Application of SCC to Dam Construction - University of …concrete.t.u-tokyo.ac.jp/fib_PhD2016/FIB...

Preview:

Citation preview

Application of SCC to Dam

Construction

-An Example of Technology and

Business Model Development-

Xuehui AN

Professor

Tsinghua University

1、Background

(Market)

Japanese Popular Magazine

AERA 2004.7.12 No.31

Taking a wedding photo in Shanghai,

there is always a construction crane.

Shanghai Wedding

JP TW KR MYSG TH CN VN

kg/capita

1950 1960 1970 1980 1990 200010

100

1000

10000

Co

nsu

mp

tio

n o

f cem

en

t p

er

cap

ita

From Dr. Ouchi

30 years

1950 1960 1970 1980 1990 2000 2010

Year

10

100

1000

Consum

ptin o

f cem

ent per

capita (

kg)

Japan

China

kg/capita

China, the Largest Concrete Market in the World

World Cement Consumption in 2013: 4,000,000,000 ton

China

58.6%

Japan

1.5%

USA

1.9%

India

7%

five east-west lines

five north-south lines

eight connection lines

The development of the high-speed railway in China

>200km/h

The development of the high-speed railway in China

in 2008.8.1

the first high-speed railway

in 2010.7.1

the mileage number become

NO.1 in the world

The aim

The development

in 2020 ,over 16,000 km

Reached at the end of 2014

6900

33002319

120

7055

13000

Dams to be constructed in China

China, the Largest Concrete Market in the World

Dams to be constructed in China

China, the Largest Concrete Market in the World

TGD

三峡

Bird’s View of TGD under Construction

China, the Largest Concrete Market in the World

TGD(2002)

World records:

Reservoir : 39,300,000,000m3

Reservoir length: 650 km

Power Capacity: 18,200,000kw

Concrete: 23,150,000m3

1999: 4,585,300m3

China, the Largest Concrete Market in the World

Needs and Challenges in Dam Construction

Vibrating-compacted concrete

Complicated process with vibrating, cooling

pipe placing, etc. High heat, of hydrationcomplicated temperature control, easy to

crack, high project cost

Masonry & Rubble concrete

Low technology required, low cost,

suitable for small-sized projects. Hard

for quality control with low level of

mechanization. Eliminated gradually

because of increasing labor costs.

Roller compacted concrete

Large working space and heavy

machinery required, only be suitable

for large-sized projects, and hard to be

used for ultra-high dam construction

Urgent need for a new -type concrete construction way

– Simple process, ease for quality control: No vibrating and temperature

control

– High speed, high efficiency: make best use of the mechanical operation

– Low cost, easy to popularization: Low cement required

– Wide adaptation:suitable for different size of working space

2、Technology Development

(R&D)

SCC: to meet the needs Technology of Self-Compacting Concrete

(SCC), developed in concrete lab, University

of Tokyo, Japan.

SCC Family in Japan

SCC was invented in 1980s

More and more Reinforced Concrete projects have been built by SCC due to good workability and high durability

SCC is difficult to use in Mass Concrete due to high price and high adiabatic temperature rise

SCC: Experimental Dam Concrete in Japan

Rock-Filled Concrete: SCC+Rock=Dam

Invented in early 2003 by Tsinghua University

Rock

>300mm

SCC

SCC

RFC RockHardening

Experimental Work

2003~2004

Study on the filling ability of SCC

1h

喷水养护3d

拆模

喷水养护

热缝 冷缝

2005~2007

Study on the compression strength and

permeability by piece-cutting method

Experimental Work

2008~2011

Study on the full-scale integrated property

• Compressive strength :fc

RFC/fcSCC=1.3~1.5

• Modulus of elasticity :Ec

RFC/EcSCC=1.3

• Tensile strength:ft

RFC/ftSCC=0.9

• Ultimate tensile strain:

RFC: 97×10-6

SCC: 117×10-6

• Shear strength:f=1.71 c=1.59MPa

• Adiabatic temperature rise

14.2~16.1℃

• Permeability coefficient:

RFC: 10-11m/s,

SCC: 10-12m/s

General-Type RFC Construction

Proposed in the

project with a

large working

space

1. Transportation of

Rock Block

2. SCC Pouring

SCC

pouring

Transportation

of rock block

Working

space

SCC

pouring

Riprap-Type RFC Construction

Proposed in the project with a small working space and a

significant drop in elevation

1. SCC Pouring

2. Rock Block Dumping

SCC pouringRock dumping

Working

space

Employment of RFC

Auxiliary dam of upper reservoir in Baoquan pumped-storage

hydroelectric plant project.

