81

Three gorges project

Embed Size (px)

Citation preview

Page 1: Three gorges project
Page 2: Three gorges project
Page 3: Three gorges project
Page 4: Three gorges project

The Yangtze rises in the Quinghai-Tibet plateau and flows across China`s 11provinces, municipalities directly under theCentral Government and Autunomous Regions such as Quinghai,Tibet, Sichuan, Yunnan, Hubei, Hunan, Jiangxi, Anhui, Jiangsu and Shanghai. With a total length of 6300 km, a drainage area of 1,8 x 10 km² and a yearly volume of 976 x 10 m³ pouring into the Pacific Ocean. It is the largest River of China and ranks third of the World. The drainage area is one of Chinas most developed and prosperous areas, the land there is fertile and abundant in natural resources. The harnessing and exploitation of the Yangtze has a great impact on the development of the Chinese economy and its society.

9

6

Page 5: Three gorges project
Page 6: Three gorges project
Page 7: Three gorges project
Page 8: Three gorges project

The Qutang Gorge rises from Baidi City, ends in Daxi Town from the west to the east and meanders over 8 km. The steep and towering hills in the Gorge embodied the magnificence of “controlling thousends of ravines in the west, overwhelming rolling hills while adjoining Hubei and Hunan provinces in the east”.

Page 9: Three gorges project

The Wu Gorge rises from the estuary of Daning River in Wushan County, Chongqing, ends in Guandukou, Badong County, Hubei Province and meanders over 45 km. The Wu Gorge features beautiful hill peaks and cliffs range upon range and is known for its deepness, serenity and beauty.

Page 10: Three gorges project

The Xiling Gorge rises from Xiangxikou, Zigui County, Hubei Province, ends in Nanjinguan, Yichang City and meanders over 76 km. There were serried reefs, surging swirls and the Gorge was known for rapids and dangerous shoals.

Page 11: Three gorges project
Page 12: Three gorges project

CONSTRUCTION OF THE THREE GORGES DAM

Page 13: Three gorges project
Page 14: Three gorges project
Page 15: Three gorges project
Page 16: Three gorges project

The TGP under construction (1997)

Page 17: Three gorges project

The TGP under construction (1998)

Page 18: Three gorges project

The TGP under construction (1999)

Page 19: Three gorges project

The TGP under construction (2000)

Page 20: Three gorges project

The TGP under construction (2001)

Page 21: Three gorges project

The TGP under construction (2002)

Page 22: Three gorges project

The TGP under construction (2003)

Page 23: Three gorges project

THREE GORGES DAM SITE AREA

Page 24: Three gorges project

Probably the biggest site project for the world largest Power Station.

Page 25: Three gorges project

“The wall”, total length of 2310 m, 185 m high and 190 m wide. 27 Mio. m³ concrete used. Coast about 25 milliard USD. Project time of 75 years, construction time of 15 years (1994 – 2009).

Page 26: Three gorges project

ELEVATIONS AND WATER LEVELS

68.8121.2

40.0

OHL

27.0

57.0

185.0

62.0

82.0

FCL

175.0

145.0

NPL

Page 27: Three gorges project

Water filling before demolation of coffer dam.

Turbine outlet basin under construction.

Page 28: Three gorges project

View from down stream, left bank side.

Page 29: Three gorges project

Construction works between power house

and dam.

Page 30: Three gorges project

Penstocks with a diameter of 12.4 m.

Page 31: Three gorges project
Page 32: Three gorges project

Spill way and left bank hydro power plant.

Page 33: Three gorges project

The right bank coffer dam (upstream) is 580 m long, top elevation 140 m, providing the necessary condition for the timely initial reservoir impoundment, power generation of first commissioned units and navigation through the double-lane shiplock.

Page 34: Three gorges project

The upstream coffer dam will not be removed after finishing of “right bank”. The Units can operate only with high water level.

Page 35: Three gorges project

Upside dam: the flooded areas have a length of 660 km and reach a surface of 1100 km², total water volume of 39.3 milliard m³. The waterflow of the river is 16`000 m³ / s (average).

