Conventional Facilities – MMF Presentation Outline

Preview:

DESCRIPTION

Conventional Facilities – MMF Presentation Outline. Facility Design Criteria Site Location Facility Design Schedule. Facility Design Criteria. Facility Use Space Requirements Environmental Stability Temperature +/- 0.1 deg. C. Humidity Vibration

Citation preview

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20041

Conventional Facilities – MMF Presentation Outline

Facility Design Criteria

Site Location

Facility Design

Schedule

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20042

Facility Design Criteria

Facility UseSpace RequirementsEnvironmental Stability

Temperature +/- 0.1 deg. C.Humidity

Vibration <0.5 micronsUtility Requirements

ElectricalOther

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20043

MMF Facility Uses

Undulator magnet tuning – 2 magnet measuring machine test stands

Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall.

Undulator fiducialization – large coordinate measuring machineCradle assembly areaMagnet storage/temperature acclimationWork desks in lab and office space for 2 employees

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20044

Resultant Building Criteria

~4800 sq. ft. floor space (inc. ~3000 laboratory space) + mezzanine

Locate within an existing building to aid in temperature control

Adequate ceiling height for overhead cranes

Accessible for magnet delivery using trucks and forklifts

Availability of required utilities, esp. electrical service – 600A, 480v 3f

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20045

Building 081 Location

LCLS Undulator Hall

Research Yard

PEP Ring Road

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20046

Building 081 Site Layout

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20047

Building 081 Current Uses

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20048

New Space Allocation for Bldg. 081

SHIPPING & RECEIVING

EQUIPMENT REPAIR

VEHICLE SHOP

Offices

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 20049

MMF Ground Floor Plan

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200410

MMF Ground Floor Plan

Magnet Measuring Lab

~1600 ft. sq.

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200411

MMF Ground Floor Plan

Coordinate Measuring

Area~ 1000 ft. sq.

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200412

MMF Ground Floor Plan

Cradle Assembly Area~325 ft. sq.

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200413

MMF Ground Floor Plan

Magnet Loading and Storage~850 ft. sq.

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200414

Mezzanine Floor Plan

Mezzanine for Mechanical Equipment

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200415

Cross Sections

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200416

Rear Elevation

Roll up door for magnet delivery

Mechanical Access

Staff Access

Jo Beth Folger

MMF Site and Construction jbfolger@slac.stanford.edu

October 14, 200417

Schedule

Completion of Title II drawings December 2004

Bid and contract with general contractor January – April 2005

Construction May – November 2005 (Early Finish) February 2006 (Beneficial Occupancy)

Recommended