Designed as a 50000 m3, masonry gravity dam, 42.6m high.

The top 3m,

with a volume

of 3000m3,

was made of

RFC.

1st

Batching and

mixing plant:

mix SCC

Road : used for

transporting rock

blocks to the working

space by dump truckWorking space: construct

riprap by excavators and

bulldozers

Tower Crane:

transport SCC to

the working space

Bucket: load SCC

during transportation

Unit Weight:2401kg/m3

Rock:53.2%

SCC:42.8%

Air:4%

Employment of RFC 1st

Observed temperature history inside RFC

5.0

7.0

9.0

11.0

13.0

15.0

17.0

19.0

07.1.8 07.1.13 07.1.18 07.1.23 07.1.28 07.2.2 07.2.7 07.2.12

T1 T2

Employment of RFC 1st

JSCE

Technical Features

Low cost and

environmental friendly

Low cement and low heat of hydration

Decreased construcntion cost and impoved economic efficiency

Effective recycling of solid waste

Energy saving, reduced CO2 emissions

Safe and high quality

guaranteed

High density and high compressive strength guranteed

Good volume stability, outstanding fracture resistance

Excellent impermeability

Simpified and effective quality control

Simple construction way

High construction speed

Strong shear strength, eliminating surface roughening process

Simplifying temperature control process

Continuous construction, improved efficiency, shorten construction period significantly

3、Applications

(Engineering Solution)

Baoquan Hydropower StationQingyu Reservoir Weitan Reservoir

Jili Hydropower Station

Project Reference

Qiannian Reservoir

Xiaoshixia Hydropower StationGaoche Reservoir

Yangzhuang Levee Sanming LeveeSanwanWater Supply Project

First RFC gravity dam in Beijing

Tunnel lLining in Zhaikou Hydropower Station

Retaining wall of Huixin Highway

Karst Cave Filling in Aikou ReservoirTunnel Lining in Wuyue Reservoir

Project Reference

Cofferdam in Buerjin Hydropower station

Penstock Filling in Zhongliang Hydropower Station

Changkeng Reservoir Curtain Grouting in Xieka Hydropower Station

Open Caisson FillingIn Xiangjiaba Hydropower Statoin

Henshan Reservoir Reinforcement

Retaining wall of Sai-Guo HighwayPenstock Filling in

Dukouba Hydropower Station

Zhaojiayao Reservoir Reinforcement

Minhe Levee

Nahe-2 Hydropower Station

Project Reference

Xianyinhe Hydropower Station Miniu Reservoir

Donshen Hydropower Station

Menshan Reservoir

Shihe Reservoir Reinforcement Meizhou Levee Reinforcement Dalongtan Reservoir Reinforcement

Shuigoukou-2 Reservoir Reinforcement Hutiaoxia Reservoir Pula Reservoir

RFC volume (m3)

Project number

Project Reference

Located in Shanxi Province, total capacity of

reservoir is 2.33 million m3

Concrete gravity dam with height of 42.5m,

top width of 38.3m and length of 203m

Except impervious panel and overflow

section panel were constructed by CVC, all

the other parts of dam are constructed by

RFC

Total concrete quantity: 70,000 m3

Project Profile

Qingyu Reservoir —— Gravity Dam

Site Layout

SCC Plant

Pipe

Road

Rock Blocks

Casting

Project Profile

The first arch dam in the world

Single curvature arch dam with a gravity podium at each side.

Dam height is 24.5m and length is 120m. The length of arched dam part is 62m

All the dam is constructed by C25 RFC with total concrete amount of 12,000 m3

Menshan Reservoir —— Arch Dam

Rock

blocks

Aggregate

Fly ash、cement

Concrete

mixer

Concrete

pump

Tower crane

Menshan Reservoir —— Arch Dam

Changkeng Reservoir —— Dam Rebuilt

Project Profile

Rebuilding project with RFC gravity arched dam. Height of

RFC dam is 24.5m, length of dam is 88m and total capacity

is 1.61 million m3

Rubble demolished from the old masonry dam,

accomplishing resource recycling of solid waste

Rebuilt

Water leakage in old

dam

SCC Manufacture SCC Transportation SCC Pumping

Full-recycle the old dam body as rock material for RFC

Xiangjiaba Hydropower station —— Caisson Backfilling

Project profile

The last cascade hydroelectric station located on Jinsha River. The ten caissons of

this projects was the largest caisson group in China with max backfilling depth of

57.4m

In order to shorten the construction period, Riprap-Type RFC is used for all the

backfilling parts except the ferroconcrete ones.