Page 36: Three gorges project

THE DOUBLE-LANE FIVE-STEP SHIP LOCK

Page 37: Three gorges project

Ship lock under construction

Technical datas:

Type: double laneSteps: 5Step dimension: 280 x 34 x 5 mTotal length: 1500 mMax. capacity: 10 000 t Ships

Page 38: Three gorges project

The largest “Gate” in the world.

Page 39: Three gorges project

The Ship Lock in operation.

Page 40: Three gorges project

THE LEFT BANK POWER HOUSE

Page 41: Three gorges project

The building with the GIS (gas insulated switch yard) and the Transformers. View from dam down to the backside of the Power House.

Page 42: Three gorges project

The gas (SF6) insulated switch yard ”GIS”.

Page 43: Three gorges project

Power transmission from 20 kV up to 500 kV.

Page 44: Three gorges project

Construction of left bank power house. The “Draft Tube, the Draft Tube Cone and Spiral Case” of turbines are erected first.

Page 45: Three gorges project

View inside Left Bank Power House:

14 Turbine Generators with 700 MW each.

Page 46: Three gorges project

6 VGS UNITSTechnical datas:

S n = 777.8 MVA

S max = 840 MVA

Stator:

U n = 20 kV

U p = 43 kV

I n = 22 453 A

Slot No. = 510

Bore = 18.5 m

Core height = 3.13 m

Rotor:

Pole No. = 80

N = 75 1/min

N max = 149.5 1/min

Weight = 1350 t

Page 47: Three gorges project

VGS-Unit: stator complete, lower bracket placed.

Page 48: Three gorges project

ALSTOM UNIT8 ALSTOM UNITS

Technical datas:

S n = 777.8 MVA

S max = 840 MVA

Stator:

U n = 20 kV

U p = 43 kV

I n = 22 453 A

Slot No. = 540

Bore = 18.8 m

Core height = 2.95 m

Rotor:

Pole No. = 80

N = 75 1/min

N max = 151 1/min

Weight = 2554 t

Page 49: Three gorges project

Turbine datas:

Type francis turbine

Runner: Weight: 455 tons Diameter: 9.25 / 10,43 m

No. of blades: 15 Height of blade: 4.67 m

Spiral case: Inlet diameter: 12 m Rated water flow: 966 m³/s

Page 50: Three gorges project

Spiral case prior to concrete filling.

Page 51: Three gorges project

455 tons Turbine Runner lowering into pit.

Page 52: Three gorges project

Stator frame and core with a total weight of about 700 tons, liftet off

“Erection Bay” and transported to its final destination: into Pit.

Page 53: Three gorges project

Stator frame on lifting device.

Page 54: Three gorges project

Assembly and adjustment of rotor spider and segments.

Page 55: Three gorges project

Rotor body ready for welding.

Page 56: Three gorges project

Masterpiece: Lower bracket complete.

Page 57: Three gorges project

Thrust Bearing24 thrust pads on spindle supports. Every pad is provided with a “load segment” able to adjust on ± 0.01 mm to guarantee an optimal weight distribution and regular pad temperatures.

The complete thrust bearing will take up an axial load from 5520 tons during operation of the Unit

Page 58: Three gorges project

Stator winding; overhang NDE.

Page 59: Three gorges project

Hi-tech: pure water cooled two shift wave winding (five groups parallel), installed with “round packing” and “ripple spring” slot wedges. Stator bars with “micadur ®” insulation, stainless steel hollow conductors and PTFE hoses. Splitted neutral point.

Page 60: Three gorges project

One of the three main terminals, output 20 kV and 7484 A.

Page 61: Three gorges project

Generator rotor (1970 tons) on lifting device. The two cranes used for the transport of the rotor have a capacity to lift 1500 tons each.

Page 62: Three gorges project

Generator rotor ready to transport to the pit.

Page 63: Three gorges project

Lowering rotor into the stator.

Page 64: Three gorges project

A difficult action: lowering the rotor into stator, by an air gap of only 35 mm and set down

carefully onto thrust block in lower bracket.

