & issue comments
Response to Cx comments
Issue construction documents
Cx Sequence of Events
ICE Activities OAC Activities Schedule Cx Kick-Off Meeting
Cx Kick-Off Meeting
Issue Meeting Minutes
Cx Sequence of Events
ICE Activities OAC Activities Notify Cx of 30% MEP progress (2 weeks)
Perform 30% field inspection
Issue Action Items Response to Cx comments
Cx Sequence of Events
ICE Activities OAC Activities Preliminary O&M Manual w/ submittals
Issue Final Cx plan Response to Cx Plan
Cx Sequence of Events
ICE Activities OAC Activities Notify Cx of 60% MEP progress (2 weeks)
Perform 60% field inspection
Issue Action Items Response to Cx comments
Cx Sequence of Events
ICE Activities OAC Activities
Equipment Start-up
Issue Equipment Start-up Verification
Cx Sequence of Events
ICE Activities OAC Activities Notify Cx of 90% MEP progress (2 weeks)
Perform 90% field inspection
Issue Action Items Response to Cx comments
Cx Sequence of Events
ICE Activities OAC Activities
TAB Field Work
Controls Field Work
Issue TAB Deficiency List
Cx Sequence of Events
ICE Activities OAC Activities Notify Cx of 100% MEP completion (2 weeks)
Begin FPT Support FPT effort
Issue Preliminary FPT Report
Response to FPT Report
Cx Sequence of Events
ICE Activities OAC Activities Finish FPT Support FPT effort
Issue FPT AIS Report Response to Cx AIS
Deficiencies remedied appropriately
Notify Cx of remedies
Recommended