Total concrete amount is up to 80,000 m3

23000

43000-57400

4400 5200 4400

RFC

Concrete mixing plant

9# Caisson

Aggregate field

Rock blocks

Rock blocks cleaning

SCC

Rock

construction area

Construction Site of Riprap-type RFC

Evaluation from xiangjiaba project

department

High compactness, high bulk density and compressive

strength, meeting the design requirements

Low heat of hydration. The max temperature rise

detected is only 7.1 C

High construction speed. The construction period is

shorten to 5-7 days from 20 – 30 days

Simple process, the project cost is less than CVC

Application Effect

Xiangjiaba Hydropower Station —— Caisson Backfilling

Project Profile

Because the security risks caused by dam cracks,

and abutment sliding stability can not meet the

requirements as well as other dam mechanical

properties, the dam began to be reinforced in 2009

Reinforcing the dam downstream. Over 45,000 m3

RFC were concreted. The concreting project was

finished in late 2010

The first double curvature arch dam of China, with 69m in height

Hengshan Reservoir —— Arch Dam Reinforcement

Construction Plan

RFC

Hengshan Reservoir

Thicken the dam body at downstream by using RFC

Reduce the amount of cement, to simplify the construction

process, shorten the construction period

Compared with CVC dam, RFC dam has larger bulk density,

better reinforced stability

Low heat of hydration, greatly reducing the cracks of interface

between the old and new dam, improving reinforcement quality

施工方案

Form work Concrete mixing

Concreting by pump

Constructing rock blocks into

working space by tower crane

SCC transported by mixing truck

Hengshan Reservoir —— Arch Dam Reinforcement

Application Effects

The average temperature rise of RFC is only 10℃

Effectively solve the complex issues

of temperature control, including

cracks happened between the new

and old dams caused by extreme

temperature difference new and old

dam open reinforcement works

Hengshan Reservoir —— Arch Dam Reinforcement

Application Effects

This project has caused wide public concern. In 2010, CCTV specially reports this

projects on “The Light of Science”

High compactness, high compressive strength to meet the

design requirements

Low heat of hydration, simple construction process, lower

project cost.

Low noise and environmental pollution, solving the

problem caused by narrow construction site and influence

to scenic

Hengshan Reservoir —— Arch Dam Reinforcement

4、Business Model

(Company Strategy)

History of RFC Business

2003 Rock-filled Concrete was invented

2005

2008 Company was founded

2009RFC technology was selected into the list of Key Promotion

Technologies of the Ministry of Water Resources of P.R. China

2010 Awarded as National High-Tech Enterprise

2012

• RFC was selected into the list of National Encouraged Technologies,

Techniques and Devices in the field of Circular Economy

• The first RFC arch dam in the world was built up at Menshan

reservoir

The first RFC gravity dam was built up in Beijing

R&D — Solution — Promotion — Service

Beijing Business Center

Beijing, China

RFC R&D Center

Tsinghua UniversityPlant

Engineering Center

Business

Center in

Chengdu

HQ in Beijing

One R&D Center

One Manufacturing Plant

One Engineering Center

Four Business Center

Business

Center in

Changsha

Business

Center in

Kunming

RFC Joint Research Center established

by Tsinghua University and SINOCONFIX

Chief ScientistsPro. Jin FengPro. An Xuehui

SINOCONFIX

National supporting and promotion

Advanced Practical Technology awarded by Ministry of Water Resources of People’s Republic of China (2009)

Key promoting technology of Ministry of Water Resources (2008~2014)

5 sessions of RFC technology seminar held by MWR of P.R. China

Key promotion technologies of Ministry

of Water Resources of P.R. China

1. “Low cement RFC Technology” was selected into the list of

National Encouraged Technologies, Techniques and Devices in

the Field of Cycle Economy

2. Be select into Advanced energy-saving technology awarded by

Beijing Municipal Commission of Development and Reform

3. “Top 100 Environment Friendly Technologies”

National supporting and promotion

Future of RFC

“Technical Guidelines for RFC&CSG dams” is issued by the Ministry

of Water Resources of China in 2014.

Songlin gravity dam (90m high) in Yunnan Province, the highest RFC

dam will finish construction in 2017.

Songlin Reservoir

77 RFC dams planed to be constructed in China

in near future

International Concern

RFC has been introduced as a

cover story by

<International Water Power &

Dam Construction > in 2008.

ICOLD(International

Commission on Large Dams):Technical Committee on

Cemented Material Dams (RFC,

CSG, Hardfill and etc. )has been

established in August 2013.