Page 65: Three gorges project

Lowering generator rotor.

Page 66: Three gorges project

TYPE TESTAfter completion of the first four Alstom Units with GMEC, a “Performance Test” were made on Unit No 10, to guarantee the efficiency of the Turbine -Generator acoording to the contract.

For the “Type Test” of the Unit with this size, a tremendous expenditure were necessary for the exact location of all losses, especially with all auxiliary systems.

Measure points and Equipment:

PT-100: Surfaces and environment 112 pc.Cooling water 12 pc.Pure water 4 pc.

Pressure transmitter: Flow measurement 4 pc.Shunt 0.0266843 m (80kg): Sudden short circuit 3 pc.Interface boxes: PT-100 / pressure transmitter 24 pc.Used cables: Connections 3200 m

Guaranteed Efficiencies according to the contractGuaranteed rated efficiency: 98.77%Reached rated efficiency: 98.80%Guaranteed efficiency at max. capacity: 98.76%Reached efficiency at max. capacity: 98.79%Guaranteed weigthed average efficiency: 98.76%Reached weigthed average efficiency: 98.79%

Page 67: Three gorges project

Layout of the temperature measurement and surfaces for the efficiency test

A 5

A 11 m

A 4A 3.2

MP 39-42MP 43-46

MP 109-112MP 105-108

MP 13-24MP 1-12

MP 103 / 104MP 101 / 102

A 3.1MP 28-30

A 2 A 6.1MP 49 / 50MP 47 / 48

A 7 (A 7.1 / 7.2)

MP 135-142MP 143-150

MP 119-126MP 127-134

A 6.2

MP 31-34MP 35-38

MP 25-27

Issued: Ralph Studer HPESApproved: Markus Regli CSXC4

Doc. No: 1AHX 447833

Page 20 / 24THREE GORGES TYPE TEST Generator No: 10 / Pit 10

Page 68: Three gorges project

Setting PT-100 for temperature measurement on pit-cover surfaces for the efficiency test.

Page 69: Three gorges project

Equalization of PT-100 in pairs for the

measurement of the cooling water temperatures.

Page 70: Three gorges project

PT-100 in cooling water circuit of lower bearing bracket to determine losses.

PT-100 in cooling water circuit of stator coolers to determine losses.

Page 71: Three gorges project

Sudden short circuit test by 55 %:

Three shunts were placed and connected on bracking switch of generator.

Typical resistance 0.0266843 m

During the test, the magnetic field was so strong to lift even the 80kg heavy shunts (20 cm).

Page 72: Three gorges project

Voltage measurement during short circuit test

between the phases.8 times 240 mm² were

connected between main terminal and star point.

Braking Circuit breaker

External supply

C

B

CT 30000 / 1A

Generator

Rotor

Shunt 10000 A / 150 mV

IA

If

IC IB

A

Page 73: Three gorges project

Differential pressure transmitter installed for

main cooling water, pure water system and lower

bearing coolers.

Page 74: Three gorges project

Left Bank Power House: 14 Turbine Generator Units with 700 MW (total 9800 MW)Right Bank Power House: 12 Turbine Generator Units with 700 MW (total 8400 MW)Underground Power House: 6 Turbine Generator Units with 700 MW (total 4200 MW)(additional two House Turbine Generators for domestic requirements)

Total 32 Turbine Generator Units, maximum output of 22`400 MW.Most possible energy production per year (theoretical) of 196`224 GWh.

In 2009 the whole “Three Gorges Hydro Power Station” will be in fully operation:

Page 75: Three gorges project

On top of the dam, elevation 185 m.

Page 76: Three gorges project

View on the upstream water intakes of left bank power station.

Page 77: Three gorges project

Spill ways:

in the middle part of the dam are placed 24 ground-, middle- and upper spillways.

Page 78: Three gorges project
Page 79: Three gorges project

CENTRAL CONTROLE ROOM OF POWER STATION

Page 80: Three gorges project

CASCADE DISPATCH CENTER

Page 81: Three gorges project

Hydro Ltd.