Clean TeQ Sunrise

CCC Meeting – 29 November 2019

Clean TeQ Sunrise

Project Update

Community Engagement Update

Environmental Management Update

CCC Member Questions

Summary

CCC Meeting Presentation – 29 November 2019 Page 2

Project Update

Page 3

Clean TeQ Sunrise

Project Update

CCC Meeting Presentation – 29 November 2019 Page 4

• Sunrise Project Team working to prepare Project Execution Plan.

• This work covers updating Sunrise project schedule and cost based on project development since the DFS.

• Continue to work with the Shires of Lachlan and Forbes on the water pipeline agreement, with good progress made.

• Positioning Sunrise to be ready for a final investment decision in mid-2020, subject to the completion of a financing package by that time.

• Various parties remain engaged in the Sunrise partnering process.

Clean TeQ Sunrise

Project Update

CCC Meeting Presentation – 29 November 2019 Page 5

• Completed drilling program

• Completed bypass fencing

• Particulate monitoring installation progressing

• Ongoing site maintenance activities

Clean TeQ Sunrise

Emergency Management Plan• Emergency Maps• Assembly Points• Liaising Emergency ServicesProperty Clean Up• Scrap metal recycled • Sump oils recycledWeed Spraying• Training for spot spraying• Contract for wide area sprayingKangaroo Culling• Contractor commissioned • Commercial harvesting • Licence approved

Land Management

CCC Meeting Presentation – 29 November 2019 Page 6

Before. After.

Community Engagement Update

Page 7

Clean TeQ Sunrise

What we’ve been up to

CCC Meeting Presentation – 29 November 2019 Page 8

Building relationships across the community through engagement and active participation

– Participated in and sponsored the Trundle Bush Tucker day

– Hosted the Northern Panel of the Grains Research and

Development Corporation (GRDC) for two days in the Parkes

office

– Provided in-kind support in planning the 2019 Condo SkyFest

– Rolled out the Happy Daze coffee cart at the Western Business

Forum

Clean TeQ Sunrise

What we’ve been up to

CCC Meeting Presentation – 29 November 2019 Page 9

• Education and Investment

– Hosted a school holidays BBQ in Forbes with the Lake Cowal

Conservation Centre – providing a sausage sizzle lunch and a range of

fun environmental activities

– Supported Parkes Public School through our matched funding program

to assist with playground upgrades

– Provided matched funding to the Bedgerabong Public School to assist

with the installation of sunshades over play areas

– Purchased two x 50,000 Ltr water tanks for the Warroo Community Hall

Clean TeQ Sunrise

VPA investment at work

CCC Meeting Presentation – 29 November 2019 Page 10

• New shade sail in the Hannah Mahon Park was the first

project completed under the VPA funds with many more

to come. Lachlan Children Services also received a

new sun sail on Wednesday this week.

• Parkes Shire Council has recently placed the Trundle

Mainstreet paper on public exhibition and is calling for

community feedback

Clean TeQ Sunrise

Keeping people informed

CCC Meeting Presentation – 29 November 2019 Page 11

• Community newsletter– Published in September, next edition late December

– Distributed through newspapers, mailbox and e-delivery

– Dennis Brady profiled in the September edition– Steve Karaitiana is up next

• Fact Sheets – available on the webpage as completed • Facebook – continue to share short articles on Facebook • Website

– Complaints register published, zero complaints received YTD

• Shop fronts– Continue to operate in Condobolin, occasionally in Trundle

Environmental Management Update

Page 12

Clean TeQ Sunrise

• Environmental Management Strategy has been approved

• The following EMPs (incorporating Modification 4 changes) have been approved for the initial construction activities by the DPIE:– Environmental Management Strategy– Blast Management Plan– Road Upgrade and Maintenance Strategy– Noise Management Plan– Heritage Management Plan– Rehabilitation Management Plan – Biodiversity Management Plan and Revegetation Strategy– Traffic Management Plan

• EMPs approved for the “initial construction activities” will need to be revised and re-approved by DPIE before commencement of any works after this stage

Environmental Management Plans (EMPs)

CCC Meeting Presentation – 29 November 2019 Page 13

Clean TeQ Sunrise

Environmental Monitoring – Air, Noise, Groundwater

CCC Meeting Presentation – 29 August 2019 Page 14

AIR

• Real time particulate matter monitors

– EPA approved - Teledyne API T640x

– Installed this week

NOISE

• Quarterly noise monitoring

– Completed 11 September 2019

– Scheduled 2/3 December 2019

GROUNDWATER

• Monitoring undertaken 11-15 November 2019

• Standing water levels and water quality from minesite and borefield

CCC Member Questions

Page 15

Clean TeQ Sunrise

• No questions received

CCC Member Questions

CCC Meeting Presentation – 29 November 2019 Page 16

Clean TeQ Sunrise CCC Meeting Presentation – 3 December 2019

Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA

www.cleanteq.com

Recommended