Clean TeQ Sunrise

CCC Meeting – 29 November 2019

Page 2: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Project Update

Community Engagement Update

Environmental Management Update

CCC Member Questions

Summary

CCC Meeting Presentation – 29 November 2019 Page 2

Page 3: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Project Update

Page 3

Page 4: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Project Update

CCC Meeting Presentation – 29 November 2019 Page 4

• Sunrise Project Team working to prepare Project Execution Plan.

• This work covers updating Sunrise project schedule and cost based on project development since the DFS.

• Continue to work with the Shires of Lachlan and Forbes on the water pipeline agreement, with good progress made.

• Positioning Sunrise to be ready for a final investment decision in mid-2020, subject to the completion of a financing package by that time.

• Various parties remain engaged in the Sunrise partnering process.

Page 5: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Project Update

CCC Meeting Presentation – 29 November 2019 Page 5

• Completed drilling program

• Completed bypass fencing

• Particulate monitoring installation progressing

• Ongoing site maintenance activities

Page 6: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Emergency Management Plan• Emergency Maps• Assembly Points• Liaising Emergency ServicesProperty Clean Up• Scrap metal recycled • Sump oils recycledWeed Spraying• Training for spot spraying• Contract for wide area sprayingKangaroo Culling• Contractor commissioned • Commercial harvesting • Licence approved

Land Management

CCC Meeting Presentation – 29 November 2019 Page 6

Before. After.

Page 7: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Community Engagement Update

Page 7

Page 8: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

What we’ve been up to

CCC Meeting Presentation – 29 November 2019 Page 8

Building relationships across the community through engagement and active participation

– Participated in and sponsored the Trundle Bush Tucker day

– Hosted the Northern Panel of the Grains Research and

Development Corporation (GRDC) for two days in the Parkes

office

– Provided in-kind support in planning the 2019 Condo SkyFest

– Rolled out the Happy Daze coffee cart at the Western Business

Forum

Page 9: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

What we’ve been up to

CCC Meeting Presentation – 29 November 2019 Page 9

• Education and Investment

– Hosted a school holidays BBQ in Forbes with the Lake Cowal

Conservation Centre – providing a sausage sizzle lunch and a range of

fun environmental activities

– Supported Parkes Public School through our matched funding program

to assist with playground upgrades

– Provided matched funding to the Bedgerabong Public School to assist

with the installation of sunshades over play areas

– Purchased two x 50,000 Ltr water tanks for the Warroo Community Hall

Page 10: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

VPA investment at work

CCC Meeting Presentation – 29 November 2019 Page 10

• New shade sail in the Hannah Mahon Park was the first

project completed under the VPA funds with many more

to come. Lachlan Children Services also received a

new sun sail on Wednesday this week.

• Parkes Shire Council has recently placed the Trundle

Mainstreet paper on public exhibition and is calling for

community feedback

Page 11: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Keeping people informed

CCC Meeting Presentation – 29 November 2019 Page 11

• Community newsletter– Published in September, next edition late December

– Distributed through newspapers, mailbox and e-delivery

– Dennis Brady profiled in the September edition– Steve Karaitiana is up next

• Fact Sheets – available on the webpage as completed • Facebook – continue to share short articles on Facebook • Website

– Complaints register published, zero complaints received YTD

• Shop fronts– Continue to operate in Condobolin, occasionally in Trundle

Page 12: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Environmental Management Update

Page 12

Page 13: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

• Environmental Management Strategy has been approved

• The following EMPs (incorporating Modification 4 changes) have been approved for the initial construction activities by the DPIE:– Environmental Management Strategy– Blast Management Plan– Road Upgrade and Maintenance Strategy– Noise Management Plan– Heritage Management Plan– Rehabilitation Management Plan – Biodiversity Management Plan and Revegetation Strategy– Traffic Management Plan

• EMPs approved for the “initial construction activities” will need to be revised and re-approved by DPIE before commencement of any works after this stage

Environmental Management Plans (EMPs)

CCC Meeting Presentation – 29 November 2019 Page 13

Page 14: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

Environmental Monitoring – Air, Noise, Groundwater

CCC Meeting Presentation – 29 August 2019 Page 14

AIR

• Real time particulate matter monitors

– EPA approved - Teledyne API T640x

– Installed this week

NOISE

• Quarterly noise monitoring

– Completed 11 September 2019

– Scheduled 2/3 December 2019

GROUNDWATER

• Monitoring undertaken 11-15 November 2019

• Standing water levels and water quality from minesite and borefield

Page 15: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

CCC Member Questions

Page 15

Page 16: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise

• No questions received

CCC Member Questions

CCC Meeting Presentation – 29 November 2019 Page 16

Page 17: Clean TeQ Sunrise CCC Presetnation 191129CCC Meeting Presentation –29 November 2019 Page 13 Clean TeQ Sunrise Environmental Monitoring –Air, Noise, Groundwater CCC Meeting Presentation

Clean TeQ Sunrise CCC Meeting Presentation – 3 December 2019